Nombre ComúReport no.

Report date Desde* Hasta* MD from (ft)


CHICHIMENE 1 5/14/2019 5/14/2019 ### 31.1
CHICHIMENE 1 5/14/2019 5/14/2019 ### 31.1
CHICHIMENE 1 5/14/2019 5/14/2019 5/15/2019 45
CHICHIMENE 2 5/15/2019 5/15/2019 5/15/2019 0:00:00
CHICHIMENE 2 5/15/2019 5/15/2019 ### 250
CHICHIMENE 2 5/15/2019 5/15/2019 ### 250
CHICHIMENE 2 5/15/2019 5/15/2019 ### 250
CHICHIMENE 2 5/15/2019 5/15/2019 ### 250
CHICHIMENE 2 5/15/2019 5/15/2019 ### 250
CHICHIMENE 2 5/15/2019 5/15/2019 ### 250
CHICHIMENE 2 5/15/2019 5/15/2019 ### 557
CHICHIMENE 2 5/15/2019 5/15/2019 ### 557
CHICHIMENE 2 5/15/2019 5/15/2019 ### 970
CHICHIMENE 2 5/15/2019 5/15/2019 5/16/2019 970
CHICHIMENE 3 5/16/2019 5/16/2019 5/16/2019 0:00:00
CHICHIMENE 3 5/16/2019 5/16/2019 ### 970
CHICHIMENE 3 5/16/2019 5/16/2019 ### 970
CHICHIMENE 3 5/16/2019 5/16/2019 ### 970
CHICHIMENE 3 5/16/2019 5/16/2019 ### 970
CHICHIMENE 3 5/16/2019 5/16/2019 ### 970
CHICHIMENE 3 5/16/2019 5/16/2019 ### 970
CHICHIMENE 3 5/16/2019 5/16/2019 5/17/2019 970
CHICHIMENE 4 5/17/2019 5/17/2019 5/17/2019 0:00:00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 ### 1,810.00
CHICHIMENE 4 5/17/2019 5/17/2019 5/17/2019 0:00:00
CHICHIMENE 4 5/17/2019 5/17/2019 5/18/2019 1,810.00
CHICHIMENE 5 5/18/2019 5/18/2019 ### 1,810.00
CHICHIMENE 5 5/18/2019 5/18/2019 ### 1,810.00
CHICHIMENE 5 5/18/2019 5/18/2019 ### 1,810.00
CHICHIMENE 5 5/18/2019 5/18/2019 ### 1,810.00
CHICHIMENE 5 5/18/2019 5/18/2019 ### 1,810.00
CHICHIMENE 5 5/18/2019 5/18/2019 ### 1,810.00
CHICHIMENE 5 5/18/2019 5/18/2019 ### 1,810.00
CHICHIMENE 5 5/18/2019 5/18/2019 ### 1,810.00
CHICHIMENE 5 5/18/2019 5/18/2019 ### 1,810.00
CHICHIMENE 5 5/18/2019 5/18/2019 5/18/2019 0:00:00
CHICHIMENE 5 5/18/2019 5/18/2019 5/19/2019 1,810.00
CHICHIMENE 6 5/19/2019 5/19/2019 ### 1,810.00
CHICHIMENE 6 5/19/2019 5/19/2019 ### 1,810.00
CHICHIMENE 6 5/19/2019 5/19/2019 ### 1,810.00
CHICHIMENE 6 5/19/2019 5/19/2019 ### 1,810.00
CHICHIMENE 6 5/19/2019 5/19/2019 ### 1,810.00
CHICHIMENE 6 5/19/2019 5/19/2019 ### 1,810.00
CHICHIMENE 6 5/19/2019 5/19/2019 ### 1,810.00
CHICHIMENE 6 5/19/2019 5/19/2019 ### 1,810.00
CHICHIMENE 6 5/19/2019 5/19/2019 ### 1,810.00
CHICHIMENE 6 5/19/2019 5/19/2019 ### 1,810.00
CHICHIMENE 6 5/19/2019 5/19/2019 5/19/2019 0:00:00
CHICHIMENE 6 5/19/2019 5/19/2019 5/20/2019 1,810.00
CHICHIMENE 7 5/20/2019 5/20/2019 ### 1,810.00
CHICHIMENE 7 5/20/2019 5/20/2019 ### 1,810.00
CHICHIMENE 7 5/20/2019 5/20/2019 ### 1,810.00
CHICHIMENE 7 5/20/2019 5/20/2019 ### 1,810.00
CHICHIMENE 7 5/20/2019 5/20/2019 ### 1,810.00
CHICHIMENE 7 5/20/2019 5/20/2019 ### 1,810.00
CHICHIMENE 7 5/20/2019 5/20/2019 ### 1,815.00
CHICHIMENE 7 5/20/2019 5/20/2019 ### 1,815.00
CHICHIMENE 7 5/20/2019 5/20/2019 ### 1,881.00
CHICHIMENE 7 5/20/2019 5/20/2019 ### 1,881.00
CHICHIMENE 7 5/20/2019 5/20/2019 ### 2,070.00
CHICHIMENE 7 5/20/2019 5/20/2019 5/20/2019 0:00:00
CHICHIMENE 7 5/20/2019 5/20/2019 5/21/2019 2,335.00
CHICHIMENE 8 5/21/2019 5/21/2019 ### 2,840.00
CHICHIMENE 8 5/21/2019 5/21/2019 ### 3,590.00
CHICHIMENE 8 5/21/2019 5/21/2019 5/21/2019 4,120.00
CHICHIMENE 8 5/21/2019 5/21/2019 5/22/2019 0:00:00
CHICHIMENE 9 5/22/2019 5/22/2019 5/23/2019 4,470.00
CHICHIMENE 10 5/23/2019 5/23/2019 ### 5,304.00
CHICHIMENE 10 5/23/2019 5/23/2019 ### 5,385.00
CHICHIMENE 10 5/23/2019 5/23/2019 ### 5,385.00
CHICHIMENE 10 5/23/2019 5/23/2019 ### 5,473.00
CHICHIMENE 10 5/23/2019 5/23/2019 ### 5,573.00
CHICHIMENE 10 5/23/2019 5/23/2019 5/23/2019 0:00:00
CHICHIMENE 10 5/23/2019 5/23/2019 5/24/2019 5,855.00
CHICHIMENE 11 5/24/2019 5/24/2019 ### 6,139.00
CHICHIMENE 11 5/24/2019 5/24/2019 5/24/2019 0:00:00
CHICHIMENE 11 5/24/2019 5/24/2019 5/25/2019 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 ### 6,707.00
CHICHIMENE 12 5/25/2019 5/25/2019 5/25/2019 0:00:00
CHICHIMENE 12 5/25/2019 5/25/2019 5/26/2019 6,707.00
CHICHIMENE 13 5/26/2019 5/26/2019 ### 6,741.00
CHICHIMENE 13 5/26/2019 5/26/2019 5/26/2019 0:00:00
CHICHIMENE 13 5/26/2019 5/26/2019 5/27/2019 7,440.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,465.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,465.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,475.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,475.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,475.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,475.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,475.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,475.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,475.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,475.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,475.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,475.00
CHICHIMENE 14 5/27/2019 5/27/2019 ### 7,475.00
CHICHIMENE 14 5/27/2019 5/27/2019 5/27/2019 0:00:00
CHICHIMENE 14 5/27/2019 5/27/2019 5/28/2019 7,475.00
CHICHIMENE 15 5/28/2019 5/28/2019 ### 7,475.00
CHICHIMENE 15 5/28/2019 5/28/2019 ### 7,475.00
CHICHIMENE 15 5/28/2019 5/28/2019 ### 7,475.00
CHICHIMENE 15 5/28/2019 5/28/2019 ### 7,475.00
CHICHIMENE 15 5/28/2019 5/28/2019 ### 7,475.00
CHICHIMENE 15 5/28/2019 5/28/2019 ### 7,475.00
CHICHIMENE 15 5/28/2019 5/28/2019 5/28/2019 7,475.00
CHICHIMENE 15 5/28/2019 5/28/2019 5/29/2019 0:00:00
CHICHIMENE 16 5/29/2019 5/29/2019 5/30/2019 7,777.00
CHICHIMENE 17 5/30/2019 5/30/2019 ### 8,338.00
CHICHIMENE 17 5/30/2019 5/30/2019 ### 8,533.00
CHICHIMENE 17 5/30/2019 5/30/2019 ### 8,533.00
CHICHIMENE 17 5/30/2019 5/30/2019 ### 8,533.00
CHICHIMENE 17 5/30/2019 5/30/2019 ### 8,533.00
CHICHIMENE 17 5/30/2019 5/30/2019 ### 8,533.00
CHICHIMENE 17 5/30/2019 5/30/2019 ### 8,533.00
CHICHIMENE 17 5/30/2019 5/30/2019 ### 8,533.00
CHICHIMENE 17 5/30/2019 5/30/2019 5/30/2019 0:00:00
CHICHIMENE 17 5/30/2019 5/30/2019 5/31/2019 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 ### 8,533.00
CHICHIMENE 18 5/31/2019 5/31/2019 5/31/2019 0:00:00
CHICHIMENE 18 5/31/2019 5/31/2019 6/1/2019 8,533.00
CHICHIMENE 19 6/1/2019 6/1/2019 ### 8,533.00
CHICHIMENE 19 6/1/2019 6/1/2019 ### 8,533.00
CHICHIMENE 19 6/1/2019 6/1/2019 ### 8,533.00
CHICHIMENE 19 6/1/2019 6/1/2019 ### 8,533.00
CHICHIMENE 19 6/1/2019 6/1/2019 ### 8,533.00
CHICHIMENE 19 6/1/2019 6/1/2019 ### 8,533.00
CHICHIMENE 19 6/1/2019 6/1/2019 ### 8,533.00
CHICHIMENE 19 6/1/2019 6/1/2019 ### 8,533.00
CHICHIMENE 19 6/1/2019 6/1/2019 ### 8,533.00
CHICHIMENE 19 6/1/2019 6/1/2019 ### 8,533.00
CHICHIMENE 19 6/1/2019 6/1/2019 6/1/2019 0:00:00
CHICHIMENE 19 6/1/2019 6/1/2019 6/2/2019 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 ### 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 ### 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 ### 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 ### 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 ### 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 ### 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 ### 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 ### 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 ### 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 ### 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 ### 8,533.00
CHICHIMENE 20 6/2/2019 6/2/2019 6/2/2019 0:00:00
CHICHIMENE 20 6/2/2019 6/2/2019 6/3/2019 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 ### 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 ### 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 ### 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 ### 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 ### 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 ### 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 ### 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 ### 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 ### 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 ### 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 ### 8,533.00
CHICHIMENE 21 6/3/2019 6/3/2019 6/3/2019 0:00:00
CHICHIMENE 21 6/3/2019 6/3/2019 6/4/2019 8,533.00
CHICHIMENE 22 6/4/2019 6/4/2019 ### 8,533.00
CHICHIMENE 22 6/4/2019 6/4/2019 ### 8,533.00
CHICHIMENE 22 6/4/2019 6/4/2019 ### 8,533.00
CHICHIMENE 22 6/4/2019 6/4/2019 ### 8,533.00
CHICHIMENE 22 6/4/2019 6/4/2019 ### 8,533.00
CHICHIMENE 22 6/4/2019 6/4/2019 ### 8,533.00
CHICHIMENE 22 6/4/2019 6/4/2019 ### 8,533.00
CHICHIMENE 22 6/4/2019 6/4/2019 ### 8,533.00
CHICHIMENE 22 6/4/2019 6/4/2019 6/4/2019 0:00:00
CHICHIMENE 22 6/4/2019 6/4/2019 6/5/2019 8,533.00
CHICHIMENE 23 6/5/2019 6/5/2019 ### 8,533.00
CHICHIMENE 23 6/5/2019 6/5/2019 ### 8,533.00
CHICHIMENE 23 6/5/2019 6/5/2019 ### 8,533.00
CHICHIMENE 23 6/5/2019 6/5/2019 ### 8,533.00
CHICHIMENE 23 6/5/2019 6/5/2019 ### 8,533.00
CHICHIMENE 23 6/5/2019 6/5/2019 6/5/2019 0:00:00
CHICHIMENE 23 6/5/2019 6/5/2019 6/6/2019 8,533.00
CHICHIMENE 24 6/6/2019 6/6/2019 ### 8,533.00
CHICHIMENE 24 6/6/2019 6/6/2019 ### 8,533.00
CHICHIMENE 24 6/6/2019 6/6/2019 ### 8,540.00
CHICHIMENE 24 6/6/2019 6/6/2019 ### 8,540.00
CHICHIMENE 24 6/6/2019 6/6/2019 ### 8,540.00
CHICHIMENE 24 6/6/2019 6/6/2019 ### 8,540.00
CHICHIMENE 24 6/6/2019 6/6/2019 ### 8,540.00
CHICHIMENE 24 6/6/2019 6/6/2019 ### 8,540.00
CHICHIMENE 24 6/6/2019 6/6/2019 ### 8,540.00
CHICHIMENE 24 6/6/2019 6/6/2019 ### 8,608.00
CHICHIMENE 24 6/6/2019 6/6/2019 6/6/2019 0:00:00
CHICHIMENE 24 6/6/2019 6/6/2019 6/7/2019 8,608.00
CHICHIMENE 25 6/7/2019 6/7/2019 ### 8,732.00
CHICHIMENE 25 6/7/2019 6/7/2019 ### 8,920.00
CHICHIMENE 25 6/7/2019 6/7/2019 ### 9,070.00
CHICHIMENE 25 6/7/2019 6/7/2019 ### 9,070.00
CHICHIMENE 25 6/7/2019 6/7/2019 ### 9,070.00
CHICHIMENE 25 6/7/2019 6/7/2019 6/7/2019 0:00:00
CHICHIMENE 25 6/7/2019 6/7/2019 6/8/2019 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 ### 9,070.00
CHICHIMENE 26 6/8/2019 6/8/2019 6/8/2019 0:00:00
CHICHIMENE 26 6/8/2019 6/8/2019 6/9/2019 9,070.00
CHICHIMENE 27 6/9/2019 6/9/2019 ### 9,070.00
CHICHIMENE 27 6/9/2019 6/9/2019 ### 9,070.00
CHICHIMENE 27 6/9/2019 6/9/2019 ### 9,070.00
CHICHIMENE 27 6/9/2019 6/9/2019 ### 9,070.00
CHICHIMENE 27 6/9/2019 6/9/2019 ### 9,070.00
CHICHIMENE 27 6/9/2019 6/9/2019 ### 9,070.00
CHICHIMENE 27 6/9/2019 6/9/2019 ### 9,070.00
CHICHIMENE 27 6/9/2019 6/9/2019 ### 9,070.00
CHICHIMENE 27 6/9/2019 6/9/2019 ### 9,070.00
CHICHIMENE 27 6/9/2019 6/9/2019 ### 9,070.00
CHICHIMENE 27 6/9/2019 6/9/2019 6/9/2019 0:00:00
CHICHIMENE 27 6/9/2019 6/9/2019 6/10/2019 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 ### 9,070.00
CHICHIMENE 28 6/10/2019 6/10/2019 6/10/2019 0:00:00
CHICHIMENE 28 6/10/2019 6/10/2019 6/11/2019 9,070.00
CHICHIMENE 29 6/11/2019 6/11/2019 ### 9,070.00
CHICHIMENE 29 6/11/2019 6/11/2019 ### 9,070.00
CHICHIMENE 29 6/11/2019 6/11/2019 ### 9,070.00
CHICHIMENE 29 6/11/2019 6/11/2019 ### 9,070.00
CHICHIMENE 29 6/11/2019 6/11/2019 ### 9,070.00
CHICHIMENE 29 6/11/2019 6/11/2019 ### 9,070.00
CHICHIMENE 29 6/11/2019 6/11/2019 ### 9,070.00
CHICHIMENE 29 6/11/2019 6/11/2019 ### 9,070.00
CHICHIMENE 29 6/11/2019 ### ### 9,070.00
CHICHIMENE 29 6/11/2019 ### 6/12/2019 9,070.00
MD to (ft) Profundidad Siglas del Ev Duración (hr)P/N* Tipo de NPT Descripción Código*
1/30/1900 0:00:00 ODR 1P Charla de Seg 1700
2/13/1900 0:00:00 ODR 0.5 P Bajando BHA D 1100
5/10/1900 131 ODR 4.5 P Perforando R 1400
250 250 ODR 4P Perforando R 1400
9/6/1900 0:00:00 ODR 0.5 P Circulando (H 1500
9/6/1900 0:00:00 ODR 1P Quebrando B 1400
9/6/1900 0:00:00 ODR 0.5 P Charla de Seg 1700
9/6/1900 0:00:00 ODR 2.5 P Armando BH 1400
9/6/1900 0:00:00 ODR 0.5 P Bajando BHA D 1100
7/10/1901 0:00:00 ODR 5P Perforando R 1400
7/10/1901 0:00:00 ODR 0.5 N WAIT Esperando po 1900
8/27/1902 0:00:00 ODR 8P Perforando R 1400
8/27/1902 0:00:00 ODR 0.5 N DEFAL Circulando (H 1500
8/27/1902 276 ODR 1N DEFAL Sacando BHA D 1100
970 90 ODR 0.5 N DEFAL Sacando BHA D 1100
8/27/1902 0:00:00 ODR 0.5 N DEFAL Charla de Seg 1700
8/27/1902 0:00:00 ODR 4N DEFAL Quebrando B 1400
8/27/1902 0:00:00 ODR 0.5 N DEFAL Charla de Seg 1700
8/27/1902 0:00:00 ODR 3N DEFAL Armando BH 1400
8/27/1902 0:00:00 ODR 1N DEFAL Bajando BHA D 1100
8/27/1902 0:00:00 ODR 0.5 N DEFAL Bajando BHA D 1100
12/14/1904 1,810.00 ODR 14.00 P Perforando R 1400
1,810.00 1,810.00 ODR 0.50 P Circulando (H 1500
12/14/1904 0:00:00 ODR 2.50 P Sacando BHA D 1100
12/14/1904 0:00:00 ODR 0.50 P Circulando (H 1500
12/14/1904 0:00:00 ODR 0.50 P Bajando BHA 1100
12/14/1904 0:00:00 ODR 0.50 P Circulando (H 1500
12/14/1904 0:00:00 ODR 3.00 P Sacando BHA D 1100
12/14/1904 0:00:00 ODR 1.00 P Sacando BHA D 1100
12/14/1904 0:00:00 ODR 0.50 P Charla de Seg 1700
12/14/1904 0:00:00 ODR 1.50 P Quebrando B 1400
12/14/1904 0:00:00 ODR 0.50 P Rig Service 1300
12/14/1904 0:00:00 ODR 2.00 P Drenando Co 1300
12/14/1904 0:00:00 ODR 0.50 P Charla de Seg 1700
12/14/1904 0:00:00 ODR 0.50 P Armar Colgado 1200
12/14/1904 0:00:00 ODR 1.00 P Bajar Casing / 1200
12/14/1904 0:00:00 ODR 5.00 P Bajar Casing / 1200
12/14/1904 0:00:00 ODR 0.50 P Desinstalar E 1200
12/14/1904 0:00:00 ODR 0.50 P Instalar Equ 1200
12/14/1904 0:00:00 ODR 1.00 P Circulando (H 1500
12/14/1904 1,805.00 ODR 0.50 P Instalar/Desi 1000
1,810.00 1,805.00 ODR 1P Instalar/Desi 1000
12/14/1904 0:00:00 ODR 0.50 P Charla de Seg 1700
12/14/1904 0:00:00 ODR 0.50 P Instalar Equi 2100
12/14/1904 0:00:00 ODR 3.50 P Cementación 2100
12/14/1904 0:00:00 ODR 1.00 P Desinstalar E 1200
12/14/1904 0:00:00 ODR 1.00 P Cortar Bisela 1000
12/14/1904 0:00:00 ODR 2.00 P Drenando Co 1300
12/14/1904 0:00:00 ODR 1.50 P Instalar / De 1000
12/14/1904 0:00:00 ODR 0.50 P Charla de Seg 1700
12/14/1904 0:00:00 ODR 8.00 P Instalar de P 1000
12/14/1904 0.00 ODR 3.5 N RIG Preventive M 2500
1,810.00 0.00 ODR 0.5 P Instalar / De 1000
12/14/1904 0:00:00 ODR 2.00 P Parando tuber 1300
12/14/1904 0:00:00 ODR 2.50 P Parando tuber 1300
12/14/1904 0:00:00 ODR 1.00 N WAIT Esperando po 1900
12/14/1904 0:00:00 ODR 2.50 P Parando tuber 1300
12/14/1904 0:00:00 ODR 5.00 N RIG Falla/Repara 1900
12/14/1904 0:00:00 ODR 2.50 P Parando tuber 1300
12/14/1904 0:00:00 ODR 0.50 P Charla de Seg 1700
12/14/1904 0:00:00 ODR 3.00 P Armando BH 1400
12/14/1904 0:00:00 ODR 1.00 P Bajando BHA D 1100
12/14/1904 0:00:00 ODR 3.00 N WAIT Esperando po 1900
12/14/1904 191.00 ODR 1N RIG Falla/Repara 1900
1,810.00 191.00 ODR 1N DEFAL Falla/Reparac 1900
12/14/1904 0:00:00 ODR 1.00 P Bajando BHA D 1100
12/14/1904 0:00:00 ODR 1.00 P Levantando y 1400
12/14/1904 0:00:00 ODR 1.00 P Bajando BHA D 1100
12/14/1904 0:00:00 ODR 1.50 P Bajando BHA D 1100
12/14/1904 0:00:00 ODR 3.50 P Moliendo Cem 1400
12/14/1904 0:00:00 ODR 0.50 P Desplazamien 1500
12/19/1904 0:00:00 ODR 0.50 P Perforando R 1400
12/19/1904 0:00:00 ODR 0.50 P Prueba de In 2000
2/23/1905 0:00:00 ODR 0.50 P Perforando R 1400
2/23/1905 0:00:00 ODR 1.00 N DEFAL Falla/Reparac 1900
8/31/1905 0:00:00 ODR 1.50 P Perforando R 1400
8/31/1905 2,070.00 ODR 1.00 N WAIT Esperando po 1900
2,335.00 2,335.00 ODR 3.00 P Perforando R 1400
10/10/1907 0:00:00 ODR 8.50 P Perforando R 1400
10/29/1909 0:00:00 ODR 10.00 P Perforando R 1400
4/12/1911 4,120.00 ODR 9.00 P Perforando R 1400
4,425.00 4,425.00 ODR 4P Perforando R 1400
4,470.00 4,470.00 ODR 1.00 P Perforando R 1400
7/9/1914 0:00:00 ODR 24.00 P Perforando R 1400
9/28/1914 0:00:00 ODR 3.50 P Perforando R 1400
9/28/1914 0:00:00 ODR 1.00 N WAIT Esperando po 1900
12/25/1914 0:00:00 ODR 4.00 P Perforando R 1400
4/4/1915 0:00:00 ODR 5.00 P Perforando R 1400
1/11/1916 5,855.00 ODR 5.00 P Perforando R 1400
5,855.00 5,585.00 ODR 1.50 P Circulando (H 1500
10/21/1916 0:00:00 ODR 4.00 P Perforando R 1400
5/12/1918 6,707.00 ODR 20.00 P Perforando R 1400
6,707.00 6,707.00 ODR 2.00 P Circulando (H 1500
5/12/1918 0:00:00 ODR 2.00 P Sacando BHA D 1100
5/12/1918 0:00:00 ODR 0.50 P Circulando (H 1500
5/12/1918 0:00:00 ODR 5.00 P Sacando BHA D 1100
5/12/1918 0:00:00 ODR 0.50 P Circulando (H 1500
5/12/1918 0:00:00 ODR 1.00 P Sacando BHA D 1100
5/12/1918 0:00:00 ODR 1.00 P Sacando BHA D 1100
5/12/1918 14:24:00 ODR 1.50 P Sacando BHA D 1100
5/12/1918 14:24:00 ODR 0.50 P Charla de Seg 1700
5/12/1918 0:00:00 ODR 0.50 P Quebrando B 1400
5/12/1918 0:00:00 ODR 1.00 P Armando BH 1400
5/12/1918 0:00:00 ODR 1.00 P Bajando BHA D 1100
5/12/1918 0:00:00 ODR 1.00 P Bajando BHA D 1100
5/12/1918 0:00:00 ODR 0.50 P Rig Service 1300
5/12/1918 0:00:00 ODR 1.00 N RIG Falla/Repara 1900
5/12/1918 0:00:00 ODR 2.50 P Bajando BHA D 1100
5/12/1918 3,979.00 ODR 1.00 P Circulando (H 1500
6,707.00 6,707.00 ODR 3.00 P Bajando BHA D 1100
6/15/1918 0:00:00 ODR 2.50 P Perforando R 1400
5/20/1919 7,080.00 ODR 12.00 P Perforando R 1400
7,440.00 7,440.00 ODR 11.00 P Perforando R 1400
6/8/1920 0:00:00 ODR 1.00 P Perforando R 1400
6/8/1920 0:00:00 ODR 1.00 P Prueba de Lín 2000
6/18/1920 0:00:00 ODR 1.00 P Perforando R 1400
6/18/1920 0:00:00 ODR 1.00 N DEFAL Acondicionam 1500
6/18/1920 0:00:00 ODR 1.00 N DEFAL Circulando (H 1500
6/18/1920 0:00:00 ODR 3.50 N DEFAL Sacando BHA D 1100
6/18/1920 0:00:00 ODR 1.00 N DEFAL Acondicionam 1500
6/18/1920 0:00:00 ODR 4.50 N DEFAL Sacando BHA D 1100
6/18/1920 0:00:00 ODR 1.00 N WAIT Esperando po 1900
6/18/1920 0:00:00 ODR 1.50 N DEFAL Sacando BHA D 1100
6/18/1920 14:24:00 ODR 1.00 N DEFAL Sacando BHA D 1100
6/18/1920 14:24:00 ODR 0.50 N DEFAL Charla de Seg 1700
6/18/1920 0:00:00 ODR 2.50 N DEFAL Quebrando He 1400
6/18/1920 97.00 ODR 2.50 N DEFAL Armando BH 1400
7,475.00 649.00 ODR 1.00 N DEFAL Bajando BHA D 1100
6/18/1920 0:00:00 ODR 1.00 N DEFAL Bajando BHA D 1100
6/18/1920 0:00:00 ODR 1.50 N DEFAL Correr-Cortar 1300
6/18/1920 0:00:00 ODR 1.00 N DEFAL Instalar / Eq 1300
6/18/1920 0:00:00 ODR 2.00 N DEFAL Rig Service 1300
6/18/1920 0:00:00 ODR 1.00 N DEFAL Circulando (H 1500
6/18/1920 0:00:00 ODR 4.00 N DEFAL Bajando BHA D 1100
6/18/1920 7,475.00 ODR 1.50 P Acondicionam 1500
7,615.00 7,615.00 ODR 5P Perforando R 1400
7,777.00 7,777.00 ODR 8.00 P Perforando R 1400
10/29/1922 0:00:00 ODR 24.00 P Perforando R 1400
5/12/1923 0:00:00 ODR 10.00 P Perforando R 1400
5/12/1923 0:00:00 ODR 1.00 P Circulando (H 1500
5/12/1923 0:00:00 ODR 2.50 P Circulando (H 1500
5/12/1923 0:00:00 ODR 0.50 P Sacando BHA D 1100
5/12/1923 0:00:00 ODR 0.50 P Bajando BHA D 1100
5/12/1923 0:00:00 ODR 2.00 P Sacando BHA D 1100
5/12/1923 0:00:00 ODR 1.00 P Circulando (H 1500
5/12/1923 7,746.00 ODR 0.50 P Sacando BHA D 1100
8,533.00 7,711.00 ODR 3.00 N WAIT Esperando po 1900
5/12/1923 0:00:00 ODR 3.00 P Sacando BHA D 1100
5/12/1923 0:00:00 ODR 1.00 P Circulando (H 1500
5/12/1923 0:00:00 ODR 3.50 P Sacando BHA D 1100
5/12/1923 0:00:00 ODR 0.50 P Circulando (H 1500
5/12/1923 0:00:00 ODR 2.00 P Sacando BHA D 1100
5/12/1923 0:00:00 ODR 0.50 P Acondicionam 1500
5/12/1923 0:00:00 ODR 1.50 P Sacando BHA D 1100
5/12/1923 0:00:00 ODR 1.00 P Sacando BHA D 1100
5/12/1923 0:00:00 ODR 0.50 P Charla de Seg 1700
