You are on page 1of 6

Project Title: Marriot Grand Ballroom

Contract Package No. 02 CONCRETE WORKS

Document Title:

Method Statement for Rubbed Concrete

REVISION HISTORY

MARK DATE DESCRIPTION MEPF CIVIL / STRUCTURAL

A1 1st Submission

GENERAL CONTRACTOR
Prepared By: NGCB CQC

Checked By: QA/QC Head


NGCB DATE
PROJECT MANAGEMENT
Mechanical Engineer

Reviewed by: Electrical Engineer


EELHI Civil Engineer
Architect

Project Manager
Approved By:
Sr. Project Manager
EELHI

CONTRACTOR’S DOCUMENT No.: MGB-MS-017-AR-001 REVISION A1

MGB-MS-017-AR-001 Page 1
TABLE OF CONTENT

1. PURPOSE
2. SCOPE AND APPLICATON OF WORKS
3. REFERENCES
4. DEFINITIONS AND ABBREVIATIONS
5. SPECIFICATION CLAUSE
6. RESOURCES AND MOBILIZATION
7. CONSTRUCTION EQUIPMENT
8. PERSONNEL
9. MATERIALS
10. CONSTRUCTION PROCEDURE AND METHODOLOGY
11. TESTING AND INSPECTION
12. RESPONSIBILITY
13. DESIGN DRAWINGS
14. QUALITY ASSURANCE
15. HEALTH AND SAFETY
16. ORGANIZATIONAL CHART
17. INSPECTION
18. ATTACHEMENTS

___________________________________________________________________________

1. PURPOSE

This method of statement defines that the Rubbed Concrete Works to be conducted in the site are in
compliance with the Architectural Works Technical Specification and approve Construction
Methodology. And the Materials to be used for specific works are in compliance with the approved
design and material approvals. And will ensure that work procedures are in compliance with the
Project Safety Plan. The inspection will be based from the Project Quality Plan. The inspection is
associated quality procedures and an approved Inspection and Test Plan for the concrete repair
works.

2. SCOPE OF WORK

The work method is summarized as follows:

2.1. Checking of concreted area needs to be rubbed concrete


2.2. Preparation of the area
2.3. Inspection of Rubbed Concrete Materials
2.4. Setting out of the works
2.5. Layouts for references
2.6. Cleaning and retouching works
2.7. Inspection

3. REFERENCES

This method statement has been prepared with reference to the following documents:

3.1. Approved Architectural Works Technical Specification


3.2. Submitted approved Rectification Materials
3.3. Approved Project Safety Plan
3.4. Approved Project Quality Plan
3.5. Approved Inspection Test Plan

MGB-MS-017-AR-001 Page 2
4. DEFINITIONS AND ABREVIATIONS

4.1. EL - Elevation
4.2. MM - Millimeter
4.3. OC - On Center
4.4. ITP - Inspection Test Plan
4.5. MS - Method Statement

5. SPECIFICATION CLAUSE

The specification requirements for Rubbed Concrete works are described within Project Technical
Specification of Architectural Works and For Construction Design Drawings as follows:

5.1. Technical Specification for Structural Works

5.1.1.Materials:
5.1.1.1. SKIM COAT
5.1.1.2. Brand Name: GRANDFIX SKIM COAT SF
5.1.1.2.1. Description: Grandfix skim coat is a finishing cementitious surfaces compound
specially formulated for concrete surfaces and pre-casts for indoor and
outdoor use. It is supplied as a ready to use blend of dry powders which
requires only the addition of clean water. The product exhibits excellent non-
sag properties that provide great workability on overhead and vertical
applications.

It is used independently as render of up to 3mm thick to face up most types of


masonry.

5.1.1.2.2. Instruction for use as per supplier/manufacturer:


5.1.1.2.2.1. Preparation
Clean the surface and remove all dust, oil or traces of foreign materials.
Oil and grease deposits should be removed by stream cleaning,
detergent scrubbing or the use of a degreaser. The clean areas should
be blown clean with oil-free compressed air before continuing.

For a durable finish all surfaces should be thoroughly dampen prior to


the application of Grandfix skim coat SF.

5.1.1.2.2.2. Mixing
Using a plastic container, place 5.0 to 7.5 liters of clean water in the
container and add 25 kg of Grandfix skim coat SF. Mix thoroughly using
a slow speed electric drill fitted with a paddle for 3-5mintues until desired
homogeneous paste is achieved. Depending on the ambient
temperature and the desired consistency, the amount of water required
may vary slightly but should not exceed 7.5 liters per 25kg of Grandfix
skim coat SF.

Always add power to water. Yield is approximately 15 liters per 25 kg


bag.

5.1.1.2.2.3. Application
Apply the mixed Grandfix skim coat SF using a steel trowel up to 3mm
thick. Thin skim coating will dry in about 30-45 minutes depending on
temperature and porosity of substrate. Smoothen the skim coat with soft
paint brush or trowelled smooth.

Note: No further addition of water to unused plasteris required.

5.1.1.2.2.4. Overcoating
Grandfix Skim Coat SF may be overcoated with a decorative coating
after about 48 hours depending on the ambient conditions

MGB-MS-017-AR-001 Page 3
6. RESOURCES AND MOBILIZATION

The Accessibility at the site will be planned and subject for approval. The Safety of the staff, workers
and material delivery also concentrate on the plan in order to mobilize in accordance from the project
requirements. All the materials to be used are subject for submittal and approval in accordance with
the Architectural Work Technical Specification.

The General Contractor (NGCB) will notify the schedule one day before the actual mobilization of the
staff, workers, equipment.

It is understood that NGCB will be responsible for the provision of appropriate type of crane for the
transportation of materials and equipment to complete the works including temporary construction
water and power supplies and lighting system.

7. CONSTRUCTION EQUIPMENT

This Method of Statement for Rubbed Concrete Works has been envisaged that no major equipment
will be required by this activity. The typical construction equipment requirements are as listed below
and will be used up to the completion of the activities.

7.1. PPE for all staff and workers


7.2. Measuring tapes and setting out markers
7.3. Leveling instrument
7.4. Shovel
7.5. Trowel
7.6. Preparation Tools (chipping tools/gun, cleaning equipment, grinder)

8. PERSONNEL

For this Rubbed Concrete works will be organized by both General Contractor and Nominated
Subcontractor. All the personnel shall be fully competent and trained to carry out all works associated
with the Rubbed Concrete. They shall have attended the required contractor’s safety induction and
will abide by the Health and Safety Plan, policy and procedures as well as environmental plan. It is
envisaged that the installation will be conducted by the followings:

8.1. Site Engineer


8.2. Survey Team
8.3. Quality Control Engineer
8.4. Foreman
8.5. Mason
8.6. Labor

9. MATERIALS
The Materials for rubbed concrete works shall be prepared and inspected at the NGCB site
warehouse before the retouching Works. The retouching works will be done at site using a manual
procedure provided by NGCB and as per specifications by supplier/manufacturer.

All materials delivered to the site will be inspected by NGCB Engineers In-charge together with the
QA/QC Inspectors and EELHI Inspectors to check if the materials are in accordance with the site
requirement and conform to the approved design and material qualification. A sample of mix
materials shall be inspected at site and tested before the retouching works; rejected materials shall
not be accepted and shall be returned to supplier.

The inward inspection of materials will be carried out in accordance with the relevant QA/QC
procedures and or approved Project Quality Control Plan and manufacturer’s / specification of
suppliers.

MGB-MS-017-AR-001 Page 4
Note: No materials shall be permitted to enter and/or installed inside the jobsite without inspection
and approval from CQC Engineers upon arrival at jobsite.

10. CONSTRUCTION PROCEDURE AND METHODOLOGY

This Concrete Rehabilitation construction procedures and methods define the Scope of Work
summarized in section two of this method statement.

10.1.PREPARATION OF THE WORKS

Before the concrete rehabilitation, the following are required to be carried out:

10.1.1. Identifying on rectification procedure needed


10.1.2. Securing Material submittal and ITP are with approved status.
10.1.3. Check if the materials have been inspected and ready for fabrication
10.1.4. Check that the site access to the work area available, clean and safe.
10.1.5. Check if the temporary services provisions are available.

10.2.DELIVERY & INSPECTION OF MATERIALS FOR RUBBED CONCRETE

10.2.1. All delivered materials shall be inspected upon arrival on site. The inspection shall be
advised, in advance, as required by the ITP and in accordance with the Project Quality
Plans
10.2.2. The delivered materials shall be in accordance with the approved design technical
specification and approved material submittal.
10.2.3. Material approvals in form of approved SRF and all applicable documentations and
certifications shall be available during incoming material inspection.
10.2.4. Any materials delivered in the site that are not complying with the approved material
submittals and structural technical specification or rejected by EELHI Engineer shall
either be returned to the supplier or stored in the site at a suitable quarantine area.
10.2.5. The materials shall be free from defects or damaged, and still workable.

10.3.RUBBED CONCRETE: SETTING OUT OF WORKS

10.3.1. Generally, prior to commencement of the delivery of materials for retouching of concrete,
the setting out of the retouching works shall be conducted to determine the location and
elevation.
10.3.2. The setting out of the works shall be on the basis of an “approved for construction
drawings and or approved shop drawings”. Settings points shall be from the common
reference point established provided in the site by NGCB.
10.3.3. Any discrepancy between the common reference point on the approved for construction
drawings and the actual site provisions shall be notified to EEHLI and an NCR shall be
raised.
10.3.4. Work shall not proceed when weather conditions detrimentally affect the quality of
rectification materials.

10.4.RUBBED CONCRETE PROCEDURE

10.4.1. General: check the area of concrete to be rectify, if sanding is needed


10.4.2. Clean and remove dirt from the concrete
10.4.3. Use Baufix on uneven surfaces to correct the plumbness/alignment of the concrete
10.4.4. Before application of skimcoat, concrete must be moistened enough
10.4.5. Mix the skimcoat materials in accordance with the manufacturers instruction
10.4.6. Application of the mixed skimcoat materials shall be performed within the working life of
the skimcoat system
10.4.7. Unused mixed materials which have reached the end of the working life shall be
removed from the jobsite
10.4.8. smoothen the skim coat with soft paintbrush or trowelled smooth.
11. TESTING AND INSPECTION

MGB-MS-017-AR-001 Page 5
11.1. Inspection: Examine the delivered materials at the site. Application procedures and
preparation will be examined by the engineer, if it will comply to the requirements
specified
11.2. Check each surface of retouched concrete area if acceptable or not acceptable. If
there’s any defect from rectified concrete. Immediately repair defects.

12. RESPONSIBILITY
The Contractor (NGCB) will be supervising all activities in the site through Construction
Supervisors, Foreman and skilled workers at the site. The QA/QC Inspectors will be
responsible for arranging and controlling the inspection and testing activities with the
EELHI Inspectors.

13. DESIGN AND DRAWINGS


The Construction Designs and Material Specifications for the Rubbed Concrete shall be submitted
and subject for approval of the consultant through Material Submittal, Submittal Review Form
Made by NGCB and NSC before the work starts.

14. QUALITY ASSURANCE


The execution of work will strictly follow the Project Quality Plan

15. HEALTH AND SAFETY PLAN


The execution of work will strictly follow the Project Safety Manual.

16. ORGANIZATIONAL CHART


As per Organizational Chart of the Project

17. INSPECTION TEST PLAN


As per attached ITP

18. ATTACHEMENTS
 Checklist for inspection of incoming material for Rubbed Concrete materials.
 Checklist for Inspection of Rubbed concrete

MGB-MS-017-AR-001 Page 6

You might also like