You are on page 1of 119

TECHNICAL REPORT & SPECIFICATION

Name of Road Kalmidih To Barampur

Situation of Work At Block :- Lormi

Estimated cost Rs ( Lacs ) - 105.83

Authourity (a) Technical Sanction :-

(b) Administrative Sanction :-

Neccesity of Work To provide the transportation and comunication facility to the villagers

Provision Estimate has following provision

1. 300 mm th Subgrade in full width of Road


2. 125mm thick GSB in 4.05 m Width
3. 150 mm thick WMM - 3.80 m width of road as non availabilitiy G-II and
G-III metal

4. 20mm PMC with Seal coat in 3.75m width


5. Hard Shoulder 1.875 m width in both side
Rates Estimate prepared on the basis on SOR enforcd by 01.09.2014 issued by Chief
Engineer , C.G. Rural Road Development Agency , Raipur (C.G.)

Specification As IRC :SP - 72 -2015 & SP - 62

Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli
TECHNICAL REPORT & SPECIFICATION

Name of Road Kalmidih To Barampur

Name of Work Construction of Yatri Pratikchhalay+ Toilet Block + Hand pump

Situation of Work At Block :- Lormi

Estimated cost Rs ( Lacs) 0.000

Authourity (a) Technical Sanction :-

(b) Administrative Sanction :-

Neccesity of Work To provide the transportation and comunication facility to the villagers

Provision Estimate has following provision

1 Foundation - Column Foundation

2 Base Concrete - Plain Cement Concrete 1:4:8 with 40 mm graded metal

3 Brick Masonary - Class 25 brick masonary for super structure CM1:6

4 The R.C.C. 1:2:4 is provided in footing , column , plinth beam , lintel , chajja ,
self and slab .
5 Door and window - Steel frem and Flush door shutter

6 Plaster - 15 mm with CM 1:6 of wall inside and outside

7 Flooring - Kota Stone slab flooring

8 Painting - Ready mix paint two coats doors and windows with one coat of
prime coat
9 Washing - Snowcem Painting

Rates Estimate prepared on the basis on SOR enforcd by 01.09.2014 issued by


Engineer in Chief , P.W.D. Raipur

Specification

Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli
TECHNICAL REPORT & SPECIFICATION

Name of Road Kalmidih To Barampur

Name of Work Construction of Earth Embankement by NAREGA

Situation of Work At Block :- Lormi

Estimated cost Rs ( Lacs) 103.990

Authourity (a) Technical Sanction :-

(b) Administrative Sanction :-

Neccesity of Work To provide the transportation and comunication facility to the villagers

Provision Estimate has following provision

1. Widening of Road
2. Dressing of earth work
3. watering
4. Compaction
Rates Estimate prepared on the basis on Rate derived from Jilla Panchyat Bilaspur
under NAREGA

Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli
ROAD NAME - Kalmidih To Barampur
RD:- 3450 m

Step -1 Catchment area as per topo sheet 6.4 hect


or 0.064 Sq-km
Maximum peak discharge (design discharge) for the Catchment area for a
frequancy of 10 years from Dickens discharge

Step -2 Method given in IRC SP 13 Q= CM3/4 Cum / sec


here C= 14
M= Catchment area in Sq-Km

Hence Design discharge Q= 1.78 Cum / Sec


Step -3
Dischrege through Single Pipe as per mannings equation = velocity in pipe X C/S of pipe
1.00

Here,
A = Area of 1 pipe of 1000 mm dia
= 1x (3.14/4 ) x1.0x1.0
= 0.785 sqm

V = Velocity in pipe
= 1/n(R 2/3) S 1/2

n= = 0.012
R= Hydrolic radius = Area / perimeter = 0.25
S = Gradient =1 in 180 = 0.0056 0.0055556
0.396850263 0.0745356
V= 2.4650

Step -4 hence discharge through 1x1000 mm Dia pipe Q1 = 1.93 Cum/sec

Step -5 Since design discharge Q less than Q1 hence provide 1 Row of 1000mm Dia Pipe Culvert

Step -6 Q< Q1 hence safe

consultant Sub - Engineer Assistant Engineer,


ROAD NAME - Kalmidih To Barampur
At CH. 1190 m

Step -1 Catchment area as per topo sheet 11.3 hect


or 0.113 Sq-km
Maximum peak discharge (design discharge) for the Catchment area for a
frequancy of 10 years from Dickens discharge

Step -2 Method given in IRC SP 13 Q= CM3/4 Cum / sec


here C= 14
M= Catchment area in Sq-Km

Hence Design discharge Q= 2.73 Cum / Sec


Step -3
Dischrege through Slab Culvert as per mannings equation = velocity X C/S = Ax V
Assumed Slab Culvert Span L= 1.50 M
Assumed Slab Culvert Height H= 1.50 M
After deduction of free board ht.= 1.20 M

Velocity in pipe V= 1/n(R 2/3) S 1/2

n= as per IRC SP 42 0.022


R= Hydrolic radius = Area / perimeter= (d/4) 0.4000
S = Gradient = 1 : 210 0.0048
0.5428835233 0.0690066
V= 1.70 m/sec
Cross Section Area A= LxH

hence A= 1.80 Sqm

Step -4 hence discharge through 1x 1.50 m Culvert Q1 = 3.07 Cum/sec

Step -5 Since design discharge Q less than Q1 hence provide 1x 1.50 M culvert

Step -6 Q< Q1 hencr safe

consultant Sub - Engineer Assistant Engineer,


ROAD NAME - Kalmidih To Barampur
At CH. 1800 m

Step -1 Catchment area as per topo sheet 38 hect


or 0.38 Sq-km
Maximum peak discharge (design discharge) for the Catchment area for a
frequancy of 10 years from Dickens discharge

Step -2 Method given in IRC SP 13 Q= CM3/4 Cum / sec


here C= 14
M= Catchment area in Sq-Km

Hence Design discharge Q= 6.78 Cum / Sec


Step -3
Dischrege through Slab Culvert as per mannings equation = velocity X C/S = Ax V
Assumed Slab Culvert Span L= 3.00 M
Assumed Slab Culvert Height H= 1.80 M
After deduction of free board ht.= 1.50 M

Velocity in pipe V= 1/n(R 2/3) S 1/2

n= as per IRC SP 42 0.04


R= Hydrolic radius = Area / perimeter= (d/4) 0.6818
S = Gradient =1 in 94 0.0106
0.7746622368 0.1031421
V= 2.00 m/sec
Cross Section Area A= LxH

hence A= 4.50 Sqm

Step -4 hence discharge through1x 3.00 m Culvert Q1 = 8.99 Cum/sec

Step -5 Since design discharge Q less than Q1 hence provide 1x 3.00 M culvert

Step -6 Q< Q1 hencr safe

consultant Sub - Engineer Assistant Engineer,


0.047619
KEY PLAN
NAME OF ROAD :- Kalmidih To Barampur
DISTRICT :- Mungeli
BLOCK :- Lormi
LENGTH :- 2.220 Km

RD 1820

Karankapa Rd 1400 Barampur


End Chainage

Pro. CC road 300

Starting Point 0.0 m Vill. Kalmidih


Table 8.2 – Horizontal Curve details

Radius Ls Speed Def Angle Lc Ltotal


Hand of Area of
Curv
e No. IP Chainage S.E. Extra
Curve widening
(m) (m) (Kmph) D M S (m) (m)

1 840 45 0 40 0.60 32 0 0.00 25.12 25.12 R 15.07


2 930 39 0 40 0.60 24 0 0.00 16.33 16.33 R 9.80
24.87
M
U
K
H
A
Y
A MUKHYA MANTRI GRAM
M SADAK EVAM VIKAS YOJNA
A
N
T
R
I DETAILED PROJECT REPORT
G
R
A
M 2007
VOLUME I & II
S
A
D
A Name of Road:- Kalmidih To Barampur
K

E Length of road :- 2.22 Km


V
A
M Block:- Lormi
V
I
K District:- Mungeli
A
S
Total Cost (Rs.):- 105.83 Lakhs (Excluding Earthwork )
Y
O Total Cost (Rs.):- 105.83 Lakhs (Including Earthwork )
J
N
A

Executive Engineer
Rural Development Division,
CGRRDA , Mungeli
PRADHAN MANTRI GRAM SADAK

Name of Road :-Fro Kalmidih To Barampur

Length (Km. ) :- 2.220 Km. Block :- Lormi


Upgrade Lormi
New 2.220 Road No

Design CBR 3 %

CBR Value Length CBR CH


1 2.43 514
2 2220 Total Length ( M ) Drain Ord
3
4
5 C.C Road Length (m) 0 Drain(BT)
6 Scarifying of WBM Roa 700 Drain(CC)
7 Exiting ( if any ) ( M )
8 Dismantle of CC Road (m)
9 Pavement Length:- 2220
Gali
Thickness

0.595 Total Crust Thickness


0.125 G.S.B. Thickness Drain. Layer
if provide both fill twice if provide
0.300 Sub Grade/Modified Soil
0.300
0.075 G-2 0.075 G-3

No. Culvert Details Location


1000 mm HPC 1800
1x 1 m SC 0
1x 1.5 m Slab Culverts 1,190
1x 2.0 m Slab Culverts
1x 3.0 m Slab Culverts
1x5.0 m Slab Culverts
1x6.0 m Slab Culverts
2x6.0 m Slab Culverts
3x5.0 m Slab Culverts

2 No of Existing Culverts All

Village Area
Koliha
ANTRI GRAM SADAK YOJANA

Lormi District:- Mungeli

Consultant Anand Vibhor

856.6667

9540.50 Embankment Filling Qnty

Hilly Cutting length 0 Speed Breaker


501.250 Embankment Cutting Qnty Retaining Wall
7 No of Field Crossings 600 mm Toe Wall
No of Field Crossings 450 mm Pitching Length ( M )
8 No of Field Crossings 300 mm
Road Furniture Cautionary, Mandatory 5 No 470 Boundery 466.6667

0 No
Quick Accesses

General Abstract Wearing Course (m)


Pavement Estimate Filler Joint (Nos)
CC Estimate M-15 Approch Slab (m)
RCC M-25 Approch Slab (m)
Traffic Design Electric pole shifting

S.T. A Chick List Distances 25


Sand Bilaspur
Quarry Stone Mungeli Moorum Dhapai
Distances 27 1

Result of Road Cost

Cost Per Km
CD Cost 11.3 5.09 Lakha
CC Road 0 #DIV/0! Lakha
Total Cost 25.40 11.440 Lakha

From To Unconnected Habitation


1020 1230 210 Koliha Popula 469
0
0
0 L0
0.210
MUKHAYA MANTRI GRAM SADAK EVAM VIKAS YOJANA

GENERAL ABSTARCT

Name of Road :- Kalmidih To Barampur Package No :-


District :- Mungeli BLOCK :- Lormi
Length :- 2.22 Km

Length of
S.No. Item of work Road Cost Total cost
(Km)

Cost of Earthwork etc. Under


2.22 0
MGNREGA

1 Cost of (Bituminous+CC) Road 2.220 10088198

2 Cost of Cement Concrete Road (gali) 0.000 0

3 Cost of C.D. works i/c Protection 0

Other works (Yatri Pratikchhalay+


4 0 0
Toilet Block + Hand pump)
Total Length of Road (Km) 2.220 10088198 10088198
Sub Total 10088198
Add 1 % Contingency
5 Preparation of D.P.R. 0
6 Maintenance cost 310800
Grand Total (Excluding MGNREGA ) 10398998
Grand Total (Including MGNREGA ) 10398998
Cost of road per Km is ( Rs) 4684233

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli

Superintending Engineer
Chhattisgarh Rural Road Development Agency
Project Circle Bilaspur (C.G.)
MUKHAYA MANTRI GRAM SADAK EVAM VIKAS YOJANA
GENERAL ABSTARCT
Name of Road :- Kalmidih To Barampur
Vidhansabha :- Lormi
Block :- Lormi
Length(km):- 2.22
Per km
S.No. Particular of Work Quantity Unit Amount cost (in Remark
lakhs)
1 Bituminous Road
a Flexible Pavemnt 2.22 km 87.93 39.61
b Drain along with Flexible Pavement 0.00 km 0.00 #DIV/0!
Total 1(a+b) 87.93
2 CC Road
c Rigid Pavement 0.00 km 1.85 #DIV/0!
d CC Drain along with rigid Pavment 0.00 km 0.00 #DIV/0!
Total 2(c+d) 1.85
3 C. D. Work (as per Site Condition)
I 1000 mm dia HPC 0.00 No 0.00
II 1.0 MTR. SLAB CULVERT 0.00 No 0.00
III 1.5 MTR. SLAB CULVERT 0.00 No 0.00
IV 3.00MTR SLAB CULVERT 0.00 No
V 6.00MTR. SLAB CULVERT 0.00 No
VI V.C.W. 5 ROW OF 1000 mm Dia 0.00 No
VII V.C.W. 10 ROW OF 1000 mm Dia 0.00 No
VIII V.C.W. 15 ROW OF 1000 mm Dia 0.00 No
Total 1(I+II+III+IV+V+VI+VII+VIII) 0.00 0.00
Protection work (Retaining Wall, Toe wall 0.00 km 0.00
4 ,Pitching etc.)
5 Field Crossing 15.00 No 5.81

6 Road furniture 7.14

7 Earthwork Cost 0.00

A Total Cost (1+2+3+4+5+6+7) 102.73


B Add 2% Contengency (Total Cost A)

C Maintanance Cost @ 4.10 Lacs Per K.M. 3.11

D DPR Preparation 0.00

G. Total (A+B+C+D+E) 105.83 47.67 Lacs

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli
MUKHAYA MANTRI GRAM SADAK YOJANA
DETAILED COST ESTIMATE
Name of Road - Kalmidih To Barampur Format F-6
Length of Road:-
2.22 Dist. :- Mungeli
Block :- Lormi

Sr. SSR Description of Item


no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No.
1 2 3 4 5 6 7 8 9 10 11
(A) Flexible Pavement
1 2.1 Setting out :- Setting out work complete wiyh construction of bench
mark ( min 1 / km ), working bench mark ( min 4/km ) and near all
bridges & CD works made of bricks/ stone masonary or concrete and
reference pillars made of Precast concrete poles/ concrete filled 100
mmdia AC pipe @ 100 m interval of as required on both sides of the
formation width , marking on central line , setting out curves and
recording of central line levels and other required levels and distance
etc. including setting out of CD & bridges with required reference
pillars and marking etc. as directed by Engineer - in - charge

1 2.220 2.220 km 14968.00 33228.96


2 2.3 Clearing and grubbing road land including uprooting wild vegetation,
grass, bushes, shrubs, saplings and trees of girth upto 300 mm,
removal of stumps of such trees cut earlier and disposal of
unserviceable materials and stacking of serviceable material to be
used or auctioned, upto a lead of 1000 m including removal and
disposal of top organic soil not exceeding 150 mm in thickness as per
Technical Specification Clause 201.

(A) In area of non throny jungle 1 2220.000 3.00 6660.00 sqm 3.00 19980.00
3 2.2 Clearing Grass and Removal of Rubbish: Clearing grass and
removal of rubbish up to a distance of 30 m outside the periphery of
the area as per Technical Specification Clause 201.
2220.000 3.00 0.00 sqm 0.81 0.00
Sr. SSR Description of Item
no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No.
1 2 3 4 5 6 7 8 9 10 11
2 2.14 Removal of Telephone/Electric Poles and Lines Removal of
telephone/electric poles with wires including excavation and
dismantling of foundation concrete and lines under the supervision of
concerned department, disposal with all lifts and upto a lead of 1000 m
and stacking the serviceable and unserviceable material separately as
per Technical Specification Clause 202.

0 0.00 Nos 20125.00 0.00


3.1 Scarifying Existing Granular Surface to a Depth of 50 mm
Scarifying existing granular/bituminous surface to a depth of 50 mm
and disposal of scarified material with a lift upto 3 m and leads upto
1000 m as per Technical Specification Clause 301.4.
( Rd0 to 650 m )
1 2.7 - sqm 16.00 0.00
2 3.2 Compacting original ground / Existing Embankement
(i)Compacting
original ground supporting embankement/subgrade Loosing ,
levelling and compacting original ground supporting embankement /
subgrade to facilitate placement of first layer of embankement ,
scarified to a depth of 150 mm mixed with water at OMC and then
compacted by compacted by rolling to achieve minimum dry density
as given in table 300.1 and 300.2 for embankement construction as
per Technical Specification Clause 301.4.1 Rd 0 to to 1820m
1 2220 9.88 0.15 3,290.04 Cum 23.00 75670.92
4 3.5(i) Excavation in cutting in soil with lead upto 50m:--Excavation for
roadway in soil for caryying of cut earth to embankment site with all
lift and lead upto 50m as per technical specification clause no. 302.3

as per earth work calculation statement 501.25


CC galli 1 300 5.00 0.350 525.00
For making proper embankement width 2220 7.00 0.200 0.00
1026.25 Cu.m 76.00 77995.00
5 3.3(i) Construction of embankment with material obtained from
roadway cutting:--a.Construction of embankment with approved
materials deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and compacted to
meet requirement of Tables 300.1 and 300.2 as per Technical
Specification Clause 301.5
Cu.m 60.00
Sr.
5 3.3(i)
SSR Construction of embankment Description of Item obtained from
with material
no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No. roadway cutting:--a.Construction of embankment with approved
1 materials
3 deposited at site from roadway cutting and excavation from 4 5 6 7 8 9 10 11
2
drain and foundation of other structures graded and compacted to
meet requirement of Tables 300.1 and 300.2 as per Technical
Specification Clause 301.5
501.25 Cu.m 60.00 30075.00
6 3.4(i) Construction of embankment with approved material obtained
from borrow pits, transporting to site, spreading, grading to required
slope and compacting using Vibratory Roller to meet requirement of
Tables 300.1 and 300.2 with a lead up to250 m as per Technical As Per Earth Work
Specification Clause 301.5 Calculation
(9540.5 - 1026.25) 9039.25 Cu.m 152.00 1373966.00
7 3.12(b) Construction of subgrade and earthen shoulders with approved
material (Granular Material having CBR more than 7%) with all lifts
and leads, transporting to site, spreading, grading to required slope
and compacted to meet requirement of Table 300.2 as per Technical
Specification Clause 303.1.
2220 9.24 0.30
Qty required in CC road section ( as per calculation sheet)

As a subgrade ( Rd 0 to to 1820 m )
1 2220 9.28 0.30 6180.48
Earthen Shoulders ( Rd 0 to to 18200 m )
2 2220 2.190 0.125 1215.45
7395.93 Cu.m 176.00 1301683.68
8 3.8(i) Surface drain in soil- Construction of unlined surface drains of
average cross section 0.4 sqm in soil to specified lines , grades ,
levels and dimension . Excavated material to be used in
embankement with a lift upto 3 m and lead of 50 m ( average lead 25
m ) as per Technical Specification Clause 307
1 0 0.00 Rmt 40.00 0.00
9 4.1 Grainular subbase with well graded material (table 400.1):----
Construction of granular sub-base by providing well graded material,
A(iii) spreading in uniform layers with motor grader on prepared surface,
mixing by mix in place method with rotavator at OMC, and
compacting with vibratory wheel roller to achieve the desired
density, complete as per Technical Specification Clause 401.

(A) Crushed Stone Materail


(iii) For Grading - III Material
( Rd 0 to to 1820 m ) 1 2220 4.05 0.125 1123.88
Extra widening at Junction at Rd 1400 m
1 15 5 0.125 9.38
Sr. SSR Description of Item
no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No.
1 2 3 4 5 6 7 8 9 10 11
Extra Widining ( As per Curve design )
1 24.87 0.125 3.11
Total 1136.36 Cu.m 820.00 931814.05
10 4.12 Construction of hard shoulder as per technical specification clause
407:---Construction of hard shoulder with selected granular material
having CBR value not less than 15 including all leads & lift, watering &
compaction with smooth wheeled roller to achieve the desired density
as per technical specification clause 407 & 401.

Side of WMM and BT 2 2220 2.02 0.17 1524.70

1524.696 Cu.m 358.00 545841.17


19 4.8 Wet Mix Macadam :- Providing, laying, spreading and compacting
graded stone aggregate to wet mix macadam specification including
premixing the material with water at OMC in mechanical mixer (Pug
Mill), carriage of mixed material by tipper to site, laying in uniform
layers in sub-base/base course on a well prepared sub-base and
compacting with smooth wheel roller of 80 to 100kN weight to achieve
the desired density including lighting, barricading and maintenance of
diversion, etc as per Tables 400.11 & 400.12 and Technical
Specification Clause 406.
1 2220 3.8 0.15 1265.4 Cu.m 1583.00
Extra widening at Junction at Rd 1400 m 1 15 5 0 11.25
Extra Widining ( As per Curve design ) 1 25 0 3.73
1280.38032 Cu.m 1583.00 2026842.05
11 4.7(2) WBM Grading 2:--Providing, laying, spreading and compacting
Mechanically crushed stone aggregates of specific sizes to water
bound macadam specification including spreading in uniform
thickness, hand packing, rolling with three wheel 80-100 kN static
roller in stages to proper grade and camber, applying and brooming,
crushable screening to fill-up the interstices of coarse aggregate,
watering and compacting to the required density Grading II as per
Technical Specification Clause 405.(Deduct if hand broken stone
aggregates used Rs 200 / cum )
1 2220 3.85 0.075
Extra Widining at Structure 0 3 6.7 0.075
Sr. SSR Description of Item
no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No.
1 2 3 4 5 6 7 8 9 10 11
0 1.5 1.5 0.075
Extra widening at Junction at Rd 1400 m 1 15 5 0.075
Extra Widining ( As per Curve design )
1 24.87 0.075
0.000 Cu.m 1583.00 0.00
12 4.7(3) WBM Grading 3:-Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling with
three wheel 80-100 kN static roller in stages to proper grade and
camber, applying and brooming, crushable screening to fill-up the
interstices of coarse aggregate, watering and compacting to the
required density Grading 3 as per Technical Specification Clause 405.
(Deduct if hand broken stone aggregates used Rs 200 / cum )

Grading No. 3 material 53mm To 22.4mm 1 2220 3.75 0.075


Extra widening at Junction at Rd 1400 m 1 15.0 5 0.075
Extra Widining ( As per Curve design ) 1 24.87 0.075
0.00 Cu.m 1694.00 0.00
13 5.1 Prime coat
Providing and applying primer coat with bitumen
emulsion (SS-1) on prepared surface of granular base including
cleaning of road surface and spraying primer at the rate of 0.70-1.0
kg/sqm using mechanical means as per Technical Specification
Clause 502
1 2220 3.75 8325.00
Extra widening at Junction at Rd 1400 m 1 15.0 5 75.00
Extra Widining ( As per Curve design ) 1 24.87 24.87
8424.87 Sq.m 53.00 446518.05
14 5.2(ii) Tack coat
(ii)Providing and applying tack coat with
Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25
to 0.30 kg per sqm on the prepared dry and hungry bituminous
surface cleaned with Hydraulic broom as per Technical Specification
Clause 503. 1 2220 3.75 8325.00
Extra widening at Junction at Rd 1400 m 1 15 5 75
Sr. SSR Description of Item
no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No.
1 2 3 4 5 6 7 8 9 10 11
Extra Widining ( As per Curve design ) 1 24.87 24.87
8424.87 Sq.m 18.00 151647.64
15 5.3 (ii) 20 mm thick Open Graded Premix Carpet using Bituminious
( VG/modified bitumen) Binder
Providing, laying and rolling of open-graded premix
carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm
aggregates either using penetration grade bitumen/VG bitumen or
emulsion to required line, grade and level to serve as wearing course
on a previously prepared base, including mixing in a suitable plant,
laying and rolling with a three wheel 80-100 kN static roller capacity,
finished to required level and grades to be followed by seal coat of
either Type A or Type B or Type C as per Technical Specification
Clause 508. Viscocity grade (VG) Bitumen specification as per
IS73:2006

(ii) Bitumen (VG-30) 1 2220 3.75 8325.00


Extra widening at Junction at Rd 1400 m 1 15 5 75.00
Extra Widining ( As per Curve design ) 1 24.87 24.87
8424.87 Sq.m 155.00 1305854.66
16 5.5B(ii) Seal Coat

Providing and laying Seal Coat sealing the voids in a bituminous


surface laid to the specified levels, grade and cross fall using Type B
as per Technical Specification Clause 510
Case II -
Type B
(ii) Bitumen (VG-30) 1 2220 3.75 8325.00
Extra widening at Junction at Rd 1400 m 1 15 5 75
Extra Widining ( As per Curve design ) 1 24.87 24.87
8424.87 Sq.m 56.00 471792.65
17 6.5 Construction of Plain Cement Concrete Drain with P.C.C. grade M-
15 including all shuttering/form work etc. complete as per
drawings/technical specification and direction of engineer in charge.

For CC Drain along with Flexiable pavement (0 to 200 RHS)


1 0 0.70 0.15 0
Sr. SSR Description of Item
no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No.
1 2 3 4 5 6 7 8 9 10 11
For CC Drain along with Flexiable pavement (0 to 200 RHS)
2 0 0.40 0.15 0
0.000 Cum 3811.00 0.00
Total of (A) Flexible Pavement 8792909.83
( B) Rigid Pavement
18 4.1 Grainular subbase with well graded material (table 400.1):----
Construction of granular sub-base by providing well graded material,
A(iii) spreading in uniform layers with motor grader on prepared surface,
mixing by mix in place method with rotavator at OMC, and
compacting with vibratory wheel roller to achieve the desired
density, complete as per Technical Specification Clause 401.

(A) Crushed Stone Materail


(iii) For Grading - III Material
Main road karankapa to rajesh satnami house 1 300 5 0.15 225.00
Total 225.00 Cu.m 820.00 184500.00

19 6.1(ii) Cement Concrete Pavement


(ii) Construction of un-reinforced, jointed at expansion and
construction joint only, plain cement concrete pavement, thickness as
per design, over a prepared sub base, with 43 grade cement or any
other type as per Clause 1501.2.2 M30 (Grade), coarse and fine
aggregates conforming to IS:383, maximum size of coarse aggregate
not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2
cum capacity and appropriate weigh batcher using approved mix
design, laid in approved fixed side formwork (steel channel, laying
and fixing of 125 micron thick polythene film, wedges, steel plates
including leveling the formwork as per drawing), spreading the
concrete with shovels, rakes, compacted using needle, screed and
plate vibrators and finished in continuous operation including provision
of contraction and expansion, construction joints, applying, primer,
sealant,
using curing compound (where specified) and water finishing to lines
and grade as per drawing and Technical Specification Clause 1501.
Sr. SSR Description of Item
no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No.
1 2 3 4 5 6 7 8 9 10 11
Main road karankapa to rajesh satnami house 1 0 3.750 0.2 0.00
0.00 Cum. 5097.00 0.00
22 6.5 Construction of Plain Cement Concrete Drain with P.C.C. grade M-
15 including all shuttering/form work etc. complete as per
drawings/technical specification and direction of engineer in charge.

2 0 0.80 0.15 0
0 2 0 0.30 0.15 0
0.000 Cum 3811.00 0.00
Total of ( B) Rigid Pavement 184500.00
(C) Protection Work
Total of (C) Protection Work 0.00
(D) Field Crossing

26 3.5(i) Excavation in cutting in soil with lead upto 50m:--Excavation for


roadway in soil for caryying of cut earth to embankment site with all
lift and lead upto 50m as per technical specification clause no. 302.3

For Field crossing - 300 mm dia.


8 12.50 0.80 0.8 64.00
for provided field crossing pipes(600 mm Dia)
7 12.5 1.00 1.00 87.50
Total
87.50 Cum 76.00 6650.00
27 7.3(ii) Bedding for Causeway / pipes

Type B (First Class) Bedding

Laying (First Class) bedding on well


for field crossing
compacted sand, pipes
moorum(300
ormm Dia) granular material as per
approved 8 12.50 0.70 0.00
Clause
for field1105
crossing pipes(600 mm Dia) - 7 12.50 1.00 0.00
0.00 Cum 956.00 0.00
Sr. SSR Description of Item
no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No.
1 2 3 4 5 6 7 8 9 10 11
28 7.6 Providing and laying reinforced cement concrete pipe NP3 for
culverts/Burried conduits on first class bedding of granular material
including fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonry works
in head walls and parapets Clause 1106.

(d) for field crossing pipes (300 mm Dia) 8 12.50 100.00 Rmt 1129.00 112900.00
7.6(A) for field crossing pipes(600 mm Dia) -
7 12.50 87.50 Rmt 2928.00 256200.00
7.10 Providing concrete for plain/reinforced concrete in open foundation
(ii) complete as per drawings and technical specifications Clause 802,
803, 1202 & 1203
P.C.C grade M 15(Nominal mix (1:2.5:5)
FOR of 600 mm dia Field crossing
7 12.50 1.325 0.2 23.19

42 0.30 1.325 1.025 17.11


Deduction for pipe
-42 0.30 0.785 0.52563 -5.20
FOR f 300 mm dia Field crossing
7 12.50 0.800 0.2 14.00

42 0.30 0.800 0.6 6.05


Deduction for pipe
-42 0.30 0.785 0.25 -2.47

52.68 cum 3899.00 205384.38


Total of (D) Field Crossing 581134.38
(D) TRAFFIC SIGNS AND OTHER APPURTENANCES
Sr. SSR Description of Item
no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No.
1 2 3 4 5 6 7 8 9 10 11
29 9.2(A) Cautionary, mandatory, informatory direction and place identification sign
boards. (A)Semi-
Reflective Traffic signs upto 0.90 sqm
Direction and place indentification signs up to 0.9 sqm size board
Providing and erecting direction and place identifications of semi reflective
sign boards as per IRC:67 made of 2 mm thick M.S. Sheet duly stove
enameled paint in white colour in front and grey colour on back with red
reflective border of 70 mm width and required message, letters, figures with
reflective engineering grade tape as per MORD specifications of required
shade and colour. Supported and welded on 47 mm x 47mm of 12 SWG
Square tube of 3050 mm height duly strengthened by 25 mm x 5 mm M/s
flat iron on edges on back firmly fixed to the ground by means of properly
designed foundations with M-15 grade cement concrete 450 mm x 450 mm x
600 mm, 600 mm below ground level as per approved drawing and Technical
Specification Clause 1701

5 0.90 0.90 4.05 sqm 5308.00 21497.40


30 9.2(B) Semi-Reflective Traffic signs
more than 0.90 sqm sign board
Providing and erecting direction and place identification of semi reflective
sign boards as per IRC-67 made of 2 mm thick M.S. Sheet duly stove
enameled paint white colour in front and grey colour on back with reflective
border of 70 mm width and required message, letters, figures with reflective
tape of engineering grade as per MORD specifications of required shade and
colour. Supported and welded on two nos. 47 mm x 47 mm of 12 SWG
square tube of 3050 mm height duly strengthened by 25 mm x 5 mm MS flat
iron on edges on back firmly fixed to the ground by means of properly
designed foundations with M-15 grade cement concrete 450 mm x 450 mm x
600 mm, 600 mm below ground level as per approved drawing and Technical
Specification Clause 1701
2 2.00 sqm 4667.00 9334.00
31 9.8 Kilometre Stone Reinforced cement concrete M15 grade kilometre
stone/local stone of standard design as per IRC:8 fixing in position including
painting and printing, etc as per drawing and Technical Specification Clause
1703
(i) 5th Kilometre Stone (precast) 0 0 Each 3605.00 0.00
(ii) Ordinary Kilometer Stone (Precast) 3 3 Each 2154.00 6462.00
(iii) 200 m stone (precast) 6 6 Each 449.00 2694.00
Sr. SSR Description of Item
no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No.
1 2 3 4 5 6 7 8 9 10 11
32 9.9 Boundary Pillar Reinforced cement concrete M15 grade boundary
pillars/local stone of standard design as per IRC:25, fixed in position
including finishing and lettering but excluding painting as per drawing and
Technical Specification Clause 1704
470 470 Each 489.00 229830.00
33 9.14 Providing and Fixing Informtory and Logo Board of PMGSY Project
(B) (B)
Providing and fixing of typical PMGSY informatory sign board with Logo as
per MORD specifications and drawing. Three MS Plates of 1.6 mm thick, top
and middle plate duly welded with MS flat iron 25mm x 5m size on back on
edges. The lower plate will be welded with MS angle iron frame of 25mm x
25mm x 5mm. The angle iron frame of the lower most plate and flat iron 1 1 Each 14930.00 14930.00
frame of middle plate will be welded to 2 nos. 75mm x 75 mm of 12 SWG
34 9.15 10.15(A)
sheet tubesProviding
posts dulyandembedded
fixing 'Citizen
in cementInformation Board'
concrete M-15 of blocks
grade PMGSY of
(A) Project (A) Providing and fixing of
450mm x 450mm x 600mm, 600mm below ground level. The toptypical " PMGSY Citizen
most
Information
diamond plateBoard"
will bewith
weldedLogo as per plate
to middle MoRD by specifications
47mm x 47mm&ofdrawings,
12 SWG
made
steel plate tube. All M.S. will be stove enameled ontube
of 75 mm square or 75 mm dia circular steel bothofsides.
12 SWG 3.2 m
Lettering
height and cross member 2 nos 1m long, fixed with angle iron 50x50x5
and printing arrows, border etc. will be painted with ready mixed synthetic mm
MS angle on the back
enamel paint of superior quality in required shade and colour. All sections of
framed posts and steel tube will be painted with primer and two coats of 2 2 Each 14015.00 28030.00
35 9.18 epoxy
Road paint as perwith
marking drawing
Hot Clause
Applied1701 and Annexure Compound
Thermoplastic 1700.1 with
Reflectorizing Glass Beads on Bituminous Surface (Providing and
laying of hot applied thermoplastic compound 2.5 mm thick including
reflectorizing glass beads @ 250 gms per sqm area, thickness of 2.5
mm is exclusive of surface applied glass beads as per IRC: 35. The
finished surface to be level, uniform and free from streaks and holes.)
2 2220.00 0.10 444 sqm 904.00 401376.00
Total of (D) TRAFFIC SIGNS 714153.40
(E) LAY BY PLATFORM ESTIMATE
36 Preperation of DPR with survey 1 2.22 2.22 km 13000.0
Total of (E) DPR Preperation 0.00
Total Pavement Cost 10272697.61

Sub. Engineer Asst. Engineer Executive Engineer #VALUE!


Rural Development Division,
CGRRDA , Mungeli
Suplementary Shedule of Extra item and 25% beyond BOQ
Package No :- MGL -19
Name of Contractor :- M/s Landmark Royal Engineering (I) Pvt Ltd
Road from Kalmidih To Barampur
Agrement No- 150 DL/MMGSY/2018-19 dt 09/05/2018
length 1.80km

As per Boq As per Revise Excess(-)


SS
Sr. R
no Description of Item Unit Rate Qty Amount Qty Amount Qty Amount Remark
I.N
o.
1 2 3
6 3.2 Compacting original ground / Existing
Embankement

(i)Compacting original ground supporting


embankement/subgrade Loosing , levelling
and compacting original ground supporting
embankement / subgrade to facilitate
placement of first layer of embankement , Beyond
scarified to a depth of 150 mm mixed with Cum 23.00 2074.80 47720 3290.04 75671 -1215.24 -27951
25%
water at OMC and then compacted by
compacted by rolling to achieve minimum dry
density as given in table 300.1 and 300.2 for
embankement construction as per Technical
Specification Clause 301.4.1 ( Rd 700 to 850
m)

13 3.5(i) Excavation in cutting in soil with lead upto


50m:--Excavation for roadway in soil for Beyond
Cu.m 76.00 442.61 33638 1113.75 84645 -671.14 -51007
caryying of cut earth to embankment site with 25%
all lift and lead upto 50m as per technical
17 3.1 Construction of no.
specification clause subgrade
302.3 and earthen
shoulders with approved material (Granular
Material having CBR more than 7%) with all
lifts and leads, transporting to site, spreading,
Beyond
grading to required slope and compacted to Cu.m 176.00 4664.10 820882 7395.93 1301684 -2731.83 -480802
25%
meet requirement of Table 300.2 as per
Technical Specification Clause 303.1.

194.1A(iii)
Grainular subbase with well graded material
(table 400.1):---- Construction of granular
sub-base by providing well graded material,
spreading in uniform layers with motor grader
on prepared surface, mixing by mix in place Beyond
method with rotavator at OMC, and Cu.m 820.00 990.26 812012 1361.36 1116314 -371.10 -304302
25%
compacting with vibratory wheel roller to
achieve the desired density, complete as per
Technical Specification Clause 401.

227.3(ii)Bedding for Causeway / pipes Type B (First Beyond


Cum 956.00 12.75 12189 0.00 0 12.75 12189
Class) Bedding 25%
23 4.8 Wet Mix Macadam :- Providing, laying,
Laying
spreading and compacting graded stone Cu.m 1583.00 0.00 0 1280.38 2026842 -1280.38 ### Extra item
(First Class) bedding on well compacted sand,
aggregate to wet mix macadam specification
moorum or approved granular material as per
including premixing the material with water at
Clause 1105 For Field Crossing
26 5.1 Prime
OMC incoat mechanical mixer (Pug Mill), carriage
of mixed material by tipper to site, laying in Beyond
Sq.m 53.00 5460.87 289426 8424.87 446518 -2964.00 -157092
uniform layers
Providing in sub-base/base
and applying primer coatcourse
with on a 25%
well prepared
bitumen sub-base
emulsion and
(SS-1) oncompacting
prepared with
275.2(ii)Tack
smooth
surface coat
ofwheel roller
granular of 80
base to 100kN
including weightofto
cleaning
achieve
road the desired
surface density
and spraying including
primer at thelighting,
rate Beyond
Sq.m 18.00 5460.87 98296 8424.87 151648 -2964.00 -53352
(ii)Providing
barricading
of andmaintenance
and
0.70-1.0 kg/sqm applying tackofcoat
using mechanical with
diversion,
meansetc 25%
Bitumen
as per emulsion
per Technical
Tables (RS-1)
400.11 using
& 400.12
Specification emulsion
and
Clause Technical
502
distributor
295.3 (ii)20 mm thick
Specificationat the
OpenrateGraded
Clause of 0.25 Premix
406. to 0.30 kg per
Carpet
sqm onBituminious
using the prepared( dry and hungrybitumen)
VG/modified
bituminous
Binder surface laying
Providing, cleanedandwith Hydraulic
rolling of open-
broom as
graded per Technical
premix carpet ofSpecification
20 mm thickness Clause
503.
composed of 13.2 mm to 5.6 mm aggregates
either using penetration grade bitumen/VG
Beyond
bitumen or emulsion to required line, grade Sq.m 155.00 5460.87 846435 8424.87 1305855 -2964.00 -459420
25%
and level to serve as wearing course on a
previously prepared base, including mixing in
a suitable plant, laying and rolling with a three
wheel 80-100 kN static roller capacity, finished
to required level and grades to be followed by
seal coat of either Type A or Type B or Type C
305.5B(ii)as
Seal perCoat
Technical Specification Clause 508.
Beyond
Viscocity grade (VG) Bitumen specification as Sq.m 56.00 5460.87 305809 8424.87 471793 -2964.00 -165984
per IS73:2006(ii) Bitumen (VG-30) 25%
Providing and laying Seal Coat sealing
the voids in a bituminous surface laid to the
specified levels, grade and cross fall using
Type B as per Technical Specification Clause
SS
Sr. R
no I.N Description of Item Unit Rate Qty Amount Qty Amount Qty Amount Remark
o.
1 2 3
327.6 (A)Providing and laying reinforced cement
concrete pipe NP3 for Culverts/ Burried
conduits on first class bedding of granular
material including fixing collar with cement
mortar 1:2 but excluding excavation, Beyond
protection works, backfilling, concrete and Rmt 2928.00 50.00 146400 87.50 256200 -37.50 -109800
25%
masonry works in head walls and parapets as
per Clause 1106

(A) 600 mm dia


347.6 (D)300 mm Dia Beyond
Rmt 1129.00 50.00 56450 100.00 112900 -50.00 -56450
25%
39 7.1 Providing concrete for plain/reinforced
0 concrete in open foundation complete as per Beyond
drawings and technical specifications Clause Cum 3899.00 77.57 302436 52.68 205384 24.89 97051
25%
(ii) 802, 803, 1202 & 1203

Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA MUNGELI
Comparative
Road from Kalmidih
- To Barampur
Length of Road:-
2.22

As per Boq As per actual Excess(-) saving(-)


Sr.
no
SSR Description of Item
I.No. Unit Rate Qty Amount Qty Amount Qty Amount
1 2 3
1 2.1 Setting out :- Setting out work complete wiyh construction of bench
mark ( min 1 / km ), working bench mark ( min 4/km ) and near all
bridges & CD works made of bricks/ stone masonary or concrete and km 14968.00 1.82 27241.76 2.22 33228.96 -0.40 -5987
reference pillars made of Precast concrete poles/ concrete filled 100
mmdia AC pipe @ 100 m interval of as required on both sides of the
formation width , marking on central line , setting out curves and
2 2.3 recording and
Clearing of central
grubbingline levels and including
road land other required levelswild
uprooting andvegetation,
distance
etc. including
grass, bushes,setting
shrubs, outsaplings
of CD &and
bridges
treeswith required
of girth reference
upto 300 mm, pillars sqm
and marking etc. asofdirected by Engineer
3.00 6030.00 18090 6660.00 19980 -630.00 -1890
removal of stumps such trees cut earlier- inand
- charge
disposal of
unserviceable materials and stacking of serviceable material to be used
3 2.2 or auctioned,
Clearing Grassupto a lead
and of 1000
Removal of m includingClearing
Rubbish: removalgrass
and disposal
and of
top organic
removal soil not up
of rubbish exceeding 150 mm
to a distance in m
of 30 thickness
outside as
theper Technical
periphery of the sqm
Specification Clause 201. 0.81 6030.00 4884.3 0.00 0 6030.00 4884
area as per Technical Specification Clause 201.

4 2.14 Removal of Telephone/Electric Poles and Lines Removal of


telephone/electric poles with wires including excavation and dismantling Nos 20125.00 0.00 0 0.00 0 0.00 0
of foundation concrete and lines under the supervision of concerned
department, disposal with all lifts and upto a lead of 1000 m and
5 3.1 stacking theExisting
Scarifying serviceable and unserviceable
Granular Surface to amaterial
Depth ofseparately
50 mm as per
Technical Specification
Scarifying Clause 202.
existing granular/bituminous surface to a depth of 50 mm sqm 16.00 0.00 0 0.00 0 0.00 0
and disposal of scarified material with a lift upto 3 m and leads upto
6 3.2 1000 m as peroriginal
Compacting Technical Specification
ground Clause
/ Existing 301.4. ( Rd 1004 to1480
Embankement
= 476m ) (i)Compacting Cum 23.00 2074.80 47720.4 3290.04 75670.92 -1215.24 -27951
original ground supporting embankement/subgrade Loosing , levelling
7 and compacting original ground supporting embankement / subgrade to
2.1 Removing all types of Hume pipes and stacking within a lead of
facilitate placement of first layer of embankement , scarified to a depth
1000 m i/c Earthwork and Dismantling of masonary works as per
of 150 mm mixed with water at OMC and then compacted by
Rmt 105.00 0.00 0 0.00 0 0.00 0
Technical Specification clause 202
compacted by rolling to achieve minimum dry density as given in table
8 2.10 300.1
(B) above
and 600 mm
300.2 fortoembankement
900 mm dia Hume pipe - Rd
construction as1084
per Technical
(B) (A) Upto 600 mm dia Hume pipe - Rmt 141.00 0.00 0 0.00 0 0.00 0
Specification Clause 301.4.1 ( Rd 700 to 850 m )
9 2.10 (C) Above 900 mm dia Hume pipe - Rd 505
(C )
Rmt 242.00 0.00 0 0.00 0 0.00 0
10 3.8(i) Surface drain in soil- Construction of unlined surface drains of
average cross section 0.4 sqm in soil to specified lines , grades , levels
and dimension . Excavated material to be used in embankement with a Rmt 40.00 500.00 20000 0.00 0 500.00 20000
lift upto 3 m and lead of 50 m ( average lead 25 m ) as per Technical
Specification Clause 307
Sr.
no
SSR Description of Item
I.No. Unit Rate Qty Amount Qty Amount Qty Amount
1 2 3
11 2.6 Dismentling of Structures
( A) Dismantling of Exisisting
structure like culvert , bridges retaining walls and other structure
comprising of masonry , cement concrete , wood work i/c T&P and
scaffolding wherever necessary Sorting the dismantled material Cum 277.00 0.00 0 0.00 0 0.00 0
disposal of unserviceable material with all lifts and lead of 1000m as
per Technical Specification clause 202

(A)Lime Concrete
2.6 (B)Cement Concrete
(B) Cum 317.00 0.00 0 0.00 0 0.00 0
2.6 (C))Reinforced Cement Concrete
© Cum 699.00 0.00 0 0.00 0 0.00 0
12 2.8(A) Dismentling of Stone masonary as per Technical Specification clause
202. Dismantling of Exisisting structure like culvert , bridges retaining Cum 212.00 0.00 0 0.00 0 0.00 0
walls and other structure comprising of stone masonry i/c of
13 3.5(i) unserviceable
Excavation inmaterial
cutting with all with
in soil lifts and
leadlead of 50m:--Excavation
upto 1000m as per Technical
for
Specification
roadway clause
in soil 202
for caryying of cut earth to embankment site with all lift Cu.m 76.00 442.61 33638.36 1113.75 84645 -671.14 -51007
and lead upto 50m as per (A) Rubblespecification
technical Stone masonary
clauseinno.
lime / cement/
302.3
mud mortar
14 8.3(ii) Excavation in hilly areas in soil by mechanical means including
A cutting andtrimming of side slopes and disposing of excavated cum 80.00 0.00 0 0.00 0 0.00 0
earth with a lift upto 1.5 m and a lead upto 20 m as per
15 Construction of embankment with material obtained from roadway cutting:--
3.3(i) technicalspecification
a.Construction of embankment with approved materials deposited at site from
roadway cutting and excavation from drain and foundation of other structures Cu.m 60.00 392.61 23556.6 501.25 30075 -108.64 -6518
graded and compacted to meet requirement of Tables 300.1 and 300.2 as per
Technical Specification Clause 301.5
16 3.4(i) Construction of embankment with approved material obtained
from borrow pits, transporting to site, spreading, grading to required
slope and compacting using Vibratory Roller to meet requirement of
Tables 300.1 and 300.2 with a lead up to250 m as per Technical Cu.m 152.00 5123.93 778836.6 9039.25 1373966 -3915.33 -595129
Specification Clause 301.5

17 3.12 Construction of subgrade and earthen shoulders with approved


material (Granular Material having CBR more than 7%) with all lifts and Cu.m 176.00 4664.10 820881.6 7395.93 1301683.68 -2731.83 -480802
leads, transporting to site, spreading, grading to required slope and
compacted to meet requirement of Table 300.2 as per Technical
18 3.12 Construction
Specification of subgrade
Clause and earthen shoulders with approved material
303.1.
(a) (Granular material having CBR not less than 10) obtained from Cu.m 196.00 0.00 0 0.00 0 0.00 0
borrow pits with all lifts and leads, transporting to site, spreading,
grading to required slope and compacted to meet requirement of Table
19 4.1A(iii) Grainular
300.2 as persubbase
Technicalwith well graded
Specification Clausematerial
303.1. (table 400.1):----
Construction of granular sub-base by providing well graded material, Cu.m 820.00 990.26 812012.052 1361.36 1116314.052 -371.10 -304302
spreading in uniform layers with motor grader on prepared surface,
mixing by mix in place method with rotavator at OMC, and compacting
21 4.12 Construction
with vibratoryof hard
wheelshoulder asachieve
roller to per technical specification
the desired clause
density, complete
407:---Construction of hard shoulder
as per Technical Specification with selected granular material
Clause 401. Cu.m 358.00 1122.52 401862.16 1524.70 545841.168 -402.18 -143979
having CBR value not less than 15 including all leads & lift, watering &
compaction with smooth wheeled roller to achieve the desired density
as per technical specification clause 407 & 401.
Sr.
no
SSR Description of Item
I.No. Unit Rate Qty Amount Qty Amount Qty Amount
1 2 3
22 7.3(ii) Bedding for Causeway / pipes Type B (First Class) Bedding
Cum 956.00 12.75 12189 0.00 0 12.75 12189
23 4.8 Wet Mix Macadam :- Providing, Laying (First spreading
laying, Class) beddingand on well
compacting
compacted
graded stone sand, moorumto
aggregate or wet
approved granular material
mix macadam as perincluding
specification Clause Cu.m 1583.00 0.00 0 1280.38 2026842.047 -1280.38 -2026842
1105 For Field
premixing the Crossing
material with water at OMC in mechanical mixer (Pug
Mill), carriage of mixed material by tipper to site, laying in uniform
24 4.7(2) WBM Grading 2:--Providing,
layers in sub-base/base course laying,
on a wellspreading
prepared andsub-base
compactingand
Mechanically
compacting with smooth wheel roller of 80 to 100kN weight totoachieve
crushed stone aggregates of specific sizes water Cu.m 1583.00 420.07 664963.1483 0.00 0 420.07 664963
bound
the desiredmacadamdensity specification includingbarricading
including lighting, spreading in anduniform thickness,
maintenance of
hand packing,
diversion,
WBM Grading etc rolling with
as per laying,
3:-Providing, three wheel
Tablesspreading 80-100
400.11and kN static
& compacting
400.12 and roller in stages
stone Technical
25 4.7(3) to proper ofgrade
Specification
aggregates Clauseand
specific 406.camber,
sizes applying
to water bound and specification
macadam brooming, including
crushable
screeningintouniform
spreading fill-upthickness,
the interstices of coarse
hand packing, aggregate,
rolling with three watering
wheel 80-100and Cu.m 1694.00 409.57 693803.381 0.00 0 409.57 693803
compacting
kN static roller to the required
in stages to prope density Grading II as per Technical
26 5.1 Specification
Prime coat Clause 405.
Providing and applying primer coat with bitumen Sq.m 53.00 5460.87 289426.0464 8424.87 446518.0464 -2964.00 -157092
emulsion (SS-1) on prepared surface of granular base including
27 5.2(ii) cleaning of road surface and spraying primer at the rate of 0.70-1.0
Tack coat
kg/sqm using mechanical means as per Technical Specification Clause
(ii)Providing and applying tack coat with Bitumen Sq.m 18.00 5460.87 98295.6384 8424.87 151647.6384 -2964.00 -53352
502
emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30
kg per sqm on the prepared dry and hungry bituminous surface cleaned
28 5.8 (B) MPM Construction of as
penetration macadam over prepared
with Hydraulic broom per Technical Specification Clausebase 503. by
(ii) providing a layer of compacted crushed course aggregate using chips 0 0.00 0 0.00 0
spreader with alternate applications of bituminous binder and key
aggregates and rolling with a three wheel 80-100 kn static roller to
29 5.3 (ii) 20 mm thick Open Graded
achieve the desired degree ofPremix Carpet
compaction asusing Bituminious
per technical specification
(clouse
VG/modified bitumen)
506 , Viscocity gradeBinder
(VG) Providing, laying and rolling
Bitumen specification as perof open-
graded
IS73:2006 premix carpet of 20 mm thickness composed of 13.2 mm(B) to 5.6
75
mm
mm aggregates
thick either using penetration grade bitumen/VG bitumen or
emulsion to required line, grade and level to serve as wearing course
(ii)Bitumen(VG-30)
on a previously prepared base, including mixing in a suitable plant, Sq.m 155.00 5460.87 846434.664 8424.87 1305854.664 -2964.00 -459420
laying and rolling with a three wheel 80-100 kN static roller capacity,
finished to required level and grades to be followed by seal coat of
either Type A or Type B or Type C as per Technical Specification Clause
508. Viscocity grade (VG) Bitumen specification as per IS73:2006(ii)
Bitumen (VG-30)

30 5.5B(ii) Seal Coat


Sq.m 56.00 5460.87 305808.6528 8424.87 471792.6528 -2964.00 -165984
Providing and laying Seal Coat sealing the voids in a bituminous
31 7.4(B) Laying
surface Reinforced Cementlevels,
laid to the specified Concrete Pipe
grade andNP3 asfall
cross per drawing
using Type and
B as
technical specification
per Technical Clause
Specification Clause1402.6
510
Providing and laying reinforced cement concrete
Case IIpipe NP3 for
- Type
culverts on first(VG-30)
B(ii) Bitumen class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but excluding excavation, Rmt 5177.00 0.00 0 0.00 0 0.00 0
protection works, backfilling, concrete and masonry works in head walls
and parapets Clause 1106.(B)1000 mm dia
Sr.
no
SSR Description of Item
I.No. Unit Rate Qty Amount Qty Amount Qty Amount
1 2 3
32 7.6 (A) Providing and laying reinforced cement concrete pipe NP3 for Culverts/
Burried conduits on first class bedding of granular material including fixing
collar with cement mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and parapets as per Rmt 2928.00 50.00 146400 87.50 256200 -37.50 -109800
Clause 1106
(A) 600 mm dia

33 7.6 (C) 450 mm Dia


Rmt 1961.00 0.00 0 0.00 0 0.00 0
34 7.6 (D) 300 mm Dia
Rmt 1129.00 50.00 56450 100.00 112900 -50.00 -56450
35 6.1(ii) Cement Concrete Pavement
(ii) Construction of un-reinforced, jointed at expansion and
construction joint only, plain cement concrete pavement, thickness as
per design, over a prepared sub base, with 43 grade cement or any
other type as per Clause 1501.2.2 M30 (Grade), coarse and fine
aggregates conforming to IS:383, maximum size of coarse aggregate Cum. 5097.00 315.00 1605555 0.00 0 315.00 1605555
not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2
cum capacity and appropriate weigh batcher using approved mix
design, laid in approved fixed side formwork (steel channel, laying and
fixing of 125 micron thick polythene film, wedges, steel plates including
leveling the formwork as per drawing), spreading the concrete with
36 shovels, rakes,ofcompacted
6.5 Construction usingConcrete
Plain Cement needle, screed
Drain and
withplate vibrators
P.C.C. grade M-
andincluding
15 finished all
in continuous operation
shuttering/form including
work etc. provision
complete as perof contraction
and expansion, construction joints,
Cum 3811.00 218.70 833465.7 0.00 0 218.70 833466
drawings/technical specification andapplying,
directionprimer, sealant,
of engineer in charge.
using curing compound (where specified) and water finishing to lines
37 and grade asfor
7.1(I) Excavation per drawing and
structuresas perTechnical Specification
drawing and technical Clause 1501.
specifications
Clause 305.1 including seting out, construction of shoring and bracing, Cum 161.00 0.00 0 0.00 0 0.00 0
removal of stumps and othar deletercus material and dis posal upto a
38 7.1(II) lead of 50m
Ordanary Rock dressing of sides and bottom and backfilling in trenches
with excavated suitable material . Cum 192.00 0.00 0 0.00 0 0.00 0
39 7.10 Providing concrete for plain/reinforced concrete in open foundation
(ii) complete as per drawings and technical specifications Clause 802, 803, Cum 3899.00 77.57 302435.6825 52.68 205384.3795 24.89 97051
1202 & 1203
57 9.2(A) Cautionary, mandatory, informatory direction and place identification sign
boards. (A)Semi-Reflective Traffic signs upto 0.90 sqm
Direction and place indentification signs up to 0.9 sqm size board
Providing and erecting direction and place identifications of semi reflective
sign boards as per IRC:67 made of 2 mm thick M.S. Sheet duly stove
enameled paint in white colour in front and grey colour on back with red
reflective border of 70 mm width and required message, letters, figures with sqm 5308.00 4.05 21497.4 4.05 21497.4 0.00 0
reflective engineering grade tape as per MORD specifications of required
shade and colour. Supported and welded on 47 mm x 47mm of 12 SWG
Square tube of 3050 mm height duly strengthened by 25 mm x 5 mm M/s flat
iron on edges on back firmly fixed to the ground by means of properly
designed foundations with M-15 grade cement concrete 450 mm x 450 mm x
600 mm, 600 mm below ground level as per approved drawing and Technical
Specification Clause 1701
Sr.
no
SSR Description of Item
I.No. Unit Rate Qty Amount Qty Amount Qty Amount
1 2 3
59 9.2(B) Semi-Reflective Traffic signs
more than 0.90 sqm sign board Providing and erecting direction and place
identification of semi reflective sign boards as per IRC-67 made of 2 mm
thick M.S. Sheet duly stove enameled paint white colour in front and grey
colour on back with reflective border of 70 mm width and required message,
letters, figures with reflective tape of engineering grade as per MORD
sqm 4667.00 2.00 9334 2.00 9334 0.00 0
specifications of required shade and colour. Supported and welded on two
nos. 47 mm x 47 mm of 12 SWG square tube of 3050 mm height duly
strengthened by 25 mm x 5 mm MS flat iron on edges on back firmly fixed to
the ground by means of properly designed foundations with M-15 grade
cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as
per approved drawing and Technical Specification Clause 1701
60 9.8 (I) Kilometre Stone Reinforced cement concrete M15 grade kilometre
stone/local stone of standard design as per IRC:8 fixing in position including
painting and printing, etc as per drawing and Technical Specification Clause Each 3605.00 0.00 0 0.00 0 0.00 0
1703 (i) 5th Kilometre Stone (precast)
61 9.8 (II) Ordinary Kilometer Stone (Precast) Each 2154.00 3.00 6462 3.00 6462 0.00 0
62 9.8 200 m stone (precast) Each 449.00 6.00 2694 6.00 2694 0.00 0
(III)
63 9.9 Boundary Pillar Reinforced cement concrete M15 grade boundary
pillars/local stone of standard design as per IRC:25, fixed in position
including finishing and lettering but excluding painting as per drawing and Each 489.00 470.00 229830 470.00 229830 0.00 0
Technical Specification Clause 1704
64 9.14 Providing and Fixing Informtory and Logo Board of PMGSY Project
(B) (B) Providing
and fixing of typical PMGSY informatory sign board with Logo as per MORD
specifications and drawing. Three MS Plates of 1.6 mm thick, top and middle
Each 14930.00 1.00 14930 1.00 14930 0.00 0
plate duly welded with MS flat iron 25mm x 5m size on back on edges. The
lower plate will be welded with MS angle iron frame of 25mm x 25mm x
5mm. The angle iron frame of the lower most plate and flat iron frame of
middle plate will be welded to 2 nos. 75mm x 75 mm of 12 SWG sheet tubes
65 posts dulyProviding
9.15 10.15(A) embeddedand in fixing
cement 'Citizen
concrete Information
M-15 grade blocks
Board'ofof450mm
PMGSY x
(A) 450mm
Project x 600mm, 600mm below ground
(A) Providing level. of
and fixing The top most
typical diamond
" PMGSY plate
Citizen
will be welded
Information to middle
Board" plate by
with Logo as 47mm
per MoRDx 47mm of 12 SWG
specifications & steel plate tube.
drawings, made
All M.S.
of 75 mmwill be stove
square or 75 enameled on bothsteel
mm dia circular sides.
tubeLettering
of 12 SWGand3.2
printing arrows,
m height and
bordermember
cross etc. will2be
nospainted withfixed
1m long, readywith
mixed synthetic
angle enamelmm
iron 50x50x5 paint
MSof angle
superior
on Each
quality 14015.00 2.00 28030 2.00 28030 0.00 0
the backin required shade and colour. All sections of framed posts and steel
tube will be painted with primer and two coats of epoxy paint as per drawing
Clause 1701 and Annexure 1700.1
Sr.
no
SSR Description of Item
I.No. Unit Rate Qty Amount Qty Amount Qty Amount
1 2 3
66 9.18 Road marking with Hot Applied Thermoplastic Compound with
Reflectorizing Glass Beads on Bituminous Surface (Providing and
laying of hot applied thermoplastic compound 2.5 mm thick including
reflectorizing glass beads @ 250 gms per sqm area, thickness of 2.5
mm is exclusive of surface applied glass beads as per IRC: 35. The
finished surface to be level, uniform and free from streaks and holes.)
Sq.m 904.00 295.00 266680 444.00 401376 -149.00 -134696

Total Construction 9423408 10272698 -849289


Less Tender Rtae 12% below -1130808.977 -1232723.713 101915
Total Construction cost as per aggrement 8292599 9039974 -747375
68 Maintenance of Road for I Year after Construction
st
per km 30000.00 1.82 54600 2.22 66600 -0.40 -12000
69 Maintenance of Road for IInd Year after Construction per km 40000.00 1.82 72800 2.22 88800 -0.40 -16000
70 Maintenance of Road for IIIrd Year after Construction per km 70000.00 1.82 127400 2.22 155400 -0.40 -28000
Total cost of Maintenance TOTAL 254800 310800 -56000
G. Total G. Total 9678208 10583498 -905289

Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA MUNGELI
Comparative

Remark
Remark

CC galli
excavatio
n

increase
in BT
Length

increase
in BT
Length

increase
in BT
Length

increase
in BT
Length

increase
in BT
Length
Remark

WMM
Propose
inWBM

increase
in BT
Length

increase
in BT
Length

increase
in BT
Length

increase
in BT
Length

increase
in BT
Length
increase
in BT
Length
Remark
Remark
Remark

9.012551
DETAILED COST ESTIMATEFOR SPEED BREAKER
New construction Format F-6
SSR Description of Item No.
Lengt
Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No. h
4.1
A(iii) Grainular subbase with well graded material (table 400.1):---- Construction of
granular sub-base by providing well graded material, spreading in uniform
layers with motor grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with vibratory wheel roller to achieve
the desired density, complete as per Technical Specification Clause 401.
(A)Having CBR value more than 20% ,
by mix in Place Method
(iii) For Grading - III Material
2 3.7 7.5 0.125 6.94
6.94 Cu.m 820.00 5688.75
4.8(2) WBM Grading 2:--Providing, laying, spreading and compacting Mechanically
crushed stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling
with three wheel 80-100 kN static roller in stages to proper grade and camber,
applying and brooming, crushable screening to fill-up the interstices of coarse
aggregate, watering and compacting to the required density Grading II as per
Technical Specification Clause 405.
2 3.7 7.5 0.075 4.163

4.163 Cu.m 1583.00 6589.24


4.7(3) WBM Grading 3:-Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam specification including
spreading in uniform thickness, hand packing, rolling with three wheel 80-100
kN static roller in stages to proper grade and camber, applying and brooming,
stone screening/binding material to fill-up the interstices of coarse aggregate,
watering and compacting to the required density Grading 3 as per Technical
Specification Clause 405. 2 3.7 7.5 0.075 4.163

4.163 Cu.m 1694.00 7051.28


5.1 Prime coat
Providing and applying primer coat with bitumen emulsion (SS-1)
on prepared surface of granular base including cleaning of road surface and
spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per
Technical Specification Clause 502
2 3.7 7.5 55.5
55.50 Sq.m 53.00 2941.50
SSR Description of Item No.
Lengt
Width Thicknes Qnty. Unit Rate(Rs) Amount
I.No. h
5.2(ii) Tack coat
(ii)Providing and applying tack coat with Bitumen emulsion
(RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the
prepared dry and hungry bituminous surface cleaned with Hydraulic broom as
per Technical Specification Clause 503.
2 3.7 7.5 55.5
55.50 Sq.m 18.00 999.00
5.3 (ii) 20 mm thick Open Graded Premix Carpet using Bituminious
( VG/modified bitumen) Binder
Providing, laying and rolling of open-graded premix carpet of 20 mm
thickness composed of 13.2 mm to 5.6 mm aggregates either using
penetration grade bitumen/VG bitumen or emulsion to required line, grade and
level to serve as wearing course on a previously prepared base, including
mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static
roller capacity, finished to required level and grades to be followed by seal coat
of either Type A or Type B or Type C as per Technical Specification Clause
508. Viscocity grade (VG) Bitumen specification as per IS73:2006

(ii)Bitumen(VG-30) 2 3.7 7.5 55.5


55.50 Sq.m 155.00 8602.50
5.5B Seal Coat
(ii) Providing
and laying Seal Coat sealing the voids in a bituminous surface laid to the
specified levels, grade and cross fall using Type B as per Technical
Specification Clause 510
Case II - Type B
(ii)Bitumen(VG-30)
2 3.7 7.5 55.5

55.50 Sq.m 56.00 3108.00


9.18 Road marking with Hot Applied Thermoplastic Compound with
Reflectorizing Glass Beads on Bituminous Surface (Providing and laying of hot
applied thermoplastic compound 2.5 mm thick including reflectorizing glass
beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface
applied glass beads as per IRC: 35. The finished surface to be level, uniform
and free from streaks and holes.)

In checkared pattern (0.5mx0.5m alternate) as per drawing 2 0.5 8 7.50 Sq.m 904.00 6780.00

Total Pavement Cost 41760.26

Consulta Sub. Engineer Asst. Engineer Executive Engineer


Anand Vibhor Rural Development Division,
CGRRDA , Mungeli
MUKHAYA MANTRI GRAM SADAK YOJANA
ABSTARCT - A ( For Earthwork ) Format F-6

Name of Road :- Kalmidih To Barampur Package No :-


District :- Mungeli BLOCK :- Lormi
Length :- 2.22 Km

Length of Cost Total cost


S.No. Item of work Road (Km)

1 Earthwork 2.220 0.00

Sub Total 0

Cost of road per Km is ( lakh) 0.00

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli
MUKHAYA MANTRI GRAM SADAK YOJANA
DETAILED COST ESTIMATE FOR EARTH WORK
Name of Road - Kalmidih To Barampur Format F-6
Length of Road:-2.22 Km Dist. :- Mungeli
Block :- Lormi
Sr. Item.N Description of Item
no No. Length Width Thicknes Qnty. Unit Rate(Rs) Amount
o.
1 2 3 4 5 6 7 8 9 10 11
(A) Flexible Pavement
1 2.3 Clearing and grubbing road land including uprooting wild vegetation, grass,
bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of
such trees cut earlier and disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, upto a lead of 1000 m including
removal and disposal of top organic soil not exceeding 150 mm in thickness as
per Technical Specification Clause 201.

(A) In area of non throny jungle


0 2010.000 3.00 0.00 sqm 3.00 0.00
2 2.2 Clearing Grass and Removal of Rubbish: Clearing grass and removal of
rubbish up to a distance of 30 m outside the periphery of the area as per
Technical Specification Clause 201.
0 2010.000 3.00 0.00 sqm 0.81 0.00
3 3.4(i) Construction of embankment with approved material obtained from borrow
pits, transporting to site, spreading, grading to required slope and compacting
using Vibratory Roller to meet requirement of Tables 300.1 and 300.2 with a lead
up to250 m as per Technical Specification Clause 301.5

0.00 cum 152.00 0.00

Total Pavement Cost 0.00

Consultant Sub. Engineer Asst. Engineer Executive Engineer #VALUE!


Anand Vibhor Rural Development Division,
CGRRDA , Mungeli

Pavement Estmate EW-NAREGA 47 426444861.xls


MUKHAYA MANTRI GRAM SADAK YOJANA
ABSTARCT - B Format F-6
Name of Road :- Kalmidih To Barampur Package No :-
District :- Mungeli BLOCK :- Lormi
c 2.22 Km
Length of Cost Total cost
S.No. Item of work Road (Km)
1 Flexiable pavement (BT
Road ) 2.220 8792909.83
Rigid pavement
2 (CC road ) 0.000 0
3 Protection Work 0
4 Field Crossing 581134
5 Road Furniture 714153
6 D.P.R Preparation for 0
Total Length of Road 2.220
Sub Total 10088198
7 C.D. work
Type of CD Rd Cost

Sub Total 0
Total Cost of road without maintenance Rs. 10088198
8 Road Maintenance for five year 310800
Total Cost of road with maintenance Rs. 10398998
Cost of road per Km is ( lakh) 46.84

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli

Superintending Engineer
Chhattisgarh Rural Road Development Agency
Project Circle Bilaspur (C.G.)
MUKHAYA MANTRI GRAM SADAK YOJANA
ABSTARCT - C ( Internal Gali CC Road )

Name of Road :- Kalmidih To Barampur Package No :-


District :- Mungeli BLOCK :- Lormi
Length :- 2.22 Km

Length of
S.No. Item of work Cost Total cost
Road (Km)
Internal Gali CC Road
1
with CC Drain

In Village :- Karhi Total


i) 0.000 0
Gali .

ii) Gali No. -1 0.000

iii) Gali No. - 2 0.000

iv) Gali No. - 3 0.000

Total Length of Gali


0.000 0
(Km)

Sub Total 0

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli
MUKHAYA MANTRI GRAM SADAK YOJANA
ABSTARCT - D

Name of Road :- Kalmidih To Barampur


District :- Mungeli BLOCK :- Lormi
Length :- 2.22 Km

S.No. Item of work No Cost Total cost

Yatri Pratikchhalay+
1 Toilet Block + Hand 435788 0
pump

Sub Total 0

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli
NAJARI NAKSHA FOR C.C. ROAD IN GALI
Name of Road :- Kalmidih To Barampur

Length
S.No. Gali No. Situation
(m)
In Village :- Karhi
1 1 from house of Bed Singh to School 0
Lamti Pahuch
2 2 from house of Harinandan to
Marg 0

3 3 from house of Jai Stambh to Shamsan Ghat 0

Total 0
NAJARI NAKSHA FOR C.C. ROAD IN GALI
Name of Road :- Kalmidih To Barampur

Gali 1

Kalewa Road
Rd-0 Pro. Road Rd-1300

Vilage Belgaon Vilage Jatkanhar


Gali 2
Ghumka
MUKHAYA MANTRI GRAM SADAK YOJANA

COST ESTIMATE FOR CEMENT CONCRETE ROAD CONSTRUCTION -


Format F-6
Name of Kalmidih To Barampur
District :- Mungeli
Road :-

S. Rate
SOR Description of Item No. L(m) B (m) D (m) Quantity Unit Amount (Rs.)
No. (Rs.)
1 3.5(i)
Excavation in cutting in soil with lead upto 50m:--Excavation for roadway in soil for
caryying of cut earth to embankment site with all lift and lead upto 50m as per technical
specification clause no. 302.3

In Village :- Karhi

Gali no. 1 1 0 3.00 0.35 0.00

Gali no. 2 1 0 3.00 0.35 0.00

Gali no. 3 1 0 3.00 0.35 0.00

For Field Crossing - 300 mm dia 7.5 0.50 0.65 0.00


0.0 Cum 76.00 0
2 4.1
Grainular subbase with well graded material (table 400.1):-- Construction of granular sub-
A(iii) base by providing well graded material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator at OMC, and compacting
with vibratory wheel roller to achieve the desired density, complete as per Technical
Specification Clause 401. (A)Having CBR value more than 20% , by
mix in Place Method (iii) For Grading - III
Material

In Village :- Karhi
Gali no. 1 1 0 3.00 0.15 0.00

Gali no. 2 1 0 3.00 0.15 0.00

Gali no. 3 1 0 3.00 0.15 0.00

0.00 cum 820.0 0


S. Rate
SOR Description of Item No. L(m) B (m) D (m) Quantity Unit Amount (Rs.)
No. (Rs.)
3 6.1 Cement Concrete Pavement
Construction of un-reinforced, dowel jointed at
expansion and construction joint only, plain cement concrete pavement, thickness as per
design, over a prepared sub base, with 43 grade cement or any other type as per Clause
1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of
coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum
capacity and appropriate weigh batcher using approved mix design, laid in approved fixed
side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges,
steel plates including eveling the formwork as per drawing), spreading the concrete with
shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous
operation including provision of contraction and expansion, construction joints, applying
debonding strips, primer, sealant, dowel bars, near approaches to bridge/culvert and
construction joints, admixtures as approved, curing of concrete slabs for 14-days, using curing
compound (where specified) and water finishing to lines and grade as per drawing and
Technical Specification Clause 1501.

In Village :- Karhi

Gali no. 1 1 0 3.00 0.20 0.00


Gali no. 2 1 0 3.00 0.20 0.00
Gali no. 3 1 0 3.00 0.20 0.00
0.00 Cu.m 5097 0
4 6.5 Construction of Plain Cement Concrete Drain with P.C.C. grade M-15 including all
shuttering/form work etc. complete as per drawings/technical specification and
direction of engineer in charge.
For CC Drain ( both side in Gali no 1 ) 750 0.60 0.15 0
For CC Drain ( both side in Gali no 1 ) 750 0.20 0.15 0
0.00 Cum 3811 0
4.12 Construction of hard shoulder as per technical specification clause 407:---
Construction of hard shoulder with selected granular material having CBR value not
less than 15 including all leads & lift, watering & compaction with smooth wheeled
roller to achieve the desired density as per technical specification clause 407 & 401.

Side of CC Road 2 0 0.6 0.2 0 Cum 358 0


S. Rate
SOR Description of Item No. L(m) B (m) D (m) Quantity Unit Amount (Rs.)
No. (Rs.)
7.3(ii) Bedding for Causeway / pipes
Type B (First Class)
Bedding 0 7.50 0.50 0.15 0.00 Cum 956.0 0
Laying (First Class) bedding on well compacted sand, moorum or
approved granular material as per Clause 1105 For Field Crossing
7.6 Providing and laying reinforced cement concrete pipe NP3 for culverts/Burried
conduits on first class bedding of granular material including fixing collar with
cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete 0 7.50 0.00 rmt 1129 0
and masonry works in head walls and parapets Clause 1106. (D) 300
mm dia pipe

Total Cost of CC Pavement 0

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli
MUKHAYA MANTRI GRAM SADAK YOJANA

COST ESTIMATE FOR CEMENT CONCRETE ROAD CONSTRUCTION -


Format F-6
Name of Kalmidih To Barampur
District :- Mungeli
Road :-

S. Rate
SOR Description of Item No. L(m) B (m) D (m) Quantity Unit Amount (Rs.)
No. (Rs.)
1 3.5(i) Excavation in cutting in soil with lead upto 50m:--Excavation for roadway in soil for
caryying of cut earth to embankment site with all lift and lead upto 50m as per technical
specification clause no. 302.3
0
Gali no. 1 1 0 3.75 0.35 0.00

Gali no. 2 1 0 3.75 0.35 0.00

Gali no. 3 1 0 3.75 0.35 0.00

Gali no. 4 1 0 3.75 0.35 0.00

Gali no. 5 1 0 3.30 0.35 0.00

Gali no. 6 1 0 3.00 0.35 0.00

Gali no. 7 1 0 3.75 0.35 0.00

Gali no. 8 1 0 3.75 0.35 0.00

Gali no. 9 1 0 3.25 0.35 0.00

Gali no. 10 1 0 3.30 0.35 0.00

Gali no. 11 1 0 3.00 0.35 0.00

Gali no. 12 1 0 2.75 0.35 0.00

Gali no. 13 1 0 3.75 0.35 0.00

Gali no. 14 1 0 3.75 0.35 0.00

Gali no. 15 1 0 3.75 0.35 0.00

For Field Crossing - 300 mm dia 7.5 0.50 0.65 0.00


S. Rate
SOR Description of Item No. L(m) B (m) D (m) Quantity Unit Amount (Rs.)
No. (Rs.)
0.0 Cum 76.00 0
2 4.1
Grainular subbase with well graded material (table 400.1):-- Construction of granular sub-
A(iii) base by providing well graded material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator at OMC, and compacting
with vibratory wheel roller to achieve the desired density, complete as per Technical
Specification Clause 401. (A)Having CBR value more than 20% , by
mix in Place Method (iii) For Grading - III
Material

Gali no. 1 1 0 3.75 0.15 0.00

Gali no. 2 1 0 3.75 0.15 0.00

Gali no. 3 1 0 3.75 0.15 0.00

Gali no. 4 1 0 3.75 0.15 0.00

Gali no. 5 1 0 3.30 0.15 0.00

Gali no. 6 1 0 3.00 0.15 0.00

Gali no. 7 1 0 3.75 0.15 0.00

Gali no. 8 1 0 3.75 0.15 0.00

Gali no. 9 1 0 3.25 0.15 0.00

Gali no. 10 1 0 3.30 0.15 0.00

Gali no. 11 1 0 3.00 0.15 0.00

Gali no. 12 1 0 2.75 0.15 0.00

Gali no. 13 1 0 3.75 0.15 0.00

Gali no. 14 1 0 3.75 0.15 0.00

Gali no. 15 1 0 3.75 0.15 0.00


S. Rate
SOR Description of Item No. L(m) B (m) D (m) Quantity Unit Amount (Rs.)
No. (Rs.)

0.00 cum 820.0 0


3 6.1 Cement Concrete Pavement
Construction of un-reinforced, dowel jointed at
expansion and construction joint only, plain cement concrete pavement, thickness as per
design, over a prepared sub base, with 43 grade cement or any other type as per Clause
1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of
coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum
capacity and appropriate weigh batcher using approved mix design, laid in approved fixed
side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges,
steel plates including eveling the formwork as per drawing), spreading the concrete with
shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous
operation including provision of contraction and expansion, construction joints, applying
debonding strips, primer, sealant, dowel bars, near approaches to bridge/culvert and
construction joints, admixtures as approved, curing of concrete slabs for 14-days, using curing
compound (where specified) and water finishing to lines and grade as per drawing and
Technical Specification Clause 1501.

Gali no. 1 1 0 3.75 0.20 0.00


Gali no. 2 1 0 3.75 0.20 0.00
Gali no. 3 1 0 3.75 0.20 0.00
Gali no. 4 1 0 3.75 0.20 0.00
Gali no. 5 1 0 3.30 0.20 0.00

Gali no. 6 1 0 3.00 0.20 0.00

Gali no. 7 1 0 3.75 0.20 0.00

Gali no. 8 1 0 3.75 0.20 0.00

Gali no. 9 1 0 3.25 0.20 0.00

Gali no. 10 1 0 3.30 0.20 0.00

Gali no. 11 1 0 3.00 0.20 0.00

Gali no. 12 1 0 2.75 0.20 0.00

Gali no. 13 1 0 3.75 0.20 0.00


S. Rate
SOR Description of Item No. L(m) B (m) D (m) Quantity Unit Amount (Rs.)
No. (Rs.)

Gali no. 14 1 0 3.75 0.20 0.00

Gali no. 15 1 0 3.75 0.20 0.00

0.00 Cu.m 5097 0


4 6.5 Construction of Plain Cement Concrete Drain with P.C.C. grade M-15 including all
shuttering/form work etc. complete as per drawings/technical specification and
direction of engineer in charge.
For CC Drain ( both side in Gali no 1 to 9 & 13 to 15 ) 2 0.60 0.15 0
For CC Drain ( both side in Gali no 1 to 9 & 13 to 15 ) 4 0.20 0.15 0
For CC Drain ( one side in Gali no 10 to12) 1 0.60 0.15 0
For CC Drain ( one side in Gali no 10 to12) 2 0.20 0.15 0
0.00 Cum 3811 0
4.13 Construction of hard shoulder as per technical specification clause 407:---
Construction of hard shoulder with selected granular material having CBR value not
less than 15 including all leads & lift, watering & compaction with smooth wheeled
roller to achieve the desired density as per technical specification clause 407 & 401.

Side of CC Road 2 0.9 0.2 0 Cum 358 0


7.3(ii) Bedding for Causeway / pipes
Type B (First Class)
Bedding 0 7.50 0.50 0.15 0.00 Cum 956.0 0
Laying (First Class) bedding on well compacted sand, moorum or
approved granular material as per Clause 1105 For Field Crossing
7.6 Providing and laying reinforced cement concrete pipe NP3 for culverts/Burried
conduits on first class bedding of granular material including fixing collar with
cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete 0 7.50 0.00 rmt 1129 0
and masonry works in head walls and parapets Clause 1106. (D) 300
mm dia pipe

Total Cost of CC Pavement 0

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
S. Rate
SOR Description of Item No. L(m) B (m) D (m) Quantity Unit Amount (Rs.)
No. (Rs.)
CGRRDA , Mungeli
Detailed Estimate for Maintenance of Road (For 5 Years)
Format F-6

Name of Road :- Kalmidih To Barampur District :- Mungeli

BLOCK :- Lormi

Sr.No. Description Length Unit Rate Amount

1 Maintenance of Road for Ist Year after Construction 2.220 Km 30000 66600

2 Maintenance of Road for IInd Year after Construction 2.220 Km 40000 88800

3 Maintenance of Road for IIIrd Year after Construction 2.220 Km 70000 155400

4 Maintenance of Road for IVth Year after Construction Km

5 Maintenance of Road for Vth Year after Construction Km

Total Rs. 310800

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli
MUKHYA MANTRI GRAM SADAK YOJANA
COST ESTIMATE FOR 600MM DIA. HUME PIPE CULVERT ( ONE ROW )

CSR
Sr. I.M. Length Width Thickness
no Page Description of Item No.
(m) (m) (m)
Qnty. Unit Rate(Rs)
SOR no
Item
1 2 3 4 5 6 7 8 9 10
No.
1 7.1(I)
Excavation for structuresas per drawing and technical specifications
Clause 305.1 including seting out, construction of shoring and bracing,
removal of stumps and othar deletercus material and dis posal upto a
lead of 50m dressing of sides and bottom and backfilling in trenches
with excavated suitable material .Oridanary soil (i) upto 3 m depth

Head Wall 4.3 1.3 1 0.00 Cum


Pipe portion 7.44 1.1 0.8 0.00 Cum
0.00 Cum 161.00
2 7.10 Providing concrete for plain/reinforced concrete in open foundation
(ii) complete as per drawings and technical specifications Clause 802, 803,
1202 & 1203

Head Wall
4.30 1.30 0.2 0.00
Total
0.00 Cum 3899.00
Plain/reinforced cement concrete in substructure complete as per
3 7.18 (I)
drawings and technical specification Clauses 802, 804, 805, 806, 807,
1202 ans 1204
For height upto 5 m

(I)P.C.C grade M 15 (Nominal mix (1:2.5:5)


M -15 Head Wall Av. W = ( 0.40+1.10 )/2 = 0.75 4.00 0.750 2.00 0.00

4.00 0.400 0.50 0.00


Deduct Pipe Portion 0.76 0.50 0.00
0.00 Cum 4031.00
5 7.6(A) Providing and laying reinforced cement concrete pipe NP3 for
Culverts/ Burried conduits on first class bedding of granular material
including fixing collar with cement mortar 1:2 but excluding excavation,
protection works, backfilling, concrete and masonry works in head walls
and parapets as per Clause 1106 (A)
600 mm dia

10 0.00 Rmt 2928.00


CSR
Sr. I.M. Length Width Thickness
no Page Description of Item No.
(m) (m) (m)
Qnty. Unit Rate(Rs)
SOR no
Item
1 2 3 4 5 6 7 8 9 10
No.
7 7.3(ii) Bedding for Causeway / pipes

Type B (First Class)


Bedding
7.44 1.00 0.25 0.00
Laying
(First Class) bedding on well compacted sand, moorum or 0.00 Cum 956.00
8 Backfillinggranular
7.23(I) approved behind abutment,
material aswing
per wall and1105
Clause returnFor
wall complete as
Field
per drawings & technical specification Clause 1204.3.8
Crossing
(I) Granular 4.30 0.15 0.68 0.00 Cum
material 4.30 0.38 0.68 0.00 Cum
0.00 Cum 654.00
Total

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Anand Vibhor Rural Development Division,
CGRRDA , Mungeli
NTRI GRAM SADAK YOJANA
00MM DIA. HUME PIPE CULVERT ( ONE ROW )
Format F-6

Amount( Rs/- )

11

0.00

0.00

0.00

0.00
Amount( Rs/- )

11

0.00

0.00
0.00

Executive Engineer
Rural Development Division,
CGRRDA , Mungeli
PRADHAN MANTRI GRAM SADAK YOJANA
COST ESTIMATE FOR 1x1000MM DIA. HUME PIPE CULVERT ( ONE ROW )
Road Name:Kalmidih To Barampur Format F-7
Location ( R.D ):- 1800
Sr. SOR Length Width Thickness Amount
no I.No. Description of Item No.
(m) (m) (m)
Qnty. Unit Rate(Rs)
( Rs/- )
1 2 3 4 5 6 7 8 9 10 11
1 7.1(I) Excavation for structuresas per drawing and technical specifications Clause
305.1 including seting out, construction of shoring and bracing, removal of
stumps and othar deletercus material and dis posal upto a lead of 50m
dressing of sides and bottom and backfilling in trenches with excavated
suitable material .Oridanary soil (i) upto 3 m depth

Head Wall 2 6.45 1.85 1 23.87 Cum


Pipe portion 1 4.1 1.55 0.25 1.59 Cum
25.45 Cum 161 4098
2 7.10 Providing concrete for plain/reinforced concrete in open foundation
(ii) complete as per drawings and technical specifications Clause 802, 803,
1202 & 1203
Head Wall - Foundation 2 6.45 1.70 0.15 3.29
Head Wall - Upto NBL
2 6.15 1.33 1.4 22.90
- Avg Width ( 1.10+1.56)/2=1.33
Total 26.19 Cum 3899 102123
3 7.18 (I) Plain/reinforced cement concrete in substructure complete as per
drawings and technical specification Clauses 802, 804, 805, 806, 807,
1202 ans 1204
For height upto 5 m

(I)P.C.C grade M 15 (Nominal mix (1:2.5:5)


Head Wall - From NBL to Top
2 6.15 0.70 2.10 18.08
Av. Width = ( 0.40+1.10 )/2 = 0.70
Deduct Pipe Portion -2 1.18 0.90 -2.11
End Piller 2 0.40 0.40 0.60 0.19
16.16 Cum 4031 65144
Sr. SOR Length Width Thickness Amount
no I.No. Description of Item No.
(m) (m) (m)
Qnty. Unit Rate(Rs)
( Rs/- )
1 2 3 4 5 6 7 8 9 10 11
4 7.4(B) Laying Reinforced Cement Concrete Pipe NP3 as per drawing and
technical specification Clause 1402.6
Providing and laying reinforced cement concrete pipe NP3
for culverts on first class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but excluding excavation,
protection works, backfilling, concrete and masonry works in head walls
and parapets Clause 1106.

(B)1000 mm dia 1 7.5 7.50 Rmt 5177 38828


5 7.22
Providing weepholes in brick masonry/stone masonry, plain/ reinforced
concrete abutment, wing wall, return wall with 100 mm dia AC pipe
extending through the full width of the structures with slope of
1(V):20(H) towards drawing face complete as per drawing and
technical specification Clauses 614, 709, 1204.3.7
Bedding for Causeway / pipes 4 4.00 Nos 276 1104
6 7.3(ii)
Type B (First Class) Bedding 1 5.27 1.55 0.25 2.04

Laying (First Class) bedding on well 2.04 Cum 956 1952


compacted sand, moorum or approved granular material as per Clause
7 7.23(I) 1105 2 6.45 0.15 0.50 0.97 Cum
Backfilling behind abutment, wing wall and return wall complete as per 2 6.45 0.38 0.50 2.42 Cum
drawings & technical specification Clause 1204.3.8
(I) Granular material 1 6.15 6.27 0.30 11.57 Cum
14.95 Cum 654 9780
8 10.5(I) Providing and laying pitching on slopes laid over prepared filter media
as per drawing and technical specifications Clause 1302
(I)Stone/Boulder 4 1.50 1.50 0.23 9.00 Cum 1430 12870
11 10.6 Providing and laying Filter Material underneath pitcing in slopes
complete as per drewing specifications Clause 1302 2.30 2.00 0.10 0.00 Cum 1657.00 0.00

Total Total for one 1000mm dia. One row CD work is Rs /- 235899

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Anand Vibhor Rural Development Division,
CGRRDA ,Mungeli
PRADHAN MANTRI GRAM SADAK YOJNA (PMGSY)
DETAIL ESTIMATE FOR 1 X 1.00M SPAN SLAB CULVERT Format F-7
Name of Road:-Kalmidih To Barampur RD:- 0
SOR
Height/
S.No. Item Description of Item No. Length Width Quantity Unit Rate Amount
Depth
No.
1 7.1(I)
Excavation for structuresas per drawing and technical specifications Clause 305.1
including seting out, construction of shoring and bracing, removal of stumps and othar
deletercus material and dis posal upto a lead of 50m dressing of sides and bottom and
backfilling in trenches with excavated suitable material .Oridanary soil (i) upto 3 m
depth
Abutments 2 7.7 1.40 0.60 12.94 cum

Total 12.936 cum 161 2083


2 7.10 Providing concrete for plain/reinforced concrete in open foundation complete as per
(ii) drawings and technical specifications Clause 802, 803, 1202 & 1203 (II)P.C.C grade M
15(Nominal mix (1:2.5:5)

Abutments- Foundation PCC


2 7.7 1.40 0.20 4.31

Abutments-Bottom Block ( From foundation to NBL)


2 7.70 (1.20+0.70)/2 1.50 21.95

26.26 cum 3899 102376


4 7.27(II) Providing and laying cement for rainforced cement conctete in super structure including
centering & form awork complete as per drawing and specifications. (II)R.C.C. M 25
( Dssign Mix)
Abutment cap 2 7.50 0.70 0.20 2.10
Dirt Wall 2 7.50 0.40 0.20 1.20
For Slab
1 1.60 7.50 0.20 2.40

5.700 cum 5412 30848


5 7.28 Providing laying and placing in position HYSD rainforcement in super structure complete
as per drawing and specification.

For Cap beam & dirt wall 163.60


for slab

Main bar - 12 mm dia@120 mm c/c 1 63 2.09 0.89 117.19

Distribution bar -8 mm dia@160 mm c/c 1 14 7.42 0.395 41.03

Top - Longitudinal bar - 10 mm dia@300 mm c/c 1 8 7.42 0.617 36.63

1.0 m Slab Page 68


SOR
Height/
S.No. Item Description of Item No. Length Width Quantity Unit Rate Amount
Depth
No.

Top - Transerves bar - 10 mm dia@300 mm c/c 1 25 2.02 0.617 31.16

For chair - 12mm dia 1 12 0.94 0.89 10.04

Total 399.64 kg

0.400 MT. 59801 23899

GRAND TOTAL 159206

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Anand Vibhor Rural Development Division,
CGRRDA , Mungeli

1.0 m Slab Page 69


MUKHYA MANTRI GRAM SADAK YOJNA (PMGSY)

DETAIL ESTIMATE FOR 1 X 1.50M SPAN SLAB CULVERT Format F-7


Name of Road:- Kalmidih To Barampur RD:- 1190
Sr. SOR
ITEM DESCRIPTION No. L B H Qty. UNIT RATE AMOUNT
NO No.
1 7.1(I) Excavation for structuresas per drawing and technical specifications Clause 305.1
including seting out, construction of shoring and bracing, removal of stumps and
othar deletercus material and dis posal upto a lead of 50m dressing of sides and
bottom and backfilling in trenches with excavated suitable material .Oridanary soil (i)
upto 3 m depth ###
Abutments 2 8.7 2.00 1.40 48.720 ###
Wingwalls 4 1.80 1.80 1.40 18.144 ###
66.864 Cum 161 10,765
2 7.10 Providing concrete for plain/reinforced concrete in open foundation complete as per
(ii) drawings and technical specifications Clause 802, 803, 1202 & 1203 (II)P.C.C grade
M 15(Nominal mix (1:2.5:5) ###
Abutments- Foundation PCC 2 8.7 2.00 0.20 6.960 ###
Abutments-Bottom Block ( From foundation to NBL) (7.7+8.5)/ (1.40+1.80)/
2 1.20 31.104
2 2
Wingwalls - Foundation PCC 4 1.8 1.8 0.20 2.592 ###
Wingwalls -Bottom Block ( From foundation to NBL) (1.20+1.60)/
4 1.70 1.20 11.424
2
52.080 Cum 3,899 203,060
3 7.18 (I) Plain/reinforced cement concrete in substructure complete as per drawings and
technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204
For height upto 5 m

(I)P.C.C grade M 15 (Nominal mix (1:2.5:5) ###


Abutments ###
Top Block ( From NBL to Abutment cap ) (0.70+1.20)/
2 7.50 1.50 21.375
2
Wingwalls
Top Block ( From NBL to Wing wall cap ) (1.8+2.3)/ (0.40+1.00)/
4 1.76 10.102
2 2
Wing wall cap 4 2.30 0.40 0.150 0.552
For Kerb 2 7.50 0.40 0.375 2.250
Wheel guard 2 0.40 0.40 0.60 0.192

1.50m Slab Page 70


Sr. SOR
ITEM DESCRIPTION No. L B H Qty. UNIT RATE AMOUNT
NO No.
34.471 Cum 4,031 138,954
4 7.27 Providing and laying reinforced cement concrete in superstructure as per drawing and
(II) technical specificationsClause 800, 1205.4 and 1205.5

(II)R.C.C. M 25 ( Dssign Mix)


Abutment cap 2 7.50 0.70 0.20 2.100
Dirt Wall 2 7.50 0.40 0.21 1.260
For Slab 1 2.10 7.50 0.21 3.308
6.668 Cum 5,412 36,085
5 7.28
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as 0.40 MT 59,801 23,791
per drawing and technical specifications Clauses 1002, 1010 and 1202
For Cap beam & dirt wall 161.80
for slab

Main bar - 12 mm dia@120 mm c/c 1 63 2.09 0.89 117.19

Distribution bar -8 mm dia@160 mm c/c 1 14 7.42 0.395 41.03

Top - Longitudinal bar - 10 mm dia@300 mm c/c 1 8 7.42 0.617 36.63

Top - Transerves bar - 10 mm dia@300 mm c/c 1 25 2.02 0.617 31.16

For chair - 12mm dia 1 12 0.94 0.89 10.04


236.04 Kg
6 7.22 Providing weepholes in brick masonry/stone masonry, plain/ reinforced concrete
abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full
10 10.00 No 276 2,760
width of the structures with slope of 1(V):20(H) towards drawing face complete as per
drawing and technical specification Clauses 614, 709, 1204.3.7
7 7.41(II) Providing and fixing 20 mm thick compressible fibre board in expansion joint complete
2 7.50 15.00 m 342 5,130
as per drawing and technical specifications
9 7.23 Backfilling behind abutment, wing wall and return wall complete as per drawings &
(I) technical specification Clause 1204.3.8
(I) Granular material
Abutment - Upto NBL (7.7+8.5)/
2 (0.1+0.50)/2 1.20 5.83
2
(7.7+8.5)/
2 0.10 1.20 1.94
2
Wing wall
4 1.70 (0.1+0.50)/2 1.20 2.45

1.50m Slab Page 71


Sr. SOR
ITEM DESCRIPTION No. L B H Qty. UNIT RATE AMOUNT
NO No.
4 1.70 0.10 1.20 0.82
Top Block - Behind abutment & wing wall (4.0+5.2)/
2 (1.8+2.30)/2 1.50 28.29
2
39.33 Cum 654 25,722
10 10.5
(I) Providing and laying pitching on slopes laid over prepared filter media as per drawing
4 1.50 1.50 0.23 2.07 Cum 1,430 2,960
and technical specifications Clause 1302 (I)Stone/Boulder

11 10.6 Providing and laying Filter Material underneath pitcing in slopes complete as per
drewing specifications Clause 1302 4 1.50 1.50 0.10 0.90 Cum 1,657 1,491

TOTAL Rs. 450,718

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Anand Vibhor Rural Development Division,
CGRRDA , Mungeli

1.50m Slab Page 72


MUKHYA MANTRI GRAM SADAK YOJNA (PMGSY)

DETAIL ESTIMATE FOR 1 X 2.00M SPAN SLAB CULVERT Format F-7


Name of Road:- Kalmidih To Barampur RD:- 0
Sr. SOR
ITEM DESCRIPTION No. L B H Qty. UNIT RATE AMOUNT
NO No.
1 7.1(I) Excavation for structuresas per drawing and technical specifications Clause 305.1
including seting out, construction of shoring and bracing, removal of stumps and
othar deletercus material and dis posal upto a lead of 50m dressing of sides and
bottom and backfilling in trenches with excavated suitable material .Oridanary soil (i)
upto 3 m depth
###
Abutments 2 8.7 2.00 1.40 48.72 ###
Wingwalls 4 1.80 1.80 1.40 18.14 ###

66.86 Cum 161 10,765


2 7.10 Providing concrete for plain/reinforced concrete in open foundation complete as per
(ii) drawings and technical specifications Clause 802, 803, 1202 & 1203 (II)P.C.C grade
M 15(Nominal mix (1:2.5:5) ###
Abutments- Foundation PCC
2 8.7 2.00 0.20 6.96
###
Abutments-Bottom Block ( From foundation to NBL) (7.7+8.5)/ (1.40+1.80)/
2 1.20 31.10
2 2
Wingwalls - Foundation PCC
4 1.8 1.8 0.20 2.59
###
Wingwalls -Bottom Block ( From foundation to NBL) (1.20+1.60)/
4 1.70 1.20 11.42
2

52.08 Cum 3,899 203,060

3 7.18 (I) Plain/reinforced cement concrete in substructure complete as per drawings and
technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204
For height upto 5 m

(I)P.C.C grade M 15 (Nominal mix (1:2.5:5) ###


Abutments ###
Top Block ( From NBL to Abutment cap )
(0.70+1.20)/
2 7.50 1.50 21.38
2

Wingwalls

2.00m Slab) Page 73


Sr. SOR
ITEM DESCRIPTION No. L B H Qty. UNIT RATE AMOUNT
NO No.
Top Block ( From NBL to Wing wall cap ) (1.8+2.3)/ (0.40+1.00)/
4 1.79 10.27
2 2
Wing wall cap 4 2.30 0.40 0.150 0.55
For Kerb 2 8.00 0.40 0.375 2.40
Wheel guard 2 0.40 0.40 0.60 0.19

34.79 Cum 4,031 140,253


4 7.27 Providing and laying reinforced cement concrete in superstructure as per drawing and
(II) technical specificationsClause 800, 1205.4 and 1205.5

(II)R.C.C. M 25 ( Dssign Mix)


Abutment cap 2 7.50 0.70 0.20 2.10
Dirt Wall 2 7.50 0.40 0.24 1.44
For Slab 1 2.60 7.50 0.24 4.68

8.22 Cum 5,447 44,774


5 7.28

Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as 0.50 MT 60,343 30,273
per drawing and technical specifications Clauses 1002, 1010 and 1202

For Cap beam & dirt wall 161.80

for slab

Main bar - 12 mm dia@85 mm c/c 1 89 2.60 0.89 205.95

Distribution bar -10 mm dia@250 mm c/c 1 11 7.42 0.617 50.36

Top - Longitudinal bar - 10 mm dia@300 mm c/c 1 9 7.42 0.617 41.20

Top - Transerves bar - 10 mm dia@300 mm c/c 1 25 2.02 0.617 31.16

For chair - 12mm dia 1 12 1.05 0.89 11.21


501.68 Kg

2.00m Slab) Page 74


Sr. SOR
ITEM DESCRIPTION No. L B H Qty. UNIT RATE AMOUNT
NO No.
6 7.22
Providing weepholes in brick masonry/stone masonry, plain/ reinforced concrete
abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full
10 10.00 No 276 2,760
width of the structures with slope of 1(V):20(H) towards drawing face complete as per
drawing and technical specification Clauses 614, 709, 1204.3.7

7 7.41(II) Providing and fixing 20 mm thick compressible fibre board in expansion joint complete
2 7.50 15.00 m 310 4,650
as per drawing and technical specifications
8 7.35
Drainage spouts complete as per drawing and technical specifications Clause 1209 2 2.00 4.00 No. 1,509 6,036

9 7.23 Backfilling behind abutment, wing wall and return wall complete as per drawings &
(I) technical specification Clause 1204.3.8
(I) Granular material
Abutment - Upto NBL (7.7+8.5)/
2 (0.1+0.50)/2 1.20 5.83
2

(7.7+8.5)/
2 0.10 1.20 1.94
2
Wing wall
4 1.70 (0.1+0.50)/2 1.20 2.45

4 1.70 0.10 1.20 0.82

Top Block - Behind abutment & wing wall (4.0+5.2)/


2 (1.8+2.30)/2 1.50 28.29
2
39.33 Cum 654 25,722
10 10.5
(I) Providing and laying pitching on slopes laid over prepared filter media as per drawing
4 1.50 1.50 0.23 2.07 Cum 1,430 2,960
and technical specifications Clause 1302 (I)Stone/Boulder

11 10.6 Providing and laying Filter Material underneath pitcing in slopes complete as per
drewing specifications Clause 1302 4 1.50 1.50 0.10 0.90 Cum 1,548 1,393

TOTAL Rs. 472,646

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Anand Vibhor Rural Development Division,
CGRRDA , Bilaspur

2.00m Slab) Page 75


PRADHAN MANTRI GRAM SADAK YOJNA (PMGSY)
DETAIL ESTIMATE FOR 1 X 3.00M SPAN SLAB CULVERT
Name of Road:- Kalmidih To Barampur RD:- 0
Sr. SOR Total UNI
ITEM DESCRIPTION No. L B H RATE
NO No. Qty. T

1 7.1(I) Excavation for structuresas per drawing and technical specifications Clause
305.1 including seting out, construction of shoring and bracing, removal of
stumps and othar deletercus material and dis posal upto a lead of 50m
dressing of sides and bottom and backfilling in trenches with excavated
suitable material .Oridanary soil (i) upto 3 m depth

A i) Upto 3m depth below av. GL


I Ordanary Soil
Abutments 2 8.7 2.10 1.00 36.54
Wingwalls 4 1.85 1.70 1.00 12.58
49.12 Cum 161
2 II Ordanary Rock ( Not Requiring Blasting)
Abutments 2 8.7 2.10 0.20 7.31 Cum
Wingwalls 4 1.85 1.70 0.20 2.52 Cum
9.82 Cum 192
3 7.10 Providing concrete for plain/reinforced concrete in open foundation
(ii) complete as per drawings and technical specifications Clause 802, 803,
1202 & 1203 (II)P.C.C grade M 15(Nominal mix (1:2.5:5)

Abutments- Foundation PCC 2 8.7 2.10 0.20 7.31


Abutments-Bottom Block ( From foundation to NBL) 2 (7.7+8.50)/2 (1.50+1.90)/2 1.20 33.05
Wingwalls - Foundation PCC 4 1.85 1.70 0.20 2.52
Wingwalls -Bottom Block ( From foundation to NBL) 4 1.60 (1.25+1.65)/2 1.20 11.14

54.01 Cum 3899

1x3.0 m span Slab culvert Page 76


Sr. SOR Total UNI
ITEM DESCRIPTION No. L B H RATE
NO No. Qty. T
4 7.18 (I) Plain/reinforced cement concrete in substructure complete as per drawings
and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204
For height upto 5 m
(I)P.C.C
grade M 15 (Nominal mix (1:2.5:5)
Abutments
Top Block ( From NBL to Abutment cap ) 2 7.50 (0.70+1.30)/2 1.80 27.00
Wingwalls
Top Block ( From NBL to Wing wall cap ) 4 (1.7+2.3)/2 (0.40+1.15)/2 2.15 13.33
Wing wall cap 4 2.30 0.40 0.150 0.55
For Kerb 2 9.00 0.40 0.375 2.70
Wheel guard 2 0.40 0.40 0.60 0.19
43.77 Cum 4031
5 7.27 Providing and laying reinforced cement concrete in superstructure as per drawing
(II) and technical specificationsClause 800, 1205.4 and 1205.5

R.C.C. M 25 ( Dssign Mix)


Abutment cap 2 7.50 0.70 0.20 2.10
Dirt Wall 2 7.50 0.40 0.30 1.80
For Slab 1 3.60 7.50 0.30 8.10
8.10 Cum 5412
6 7.28 Providing laying and placing in position HYSD rainforcement in super 0.75 MT 59801
structure complete as per drawing and specification.
For Cap beam & dirt wall 167.21

for slab
Main bar - 16 mm dia@125 mm c/c 1 60 3.63 1.58 343.84

Distribution bar -10 mm dia@175 mm c/c 1 21 7.42 0.617 96.14

Top - Longitudinal bar - 10 mm dia@300 mm c/c 1 13 7.42 0.617 59.52

1x3.0 m span Slab culvert Page 77


Sr. SOR Total UNI
ITEM DESCRIPTION No. L B H RATE
NO No. Qty. T
Top - Transerves bar - 10 mm dia@300 mm c/c 1 25 3.52 0.617 54.30

For chair - 16mm dia 1 14 1.27 1.58 28.09

Total 749 kg
7 7.22 Providing weepholes in brick masonry/stone masonry, plain/ reinforced
concrete abutment, wing wall, return wall with 100 mm dia AC pipe
extending through the full width of the structures with slope of 1(V):20(H) 10 10.00 No 276
towards drawing face complete as per drawing and technical specification
Clauses 614, 709, 1204.3.7
8 7.41(II) Providing and fixing 20 mm thick compressible fibre board in expansion joint
2 7.50 15.00 M 342
complete as per drawing and technical specifications
9 7.35 Drainage spouts complete as per drawing and technical specifications
2 2.00 4.00 No. 1632
Clause 1209
10 7.23(I) Backfilling behind abutment, wing wall and return wall complete as per
drawings & technical specification Clause 1204.3.8
(I) Granular material
Abutment - Upto NBL 2 (7.7+8.50)/2 (0.1+0.50)/2 1.20 5.83
2 (7.7+8.50)/2 0.10 1.20 1.94
Wing wall 4 1.60 (0.1+0.50)/2 1.20 2.30
4 1.70 0.10 1.20 0.82
Top Block - Behind abutment & wing wall 2 (3.7+5.2)/2 (1.7+2.30)/2 1.80 32.04
42.94 Cum 654
11 10.5(I) Providing and laying pitching on slopes laid over prepared filter media as
per drawing and technical specifications Clause 1302 4 2.00 2.50 0.23 4.60 Cum 1430
(I)Stone/Boulder
12 10.6 Providing and laying Filter Material underneath pitcing in slopes
complete as per drewing specifications Clause 1302 4 2.00 2.50 0.10 2.00 Cum 1657

TOTAL Rs.

1x3.0 m span Slab culvert Page 78


Sr. SOR Total UNI
ITEM DESCRIPTION No. L B H RATE
NO No. Qty. T

Consultant Sub. Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli

1x3.0 m span Slab culvert Page 79


TRI GRAM SADAK YOJNA (PMGSY)
Format F-7

AMOUNT

7908

1886

210577

1x3.0 m span Slab culvert Page 80


AMOUNT

176453

43837

44797

1x3.0 m span Slab culvert Page 81


AMOUNT

2760

5130

6528

28080

6578

3314

537849

1x3.0 m span Slab culvert Page 82


PRADHAN MANTRI GRAM SADAK YOJNA (PMGSY)
DETAIL ESTIMATE FOR 1 X 5.00M SPAN SLAB CULVERT Format F-7
Name of Road:- Kalmidih To Barampur RD:- 0
Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.
1 7.1(I) Excavation for structuresas per drawing and technical specifications
Clause 305.1 including seting out, construction of shoring and bracing,
removal of stumps and othar deletercus material and dis posal upto a lead
of 50m dressing of sides and bottom and backfilling in trenches with
excavated suitable material .Oridanary soil
(i) upto 3 m depth

I Ordanary Soil
Abutments 2 8.7 2.20 1.10 42.11
Returns 4 2.60 2.05 1.10 23.45
65.56 Cum 153 10031
2 II Ordanary Rock ( Not Requiring Blasting)
Abutments 2 8.7 2.20 0.20 7.66 Cum
Returns 4 2.60 2.05 0.20 4.26 Cum
11.92 Cum 192 2289
3 7.10 Providing concrete for plain/reinforced concrete in open foundation
(ii) complete as per drawings and technical specifications Clause 802, 803,
1202 & 1203 (II)P.C.C grade M 15(Nominal mix (1:2.5:5)
PCC Grade M-15
Abutments- Foundation PCC 2 8.7 2.20 0.20 7.66
Abutments-Bottom Block ( From foundation to NBL) 2 (7.7+8.5)/2 (1.60+2.00)/2 1.20 34.99
Wingwalls - Foundation PCC 4 2.60 2.05 0.20 4.26
Wingwalls -Bottom Block ( From foundation to NBL) 4 2.50 (1.45+1.85)/2 1.20 19.80
66.71 Cum 3647 243299
4 7.18 (I) Plain/reinforced cement concrete in substructure complete as per drawings
and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans
1204 For height
upto 5 m
(I)P.C.C grade M
15 (Nominal mix (1:2.5:5)
PCC Grade M-15
Abutments
Top Block ( From NBL to Abutment cap ) 2 7.50 (0.70+1.40)/2 2.00 31.50
Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.
Wingwalls

Top Block ( From NBL to Wing wall cap ) 4 (2.6+3.3)/2 (0.40+1.25)/2 2.48 24.14
Wing wall cap 4 3.30 0.40 0.150 0.79
For Kerb 2 11.00 0.40 0.375 3.30
Wheel guard 2 0.40 0.40 0.60 0.19

59.93 Cum 3857 231138


5 7.27(II Providing and laying reinforced cement concrete in superstructure as per
) drawing and technical specificationsClause 800, 1205.4 and 1205.5
(II)R.C.C. M 25 ( Dssign Mix)

Abutment cap 2 7.50 0.70 0.20 2.10


Dirt Wall 2 7.50 0.30 0.43 1.94
For Slab 1 5.80 7.50 0.43 18.71
20.64 Cum 5447 112426
0
6 7.28
Supplying, fitting and placing HYSD bar reinforcement in superstructure
complet as per drawing and technical specifications Clause 1002, 1010 1.96 MT 59801 117369
and 1202.

For Cap beam & dirt wall 172.01

for slab

Main bar - 20 mm dia@140 mm c/c 1 54 5.81 2.47 775.20

Distribution bar -12 mm dia@175 mm c/c 1 21 7.42 0.890 138.68

Top - Longitudinal bar - 10 mm dia@300 mm c/c 1 20 7.42 0.617 91.56

Top - Transerves bar - 10 mm dia@300 mm c/c 1 25 5.72 0.617 88.23

For chair - 20mm dia 1 12 1.49 2.47 44.16

Surface Reinforcement for - Abutment & wing wall @ 5kg/sqm 2 20.40 3.20 5.00 652.80

1962.65 Kg
Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.
7 7.22
Providing weepholes in brick masonry/stone masonry, plain/ reinforced
concrete abutment, wing wall, return wall with 100 mm dia AC pipe
extending through the full width of the structures with slope of 1(V):20(H) 12 12.00 No 276 3312
towards drawing face complete as per drawing and technical specification
Clauses 614, 709, 1204.3.7

8 7.24 Providing and laying filter media with granular crushed aggregates as per
specification to a thickness of not less than 600 mm with smaller size
towards the soil and bigger size towards the wall and providing over the
entire surface behind abutment, wing wall, return wall to the full height,
compacted to firm condition complete as per drawing and technical
specification Clause 1204.3.8
Behind Abutments 6.50 0.30 3.00 0.00
Behind Returns 3.35 0.30 1.50 0.00
0.00 Cum 1291 0
8 7.35
Drainage spouts complete as per drawing and technical specifications
2 2.00 4.00 No. 1632 6528
Clause 1209

9 7.23 (I) Backfilling behind abutment, wing wall and return wall complete as per
drawings & technical specification Clause 1204.3.8
(I) Granular material
Abutment - Upto NBL 2 (7.7+8.5)/2 (0.1+0.50)/2 1.20 5.83

2 (7.7+8.5)/2 0.10 1.20 1.94


Wing wall 4 2.60 (0.1+0.50)/2 1.20 3.74

4 2.70 0.10 1.20 1.30


Top Block - Behind abutment & wing wall 2 (3.5+5.2)/2 (2.7+3.30)/2 2.00 52.20

65.02 Cum 654 42520


10 7.41(II Providing and fixing 20 mm thick compressible fibre board in expansion
) 2 7.50 15.00 m 342 5130
joint complete as per drawing and technical specifications
11 10.5 Providing and laying pitching on slopes laid over prepared filter media as
per drawing and technical specifications Clause 1302 4 3.00 2.00 0.23 5.52 Cum 1430 7894
(I) (I)Stone/Boulder
Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.
12 10.6 Providing and laying Filter Material underneath pitcing in slopes
complete as per drewing specifications Clause 1302 4 3.00 2.00 0.10 2.40 Cum 1657 3977

TOTAL Rs. 785911

Consultant Sub Engineer Asst. Engineer Executive Engineer


Anand Vibhor Rural Development Division,
CGRRDA , Mungeli
153

192

3647
3857

5447
0
59062

250
514

310
1509

594

1314

1548
PRADHAN MANTRI GRAM SADAK YOJNA (PMGSY)
DETAIL ESTIMATE FOR 1 X 6.00M SPAN SLAB CULVERT Format F-7
Name of Road:-Kalmidih To Barampur RD:- 0
Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.
1 7.1(I) Excavation for structuresas per drawing and technical specifications Clause
305.1 including seting out, construction of shoring and bracing, removal of
stumps and othar deletercus material and dis posal upto a lead of 50m
dressing of sides and bottom and backfilling in trenches with excavated
suitable material .Oridanary soil (i) upto 3 m depth

I Abutments 2 8.7 2.50 1.10 47.85


Returns 4 3.20 2.40 1.10 33.79
81.64 Cum 153 12491
2 II Ordanary Rock ( Not Requiring Blasting)
Abutments 2 8.7 2.50 0.20 8.70 Cum
Returns 4 3.20 2.40 0.20 6.14 Cum
14.84 Cum 192 2850
3 7.10 Providing concrete for plain/reinforced concrete in open foundation complete
(ii) as per drawings and technical specifications Clause 802, 803, 1202 & 1203
(II)P.C.C grade M 15(Nominal mix (1:2.5:5)
PCC Grade M-15

Abutments- Foundation PCC 2 8.7 2.50 0.20 8.70


Abutments-Bottom Block ( From foundation to NBL) 2 (7.7+8.50)/2 (1.90+2.30)/2 1.20 40.82
Wingwalls - Foundation PCC 4 3.20 2.40 0.20 6.14
Wingwalls -Bottom Block ( From foundation to NBL) 4 3.20 (1.80+2.2)/2 1.20 30.72
86.39 Cum 3647 315057
4 7.18 Plain/reinforced cement concrete in substructure complete as per drawings
(I) and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204
For height upto 5 m

(I)P.C.C grade M 15 (Nominal mix


(1:2.5:5)
4 7.18
(I)

Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.
PCC Grade M-15
Abutments
Top Block ( From NBL to Abutment cap ) 2 7.50 (0.70+1.70)/2 3.00 54.00
Wingwalls
Top Block ( From NBL to Wing wall cap ) 4 (3.3+4.3)/2 (0.40+1.60)/2 3.53 53.66
Wing wall cap 4 4.30 0.40 0.150 1.03
For Kerb 2 16.00 0.40 0.375 4.80
Wheel guard 2 0.40 0.40 0.60 0.19
113.68 Cum 3857 438464
5 7.27(II Providing and laying reinforced cement concrete in superstructure as per drawing
) and technical specificationsClause 800, 1205.4 and 1205.5(II)R.C.C. M 25 ( Dssign
Mix)

R.C.C. M 25 ( Dssign Mix)


Abutment cap 2 7.50 0.70 0.20 2.10
Dirt Wall 2 7.50 0.30 0.48 2.16
For Slab 1 6.80 7.50 0.48 24.48
24.48 Cum 5447 133343
6 7.28 Supplying, fitting and placing HYSD bar reinforcement in superstructure
complet as per drawing and technical specifications Clause 1002, 1010 and 2.82 MT 59801 168588
1202.

For Cap beam & dirt wall 175.01

for slab
Main bar - 20 mm dia@115 mm c/c 1 66 6.82 2.47 1110.98

Distribution bar -12 mm dia@150 mm c/c 1 46 7.42 0.890 303.77

Top - Longitudinal bar - 10 mm dia@300 mm c/c 1 23 7.42 0.617 105.30

Top - Transerves bar - 10 mm dia@300 mm c/c 1 25 6.72 0.617 103.66

For chair - 20mm dia 1 16 1.59 2.47 62.84


Surface Reinforcement for - Abutment & wing wall @ 5kg/sqm 2 22.80 4.20 5.00 957.60
Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.
2819.16 Kg
7 7.22 Providing weepholes in brick masonry/stone masonry, plain/ reinforced
concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending
through the full width of the structures with slope of 1(V):20(H) towards 16 16.00 No 276 4416
drawing face complete as per drawing and technical specification Clauses
614, 709, 1204.3.7
8 7.35 Drainage spouts complete as per drawing and technical specifications Clause
1209
2 2.00 4.00 No. 1632 6528
9 7.23(I) Backfilling behind abutment, wing wall and return wall complete as per
drawings & technical specification Clause 1204.3.8
(I) Granular material
Abutment - Upto NBL 2 (7.7+8.50)/2 (0.1+0.50)/2 1.20 5.83

2 (7.7+8.50)/2 0.10 1.20 1.94


Wing wall 4 3.20 (0.1+0.50)/2 1.20 4.61

4 3.20 0.10 1.20 1.54


Top Block - Behind abutment & wing wall 2 (2.8+5.2)/2 (3.3+4.30)/2 3.00 91.20
105.12 Cum 654 68748
10 7.41(II Providing and fixing 20 mm thick compressible fibre board in expansion joint
) 2 7.50 15.00 m 342 5130
complete as per drawing and technical specifications
11 10.5(I) Providing and laying pitching on slopes laid over prepared filter media as per
drawing and technical specifications Clause 1302 4 3.00 2.00 0.23 5.52 Cum 1430 7894
(I)Stone/Boulder
12 10.6 Providing and laying Filter Material underneath pitcing in slopes
complete as per drewing specifications Clause 1302 4 3.00 2.00 0.10 2.40 Cum 1657 3977

TOTAL Rs. 1167486

Consultant Sub Engineer Asst. Engineer Executive Engineer


Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.
Anand Vibhor Rural Development Division,
CGRRDA , Mungeli
PRADHAN MANTRI GRAM SADAK YOJNA (PMGSY)
DETAIL ESTIMATE FOR 2 X 6.00M SPAN SLAB CULVERT Format F-7
Name of Road:- Kalmidih To Barampur RD:- 0
Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.
1 7.1(I) Excavation for structuresas per drawing and technical specifications
Clause 305.1 including seting out, construction of shoring and
bracing, removal of stumps and othar deletercus material and dis
posal upto a lead of 50m dressing of sides and bottom and
backfilling in trenches with excavated suitable material .Oridanary
soil (i) upto 3 m depth
I Abutments 2 8.7 2.50 1.10 47.85
Returns 4 3.20 2.40 1.10 33.79
Pier
1 8.90 1.40 1.10 13.71

95.35 Cum 153 14588


2 II Ordanary Rock ( Not Requiring Blasting)

Abutments 2 8.7 2.50 0.20 8.70


Cum
Returns 4 3.20 2.40 0.20 6.14
Cum
Pier
1 8.90 1.40 0.20 2.49

17.34 Cum 192 3329


3 7.10
(ii) Providing concrete for plain/reinforced concrete in open foundation
complete as per drawings and technical specifications Clause 802,
803, 1202 & 1203 (II)P.C.C grade M 15(Nominal mix (1:2.5:5)

PCC Grade M-15 ( Nominal Mix 1:2.5:5)


Abutments- Foundation PCC 2 8.7 2.50 0.20 8.70
Abutments-Bottom Block ( From foundation to NBL) 2 (7.7+8.50)/2 (1.90+2.30)/2 1.20 40.82
Wingwalls - Foundation PCC 4 3.20 2.40 0.20 6.14
Wingwalls -Bottom Block ( From foundation to NBL) 4 3.20 (1.80+2.2)/2 1.20 30.72
Pier - Foundation PCC
1 8.90 1.40 0.20 2.49

2x6.0 m slab culvert


Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.
Pier -Bottom Block ( From foundation to NBL)
1 8.70 1.20 1.20 12.53

101.41 Cum 3647 369835


4 7.18 (I) Plain/reinforced cement concrete in substructure complete as per
drawings and technical specification Clauses 802, 804, 805, 806,
807, 1202 ans 1204
For height upto 5 m

(I)P.C.C grade M 15 (Nominal mix (1:2.5:5)


PCC Grade M-20 ( Nominal Mix 1:2:4)
Abutments
Top Block ( From NBL to Abutment cap ) 2 7.50 (0.70+1.70)/2 3.00 54.00
Wingwalls

Top Block ( From NBL to Wing wall cap ) 4 (3.3+4.3)/2 (0.40+1.60)/2 3.53 53.66
Wing wall cap 4 4.30 0.40 0.150 1.03
For Kerb 2 22.00 0.40 0.375 6.60
Wheel guard 2 0.40 0.40 0.60 0.19
Pier
1 8.50 1.00 3.00 25.50
3857 543760
140.98 Cum
5 7.27(II) Providing and laying reinforced cement concrete in superstructure as per
drawing and technical specificationsClause 800, 1205.4 and
1205.5(II)R.C.C. M 25 ( Dssign Mix)

R.C.C. M 25 ( Dssign Mix)


Abutment cap 2 7.50 0.70 0.20 2.10
Dirt Wall 2 7.50 0.30 0.48 2.16
For Slab 2 6.90 7.50 0.48 49.68
Pier Cap 1 8.50 1.00 0.200 1.70

2x6.0 m slab culvert


Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.
55.64 Cum 5447 303071
6 7.28 Supplying, fitting and placing HYSD bar reinforcement in
superstructure complet as per drawing and technical specifications 59801 294070
Clause 1002, 1010 and 1202. 4.92 MT

For Cap beam & dirt wall 265.15

for slab

Main bar - 20 mm dia@115 mm c/c 2 66 6.92 2.47 2254.57

Distribution bar -12 mm dia@150 mm c/c 2 46 7.42 0.890 607.55

Top - Longitudinal bar - 10 mm dia@300 mm c/c 2 23 7.42 0.617 210.59

Top - Transerves bar - 10 mm dia@300 mm c/c 1 25 6.82 0.617 105.20

For chair - 20mm dia 2 15 1.59 2.47 117.82

Surface Reinforcement for - Abutment & wing wall @ 5kg/sqm 2 22.80 4.20 5.00 957.60

Surface Reinforcement for - Pier @ 5kg/sqm 1 19.00 4.20 5.00 399.00

4917.48 Kg
7 7.22
Providing weepholes in brick masonry/stone masonry, plain/
reinforced concrete abutment, wing wall, return wall with 100 mm
dia AC pipe extending through the full width of the structures with 276 5520
slope of 1(V):20(H) towards drawing face complete as per drawing
and technical specification Clauses 614, 709, 1204.3.7 20 20.00 No
8 7.35 Drainage spouts complete as per drawing and technical
specifications Clause 1209 2 4.00 1632 13056
8.00 No.
9 7.41(II)
Providing and fixing 20 mm thick compressible fibre board in 342 7695
expansion joint complete as per drawing and technical specifications 3 7.50 22.50 sqm
10 7.23(I) Backfilling behind abutment, wing wall and return wall complete as
per drawings & technical specification Clause 1204.3.8
(I) Granular
material
Abutment - Upto NBL 2 (7.7+8.50)/2 (0.1+0.50)/2 1.20 5.83

2x6.0 m slab culvert


Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO No.

2 (7.7+8.50)/2 0.10 1.20 1.94


Wing wall 4 3.20 (0.1+0.50)/2 1.20 4.61

4 3.20 0.10 1.20 1.54


Top Block - Behind abutment & wing wall 2 (2.8+5.2)/2 (3.3+4.30)/2 3.00 91.20

Pier 2 8.70 0.10 1.20 2.09

2 1.20 0.10 1.20 0.29

107.50 Cum 654 70302


11 10.5(I) Providing and laying pitching on slopes laid over prepared filter
media as per drawing and technical specifications Clause 1302 1430 7894
(I)Stone/Boulder 4 3.00 2.00 0.23 5.52 Cum
12 10.6 Providing and laying Filter Material underneath pitcing in
slopes complete as per drewing specifications Clause 1302 1657 3977
4 3.00 2.00 0.10 2.40 Cum

TOTAL Rs. 1637097

Consultant Sub Engineer Asst. Engineer Executive Engineer


Anand Vibhor Rural Development Division,
CGRRDA , Mungeli

2x6.0 m slab culvert


F-7

2x6.0 m slab culvert


PRADHAN MANTRI GRAM SADAK YOJNA (PMGSY)
DETAIL ESTIMATE FOR 3 X 5.00M SPAN SLAB CULVERT Format F-7
Name of Road:- Kalmidih To Barampur RD:- 0
Sr. SOR
ITEM DESCRIPTION No. L B H Total Qty. UNIT RATE AMOUNT
NO REF. No.

1 7.1(I) Excavation for structuresas per drawing and technical


specifications Clause 305.1 including seting out,
construction of shoring and bracing, removal of stumps
and othar deletercus material and dis posal upto a lead
of 50m dressing of sides and bottom and backfilling in
trenches with excavated suitable material .Oridanary
I Abutments
soil (i) upto 3 m depth 2 2.70 7.90 1.60 68.26
Returns 4 2.66 2.24 1.60 38.13
Pier 2 2.20 7.90 1.40 48.66
155.05 Cum 153 23,723
2 II Ordanary Rock ( Not Requiring Blasting)
Abutments 2 2.70 7.90 0.20 8.53 Cum
Returns 4 2.66 2.24 0.20 4.77 Cum
Pier 2 2.20 7.90 0.20 6.95
20.25 Cum 192.00 3888
3 7.10 Providing concrete for plain/reinforced concrete in open
(ii) foundation complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 (II)P.C.C
grade M 15(Nominal mix (1:2.5:5)
PCC Grade M-15 ( Nominal Mix 1:2.5:5)
Abutments 2 2.70 7.90 0.20 8.53
Bottom Block 2 2.20 7.70 1.40 47.43
Returns 4 2.66 2.24 0.20 4.77
Bottom Block 4 2.16 2.58 1.40 31.21
Pier

2 2.20 7.90 0.20 6.95


98.89 Cum 3647.00 360,653
Plain/reinforced cement concrete in substructure
4 7.18 (I)
complete as per drawings and technical specification
Clauses 802, 804, 805, 806, 807, 1202 ans 1204
For
height upto 5 m

(I)P.C.C grade M 15 (Nominal


mix (1:2.5:5)
PCC Grade M-15
Abutments
Top Block 2 1.20 7.50 3.00 54.00
Abutment cap 2 0.70 7.50 0.20 2.10
Dirt Wall 2 0.40 7.50 0.48 2.88
Returns
Top Block ( up to Abutment cap bottom) 4 2.74 1.02 3.68 40.86
Top Block ( From Abutment cap bottom to cap top) 4 3.35 0.49 0.68 4.44
Coping above Return Wall 3.35 0.40 0.15 0.00
Pier 2 7.70 1.00 4.00 61.60
Pier Cap 2 7.50 1.00 0.20 3.00
267.78 Cum 3857.00 1,032,810
5 7.27(II) Providing and laying reinforced cement concrete in
superstructure as per drawing and technical
specificationsClause 800, 1205.4 and 1205.5(II)R.C.C. M 25
( Dssign Mix)

R.C.C. M 25 ( Dssign Mix)


For Slab 3 5.90 7.50 0.43 57.08
For R.C.C. Kerb 6 5.90 0.45 0.38 5.97
63.06 Cum 5447.00 343467

6 7.28 Supplying, fitting and placing HYSD bar reinforcement


in superstructure complet as per drawing and technical
specifications Clause 1002, 1010 and 1202. 5.50 MT 59,801 328,841
Surface Area of Abutment 4 2.20 1.40 12.32
4 1.20 3.00 14.40
2 9.80 7.50 147.00
Surface Area of Return 4 2.16 1.40 12.10
4 1.02 3.68 14.94
4 2.74 11.08 121.44
Surface Area of Pier 2 8.70 4.00 69.60
391.79 Sqm
For Slab @60kg/Cum 70 57.08 3995.78
For Kerb 120kg/Cum 120 5.97 716.85
For Abutment Cap '@ 85.0 kg / sqm 85 2.10 178.50
For Ballast wall '@ 75.00 kg / cum 75 2.88 216.00
For Surface Reinforcement @5kg /Sqm 1 391.79 391.79
5498.92 Kg
7 7.22 Providing weepholes in brick masonry/stone masonry,
plain/ reinforced concrete abutment, wing wall, return
wall with 100 mm dia AC pipe extending through the full
width of the structures with slope of 1(V):20(H) towards
drawing face complete as per drawing and technical
specification Clauses 614, 709, 1204.3.7 20 20 No 276.00 5520
8 7.24
Providing and laying filter media with granular crushed
aggregates as per specification to a thickness of not
less than 600 mm with smaller size towards the soil
and bigger size towards the wall and providing over the
entire surface behind abutment, wing wall, return wall to
the full height, compacted to firm condition complete as
per drawing and technical specification Clause
1204.3.8

Behind Abutments 2 6.50 0.30 3.00 11.70


Behind Returns 4 3.35 0.30 1.50 6.03
17.73 Cum 1291.00 22889
9 7.32
Construction of R.C.C. railing of M 25 grade in cast-in-
situ with 20 mm nominal size aggregate, true to line and
grade, tolerance of vertical railing post not to exceed 1
in 500, centre-to-centre spacing between vertical posts
not to exceed 2000 mm as per drawing and technical
specifications Clauses 800, 900 and 1208.3
2 21.00 42.00 Rm 2272.00 95424
10 7.35
Drainage spouts complete as per drawing and technical
specifications Clause 1209
0.00 No. 1632.00 0
11 7.23(I) Backfilling behind abutment, wing wall and return wall
complete as per drawings & technical specification Clause
1204.3.8
(I) Granular material

30.00 Cum 654 19620


12 7.41(II) Providing and fixing 20 mm thick compressible fibre
board in expansion joint complete as per drawing and
technical specifications 4 7.50 30.00 Sqm 342 10260
13 10.5(I) Providing and laying pitching on slopes laid over
prepared filter media as per drawing and technical
specifications Clause 1302
(I)Stone/Boulder 4 5.00 3.00 0.23 13.80 Cum 1430.00 19734
14 10.6 Providing and laying Filter Material underneath
pitcing in slopes complete as per drewing
specifications Clause 1302 5.00 2.00 0.10 0.00 Cum 1657.00 0

TOTAL Rs. 2266831

Consultant Sub Engineer Asst. Engineer Executive Engineer


Rural Development Division,
CGRRDA , Mungeli
Table 5.1 Average daily Traffic both directions for three days

Sl. No. Type of Vehicle Day-1 Day-2 Day-3 Average


1 Car, Jeep, Van 11 12 14 12
2 Auto Rickshaw 14 11 12 12
3 Scooters/Motorbikes 53 47 42 47
4 Bus / Minibus 2 2 3 2
5 Trucks 14 18 19 17
6 Tractors with trailer 35 41 33 36
7 Tractor without trailer 0 0 0 0
8 Cycles 135 141 125 134
9 Cycle Rickshaw / Hand Cart 0 0 0 0
10 Horse cart / Bullock Cart 14 15 10 13
11 Pedestrian 0 0 0 0
Total commercial vehicle per day (cvpd) 274

Total motorised vehicle per day 128

Total non-motorised vehicle per day 147

Total ESAL

{Tick the relevant box}


a) Traffic volume and mix do not vary along the road
b) Traffic volume and mix vary along the road
c) Traffic volume and mix will vary along the road in the future
d) There is a potential for through traffic using the road
e) % of loaded vehicles
HCV MCV M/CYCLES CARTS CYCLES
LCV CAR/JEEP
S. No. L UL L UL L UL

5 5 9 9 2 12 42 6 0 102

1 TOTAL MOTORISED VEHICLE 85

2 TOTAL NON MOTORISED VEHICLE 108

3 AVERAGE DAILY TRFFIC ADT 192

4 ANNUAL AVERAGE DAILY TRAFFIC AADT (During Non Harvesting Season) 119.88

5 PROJECTED ANNUAL AVERAGE DAILY TRAFFIC AADT( FOR 2 YEAR PERIOD) 135

6 PROPORTION FACTOR 0.700

7 PROJECTED TRAFFIC

HCV MCV

L UL L UL

3.50 3.50 6.54 6.54

8 VEHICLE DAMAGE FACTOR VDF

HCV MCV
TOTAL
L UL L UL

10.01 1.09 2.22 0.13 13.45

9 TOTAL ESAL ( EQUIVALENT STANDARD AXLE LOAD)PER DAY 13.45

10 CUMULATIVE ESAL OVER 10 YEARS @ 6% GROWTH RATE 64724


CHECK LIST FOR SUBMITTING PROJECTS
PROPOSALS FOR FINANCE UNDER R.I.D.F WITH NABARD
FOR APPRAISAL REPORT
1 Whether complete details in appraisal report. Filled porperly and Yes No
no. coulumn left blank particularly the following details.
a) Whether F.D. reference No. and date S.No. in enclosed Yes No
b) Whether Category of road i.e. VR/ORD/MDR, etc is Yes No
mentioned
c) Whether the budget item No. and Budget provision for current Yes No
financial year is mentioned.
d) Whether date of start of work is entered. Yes No
e) Whether technical details are properly entered. Yes No

f) Whether the column of Total work, work to be done and Yes No


balance work is filled properly K.M. wise, quaintly-wise and
amount wise.
g) Whether all CD's listed out and categorized Yes No
h) Whether prescribed in appraisal report is given. Yes No
i) Whether the tables prescribed are properly filled (Table-1), Yes No
Table-2 & Table-3 of appraisal report)

FOR INDEX MAP AND KEY MAP


2 Whether proposal is marked on the index map and key map Yes No
with details required connectivity is shown clearly, N.H. is
marked in yellow colour, SH is marked in Green colour. MDR in
Red colour and ODR, VR with black colour in double line
particularly the following :

a) Whether other WBM & BT roads are marked on the maps. Yes No
b) Whether the railway crossing (manned & unmanned) are Yes No
marked.
c) Whether other alternative roads available at present is Yes No
marked.
d) Whether reduction of distance if new proposed road is Yes No
complete, is calculated and marked.

e) Whether canal crossing if any are marked. Yes No


f) Whether villages are marked. Yes No
g) Whether marked yart/godowns are marked. Yes No
h) Whether cold storage are marked. Yes No
i) Whether School/Collage are marked. Yes No
j) Whether Hospital& dispensaries marked. Yes No
k) Whether Railway staton& Bus station are marked. Yes No
FOR INDEX MAP AND KEY MAP
2 Whether proposal is marked on the index map and key map with details Yes No
required connectivity is shown clearly, N.H. is marked in yellow colour, SH
is marked in Green colour. MDR in Red colour and ODR, VR with black
colour in double line particularly the following:

a) Whether other WBM & BT roads are marked on the maps. Yes No
b) Whether the railway crossing (manned & unmanned) are marked. Yes No

c) Whether other alternative roads available at present is marked. Yes No

d) Whether reduction of distance if new proposed road is complete, is Yes No


calculated and marked.
e) Whether canal crossing if any are marked. Yes No
f) Whether villages are marked. Yes No
g) Whether marked yart/godowns are marked. Yes No
h) Whether cold storage are marked. Yes No
i) Whether School/Collage are marked. Yes No
j) Whether Hospital& dispensaries marked. Yes No
k) Whether Railway staton& Bus station are marked. Yes No
FOR ESTIMATE
3 Whether details of work done and work to be done is marked properly in Yes No
ber chart with locations of CD's constructed.

4 Whether self expplanatory technical report for project proposal included (As Yes No
per Annexure-A)
5 Whether typical cross section of road existing and proposal are included Yes No
in the project.
6 Whether details of work done and work to be done tally with appriasal Yes No
proforma, technical repot, bar chart and estimate.

7 In case of new earth work whether chain and compass survey conducted Yes No
and L-section and cross section drawn to comput the earth work.

8 Whether reasonability certificate for the rates provided in the estimate for Yes No
land acquistion is attached (if land is to be acquired).

9 Whether the reasonability certificate for higher/lower tender percentage is Yes No


attached.
10 Whether provision for is escalation in cost made. Yes No
11 Whether reson for high/low cost of construction per km. of road is Yes No
indicated.
12 a) Whether serve detailed design catchment area-plan site plan and Yes No
working drawing for corss dranage work are attached.
b) Whether site-plan working drawing and designed including hydraulic Yes No
calculation for CDs work having waterway 6.00 M. or more are approved by
competent authority (SE/CE)

GENERAL
13 Whether all the document of the project are signed by the executive
engineer.
14 Whether index sheet properly filled and attached with the project.

SubEngineer Sub Divisional Officer Executive Engineer


Rural Development Division Rural Development Division Rural Development Division
CGRRDA , Mungeli CGRRDA , Mungeli CGRRDA , Mungeli
RURAL INFASTRUCTURE DEVELOPMENT FUND
ROAD PROJECT APPRAISAL REPORT

1 Name of the Project :- Constructions of Road from


Kalmidih To Barampur
road Under MMGSVY
2 Project Location :- District:- Mungeli

Tahsil:- Mungeli

Block:- Lormi

Distance form the district :- 12 km.


Headquarters of the 12
nearest end Km.) :
3 Financial deptt. Reference

Letter no. : Date Sr. No.

Grant no. : (General)

4 Length of road : From Kalmidih Km. 0.00

To Barampur Km. 2.22

Total length Km. 2.22

5 Category of road : Village road

6 Project Status New work

7 Implementing Agency : Zone:- CGRRDA Raipur

Circle: CGRRDA Bilaspur

Division: Rural Development Division, Mungeli

Sub- -
division:
8 Details of Administrative approval :-

No.:-

Date:-

Provision:- Lacs

Amount:- 105.83 Lacs

9 Details of Technical Section Rs.: Lacs

No.:-

Date:-

Provision:-

10 Budget item no. 2016-17 No.


Budget provision for 2016-17 Rs.:- Lacs
11 Year of commencment 2016-17

12 Revised update cost Rs.: 0 Lacs


13 Expenditure upto March 2016 Rs.: 0 Lacs
14 Financial acchivement upto March 2016 …………% 0 Lacs
15 Balance cost Rs….Lac's Lacs
16 Year wise Assistance Reqired for complection of
projcet :-
S.No Year Amount (In Lacs Rs.)
.
a 2016-17 0.00

b 2017-18 105.83

c 2018-19 0.00

17 Details of Connectivity of the proposed road with existing transportation system :-

Whether the road connects with urban


center/marketing center/other road
i) End A :
Yes
ii) End B :
Name of the urban center/marketing
center/other road contact :-
i) End A : Kalmidih Road
Karankapa Barampur road
ii) End B :
If connects other road give following
particulars :-
(i) End A - Kalmidih
Road
- Name of road VR

- Category of road earthen


-
(VR/ODR/MDR)
ii) End B -
- Name of road - Karankapa Barampur road
Status of the road (class I/II) - VR
Category of road
- (VR/ODR/MDR) Earthen
-
Status of the road (class I/II)
18 Technical details: -
Sr.No Item Existing Praposed Increase Reasons for Deviation if any
.

1 Road way width (m) 6.00 7.50


2 Carrige way width (m) 3.75 3.75
3 Thickness (m)
a. Sub grade - 0.300
b. Sub base - 0.125
c. WBM
Grade I - -
Grade II - 0.075
Grade III - 0.075
d. BT - 0.020
19 Project physical details :
Total physical work Progress upto March 20
S.No. Items Unit Qty. Amt. Qty. Amt.(Rs In Lacs
(Rs. In Lacs)
1 Land Acquisition Ha. - 0
2 Formation Erthwork km/cum 2.22/1026.25 14.82
3 Sub grade km/cum 2.22/6180.48 10.88

4 Sub base km/cum 2.22/1136.3586 9.32


5 WBM-Grade I km/cum - -
Grade II (1 coat) km/cum 2.22/0 0.00
Grade II (2 coat) km/cum - -
Grade III km/cum 2.22/0 0.00

6 B.T.i/c hard shoulder & earthen km 2.22 31.36


Shoulder
7 C.C. road km 0 1.85
8 fixed item viz. Meterage, stones, L.S 7.14
Boundry stones, signage,
arboriculture, Land scaping,
drains, stone paving etc.
9 CD work No. 0 0.00
10 Canal/Ray.Crossing (Specify) No. 0 -
11 Other work (Field Rs. 30.48
crossing,W/C,Shed,H.P.,DPR.,co
ntengency & Maintance )

Total 105.83
Details of CD work
Type No.
1 600 mmФ FC 7
2 450 mmФ FC 0
3 1x1.5 mm SC 0
4 1000 mmФ HPC 0
5 1x1.0 mm SC 0
6 1x3.0 mm SC 0
7 1x5.0 mm SC 0
8 1x6.0 mm SC 0
20 Details of Balance works :-

S.No. Item Unit Physical Estimated cost (Rs. In Lac's) Consultant's


Recommendations
Qty.
Previous Cost of Total
liability balance work

1 Land Acquisition Ha. - - 0 0

2 Formation Erthwork km/cum 2.22/1026.25 - 14.82 14.82

3 Sub grade km/cum 2.22/6180.48 - 10.88 10.88

4 Sub base km/cum 2.22/1136.3586 - 9.32 9.32

5 WBM-Grade I km/cum - - -

Grade II (1 coat) km/cum 2.22/0 - 0.00 0.00

Grade II (2 coat) km/cum - - -

Grade III km/cum 2.22/0 - 0.00 0.00

6 B.T.i/c hard shoulder & earthen km 2.22 - 31.36 31.36


Shoulder
7 C.C. road km 0 - 1.85 1.85

8 fixed item viz. Meterage, stones, L.S - 7.14 7.14


Boundry stones, signage,
9 arboriculture,
CD work Land scaping, No. - 0.00 0.00
drains, stone paving etc.

10 Canal/Ray.Crossing (Specify) No. - - -

11 Other work Rs. - 30.48 30.48


(HPC,W/C,Shed,H.P.,DPR., &
Maintance )
Total 105.83 105.83
Details of CD work
Type No.
1 HP culvert- -

2 Slab culvert- 0

3 HP culvert- 0
21 Total Cost/Km. :- 46.842 Lakhs
If the Cost Is higher/lower
Than Rs……………………..
Lacs/km. reasons For the
22 same with details.
Whether any alternate class 1 road available No
Connecting two ends of the road.
23 if yes, provide following information
(i) Name of the road :-
(ii) Length between the two points
Through the alternate rout.
(iii) Net reduction in distance
(Length of alternate rout-length
of th proposed road)
Note :- Provide index plan of the alternate rout.
24 Boulenecks faced/being faced in
Implementation related with : (a) Land Acquisition No
(b) Contractual litigation No
(c) forest/Environment clearance No
(d) Railway permission for crossing No
(e) Others, if any No
25 Weather any irrigation tank project is located
Down stream, if so, No
(i) Location
(ii) Likelihood of road coming under submergence
26 Any other information relevant to the project No
ECONOMICS
27 The road project would provide benefts of
connectivity to :
S.No. Particulars No.
a. Villages 1
b. Market yard/Godowns
c. Cold Storage/coal Dipo
d. Schools and Collages 1
e. Hospital and dispensaries
f Railway Station and bus Station
g Population benefitted ad per the latest census
h Area benefitted (ha.)
28 Actual Vehicular traffic/Day :

29 Total Farm Incom (as per table :


I)
30 Annual Maintenance Cost (as per 0.62 Lacs
31 Table 3)
Special Justification/benefits of the project :
32 Remarks, if any :

:
SubEngineer Sub Divisional Officer Executive Engineer
Rural Development Division
CGRRDA , Mungeli
TABLE NO. 1 Actual Vehicular Traffic/Day.
S.No. Vehicle Type No. of Conversion Standard
pass/day factor Passenger

Car Unit (PCU)


1 Cycle
133.67 0.50 66.83
2 Cycle rickshaws
0.00 0.00
3 Handcart
0.00 0.00
4 Hors drawn vehicle
0.00 0.00
5 Bullock cart
13.00 8.00 104.00
6 Motor cycle/scooter
47.33 0.50 23.67
7 Passenger car/pickup/Autorickshaw
24.67 1.00 24.67
8 Agriculture tractor/LVC
36.33 1.00 36.33
9 Truck or bus
19.33 3.00 58.00
10 Truck-Trailar/Agricultural tractor-
3.00 0.00
trailer
Total 274.33 313.50

SubEngineer Sub Divisional Officer Executive Engineer


Rural Development Division
CGRRDA , Mungeli
Certficate
1 Certificate that in respect of the proposed, the physical assets created prior to 31.03.2017 As
indicated under item No. 19 of the proposed are in existence and an amount of Rs.

Lakhs has been spent on the project upto 31.03.2017


2 It is further certificate that in completion of the balance items as proposed under item No. 20 of
the project proposal, the road will be completed in all respects all the required cross drainage
works (i.e. minor, medium and major)

3 Certificate that the Kilometers proposed for black topping have not been black topped earier.

4 Certificate that a minimum metal thickness of 150 mm will be ensured before laying B.T Carpet.

5 It is certified that transect walk has been done and the 1st stage estimate is correct as per site
condition . Sufficent length and width of land for the proposed road is available .

6 Certificate that the Road Kalmidih to Barampur situated in Lormi block of Mungeli District . Most
of the area in this block is of Black cotton soil . As per topographic and material survey it has
been found that CBR value in this area ranging from 2 to 3 % (2.60 & 2.51 % ) . Looking to this
site condition it has been decided to provide 300 mm thick subgrade over MANRGA eartwork
after due correction . Accordingly we have provided 300 mm subgrade below crust design
thickness

7 Certificate that due to non availability of moorum required in GSB material , Crushed stone
material (G-III ) GSB is provided in estimation .

SubEngineer Sub Divisional Officer Executive Engineer


Rural Development Division
CGRRDA , Mungeli
TECHNICAL PROJECT REPORT
This Project reports should contain information under the Following heads
1 Preliminary : s
a) Nature of Work and as broad scopes The RoadKalmidih to Barampur situated in Lormi block
of mungeli District. The existing road is earthen
road .Protection work required near culvert &
Nalla.Ten no of culvert is required .

As per IRC :SP:72:2015 provisin made as follows


1. 300 mm th Subgrade in full width of Road
2. 125mm thick GSB in 4.05 m Width
3. 75 mm thick WBM G - II in 3.85 m width of road
4. 75 mm thick WBM G - III in 3.75 m width of road
5. 20mm PMC with Seal coat in 3.75m width
b) Authority And plan Provision. Chhattisgarh
c) History, Geography Climates etc. Plane, hot and cold Climates
d) Necessity Access facilities to Community
2 Road Features :
a) Route Selection Existing
b) Alignment Existing
c) Environmental Factor Nill
d) Road land Roadways Carriage way Enclosed
and other cross-section elements
Including crust thickness. Existing and
proposed
e) Traffic Enclosed (Table No.1)
3 Road Design and Specification :
a) Road design Typical Cross-Section Enclosed
b) Pavement design Typical pavmeant design Enclosed
c) Masonry work (other than CD's like Not applicable
retaining walls breast walls pitching
parapet walls alling etc.
4 Drainage Facilities

a) Investigation carried out Yes


b) Details of surface and sub surface Enclosed
drainage
c) Special measure, if any Nil
d) Improvements to existing CD Structure Nil
e) Standard Design adopted Yes
5 Requirement and avalability of materials Local
labour and Equipments
6 Rate adopte
a) Provision made over and SOR SOR 01.09.2014
adopted with reason
b) Provision for escalation if any
7 Special mentions :
a) Whether any Railways level crossing Nil
existing if yes.
GENERAL ABSTRACT
New B.T. of :- Kalmidih To Barampur

Length( Km.):- 2.22

S. No. Sub-head Amount

1 A. Earthwork 0

2 B. Pavment cost i/c cross drainage work 10088198

3 C. Internal gali C.C. Road

Total gali 0 No

Length ( m) 0 0

D. yatri Pratikchalaya+ Toilet Block + Hand


4 0 0
pump - ( No.)

5 Preparation of DPR 0

6 Maintenance cost 310800

Total Rs. 10398997.61

Add 1% for W.C. Estt. & Contingencies


100881.98
Rs.

Add 2 % work charge Establishment Rs

Grand Total Rs. 10499879.58

Say Rupees 105.00 Lacks

SubEngineer Sub Divisional Officer Executive Engineer


Rural Development Division
CGRRDA , Mungeli
REPORT AND SPECIFICATION

1 Name of work :- New B.T 0f. Kalmidih To Barampur

2 Constituency :- CGRRDA Block- Lormi


Distt- Mungeli
3 Amount :- Rs ( Lacks ):- 105.00

4 Athority :- Govt. of Chhattisgarh. CGRRDA Raipur A.A. Rs


102.99 lacks vide CGRRDA latter no

5 Provision :- The following provisions has been made in the


estimate
1. 300 mm th Subgrade in full width of Road
2. 125mm thick GSB in 4.05 m Width
3. 150 mm thick WMM - 3.80 m width of road as non
availabilitiy G-II and G-III metal
4. 75 mm thick WBM G - III in 3.75 m width of road
4. 20mm PMC with Seal coat in 3.75m width
5. Hard Shoulder 1.875 m width in both side
6 Rate :- Schedule of rates taken S.O.R. of P.M.G.S.Y. issued
by CGRRDA in force from SOR 01.09.2014

7 Specification :- The work will be strictly executed as per MORT & H,


New Delhi specification for road and bridge work Ivth
revision and general nots of S.O.R.

SubEngineer Sub Divisional Officer Executive Engineer


Rural Development Division
CGRRDA , Mungeli
Name of Road:- Kalmidih To Barampur

Length of Road:- (km) 2.22


1 Name of Villages & population as per Census 1991 falling on road

Sr. No. Name of Villages population (2001)

1 Barampur

SubEngineer Sub Divisional Officer Executive Engineer


Rural Development Division
CGRRDA , Mungeli

You might also like