You are on page 1of 14

Design and Construction of Deep Shafts in Hong Kong

Special Administrative Region (SAR), China


L. J. Pakianathan
Mott MacDonald Pte Ltd, Singapore

A. K. L. Kwong
University of Hong Kong, Hong Kong

D. D. McLearie
Montgomery Watson Harza, Hong Kong

W. K. Ng
Drainage Services Department, Government of the Hong Kong SAR, Hong Kong

ABSTRACT: Shafts play an essential part in the construction, operation and maintenance of tunnels
and deep underground structures but are rarely given exclusive prominence in technical publications.
The aim of this paper is to summarise the experiences gained in Hong Kong SAR during the
construction of the Harbour Area Treatment Scheme Stage 1 where seventeen shafts were constructed.
Their excavated diameters range between 2.5 m to 50 m and at a maximum depth over 150 m these are
the deepest shafts below sea level in Hong Kong. All shafts were located in reclaimed land and in
close proximity to the sea. The upper shafts in soils and weak rock were constructed by diaphragm
walling method and the lower shafts in rock by mainly drilling and blasting. Raise boring and blind
shaft drilling methods were also employed. The upper shafts and permanent shaft linings were
designed using conventional methods and the primary support selection for the lower shaft was based
on Barton’s (1974) ‘Q’ system. Settlement monitoring and inclinometer measurements were
undertaken during excavation to confirm the design assumptions. During construction several
difficulties were met that had to be overcome. All shafts with the exception of one were successfully
excavated and completed. This paper addresses the key design and construction issues and the
difficulties that were encountered which may be common for deep shafts constructed in an urban
setting near a coastline.

1 INTRODUCTION

The Harbour Area Treatment Scheme (formerly known as Strategic Sewage Disposal Scheme) is an
environmental improvement project aimed at cleaning up the waters in the Victoria Harbour. The first
stage consists of transfer tunnels linking the primary treatment works located at the southern part of
Kowloon and eastern part of Hong Kong Island to a centrally located chemically enhanced treatment
facility at the Stonecutters Island. A network of 25 km long transfer tunnels were constructed in
bedrock at depths varying between 75 m and 145 m below sea level making these the deepest tunnels
to date below sea level in Hong Kong SAR.

In order to construct the tunnels and to transfer the sewage from the coastal treatment works, 17 shafts
were constructed. The excavated diameter of the shafts varies from 2.5 m to 50 m and they reach down
to a maximum depth of over 150 m. The decision to locate the tunnels at a deep level in the rock well
below toe levels of pile foundations, made it possible to construct the tunnels along a most direct as
well as shortest route. It became necessary however to sink deep shafts to link the tunnels to the
ground surface. The functions of the different types of shafts are summarised in Table 1.
Table 1 Function of different types of shafts
Shaft Type Function
Production shafts to excavate the tunnels and to construct the permanent lining
Drop shafts to transfer the sewage from the terminal manholes to the tunnels
Riser shafts to convey the sewage from the tunnels back to the surface installations
Pumping station shafts to raise the hydraulic head of sewage using submersible pumps

Figure 1 shows the location of the shafts and Table 2 shows their particulars. All deep shafts were
excavated in two parts as upper and lower shaft to suit the operation and the differing ground
conditions. The upper shafts were constructed by diaphragm walling or open cut methods through soil
and weak rock and the lower shafts were excavated by drilling and blasting, raise boring or blind hole
drilling methods in hard rock. Of these, diaphragm walling and drilling & blasting methods were
predominantly used.

The upper section the production shafts were typically 10 m in diameter and reduce to 8.0 m at the
lower section by the installation of a 1 m thick toe level ring beam at the rock/soil interface, Figure 2.

The drop shafts are of a larger diameter in the upper section to function as a chamber to remove air
from the sewage and to accommodate a bell mouth and vortex drop pipe. These reduce in size to
approximately 2.5 m excavated diameter in the lower section. The drop shafts incorporate a 4.0 m deep
sump below the tunnel invert level to accommodate submersible pumps for emergency dewatering.

The land based riser shafts were excavated at the same size as the production shafts to enable the
removal of the tunnel boring machines. The permanent linings for the riser shafts are made of steel
pipes or in-situ concrete. Their internal diameters are identical to those of the tunnels to maintain the
same flow velocity so as to prevent any sedimentation at the shaft bottom.

The pumping station shafts were sized on the basis of the required holding capacity and pumping
arrangement. They are up to 38m deep and are founded in soil. The Stonecutters Island Main Pumping
Station (SCIMPS) shaft at 50 m diameter is among the largest in Asia.