5/12/1923 0:00:00 ODR 2.00 P Quebrando B 1400
5/12/1923 0:00:00 ODR 0.50 P Instalar / De 1000
5/12/1923 0:00:00 ODR 0.50 P Rig Service 1300
5/12/1923 0:00:00 ODR 0.50 P Charla de Seg 1700
5/12/1923 0.00 ODR 1.50 P Instalar Equ 1200
8,533.00 0.00 ODR 0.50 P Charla de Seg 1700
5/12/1923 0:00:00 ODR 8.00 P Bajar Casing / 1200
5/12/1923 0:00:00 ODR 0.50 P Circulando (H 1500
5/12/1923 0:00:00 ODR 2.00 P Bajar Casing / 1200
5/12/1923 0:00:00 ODR 1.00 P Circulando (H 1500
5/12/1923 0:00:00 ODR 5.50 P Bajar Casing / 1200
5/12/1923 0:00:00 ODR 1.50 N WAIT Esperando po 1900
5/12/1923 0:00:00 ODR 2.00 P Bajar Casing / 1200
5/12/1923 0:00:00 ODR 1.00 P Circulando (H 1500
5/12/1923 0:00:00 ODR 1.00 P Bajar Casing / 1200
5/12/1923 0:00:00 ODR 1.00 P Circulando (H 1500
5/12/1923 8,360.00 ODR 4.00 P Bajar Casing / 1200
8,533.00 8,360.00 ODR 1.00 P Circulando (H 1500
5/12/1923 0:00:00 ODR 3.50 P Bajar Casing / 1200
5/12/1923 0:00:00 ODR 7.50 P Bajar Casing / 1200
5/12/1923 0:00:00 ODR 3.00 P Bajar Casing / 1200
5/12/1923 0:00:00 ODR 2.50 P Circulando (H 1500
5/12/1923 0:00:00 ODR 0.50 P Charla de Seg 1700
5/12/1923 0:00:00 ODR 1.00 P Circulando (H 1500
5/12/1923 0:00:00 ODR 0.50 P Instalar Equi 2100
5/12/1923 0:00:00 ODR 1.00 P Cementación 2100
5/12/1923 0:00:00 ODR 3.00 P Cementación 2100
5/12/1923 0:00:00 ODR 1.00 P Desinstalar 2100
5/12/1923 0:00:00 ODR 0.50 P Desinstalar / 1300
5/12/1923 0.00 ODR 0.5 P Charla de Seg 1700
8,533.00 0.00 ODR 2.5 P Instalar / De 1000
5/12/1923 0:00:00 ODR 0.50 N WAIT Esperando po 1900
5/12/1923 0:00:00 ODR 3.50 N WAIT Esperando po 1900
5/12/1923 0:00:00 ODR 1.50 P Drenando Co 1300
5/12/1923 0:00:00 ODR 1.00 P Colgando Rev 1000
5/12/1923 0:00:00 ODR 2.00 P Cortar Bisela 1000
5/12/1923 0:00:00 ODR 0.50 P Desinstalar P 1000
5/12/1923 0:00:00 ODR 2.00 P Instalar / De 1000
5/12/1923 0:00:00 ODR 0.50 P Instalar de P 1000
5/12/1923 0:00:00 ODR 1.50 P Prueba de Pr 1000
5/12/1923 0:00:00 ODR 0.50 P Instalar / De 1000
5/12/1923 0:00:00 ODR 0.50 P Charla de Seg 1700
5/12/1923 0.00 ODR 1P Desinstalar E 1200
8,533.00 0.00 ODR 0.5 P Charla de Seg 1700
5/12/1923 0:00:00 ODR 9.00 P Instalar / Eq 1300
5/12/1923 0:00:00 ODR 3.50 P Instalar / Eq 1300
5/12/1923 0:00:00 ODR 1.50 P Instalar / Eq 1300
5/12/1923 0:00:00 ODR 0.50 P Parada de Se 1700
5/12/1923 0:00:00 ODR 0.50 P Instalar / Eq 1300
5/12/1923 0:00:00 ODR 3.00 P Armando BH 1400
5/12/1923 0:00:00 ODR 1.00 N RIG Mantenimiento 1500
5/12/1923 0:00:00 ODR 2.50 P Bajando BHA D 1100
5/12/1923 2,867.00 ODR 9.50 N RIG Mantenimiento 1500
8,533.00 2,867.00 ODR 0.50 N WAIT Esperando po 1900
5/12/1923 0:00:00 ODR 1.50 N RIG Mantenimiento 1500
5/12/1923 0:00:00 ODR 1.00 N FLUID Mantenimiento 1500
5/12/1923 0:00:00 ODR 4.00 P Bajando BHA D 1100
5/12/1923 0:00:00 ODR 2.50 P Bajando BHA D 1100
5/12/1923 0:00:00 ODR 0.50 P Acondicionam 1500
5/12/1923 8,433.00 ODR 12.00 N SFAL Falla/Repara 1900
8,533.00 8,433.00 ODR 0.50 P Charla de Seg 1700
5/12/1923 0:00:00 ODR 3.50 P Moliendo Cem 1400
5/12/1923 0:00:00 ODR 1.00 P Moliendo Cem 1400
5/19/1923 0:00:00 ODR 0.50 P Perforando R 1400
5/19/1923 0:00:00 ODR 0.50 P Circulando (H 1500
5/19/1923 0:00:00 ODR 0.50 P Prueba de Inf 1500
5/19/1923 0:00:00 ODR 0.50 P Charla de Seg 1700
5/19/1923 0:00:00 ODR 1.00 P Sacando BHA D 1100
5/19/1923 0:00:00 ODR 1.00 P Bajando BHA D 1100
5/19/1923 0:00:00 ODR 2.00 P Desplazamien 1500
7/26/1923 0:00:00 ODR 7.00 P Perforando R 1400
7/26/1923 8,608.00 ODR 0.50 N SFAL Falla/Repara 1900
8,608.00 8,608.00 ODR 0.50 N SFAL Falla/Repara 1900
11/27/1923 0:00:00 ODR 9.00 P Perforando R 1400
6/2/1924 0:00:00 ODR 9.50 P Perforando R 1400
10/30/1924 0:00:00 ODR 7.00 P Perforando R 1400
10/30/1924 0:00:00 ODR 2.00 P Circulando (H 1500
10/30/1924 0:00:00 ODR 1.00 P Sacando BHA D 1100
10/30/1924 9,070.00 ODR 2.00 P Bajando BHA D 1100
9,070.00 9,070.00 ODR 2.00 P Circulando (H 1500
10/30/1924 0:00:00 ODR 0.50 P Circulando (H 1500
10/30/1924 0:00:00 ODR 0.50 P Circulando (H 1500
10/30/1924 0:00:00 ODR 0.50 P Sacando BHA D 1100
10/30/1924 0:00:00 ODR 0.50 P Charla de Seg 1700
10/30/1924 0:00:00 ODR 1.00 P Desinstalar / 1300
10/30/1924 0:00:00 ODR 1.00 P Instalar / Eq 1300
10/30/1924 0:00:00 ODR 7.50 P Sacando BHA D 1100
10/30/1924 0:00:00 ODR 2.50 P Quebrando B 1400
10/30/1924 0:00:00 ODR 0.50 P Charla de Seg 1700
10/30/1924 0:00:00 ODR 2.00 P Tomando Regi 1800
10/30/1924 0:00:00 ODR 1.50 P Tomando Regi 1800
10/30/1924 0:00:00 ODR 1.00 P Tomando Regi 1800
10/30/1924 0:00:00 ODR 1.00 P POOH Herrami 1800
10/30/1924 0:00:00 ODR 1.00 P Desinstalar E 1800
10/30/1924 0.00 ODR 1.50 P Instalar / De 1800
9,070.00 9,070.00 ODR 1.00 P Bajando herr 1800
10/30/1924 0:00:00 ODR 1.00 P Tomando Regi 1800
10/30/1924 0:00:00 ODR 7.00 P Tomando Regi 1800
10/30/1924 0:00:00 ODR 1.00 P POOH Herrami 1800
10/30/1924 0:00:00 ODR 1.00 P Desinstalar E 1800
10/30/1924 0:00:00 ODR 0.50 P Instalar Equ 1200
10/30/1924 0:00:00 ODR 0.50 P Charla de Seg 1700
10/30/1924 0:00:00 ODR 1.00 P Instalar Equ 1200
10/30/1924 0:00:00 ODR 0.50 P Charla de Seg 1700
10/30/1924 0:00:00 ODR 2.50 P Bajar Casing / 1200
10/30/1924 0:00:00 ODR 0.50 P Charla de Seg 1700
10/30/1924 745.00 ODR 0.50 P Armar Colgado 1200
9,070.00 745.00 ODR 0.50 P Desinstalar E 1200
10/30/1924 0:00:00 ODR 8.50 P Bajar Casing / 1200
10/30/1924 0:00:00 ODR 5.00 P Bajar Casing / 1200
10/30/1924 0:00:00 ODR 1.00 P Charla de Seg 1700
10/30/1924 0:00:00 ODR 0.50 P Bajar Casing / 1200
10/30/1924 0:00:00 ODR 2.50 P Bajar Casing / 1200
10/30/1924 0:00:00 ODR 0.50 P Circulando (H 1500
10/30/1924 0:00:00 ODR 0.50 P Instalar Equi 2100
10/30/1924 0:00:00 ODR 3.50 P Circulando (H 1500
10/30/1924 0:00:00 ODR 1.50 P Circulando (H 1500
10/30/1924 0:00:00 ODR 0.50 P Cementación 2100
10/30/1924 0:00:00 ODR 1.50 P Circulando (H 1500
10/30/1924 0:00:00 ODR 0.50 P Desinstalar 2100
10/30/1924 7,971.00 ODR 0.50 P Quebrando B 1400
9,070.00 7,971.00 ODR 0.5 P Charla de Seg 1700
10/30/1924 0:00:00 ODR 1.00 P Quebrando B 1400
10/30/1924 0:00:00 ODR 0.50 P Quebrando B 1400
10/30/1924 0:00:00 ODR 5.00 P Quebrando B 1400
10/30/1924 0:00:00 ODR 1.00 P Quebrando B 1400
10/30/1924 0:00:00 ODR 0.50 P Charla de Seg 1700
10/30/1924 0:00:00 ODR 5.00 P Quebrando Tu 1300
10/30/1924 0:00:00 ODR 4.00 P Quebrando Tu 1300
10/30/1924 0:00:00 ODR 5.00 N RIG Quebrando Tu 1300
10/30/1924 0.00 ODR 1P Quebrando Tu 1300
9,070.00 0 ODR 0.5 P Charla de Seg 1700
9,070.00 0 ODR 1.5 P Correr-Cortar 1300
Subcódigo* Operación*
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA DAR INICIO A LAS OPERACIONES DEL CHICHIMENE 2
1110 BAJÓ BHA N.1 DESDE SUPERFICIE, TOCÓ Y VERIFICÓ FONDO DE TUBO CONDUCTOR A 45 FT. REVISÓ FUNCIO
1406 PERFORÓ FASE 17 ½” FORMACIÓN GUAYABO CON BHA N. 1 CONVENCIONAL DESDE 45 FT HASTA 131 FT, (AVANCE
1406 PERFORÓ FASE 17 ½” FORMACIÓN GUAYABO CON BHA N. 1 CONVENCIONAL DESDE 131 FT HASTA 250 FT, (AVANC
1503 A 250 FT CIRCULÓ POZO FONDOS HASTA RETORNOS LIMPIOS RECIPROCANDO SARTA CON Q: 380 GPM, SPP: 160
1402 SACÓ Y QUEBRÓ BHA N.1 CONVENCIONAL DESDE 250 FT HASTA SUPERFICIE ASÍ: (6) HWDP 5 1/2" + CROSS OVER
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA ARME DE BHA N. 2 DIRECCIONAL POR PARTE DE WE
1401 ARMÓ Y BAJÓ BHA N. 2 DIRECCIONAL DESDE SUPERFICIE HASTA 90 FT ASÍ: BROCA N.2U PDC 17½" (NOV, TIPO: TF
1110 BAJÓ BHA N. 2 DIRECCIONAL DESDE 90 FT HASTA 250 FT ASÍ: (1) DC 8" + X-OVER (6?" REG PIN - XT 54 BOX) + (5) H
1407 PERFORÓ FASE 17 ½" CON BHA N.2 DIRECCIONAL EN FORMACIÓN GUAYABO DESDE 250 FT HASTA 557 FT. (AVAN
1905 SUSPENDIÓ OPERACIÓN DEBIDO A TORMENTA ELÉCTRICA NIVEL III, A 557 FT CIRCULÓ POZO CON Q: 550 GPM, SP
1407 PERFORÓ FASE 17½" CON BHA N. 2 DIRECCIONAL EN FORMACIÓN GUAYABO, ROTANDO Y DESLIZANDO DESDE 55
1503 A 970 FT CIRCULÓ HASTA RETORNOS LIMPIOS RECIPROCANDO SARTA CON Q: 780 GPM, SPP: 980 PSI, RPM: 50, TQ
1107 SACÓ DP PE 5 1/2" + BHA N. 2 DIRECCIONAL LIBRE DESDE 970 FT HASTA 276 FT (TOPE DEL BHA).
1107 SACÓ DP 5 1/2" + BHA N. 2 DIRECCIONAL DESDE 276 FT HASTA 90 FT. ASI: 5 HWDP 5 1/2 IN + CROSSOVER+ 1 DC
1701 REALIZÓ REUNIÒN PREOPERACIONAL Y DE SEGURIDAD PARA QUEBRAR BHA N. 2 DIRECCIONAL
1402 SACÓ Y QUEBRÓ BHA N. 2 DIRECCIONAL DESDE 90 FT HASTA SUPERFICIE. ASI:NMDC 8 IN + EMITTING SUB 8 IN +
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA ARME DE BHA N. 3 DIRECCIONAL POR PARTE DE WE
1401 ARMÓ Y BAJÓ BHA N. 3 DIRECCIONAL DESDE SUPERFICIE HASTA 94 FT ASÍ: BROCA #3U PDC 17½" (VAREL, TIPO: V
1110 BAJÓ BHA N. 3 DIRECCIONAL DESDE 94 FT HASTA 280 FT ASÍ: (1) DC 8" + X-OVER (6?" REG PIN - XT 54 BOX) + (5) H
1110 BAJÓ DP 5½" + BHA N. 3 DIRECCIONAL DESDE 280 FT HASTA 970 FT, BAJÓ LAVANDO POR SEGURIDAD LA ULTIMA
1407 'PERFORÓ FASE 17½" CON BHA N. 3 DIRECCIONAL EN FORMACIÓN GUAYABO, DESDE 970 FT HASTA 1810 FT, ROP
1503 A 1810 FT BOMBEÓ 30 BBLS DE PÍLDORA VISCOSA DE 10.7 PPG, 180 SG/GT Y CIRCULÓ CON Q: 780 GPM, SPP: 10
1107 SACÓ DP 5 1/2 " + BHA N. 3 DIRECCIONAL DESDE 1810 FT HASTA 971 FT ASÍ: - LIBRE DESDE 1810 FT HASTA 1720
1503 A 971 FT CIRCULÓ POZO RECIPROCANDO SARTA HASTA OBTENER RETORNOS LIMPIOS CON Q: 800 GPM, SPP: 105
1111 BAJÓ DP 5 1/2" + BHA N. 3 DIRECCIONAL LIBRE DESDE 971 FT HASTA 1810 FT BAJÓ LAVANDO POR SEGURIDAD D
1503 A 1810 FT BOMBEÓ 30 BBLS DE PÍLDORA VISCOSA DE 10.7 PPG, 180 SG/GT FT Y CIRCULÓ CON Q: 800 GPM, SPP:
1107 SACÓ DP 5½" + BHA N. 3 DIRECCIONAL DESDE 1810 FT HASTA 280 FT ASI: - LIBRE DESDE 1810 FT HASTA 1715 FT N
1107 SACÓ BHA N° 3 DIRECCIONAL DESDE 280 FT HASTA 94 FT. ASI: 5 HWDP 5½" + X-OVER (6?" REG PIN - XT 54 BOX) +
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA QUEBRAR BHA N. 2 DIRECCIONAL
1402 SACÓ BHA N. 3 DIRECCIONAL DESDE 94 FT HASTA SUPERFICIE, ASI: NMDC 8" + EMITTING SUB 8" + TOOL CARRIER
1308 REALIZÓ RIG SERVICE, ENGRASÓ BLOQUE VIAJERO, WASH PIPE Y TOP DRIVE
1306 REALIZÓ ACTIVIDADES DE ADECUACIÓN(ACHIQUE) Y LIMPIEZA DE CONTRAPOZO .
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA R/UP Y CORRIDA DE REVESTIMIENTO 13?"
1202 REALIZÓ ARME DE HERRAMIENTAS Y EQUIPOS PARA MANEJO DE REVESTIMIENTO 13?"
1206 CONECTÓ JUNTA N.1 DE REVESTIMIENTO DE 13 3/8" (K55, 54.5 LB/FT, BTC) AL FLOAT SHOE, APLICÓ SOLDADURA L
1206 BAJÓ REVESTIMIENTO 13?" (K-55, 54.5 LB/FT, BTC) DESDE 89 FT HASTA 1805 FT ROMPIÓ CIRCULACIÓN A 526 FT C
1205 RIG DOWN DE HERRAMIENTAS DE CORRIDA DE CASING DE 13 3/8” POR PARTE DE ITS
1204 RIG UP DE CABEZA Y LINEAS DE CEMENTACIÓN POR PARTE DE HALLIBURTON CEMENTACIÓN
1503 A 1805 FT CIRCULÓ POZO CON Q: 380 GPM, SPP: 270 PSI.
1006 LIMPIÓ CONTRAPOZO Y TENSIONÓ EL REVESTIMIENTO DE 13 3/8" CON 110 KLB DE PESO SUBIENDO.
1006 INSTALÓ BASE PLATE + HANGIND PLATE EN TUBO CONDUCTOR DE 20" POR PARTE DE FEPCO
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA REALIZAR TRABAJO DE CEMENTACIÓN DE REVESTIM
2101 REALIZÓ PRUEBA DE LÍNEAS DE CEMENTACIÓN CON 500 Y 3200 PSI X 5 MINUTOS, OK.
2104 REALIZÓ TRABAJO DE CEMENTACIÓN DEL REVESTIMIENTO DE 13 3/8", SEGÚN PROGRAMA ASÍ: - LIBERÓ BOTTOM
1205 RIG DOWN DE CABEZA Y LÍNEAS Y CABEZA DE CEMENTACIÓN POR PARTE DE HALLIBURTON.
1007 CORTE EN FRIO Y BISELÓ REVESTIMIENTO DE 13 3/8" CSG - FEPCO.
1306 RETIRÓ MANGUERAS, LÍNEAS, BOMBA GOORMAN Y CHUPADOR. RETIRÓ RAT HOLE. ACHICÓ Y LIMPIÓ CONTRAPO
1005 INSTALÓ CABEZAL DE 11X3K (FEPCO) Y PROBÓ SELLOS CON 800 PSI X 10 MIN, OK.
1701 REALIZÓ REUNIÓN PRE OPERACIONAL Y DE SEGURIDAD PARA INSTALACIÓN DE BOP'S 13 3/8"
1001 *INSTALÓ ADAPTER 13?"-10 K x 13 5/8K"-3K + SPOOL ADAPTER DE 13 5/8" 10 K X 13 5/8" 10K * POSICIONÓ SET
2501 MANTENIMIENTO PREVENTIVO MALACATE, SISTEMA DE BANDAS Y FRENOS.
1003 BAJÓ HERRAMIENTA INSTALÓ WEAR BUSHING. SACO HERRAMIENTA DE CORRIDA
1301 PARÓ DE LOS RACK A LA TORRE 21 JUNTAS DP 5 1/2" XT-54 , TOTAL DE PARADAS EN LA TORRE : 7
1301 PARÓ DE LOS RACK A LA TORRE 39 JUNTAS DP 5 1/2" XT-54.
1905 SUSPENDIÓ ACTIVIDADES POR ALERTA DE TORMENTA NIVEL III
1301 PARÓ DE LOS RACK A LA TORRE 25 JUNTAS DP 5 1/2" XT-54.
1916 REPARACIÓN DE MALACATE, FALLA DE ESLABÓN DE LA CADENA. SE CAMBIÓ SECCIÓN DE LA CADENA DEL EJE D
1301 CONTINUE LEVANTANDO DE LOS RACK A LA TORRE 32 JUNTAS DP 5 1/2" XT-54 - ADICIONAL PARADAS 40 Y TOTA
1701 REUNIÓN PREOPERACIONAL Y SEGURIDAD PARA ARME DE BHA N .4 DIRECCIONAL POR PARTE DE WEATHERFORD
1401 ARMÓ BHA N.4 DIRECCIONAL DESDE SUPERFICIE HASTA 97 FT, ASÍ: BROCA N. 4 HLB PDC 12 1/4" (TIPO: GTD56MO
1110 BAJÓ BHA N. 4 DIRECCIONAL DESDE 97 FT HASTA 191 FT, ASÍ: XO+ (2) DRILL COLLAR 6 1/2" + XO + (1) JTA HWDP
1905 TORMENTA ELÉTRICA NIVEL II CON PRESENCIA DE LLUVIA, SE SUSPENDEN TRABAJO EN ALTURA Y TRABAJOS DE S
1916 AJUSTE DE FLOW LINE Y TRABAJOS DE SOLDADURA
1910 REALIZÓ PRUEBA DE HERRAMIENTAS DIRECCIONALES CON Q: 500/550/600 GPM, SPP: 500/520/590 PSI, SIN ÉXIT
1110 CONTINUÓ BAJANDO BHA N. 4 DIRECCIONAL EN HUECO REVESTIDO DESDE 191 FT HASTA 312 FT, ASÍ: (4) HWDP 5
1403 CALIBRANDO SENSOR Y SEÑAL DE MWD, CON ÉXITO CON Q: 700 GPM, SPP: 760 PSI
1110 CONTINUÓ BAJANDO BHA N. 4 DIRECCIONAL EN HUECO REVESTIDO DESDE 312 FT HASTA 650 FT, ASÍ: (7) HWDP 5
1110 BAJÓ DP 5 1/2" XT-54 + BHA N. 4 DIRECCIONAL DESDE 650 HASTA 1694 FT, TOC (CMT SOBRE TOP PLUG ), VERIFIC
1410 REALIZÓ DRILL OUT DE LA FASE DE 12¼" ASÍ: PERFORÓ CEMENTÓ + TAPONES + FLOAT COLLAR + CEMENTO DESDE
1502 REALIZÓ DESPLAZAMIENTO DE AGUA-LODO-CEMENTO POR LODO PERFLEX (POLIMÉRICO SEMIDISPERSO) DE 10.6
1407 PERFORÓ CON BHA N. 4 DIRECCIONAL CEMENTÓ DESDE 1805 FT HASTA 1810 FT + 10 FM GUAYABO DESDE 1810
2004 REALIZÓ FORMATION INTEGRITY TEST (FIT) EN FM. GUAYABO, ASÍ: POSICIONÓ SARTA A 1790 FT Y CERRÓ PREVEN
1407 PERFORÓ FASE DE 12 ¼" CON BHA N. 4 DIRECCIONAL EN FM GUAYABO DESDE 1815 FT HASTA 1881 FT. (AVANCE 6
1910 CAMBIÓ SENSOR DE PRESIÓN POR PARTE DE LA COMPAÑÍA WEATHERFORD
1407 PERFORÓ FASE DE 12 ¼" CON BHA N° 4 DIRECCIONAL EN FM GUAYABO, DESDE 1881 FT HASTA 2070 FT. (AVANCE
1905 SUSPENDE OPERACIONES DEBIDO A TORMENTA NIVEL III, A 2070 FT SE CIRCULA POZO CON Q: 650 GPM, SPP: 95
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. GUAYABO, ROTANDO Y DESLIZANDO DESDE 2070 FT
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA ARENISCA SUPERIOR, DESDE 2335 FT H
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA UNIDAD ARENISCAS SUPERIORES DESD
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA UNIDAD LUTITA E DESDE 3590 FT HAST
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA UNIDAD C1 DESDE 4120 FT HASTA 442
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA UNIDAD ARENISCAS DE CARBONERA D
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA UNIDAD ARENISCAS DE CARBONERA D
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA UNIDAD ARENISCAS DE CARBONERA D
1905 SE DETUVO OPERACIÓN DEBIDO A TORMENTA NIVEL III, A 5385 FT CIRCULÓ POZO CON Q: 750 GPM, SPP: 1570 P
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA UNIDAD ARENISCAS DE CARBONERA D
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA UNIDAD C2 DESDE 5473 FT HASTA 5573
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA UNIDAD C2 DESDE 5573 FT HASTA 5855
1503 BOMBEÓ PÍLDORA VISCOSA A 5855 FT (30 BBL, 11.5 PPG, 180 SEG/QT) Y CIRCULÓ RECIPROCANDO SARTA HASTA
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA UNIDAD C2 DESDE 5855 FT HASTA 6139
1407 PERFORÓ FASE DE 12¼" CON BHA N. 4 DIRECCIONAL EN FM. CARBONERA UNIDAD C2 DESDE 6139 FT HASTA 6707
1503 BOMBEÓ PÍLDORA VISCOSA-PESADA A 6707 FT (30 BBL, 13 PPG, 200 SEG/QT) Y CIRCULÓ RECIPROCANDO SARTA H
1107 SACÓ DP 5½" + BHA N. 4 DIRECCIONAL EN HUECO ABIERTO 12¼" LIBRE DESDE 6707 FT HASTA 4770 FT NOTA: PRE
1503 CIRCULÓ FONDO ARRIBA A 4770' RECIPROCANDO LA SARTA PARÁMETROS: Q: 730 GPM, SPP: 1450 PSI, RPM: 60,
1107 SACÓ DP 5½" + BHA N. 4 DIRECCIONAL EN HUECO ABIERTO 12¼" LIBRE DESDE 4770 FT HASTA 2165 FT, DE LA SIGU
1503 CIRCULÓ FONDO ARRIBA A 2165' RECIPROCANDO LA SARTA PARÁMETROS: Q: 600-680 GPM, SPP: 800-950 PSI, RP
1107 SACÓ DP 5½" + BHA N. 4 DIRECCIONAL EN HUECO ABIERTO 12¼" DESDE 2165 FT HASTA 1805 FT, DE LA SIGUIENT
1107 'SACÓ DP 5½" + BHA N. 4 DIRECCIONAL EN HUECO REVESTIDO DESDE 1805 FT HASTA 650 FT. NOTA: CHEQUEÓ NI
1107 SACÓ BHA N. 4 DIRECCIONAL EN HUECO REVESTIDO DESDE 650 FT HASTA 97.56 FT. ASI (3) HWDP 5½" + JAR 6½"
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y SEGURIDAD PARA DESARME DE BHA N° 4 Y ARME DE BHA N. 5 DIRECCION
1402 SACÓ BHA N. 4 DIRECCIONAL EN HUECO REVESTIDO DESDE 97.56 FT HASTA SUPERFICIE. REALIZÓ CHEQUEÓ DE H
1401 ARMÓ Y BAJÓ BHA N. 5 DIRECCIONAL EN HUECO REVESTIDO 13?" DESDE SUPERFICIE HASTA 97.56 FT ASÍ: BROCA
1110 CONTINUÓ BAJANDO BHA N. 5 DIRECCIONAL EN HUECO REVESTIDO DESDE 192 FT HASTA 650 FT, ASÍ: (11) HWDP
1110 BAJÓ DP 5½" + BHA N. 5 DIRECCIONAL EN HUECO REVESTIDO DESDE 650 FT HASTA 1787 FT. (ZAPATO 13 3/8" A 18
1308 'REALIZÓ RIG SERVICES ( WASH PIPE, TOP DRIVE)
1908 CONTINUAN ACTIVIDADES DE MANTENIMIENTO AL TOP DRIVE, Y CAMBIO PIN AJUSTE ROTACION, MANEJO DEL T
1110 BAJÓ DRILL PIPE 5½" CON BHA N.5 DIRECCIONAL DESDE 1787 FT HASTA 3979 FT. ASI: PRESENTÓ PUNTOS APRETA
1503 A 3979 FT CIRCULÓ RECIPROCANDO SARTA HASTA OBTENER RETORNOS LIMPIOS PARAMETROS: Q: 380-630 GPM
1110 BAJÓ DRILL PIPE 5½" CON BHA N. 5 DIRECCIONAL DESDE 3979 FT HASTA 6707 FT. ASI: PRESENTÓ PUNTO DE APO
1407 PERFORÓ FASE DE 12¼" CON BHA N. 5 DIRECCIONAL EN FM. CARBONERA UNIDAD C2 DESDE 6707 FT HASTA 6741
1407 PERFORÓ FASE DE 12¼" CON BHA N. 5 DIRECCIONAL EN FM. CARBONERA UNIDAD C2 DESDE 6741 FT HASTA 7080
1407 PERFORÓ FASE DE 12¼" CON BHA N. 5 DIRECCIONAL EN FM. CARBONERA UNIDAD LUTITA E3 DESDE 7080 FT HAS
1407 PERFORÓ FASE DE 12¼" CON BHA N. 5 DIRECCIONAL EN FM. CARBONERA UNIDAD T1 DESDE 7440 FT HASTA 7465
2005 REALIZÓ PRUEBA DE PRESIÓN DE EQUIPO EN SUPERFICIE, PROBÓ BOMBAS DE LODO N.1 Y N.2 CON 1500 PSI DUR
1407 PERFORÓ FASE DE 12¼" CON BHA N. 5 DIRECCIONAL EN FM. CARBONERA UNIDAD T1 DESDE 7465 FT HASTA 7475
1501 A 7475' CIRCULÓ POZO CON Q: 850 GPM, SPP: 1800-2050 PSI, RPM: 40, TQ: 12 KLBF\t
1503 BOMBEÓ Y CIRCULÓ HASTA RETORNOS LIMPIOS 30 BBL DE PÍLDORA VISCOSO-PESADA (MW: 12.8 LPG, FV: 200 SE
1107 SACÓ SARTA DP 5½" + BHA N. 5 DIRECCIONAL EN HUECO ABIERTO, LIBRE DESDE 7475 FT HASTA 4819 FT.
1501 A 4819 FT REALIZÓ CHEQUEO DE HERRAMIENTAS DIRECCIONALES CON Q: 600/760, SPP: 820/1200 PSI, SIN ÉXITO
1107 SACÓ SARTA DP 5½" + BHA N. 5 DIRECCIONAL EN HUECO ABIERTO, LIBRE DESDE 4819 FT HASTA 1805 FT. - PRESE
1905 SUSPENDIÓ OPERACIONES POR ALERTA DE TORMENTA NIVEL II - SUSPENDE TRABAJO DE ALTURAS
1107 SACÓ DP 5½" + BHA N. 5 DIRECCIONAL EN HUECO REVESTIDO DESDE 1805 FT HASTA 650 FT.
1107 SACÓ BHA N. 5 DIRECCIONAL EN HUECO REVESTIDO DESDE 650 FT HASTA 97.56 FT ASI: (3) HWDP 5½" + JAR 6½"
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y SEGURIDAD PARA DESARME DE BHA N. 5 Y ARME DE BHA N. 6 DIRECCION
1404 SACÓ BHA N. 5 DIRECCIONAL EN HUECO REVESTIDO DESDE 97.56 FT HASTA SUPERFICIE ASI: NMDC 8" + HEL-BAP
