PART A
(Answer All questions)
(8 x 5 = 40)
a. Advantages of specification.
d. Specifications of reinforcement.
f. Types of estimate.
PART B
(4 X 15 = 60)
II. What is specification? What are different types of specification.
OR
III. Write the general specification for
i. Coarse aggregate
ii. Sand
iii. Cement
IV. Write detailed specification for painted wooden doors of an office building
OR
V. Write detailed specification for cement concrete 1:4:8.
VI. Prepare an estimate of quantities for the item shown below based on the attached
drawing. Assume any appropriate data, if found necessary.
VIII. Calculate unit rate of brick work for walls in cement mortar 1:4. Assume any
appropriate data, if found necessary.
Rates:
Bricks INR 9000/1000 nos
Cement INR 500/bag
Sand INR 1200/m3
Mason INR 800/person
Man 500/person
Woman 500/ person
OR
IX. Calculate the unit rate for cement mortar 1:6 for plastering walls, 12 mm thick.
Assume any appropriate data, if found necessary.
Cement 43 kg/cu m
Sand 0.15 cu m/cu m
Mason 1.00/10 cu m
Man 0.50/cu m
Woman 0.50/cu m
Rates:
Broken stone INR 650/cu m
Cement INR 500/bag
Sand INR 1200/cu m
Mason INR 800/person
Man 500/person
Woman 500/person
***