Professional Documents
Culture Documents
Rivers
Degrading
Stable
2
Deltaic
Behaviour of Rivers
Silt and sediment that flows in the river can mould the behaviour of the river. These are
main factors for the creation of numerous problems such as-
River training a wider aspect covers all those engineering works which are
constructed on a river, so as to guide and confine the flow to the river channel, and to
control and regulate the river bed configuration, thus ensuring safe and effective
disposal of floods and sediment loads.
Aim of the river training: Stabilizing and training the river along a certain alignment
with a suitable waterway is, therefore, the first and foremost aim of river training.
i) To prevent the river from changing its course and to avoid outflanking of structures
like bridges, weirs, aqueducts, etc.
ii) To prevent flooding of the surrounding countries by providing a safe passage for the
flood waters without overtopping the banks;
iii) To protect the river banks by deflecting the river away from the attacked banks;
iv) To ensure effective disposal of sediment load;
v) To provide minimum water depth required for navigation.
3
Apart from improving the drainage system, facilities are in place to monitor the flow
conditions in major rivers and to provide flood warnings to nearby villagers.
• River gauges are installed in the main rivers to monitor and record
variations of water levels during heavy rains.
• Using computerized equipment, other departments are notified for
assistance.
• When water rises to certain levels, flood warnings will be issued to
villagers to take appropriate precautionary measures.
• Flood shelters are available for the use of villagers affected by heavy
rainstorms.
• Earth dams can be built to almost any height and on foundations not strong
enough for concrete dams.
1) Materials: Where will the materials for the project come from?
2) Diversion: The water must be diverted from its normal course in order to build the dam.
Through the use of tunnel or cofferdam.
4) Forms: The size of the blocks is determined by things like how big the dam is or how far
the concrete must travel to get there. The blocks, called formwork, can be built from wood or
steel.
4
5) Pouring: Concrete must be mixed at a mixing plant, either on-site or off the site, and then
transported to the formwork and poured into it.
6) Insulation: The finish both protects the dam from premature weathering and makes the
dam more aesthetically pleasing for the public
7) Additional structures: There may be additional structures to the main dam. A spillway
might be built to release excess water from the reservoir -- it is basically a path for the water
to go around the dam. Outlet works can also be built to regulate the release of water from
the dam. If the dam is to create hydroelectric power, the power plant must be built.
Waterproofing products designed for protecting water-retaining structures for drinking water
applications need to meet additional requirements. These includes-
• The main function of water retaining structure is to protect the reserve water from
contamination or adverse effect of pollution which is used for the particular purpose
such as drinking, bathing, irrigation or aquatic culture, etc. For that reasons
cementitious waterproofing products are essentially needed to provide a number of
options for the waterproofing of water-retaining structures.
5
• the basic points
A structure that resists horizontal or lateral soil pressure an abrupt change in ground
elevation which is known as retaining structure or retaining wall.
Retaining walls are usually built to hold back soil mass. However, retaining walls can also be
constructed for aesthetic landscaping purposes.
• the purposes
6
c) Evaluate the application of retaining structures. (4 marks)
1) Retaining walls can be used on both cut and fill slopes along roads.
2) Used to physically separate roads from stream channels.
b) Large fractures forming along a cut or fill slope may indicate a potential future
slump or slide that will need reinforcement.
d) Identify the typical checklists for the bridge construction project in conjunction
with the development of a satellite city. (5
marks)
• the design of bridges requires the collection of extensive data and from this then
selection of possible action. A sensible work plan should be devised for the
organizing and operation of information throughout the project from conception to
completion. So checklists are varied from project to project, but a typical example
can made as the following.
• Feasibility Phase
• Assembly of design criteria
• Design Phase
• Construction Phase
• Performance Phase
i. Feasibility phase
• Data collection
• Topographical and hydrographical survey
• Hydrological information
7
• Geological and geo-technical information
• Site investigation requirements for soil and rock evaluation
• Meteorological and aerodynamic data
• Assembly of basic criteria
• Likely budget
i) Construction Phase
• Contractual matters;
• Construction method;
• Budget and financial control;
• Quality control;
• Supervision of construction;
• Commissioning;
8
• Operating, inspection and maintenance schedule for each part of the work.
v) Performance phase
• Obligation of owner;
• Management of facility
• Inspection, maintenance and repair
• Rehabilitation and refurbishment requirements (change of loading, widening, change of use
and durability aspects)
• Decommissioning and demolition.
The planning and design of an airport is complex and involves specialists in-
• airport planning;
• traffic forecasting;
• aeronautical ground lighting;
• telecommunications and navigational aids;
9
• air traffic control;
• baggage handling, and
• many other activities.
b) Improvement of concepts through- (i) Cutting slopes; ii) Rock cuttings; iii) Soil
cuttings; (iv) Embankments; (a) slope angles; b) Rock-falls; c) Reinforced earth; d)
Trackbed designs; e) Drainage
10
v) To determine design and construction parameters
a) Explain the factors that affect diver’s work in the underwater construction
work.
(5 marks)
b) What are the two (2) essential elements of economic tunnelling? (2marks)
c) List the elements that need to be included in highway environmental appraisal report.
(5
marks)
The elements that need to be included in a highway environmental appraisal
report are as follows:
i) Traffic noise;
ii) Visual impact;
iii) Air pollution;
iv) Community severance;
v) Effects on agriculture;
vi) Heritage and conservation areas;
vii) Ecological impact;
viii) Disruption due to construction;
ix) Pedestrians and cyclist;
x) View from the road; and
xi) Driver stress.
11
d) List the process of cost evaluation for the construction of an international
airport.
(3 marks)
i) Details structural design and its optimisation process.
ii) Need assessment and transfer the needs into total cost (such as social cost, ability
to spent and long term benefit, etc.)
iii) Strategic point analysis
e) Discuss the different stages and factors affecting the construction techniques in
offshore construction system. (6 marks)
Selection of suitable techniques for fabrication and installation of offshore structures are
influenced by many factors which include:
a) Material (steel, concrete or hybrid structures, and other new materials);
b) Economic factors such as the need to bring the field to partial production early
and improve overall cash flow;
c) Cost;
d) Environmental conditions: sea states, wind, current;
e) Water depth;
f) Safety;
g) Constraints imposed by regulatory authorities, such as vessel operation
constraints, pollution control, navigation restrictions, etc.;
h) Existence of suitable fabrication yards/ dry docks with sufficient space and
load capacity and available draught in the waterways for transport of the structures; and
i) Socio- political factors which may influence selection of yards and even the
type and form of structures.
12
vi) Topography;
vii) Obstructions to aircraft operations;
viii) Meteorology;
ix) Construction problems;
x) Utility services.
END OF PAPER
13