1401 ARMÓ Y BAJÓ BHA N. 6 DIRECCIONAL EN HUECO REVESTIDO 13?" DESDE SUPERFICIE HASTA 97 FT ASÍ: BROCA #4
1110 CONTINUÓ BAJANDO BHA N. 6 DIRECCIONAL EN HUECO REVESTIDO DESDE 97 FT HASTA 649 FT, ASÍ: (2) DC 6 1/2
1110 BAJÓ TUBERÍA DP 5" CON BHA N. 6 DIRECCIONAL DESDE 649 FT HASTA 1786 FT. **LLENÓ TUBERÍA CON Q: 300 G
1307 CORRIÓ Y CORTÓ 100 FT DE CABLE DE PERFORACIÓN DE 1 3/8".
1303 CAMBIÓ SAVER SUB 6 5/8" REG x XT54 EN CONEXIÓN DEL TOP DRIVE.
1308 BAJÓ TUBERÍA DP 5" CON BHA N. 6 DIRECCIONAL DESDE 1786 FT HASTA 4050 FT. LLENÓ TUBERÍA A 3000 FT CON
1503 CIRCULÓ POZO HASTA RETORNOS LIMPIOS RECIPROCANDO SARTA CON Q: 640 GPM, SPP: 1200 PSI. RPM: 50, TQ:
1110 BAJÓ TUBERÍA DP 5" CON BHA N. 6 DIRECCIONAL DESDE 4050 FT HASTA 5190 FT. PRESENTÓ PUNTO DE APOYO (M
1501 CIRCULÓ RECIPROCANDO SARTA PARA HOMOGENIZAR SISTEMA DE LODO CON Q: 700 GPM, SPP: 1600-1700 PSI,
1407 PERFORÓ FASE DE 12¼" CON BHA N. 6 DIRECCIONAL EN FM. CARBONERA UNIDAD T1 DESDE 7475 FT HASTA 7615
1407 PERFORÓ FASE DE 12¼" CON BHA N. 6 DIRECCIONAL EN FM. CARBONERA UNIDAD LUTITA E4 DESDE 7615 FT HAS
1407 PERFORÓ FASE DE 12¼" CON BHA N. 6 DIRECCIONAL EN FM. CARBONERA UNIDAD LUTITA E4 DESDE 7777 FT HAS
1407 PERFORÓ FASE DE 12¼" CON BHA N. 6 DIRECCIONAL EN FM. CARBONERA UNIDAD LUTITA E4 DESDE 8338 FT HAS
1503 CIRCULÓ POZO HASTA RECUPERAR MUESTRA GEOLOGICA CON Q: 880 GPM, SPP: 2580-2500 PSI. RPM: 50, TQ: 10
1503 BOMBEÓ PÍLDORA VISCOSA-PESADA A 8533 FT (30 BBL, 14 PPG, 200 SEG/QT) Y CIRCULÓ RECIPROCANDO SARTA H
1107 SACÓ DP 5½" + BHA N. 6 DIRECCIONAL EN HUECO ABIERTO 12¼" LIBRE DESDE 8533 FT HASTA 8219 FT NOTA: OBS
1110 BAJÓ LAVANDO DP 5½" + BHA N. 6 DIRECCIONAL EN HUECO ABIERTO 12¼" LIBRE DESDE 8219 FT HASTA 8533 FT P
1107 SACÓ DP 5½" + BHA N. 6 DIRECCIONAL EN HUECO ABIERTO 12¼" DESDE 8533 FT HASTA 7841 FT ASI: - CON C
1503 CIRCULÓ RECIPROCANDO SARTA HASTA OBTENER RETORNOS LIMPIOS CON Q: 700 GPM, SPP: 1650-1700 PSI, RPM
1107 SACÓ DP 5½" + BHA N. 6 DIRECCIONAL EN HUECO ABIERTO 12¼" DESDE 7841 FT HASTA 7746 FT ASI: - PRESENTÓ
1905 SUSPENDIÓ OPERACIONES POR TORMENTA NIVEL II Y III. CIRCULÓ Y RECIPROCÓ SARTA DE LA SIGUIENTE MANERA
1107 SACÓ DP 5½" + BHA N. 6 DIRECCIONAL EN HUECO ABIERTO 12¼" DESDE 7711 FT HASTA 6772 FT ASI: -BOMBEÓ P
1503 CIRCULÓ RECIPROCANDO SARTA HASTA OBTENER RETORNOS LIMPIOS CON Q: 750 GPM, SPP: 1650-1780 PSI, RPM
1107 SACÓ SARTA DE PERFORACIÓN CON BHA N. 6 DIRECCIONAL EN HUECO ABIERTO DE 12¼" DESDE 6772 FT HASTA 4
1503 OBSERVÓ AUMENTO DE ARRASTRE EN EL PESO DE LA SARTA, A 4050 FT CIRCULÓ HASTA RETORNOS LIMPIOS PAR
1107 SACÓ SARTA DE PERFORACIÓN CON BHA N. 6 DIRECCIONAL EN HUECO ABIERTO 12¼" LIBRE DESDE 4050 FT HAST
1501 CIRCULÓ RECIPROCANDO SARTA HASTA OBTENER RETORNOS LIMPIOS (PARAMETROS: Q: 480 GPM, SPP: 520 PSI,
1107 SACÓ SARTA DE PERFORACIÓN + BHA N. 6 DIRECCIONAL EN HUECO REVESTIDO DESDE 1805 FT HASTA 650 FT. NO
1107 SACÓ BHA N. 6 DIRECCIONAL EN HUECO REVESTIDO DESDE 650 FT HASTA 97 FT ASI: (3) HWDP 5½" + JAR 6½" + (2
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y SEGURIDAD PARA DESARME DE BHA N. 6 DIRECCIONAL POR PARTE DE WE
1402 SACÓ BHA N. 6 DIRECCIONAL EN HUECO REVESTIDO DESDE 97 FT HASTA SUPERFICIE ASI: NMDC 8" + HEL-BAP + E
1003 ARMÓ HERRAMIENTAS PARA BAJAR Y RECUPERAR WEAR BUSHING. RETIRÓ WEAR BUSHING. DESARMÓ HERRAM
1308 REALIZÓ 'RIG SERVICES. (ENGRASÓ WASH PIPE, TOP DRIVE Y BLOQUE VIAJERO)
1701 REALIZÓ REUNION PREOPERACIONAL Y DE SEGURIDAD PARA ARMAR HERRAMIENTAS PARA MANEJO DE CASING
1204 REALIZÓ RIG UP DE HERRAMIENTAS PARA MANEJO DE CASING DE 9 5/8"
1701 REALIZÓ REUNIÓN PRE-OPERACIONAL Y DE SEGURIDAD PARA LA CORRIDA DE REVESTIMIENTO DE 9 5/8" POR PAR
1206 REALIZÓ CORRIDA DEL REVESTIMIENTO DE 9 5/8", P-110 / N80Q, TXP-BTC DESDE SUPERFICIE HASTA 2960 FT ASÍ:
1503 CIRCULÓ UN FONDO ARRIBA A 2960 FT HASTA OBTENER RETORNOS LIMPIOS (PARAMETROS Q: 420 GPM, SPP: 28
1206 BAJÓ REVESTIMIENTO 9 5/8", P-110, TXP-BTC EN HUECO ABIERTO DESDE 2960 FT HASTA 4076 FT NOTAS:
1503 CIRCULÓ UN FONDO ARRIBA A 4076 FT HASTA OBTENER RETORNOS LIMPIOS (PARAMETROS: Q: 410 GPM, SPP: 3
1206 BAJÓ REVESTIMIENTO 9 5/8", P-110, TXP-BTC EN HUECO ABIERTO DESDE 4076 FT HASTA 6000 FT. -ROMPIÓ GELES
1905 ALERTA DE TORMENTA ELECTRICA NIVEL III . CIRCULÓ RECIPROCANDO SARTA POR CON Q:400 GPM Y SPP: 280-25
1206 BAJÓ REVESTIMIENTO 9 5/8", P-110, TXP-BTC EN HUECO ABIERTO DESDE 6000 FT HASTA 7000 FT -ROMPIÓ GELES
1503 CIRCULÓ UN FONDO ARRIBA A 7000 FT HASTA OBTENER RETORNOS LIMPIOS (PARAMETROS: Q: 400 GPM, SPP: 5
1206 BAJÓ REVESTIMIENTO 9 5/8", P-110, TXP-BTC EN HUECO ABIERTO DESDE 7000 FT HASTA 7500 FT
1503 CIRCULÓ UN FONDO ARRIBA A 7500 FT HASTA OBTENER RETORNOS LIMPIOS (PARAMETROS: Q: 400 GPM, SPP: 4
1206 'BAJÓ REVESTIMIENTO 9 5/8", P-110, TXP-BTC EN HUECO ABIERTO DESDE 7500 FT HASTA 8360 FT - ROMPIÓ GELE
1503 CIRCULÓ UN FONDO ARRIBA A 8360 FT HASTA OBTENER RETORNOS LIMPIOS (PARAMETROS: Q: 500-520 GPM, SP
1206 BAJÓ REVESTIMIENTO 9 5/8", P-110, TXP-BTC DESDE 8360 FT HASTA 8445 FT PRESENTANDO RESTRICCIÓN. CON C
1206 BAJÓ REVESTIMIENTO 9 5/8", P-110, TXP-BTC, TRABAJANDO SARTA MECÁNICAMENTE CON CIRCULACIÓN DESDE
1206 CIRCULÓ POZO A 8528 FT HASTA OBTENER RETORNOS LIMPIOS (PARAMETROS: Q: 400-600 GPM, SPP: 180-300 PS
1503 CIRCULÓ POZO A 8528 FT HASTA OBTENER RETORNOS LIMPIOS (PARAMETROS: Q: 400-600 GPM, SPP: 180-300 PS
1701 REALIZÓ REUNION PREOPERACIONAL Y DE SEGURIDAD PARA CEMENTAR REVESTIMIENTO DE 9 5/8" POR PARTE D
1503 CIRCULÓ POZO A 8528 FT HASTA OBTENER RETORNOS LIMPIOS (PARAMETROS: Q:600 GPM, SPP: 380 PSI) MONIT
2101 REALIZÓ RIG UP DE LINEAS Y CABEZA DE CEMENTACION
2104 CIRCULÓ POZO A TRAVÉS DE CABEZA DE CEMENTACIÓN (PARAMETROS: Q: 460 GPM, SPP: 590 PSI.) SIMULTANEAM
2104 REALIZÓ CEMENTACIÓN DEL REVESTIMIENTO DE 9 5/8" BAJÓ EL SIGUIENTE PROGRAMA: BOMBEÓ 40 BBL DE LAV
2102 REALIZÓ RIG DOWN CABEZA Y LÍNEAS DE CEMENTACIÓN
1304 RETIRÓ MOUSE HOLE Y BAJÓ CUÑERO NEUMÁTICO.
1701 REALIZÓ REUNIÓN PREOPERACIONALY DE SEGURIDAD PARA LEVANTAR SET DE BOP`S.
1005 RETIRÓ TORNILLERÍA DE LA CAMPANA DEL FLOW LINE. RETIRÓ CAMISA DE FLOW LINE.SOLTÓ Y LEVANTO SET DE P
1905 ALERMA TORMENTA NIVEL II. SUSPENDE TRABAJOS EN ESPACIOS CONFINADOS Y EN ALTURA
1905 ALARMA TORMENTA NIVEL II Y NIVEL III. SUSPENDE LABORES DE FORMA INMEDIATA. SE PRESENTAN FUERTES LLU
1306 REALIZÓ ACTIVIDADES DE ACHIQUE Y LIMPIEZA DEL CONTRAPOZO PARA RETIRAR HANDING PLATE Y CORTE DE RE
1010 TENSIONÓ REVESTIMIENTO E INSTALÓ CASING HANGER, SENTÓ CON 40 KLB DE PESO.
1007 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA CORTAR Y BISELAR REVESTIMIENTO DE 9 5/8". INSTA
1002 SOLTÓ TORNILLERIA. RETIRÓ CAMPANA. RETIRÓ SET DE BOP
1004 INSTALÓ Y TORQUEÓ PEGUE ENTRE LA SECCIÓN "A" Y "B" DEL CABEZAL. REALIZÓ PRUEBA DE SELLO CON 2000 PS
1001 REALIZÓ REUNIÓN DE SEGURIDAD Y PREOPERACIONAL PARA INSTALAR SET DE PREVENTORAS SOBRE SECCIÓN "B
1009 INSTALÓ Y TORQUEÓ SET DE PREVENTORAS SOBRE SECCIÓN "B". ARMÓ Y BAJÓ SARTA DE PRUEBA CON TEST PLU
1003 ARMÓ SARTA ASÍ: TEST PLUG + CROSS OVER + (1) DP 4 1/2" RECUPERÓ TEST PLUG E INSTALÓ WEAR BUSHING. SA
1701 REALIZÓ REUNIÓN DE SEGURIDAD Y PREOPERACIONAL PARA DESARME DE HERRAMIENTAS DE CORRIDA DE REVE
1205 REALIZÓ RIG DOWN DE HERRAMIENTAS DE CORRIDA DE DE REVESTIMIENTO DE 9 5/8" (SPIDER Y HERRAMIENTAS
1701 REALIZÓ REUNIÓN PRE-OPERACIONAL Y DE SEGURIDAD PARA INSTALAR CABEZA ROTATIVA DEL SISTEMA MPD PO
1303 REALIZÓ RIG UP EQUIPOS Y HERRAMIENTAS DEL SISTEMA MPD. - IZÓ CABEZA ROTATIVA CON LAS VÁLVULAS DEL F
1303 CONTINUÓ REALIZANDO RIG UP EQUIPOS Y HERRAMIENTAS DEL SISTEMA MPD. - INSTALÓ MANGUERAS DE VÁLV
1303 REALIZÓ ALISTAMIENTO PARA PRUEBA, SUBIÓ E INSTALÓ TAPÓN DE PRUEBA. ACONDICIONÓ LÍNEA KILL LINE PARA
1704 REALIZÓ REUNIÓN DE SEGURIDAD Y PREOPERACIONAL PARA ARME DE BHA No. 7 CONVENCIONAL
1303 REALIZÓ INSTALACIÓN DE EMPAQUE BEARING EN PARADA DE TUBERÍA DE DP 5 1/2" ASÍ: SENTÓ EMPAQUE BEAR
1401 ARMÓ Y BAJÓ BHA N. 7 CONVENCIONAL DESDE SUPERFICIE HASTA 596 FT ASÍ: BROCA PDC 8 1/2" (TIPO: MSi616
1508 FALLA EN BOMBAS 1, 2 Y 3. REALIZÓ PRUEBAS DE PRESIÓN A BOMBAS DE LODO SIN OBSERVAR COMPORTAMIEN
1110 BAJÓ TUBERÍA DP 5 1/2" CON BHA N.7 CONVENCIONAL DESDE 596 FT HASTA 2867 FT. NOTA: SE OBSERVA FUGA
1508 REPARACIÓN DE SOLDADURA EN FLOW LINE POR PRESENCIA DE FUGA. NOTA: -SE PRESENTA SOLDADOR A LAS 1
1905 ALERTA TORMENTA NIVEL III. ACTIVIDAD DE RAYOS SOBRE EL SITIO. SE RECOMIENDA SUSPENDER LABORES DE FO
1508 CONTINUÓ ACTIVIDADES DE REPARACIÓN DE FLOW LINE CON SOLDADURA POR PRESENCIA DE FUGA.
1508 'NPT: REPARÓ FLOW LINE CON SOLDADURA POR PRESENCIA DE FUGA
1110 'BAJÓ TUBERÍA DP 5 1/2" CON BHA N. 7 CONVENCIONAL DESDE 2867 FT HASTA 8000 FT. LLENÓ TUBERÍA CADA 15
1110 'BAJÓ TUBERÍA DP 5 1/2" CON BHA N. 7 CONVENCIONAL LAVANDO DESDE 8000 FT HASTA 8433 FT (TOC) PARÁME
1501 REALIZÓ PRUEBA DE INTEGRIDAD AL REVESTIMIENTO DE 9 5/8" CON SPP: 2600 PSI DURANTE 30 MIN. OK
1916 NPT: ACONDICIONÓ Y CALIBRÓ EQUIPOS DE CONTROL DE POZO (ACUMULADOR- CONSOLA DE PERFORADOR) PO
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA REALIZAR DRILL OUT Y PERFORAR FASE 8 1/2" CON
1410 REALIZÓ DRILL OUT DESDE 8433 FT HASTA 8528 FT, ASI: PERFORÓ TAPONES, COLLAR FLOTADOR, CEMENTO Y ZAP
1410 REALIZÓ DRILL OUT PERFORANDO BOLSILLO DE CEMENTO DESDE 8528 FT HASTA 8533 FT. PARÁMETROS: Q: 250 G
1406 PERFORÓ FASE DE 8½" CON BHA N. 7 CONVENCIONAL EN FM. CARBONERA UNIDAD LUTITA E4 DESDE 8533 FT HA
1503 A 8540 FT CIRCULÓ POZO HASTA ASEGURAR CORTES POR ENCIMA DEL BHA, CON: Q: 250 GPM, SPP: 250 PSI, RPM
1507 A 8322 FT REALIZÓ CHEQUEO DE FLUJO DE POZO EN ESTÁTICO X 30 MIN, OK.
1701 REALIZÓ REUNIÓN PRE-OPERACIONAL PARA INSTALACIÓN DE ELEMENTO DE SELLO Y VÁLVULA NRV
1107 SACÓ DP 5½" Y BHA N. 7 POR ENCIMA DE ZAPATO 9 ?" DESDE 8540 FT HASTA 8322 FT. RETIRÓ CAMPANA DE VIAJ
1110 BAJÓ EN HUECO REVESTIDO DP 5½" Y BHA N. 7 DESDE 8322 FT HASTA 8451 FT, PROFUNDIDAD A LA CUAL CONEC
1502 HOMOGENIZÓ LODO A SISTEMA BIFÁSICO A 8517 FT CON LA UNIDAD DE NITRÓGENO AL SISTEMA ACTIVO, ASÍ: B
1406 PERFORÓ FASE DE 8 ½" CON BHA N. 7 CONVENCIONAL EN FM. T2 DESDE 8540 FT HASTA 8608 FT CON ROP CONT
1912 A 8608 FT PRESENTÓ CAÍDA DE PRESIÓN DE INYECCCIÓN EN UNIDAD DE NITROGENO, LEVANTÓ Y SACÓ SARTA DE
1912 A 8608 FT RESTAURÓ PARÁMETROS NORMALES DE PERFORACIÓN Q: 163 GPM, Q GAS: 950 SCFM, SPP: 320 PSI
1406 PERFORÓ FASE DE 8½" CON BHA N. 7 CONVENCIONAL EN FM. CARBONERA UNIDAD T2 DESDE 8608 FT HASTA 87
1406 PERFORÓ FASE DE 8½" CON BHA N. 7 CONVENCIONAL EN FM. UNIDAD T2 DESDE 8732 FT HASTA 8920 FT, CON RO
1406 PERFORÓ FASE DE 8½" CON BHA N. 7 CONVENCIONAL EN FM. UNIDAD K1 SUPERIOR DESDE 8920 FT HASTA 9070
1503 A 9070 FT CIRCULÓ POZO RECIPROCANDO SARTA HASTA RETORNOS LIMPIOS, PARÁMETROS: Q LIQ: 220 GPM Y Q
1107 SACÓ DP 5½" + BHA N. 7 CONVENCIONAL EN HUECO ABIERTO 8½" LIBRE DESDE 9070 FT HASTA 8481 FT. ( CASING
1110 BAJÓ DP 5½" + BHA N. 7 CONVENCIONAL EN HUECO ABIERTO 8½" CON CIRCULACIÓN DESDE 8549 FT HASTA 9070
1503 A 9070 FT CIRCULÓ POZO RECIPROCANDO SARTA HASTA RETORNOS LIMPIOS PARÁMETROS: Q LIQ: 220 GPM Y Q
1503 A 9070 FT BOMBEÓ Y DESPLAZÓ 45 BBL DE PILDORA LUBRICANTE DE 8.8 LPG Y 3% DE VOLUMEN LUBRICANTE , C
1503 A 9070 FT DESPLAZÓ Y ESPOTEÓ 45 BBL DE PILDORA LUBRICANTE DE 8.8 LPG Y 3% DE VOLUMEN LUBRICANTE PA
1107 SACÓ DP 5½" Y BHA N. 7 CONVENCIONAL EN HUECO ABIERTO 8½" LIBRE DESDE 9070 FT HASTA 8448 FT.
1701 REALIZÓ REUNION PREOPERACIONAL Y DE SEGURIDAD PARA RETIRAR BEARING E INSTALAR CAMPANA.
1304 ACHICÓ CONTRAPOZO. REALIZÓ REGISTRO ECHOMETER A 8448 FT, SIN ÉXITO POR ALTA PRESENCIA DE NITRÓGEN
1303 RETIRÓ BEARING E INSTALÓ CAMPANA DE VIAJE DEL SISTEMA MPD POR PARTE DE HALLIBURTON
1107 'SACÓ DP 5½" Y BHA N. 7 CONVENCIONAL EN HUECO REVESTIDO 9?" DESDE 8448 FT HASTA 596 FT. REALIZÓ REG
1402 SACÓ BHA N. 7 CONVENCIONAL DESDE 596 FT HASTA SUPERFICIE ASÍ: (2) HWDP 5 1/2" + DRILLING JAR 6 1/2" + (1
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA REALIZAR CORRIDA DE REGISTROS ELÉCTRICOS.
1804 LEVANTÓ E INSTALÓ POLEAS, ARMÓ SONDA DE CORRIDA N. 1 DE REGISTROS TRIPLE COMBO (GR-MDN-MPD-MM
1804 BAJÓ LIBRE SONDA DE REGISTROS TRIPLE COMBO (GR-MDN-MPD-MMR-MDL-CAL-SP) DESDE SUPERFICIE HASTA
1804 REALIZÓ CORRIDA N. 1 REGISTRO TRIPLE COMBO SECCIÓN PRINCIPAL REGISTRADA DESDE 9070 FT HASTA 8522 FT
1812 SACÓ SONDA REGISTRO TRIPLE COMBO (GR-MDN-MPD-MMR-MDL-CAL-SP) DESDE 9070 FT HASTA SUPERFICIE
1803 RIG DOWN HERRAMIENTAS DE REGISTROS DE TRIPLE COMBO (GR-MDN-MPD-MMR-MLL-SP-CAL).
1802 ARMÓ SONDA DE REGISTROS EN SUPERFICIE CORRIDA No 2. PUNTOS DE PRESIÓN (MDT). PROBÓ HERRAMIENTAS
1811 BAJÓ SONDA DE REGISTROS ELÉCTRICOS PUNTOS DE PRESIÓN (MDT) DESDE SUPERFICIE HASTA 9070 FT.
1806 REALIZÓ TOMA DE PUNTOS DE PRESIÓN DESDE 9070 FT HASTA 8571 FT PROFUN PRE. FORM RESULTA
1806 REALIZÓ TOMA DE PUNTOS DE PRESIÓN DESDE 8571 FT HASTA 8991 FT, SE REGISTÓ 14 PUNTOS DE PRESIÓN DE
1812 SACÓ SONDA DE REGISTROS DE CORRIDA N.2 (TOMA DE PUNTOS DE PRESIÓN -MFT) DESDE 8991 FT HASTA SUPE
1803 'DESARMÓ SONDA Y HERRAMIENTAS DE REGISTROS ELÉCTRICOS PUNTOS DE PRESIÓN -MFT Y RETIRÓ UNIDAD DE
1204 'LEVANTÓ Y CONECTÓ ENSAMBLAJE DE LINER HANGER E INSTALÓ Y TORQUEÓ PUP JOINT NC 50 X XT 54 CON 30 K
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA EL ARME DE LAS HERRAMIENTAS DE MANEJO DE LIN
1204 REALIZÓ RIG UP DE HERRAMIENTAS DE MANEJO Y CORRIDA DE LINER DE 7" DE ITS.
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA CORRER LINER 7" LIDERADA POR PESONAL DE ITS. D
1206 REALIZÓ CORRIDA DE LINER 7" N-80, 26 LB/PIE, TXP/BTC, DESDE SUPERFICIE HASTA 91 FT ASÍ: LEVANTÓ JUNTA N.
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA IZAJE Y CONEXIÓN DEL COLGADOR DE LINER POR PA
1202 CONECTÓ ENSAMBLAJE DE LINER HANGER (XO ADAPTER + LINNER HANGER + PBR + SETTING TOOL + PUP JOINT +
1205 REALIZÓ RIG DOWN DE HERRAMIENTAS DE MANEJO DE LINER DE 7" DE ITS.
1206 BAJÓ DP 5 1/2" XT 54 + LINER HANGER 7" + LINER 7" N-80, 26 LB/PIE, TXP/BTC DESDE 745 FT HASTA 6136 FT NO
1206 BAJÓ LINER 7" N-80, 26 LB/PIE, TXP/BTC, CON TUBERÍA DP 5½" EN HUECO REVESTIDO 9?" DESDE 6136 FT HASTA
1701 'REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA RETIRAR CAMPANA E INSTALAR BEARING.TOMÓ PA
1206 RETIRÓ CAMPANA DE VIAJE E INSTALÓ ELEMENTO DE SELLO. BAJÓ LINER 7" CON TUBERÍA DP 5½" EN HUECO REV
1206 BAJÓ LINER 7" N-80, 26 LB/PIE, TXP/BTC, CON TUBERÍA DP 5½" EN HUECO ABIERTO 8½" CON CIRCULACIÓN DESD
1503 CIRCULÓ POZO A 9065 FT CON FLUIDO MONOFASICO CON Q: 100 GPM, SPP: 280 PSI, RPM: 20, TQ: 12 KLBF *FT.
2101 LEVANTÓ Y CONECTÓ CABEZA ROTATIVA DE CEMENTACIÓN DE HALLIBURTON
1503 CIRCULÓ
TQ: 12-14POZO CON SISTEMA BIFASICO CON CABEZAL DE CEMENTACIÓN ROTATIVA CON PARÁMETROS: Q: 240 G
1503 KLBF*FT.
2104 REALIZÓ PROCEDIMIENTO PARA SENTAR EL COLGADOR DEL LINER DE 7" ASÍ: POSICIONO SARTA A 9065 FT (CASIN
1503 RECIPROCÓ SARTA DESDE 8345 FT HASTA 8280 FT Y CIRCULÓ EXCESO DE CEMENTO CON 30 BBL PILDORA ABRAS
2102 DESCONECTÓ Y QUEBRÓ CABEZA ROTATIVA DE CEMENTACIÓN DE HALLIBURTON
1402 SACÓ DP 5½" + SETTING TOOL EN HUECO REVESTIDO DESDE 8280 FT HASTA 7971 FT
1701 REALIZÓ REUNIÓN PREOPERACIONAL Y DE SEGURIDAD PARA RETIRAR BEARING.
1402 DESINSTALÓ BEARING POR PARTE DE HALLIBURTON MPD
1402 BAJÓ PARADA CON BEARING DE BACK UP Y RETIRÓ AMBOS ELEMENTOS DE SELLO E INSTALÓ CAMPANA DE VIAJE
1402 SACÓ DP 5½" XT -54 + SETTING TOOL DESDE 7971 FT HASTA SUPERFICIE,.
1402 QUEBRÓ SETTING TOOL , OBSERVÓ EL DEPLAZAMIENTO DEL CONO COMPLETO, MECÁNISMO DE LIBERACIÓN DE
1701 REALIZÓ REUNION PREOPERACIONAL Y DE SEGURIDAD PARA DESARMAR CABEZA ROTATIVA Y LINEA DE FLOTE (M
1302 REALIZÓ RIG DOWN DE HERRAMIENTAS Y EQUIPO DE MPD RETIRO CABEZA ROTATORIA Y LINEA DE FLOTE. -R
1302 QUEBRÓ ELEMENTOS DE BHA CON LLAVES DE POTENCIA, ASÍ: (3) DC 6 ½" + CROSS OVER + BIT SUB + (2) DC 8" + (
1302 'IZÓ CAMPANA SOBRE BOP´S, EVIDENCIANDO DESACOPLE CON FLOW LINE Y ESTRUCTURA. SE REALIZÓ TRABAJO
1302 IZÓ NUEVAMENTE, ACOPLO SOBRE ANULAR Y CONECTÓ CON CAMISA DEL FLOW LINE.
1701 REALIZÓ REUNION PREOPERACIONAL Y DE SEGURIDAD PARA CORRER Y CORTAR DE CABLE DE PERFORACIÓN
1307 REALIZÓ CORRIDA Y CORTE DE 100 FT DE CABLE DE PERFORACIÓN 1 3/8". FINALIZÓ EVENTO ODR DEL CHIC 218
OPERACIONES DEL CHICHIMENE 218, ECOPETROL RECIBIÓ EQUIPO NABORS 137 EL 14-05-2019 CON EL 100 % DE CIERRE DE ACCIONES IMP
OR A 45 FT. REVISÓ FUNCIONAMIENTO DEL CHUPADOR, BOMBA GORMAN. OK
SDE 45 FT HASTA 131 FT, (AVANCE: 86 FT), 100 % ROTADO, ROP PROMEDIO:19.11 (FT/HR), ROP EFECTIVA: 45.26 FT/HR , CON LOS SIGUIENT
SDE 131 FT HASTA 250 FT, (AVANCE:119 FT), 100 % ROTADO, ROP PROMEDIO:29.75 (FT/HR), ROP EFECTIVA: 69.11 FT/HR , CON LOS SIGUIE
ARTA CON Q: 380 GPM, SPP: 160 PSI, RPM: 65, TQ: 0.5-2.0 KLBF-FT. SE INCREMENTA PESO DE LODO A 10.1 PPG PARA VIAJE A SUPERFICIE, P
(6) HWDP 5 1/2" + CROSS OVER + (1) DC 8" + STAB 17 3/8" + (1) DC 8" + BIT SUB 8" + BROCA TRC 17 1/2" (TIPO HR1GJMRS, SN: 1479882,
DIRECCIONAL POR PARTE DE WEATHERFORD.
CA N.2U PDC 17½" (NOV, TIPO: TFFX519S, S/N: A248665, TFA: 0.907 (7x20/32)) + MOTOR 9½" (CAMISA 14?", 0.12 REV/GAL, BH: 1.5°) + PIN
(6?" REG PIN - XT 54 BOX) + (5) HWDP 5½".
ESDE 250 FT HASTA 557 FT. (AVANCE 307 FT), ROPAVG: 61.40 FT/HR, ROP EFFEC: 102.33 FT/HR. REPASÓ DOS VECES CADA PARADA. PARÁM
RCULÓ POZO CON Q: 550 GPM, SPP: 450 PSI, 20 RPM, TQ: 3 KLB*FT
OTANDO Y DESLIZANDO DESDE 557 FT HASTA 970 FT. (AVANCE 413 FT), ROP AVG: 51.63 FT/HR, ROP EFFEC: 111.02 FT/HR. REAPASÓ CADA PA
0 GPM, SPP: 980 PSI, RPM: 50, TQ: 1-3 KLBF-FT.
(TOPE DEL BHA).
WDP 5 1/2 IN + CROSSOVER+ 1 DC 8 IN + CROSSOVER
2 DIRECCIONAL
MDC 8 IN + EMITTING SUB 8 IN + TOOL CARRIER 8 IN + CROSSOVER + MOTOR 9 1/2 IBN CAMISA 14 5/8 IN + BROCA PDC 17 1/2 IN N° 2 (NO
DIRECCIONAL POR PARTE DE WEATHERFORD.
CA #3U PDC 17½" (VAREL, TIPO: VTD519SDHU, S/N: 4011339, TFA: 0.928 (10x11/32)) + MOTOR 9½" (CAMISA 15?", 0.12 rev/gal, BH: 1.5°) +
(6?" REG PIN - XT 54 BOX) + (5) HWDP 5½"
NDO POR SEGURIDAD LA ULTIMA PARADA CON: Q: 600 - 800 GPM, SPP: 700 - 1150 PSI, RPM: 40, TQ: 1 - 2 KLBF-FT.
ESDE 970 FT HASTA 1810 FT, ROP AVG: 62.22 FT/HR, ROP EFEC: 122.99 FT/HR. REPASÓ CADA PARADA. PARÁMETROS ROTANDO: ROTÓ 506
RCULÓ CON Q: 780 GPM, SPP: 1050 PSI, 50 RPM, TQ: 2.-4 KLB*FT, CHEQUEÓ NIVEL ESTÁTICO DEL POZO X 10 MIN,OK.
BRE DESDE 1810 FT HASTA 1720 FT NOTA: OBSERVÓ RESTRICCIÓN A 1720 FT, INTENTÓ PASAR MECANICAMENTE, SIN ÉXITO. MÁXIMO OVE
MPIOS CON Q: 800 GPM, SPP: 1050 PSI, 50 RPM, TQ: 2-3 KLB*FT,
AJÓ LAVANDO POR SEGURIDAD DESDE 1723 FT HASTA 1810 FT Q: 800 GPM, SPP: 1080 PSI, 50 RPM, TQ: 3-5 KLB*FT.
Y CIRCULÓ CON Q: 800 GPM, SPP: 1080 PSI, 50 RPM, TQ: 2.-3 KLB*FT,
E DESDE 1810 FT HASTA 1715 FT NOTA: OBSERVÓ RESTRICCIÓN A 1715 FT, INTENTÓ PASAR MECANICAMENTE SIN EXITO. MÁXIMO OVER PU
OVER (6?" REG PIN - XT 54 BOX) + (1) DC 8"
2 DIRECCIONAL
MITTING SUB 8" + TOOL CARRIER 8" + PIN-PIN + MOTOR 9½" (CAMISA 15?", 0.12 REV/GAL, BH: 1.5°) + BROCA #3U PDC 17½" (VAREL, TIPO

E REVESTIMIENTO 13?"

LOAT SHOE, APLICÓ SOLDADURA LÍQUIDA Y TORQUEÓ ROSCA BTC OK., BAJÓ HASTA 40 FT, LLENÓ CON LODO Y PROBÓ EQUIPO DE FLOTACIÓ
ROMPIÓ CIRCULACIÓN A 526 FT CON: Q: 250 GPM, SPP: 100 PSI ROMPIÓ CIRCULACIÓN A 1011 FT CON: Q: 250 GPM, SPP: 130 PSI ROMPIÓ

MENTACIÓN

DE PESO SUBIENDO.
E DE FEPCO
O DE CEMENTACIÓN DE REVESTIMIENTO DE 13 3/8", SIMULTÁNEAMENTE CIRCULÓ POZO A TRAVES DE CABEZA DE CEMENTACION @ 1805 F
ROGRAMA ASÍ: - LIBERÓ BOTTOM PLUG - BOMBEÓ 40 BBL DE AGUA FRESCA DE 8.33 PPG @ 5 BPM,140-160 PSI, - BOMBEÓ 275 BBL DE L
LLIBURTON.

OLE. ACHICÓ Y LIMPIÓ CONTRAPOZO

BOP'S 13 3/8"
X 13 5/8" 10K * POSICIONÓ SET BOP´S 13 5/8 5K SOBRE SPOOL ADPATER * TORQUEÓ TORNILLERÍA ENTRE MONOBLOQUE, DSA Y BOP.

S EN LA TORRE : 7

ECCIÓN DE LA CADENA DEL EJE DE MANDO QUE COMUNICA AL DRAW WALL AL BLOWER DEL MALACATE, REVISÓ ESTADO DE PIÑONES DE
- ADICIONAL PARADAS 40 Y TOTAL 93 PARADAS HWDP 5 1/2" EN TORRE.
AL POR PARTE DE WEATHERFORD.
HLB PDC 12 1/4" (TIPO: GTD56MOS, S/N: 13228587, TFA:1.052 IN2) + 8" MUD MOTOR 6750 CAMISA 11 3/4", BEND 1.5, 0.17 REV/GAL, GAP
LAR 6 1/2" + XO + (1) JTA HWDP 5 1/2". NOTA: INICIÓ DE TRABAJO DE SOLDADURA PARA ADECUACIÓN DEL FLOW LINE
AJO EN ALTURA Y TRABAJOS DE SOLDADURA

M, SPP: 500/520/590 PSI, SIN ÉXITO. SE EVIDENCIA RUIDO EN EXCESIVO EN LA DETECCIÓN DE LA SEÑAL. SE REALIZÓ CAMBIO DE SENSORE
FT HASTA 312 FT, ASÍ: (4) HWDP 5 1/2", BAJÓ TUBO A TUVO

FT HASTA 650 FT, ASÍ: (7) HWDP 5 1/2" + JAR 6 1/2" + (3) HWDP 5 1/2", BAJÓ TUBO A TUBO 5 JUNTAS HWDP 5 1/2".
(CMT SOBRE TOP PLUG ), VERIFICÓ TOPE DEL CEMENTO CON 5 KLB. BAJÓ LAVANDO DESDE 1000 HASTA 1694 FT CON: Q: 200 GPM, SPP: 2
FLOAT COLLAR + CEMENTO DESDE 1694 FT HASTA 1800 FT CON PARAMETROS: Q: 300 GPM, SPP: 320-760 PSI, RPM: 20-40, TQ: 1 - 5 KLBF-F
IMÉRICO SEMIDISPERSO) DE 10.6 LPG AL VUELO MIENTRAS PERFORÓ CEMENTÓ + FLOAT SHOE DESDE 1800 FT HASTA 1805 FT, CON PARAM
+ 10 FM GUAYABO DESDE 1810 FT HASTA 1815 FT. CON PARAMETROS: Q: 300 GPM, SPP: 320-760 PSI, RPM: 20-40, TQ: 1 - 5 KLBF-FT, WO
ARTA A 1790 FT Y CERRÓ PREVENTOR ANULAR. REALIZÓ PRUEBA FIT (PESO DE LODO EQUIVALENTE 13.5 LPG). AUMENTÓ PRESIÓN A 270 P
815 FT HASTA 1881 FT. (AVANCE 66 FT), ROP AVG: 132.0 FT/HR, ROP EFEC: 132.0 FT/HR. CON PARAMETROS ROTANDO: ROTO 100% Q: 650

1881 FT HASTA 2070 FT. (AVANCE: 189 FT), ROP AVG: 126.0 FT/HR, ROP EFEC: 262.5 FT/HR. PARÁMETROS ROTANDO: ROTÓ (100%), Q: 750
A POZO CON Q: 650 GPM, SPP: 950 PSI, 45 RPM, TQ:1-2 KLB*FT
O Y DESLIZANDO DESDE 2070 FT HASTA 2335 FT. (AVANCE 265 FT), ROP AVG: 88.3 FT/HR, ROP EFEC: 278.9 FT/HR. PARÁMETROS ROTANDO
SCA SUPERIOR, DESDE 2335 FT HASTA 2840 FT. (AVANCE 505 FT), ROP AVG: 59,4 FT/HR, ROP EFEC: 128.83 FT/HR. PARÁMETROS ROTANDO
AD ARENISCAS SUPERIORES DESDE 2840 FT HASTA 3590 FT. (AVANCE 750 FT), ROP AVG: 75.00 FT/HR, ROP EFEC: 133.92 FT/HR. REPASÓ CAD
AD LUTITA E DESDE 3590 FT HASTA 4120 FT. (AVANCE 530 FT), ROP AVG: 86.18 FT/HR, ROP EFEC: 58.89 FT/HR. PARÁMETROS ROTANDO: RO
AD C1 DESDE 4120 FT HASTA 4425 FT. (AVANCE 305 FT), ROP AVG: 76.25 FT/HR, ROP EFEC: 132.61 FT/HR. REPASÓ CADA PARADADA PARÁM
AD ARENISCAS DE CARBONERA DESDE 4425 FT HASTA 4470 FT. (AVANCE 45 FT), ROP AVG: 45 FT/HR, ROP EFEC: 95.74 FT/HR. REPASÓ CADA
AD ARENISCAS DE CARBONERA DESDE 4470 FT HASTA 5304 FT. (AVANCE 834 FT), ROP AVG: 32.75 FT/HR, ROP EFEC: 52.52FT/HR. REPASÓ C
AD ARENISCAS DE CARBONERA DESDE 5304 FT HASTA 5385 FT. (AVANCE 81 FT), ROP AVG: 23.14 FT/HR, ROP EFEC: 27.64 FT/HR. REPASÓ
ZO CON Q: 750 GPM, SPP: 1570 PSI, RPM: 50, TQ: 8-10 KLBF-FT
AD ARENISCAS DE CARBONERA DESDE 5385 FT HASTA 5473 FT. (AVANCE 88 FT), ROP AVG: 22.00 FT/HR, ROP EFEC: 26.67 FT/HR. PARÁMET
AD C2 DESDE 5473 FT HASTA 5573 FT. (AVANCE 100 FT), ROP AVG: 20.00 FT/HR, ROP EFEC: 43.10 FT/HR. PARÁMETROS ROTANDO: ROTÓ 76
AD C2 DESDE 5573 FT HASTA 5855 FT. (AVANCE 282 FT), ROP AVG: 56.4 FT/HR, ROP EFEC: 90.01 FT/HR. PARÁMETROS ROTANDO: ROTÓ (10
Ó RECIPROCANDO SARTA HASTA OBTENER RETORNOS LIMPIOS PARAMETROS: Q: 700 GPM, SPP: 1800-1780 PSI, RPM: 40-60, TQ: 5-11 KLB
AD C2 DESDE 5855 FT HASTA 6139 FT. (AVANCE 284 FT), ROP AVG: 71 FT/HR, ROP EFEC: 98.61 FT/HR. PARÁMETROS ROTANDO: ROTÓ (100%
AD C2 DESDE 6139 FT HASTA 6707 FT. (AVANCE 568 FT), ROP AVG: 28.4 FT/HR, ROP EFEC: 43.36 FT/HR. PARÁMETROS ROTANDO: ROTÓ 39
CIRCULÓ RECIPROCANDO SARTA HASTA OBTENER RETORNOS LIMPIOS PARAMETROS: Q: 860 GPM, SPP: 2300-1800 PSI, RPM: 50-60, TQ: 7.
6707 FT HASTA 4770 FT NOTA: PRESENTÓ PUNTO APRETADO A 4770 FT (MÁX OVERPULL 30 KLB). TRABAJÓ SARTA MECÁNICAMENTE ARRIB
30 GPM, SPP: 1450 PSI, RPM: 60, TQ: 5-6 KLBF-FT MAXIMO CAVING: 0.9 BPH, CAVING FINAL 0.4 BPH
770 FT HASTA 2165 FT, DE LA SIGUIENTE MANERA: LIBRE DESDE 4770 FT HASTA 4155 FT. PRESENTÓ PUNTOS APRETADOS (MÁX OVERPULL
00-680 GPM, SPP: 800-950 PSI, RPM: 30-40, TQ: 5-6 KLBF-FT. MAXIMO CAVING: 2.7 BPH, CAVING FINAL 0.5 BPH
T HASTA 1805 FT, DE LA SIGUIENTE MANERA: LIBRE DESDE 4770 FT HASTA 4155 FT. PRESENTÓ PUNTOS APRETADOS (MÁX OVERPULL: 20 KL
ASTA 650 FT. NOTA: CHEQUEÓ NIVEL ESTATICO DEL POZO, OK
FT. ASI (3) HWDP 5½" + JAR 6½" + (2) HWDP 5½" + XO+ (2) DRILL COLLAR 6 1/2" + XO.
4 Y ARME DE BHA N. 5 DIRECCIONAL POR PARTE DE WEATHERFORD
ERFICIE. REALIZÓ CHEQUEÓ DE HERRAMIENTAS DIRECCIONALES. LIMPIÓ Y REVISÓ BROCA REALIZÓ PRUEBA GAP OUT: 9 MM (GAP IN: 2
FICIE HASTA 97.56 FT ASÍ: BROCA # 4R PDC 12¼" (HALLIBURTON, TIPO: GTD56MOs, S/N: 13228587, TFA: 1.052 (7x14/32)) + MOTOR 8" (CA
FT HASTA 650 FT, ASÍ: (11) HWDP 5½" + JAR 6½" + (3) HWDP 5½".
STA 1787 FT. (ZAPATO 13 3/8" A 1805 FT).

JUSTE ROTACION, MANEJO DEL TUBERIA.


T. ASI: PRESENTÓ PUNTOS APRETADOS (MÁX OVERPULL: 20 KLB), A 3093 FT, 3139 FT, 3832 FT, 4020 FT, 4038 FT TRABAJÓ SARTA ARRIBA /AB
S PARAMETROS: Q: 380-630 GPM, SPP: 730-1000 PSI, RPM: 50, TQ: 4.0-5.0 KLBF-FT CAVING MÁXIMO: 1.8 BBL/HR, CAVING FINAL: 0.5 BBL/
T. ASI: PRESENTÓ PUNTO DE APOYO (MÁX SLACK OFF: 30 KLB), A 5408 FT. SE TRABAJÓ SARTA ARRIBA /ABAJO, SIN ÉXITO, TRABAJÓ CON B
AD C2 DESDE 6707 FT HASTA 6741 FT. (AVANCE 34 FT), ROP AVG: 13.6 FT/HR, ROP EFEC: 25.75 FT/HR. PARÁMETROS ROTANDO: Q: 850 GPM
AD C2 DESDE 6741 FT HASTA 7080 FT. (AVANCE 339 FT) PIES ROTADOS: 239 FT (70.5%), PIES DESLIZADOS: 100 FT (29.5%), ROP AVG: 28.25
AD LUTITA E3 DESDE 7080 FT HASTA 7440 FT. (AVANCE 360 FT) PIES ROTADOS: 295 FT (81.94%), PIES DESLIZADOS: 65 FT (18.06%), ROP AVG
AD T1 DESDE 7440 FT HASTA 7465 FT. (AVANCE 25 FT) PIES ROTADOS: 21 FT (84%), PIES DESLIZADOS: 4 FT (16%), ROP AVG: 25.00 FT/HR, RO
ODO N.1 Y N.2 CON 1500 PSI DURANTE 5 MINUTOS CADA UNA. OK SACÓ SARTA DE DP 5" CON BHA N. 5 DIRECCIONAL DESDE 7465 FT HAS
AD T1 DESDE 7465 FT HASTA 7475 FT. (AVANCE 10 FT) PIES ROTADOS: 10 FT (100%), ROP AVG: 10.00 FT/HR, ROP EFEC: 50 FT/HR. PARÁME

ESADA (MW: 12.8 LPG, FV: 200 SEC/QT) RECIPROCANDO SARTA PARÁMETROS: Q: 830 GPM, SPP: 1800-1900 PSI, RPM: 40, TQ: 12 KLBF*FT.
7475 FT HASTA 4819 FT.
60, SPP: 820/1200 PSI, SIN ÉXITO OBSERVANDO QUE LA PRESION NO SE MANTIENE ESTABLE, LIMPIÓ FILTROS DE LAS BOMBAS AGREGÓ AN
4819 FT HASTA 1805 FT. - PRESENTÓ PUNTO APRETADO (MÁX OVERPULL: 20 KLB) A 3847 FT. TRABAJÓ SARTA ARRIBA/ABAJO, CON ÉXITO
ABAJO DE ALTURAS
ASTA 650 FT.
FT ASI: (3) HWDP 5½" + JAR 6½" + (2) HWDP 5½" + XO+ (2) DRILL COLLAR 6 1/2" + XO. A 434 FT REALIZÓ CHEQUEO NIVEL ESTATICO DEL PO
5 Y ARME DE BHA N. 6 DIRECCIONAL POR PARTE DE WEATHERFORD.
ERFICIE ASI: NMDC 8" + HEL-BAP + ESTABILIZADOR 11½" + MOTOR 8" (CAMISA 11¾", 0.17 rev/gal, BH: 1.5°) + BROCA #4R PDC 12¼". QUEB
FICIE HASTA 97 FT ASÍ: BROCA #4RR PDC 12¼" (HALLIBURTON, TIPO: GTD56MOs, S/N: 13228587, TFA: 1.052 (7x14/32)) + MOTOR 8" (CAM
T HASTA 649 FT, ASÍ: (2) DC 6 1/2" + CROSS OVER + (12) HWDP 5½" + JAR 6½" + (3) HWDP 5½". NOTA: PESO POR DEBAJO DEL MARTILLO:
**LLENÓ TUBERÍA CON Q: 300 GPM, SPP: 240 PSI.

T. LLENÓ TUBERÍA A 3000 FT CON Q: 240 GPM, SPP: 230 PSI. LLENÓ TUBERÍA A 4050 FT CON Q: 270 GPM, SPP: 230 PSI.
GPM, SPP: 1200 PSI. RPM: 50, TQ: 4-5 KLBF*FT ECD: INICIAL 12.36 LPG. FINAL: 12.08 LPG
T. PRESENTÓ PUNTO DE APOYO (MÁX SLACK OFF: 30 KLB), A 6168 FT, 6387 FT. TRABAJÓ SARTA ARRIBA /ABAJO, CON ÉXITO. BAJÓ LAVANDO
Q: 700 GPM, SPP: 1600-1700 PSI, RPM: 60, TQ: 9.0 - 10 'KLBF*FT MONITOREO CAVING: MAXIMO: 1.6 BBL/HR, FINAL: 0.4 BBL/HR ECD: INICI
AD T1 DESDE 7475 FT HASTA 7615 FT. (AVANCE 140 FT) PIES ROTADOS: 105 FT (75.0%), PIES DESLIZADOS: 35 FT (25.0%), ROP AVG: 28.0 FT/
AD LUTITA E4 DESDE 7615 FT HASTA 7777 FT. (AVANCE 162 FT) PIES ROTADOS: 91 FT (56.17%), PIES DESLIZADOS: 71 FT (43.83%), ROP AVG:
AD LUTITA E4 DESDE 7777 FT HASTA 8338 FT. (AVANCE 561 FT) PIES ROTADOS: 330 FT (58.82%), PIES DESLIZADOS: 231 FT (41.18%), ROP AV
AD LUTITA E4 DESDE 8338 FT HASTA 8533 FT. (AVANCE 195 FT) PIES ROTADOS: 80 FT (41.03%), PIES DESLIZADOS: 115 FT (58.97%), ROP AVG
: 2580-2500 PSI. RPM: 50, TQ: 10-13 KLBF*FT. SE VALIDO CON GEOLOGO WELLSITE EN POZO, PROFUNDIDAD FINAL HUECO 12.1/4" A 853
CIRCULÓ RECIPROCANDO SARTA HASTA OBTENER RETORNOS LIMPIOS PARAMETROS: Q: 880 GPM, SPP: 2500-2470 PSI, RPM: 60-70, TQ: 10
533 FT HASTA 8219 FT NOTA: OBSERVA ARRASTRE INERCIAL EN LA CONEXIÓN DE 100 KLB DE OVERPOOL
E DESDE 8219 FT HASTA 8533 FT PARAMETROS: Q: 800 GPM, SPP: 2150 PSI, RPM: 60-70, TQ: 10-14 KLBF-FT
T HASTA 7841 FT ASI: - CON CIRCULACIÓN DESDE 8535 FT HASTA 8314 FT. PARÁMETROS: Q: 800 GPM, SPP: 2100-2300 PSI - LIBRE DESD
00 GPM, SPP: 1650-1700 PSI, RPM: 60, TQ: 9.0 - 12 KLBF*FT. MONITOREO CAVING: MAXIMO: 1.9 BBL/HR, FINAL: 1.2 BBL/HR ECD: INICIO: 1
T HASTA 7746 FT ASI: - PRESENTÓ PUNTO APRETADO (MÁX OVERPULL: 30 KLB) A 7839 FT. TRABAJÓ ARRIBA/ABAJO, SIN ÉXITO REPASÓ INTE
SARTA DE LA SIGUIENTE MANERA: - PRESENTÓ PUNTO APRETADO (MÁX OVERPULL: 30 KLB) A 7677 FT. TRABAJÓ ARRIBA/ABAJO, SIN ÉXITO
T HASTA 6772 FT ASI: -BOMBEÓ PÍLDORA A 7675 FT 60 BBL - PRESENTÓ PUNTOS APRETADOS (MÁX OVERPULL: 30 KLB) A 7603 FT, 7526
50 GPM, SPP: 1650-1780 PSI, RPM: 55, TQ: 12.0 - 15.0 KLBF*FT MONITOREO CAVING: MAXIMO: 5.1 BBL/HR, FINAL: 2.0 BBL/HR ECD: INICI
DE 12¼" DESDE 6772 FT HASTA 4050 FT ASI: - CON CIRCULACIÓN Y ROTACIÓN MODERADA DESDE 6772 FT HASTA 6393 FT (PARMETRO
Ó HASTA RETORNOS LIMPIOS PARA REDUCIR TREN DE INCREMENTO DE ARRASTRE CON LOS SIGUIENTES PARÁMETROS: (Q: 760 GPM, SPP:
12¼" LIBRE DESDE 4050 FT HASTA 2039 FT
TROS: Q: 480 GPM, SPP: 520 PSI, RPM: 25, TQ: 1-2 KLBF*FT) SACÓ SARTA DE PERFORACIÓN + BHA N. 6 DIRECCIONAL EN HUECO ABIERTO 1
DESDE 1805 FT HASTA 650 FT. NOTA: REALIZÓ SIMULACRO DE PATADA DE POZO
ASI: (3) HWDP 5½" + JAR 6½" + (2) HWDP 5½" + XO+ (2) DRILL COLLAR 6 1/2" + XO. A 637 FT REALIZÓ CHEQUEO NIVEL ESTATICO DEL POZO
6 DIRECCIONAL POR PARTE DE WEATHERFORD
FICIE ASI: NMDC 8" + HEL-BAP + ESTABILIZADOR 11½" + MOTOR 8" (CAMISA 11¾", 0.17 rev/gal, BH: 1.5°) + BROCA #4RR PDC 12¼". QUEBR
AR BUSHING. DESARMÓ HERRAMIENTAS

NTAS PARA MANEJO DE CASING DE 9 5/8" POR PARTE DEL PERSONAL DE WEATHEFORD

EVESTIMIENTO DE 9 5/8" POR PARTE DEL PERSONAL DE WEATHERFORD.


E SUPERFICIE HASTA 2960 FT ASÍ: -LEVANTÓ JUNTA N. 1 CON ZAPATO RIMADOR PRE-INSTALADO, APLICÓ SOLDADURA LÍQUIDA Y TORQU
ARAMETROS Q: 420 GPM, SPP: 280-150 PSI.) MONITOREO CAVING: MAXIMO: 0.3 BBL/HR, FINAL: 0.1 BBL/HR
T HASTA 4076 FT NOTAS: -TOMÓ PARÁMETROS DE REFERENCIA A 3000 FT ASI: P/UP 150 KLB - S/OFF 135 KLB - R/W 140 KLB, R
ARAMETROS: Q: 410 GPM, SPP: 320-160 PSI.) (PARÁMETROS DE REFERENCIA A 4080 FT : P/UP 190 KLB - S/OFF 160 KLB - R/W 172 KLB, RPM
T HASTA 6000 FT. -ROMPIÓ GELES A 4500 FT (PARAMETROS: Q:210 GPM Y SPP: 270-200 PSI, RPM: 30, TQ: 4.0 KLB*FT. P/UP 220 KLB - S/OF
OR CON Q:400 GPM Y SPP: 280-250 PSI.
T HASTA 7000 FT -ROMPIÓ GELESA 6500 FT (PARAMETROS: Q:200-400 GPM Y SPP: 350-390 PSI)
ARAMETROS: Q: 400 GPM, SPP: 520-350 PSI) TOMÓ PARÁMETROS DE REFERENCIA A 7000 FT ASI: P/UP 320 KLB - S/OFF 205 KLB MONITOR
T HASTA 7500 FT
ARAMETROS: Q: 400 GPM, SPP: 460- 280 PSI.) TOMÓ PARÁMETROS DE REFERENCIA A 7500 FT ASI: P/UP 350 KLB - S/OFF 240 KLB - R/W 28
FT HASTA 8360 FT - ROMPIÓ GELES A 8000 FT (PARAMETROS: Q:400 GPM Y SPP: 400-380 PSI) - PRESENTÓ APOYO A 8296 FT ENTRE 40 - 45
ARAMETROS: Q: 500-520 GPM, SPP: 500-440 PSI.) MONITOREO CAVING: MAXIMO: 1.5 BBL/HR, FINAL: 0.3 BBL/HR
ESENTANDO RESTRICCIÓN. CON CIRCULACIÓN (PARAMETROS: Q: 300-250 GPM, SPP: 250-460 PSI.) NOTA: TRABAJÓ SARTA MECANICAMEN
MENTE CON CIRCULACIÓN DESDE 8360 FT HASTA 8528 FT (PARAMETROS: Q: 260-550 GPM, SPP: 380-700 PSI.) MONITOREO CAVING: MAXI
Q: 400-600 GPM, SPP: 180-300 PSI) MONITOREO CAVING: NO SE OBSERVAN CAVING EN SUPERFICIE
Q: 400-600 GPM, SPP: 180-300 PSI) MONITOREO CAVING: NO SE OBSERVAN CAVING EN SUPERFICIE
TIMIENTO DE 9 5/8" POR PARTE DE HALLIBURTON SIMULTANEAMENTE CONTINUÓ CIRCULANDO POZO CON CON Q: 600 GPM, SPP: 300-38
Q:600 GPM, SPP: 380 PSI) MONITOREO CAVING: NO SE OBSERVAN CAVING EN SUPERFICIE.

GPM, SPP: 590 PSI.) SIMULTANEAMENTE PRE-MEZCLÓ 100 BBL DE LECHADA PRINCIPAL DE 17 LPG EN UNIDAD DE CEMENTACIÓN DE HALLIB
GRAMA: BOMBEÓ 40 BBL DE LAVADOR MUD FLUSH DE 8.4 LPG A 5 BPM, SPP: 270-340 PSI BOMBEÓ 80 BBL DE ESPACIADOR MECANICO CL

W LINE.SOLTÓ Y LEVANTO SET DE PREVENTORAS.


Y EN ALTURA
IATA. SE PRESENTAN FUERTES LLUVIAS.
R HANDING PLATE Y CORTE DE REVESTIMIENTO.

REVESTIMIENTO DE 9 5/8". INSTALÓ HERRAMIENTAS PARA CORTE DE REVESTIMIENTO. CORTÓ Y BISELÓ REVESTIMIENTO DE 9 5/8". RETIRÓ

Ó PRUEBA DE SELLO CON 2000 PSI X 15 MIN. OK


REVENTORAS SOBRE SECCIÓN "B".
SARTA DE PRUEBA CON TEST PLUG + PUP JOINT + (1) JUNTA DP 5 1/2". REALIZÓ PRUEBA DE SET BOP's 13 5/8" -5M ASI: - PROBÓ PEGUES E
G E INSTALÓ WEAR BUSHING. SACÓ Y QUEBRÓ SARTA DE PRUEBA
RAMIENTAS DE CORRIDA DE REVESTIMIENTO DE 9 5/8"
9 5/8" (SPIDER Y HERRAMIENTAS DE MANEJO DE LA EMPRESA WHEATHERFORD).
ROTATIVA DEL SISTEMA MPD POR PARTE DEL PERSONAL DE HALLIBURTON.
OTATIVA CON LAS VÁLVULAS DEL FLOW LINE Y HRC DEL SISTEMA MPD. - INSTALÓ TORNILLERÍA DE LA UNIÓN DE LA CABEZA DE ROTATIVA Y
- INSTALÓ MANGUERAS DE VÁLVULAS HIDRÁULICAS. - ARMÓ MANGUERA 6" DE FLOW LINE QUE VA A LA CABEZA ROTATIVA.
ONDICIONÓ LÍNEA KILL LINE PARA LLENADO DE LÍNEAS DE SUPERFICIE. REALIZÓ PRUEBA LÍNEA PRIMARIA, SECUNDARIA Y RCD CON 300 P
7 CONVENCIONAL
1/2" ASÍ: SENTÓ EMPAQUE BEARING SOBRE CABEZA ROTATIVA; BAJÓ TUBERÍA DP 5 1/2" ENGANCHANDO Y PASANDO POR DENTRO DEL EM
BROCA PDC 8 1/2" (TIPO: MSi616BPXX, S/N: QF 3835, JETS: 6X12/32", TFA: 0.663) + BIT SUB 8 1/2" + (1) DC 6 1/2" + ESTABILIZADOR 8 1/4"
SIN OBSERVAR COMPORTAMIENTO DE ESTABILIZACIÓN EN LAS TRES BOMBAS.
67 FT. NOTA: SE OBSERVA FUGA POR MALA SOLDADURA EN FLOW LINE.
SE PRESENTA SOLDADOR A LAS 15:00 HRS PERO NO FUE POSIBLE REALIZAR REPARACIÓN POR FALLA EN MOTOSOLDADOR DEL CARRO TALL
NDA SUSPENDER LABORES DE FORMA INMEDIATA. BUSCAR LUGARES SEGUROS
PRESENCIA DE FUGA.

8000 FT. LLENÓ TUBERÍA CADA 1500 FT


FT HASTA 8433 FT (TOC) PARÁMETROS: Q: 250 GPM, SPP: 280 PSI, RPM: 40, TQ: 9 - 10 KLBF-FT
PSI DURANTE 30 MIN. OK
R- CONSOLA DE PERFORADOR) POR DIFERENCIA EN LECTURAS DE MANOMETROS DE PRESION. REEMPLAZÓ TRANSMITER, LIMPIEZA DE LIN
UT Y PERFORAR FASE 8 1/2" CON SISTEMA MPD MIENTRAS CIRCULÓ POZO A 8416 FT CON: Q: 180-250 GPM, SPP: 200-280 PSI
LLAR FLOTADOR, CEMENTO Y ZAPATO FLOTADOR. PARÁMETROS: Q: 250 GPM, SPP: 250 - 300 PSI, RPM: 40, TQ: 13 - 15 KLBF-FT, WOB: 5 - 10
A 8533 FT. PARÁMETROS: Q: 250 GPM, SPP: 250 - 300 PSI, RPM: 40, TQ: 13 - 15 KLBF-FT, WOB: 5 - 10 KLB. NOTA: SE OBSERVÓ 70% CEMENT
DAD LUTITA E4 DESDE 8533 FT HASTA 8540 FT. (AVANCE 7 FT), ROP AVG: 14.0 FT/HR, ROP EFEC: 14.0 FT/HR. PARÁMETROS: Q: 240-260 GPM
N: Q: 250 GPM, SPP: 250 PSI, RPM: 40, TQ: 11 - 12 KLBF-FT.

LO Y VÁLVULA NRV
22 FT. RETIRÓ CAMPANA DE VIAJE E INSTALÓ ELEMENTO DE SELLO DE RCD.
PROFUNDIDAD A LA CUAL CONECTÓ VÁLVULA NRV. TOMO PESOS SARTA MIENTRAS EL CUERPO DEL TUBO ESTÁ EN EL ELEMENTO DE SELLO
GENO AL SISTEMA ACTIVO, ASÍ: BOMBEÓ NITRÓGENO GRADUALMENTE ASÍ: Q LIQ (GPM) Q GAS (SCFM) SPP (PSI) TIEM (MIN) 230
T HASTA 8608 FT CON ROP CONTROLADA (10 FT/HR). AVANCE 68 FT, 100 % ROTANDO, ROP AVG: 9.71 FT/HR, ROP EFEC: 11.56 FT/HR. PARÁ
GENO, LEVANTÓ Y SACÓ SARTA DE DP 5 1/2" DESDE 8608 FT HASTA 8577 FT, SUSPENDIÓ CIRCULACIÓN, REALIZÓ CAMBIO DE CONEXIÓN A
Q GAS: 950 SCFM, SPP: 320 PSI, P.INY: 500 PSI, RPM: 12, TQ: 15 KLBF-FT, WOB:3-5 KLB, MW:8.8 PPG Y ECD: 8.0 PPG.
DAD T2 DESDE 8608 FT HASTA 8732 FT , CON ROP CONTROLADA (15 FT/HR). AVANCE: 124 FT, ROP AVG: 13.78 FT/HR, ROP EFEC: 14.59 FT/H
E 8732 FT HASTA 8920 FT, CON ROP CONTROLADA (20 FT/HR). AVANCE: 188 FT, 100 % ROTADO, ROP AVG: 19.78 FT/HR, ROP EFEC: 22.57 FT
RIOR DESDE 8920 FT HASTA 9070 FT, CON ROP CONTROLADA (30 FT/HR). AVANCE: 150 FT, 100 % ROTADO, ROP AVG: 21.95 FT/HR, ROP EF
ARÁMETROS: Q LIQ: 220 GPM Y Q GAS: 950 SCFM, SPP: 500 PSI, RPM: 40 , TQ: 15 KLBF*FT.
9070 FT HASTA 8481 FT. ( CASING SHOE 9 5/8" 8528 FT)
CIÓN DESDE 8549 FT HASTA 9070 FT (TD), CON PARÁMETROS: Q LIQ: 190-200 GPM Y Q GAS: 900 SCFM, SPP: 420-650 PSI, RPM: 30-40, TQ
RÁMETROS: Q LIQ: 220 GPM Y Q GAS: 950 SCFM, SPP: 700 PSI, RPM: 30-40, TQ: 9-10 KLBF-FT.
3% DE VOLUMEN LUBRICANTE , CON PARÁMETROS: Q LIQ: 230 GPM, SPP: 260-0 PSI, RPM: 20 , TQ: 9-10 KLBF-FT. NOTA: DETUVO BOMBEO
3% DE VOLUMEN LUBRICANTE PARÁMETROS: Q LIQ: 220 GPM, SPP: 0 PSI, RPM: 20, TQ: 8-9 KLBF-FT.
9070 FT HASTA 8448 FT.
E INSTALAR CAMPANA.
OR ALTA PRESENCIA DE NITRÓGENO, (LLENÓ CON 9.2 BBL). DESCONECTÓ Y QUEBRÓ VALVULA NRV. QUEBRÓ SENCILLO DE DP 5½" PARA CA
DE HALLIBURTON
8 FT HASTA 596 FT. REALIZÓ REGISTRO ECHOMETER, ASÍ: A 7470 FT, NIVEL A 780 FT. (LLENÓ CON 9.2 BBL) A 6526 FT, NIVEL A 800 FT. (LLE
5 1/2" + DRILLING JAR 6 1/2" + (12) HWDP 3 1/2" + CROSS OVER + (3) DC 6 1/2" + SAVER SUB + FLOAT SUB + STAB 8 1/4" + (1) DC 6 1/2" +
A DE REGISTROS ELÉCTRICOS.
PLE COMBO (GR-MDN-MPD-MMR-MLL-SP-CAL) INSTALÓ FUENTES RADIOCTIVAS. PROBÓ SONDA EN SUPERFICIE. OK.
AL-SP) DESDE SUPERFICIE HASTA 9070 FT. NOTA: LONGITUD DE LA SARTA: 108.40 FT, PESO SARTA: 0.84 KLB .
DA DESDE 9070 FT HASTA 8522 FT. SECCIÓN REPETIDA REGISTRADA DESDE 8550 FT HASTA 8750 FT.
DE 9070 FT HASTA SUPERFICIE
MR-MLL-SP-CAL).
N (MDT). PROBÓ HERRAMIENTAS. OK.
PERFICIE HASTA 9070 FT.
N PRE. FORM RESULTADO (FT) (PSI) *** 8540 ------ NO ESTABILIZADO 8560
GISTÓ 14 PUNTOS DE PRESIÓN DE 20 EN TOTAL 4 PUNTOS NO ESTABILIZADOS. PROFUN PRE. FORM RESULTADO (FT)
MFT) DESDE 8991 FT HASTA SUPERFICIE.
ESIÓN -MFT Y RETIRÓ UNIDAD DE REGISTROS
UP JOINT NC 50 X XT 54 CON 30 KLB, BAJÓ A LA PLANCHADA .
ERRAMIENTAS DE MANEJO DE LINER DE 7" POR PARTE DEL PERSONAL DE ITS.

IDERADA POR PESONAL DE ITS. DEFINIÓ ROLES Y RESPONSABILIDADES.


STA 91 FT ASÍ: LEVANTÓ JUNTA N.1 DE LINER 7" CON ZAPATO FLOTADOR, APLICÓ SOLDADURA LÍQUIDA Y TORQUEÓ CON 16 KLBF*FT, CONE
DEL COLGADOR DE LINER POR PARTE DEL PERSONAL DE HALLIBURTON
BR + SETTING TOOL + PUP JOINT + CROSSOVER NC50 PIN x XT54 BOX+ PUP JOINT) A ÚLTIMA JUNTA DE LINER 7". REGISTRÓ PESOS DE LA SA

DESDE 745 FT HASTA 6136 FT NOTAS: -LLENÓ POZO A 1694 FT. TOMÓ PESOS DE LA SARTA ASÍ: P/ UP: 88 KLB, R/W 88 KLB, S/ OFF: 85 KLB
STIDO 9?" DESDE 6136 FT HASTA 8407 FT NOTAS: -LLENÓ POZO A 6425 FT. TOMÓ PESOS DE LA SARTA ASÍ: P/ UP: 208 KLB, R/W: 190 KLB, S
A E INSTALAR BEARING.TOMÓ PARÁMETROS A 8407 FT ASÍ: Q: 100-120 GPM, SPP: 180-200 PSI,TOMÓ PESOS DE LA SARTA ASÍ: CON CIRCU
N TUBERÍA DP 5½" EN HUECO REVESTIDO 9?" DESDE 8407 FT HASTA 8528 FT
RTO 8½" CON CIRCULACIÓN DESDE 8528 FT HASTA 9070 FT , CON PARÁMETROS: Q: 60-80 GPM, SPP: 150-210 PSI.
80 PSI, RPM: 20, TQ: 12 KLBF *FT.

IVA CON PARÁMETROS: Q: 240 GPM, QGAS: 950 SCFM , SPP: 990-550 PSI, RPM: 15-30, TQ: 12 KLBF *FT

SICIONO SARTA A 9065 FT (CASING POINT). BOMBEÓ A 2 BPM DESDE UNIDAD DE CEMENTACIÓN HASTA 5500 PSI X 5 MIN. OBSERVÓ RETO
NTO CON 30 BBL PILDORA ABRASIVA DE 6 LB/BBL CON Q; 460-150 GPM Y SPP: 750-50 PSI .SE OBSERVÓ RETORNOS DE TREN PREFLUJOS, ES

O E INSTALÓ CAMPANA DE VIAJE

MECÁNISMO DE LIBERACIÓN DE LA CONTIGENCIA OK, COLLET FINGEREDS RETRAIDOS, PUERTOS ALINEADOS, Y WIPER PLUG LIBERADO. HE
A ROTATIVA Y LINEA DE FLOTE (MPD)
ATORIA Y LINEA DE FLOTE. -RETIRÓ MANGUERA 6" DE FLOW LINE DE LA CABEZA ROTATIVA -DESCONECTÓ MANGUERAS DE VÁLVULAS H
OSS OVER + BIT SUB + (2) DC 8" + (1) HWDP 5 ½" NOTA: LEVANTÓ Y UBICÓ MOUSE HOLE EN AREA DE MESA ROTARIA.
RUCTURA. SE REALIZÓ TRABAJO DE ACONDICIONAMIENTO CON SOLDURA, OK

DE CABLE DE PERFORACIÓN
ALIZÓ EVENTO ODR DEL CHIC 218 EL 11-06-19 A LAS 24:00 HRS
00 % DE CIERRE DE ACCIONES IMPEDITIVAS, LUEGO DE ESTABLECER COMPROMISOS PARA ASEGURAMIENTO DE ABASTECIMIENTO DE ACPM

45.26 FT/HR , CON LOS SIGUIENTES PARÁMETROS: Q: 130-200 GPM, SPP: 45-67 PSI, RPM: 45-70, TQ: 0.5-2.8 KLBS.FT, WOB: 5- 14 KLB. REP
A: 69.11 FT/HR , CON LOS SIGUIENTES PARÁMETROS: Q: 200-390 GPM, SPP: 70-180 PSI, RPM: 60-70, TQ: 0.5-2.5 KLBS.FT, WOB:10-15 KLB.
1 PPG PARA VIAJE A SUPERFICIE, PARA SEGURIDAD POR ALTO NIVEL FREATICO DE LAZONA.
(TIPO HR1GJMRS, SN: 1479882, TFA: 1.169 IN² (3X20/32 & 1X18/32 IN2), CALIFICACIÓN IADC BROCA: 0-1-NO-A-E-I-NO-BHA, REVOLUCION

4?", 0.12 REV/GAL, BH: 1.5°) + PIN - PIN + TOOL CARRIER 8" + NMDC 8".

OS VECES CADA PARADA. PARÁMETROS ROTANDO: ROTÓ 230 FT (75%), Q: 450 - 550 GPM, SPP ON : 500 PSI, SPP OFF: 300 PSI, RPM: 40 -

111.02 FT/HR. REAPASÓ CADA PARADA. PARÁMETROS ROTANDO: ROTÓ 162 FT (39.3%), Q: 550-800 GPM, SPP ON: 700-1200 PSI, SPP OFF

N + BROCA PDC 17 1/2 IN N° 2 (NOV, TIPO: TFFX519S, S/N: A248665, TFA: 0.907 IN² (7X13/32 NDS), CALIFICACIÓN: 2-3-LT-G-X-1-CT-DTF. OB

MISA 15?", 0.12 rev/gal, BH: 1.5°) + PIN - PIN + TOOL CARRIER 8" + NMDC 8".

ÁMETROS ROTANDO: ROTÓ 506 FT (60.2%), Q: 600-800 GPM, SPP ON: 800-1500 PSI, SPP OFF: 700-1050 PSI, RPM: 40-60, TQ: 3-10 KLBF-F
X 10 MIN,OK.
MENTE, SIN ÉXITO. MÁXIMO OVER PULL 20 KLBS . - CON CIRCULACION DESDE 1720 FT HASTA 971 FT CON Q: 700 GPM, SPP: 850-1050 PSI

NTE SIN EXITO. MÁXIMO OVER PULL 25 KLBS - CON CIRCULACION DESDE 1715 FT HASTA 1504 FT CON Q: 700 GPM, SPP: 850 PSI - LIBRE D

OCA #3U PDC 17½" (VAREL, TIPO: VTD519SDHU, S/N: 4011339, TFA: 0.928 (10x11/32), CALIFICACIÓN IADC BROCA 3U: 2-3-CT-A-X-I-WT-TD

DO Y PROBÓ EQUIPO DE FLOTACIÓN,OK. BAJÓ LIBRE DE 13 3/8"CSG, 54.5LB/FT, K-55 BTC, CONECTO JUNTA N.2 CON COLLAR FLOTADOR, AP
Q: 250 GPM, SPP: 130 PSI ROMPIÓ CIRCULACIÓN A 1450 FT CON: Q: 200-190 GPM, SPP: 134-80 PSI CASING SHOE: 1805 FT 41 JUNTAS DE

BEZA DE CEMENTACION @ 1805 FT CON Q: 380 GPM, SPP: 350 PSI.


160 PSI, - BOMBEÓ 275 BBL DE LECHADA DE RELLENO DE 13.6 PPG A 5.0 BPM (920 SX), 172-160 PSI - BOMBEÓ 94 BBL DE LECHADA PRINC

RE MONOBLOQUE, DSA Y BOP.

, REVISÓ ESTADO DE PIÑONES DEL EJE DE ALTA Y BAJA. NOTA: SE REALIZÓ AJUSTE INSTALACIÓN DE CAMPANA E INSTALACIÓN DE FLOW L

/4", BEND 1.5, 0.17 REV/GAL, GAP IN: 2 MM + STABA 11 1/2" + HEL-BAP +NMDC 8"
DEL FLOW LINE

SE REALIZÓ CAMBIO DE SENSORES DE PRESIÓN.

WDP 5 1/2".
1694 FT CON: Q: 200 GPM, SPP: 200-230 PSI.
PSI, RPM: 20-40, TQ: 1 - 5 KLBF-FT, WOB: 1 - 20 KLB.
00 FT HASTA 1805 FT, CON PARAMETROS: Q: 300 GPM, SPP: 320-760 PSI, RPM: 20-40, TQ: 1 - 5 KLBF-FT, WOB: 1 - 20 KLB.
PM: 20-40, TQ: 1 - 5 KLBF-FT, WOB: 1 - 15 KLB.
LPG). AUMENTÓ PRESIÓN A 270 PSI, SOSTUVO POR 10 MINUTOS, OK.
OS ROTANDO: ROTO 100% Q: 650 GPM, SPP OFF: 900 PSI, SPP ON: 1100-1300 PSI, RPM: 40-50, TQ: 2 - 5 KLBF-FT, WOB: 4 - 12 KLB. ULTIMO

ROTANDO: ROTÓ (100%), Q: 750-800 GPM, SPP OFF: 1150-1350 PSI, SPP ON: 1300-1700 PSI, RPM: 40-50, TQ: 3-6 KLBF-FT, WOB: 5-20 KLB

9 FT/HR. PARÁMETROS ROTANDO: ROTÓ 246 (93%), Q: 800 GPM, SPP OFF: 1450-1550 PSI, SPP ON: 1600-1900 PSI, RPM: 40-50, TQ: 3-5 KL
3 FT/HR. PARÁMETROS ROTANDO: ROTÓ 416 (82%), Q: 740-800 GPM, SPP OFF: 1350 PSI, SPP ON: 1750 PSI, RPM: 50, TQ: 6-8 KLBF-FT, WO
EFEC: 133.92 FT/HR. REPASÓ CADA PARADA. PARÁMETROS ROTANDO: ROTÓ 711 (94.8%), Q: 730-800 GPM, SPP OFF: 1300-1700 PSI, SPP
/HR. PARÁMETROS ROTANDO: ROTÓ 463 (87%), Q: 800-880 GPM, SPP OFF: 1650-2000 PSI, SPP ON: 1700-2400 PSI, RPM: 50-60, TQ: 5-10 K
REPASÓ CADA PARADADA PARÁMETROS ROTANDO: ROTÓ 260 (85.2%), Q: 800-880 GPM, SPP OFF: 1900-1980 PSI, SPP ON: 2100-2300 PSI
EFEC: 95.74 FT/HR. REPASÓ CADA PARADADA PARÁMETROS ROTANDO: ROTÓ 45 (100%), Q: 820 GPM, SPP OFF: 1750-1820 PSI, SPP ON: 19
ROP EFEC: 52.52FT/HR. REPASÓ CADA PARADA PARÁMETROS ROTANDO: ROTÓ 605 (73 %), Q: 600-825 GPM, SPP OFF: 1050-1900 PSI, SPP
ROP EFEC: 27.64 FT/HR. REPASÓ CADA PARADA PARÁMETROS ROTANDO: ROTÓ 23 (28.4%), Q: 720 GPM, SPP OFF: 1500 PSI, SPP ON: 1750

OP EFEC: 26.67 FT/HR. PARÁMETROS ROTANDO: ROTÓ 18 (20.5%), Q: 700-750 GPM, SPP OFF: 1450-1600 PSI, SPP ON: 1650-2000 PSI, RPM
ARÁMETROS ROTANDO: ROTÓ 76 (76%), Q: 690-720 GPM, SPP OFF: 1450 PSI, SPP ON: 1750-1950 PSI, RPM: 50, TQ: 10-12 KLBF-FT, WOB: 8
RÁMETROS ROTANDO: ROTÓ (100%), Q: 690 GPM, SPP OFF: 1450 PSI, SPP ON: 1700-2300 PSI, RPM: 50-60, TQ: 10-12 KLBF-FT, WOB: 10-22
80 PSI, RPM: 40-60, TQ: 5-11 KLBF-FT CAVING ANTES/DURANTE/DESPUES: 1.3/1.0/0.5 BBL/HR.
ÁMETROS ROTANDO: ROTÓ (100%), Q: 700-750 GPM, SPP OFF: 1500-1700 PSI, SPP ON: 1800-2150 PSI, RPM: 60, TQ: 7-13 KLBF-FT, WOB: 1
RÁMETROS ROTANDO: ROTÓ 399 (70.25%), Q: 750-880 GPM, SPP OFF: 1700-2250 PSI, SPP ON: 2100-2650 PSI, RPM: 60, TQ: 7-14 KLBF-FT
300-1800 PSI, RPM: 50-60, TQ: 7.5-12.0 KLBF-FT . SE AJUSTO PROPIEDADES DEL LODO 12.0 PPG ENTRANDO/SALIENDO, OK.
Ó SARTA MECÁNICAMENTE ARRIBA/ABAJO.

OS APRETADOS (MÁX OVERPULL: 20 KLB), TRABAJÓ SARTA ARRIBA/ABAJO, CON ÉXITO 4638 FT, 4560 FT, 4295 FT, 4288 FT, 4278 FT, 4264 FT

RETADOS (MÁX OVERPULL: 20 KLB) A 1932 FT. 1898 FT, 1855 FT, 1644 FT TRABAJÓ SARTA ARRIBA/ABAJO, CON ÉXITO

UEBA GAP OUT: 9 MM (GAP IN: 2 MM). CALIFICACIÓN IADC BROCA 4: 0-1-WT-G-X-I-NO-BHA.
1.052 (7x14/32)) + MOTOR 8" (CAMISA 11¾", 0.17 rev/gal, BH: 1.5°) + ESTABILIZADOR 11½" + HEL-BAP + NMDC 8" BAJÓ BHA N. 5 DIRECCI

38 FT TRABAJÓ SARTA ARRIBA /ABAJO, CON ÉXITO PRESENTÓ PUNTO APRETADO (MÁX OVERPULL: 30 KLB), A 3978 FT. TRABAJÓ SARTA AR
BBL/HR, CAVING FINAL: 0.5 BBL/HR
BAJO, SIN ÉXITO, TRABAJÓ CON BOMBA CON Q: 620 GPM, SPP: 1380 PSI, RPM: 50, , TQ:2.0 - 7.0 'KLBF*FT Y BAJÓ INTERVALO DESDE 5408
RÁMETROS ROTANDO: Q: 850 GPM, SPP OFF: 2150 PSI, SPP ON: 2450 PSI, RPM: 60, TQ: 9-13 KLBF-FT, WOB: 15-20 KLB. PARÁMETROS DESLI
100 FT (29.5%), ROP AVG: 28.25 FT/HR, ROP EFEC: 41.75 FT/HR. PARÁMETROS ROTANDO: Q: 750-850 GPM, SPP OFF: 1750-2300 PSI, SPP
IZADOS: 65 FT (18.06%), ROP AVG: 32.72 FT/HR, ROP EFEC: 50.70 FT/HR. PARÁMETROS ROTANDO: Q: 850 GPM, SPP OFF: 2250-2350 PSI, S
(16%), ROP AVG: 25.00 FT/HR, ROP EFEC: 40.32 FT/HR. PARÁMETROS ROTANDO: Q: 830 GPM, SPP OFF: 1750 PSI, SPP ON: 2050 PSI, RPM:
DIRECCIONAL DESDE 7465 FT HASTA 7440 FT Y REALIZÓ CHEQUEÓ DEL COMPORTAMIENTO DE PRESIÓN BAJANDO LA SARTA CADA 10 FT OB
R, ROP EFEC: 50 FT/HR. PARÁMETROS ROTANDO: Q: 850 GPM, SPP OFF: 2200 PSI, SPP ON: 2300-2500 PSI, RPM: 60, TQ: 12-14 KLBF-FT, W

00 PSI, RPM: 40, TQ: 12 KLBF*FT. CAVING ANTES: 0.2 BBL/HR, CAVING DURANTE: 0.4 BBL/HR, CAVING DESPUÉS: 0.1 BBL/HR. ECD: ANTES:

ROS DE LAS BOMBAS AGREGÓ ANTIESPUMANTE AL LODO.


ARTA ARRIBA/ABAJO, CON ÉXITO - A 3768 FT REALIZÓ CHEQUEO DE HERRAMIENTAS DIRECCIONALES CON Q : 800 GPM, SPP : 1700-1470 P

CHEQUEO NIVEL ESTATICO DEL POZO, OK

5°) + BROCA #4R PDC 12¼". QUEBRÓ HERRAMIENTA DIRECCIONAL Y BROCA. REALIZÓ PRUEBA GAP OUT: 11 MM GAP IN: 9 MM CALIFICACI
052 (7x14/32)) + MOTOR 8" (CAMISA 11¾", 0.17 rev/gal, BH: 1.5°) + ESTABILIZADOR 11½" + HEL-BAP + NMDC 8"
ESO POR DEBAJO DEL MARTILLO: 34 KLB, PESO TOTAL BHA: 36 KLB. LONGITUD TOTAL BHA: 649.81 FT. ** PRUEBA DE BHA DIRECCIONAL A

SPP: 230 PSI.

BAJO, CON ÉXITO. BAJÓ LAVANDO POR SEGURIDAD DESDE 7180 FT HASTA 7475 FT CON Q: 650-700 GPM, SPP: 1800-1570 PSI, RPM: 60, TQ
/HR, FINAL: 0.4 BBL/HR ECD: INICIO: 12.41 FINAL: 12.22 LPG
35 FT (25.0%), ROP AVG: 28.0 FT/HR, ROP EFEC: 38.67 FT/HR. PARÁMETROS ROTANDO: Q: 880 GPM, SPP OFF: 2500-2600 PSI, SPP ON: 270
ZADOS: 71 FT (43.83%), ROP AVG: 21.60 FT/HR, ROP EFEC: 32.86 FT/HR. PARÁMETROS ROTANDO: Q: 820-880 GPM, SPP OFF: 2200-2550 PS
IZADOS: 231 FT (41.18%), ROP AVG: 23.37 FT/HR, ROP EFEC: 36.67 FT/HR. PARÁMETROS ROTANDO: Q: 850-880 GPM, SPP OFF: 2200-2550
ZADOS: 115 FT (58.97%), ROP AVG: 19.5 FT/HR, ROP EFEC: 31.45 FT/HR. PARÁMETROS ROTANDO: Q: 880 GPM, SPP OFF: 2600-2700 PSI, S
DAD FINAL HUECO 12.1/4" A 8533 FT MD, ESTIMADO 5 FT ARRIBA DEL TOPE DE FORMACION T-2. ECD: INICIAL 11.98 LPG. FINAL: 12.25 LPG
500-2470 PSI, RPM: 60-70, TQ: 10-12.5 KLBF-FT CAVING ANTES: 0.5 BBL/HR, CAVING DURANTE: 0.8 BBL/HR, CAVING DESPUÉS: 0.4 BBL/HR

, SPP: 2100-2300 PSI - LIBRE DESDE 8314 FT HASTA 8219 FT. PRESENTÓ PUNTOS APRETADOS (MÁX OVERPULL: 30 KLB) A 8292 FT, 8180 FT ,
FINAL: 1.2 BBL/HR ECD: INICIO: 12.63 FINAL: 12.35 LPG
BA/ABAJO, SIN ÉXITO REPASÓ INTERVALO CON CIRCULACIÓN DESDE 7839 FT HASTA 7743 FT CON Q: 700 GPM, SPP: 1700 PSI
RABAJÓ ARRIBA/ABAJO, SIN ÉXITO REPASÓ INTERVALO CON CIRCULACIÓN DESDE 7743 HASTA 7653 FT CON Q: 400 GPM, SPP: 700 PSI, RPM
VERPULL: 30 KLB) A 7603 FT, 7526 FT, 7480 FT, 7448 FT, 7442 FT, 7334 FT. TRABAJÓ ARRIBA/ABAJO, SIN ÉXITO SACÓ CON ROTACIÓN MODE
HR, FINAL: 2.0 BBL/HR ECD: INICIO: 12.48 FINAL: 12.39 LPG
72 FT HASTA 6393 FT (PARMETROS: Q: 440 GPM, SPP: 700-800 PSI, RPM: 20-30, TQ: 12-15 KLBF-FT) - LIBRE DESDE 6393 FT HASTA 4050 FT
ARÁMETROS: (Q: 760 GPM, SPP: 1610 PSI. MONITOREO CAVING: MAXIMO: 2.5 BBL/HR, FINAL: 1.0 BBL/HR) ECD:INICIO: 12.42 FINAL: 12.3

RECCIONAL EN HUECO ABIERTO 12¼" LIBRE DESDE 2039 FT HASTA 1805 FT. A 1947 FT REALIZÓ CHEQUEO NIVEL ESTATICO DEL POZO POR

EQUEO NIVEL ESTATICO DEL POZO, OK

+ BROCA #4RR PDC 12¼". QUEBRÓ HERRAMIENTA DIRECCIONAL Y BROCA. REALIZÓ PRUEBA GAP OUT: 12 MM (GAP IN: 11 MM). CALIFICA

CÓ SOLDADURA LÍQUIDA Y TORQUEÓ CON 24 KLBF-FT, PROBÓ EQUIPO DE FLOTACIÓN. OK. -CONECTÓ JUNTA N. 2 Y TORQUEÓ, CONECTÓ JU

- S/OFF 135 KLB - R/W 140 KLB, RPM: 20-30, TQ: 2.5 - 3.0 KLB*FT. - ROMPIÓ GELESA 3500 FT (PARAMETROS: Q:200 GPM Y SPP: 180-100 P
/OFF 160 KLB - R/W 172 KLB, RPM: 20-30, TQ: 5.5 - 6.0 KLB*FT.) MONITOREO CAVING: MAXIMO: 0.2 BBL/HR, FINAL: 0.1 BBL/HR
: 4.0 KLB*FT. P/UP 220 KLB - S/OFF 175 KLB - R/W 190 KLB) -CIRCULÓ UN FONDO ARRIBA A 4970 FT HASTA OBTENER RETORNOS LIMPIOS (

20 KLB - S/OFF 205 KLB MONITOREO CAVING: MAXIMO: 0.7 BBL/HR, FINAL: 0.2 BBL/HR

50 KLB - S/OFF 240 KLB - R/W 28 KLB, RPM: 20-30, TQ: 15 - 17 KLB*FT. MONITOREO CAVING: MAXIMO: 0.3 BBL/HR, FINAL: 0.2 BBL/HR
Ó APOYO A 8296 FT ENTRE 40 - 45 KLB, TRABAJÓ MECÁNICAMENTE SIN ÉXITO. RECIPRÓ CONSTANTEMENTE LA SARTA. - BAJÓ CON CIRCULA

TRABAJÓ SARTA MECANICAMENTE DESDE 8360 FT. SE PROBÓ ROTACIÓN SIN EXITO. TOTAL JUNTAS REVESTIMIENTO 9 5/8" CORRIDAS: 91
PSI.) MONITOREO CAVING: MAXIMO: 4.6 BBL/HR, PROMEDIO: 0.7 BBL/HR NOTA: INTENTÓ ROTAR SARTA DE REVESTIMIENTO DE 9 5/

ON CON Q: 600 GPM, SPP: 300-380 PSI


DAD DE CEMENTACIÓN DE HALLIBURTON. NOTA: PROBÓ LÍNEAS DE CEMENTACIÓN CON 500 Y 4000 PSI.
BL DE ESPACIADOR MECANICO CLEANSPACER DE 13 LPG A 5 BPM, SPP: 405-365 PSI LIBERÓ BOTTOM PLUG BOMBEÓ 126 BBL DE LECHADA

REVESTIMIENTO DE 9 5/8". RETIRÓ TUBO SOBRANTE DE REVESTIMENTO DE 9 5/8".

5/8" -5M ASI: - PROBÓ PEGUES ENTRE CABEZAL DE SECCIÓN "B" Y SET BOP's 13 5/8" -5M (PARAMETROS: 300 Y 2000 PSI POR 10 MINUTO

ÓN DE LA CABEZA DE ROTATIVA Y EL PEGUE CON EL ANULAR. - REALIZÓ INSTALACIÓN DE VÁLVULA NRV Y BEARING ASSEMBLY RCD 3K - REA
CABEZA ROTATIVA.
A, SECUNDARIA Y RCD CON 300 PSI X 5 MIN Y CON 900 PSI X 10 MIN, OK.

O Y PASANDO POR DENTRO DEL EMPAQUE BEARING, SACÓ TUBERÍA DE LA CABEZA ROTATIVA Y PARÓ EN TORRE CON BEARING CONECTADO
C 6 1/2" + ESTABILIZADOR 8 1/4" + FLOAT SUB + SAVER SUB + (3) DC 6 1/2" +X-OVER + (12) HWDP 5 1/2" + DRILLING JAR 4 3/4" + (2) HWD

MOTOSOLDADOR DEL CARRO TALLER, SALE NUEVAMENTE. -SE PRESENTA SOLDADOR APROX DESDE LAS 20:00 HRS, EN ESPERA DE MEJORA

ZÓ TRANSMITER, LIMPIEZA DE LINEAS Y VALVULAS, CORRIGIÓ FUGA. NOTA: SE MONITOREÓ DURANTE EL AJUSTE DE LOS EQUIPOS Y PRUE
M, SPP: 200-280 PSI
, TQ: 13 - 15 KLBF-FT, WOB: 5 - 10 KLB NOTA: SE OBSERVÓ INTERVALOS CON VARIACIONES DE CEMENTO HASTA 70% CEMENTO BLANDO, 3
NOTA: SE OBSERVÓ 70% CEMENTO BLANDO, 30% CEMENTO DURO. FINALIZO DESPLAZAMIENTO DE AGUA/CEMENTO POR LODO PERFFLOW
HR. PARÁMETROS: Q: 240-260 GPM, SPP: 330 - 340 PSI, RPM: 40, TQ: 13 - 15 KLBF-FT, WOB: 5 - 10 KLB
O ESTÁ EN EL ELEMENTO DE SELLO: SUBIENDO: 280 KLB, BAJANDO: 160 KLB TOMO PESOS SARTA MIENTRAS EL TOOL JOINT PASA POR EL EL
M) SPP (PSI) TIEM (MIN) 230 400 400 10 230 800 550-650 15 230
HR, ROP EFEC: 11.56 FT/HR. PARÁMETROS: Q: 230 GPM, Q GAS: 1400-950 SCFM, SPP: 320 - 550 PSI, P.INY: 550-320 PSI, RPM: 45, TQ: 15 K
EALIZÓ CAMBIO DE CONEXIÓN A UNIDAD DE NITROGENO DE BACK UP.
ECD: 8.0 PPG.
3.78 FT/HR, ROP EFEC: 14.59 FT/HR. PARÁMETROS: Q: 213-230 GPM, Q GAS: 950 SCFM; SPP: 430-550 PSI, P. INY: 430-550 PSI, RPM: 45-55
: 19.78 FT/HR, ROP EFEC: 22.57 FT/HR. PARÁMETROS: Q: 230 GPM,Q GAS: 950 SCFM; SPP: 450-480 PSI,P. INY: 470-550 PSI; RPM: 60, TQ: 1
O, ROP AVG: 21.95 FT/HR, ROP EFEC: 25.95 FT/HR. PARÁMETROS: Q: 230 GPM,Q GAS: 950 SCFM; SPP: 450-500 PSI,P. INY: 430-500 PSI; RPM

SPP: 420-650 PSI, RPM: 30-40, TQ: 9-10 KLBF-FT, MW: 8.8 PPG Y ECD: 8.0 PPG.

KLBF-FT. NOTA: DETUVO BOMBEO DE NITRÓGENO ANTES DE BOMBEAR PÍLDORA LUBRICADA

RÓ SENCILLO DE DP 5½" PARA CAMBIO DE TORQUE.

L) A 6526 FT, NIVEL A 800 FT. (LLENÓ CON 27.7 BBL) A 5579 FT, NIVEL A 1400 FT, (LLENÓ CON 41.2 BBL) A 4637 FT, NIVEL A 1000 FT, (LLENÓ
B + STAB 8 1/4" + (1) DC 6 1/2" + BIT SUB 6 1/2" + BROCA PDC 8 1/2" (TIPO: MSi616BPXX, S/N: QF 3835, JETS: 6X12/32" TFA: 0.663). CALI

ERFICIE. OK.

NO ESTABILIZADO 8560 ------ NO ESTABILIZADO 8571 1039.04 OK


RESULTADO (FT) (PSI) *** 8540 ------ NO ESTABILIZADO 8560 ------ NO

ORQUEÓ CON 16 KLBF*FT, CONECTÓ FLOAT COLLAR + JUNTA N.2, APLICÓ SOLDADURA LÍQUIDA Y TORQUEÓ CON 16 KLBF-FT, LEVANTÓ JU

NER 7". REGISTRÓ PESOS DE LA SARTA ASÍ: P/ UP: 68 KLB, R/W 68 KLB, S/ OFF: 63 KLB Y BAJÓ LINER 7" N-80, 26 LB/PIE, TXP/BTC, DESDE 690

KLB, R/W 88 KLB, S/ OFF: 85 KLB -LLENÓ POZO A 2642 FT. TOMÓ PESOS DE LA SARTA ASÍ: P/ UP: 110 KLB, R/W 110 KLB, S/ OFF: 108 KLB -LL
: P/ UP: 208 KLB, R/W: 190 KLB, S/ OFF: 180 KLB -LLENÓ POZO A 7371 FT. TOMÓ PESOS DE LA SARTA ASÍ: P/ UP: 230 KLB, R/W: 215 KLB, S/
SOS DE LA SARTA ASÍ: CON CIRCULACIÓN: P/ UP: 255 KLB, R/W: 235 KLB, S/ OFF: 215 KLB, PESOS SIN CIRCULACIÓN: P/ UP: 252 KLB, R/W: 2
5500 PSI X 5 MIN. OBSERVÓ RETORNOS EN SUPERFICIE, OK. SE LIBERA PRESIÓN Y BOMBEÓ A 1 BPM DESDE UNIDAD DE CEMENTACIÓN HA
ETORNOS DE TREN PREFLUJOS, ESPACIADOR Y LECHADA NITROGENADA EN EL CATCH TANK.

DOS, Y WIPER PLUG LIBERADO. HERRAMIENTA EN BUENAS CONDICIONES. SE QUIEBRA HERRAMIENTA. SE QUIEBRA PUP JOINT DE LA CABE

CTÓ MANGUERAS DE VÁLVULAS HIDRÁULICAS -RETIRÓ TORNILLERÍA DE CABEZA RCD - DESTORQUEÓ Y RETIRÓ CABEZA ROTATIVA DEL SET
A ROTARIA.
TO DE ABASTECIMIENTO DE ACPM POR AUTORIZACIÓN DE AT, LÍDER REGIONAL, ADMINISTRADOR DE CONTRATO, INTERVENTOR Y INGENIE

-2.8 KLBS.FT, WOB: 5- 14 KLB. REPASÓ CADA PARADA. ULTIMA LITOLOGIA @ 100 FT: 90% ARENA, 10% ARCILLOLITA.
0.5-2.5 KLBS.FT, WOB:10-15 KLB. REPASÓ CADA PARADA. ULTIMA LITOLOGIA @ 250 FT: 60% ARENA, 30% ARCILLOLITA, 10% CONGLOMER

1-NO-A-E-I-NO-BHA, REVOLUCIONES TOTALES: 20046. REV ACUMULADAS: 23980.

PSI, SPP OFF: 300 PSI, RPM: 40 - 50, TQ: 1 - 3 KLBF-FT, WOB: 2 - 10 KLB. PARÁMETROS DELIZANDO: DESLIZÓ 77 FT (25%), Q: 600 GPM, SPP

M, SPP ON: 700-1200 PSI, SPP OFF: 500-900 PSI, RPM: 40-50, TQ: 1-5 KLBF-FT, WOB: 5-12 KLB. PARÁMETROS DESLIZANDO: DESLIZÓ 251 FT

CACIÓN: 2-3-LT-G-X-1-CT-DTF. OBSERVÓ SOBRETORQUE EN CONEXIONES DEL EMITTING SUB CON TOOL CARRIER Y EMITTING SUB CON N

PSI, RPM: 40-60, TQ: 3-10 KLBF-FT, WOB: 2-15 KLB. PARÁMETROS DESLIZANDO: DESLIZÓ 334 FT (39.8%), Q: 600-800 GPM, SPP ON: 700-14

N Q: 700 GPM, SPP: 850-1050 PSI NOTA: OBSERVÓ PUNTOS APRETADOS A 1650 FT, 1585 FT, 1400 FT, 1360 FT, 1280 FT, 1180 FT Y 1090 FT CO

700 GPM, SPP: 850 PSI - LIBRE DESDE 1504 FT HASTA 280 FT. NOTA: CIRCULÓ HASTA RETORNOS LIMPIOS A 655 FT, CON: Q: 770 GPM, SPP

C BROCA 3U: 2-3-CT-A-X-I-WT-TD.

A N.2 CON COLLAR FLOTADOR, APLICÓ SOLDADURA LÍQUIDA Y PROBÓ EQUIPO DE FLOTACIÓN, OK. BAJÓ CSG 13 3/8 CSG DESDE 40 FT HA
G SHOE: 1805 FT 41 JUNTAS DE CSG 13 3/8", 54.5 LB/ FT, BTC + 18 CENTRALIZADORES
MBEÓ 94 BBL DE LECHADA PRINCIPAL DE 15.6 PPG A 5.0 BPM (470 SX ), 230-261 PSI - LIBERÓ TOP PLUG REALIZÓ DESPLAZAMIENTO DES

MPANA E INSTALACIÓN DE FLOW LINE.

WOB: 1 - 20 KLB.

LBF-FT, WOB: 4 - 12 KLB. ULTIMO SURVEY: MD: 1832 FT, INC: 13.72°, AZI: 132.33°, DLS: 0.56°/100 FT. ÚLTIMA LITOLOGÍA : A 1850 FT: 90% A

, TQ: 3-6 KLBF-FT, WOB: 5-20 KLB. ULTIMO SURVEY: MD: 1927 FT, INC: 14.16°, AZI: 132.09°, DLS: 0.47°/100 FT. ÚLTIMA LITOLOGÍA : A 2050

1900 PSI, RPM: 40-50, TQ: 3-5 KLBF-FT, WOB: 5-20 KLB. PARÁMETROS DESLIZANDO: DESLIZÓ 19 FT (7%), Q: 800 GPM, SPP OFF: 1500 PSI, S
SI, RPM: 50, TQ: 6-8 KLBF-FT, WOB: 8-15 KLB. PARÁMETROS DESLIZANDO: DESLIZÓ 89 FT (18 %), Q: 740-800 GPM, SPP OFF: 1350 PSI, SPP
PM, SPP OFF: 1300-1700 PSI, SPP ON: 1450-2150 PSI, RPM: 50-60, TQ: 5-10 KLBF-FT, WOB: 2-25 KLB. PARÁMETROS DESLIZANDO: DESLIZÓ
-2400 PSI, RPM: 50-60, TQ: 5-10 KLBF-FT, WOB: 5-22 KLB. PARÁMETROS DESLIZANDO: DESLIZÓ 67 FT (13%), Q: 800-880 GPM, SPP OFF: 165
1980 PSI, SPP ON: 2100-2300 PSI, RPM: 50, TQ: 7-8 KLBF-FT, WOB: 5-20 KLB. PARÁMETROS DESLIZANDO: DESLIZÓ 45 FT (14.8%), Q: 800-8
P OFF: 1750-1820 PSI, SPP ON: 1950-2250 PSI, RPM: 50, TQ: 7-9 KLBF-FT, WOB: 8-18 KLB. SURVEY: MD: 4391 FT, INC: 25.08°, AZI: 139.38°,
M, SPP OFF: 1050-1900 PSI, SPP ON: 1500-2400 PSI, RPM: 50-60, TQ: 6-11 KLBF-FT, WOB: 5-20 KLB. PARÁMETROS DESLIZANDO: : DESLIZÓ
SPP OFF: 1500 PSI, SPP ON: 1750-2100 PSI, RPM: 50, TQ: 9-11 KLBF-FT, WOB: 8-20 KLB. PARÁMETROS DESLIZANDO: DESLIZÓ 58 FT (71.6%

PSI, SPP ON: 1650-2000 PSI, RPM: 50-60, TQ: 9-11 KLBF-FT, WOB: 8-15 KLB. PARÁMETROS DESLIZANDO: DESLIZÓ 70 FT (79.5%), Q: 700-75
M: 50, TQ: 10-12 KLBF-FT, WOB: 8-15 KLB. PARÁMETROS DESLIZANDO: DESLIZÓ 24 FT (24%), Q: 690 GPM, SPP OFF: 1450 PSI, SPP ON: 1800
0, TQ: 10-12 KLBF-FT, WOB: 10-22 KLB. SURVEY: MD: 5805 FT, INC: 23.16°, AZI: 136.73°, DLS: 0.21°/100 FT. LITOLOGÍA A 5830 FT: 80% ARCI
PM: 60, TQ: 7-13 KLBF-FT, WOB: 15-25 KLB. SURVEY: MD: 6089 FT, INC: 23.15°, AZI: 136.65°, DLS: 0.06°/100 FT. LITOLOGÍA : A 6100 FT: 60%
50 PSI, RPM: 60, TQ: 7-14 KLBF-FT, WOB: 10-25 KLB. PARÁMETROS DESLIZANDO: DESLIZÓ 169 FT (29.75%), Q: 760-880 GPM, SPP OFF: 170
NDO/SALIENDO, OK.

4295 FT, 4288 FT, 4278 FT, 4264 FT, 4250 FT, 4229 FT, 4225 FT, 4216 FT, 4211 FT, 4195 FT, 4188 FT, 4180 FT, 4175 FT, 4160 FT. CON CIRCULAC

CON ÉXITO

NMDC 8" BAJÓ BHA N. 5 DIRECCIONAL EN HUECO REVESTIDO DESDE 97.56 FT HASTA 192 FT, ASÍ: XO+ (2) DRILL COLLAR 6 1/2" + XO + (1)

), A 3978 FT. TRABAJÓ SARTA ARRIBA/ABAJO, SIN ÉXITO.

Y BAJÓ INTERVALO DESDE 5408 FT HASTA 5479 FT MD. PRESENTÓ PUNTO DE APOYO (MÁX SLACK OFF: 20 KLB), A 5486 FT. TRABAJÓ SAR
B: 15-20 KLB. PARÁMETROS DESLIZANDO: Q: 750 GPM, SPP OFF: 1580 PSI, SPP ON: 1900 PSI, , WOB: 10-20 KLB. PIES ROTADOS: 11 FT (32.3
PM, SPP OFF: 1750-2300 PSI, SPP ON: 2100-2700 PSI, RPM: 60, TQ: 7-14 KLBF-FT, WOB: 10-20 KLB. PARÁMETROS DESLIZANDO: Q: 750-85
0 GPM, SPP OFF: 2250-2350 PSI, SPP ON: 2450-2600 PSI, RPM: 60-70, TQ: 7-14 KLBF-FT, WOB: 10-20 KLB. PARÁMETROS DESLIZANDO: Q: 85
1750 PSI, SPP ON: 2050 PSI, RPM: 60-70, TQ: 7-14 KLBF-FT, WOB: 10-20 KLB. PARÁMETROS DESLIZANDO: Q: 830 GPM, SPP OFF: 1770 PSI, S
AJANDO LA SARTA CADA 10 FT OBSERVANDO PRESIÓN ENTRE 1650 Y 1800 PSI. REALIZÓ PRUEBA DE PRESIÓN EN LÍNEA DEL STAND PIPE HA
SI, RPM: 60, TQ: 12-14 KLBF-FT, WOB: 10-15 KLB. SURVEY: MD: 7415 FT, INC: 17.07°, AZI: 142.14°, DLS: 0.51°/100 FT. LITOLOGÍA : A 7470 FT

SPUÉS: 0.1 BBL/HR. ECD: ANTES: 12.14 , DESPUES: 12.09 LPG MORFOLOGÍA: 40% TABULAR, 40% BLOCOSO, 20% GRUMOS. LITOLOGÍA: 70%

N Q : 800 GPM, SPP : 1700-1470 PSI, OBSERVANDO CAIDA DE PRESION DE 230 PSI DESDE 1700 PSI HASTA 1470 PSI, DURANTE 10 MIN - A 20

11 MM GAP IN: 9 MM CALIFICACIÓN IADC BROCA 4R: 0-1-WT-G-X-I-NO-DTF

PRUEBA DE BHA DIRECCIONAL A 187 FT CON Q: 650 GPM, SPP: 680 PSI.

SPP: 1800-1570 PSI, RPM: 60, TQ: 9.0 - 10 'KLBF*FT PRESENTÓ PUNTO DE APOYO (MÁX SLACK OFF: 20 KLB), A 7430 FT, 7442 FT. TRABAJÓ S
OFF: 2500-2600 PSI, SPP ON: 2700-2900 PSI, RPM: 50, TQ: 9-13.5 KLBF-FT, WOB: 5-22 KLB. PARÁMETROS DESLIZANDO: Q: 860-880 GPM, S
880 GPM, SPP OFF: 2200-2550 PSI, SPP ON: 2400-2850 PSI, RPM: 50-60, TQ: 10-13.5 KLBF-FT, WOB: 5-22 KLB. PARÁMETROS DESLIZANDO:
50-880 GPM, SPP OFF: 2200-2550 PSI, SPP ON: 2600-2900 PSI, RPM: 50-60, TQ: 10-14 KLBF-FT, WOB: 5-20 KLB. PARÁMETROS DESLIZANDO:
GPM, SPP OFF: 2600-2700 PSI, SPP ON: 2750-3000 PSI, RPM: 50-60, TQ: 12-17 KLBF-FT, WOB: 5-25 KLB. PARÁMETROS DESLIZANDO: Q: 78
ICIAL 11.98 LPG. FINAL: 12.25 LPG
HR, CAVING DESPUÉS: 0.4 BBL/HR. MORFOLOGÍA: 50% TABULAR, 20% BLOCOSO, 20% RETRABAJADO, 10% GRUMOS. LITOLOGÍA: 80% LUTI

PULL: 30 KLB) A 8292 FT, 8180 FT , TRABAJÓ ARRIBA/ABAJO, CON ÉXITO - CON CIRCULACIÓN DESDE 8219 FT HASTA 7841 FT. PARÁMETROS:

GPM, SPP: 1700 PSI


ON Q: 400 GPM, SPP: 700 PSI, RPM: 40, TQ: 9-10 KLBF-FT - CIRCULÓ POZO RECIPROCANDO SARTA CON Q: 400 GPM, SPP: 640 PSI. POSICION
XITO SACÓ CON ROTACIÓN MODERADA DESDE 7603 FT HASTA 6772 FT CON Q: 600 GPM, SPP: 1100-1300 PSI, RPM: 30, TQ: 12-15 KLBF-FT.

RE DESDE 6393 FT HASTA 4050 FT. LLENÓ TUBERÍA CADA 5 PARADAS. PUNTOS APRETADOS: 6772 FT, 6672 FT, 6577 FT, 6481 FT. MÁX. OVER
R) ECD:INICIO: 12.42 FINAL: 12.39 LPG

O NIVEL ESTATICO DEL POZO POR 10 MIN, OK MONITOREO CAVING: MAXIMO: 0.5 BBL/HR, FINAL: 0.3 BBL/HR ECD: INICIO: 12.32 FINAL: 12

2 MM (GAP IN: 11 MM). CALIFICACIÓN IADC BROCA 4RR: 0-2-CT-G-X-I-WT-TD

NTA N. 2 Y TORQUEÓ, CONECTÓ JUNTA N. 3 CON COLLAR FLOTADOR INSTALADO, APLICÓ SOLDADURA LÍQUIDA. PROBÓ EQUIPO DE FLOTACI

ROS: Q:200 GPM Y SPP: 180-100 PSI, RPM: 30, TQ: 3.0 KLB*FT; P/UP 175 KLB - S/OFF 160 KLB - R/W 166 KLB)
HR, FINAL: 0.1 BBL/HR
A OBTENER RETORNOS LIMPIOS (PARAMETROS: Q: 410 GPM, SPP: 390-200 PSI.) -ROMPIÓ GELES A 5500 FT (PARAMETROS: Q:210 GPM Y S

.3 BBL/HR, FINAL: 0.2 BBL/HR


TE LA SARTA. - BAJÓ CON CIRCULACION DESDE 8296 FT HASTA 8360 FT (PARAMETROS: Q: 300-400 GPM, SPP: 400-460 PSI.)

STIMIENTO 9 5/8" CORRIDAS: 91 JUNTAS P-110, 109 JUNTAS N80Q CENTRALIZADORES TIPO CENTEK: 40.
ARTA DE REVESTIMIENTO DE 9 5/8" SIN ÉXITO, TORQUE LIMITE 25 KLB-PIE TOTAL JUNTAS REVESTIMIENTO 9 5/8" CORRIDAS: (91) JUNTA
G BOMBEÓ 126 BBL DE LECHADA DE RELLENO EXTENDACEM DE 13.6 LPG A 5 BPM, SPP: 465-345 PSI. BOMBEÓ 32 BBL DE LECHADA PRINC

: 300 Y 2000 PSI POR 10 MINUTOS). OK - PROBÓ ANULAR VS HCR HIDRÁULICO VS VÁLVULA EXTERNA DEL KILL LINE (PARAMETROS: 300 Y 2

BEARING ASSEMBLY RCD 3K - REALIZÓ INSTALACIÓN DE LINEA PRIMARIA.

ORRE CON BEARING CONECTADO.


+ DRILLING JAR 4 3/4" + (2) HWDP 5 1/2". (PARAMETROS BHA N. 7 CONVENCIONAL: PESO POR DEBAJO DEL MARTILLO: 30 KLB, PESO TOTA

0:00 HRS, EN ESPERA DE MEJORA DEL CLIMA POR PRESENCIA DE LLUVIAS PARA REALIZAR EL TRABAJO. NOTA 2: SE EVIDENCIA DIFERENCIA

L AJUSTE DE LOS EQUIPOS Y PRUEBAS, LAS DIFERENTES LECTURAS DE LOS MANOMETROS EN ACUMULADOR, CONSOLA DEL PERFORADOR

HASTA 70% CEMENTO BLANDO, 30% CEMENTO DURO. INICIÓ DESPLAZAMIENTO DE AGUA/CEMENTO POR LODO PERFFLOW (8.8 PPG) AL V
A/CEMENTO POR LODO PERFFLOW (8.8 PPG).
AS EL TOOL JOINT PASA POR EL ELEMENTO DE SELLO: SUBIENDO: 300 KLB, BAJANDO: 180 KLB BAJÓ EN HUECO REVESTIDO DP 5½" Y BHA N
550-650 15 230 1400 450-350 OK BOMBEÓ LODO LENTAMENTE Q: 100-150-230 GPM, SPP: 75-1
Y: 550-320 PSI, RPM: 45, TQ: 15 KLBF-FT, WOB: 5 - 10 KLB, MW:8.8 PPG Y ECD: 7.5-8.0 PPG. TOPE FORMACIÓN T2: 8533 FT MD, 8048 FT T

, P. INY: 430-550 PSI, RPM: 45-55, TQ: 14-15 KLBF-FT, WOB: 5 - 10 KLB, MW: 8.8 PPG Y ECD: 8.0 PPG. ÚLTIMA LITOLOGÍA : A 8700 FT: 70% A
INY: 470-550 PSI; RPM: 60, TQ: 15-17 KLBF-FT, WOB: 5 - 12 KLB, MW: 8.8 PPG Y ECD: 8.0 PPG. TOPE K1 SUP: 8920 FT ( MD), 8424 FT (TVD)
-500 PSI,P. INY: 430-500 PSI; RPM: 60, TQ: 15-17 KLBF-FT, WOB: 12-18 KLB, MW: 8.8 PPG Y ECD: 8.0 PPG. ÚLTIMA LITOLOGÍA : A 9070 FT:

4637 FT, NIVEL A 1000 FT, (LLENÓ CON 15 BBL). A 3690 FT, NIVEL A 970 FT, (LLENÓ CON 10 BBL). A 2745 FT, NIVEL A 940 FT, (LLENÓ CON 17
JETS: 6X12/32" TFA: 0.663). CALIFICACIÓN IADC BROCA: 1-0-CT-C-X-I-NO-TD. QUEBRÓ JAR 6 1/2" + SAVER SUB + ESTABILIZADOR 8 1/4" +

8560 ------ NO ESTABILIZADO 8571 1039.04 OK 8584 900.36 OK 8608

UEÓ CON 16 KLBF-FT, LEVANTÓ JUNTA N.3 CON LANDING COLLAR, APLICÓ SOLDADURA LÍQUIDA Y TORQUEÓ CON 16 KLBF-FT. PROBÓ EQUI

0, 26 LB/PIE, TXP/BTC, DESDE 690 FT HASTA 745 FT.

R/W 110 KLB, S/ OFF: 108 KLB -LLENÓ POZO A 3589 FT. TOMÓ PESOS DE LA SARTA ASÍ: P/ UP: 135 KLB, R/W 135 KLB, S/ OFF: 130 KLB -LLEN
P/ UP: 230 KLB, R/W: 215 KLB, S/ OFF: 195 KLB
ULACIÓN: P/ UP: 252 KLB, R/W: 235 KLB, S/ OFF: 220 KLB
DE UNIDAD DE CEMENTACIÓN HASTA 3231 PSI X 5 MIN REALIZÓ EXPANSIÓN, PROBÓ EXPANSIÓN DE LINER HANGER CON TENSIÓN @ 100

E QUIEBRA PUP JOINT DE LA CABEZA DE CEMENTACIÓN.

ETIRÓ CABEZA ROTATIVA DEL SET BOP 13 5/8" -5K


NTRATO, INTERVENTOR Y INGENIERO DE OPERACIÓN EL 14-05-2019 A LAS 18:00 HRS CON BHA N. 1 CONVENCIONAL EN LA TORRE ASÍ: BR

RCILLOLITA.
% ARCILLOLITA, 10% CONGLOMERADO.

ZÓ 77 FT (25%), Q: 600 GPM, SPP ON: 500 PSI, SPP OFF: 300 PSI, WOB: 2-5 KLB. ULTIMO SURVEY MD: 506 FT, INC: 0.34°, AZI: 202.22°, DLS

OS DESLIZANDO: DESLIZÓ 251 FT (60.7%), Q: 550-800 GPM, SPP ON: 700-1300 PSI, SPP OFF: 500-880 PSI, WOB: 5 - 15 KLB. ULTIMO SURVE

CARRIER Y EMITTING SUB CON NMDC PROBÓ CON TM 120 Y LLAVE DE POTENCIA, APLICANDO 60 KLF*FT DE TORQUE SIN ÉXITO, ES NECES

Q: 600-800 GPM, SPP ON: 700-1400 PSI, SPP OFF: 670-1050 PSI, WOB: 5 - 15 KLB. ULTIMO SURVEY: MD: 1731 FT, INC: 13.28°, AZI: 133.82°

FT, 1280 FT, 1180 FT Y 1090 FT CON INCREMENTO DE PRESION HASTA 150 PSI.

S A 655 FT, CON: Q: 770 GPM, SPP: 950 PSI.

CSG 13 3/8 CSG DESDE 40 FT HASTA 89 FT A 1012 FT CIRCULÓ POZO CON Q: 250 GPM, SPP: 120 PSI
G REALIZÓ DESPLAZAMIENTO DESDE ASÍ: - BOMBEÓ 5 BBL DE LECHADA PRINCIPAL DE 15.6 PPG A 4.0 BPM, 220 PSI - BOMBEÓ 10 BBL AGU

MA LITOLOGÍA : A 1850 FT: 90% ARCILLOLITA, 10% ARENA.

0 FT. ÚLTIMA LITOLOGÍA : A 2050 FT: 70% ARCILLOLITA, 30% ARENA

Q: 800 GPM, SPP OFF: 1500 PSI, SPP ON: 1650-1800 PSI, WOB: 5 - 15 KLB. ULTIMO SURVEY: MD: 2306 FT, INC: 15.96°, AZI: 133.91°, DLS: 0
00 GPM, SPP OFF: 1350 PSI, SPP ON: 1550 PSI, WOB: 10 - 18 KLB. SURVEY: MD: 2781 FT, INC: 22.9°, AZI: 136.5°, DLS: 1.2°/100 FT. LITOLOG
ÁMETROS DESLIZANDO: DESLIZÓ 39 FT (5.2%), Q: 740 GPM, SPP OFF: 1300-1400 PSI, SPP ON: 1500-1550 PSI, WOB: 2-8 KLB. SURVEY: MD:
%), Q: 800-880 GPM, SPP OFF: 1650-2000 PSI, SPP ON: 1950-2300 PSI, WOB: 5-20 KLB. SURVEY: MD: 4106 FT, INC: 27.33°, AZI: 137.98°, DLS
DESLIZÓ 45 FT (14.8%), Q: 800-880 GPM, SPP OFF: 1800-1980 PSI, SPP ON: 2100-2300 PSI, WOB: 5-30 KLB. SURVEY: MD: 4391 FT, INC: 25
4391 FT, INC: 25.08°, AZI: 139.38°, DLS: 0.14°/100 FT. LITOLOGÍA : A 4450 FT: 80% ARCILLOLITA. 20% ARENA. CAVING PROM. PERF.: 0.5 BBL/
METROS DESLIZANDO: : DESLIZÓ 229 FT (27 %), Q: 600-825 GPM, SPP OFF: 1050-1800 PSI, SPP ON: 1500-2250 PSI, WOB: 10-30 KLB.. SUR
SLIZANDO: DESLIZÓ 58 FT (71.6%), Q: 720-730 GPM, SPP OFF: 1500 PSI, SPP ON: 1800-1950 PSI, WOB: 20-35 KLB. SURVEY: MD: 5241 FT, IN

DESLIZÓ 70 FT (79.5%), Q: 700-750 GPM, SPP OFF: 1450-1600 PSI, SPP ON: 1700-2100 PSI, WOB: 15-30 KLB. SURVEY: MD: 5430 FT, INC: 21.
SPP OFF: 1450 PSI, SPP ON: 1800-1950 PSI, WOB: 10-25 KLB. SURVEY: MD: 5524 FT, INC: 22.98°, AZI: 136.69°, DLS: 1.16°/100 FT. LITOLOGÍ
. LITOLOGÍA A 5830 FT: 80% ARCILLOLITA, 10% LUTITA, 10% LIMOLITA. CAVING PROM. PERF: 0.6 BBL/HR SE OBSERVÓ AUMENTO EL PESO A
0 FT. LITOLOGÍA : A 6100 FT: 60% ARCILLOLITA, 10% LUTITA, 10% LIMOLITA. 20% ARENA, CAVING PROM. PERF: 0.5 BBL/HR
), Q: 760-880 GPM, SPP OFF: 1700-2250 PSI, SPP ON: 1800-2550 PSI, WOB: 10-30 KLB. SURVEY: MD: 6658 FT, INC: 21.22°, AZI: 136.32°, DLS

4175 FT, 4160 FT. CON CIRCULACIÓN DESDE 4155 FT HASTA 4060 FT. PARÁMETROS: Q: 710 GPM, SPP: 1300 PSI, RPM: 60, TQ: 5-6 KLBF-FT

DRILL COLLAR 6 1/2" + XO + (1) JTA HWDP 5 1/2". REALIZÓ PRUEBA DE HERRAMIENTAS DIRECCIONALES A 192 FT, 343 FT Y 525 FT CON Q:

20 KLB), A 5486 FT. TRABAJÓ SARTA ARRIBA/ABAJO, CON ÉXITO.


0 KLB. PIES ROTADOS: 11 FT (32.35%), PIES DESLIZADOS: 23 FT (67.65%), SURVEY: MD: 6658 FT, INC: 21.22°, AZI: 136.32°, DLS: 0.99°/
METROS DESLIZANDO: Q: 750-850 GPM, SPP OFF: 1750-2200 PSI, SPP ON: 2100-2300 PSI, WOB: 10-25 KLB. SURVEY: MD: 7037 FT, INC: 18.
PARÁMETROS DESLIZANDO: Q: 850 GPM, SPP OFF: 1950-2150 PSI, SPP ON: 2050-2300 PSI, WOB: 10-30 KLB. SURVEY: MD: 7320 FT, INC: 17
Q: 830 GPM, SPP OFF: 1770 PSI, SPP ON: 2070 PSI, WOB: 10-30 KLB. SURVEY: MD: 7415 FT, INC: 17.07°, AZI: 142.14°, DLS: 0.51°/100 FT. LIT
IÓN EN LÍNEA DEL STAND PIPE HASTA VÁLVULA HIDRÁULICA DEL TOP DRIVE ENTRE 1000 Y 2000 PSI EN INTERVALOS DE 5 Y 10 MINUTOS, O
1°/100 FT. LITOLOGÍA : A 7470 FT: 30% LUTITA, 30% LIMOLITA, 20% ARCILLOLITA, 10% ARENA, 10% ARENISCA. CAVING PROM. PERF: 0.2 B

O, 20% GRUMOS. LITOLOGÍA: 70% LUTITA, 30% ARCILLOLITA.

1470 PSI, DURANTE 10 MIN - A 2060 FT REALIZÓ CHEQUEO DE HERRAMIENTAS DIRECCIONALES CON Q : 680 GPM, SPP : 830 PSI, OBSERVA

B), A 7430 FT, 7442 FT. TRABAJÓ SARTA ARRIBA /ABAJO, CON ÉXITO.
DESLIZANDO: Q: 860-880 GPM, SPP OFF: 2450-2550 PSI, SPP ON: 2550-2700 PSI, WOB: 15-30 KLB. ECD: 12.22 - 12.37 LPG SURVEY: 7604 FT
KLB. PARÁMETROS DESLIZANDO: Q: 860-880 GPM, SPP OFF: 2200-2450 PSI, SPP ON: 2350-2600 PSI, WOB: 15-45 KLB. ECD: 12.00 - 12.15 LP
KLB. PARÁMETROS DESLIZANDO: Q: 760-880 GPM, SPP OFF: 1950-2450 PSI, SPP ON: 2100-2800 PSI, WOB: 15-35 KLB. ECD: 12.10 - 13.31 L
PARÁMETROS DESLIZANDO: Q: 780-880 GPM, SPP OFF: 1950-2700 PSI, SPP ON: 2150-2900 PSI, WOB: 15-35 KLB. ECD: 12.11 - 12.29 LPG SU

% GRUMOS. LITOLOGÍA: 80% LUTITA, 20% ARCILLOLITA. ECD: ANTES: 12.28 , DESPUES: 12.07 LPG SE AJUSTO PROPIEDADES DEL LOD

FT HASTA 7841 FT. PARÁMETROS: Q: 80 GPM, SPP: 2100-2000 PSI, RPM: 60, TQ: 9-13 KLBF-FT PRESENTÓ PUNTOS APRETADOS (MÁX OVE

400 GPM, SPP: 640 PSI. POSICIONÓ SARTA A 7711 FT. ** A 7711' DESCONECTÓ Y QUEBRÓ PRIMERA JUNTA DP 5 1/2" EN PARADA N. 75.
PSI, RPM: 30, TQ: 12-15 KLBF-FT. COMPORTAMIENTO ECD: 12.34 - 12.42 LPG.

2 FT, 6577 FT, 6481 FT. MÁX. OVERPULL: 30 KLB

/HR ECD: INICIO: 12.32 FINAL: 12.32 LPG

UIDA. PROBÓ EQUIPO DE FLOTACIÓN. OK Y TORQUEÓ CON 24 KLBF-FT Y BAJÓ REVESTIMIENTO EN HUECO REVESTIDO DESDE SUPERFICIE H

T (PARAMETROS: Q:210 GPM Y SPP: 300-250 PSI) -ROMPIÓ GELES A 6000 FT (PARAMETROS: Q:400 GPM Y SPP: 420-280 PSI) -TOMÓ PARÁ

SPP: 400-460 PSI.)

NTO 9 5/8" CORRIDAS: (91) JUNTAS P-110, (111) JUNTAS N80Q; CENTRALIZADORES TIPO CENTEK: 40.
MBEÓ 32 BBL DE LECHADA PRINCIPAL DE 17.0 LPG A 5 BPM, SPP= 645-490 PSI. BOMBEÓ 100 BBL DE LECHADA PRINCIPAL DE 17.0 LPG A 5 B

KILL LINE (PARAMETROS: 300 Y 2000 PSI POR 10 MINUTOS). OK - PROBÓ PIPE RAMS VS HCR VS VÁLVULA DEL KILL LINE (PARAMETROS: 300

DEL MARTILLO: 30 KLB, PESO TOTAL BHA: 35 KLB. LONGITUD TOTAL BHA: 596.36 FT).

OTA 2: SE EVIDENCIA DIFERENCIA DE LECTURAS DE PRESIÓN DE MANÓMETROS DE ACUMULADOR, CONSOLA REMOTA Y PANEL DE MESA R

OR, CONSOLA DEL PERFORADOR Y PANEL REMOTO , REPORTANDO DE MANERA CONTINUA A LA AUTORIDAD TECNICA DE TALADO Y DE CO

R LODO PERFFLOW (8.8 PPG) AL VUELO A 8520 FT


ECO REVESTIDO DP 5½" Y BHA N. 7 DESDE 8451 FT HASTA 8517 FT. ALINEANDO EL POZO PARA CIRCULAR POR EQUIPO DE MPD.
E Q: 100-150-230 GPM, SPP: 75-140-290 PSI. ESTABILIZÓ FLUJO CON 230 GPPM Y 300 PSI.
ACIÓN T2: 8533 FT MD, 8048 FT TVD ULTIMA LITILOGIA A 8590 FT: 40 % ARENISCA, 40 % ARENA, 10% LIMOLITA, 10 % ARCILLOLITA A 8594

MA LITOLOGÍA : A 8700 FT: 70% ARENA, 20% ARENISCA, 10% LIMOLITA.


UP: 8920 FT ( MD), 8424 FT (TVD) ÚLTIMA LITOLOGÍA : A 8910 FT: 50% ARENISCA, 30% LUTITA, 20% ARENA.
ÚLTIMA LITOLOGÍA : A 9070 FT: 90% LUTITA, 10% ARENISCA.

T, NIVEL A 940 FT, (LLENÓ CON 17 BBL). A 1798 FT, NIVEL A 960 FT, LLENÓ CON 5.3 BBL
ER SUB + ESTABILIZADOR 8 1/4" + BIT SUB + BROCA PDC. REALIZÓ REGISTRO ECHOMETER SIN TUBERÍA, NIVEL A 790 FT. LLENÓ CON 8.5 BB

0.36 OK 8608 881.84 OK 8617 887.54 OK 8644 899.34 OK 8651

EÓ CON 16 KLBF-FT. PROBÓ EQUIPO DE FLOTACIÓN. OK. CONTINUÓ BAJANDO LINER 7" N-80, 26 LB/PIE, TXP/BTC, DESDE 91 FT HASTA 690

W 135 KLB, S/ OFF: 130 KLB -LLENÓ POZO A 4537 FT. TOMÓ PESOS DE LA SARTA ASÍ: P/ UP: 155 KLB, R/W 150 KLB, S/ OFF: 140 KLB -LLENÓ
R HANGER CON TENSIÓN @ 100 KLB DE OVERPULL, LUEGO BAJÓ Y APLICÓ 50 KLB SLACK-OFF PARA LIBERACIÓN DE SETTING TOOL. LEVAN
NVENCIONAL EN LA TORRE ASÍ: BROCA N. 1 TRC 17 1/2", VAREL, TIPO HR1GJMRS, SN: 1479882, TFA: 1.169 IN² (3X20/32 & 1X18/32 IN2) + B

6 FT, INC: 0.34°, AZI: 202.22°, DLS = 0.14°/100FT. ÚLTIMA LITOLOGÍA : A 500 FT: 50% ARENA, 50% ARCILLOLITA.

WOB: 5 - 15 KLB. ULTIMO SURVEY: MD: 885 FT, INC: 0.46°, AZI: 203.46°, DLS: 0.23°/100 FT. CT-CT: 7.33 FT ÚLTIMA LITOLOGÍA : A 970 FT: 80

T DE TORQUE SIN ÉXITO, ES NECESARIO BAJAR A LOS RACK EL CONJUNTO APROX. 57 FT . SE REALIZÓ PRUEBA GAP OUT: 2.5 MM (GAP IN: 1

1731 FT, INC: 13.28°, AZI: 133.82°, DLS: 1.38°/100 FT. CT-CT: 11.45 FT ÚLTIMA LITOLOGÍA : A 1810 FT: 90% ARCILLOLITA, 10% ARENA
M, 220 PSI - BOMBEÓ 10 BBL AGUA DE 8.33 PPG DESDE UNID. CEMENTACIÓN A 8.0 BPM, 220-290 PSI - BOMBEÓ 190 BBL DE LODO DE 10

, INC: 15.96°, AZI: 133.91°, DLS: 0.85°/100 FT. TOPE ARENISCA SUPERIOR: 2335 FT MD / 2308 FT TVD ÚLTIMA LITOLOGÍA : A 2300 FT: 80%
136.5°, DLS: 1.2°/100 FT. LITOLOGÍA : A 2830 FT: 60% ARCILLOLITA, 20% ARENA, 20% LIMOLITA. CAVING PROM. PERF.: 0.7 BBL/HR.
PSI, WOB: 2-8 KLB. SURVEY: MD: 3537 FT, INC: 27.88°, AZI: 138.16°, DLS: 0.38°/100 FT. TOPE LUTITA E: 3590 FT MD / 3454 FT TVD LITOLOG
FT, INC: 27.33°, AZI: 137.98°, DLS: 1.19°/100 FT. TOPE CARBONERA UNIDAD C1: 4120 FT MD / 3921 FT TVD LITOLOGÍA : A 4120 FT: 70% AR
B. SURVEY: MD: 4391 FT, INC: 25.08°, AZI: 139.38°, DLS: 0.14°/100 FT. TOPE ARENISCA CARBONERA: 4425 FT MD / 4195 FT TVD LITOLOGÍ
A. CAVING PROM. PERF.: 0.5 BBL/HR
-2250 PSI, WOB: 10-30 KLB.. SURVEY: MD: 5241 FT, INC: 20.77°, AZI: 136.73°, DLS: 0.87°/100 FT. ECP PWD PERFO: 11.40 PPG LITOLOGÍAA
0-35 KLB. SURVEY: MD: 5241 FT, INC: 20.77°, AZI: 136.73°, DLS: 0.87°/100 FT. LITOLOGÍA : A 5350 FT: 40% ARCILLOLITA, 30% LIMOLITA, 30%

B. SURVEY: MD: 5430 FT, INC: 21.89°, AZI: 136.75°, DLS: 0.72°/100 FT. ECP PWD PERFO: 11.40 PPG LITOLOGÍA : A 5440 FT: 40% ARCILLOLITA
.69°, DLS: 1.16°/100 FT. LITOLOGÍA : A 5530 FT: 60% ARCILLOLITA, 30% LUTITA, 10% LIMOLITA. CAVING PROM. PERF: 0.5 BBL/HR SE PERFOR
E OBSERVÓ AUMENTO EL PESO ARRASTRE DE LA SARTA . EL VOLUMEN DE CAVING HASTA 1.3 BPH Y TAMAÑO HASTA 25 mm, DECIDE CIR
ERF: 0.5 BBL/HR
FT, INC: 21.22°, AZI: 136.32°, DLS: 0.99°/100 FT. ULTIMA LITOLOGÍA : A 6700 FT: 50% ARCILLOLITA, 50% LUTITA, CAVING PROM. PERF: 0.4 B

00 PSI, RPM: 60, TQ: 5-6 KLBF-FT LIBRE DESDE 4060 FT HASTA 3586 FT. PRESENTÓ PUNTOS APRETADOS (MÁX OVERPULL: 20 KLB), TRABAJÓ

A 192 FT, 343 FT Y 525 FT CON Q: 620/700/720 GPM, SPP: 530/700/830 PSI.

: 21.22°, AZI: 136.32°, DLS: 0.99°/100 FT. LITOLOGÍA A 6730 FT: 60% LUTITA, 30% ARCILLOLITA, 10% LIMOLITA, CAVING PROM. PERF:
B. SURVEY: MD: 7037 FT, INC: 18.48°, AZI: 138.32°, DLS: 0.27°/100 FT. ÚLTIMA LITOLOGÍA : A 7060 FT: 40% ARCILLOLITA, 40% LUTITA, 20%
LB. SURVEY: MD: 7320 FT, INC: 17.43°, AZI: 141.05°, DLS: 0.44°/100 FT. LITOLOGÍA : A 7430 FT: 90% LUTITA, 10% ARCILLOLITA. CAVING PRO
ZI: 142.14°, DLS: 0.51°/100 FT. LITOLOGÍA : A 7450 FT: 40% LUTITA, 30% LIMOLITA, 20% ARCILLOLITA, 10% ARENA. CAVING PROM. PERF: 0.
TERVALOS DE 5 Y 10 MINUTOS, OK.
ISCA. CAVING PROM. PERF: 0.2 BBL/HR ECD: 12.07 - 12.19 LPG ** CAÍDA DE PRESIÓN DE 2500 PSI HASTA 1670 PSI, EVALUA CON SERVICIO

680 GPM, SPP : 830 PSI, OBSERVANDO PRESION ESTABLE - A 2060 FT, 1805 FT REALIZÓ CHEQUEO NIVEL ESTATICO DEL POZO, OK
2.22 - 12.37 LPG SURVEY: 7604 FT MD, INC: 16.88°, AZI: 140.40°, DLS: 0.59°/100 FT. LITOLOGÍA : A 7640 FT: 60% LUTITA, 40% ARCILLOLITA.
: 15-45 KLB. ECD: 12.00 - 12.15 LPG SURVEY: MD: 7697 FT, INC: 16.89°, AZI: 138.71°, DLS: 0.53°/100 FT. LITOLOGÍA : A 7770 FT: 60% LUTITA
B: 15-35 KLB. ECD: 12.10 - 13.31 LPG SURVEY: MD: 8281 FT, INC: 14.13°, AZI: 142.53°, DLS: 0.49°/100 FT. LITOLOGÍA : A 8320 FT: 40% LUTITA
35 KLB. ECD: 12.11 - 12.29 LPG SURVEY: MD: 8480 FT, INC: 13.26°, AZI: 144.08°, DLS: 0.42°/100 FT. LITOLOGÍA : A 8533 FT: 40% LIMOLITA, 2

SE AJUSTO PROPIEDADES DEL LODO 12.2 PPG ENTRANDO/SALIENDO, OK.

Ó PUNTOS APRETADOS (MÁX OVERPULL: 30 KLB) A 8080 FT, 8022 FT, 7996 FT, 7933 FT. REPASÓ INTERVALO APRETADO HASTA PASAR LIBRE

A DP 5 1/2" EN PARADA N. 75.

REVESTIDO DESDE SUPERFICIE HASTA 1805 FT. -CONTINUO BAJANDO REVESTIMIENTO 9 5/8", P-110, TXP-BTC EN HUECO ABIERTO DESDE

Y SPP: 420-280 PSI) -TOMÓ PARÁMETROS DE REFERENCIA A 4990 FT ASI: P/UP 225 KLB - S/OFF 175 KLB - R/W 190 KLB, RPM: 20-30, TQ: 9.
ADA PRINCIPAL DE 17.0 LPG A 5 BPM, SPP= 490-600 PSI. LIBERÓ TOP PLUG. REALIZÓ DESPLAZAMIENTO CON AGUA + LODO PERFLEX ASÍ: B

DEL KILL LINE (PARAMETROS: 300 Y 2600 PSI POR 10 MINUTOS). OK - PROBÓ BLIND RAMS VS HCR MANUAL VS KILL LINE (PARAMETROS: 3

OLA REMOTA Y PANEL DE MESA ROTARIA. (ANTECEDENTE YA PRESENTADO EN EL POZO ANTERIOR CH218, SE SOLICITA REPARACION O AJU

DAD TECNICA DE TALADO Y DE CONTROL DE POZO. A LAS 20:00 HRS DESPUES DE HABER CALIBRADO ACUMULADOR Y CONSOLA DEL PERFO
POR EQUIPO DE MPD.

MOLITA, 10 % ARCILLOLITA A 8594 FT REALIZÓ PRUEBA APLICANDO CONTRAPRESION ENTRE 120-180 PSI EN EL ANULAR PARA OBSERVAR C

NIVEL A 790 FT. LLENÓ CON 8.5 BBL PARA DEJAR ECD EQUIVALENTE A 8.0 PPG.

899.34 OK 8651 922.42 OK 8661 922.98 OK 8703 ------ NO ESTA

TXP/BTC, DESDE 91 FT HASTA 690 FT. TOTAL JUNTAS LINER 7" CORRIDAS: 16 N-80, 26 LB/PIE, TXP/BTC; TOTAL CENTRALIZADORES CENTEK: 3

150 KLB, S/ OFF: 140 KLB -LLENÓ POZO A 5481 FT. TOMÓ PESOS DE LA SARTA ASÍ: P/ UP: 182 KLB, R/W 170 KLB, S/ OFF: 165 KLBFT
RACIÓN DE SETTING TOOL. LEVANTÓ 30 FT DESDE 8345 FT HASTA 8280 FT E INICIÓ CIRCULACIÓN EN DIRECTA CON Q: 120-200 GPM, SPP: 4
IN² (3X20/32 & 1X18/32 IN2) + BIT SUB 8" + (1) DC 8" + STAB 17 3/8" + (1) DC 8" . **NOTA: SE REALIZA RETROALIMENTACIÓN DE LECCIO

ÚLTIMA LITOLOGÍA : A 970 FT: 80% ARENA, 20% ARCILLOLITA A 757 BOMBEÓ 40 PÍLDORA VISCOSA DE 10.2 LPG Y 130 SEC/QT, SE TOM

EBA GAP OUT: 2.5 MM (GAP IN: 1 MM), SE OBSERVÓ MUY POCO FLUIDOA AL DRENAR EL MOTOR , JUEGO RADIAL NO SE PUDO REALIZAR P

ARCILLOLITA, 10% ARENA


BOMBEÓ 190 BBL DE LODO DE 10.6 PPG DESDE EL TALADRO A 12 BPM , 380-490 PSI - BOMBEÓ 50 BBL DE LODO DE 10.6 PPG DESDE EL T

IMA LITOLOGÍA : A 2300 FT: 80% ARCILLOLITA, 20% ARENA, CAVING PROM PERF.: 0.8 BBL/HR BOMBEÓ A 2330 FT TANDEM DE PÍLDORAS
PROM. PERF.: 0.7 BBL/HR.
90 FT MD / 3454 FT TVD LITOLOGÍA : A 3550 FT: 70% ARENA, 30% ARCILLOLITA. CAVING PROM. PERF.: 0.6 BBL/HR A 2862 FT BOMBEÓ EN
D LITOLOGÍA : A 4120 FT: 70% ARCILLOLITA. 30% LIMOLITA. CAVING PROM. PERF.: 0.8 BBL/HR A 3808 FT BOMBEÓ EN TANDEM DE PÍLDOR
5 FT MD / 4195 FT TVD LITOLOGÍA : A 4420 FT: 100% ARCILLOLITA. CAVING PROM. PERF: 0.6 BBL/HR A 4355 FT BOMBEÓ EN TANDEM DE

D PERFO: 11.40 PPG LITOLOGÍAA 5050 FT: 60% ARCILLOLITA, 30% LIMOLITA, 10% ARENISCA. CAVING PROM. PERF: 0.4 BBL/HR A 4355 FT B
ARCILLOLITA, 30% LIMOLITA, 30% LUTITA. CAVING PROM. PERF: 0.5 BBL/HR.

OGÍA : A 5440 FT: 40% ARCILLOLITA, 40% LIMOLITA, 10% LUTITA, 10% LIMOLITA. CAVING PROM. PERF: 0.5 BBL/HR A 5471 FT BOMBEÓ PÍLD
OM. PERF: 0.5 BBL/HR SE PERFORA ROTANDO A PARTIR DE 5573 FT.
MAÑO HASTA 25 mm, DECIDE CIRCULAR PARA DESCARGAR ANULAR. DOS SURVEYS TOMADOS DENTRO DE LA FORMACION C-2, EL POZOS D
UTITA, CAVING PROM. PERF: 0.4 BBL/HR BOMBEÓ PÍLDORA VISCOSA-PESADA AL VUELO A 6370 FT (30 BBL, 12.4 PPG, 180 SEG/QT) CAVING

MÁX OVERPULL: 20 KLB), TRABAJÓ SARTA ARRIBA/ABAJO, CON ÉXITO 4023 FT, 4020 FT, 4011 FT, 3980 FT, 3975 FT, 3965 FT, 3876 FT, 3644 FT

% LIMOLITA, CAVING PROM. PERF: 1.0 BBL/HR ECD PWD: 12 PPG


% ARCILLOLITA, 40% LUTITA, 20% LIMOLITA. CAVING PROM. PERF: 0.5 BBL/HR ECP PDW: 12.23
A, 10% ARCILLOLITA. CAVING PROM. PERF: 0.6 BBL/HR BOMBEÓ PÍLDORA VISCOSA AL VUELO A 7308 FT (40 BBL, 12 PPG, 190 SEG/QT) CAV
ARENA. CAVING PROM. PERF: 0.5 BBL/HR PERFORANDO A 7426 FT OBSERVÓ CAÍDA DE PRESIÓN DEL SISTEMA DE 2300 PSI HASTA 1970 P

A 1670 PSI, EVALUA CON SERVICIO DIRECCIONAL Y DECIDE SACAR BHA A SUPERFICIE Y REVISAR ENSAMBLAJE.

TATICO DEL POZO, OK


T: 60% LUTITA, 40% ARCILLOLITA. CAVING PROM. PERF: 0.6 BBL/HR TOPE FORMACIÓN CARBONERA UNIDAD "LUTITA E4" A 7615 FT MD / 7
TOLOGÍA : A 7770 FT: 60% LUTITA, 30% ARCILLOLITA, 10% LIMOLITA. CAVING PROM. PERF: 0.5 BBL/HR - AL ENTRAR EN FORMACION LUTITA
TOLOGÍA : A 8320 FT: 40% LUTITA, 40% ARCILLOLITA, 20% LIMOLITA. CAVING PROM. PERF: 0.8 BBL/HR PERFORÓ EN ROTACIÓN INTERVALO
GÍA : A 8533 FT: 40% LIMOLITA, 20% LUTITA, 20% ARCILLOLITA,10% ARENA, 10% ARENISCA CAVING PROM. PERF: 0.5 BBL/HRHR

O APRETADO HASTA PASAR LIBRE

P-BTC EN HUECO ABIERTO DESDE 1805 FT HASTA 2960 FT. NOTAS: -TOMÓ PARÁMETROS DE REFERENCIA EN EL ZAPATO ASI: P/U

R/W 190 KLB, RPM: 20-30, TQ: 9.5 - 10.0 KLB*FT. MONITOREO CAVING: MAXIMO: 0.4 BBL/HR, FINAL: 0.1 BBL/HR
ON AGUA + LODO PERFLEX ASÍ: BOMBEÓ 10 BBL DE AGUA A 8 BPM, SPP: 170 PSI DESDE UNIDAD DE CEMENTACIÓN. BOMBEÓ 550 BBL DE

AL VS KILL LINE (PARAMETROS: 300 Y 2600 PSI POR 10 MINUTOS). OK

, SE SOLICITA REPARACION O AJUSTE ).

MULADOR Y CONSOLA DEL PERFORADOR , SE DA EL AVAL PARA CONTINUAR OPERACIONES CON LAS CONDICIONES ACTUALES CON EL PRO
EN EL ANULAR PARA OBSERVAR COMPORTAMIENTO Y ESTABILIDAD EN NIVEL DEL SISTEMA DE FLUIDO DURANTE 5 MIN, NO OBSERVA PÉR

------ NO ESTABILIZADO 8712 945.96 OK 8725 ------ NO ESTABILIZADO 8749

TAL CENTRALIZADORES CENTEK: 32 + 64 STOP RIG.

70 KLB, S/ OFF: 165 KLBFT


ECTA CON Q: 120-200 GPM, SPP: 450-500 PSI TOPE LINER 7" @ 8345 FT. LANDING COLLAR 7": 8973.57 FT FLOAT COLLAR 7": 9018.07 FT FLO
RETROALIMENTACIÓN DE LECCIONES APRENDIDAS DURANTE SEGUIMIENTO DE CIERRE DE LAS ACCIONES IMPEDITIVAS, SE REALIZA SENS

10.2 LPG Y 130 SEC/QT, SE TOMÓ SURVEY A 790 FT, NO SE EVIDENCIA VARIACIÓN EN INCLINIACIÓN NI EN DIRECCIÓN ESPERADA, SE VAR

RADIAL NO SE PUDO REALIZAR POR CONTAR EN LA MESA CON EL TAMAÑO DE LLAVES DE CADENA APROPIADAS. TAMPOCO SE EVALUÓ M
E LODO DE 10.6 PPG DESDE EL TALADRO A 8 BPM , 420- PSI - BOMBEÓ 20 BBL AGUA DE 8.33 PPG DESDE UNID. CEMENTACIÓN A 2 BBL,

A 2330 FT TANDEM DE PÍLDORAS AL VUELO: DISPERSA (20 BBL) Y VISCOSA (20 BBL, 10.6 LPG, 180 SEC/QT), CAVING ANTES: 0.9 BBL/HR, CAV

6 BBL/HR A 2862 FT BOMBEÓ EN TANDEM DE PÍLDORAS AL VUELO: DISPERSA (20 BBL, 10.8 LPG, 42 SEC/QT) Y VISCOSA (20 BBL, 10.8 LPG,
BOMBEÓ EN TANDEM DE PÍLDORAS AL VUELO: DISPERSA (20 BBL 11.1 LPG, 42 SEC/QT) Y VISCOSA (20 BBL, 11.2 LPG, 200 SEC/QT), CAVIN
355 FT BOMBEÓ EN TANDEM DE PÍLDORAS AL VUELO: DISPERSA (20 BBL 11.2 LPG, 42 SEC/QT) Y VISCOSA (20 BBL, 11.2 LPG, 180 SEC/QT), C

M. PERF: 0.4 BBL/HR A 4355 FT BOMBEÓ TANDEM DE PÍLDORAS AL VUELO: DISPERSA (20 BBL 11.2 LPG, 42 SEC/QT) Y VISCOSA (20 BBL, 11

BBL/HR A 5471 FT BOMBEÓ PÍLDORA VISCOSA AL VUELODE 30 BBL CON 11.5 PPG, 180 SEG/QT, CAVING ANTES /DURANTE/ DESPUES: 0.4

E LA FORMACION C-2, EL POZOS DISMINUYE INCLINACION A RAZON DE -0.15°/100 ft; SE AJUSTA A 700 GPM CON EL OBJETIVO DE MANT
L, 12.4 PPG, 180 SEG/QT) CAVING ANTES: 0.6 BBL/HR, CAVING DURANTE: 1.1 BBL/HR, CAVING DESPUÉS: 0.4 BBL/HR ECD PWD: 11.08 -12.1

975 FT, 3965 FT, 3876 FT, 3644 FT, 3632 FT, 3618 FT, 3597 FT CON CIRCULACIÓN DESDE 3586 FT HASTA 3491 FT. PARÁMETROS: Q: 710 GPM

40 BBL, 12 PPG, 190 SEG/QT) CAVING ANTES/DURANTE/DESPUES: 1.0/1.3/0.8 BBL/HR TOPE FORMACIÓN CARBONERA UNIDAD "T1" A 744
TEMA DE 2300 PSI HASTA 1970 PSI, REVISÓ BOMBAS DE LODO, APLICÓ CAUDAL DE 420 GPM EN CADA BOMBA REGISTRANDO 600 PSI DE T
AD "LUTITA E4" A 7615 FT MD / 7161 FT TVD.
L ENTRAR EN FORMACION LUTITA E-4 @7615 ft, SE OBSERVO TENDENCIA A CONSTRUIR Y COLGAMIENTO SEVERO DE DD BHA.
ERFORÓ EN ROTACIÓN INTERVALO DE TANGENTE DE PRODUCCIÓN, TOMANDO SURVEYS DE CHEQUEO, CUYO TOPE QUEDÓ DEFINIDO A 80
M. PERF: 0.5 BBL/HRHR

EFERENCIA EN EL ZAPATO ASI: P/UP 108 KLB - S/OFF 105 KLB - R/W 107 KLB, TQ: 0.5 KLB*FT Y 30 RPM, CAUDAL 400 GPM, 120 PSI. -A 2000
ENTACIÓN. BOMBEÓ 550 BBL DE LODO A 14 BPM, SPP: 350-1800 PSI CON BOMBAS DEL TALADRO. BOMBEÓ 50 BBL DE LODO A 6 BPM, SPP

DICIONES ACTUALES CON EL PRONTO COMPROMISO DEL CIERRE PRIORITARIO DE LAS FALLAS PRESENTADAS EN EL PANEL REMOTO.
URANTE 5 MIN, NO OBSERVA PÉRDIDAS, PASANDO DE TRABAJAR CON UN ECD EQUIVALENTE DE 7.5 LPG A 8.0 LPG. AL OBSERVAR NIVEL EST

NO ESTABILIZADO 8749 902.81 OK 8790 894.93 OK 8832 960.75 OK 88


FLOAT COLLAR 7": 9018.07 FT FLOAT SHOE 7": 9065 FT
IMPEDITIVAS, SE REALIZA SENSIBILIZACIÓN CON TODO EL PERSONAL EN LA OPERACION PARA GENERAR CULTURA DE AUTO CUIDADO, AU

EN DIRECCIÓN ESPERADA, SE VARIAN PARÁMETROS Y SE INCREMENTA EL TRABAJO DIRECCIONAL. SE TOMÓ SURVEY DE CHEQUEO SIN EVID

PIADAS. TAMPOCO SE EVALUÓ MWD. NO ES POSIBLE DEFINIR EN POZO LA CAUSA RAIZ DEL PROBLEMA, ES NECESARIO EVALUAR LA COND
E UNID. CEMENTACIÓN A 2 BBL, 300-440 PSI OBSERVÓ RETORNOS DURANTE TODA LA OPERACIÓN, RETORNARON 60 BBL DE LECHADA C

, CAVING ANTES: 0.9 BBL/HR, CAVING DURANTE: 1.9 BBL/HR, CAVING DESPUÉS: 0.8 BBL/HR NOTA: A 2272 FT SE PRESENTÓ AUMENTO DE

QT) Y VISCOSA (20 BBL, 10.8 LPG, 180 SEC/QT), CAVING ANTES / DURANTE / DESPUES: 0.8 / 1.8 / 0.7 BBL/HR A 3330 FT BOMBEÓ A EN TAN
L, 11.2 LPG, 200 SEC/QT), CAVING ANTES / DURANTE / DESPUES: 0.8/2.0/0.6 BBL/HR
(20 BBL, 11.2 LPG, 180 SEC/QT), CAVING ANTES/DURANTE/DESPUES: 0.6 /1.3/0.4 BBL/HR

42 SEC/QT) Y VISCOSA (20 BBL, 11.2 LPG, 180 SEC/QT), CAVING ANTES/ DURANTE/DESPES: 0.6/1.3/0.4 BBL/HR, ECD PWD ANTES /DESPUE

ANTES /DURANTE/ DESPUES: 0.4/1.8/0.4 BBL/HR, ECD PWD ANTES /DESPUES: 11.65 /11.52 PPG;

GPM CON EL OBJETIVO DE MANTENER ESTA TENDENCIA. EN EL INTERVALO.


0.4 BBL/HR ECD PWD: 11.08 -12.10 LPG

91 FT. PARÁMETROS: Q: 710 GPM, SPP: 1230 PSI, RPM: 60, TQ: 5-6 KLBF-FT LIBRE DESDE 3491 FT HASTA 2879 FT. PRESENTÓ PUNTOS APRE

CARBONERA UNIDAD "T1" A 7440 FT MD / 6994 FT TVD. ECP PDW: 12.3


OMBA REGISTRANDO 600 PSI DE TRABAJO POR BOMBA, DECIDE CONTINUAR PERFORANDO OBSERVANDO COMPORTAMIENTO EN VALOR D
O SEVERO DE DD BHA.
UYO TOPE QUEDÓ DEFINIDO A 8076 FT CON INCLINACIÓN DE ENTRADA DE 14.57° / AZ 139.84° Y SURVEY EN LA BASE DE LA TANGENTE A 8

UDAL 400 GPM, 120 PSI. -A 2000 FT ROMPIÓ GELES. (PARAMETROS: Q:390 GPM Y SPP: 140-120 PSI, RPM: 20-30, TQ: 1 KLBF*FT. P/UP 120
EÓ 50 BBL DE LODO A 6 BPM, SPP: 1800-1820 PSI CON BOMBAS DEL TALADRO. BOMBEÓ 16 BBL DE AGUA A 3 BPM, SPP: 1828-2000 PSI DE

DAS EN EL PANEL REMOTO.


A 8.0 LPG. AL OBSERVAR NIVEL ESTABLE SE DISMINUYE EL CAUDAL APLICADO DE NITROGENO DE 1400 SCFM HASTA 950 SCFM PARA TRABA

960.75 OK 8844 946.71 OK 8861.5\t ------ NO ESTABILIZADO 8908 \t ------


R CULTURA DE AUTO CUIDADO, AUTORIDAD PARA DETENER EL TRABAJO Y LOGRAR EL CERO ES POSIBLE.

MÓ SURVEY DE CHEQUEO SIN EVIDENCIAR NUEVAMENTE VARIACIÓN INCLINIACIÓN NI EN DIRECCIÓN, A 885 FT SE TIENE UNA SEPARCIÓN

ES NECESARIO EVALUAR LA CONDICIONES TANTO LA SALIDA DE LA BROCAS Y HERRAMIENTA DIRECCIONALES EN BASE.


ORNARON 60 BBL DE LECHADA CONTAMINADA MAXIMO PESO DE 13.2-13.6 PPG; PRESIÓN FINAL DE BOMBEO 330 PSI. BACK FLOW: 1.5 B

2 FT SE PRESENTÓ AUMENTO DEL PORCENTAJE DE ARCILLA.

/HR A 3330 FT BOMBEÓ A EN TANDEM DE PÍLDORAS AL VUELO: DISPERSA (20 BBL 11.0 LPG, 49 SEC/QT) Y VISCOSA (20 BBL, 11.0 LPG, 180

L/HR, ECD PWD ANTES /DESPUES: 11.59 /11.50 PPG A 4832 FT BOMBEÓ PÍLDORA VISCOSA AL VUELO (30 BBL, 11.3 LPG, 180 SEC/QT), CA
2879 FT. PRESENTÓ PUNTOS APRETADOS (MÁX OVERPULL: 20 KLB), TRABAJÓ SARTA ARRIBA/ABAJO, CON ÉXITO 3051 FT, 3034 FT, 2949 FT,

O COMPORTAMIENTO EN VALOR DE PRESIÓN DE 2000 PSI.


EN LA BASE DE LA TANGENTE A 8281 FT INCLINACIÓN DE 14.13°/ AZ 142.53°. Y CON DOG LEGS MENORES A 1.0°/100 FT, OK BOMBEÓ PÍL

: 20-30, TQ: 1 KLBF*FT. P/UP 120 KLB - S/OFF 118 KLB - R/W 120 KLB) -TOTAL JUNTAS REVESTIMIENTO 9 5/8" CORRIDAS: 70 JUNTAS P-110,
A A 3 BPM, SPP: 1828-2000 PSI DESDE UNIDAD DE CEMENTACIÓN. PRESIÓN FINAL DE CIRCULACIÓN: 2000 PSI. SENTÓ TAPÓN CON 2500 PS
FM HASTA 950 SCFM PARA TRABAJAR CON UN ECD EQUIVALENTE DE 8.0 LPG.

BILIZADO 8908 \t ------ NO ESTABILIZADO 8934\t ------ NO ESTABILIZADO 8991\t 3251 OK


85 FT SE TIENE UNA SEPARCIÓN DE 7.3. FT Y -2° EN INCLINACIÓN,SEGÚN EL PLAN , DECIDE SACAR A SUPERFICIE PARA REVISAR HERRAMIE

ALES EN BASE.
MBEO 330 PSI. BACK FLOW: 1.5 BBL. SENTÓ TAPON 800 Y PROBÓ REVESTIMIENTO - 1200 PSI X 30 MIN. OK

VISCOSA (20 BBL, 11.0 LPG, 180 SEC/QT), CAVING ANTES / DURANTE / DESPUES: 0.5 /1.9 / 0.6 BBL/HR..

0 BBL, 11.3 LPG, 180 SEC/QT), CAVING ANTES: 0.5/1.5/0.4 BBL/HR.ECD PWD ANTES /DESPUES: 11.65 /11.52 PPG DURANTE PERFORACION
ÉXITO 3051 FT, 3034 FT, 2949 FT, 2926 FT, 2883 FT CON CIRCULACIÓN DESDE 2879 FT HASTA 2165 FT. PARÁMETROS: Q: 710 GPM, SPP: 117
ES A 1.0°/100 FT, OK BOMBEÓ PÍLDORA VISCOSA PESADA AL VUELO A 8030 FT (30 BBL, 12.8 PPG, 180 SEG/QT) CAVING ANTES: 0.6 BBL/HR,

/8" CORRIDAS: 70 JUNTAS P-110, CENTRALIZADORES TIPO CENTEK: 40.


0 PSI. SENTÓ TAPÓN CON 2500 PSI. BACK FLOW DE 5.5 BBL. PROBÓ INTEGRIDAD DEL REVESTIMIENTO CON 2500 PSI X 10 MINUTOS. OK.
ERFICIE PARA REVISAR HERRAMIENTAS.
52 PPG DURANTE PERFORACION DE ESTAS PARADAS, SE TOMA REGISTROS DE CHEQUEO, PARA EVALUAR SI EL SLIDE REPONDE AL SENTIDO
ÁMETROS: Q: 710 GPM, SPP: 1170 PSI, RPM: 60, TQ: 5-6 KLBF-FT
/QT) CAVING ANTES: 0.6 BBL/HR, CAVING DURANTE: 1.2 BBL/HR, CAVING DESPUÉS: 0.4 BBL/HR ECD: ANTES 12.31 LPG. DESPUES 12.19 LPG
N 2500 PSI X 10 MINUTOS. OK.
SI EL SLIDE REPONDE AL SENTIDO POSITIVO Y OPUESTO A LA TENDENCIA NATURAL DE LA FORMACIÓN (-1.3°/100 FT Y EN GIRO 0.7°/100
ES 12.31 LPG. DESPUES 12.19 LPG BOMBEÓ PÍLDORA VISCOSA PESADA AL VUELO A 8320 FT (30 BBL, 14.0 PPG, 180 SEG/QT) CAVING ANTE
-1.3°/100 FT Y EN GIRO 0.7°/100 FT A LA DERECHA). TRABAJO DIRECCIONAL REQUIERE TRABAJAR CON UN CAUDAL DE 700 GPM EN ROTAC
PPG, 180 SEG/QT) CAVING ANTES: 0.9 BBL/HR, CAVING DURANTE: 1.3 BBL/HR, CAVING DESPUÉS: 0.4 BBL/HR ECD: ANTES 12.23 LPG. DESP
N CAUDAL DE 700 GPM EN ROTACION, Y EN SLIDE ENTRE 750 GPM A 800 GPM.
L/HR ECD: ANTES 12.23 LPG. DESPUES 12.16 LPG