End User: Crane No.: SU#01 Paiton

PT. PJB Unit 1 dan Unit 2 Paiton

Project Name: Checked By: H. Boedysetijono


Penormalan Boom Ship Unloader

Project No.: HI0277.PJ/VI/612.S/UPHT/2018 Revision: 00

Date: 1 Juni 2018 Date tested:

Page 1 of 4
Main Specification

Motors

Rated Armature Field Speed


Function Qty Power Type
(HP) (V) (A) (A) (RPM)

Boom 1 125 CD5010AY 500 212 4.53 400

Test Procedure

Function Test of Boom Up/Boom Down System

The purpose of this test is to ensure that of the boom up and boom down motion.

Customer Vendor
Witnessed &
Approved by

Date

No Items Description Results Status

Ship Unloader “Crane Confirmation Indicator


1
ON” Lamp ON at Boom Station

Ship Unloader “Crane Confirmation Indicator


2
OFF” Lamp OFF at Boom Station

Ship Unloader Confirmation Indicator


3
“Emergency Stop” Lamp OFF at Boom Station

Boom Up Until Upper Slow


4 Boom Up Slow Down Zone and Confirmed Boom
Slowdown is Activated

Page 2 of 4
Continue Boom Up and
Boom Up Upper and
5 Confirmed End Stop is
stop Activated

Boom Down Until Lower


Boom Down Lower
6 Slow Zone and Confirmed
Slowdown Slowdown is Activated

Continue Boom Down Until


Boom Down Lower
7 Lower End Stop is
End Stop Activated

Brake Test

The purpose of this test is to ensure that all the brakes are able to hold and
or stop a motion.

Customer Vendor
Witnessed &
Approved by
Date

Motion Result Status

Holds Boom Structure Position Estimate 15


Degree Until 30 Degree During 3 Minutes
and Confirm No Slippage Occur

Press E-stop During Lowering at 1 Notch


and Confirm Brakes are Able to Stop
motion

Page 3 of 4
Auxiliary Items

The purpose of this test is to ensure that all the auxiliary items are
functioning and in good condition.
Customer Vendor
Witnessed &
Approved by
Date

Items Location Result Status

Boom Motor Cooling Fan DC Boom Motor

Boom Lubrication Gearbox Boom Gearbox

Boom Unlatch Pylon

Boom Latch Pylon

We hereby agree that the commissioning test is successfully completed and


the ship unloader is performing to the specifications agreed by all party.

1. For PT. PJB

____________________

Name:
Date:

2. For PT. Portek Indonesia

____________________

Name:
Date:

Page 4 of 4