Contractors Skanska-Shui On-Balfour Beatty Joint Venture excavated all the production shafts and
Kwun Tong pumping station shaft under an advance works contract DC/93/10. The value of this
contract was HK$226 million and the works commenced in August 1994. In parallel another advanced
works contract for the construction of diaphragm walls and soft ground excavation of the SCIMPS and
riser shaft was awarded to Leighton Contractors at HK$116 million. The remaining drop and riser
shafts were excavated later on as part of the tunnelling works contracts as shown in Table 2.

2 GROUND CONDITIONS

The shafts were constructed through recent Fill, Marine Deposits, Alluvium, Completely to Highly
Decomposed Rock and Bed Rock. The marine deposits are generally soft, greenish grey clays with
variable amounts of silt, sand and shell fragments. The alluvium deposits are generally characterized
by variable firm to stiff silts and silty clays. The completely decomposed rock is generally firm,
clayey, sandy Silt with some angular to sub-angular fine to occasional coarse gravel sized rock and
quartz fragments. The bedrock is made up of either Granite or Volcanic Tuffs.

Three out of the seventeen shafts were excavated in volcanic tuffs and remainders were in granite. The
ground water table was at sea level and the water met in the shafts was saline.
Table 2. The main features of the shafts
Shaft Location Function Upper Shaft Excavation Lower Shaft Excavation Permanent Lining
No. Ø Depth Constructio Contract Ø Depth Construction Contract No. Geology Type Contract
(m) (m) n method No. (m) (m) method no.
1 Kwai Chung Drop shaft 13.5 33 Diaphragm DC/93/14 2.5 107 Raise boring DC/96/20 Granite Concrete DC/96/20
PTW wall DC/96/20
2 Tsing Yi PTW Production and 8 3 Open cut DC/93/10 8 137 Drill and blast DC/93/10 Granite Concrete DC/96/20
drop shaft
3 Stonecutters Riser shaft 10 63 Diaphragm DC/93/11 8 68 Hydraulic DC/93/14 Granite Concrete DC/96/20
Island STW wall hammer; DC/96/20
Drill and blast
4 Stonecutters Pumping station 50 38 Diaphragm DC/93/11 - - - - - Concrete DC/93/16
Island STW shaft wall
5 Stonecutters Outfall production 10 10 Diaphragm DC/93/10 8 97 Drill and blast DC/93/10 Granite Concrete DC/93/18
Island and drop shaft wall
6A & Undersea Outfall riser shafts - - - - Blind hole DC/93/18 Granite Steel pipes DC/93/18
6B Outfall drilling
7 To Kwa Wan Production shaft 10 60 Diaphragm DC/93/10 8 83 Drill and blast DC/93/10 Granite Backfilled DC/96/18
wall
8 To Kwa Wan Drop shaft 12 32 Diaphragm DC/93/14 2.5 109 Raise boring DC/96/18 Granite Concrete DC/96/18
PTW wall
9 Kwun Tong Drop shaft 13 32 Diaphragm DC/93/14 2.5 116 Raise boring DC/96/18 Granite Concrete DC/96/18
PTW wall
10 Kwun Tong Production and 13 37 Diaphragm DC/93/10 8 114 Drill and blast DC/93/10 Granite Concrete DC/96/18
Pumping drop shaft wall
Station
11 Kwun Tong Pumping station 15 25 Diaphragm DC/93/10 - - - - - Concrete DC/93/14
Pumping shaft wall
Station
12 Kwun Tong Production and 10 33 Diaphragm DC/93/10 8 50 Drill and blast DC/93/10 Granite Steel pipes DC/96/17
Pumping riser shaft wall
Station
13 Tseung Kwan Production and 10 32 Diaphragm DC/93/10 8 63 Drill and blast DC/93/10 Volcanic Steel pipes DC/96/17
O PTW drop shaft wall Tuffs
14 Shau Kei Wan Drop and riser 9 25 Diaphragm DC/93/13 4.5 105 Drill and blast DC/96/17 Granite Concrete DC/96/17
PTW shaft wall
15 Shau Kei Wan Diversion chamber 7.5 26 Diaphragm DC/96/17 - - - - - Concrete DC/96/17
PTW shaft wall
16 Chai Wan PTW Production and 9 26 Diaphragm DC/93/13 5 107 Drill and blast DC/93/13 Volcanic Concrete DC/96/17
drop shaft wall Tuffs
17 Chai Wan Production shaft 10 21 Diaphragm DC/93/10 8 # Drill and blast DC/93/10 Volcanic Backfilled DC/96/17
75
wall (113) Tuffs
#-
Shaft excavation was discontinued before completion
3 DESIGN

3.1 General

The design of the shafts was based on their function which was initially to provide temporary access
for tunnel construction and then to transfer the sewage from the treatment works to the deep level
tunnels followed by conveying to the central treatments works or outfall. The availability of suitable
land space and the location and orientation of the terminal manholes at the treatment works were main
factors in deciding the location of the shafts. The upper shaft situated within the soft ground was
designed as an octagon suitable for construction by the diaphragm walling method. The lower part of
the shaft was designed to take advantage of the inherent strength of the rock during the temporary
stage and to with stand hydrostatic pressures during the permanent stage.

