Inversión
Presupuesto Costo Total %Avance
Real de
Cap. Capitulos
Ejecutada Por Ejecutar
1 Resane Y Pinturas Z. C. $ 7,000,000.00 25% 14% $ 980,000.00 $ 6,020,000.00
2 Pintura Pasamanos $ 1,000,000.00 4% 0% $ - $ 1,000,000.00
3 Rampa Entrada $ 800,000.00 3% 0% $ - $ 800,000.00
4 Resane Pintura Fachada $ 8,000,000.00 29% 4% $ 320,000.00 $ 7,680,000.00
5 Lavada Fachada Ladrillo $ 2,000,000.00 7% 0% $ - $ 2,000,000.00
6 Flanches, Fisuras Cubierta $ 1,300,000.00 5% 0% $ - $ 1,300,000.00
7 Lavado Parqueaderos $ 1,000,000.00 4% 0% $ - $ 1,000,000.00
8 Remoción - Jardines $ 2,000,000.00 7% 0% $ - $ 2,000,000.00
9 Muro Motobombas $ 1,000,000.00 4% 0% $ - $ 1,000,000.00
10 Cambio Tejas $ 2,300,000.00 8% 0% $ - $ 2,300,000.00
11 Imp. Ascensores $ 1,000,000.00 4% 0% $ - $ 1,000,000.00
12 Escombros-otros $ 600,000.00 2% 0% $ - $ 600,000.00
TOTAL $ 28,000,000.00 100% 5% $ 1,300,000.00 $ 26,700,000.00
REPORTE FOTOGRÁFICO
Piso 5 Piso 5
Piso 4 Piso 4
REPORTE FOTOGRÁFICO
Luminarias Vacio
Fachada Fachada
Fachada Rampa
Jardines Jardines