ispection date 12-Dec-16

next inspection date 27-Dec-16


Electrical motor process area
inspection check list motor number
inspected by
points to check ok correction action
Check motor frame intergrity
Check motor foundation bolts
Check motor fan & fan cover for
damage, looseness & coating
Check terminal box for damage &
looseness
Clean ventilation air flow
Check condition of motor power supply
cable gland
Check LCP for damage , cable & cleaning
Measure motor temperature
Measure motor vibration
Check for motor noise level
Check motor earthing connection
Check if motor not coated with dust
comment:
Supervisor

ispection date 12-Dec-16


next inspection date 27-Dec-16
Electrical motor process area
inspection check list motor number
inspected by
points to check ok correction action
Check motor frame intergrity
Check motor foundation bolts
Check motor fan & fan cover for
damage, looseness & coating
Check terminal box for damage &
looseness
Clean ventilation air flow
Check condition of motor power supply
cable gland
Check LCP for damage , cable & cleaning
Measure motor temperature
Measure motor vibration
Check for motor noise level
Check motor earthing connection
Check if motor not coated with dust
comment: