You are on page 1of 14

2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

 Navigation

DCS Upgrade: How to Reduce Stress During Execution


categories: dcs, intech

This guest blog post was written by Sunny R. Desai, an engineer in the DCS/PLC/SCADA
department at Reliance Industries Ltd.

The Reliance Industries Hazira complex, which manufactures a wide range of polymers,
polyesters, ber intermediates, and petrochemicals, needed to determine the best way to
update the industrial automation system. The complex commissioned a naphtha cracker plant
in March 1997 using then state-of-the-art technology, including a UNIX-based control system.
Over the years, there had been a progression of vendors developing new systems based on
the latest technological platforms and then declaring their older systems obsolete.

Many of the components of the UNIX-based control system had been declared obsolete, and
the vendor had withdrawn active support, spares, and engineering resources. There was a
decreasing availability of spares, which were very expensive. The distributed control system
(DCS) is critical for plant operation; the obsolescence and unavailability of spares directly
a ected the availability of the system for plant operation. Because electronic components
degrade over time, the failure rates of components was increasing. All these factors
increased the time and e ort to restore a failure.

https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 1/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

Evaluation philosophy
The company’s evaluation philosophy for developing an upgrade plan was based on the
following major criteria:

Plant safety and reliability were of prime importance.


E orts should be made to prolong or stretch the system life as long as possible without
compromising safety or plant reliability.
If the reliability of the existing system could be enhanced with a partial upgrade, it was
preferred.
If the partial upgrade of the system was not possible or did not improve the reliability of
the system, e orts should be made to keep the full upgrade cost to a minimum.

Evaluation
A partial system upgrade was not suggested, because it would only improve the visualization,
but not the reliability, of controllers, I/O modules, and other hardware components. Also,
keeping in mind the remaining installed base at the site, other plants would bene t from the
spares generated by removing hardware from this plant. The nal recommendation was a full
cracker plant control system upgrade.

Project scope
The following table shows an inventory of the existing DCS hardware.

Sr. No. Unit Quantity


https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 2/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

1 Marshaling panels 111

2 System panels 20

3 Total I/O 14,000

4 Alarm consoles 10

5 DCS servers 11

6 Operator stations 18

Update considerations
In the initial stage of the project, it was decided  that the new system should be similar to the
existing system in terms of the visualization, faceplates, and programming to avoid confusion
between an actual problem in the eld and a programming error.

The technical requirements the plant considered during the engineering stage included:

time scheduling for minimum downtime during plant shutdown


interfacing to existing eld instruments
reliability and safety of process areas
redundancy features
creating fresh logics in the new system from the existing system
converting proportional, integral, derivative (PID) tuning parameters from the existing
system
graphical design similar to the existing system for ease of operation
communication with third-party systems
advanced process control (APC) program modi cation
third-party historian program modi cation
secured network architecture

Method followed
Time scheduling was the biggest challenge for the entire team, with a very limited number of
days for executing the job, which included removing and tting new system panels, removing
all the components from the marshalling panels, removing and tting new alarm consoles,
formatting and installing DCS servers, replacing old operator stations with new ones,

https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 3/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

removing existing control network cables and laying new ones, and replacing all the power
circuit breakers.

The upgrade was to be performed in the short duration of a shutdown. To restrict the cost,
the team decided not to replace the I/O panels, but only the internal components. This would
also minimize the carbon footprint of this project. It would take a lot of time to remove and
x components individually, so the team decided to mount components on a plate and install
the plate in the panels. All the components, such as I/O modules, communication modules,
barriers, terminal blocks, and power supplies, were installed on the plate at the vendor’s
factory, and factory acceptance testing (FAT) was performed on the same setup.

To meet the desired system reliability, redundant controllers, communication modules, and
some analog output cards, power supplies, and diode ORings (creating logical OR
relationships) were connected in cross redundancy to avoid a single-point failure of any
device in the distribution. Power supply units were only loaded at less than 35 percent of
capacity.

The software function blocks did not have the functionality of the old system, so many
customized blocks were created in the new system, including blocks for APC and digital
loops. A team of specialized engineers, including process personnel, tested the logic in the
new system. This team visited the vendor a couple of times before conducting the FAT to
ensure that the logic worked per the existing control and automation philosophy.

The project’s new controller supported a signi cantly larger number of I/O than the existing
controllers. The plant preferred not to merge the I/O in one controller, but had them
distributed in the controllers exactly following the existing philosophy. No controllers were
designed to have third-party communication and I/O communication together.

It was decided in the design basis that all electronic components and cards should comply
with the ANSI/ISA-71.04-2013, G3 classi cation. The installed components must operate for a
minimum of 48 hours under extreme conditions: temperature at 0–50°C; relative humidity at
10–96 percent at 32°C noncondensing; maximum vibration at 0.2 G, 20–300 Hz; maximum
displacement at 0.01 inches; 5–20 Hz. Considering the constant improvements performed in
the plant during normal plant operations, it was decided to restrict the controller load to less
than 40 percent, network load to less than 50 percent, free memory to greater than 50
percent, and power supply load to less than 40 percent.

Considering the failures of the power supply and diode ORing across the site, a redundant
power supply with a redundant diode ORing scheme was used for this project. An active
diode ORing with a load-sharing indication and alarm relay was also used.

https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 4/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

Exhaustive FAT and SAT procedures were developed, and 100 percent loop testing and
redundancy testing of controllers, power supplies, I/O modules, communication networks,
and servers were performed. The team also performed 100 percent graphic testing and alarm
simulation. All the closed loops were checked and 100 percent APC functioning and OPC
communication was tested. During the SAT, the Pro bus signature was taken for all the
nodes and was preserved for future reference.

Consequences and mitigation plan


Following are the key risks involved in the project:

Accurate as-built information unavailable


Consequence: If the information available is not accurate, panel wiring and closed-loop
operation in the eld will be a ected. Also, several instruments in the eld may remain left
out, a ecting the complete plant operation and causing a delay in the startup of the plant.

Mitigation plan: To provide an accurate project design basis, several walk-downs and manual
surveys were performed to verify existing documentation was accurate. This activity was
performed while the plant was running and did not a ect the plant operation. The team took
several photographs of the existing wiring in the panels, noted the color code of every eld
cable, noted every termination where they found a discrepancy with the existing drawing,
and prepared a detailed le consisting of all the information collected. This le was the key
to the successful implementation of this project.

Manually converting the program to the new system


Consequence: If the program built in the system is not accurate per the old program, it will
a ect the entire plant operation. The running process may trip many times, causing safety
concerns in the plant and a nancial loss.

Mitigation plan: The only trusted document available for the programming was the existing
program running in the old system. First, it was important to understand the di erence
between the logic block functions of the old system and that of the new system. The team
listed the functional di erences between the two, and modi ed the new blocks to function
according to the old blocks. They decided to include the experts in the old system, from the
vendor as well as the user side, in the engineering team of the new system. This was one of
the crucial moves for ensuring a smooth upgrade. Several weeks were spent on this activity.
Once the compatible logic blocks were built in the new system, a trial test was performed to
check the operation of the blocks. On nding the operation satisfactory, clearance was given
to the vendor to continue building the program. At this point, the team calculated the
optimistic and the pessimistic time to complete the project execution, and all worked
wholeheartedly to meet the deadline.

https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 5/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

Building visualization in the new system


Consequence: If the conversion is not proper, plant operation will be a ected, as operators
will not be able to take quick actions when required. Because graphics are the main interface
between the operation team and the new system, faults in the graphics will directly a ect
the operation team’s acceptance of the new system.

Mitigation plan: The panel operators were used to the old visualization, so it was decided that
the visualization in the system should be a look-alike of the old system, and the latest
visualization features should not be used in this upgrade. This would help the operators
accept the new system and also avoid confusion between actual problems in the eld and
improper mapping of tags in the graphics during the plant startup. Once the visualization was
built in the new system, the engineering team performed a test. This test included verifying
the sketches on the graphics and mapping tags to the graphic element, alarm window, trend
window, group graphic windows, group trend window, and faceplate functioning. Once this
test was approved, the vendor was permitted to build more graphics.

Converting the PID tuning parameters


A PID controller is a control-loop feedback mechanism commonly used in industrial control
systems. A PID controller continuously calculates an “error value” as the di erence between
a measured process variable and a desired set point. The tuning parameter directly
in uences the accuracy of the control loop, and thereby the quality of the product. The value
of these parameters can only be xed during the running plant operation. These values are a
critical asset for the plant, as they are xed by the years of experience in operating the plant.

Consequence: Steady-state operation of the plant will be a ected, with a direct in uence on
the quality of the product.

Mitigation plan: The vendor had developed a mathematical equation and a tool for converting
the tuning parameters from the old system to the new system. The vendor had veri ed this
tool at a di erent conversion project where the company was satis ed by the results of the
conversion, and hence it was readily accepted in this project. Later the team found the results
of this tool were quite accurate.

Third-party communication
Online analyzers, machine-condition monitoring systems, turbine-governing systems,
antisurge systems, and plant emergency shutdown systems are standalone systems critical
for plant operation. They maintain the quality of the product, control the safe operations of
compressors, and maintain the e ciency of the compressors and safe operation of the plant.
The readings of these systems must be continuously available for the operators. The

https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 6/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

communication between the DCS and these systems is done with a Modbus protocol, which is
tricky and time consuming to con gure.

Consequence: This will have an impact during the plant startup when operators will not be
able to see some data from the online analyzers, machine vibration conditions, and data from
the emergency shutdown system of the plant. This will also a ect the steady-state operation
of the plant.

Mitigation plan: It was possible to complete this activity during the preshutdown period of
the project. The team arranged a spare controller and developed a test setup where the
running third-party system communicated with the new system. All the wiring diagrams,
communication settings, and response times were noted and later were directly
implemented in the new system. This way it became quite easy to establish the
communication with the actual new system.

Removing old components and fitting new ones in the panel


Consequence: If this activity is not completed in the planned time period, it will a ect the
entire startup of the plant.

Mitigation plan: All the cables in the panels were not to be cut and removed immediately.
Multicore cables from the eld and power cables from the main control board cabinet were
to be retained, so it was not easy to execute the system changeover during the shutdown
period. To meet this challenge, several drawings were prepared for each panel indicating
which cables and ducts were to be cut and removed and which cables were to be retained,
where the ferrules were to be changed, where the lugs were to be replaced, and TBs were
marked where there was interpanel wiring. Markings to distinguish between removal and
retention were done in each panel. All the electricians were trained to thoroughly
understand the drawing. To test the amount of time it would take to remove and x the
components in the panel, a mock operation was performed during the FAT. For this, a fully
loaded spare panel was shifted from the site to the FAT area. During the mock operation, the
team noted the time required, all the challenges faced, and the tools required, and they
planned improvements. This activity helped a lot during the actual execution of replacing the
components in each panel.

Building secured network architecture


Newer control systems are highly network based and use common standards for
communication protocols. Many controllers are Internet Protocol addressable. Standard
operating systems, such as Windows, are increasingly used in industrial control systems,
which are now typically connected to remote controllers via private networks. The ability to
access the system as a result of this interoperability exposes network assets to in ltration
and subsequent manipulation of sensitive operations. Furthermore, increasingly
https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 7/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

sophisticated cyberattack tools can exploit vulnerabilities in commercial o -the-shelf system


components, communication methods, and common operating systems found in modern
control systems.

Consequences: This a ects the safety of the plant and can have a nancial implication on
failure. This may a ect the entire business operation and can also have a social impact.

Mitigation plan: Considering the current scenario around the world and the constant increase
in the cyberthreat, the team decided on a secured network architecture with twin rewalls
installed in the system. They preferred that the two rewalls were of di erent makes. This
would help minimize any network-related threats. Antivirus software was installed in each
system, making sure it was set to run the latest de nition les. All the USB ports, CD/DVD
drives, the autorun feature of Windows, the Windows scheduler, the remote desktop feature,
and all the spare network ports were disabled. The auto log-o feature was enabled. These
steps help prevent any virus attack on the system.

APC implementation
Consequences: Steady-state operation of the plant will be a ected, minimizing the e ciency
of the process and having a direct nancial e ect.

Mitigation plan: APC implementation was a challenge in itself, because the new system did
not have similar functionality to the old system. All the programing blocks of the old system
were studied in detail, and blocks were developed in the system with the same functionality.
APC will communicate with the new system via a dedicated OPC station. In the old system,
the OPC wrote in a data block, but these data blocks were not available in the new system. To
meet this requirement, thousands of tags were created, which will not use the license. The
communication between the APC and these tags via OPC was tested during the FAT. All the
programs for taking a loop in APC and removing a loop from APC were tested during the FAT
period. The team performed 100 percent testing. Many data types required by APC that were
supported by the old system and were not supported by the new system were found during
the FAT. These data types were created in the new system and were mapped in the APC
program. APC communication was established during the shutdown period, but the APC
program in the APC controllers was modi ed in the post-shutdown period. Earlier, in the
UNIX-based system, a separate PC provided operator interface to the APC. In the new system,
a link to an Internet browser was provided for the operator to have the APC interface in the
DCS screen itself, so a separate PC was not required. Once the plant was started, the APC
program was tested for one of the furnaces, and in a week all the other APC programs were
modi ed. Similar modi cations were also done in a real-time optimizer and third-party
historian.

Technological improvements
https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 8/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

With this upgrade, we added some of modern automation’s state-of-the-art technology.


Some of the noticeable improvements were:

Secured network: The new system network was based on the demilitarized zone (DMZ)
architecture implemented using a twin rewall con guration. One rewall isolates the
enterprise network from the plant network, and another rewall isolates the plant
network from the control network, thereby creating a secured DMZ network. Both the
rewalls are of a di erent make and can only be con gured using a standalone
con guration laptop.
Enhanced diagnostic features: Diagnostic logs are generated for each module, with
master/slave in the hardware topology; they can be saved and analyzed for root-cause
analysis and preventive maintenance. A Web-based diagnostic portal, where we can view
warnings and controller errors, communication modules, and slave modules, is available
in the system.
Smart client: This smart client is a true thin-client o ce workplace that seamlessly
retrieves data from the system and connected third-party systems. The smart client is a
dashboard visualization application that provides a read-only view into the system and
allows the user to call up graphics.
Redundancy at the I/O level: For certain super-critical output tags that a ect the
production and safety of the entire plant, we have installed redundant analog output
cards. During the normal course of operation, the cards share current demand from the
eld devices. Each card is capable of supplying the full demand current from the eld
devices. When one card fails, the other identi es the need of current in the circuit and
supplies the full current.
Twin active diode-ORing scheme: Dual ORs with a load-sharing indicator are used in this
project, which helps us monitor the load sharing between the two power supplies. This
gives us an opportunity to identify a probable failure. Along with a redundant power
supply, we have also installed a redundant diode ORing.

Results
Proper planning and coordination with the vendor resulted in an e cient installation and
commissioning of the new system. All the 14,000 I/O, marshalling panels, system panels,
alarm consoles, servers, and operator stations were successfully replaced in a very limited
time. It is a success story for the entire team; we completed the project well within the
planned period. The project can be summarized with the statement: more stress on planning
reduces stress during execution.

About the Author


Sunny R. Desai has an engineering degree specializing in instrumentation and control.

https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 9/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

Desai is currently an engineer in the DCS/PLC/SCADA department, Central Engineering


Service, at Reliance Industries Ltd.

Connect with Sunny:

  

A version of this article originally was published at InTech magazine.

Share this:

   46

Related

What are the Bene ts of How a Sequenced Changeover Power, control two di erent
Migrating from an Older DCS to Approach for a Plant Upgrade issues
a New Automation System? Minimizes Downtime July 25, 2011
January 6, 2014 October 16, 2017 In "Industry"
In "InTech" In "InTech"

About guest blogging for ISA


Writers are welcome. Would you like to guest author an article for the ISA blog? Contact
info@isa.org for details.
View all posts by guest blogging for ISA →

 cracker plant, dcs, DCS upgrade, HAZOP, industrial automation, manufacturing, manufacturing
automation, process automation, process control, slider

 AutoQuiz: Can You Identify the P&ID Symbol?


Webinar Recording: How to Document Safety Instrumented Systems Inspections and Tests 

https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 10/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

0 Comments ISA Interchange 


1 Login

Sort by Best
 Recommend ⤤ Share

Start the discussion…

LOG IN WITH
OR SIGN UP WITH DISQUS ?

Name

Be the first to comment.

ALSO ON ISA INTERCHANGE

Leverage Smart Manufacturing to The Decision to Volunteer: The Why, How,


Succeed in the New Global Economy and a Personal Call to Action
1 comment • 3 years ago 1 comment • 2 years ago
Sandy Montalbano — The use of new Jonas Berge — because fewer people attend
technology can boost U.S. competitiveness, face to face presentation evens it is less
keeping … attractive to speak. how to …

How to Improve Industrial Productivity Basics of Continuous Level Measurement


with Loop Calibration 1 comment • 2 years ago
1 comment • 9 months ago Gabriel Serrano — Excellent information
Bill Robinson — I am looking for weight colleagues, greetings from venezuela.
calibration data systems that would run on an
iPad or a tablet.

✉ Subscribe d Add Disqus to your siteAdd DisqusAdd 🔒 Privacy

Follow ISA

Categories

Categories Select Category

https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 11/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

ISA’s Live Twitter Stream

Tweets by @ISA_Interchange
ISA Interchange
@ISA_Interchange
Offering world-class training, publications, networking events, industry standards, InTech
magazine and much more, ISA has so many ways to help you build your #Automation
career.

Visit now and learn why ISA isn't just another #Engineering organization! goo.gl/Y8iw5P

1m

ISA Interchange
@ISA_Interchange
How a Sequenced Changeover Approach for a Plant Upgrade Minimizes Downtime
bit.ly/2yNspDd @ROKAutomation

3h

ISA Interchange
https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 12/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution
@ISA_Interchange
R l ti i it it i f il d t bi l t K th ti ffi i t
Embed View on Twitter

LATEST

AutoQuiz: What Is the Best Location in an HMI for the Graphic Display of a Distillation Column?
FEBRUARY 16, 2018

Webinar Recording: How to Document Safety Instrumented Systems Inspections and Tests
FEBRUARY 14, 2018

DCS Upgrade: How to Reduce Stress During Execution


FEBRUARY 12, 2018

AutoQuiz: Can You Identify the P&ID Symbol?


FEBRUARY 9, 2018

What You Can Learn About Pipeline Leaks From Government Statistics
FEBRUARY 7, 2018

Plant-Wide Control Design Based on Steady-State Combined Indexes


FEBRUARY 5, 2018

AutoQuiz: What Is PID in a Control Loop?


FEBRUARY 2, 2018

Connectivity, Productivity and Efficiency Benefits of IIoT Depend on Integrated Cybersecurity


JANUARY 31, 2018

Managing the Cybersecurity Threat to Hazardous Process Plants


JANUARY 29, 2018

AutoQuiz: Line Symbol Identification


JANUARY 26, 2018

Webinar Recording: Drivers for Cloud SCADA Operations


JANUARY 24, 2018

Broadening ISA’s Global Perspective and Focusing on the Next Generation of ISA Members
JANUARY 23, 2018

Measuring Fuel Oil Viscosity in a Power Plant


JANUARY 22, 2018

AutoQuiz: What Is the Maximum Level of Precision Available Using Modbus?


JANUARY 19, 2018

Tuning of IMC-Based PID Controllers for Integrating Systems with Time Delay
JANUARY 17, 2018
https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 13/14
2/17/2018 DCS Upgrade: How to Reduce Stress During Execution

Why You Must Incorporate Safety and Cybersecurity Standards Into Your Automation Design
JANUARY 15, 2018

Search this Blog

Search... 

Sitemap || Contact Us

Posted on February 12, 2018  

© 2018 ISA Interchange. All Rights Reserved.

https://automation.isa.org/2018/02/dcs-upgrade-reduce-stress-execution/ 14/14

You might also like