Project Report for Two Node 10gR2 (10.2.0.4.

0) Real Application Clusters


On Oracle Enterprise Linux 5 Update4

For

Prepared by

1 Private and Confidential


INDEX
Sr. No Topic Page No.
I Implementation Summary 1
Ia Objective 3
Ib Background 3
Ic Scope of work 3
Id Setup Infrastructure 4
Ie Activity Summary 4
II Sign-off 7

2 Private and Confidential


I) Implementation Summary:-

Ia) Objective:

This document details Objective and Requirement of the Project:

There were 2 phases of this Project. The 1st phase was to migrate from Single Instance QUATINS, PERFATTR,
MFUNMCY and EPFQNTS databases on SET-II RAC Setup and 2nd phase was to migrate Single Instance DEDUP,
MKTDB, APPSDB and PRUICICI databases on SET-I RAC Setup.

Ib) Background:

Based on the initial discussion and the final proposal submitted by Clover Infotech, this document outlines all the
activities carried out at ICICI Prudential Mutual Fund, Goregoan

Ic) Scope of work:

 Installation of Oracle Enterprise Linux 5.4 on four Servers


 Server Hardening on four Linux Servers as per Audit Document.
 Installation of Oracle Clusterware with latest patch set.
 Installation of Oracle Database Software with latest patch set.
 Applying Opatch for Bug Fixes.
 Creation of ASM Disk group as per requirement.
 Creation of RAC Database as per requirement.
 Migration of Single Instance Production databases to RAC Databases for UAT release.
 Performing TAF Testing.
 Migration of Single Instance Production databases to RAC database for Production Go-Live
 Configuration and Testing of DataGuard (EMC SAN Replication) at DR Site.

3 Private and Confidential


Id) Setup Infrastructure:
 Total No. of Servers: 4
 OS Version: Oracle Enterprise Linux 5.4
 Oracle Version: 10gR2 (10.2.0.4.0)
 No. of CPU: 24
 Memory size: 64 GB

Ie) Activity Summary:

Sr. No Activity Carried out by Status

SET – I (QUANTIS, PERFATTR, MFUNDMCY and EPFQNTS)

1. Installation of Oracle Enterprise Linux 5.4 on two nodes. CIPL Completed

2. OS Hardening on two nodes as per Audit Document. CIPL Completed

Verifying and sorting out the installation pre-requisites for Oracle 10g
3. CIPL / ICICI Pru Completed
RAC

4. Installation of Oracle 10g CRS on both the cluster nodes CIPL Completed

Installation of 10.2.0.4.0 patch on CRS homes on both the cluster


5. CIPL Completed
nodes
Installation of Oracle Database 10.2.0.1.0 software on both cluster
6. CIPL Completed
nodes

Installation of Oracle Database 10.2.0.4.0 patch on Database homes on


7. CIPL Completed
both cluster nodes

8. Applying Opatch for Bug Fixes. CIPL Completed

4 Private and Confidential


Creation of Different ASM Diskgroup for Datafiles and Redolog files for
9. CIPL Completed
each database.

10. Creation of RAC Databases CIPL Completed

11. Configured the Listener and Tnsnames files for RAC Databases. CIPL Completed

Migration of Single Instance Production databases to RAC Databases


12. CIPL Completed
for UAT release.

Failover testing of reporting session done for the foll. scenarios - Node
13. reboot, OS cluster shutdown, Heartbeat network disconnectivity and CIPL Completed
Public network disconnectivity

14. Performing Application Testing Completed


ICICI Pru

Migration of Single Instance Production databases to RAC databases


15. CIPL Completed
for Production Go-Live

16. Installation of Oracle Enterprise Linux 5.4 on DR Server CIPL Completed

Installation of Oracle 10gR2 with latest Patchset 10.2.0.4.0 on DR


17. CIPL Completed
Server

Configuration and Testing of DataGuard (EMC SAN Replication) for


18. CIPL / ICICI Pru Completed
QUANTIS, MFUNDMCY and EPFQNTS database

SET – II (PRUICICI, APPSDB, MKTDB, DEDUP)

Installation of Oracle Enterprise Linux 5.4 on two nodes


1. CIPL Completed

2. OS Hardening on two nodes as per Audit Document CIPL Completed

Verifying and sorting out the installation pre-requisites for Oracle 10g
3. CIPL / ICICI Pru Completed
RAC

4. Installation of Oracle 10g CRS on both the cluster nodes CIPL Completed

5 Private and Confidential


Installation of 10.2.0.4.0 patch on CRS homes on both the cluster
5. CIPL Completed
nodes
Installation of Oracle Database 10.2.0.1.0 software on both cluster
6. CIPL Completed
nodes
Installation of Oracle Database 10.2.0.4.0 patch on Database homes on
7. CIPL Completed
both cluster nodes

8. Applying Opatch for Bug Fixes. CIPL Completed

Creation of Different ASM Diskgroup for Datafiles and Redolog files for
9. CIPL Completed
each databases.

Creation of RAC Databases (QUANTIS, PERFATTR, MFUNDMCY and


10. CIPL Completed
EPFQNTS) as per requirement

11. Configured the Listener and Tnsnames files for RAC Databases. CIPL Completed

Migration of Single Instance Production databases to RAC Databases


12. CIPL Completed
for UAT release. (QUANTIS, PERFATTR, MFUNDMCY and EPFQNTS)

Failover testing of reporting session done for the foll. scenarios - Node
13. reboot, OS cluster shutdown, Heartbeat network disconnectivity and CIPL Completed
Public network disconnectivity

14. Performing Application Testing Completed


ICICI Pru

Migration of Single Instance Production databases to RAC database for


15. CIPL Completed
Production Go-Live (QUANTIS, PERFATTR, MFUNDMCY and EPFQNTS)

16. Installation of Oracle Enterprise Linux 5.4 on DR Server CIPL Completed

Installation of Oracle 10gR2 with latest Patchset 10.2.0.4.0 on DR


17. CIPL Completed
Server

Configuration and Testing of DataGuard (EMC SAN Replication) for


18. CIPL / ICICI Pru Completed
QUANTIS, MFUNDMCY and EPFQNTS database.

SET-II
 Phase Include (Clusterware, Oracle Installation, DB Creation, UAT Release, Prod. Go-Live):
18th October, 2010 TO 30th October, 2010

6 Private and Confidential


 DR Setup : 1st November, 2010 - 3rd November, 2010

SET-I
 Phase Include (Clusterware, Oracle Installation, DB Creation, UAT Release, Prod. Go-Live):
25th October, 2010 TO 20th November, 2010
 DR Setup : 22nd November, 2010 - 23rd November, 2010

II) Sign Off:

AUTHORIZED SIGNATORY

Ms. Geetha Rao Mr. Deepesh Upadhye

AVP Head – Technology Solution Group


ICICI Prudential Clover Infotech Pvt. Ltd.

7 Private and Confidential