3.2 Upper Shaft

The upper shaft was designed to withstand the loading from the ground and ground water pressure
with an allowance made for surcharge and flooding of the surrounding area. The permissible deviation
of the diaphragm wall panels from true verticality was 1:75. The thickness of the walls was chosen to
maintain at least 300 mm contact between adjacent panels for the worst case scenario where their
verticality is offset in the opposing directions. For a 30 m deep shaft this works out as 1100 mm. The
typical thickness adopted for the diaphragm walls was either 1000 mm or 1200mm. A 150 mm
construction tolerance was added to the required internal radius and the contractor proposed to trim
back any excess concrete encroaching beyond this. Where the diaphragm walls were very deep and the
resulting thickness is excessive specialist equipment was used to control verticality.

The quasi-circular shafts were designed to carry the loads in hoop compression without any internal
propping or strutting. At toe level a nominal 1 m x 1 m ring beam was designed to tie the individual
panels together. Where the rock head variation was more than 1 m then deeper ring beams were
designed and installed. Where it is not possible to install a toe level ring beam as in the case of the
Shau Kei Wan diversion chamber, shear pins were drilled and grouted into the rock.

The reinforcement for the panels was selected not only to carry the forces but also to make the cages
sufficiently rigid for handlings purposes and to minimize the entrapment of bentonite mud during the
concrete placing. Steel pipes and inclinometer tubes were incorporated into the rebar cages to facilitate
the drilling of contact grouting holes and for monitoring respectively.

3.3 Lower Shaft

Four types of primary support as shown in Figure 3 were specified. The primary support design for the
lower shaft was based on the Barton’s rock mass quality ‘Q’ system, Barton et al, (1974). Using the
information from the initial site investigation (boreholes drilled at the centre of the shafts) it was
possible to estimate the corresponding ‘Q’ numbers and select the appropriate support type at different
depths. The Bills of Quantities were prepared using this method to quantify the extent of the different
support type. As the work proceeded the exposed rock face was geologically mapped after each round
of excavation and the ‘Q’ value was re-calculated and agreed with the Engineer’s Representatives on
site prior to installation of the appropriate support type. The extent of estimated support type under
contract DC/93/10 is compared with the actual in Table 4.

Table 4. Comparison of estimated support type with actual


Support type Estimate (m) Actual (m)
Type A 139 97
Type B 367 353
Type C 37 99
Type D 25 19
The permanent lining was designed to withstand full external hydrostatic pressure under flooding
conditions assuming that the shaft was empty. The inner surfaces of the permanent linings that are
exposed to condensation were protected by a High Density Polyethylene (HDPE) fully welded
protective membrane. This is resistant to hydrogen sulphide attack from the sewage. The surface areas
that are always fully submerged did require such protection.

4 CONSTRUCTION OF UPPER SHAFT

4.1 Guide Walls

The diaphragm wall construction began with the construction of guide walls. These were temporary
structures constructed along both faces of the diaphragm wall. The top of the guide walls was located
approximately 0.5 m to 1.0 m above the surrounding ground level so that a positive head of bentonite
slurry can be maintained in the excavation to control ground settlement. A sheet pile cofferdam was
first erected before the excavation of the typically 1.0 m deep guide walls in view of the high ground
water table. The guide walls were constructed of nominally reinforced concrete.

4.2 Diaphragm walls

The diaphragm walls were excavated as eight separate panels generally using clamshell grabs
suspended from a 50 Tonne crawler crane. The storage silos for the bentonite and plants for slurry
separation and desanding were installed on site prior to the commencement of excavation. The panels
were excavated in one to three bites. The operation of the grabs was stopped when a hard stratum was
reached and it was no longer practical to use this method. Circular and rectangular chisels were
employed to excavate through the hard stratum until the predefined toe level of the panel which is at
least 500mm below the top of Grade III rock was reached. Following completion of excavation of a
panel stop ends were installed and recirculation and pumping out of bentonite from the toe level was
carried out for long periods of time (usually overnight) to remove all sediment deposits from the
founding level which were mainly sand and rock chippings.

When the trench is sufficiently clean the reinforcement cages were lowered in sections up to 12 m long
and coupled up vertically using bulldog clips. A tremie pipe was positioned with its end at the bottom
of the excavation to enable underwater concrete placing. A high slump Grade 35 concrete mix was
delivered to the site and was discharged directly from the truck mixers to the hoppers fitted on top of a
tremie pipe. During concrete placing the tremie pipe was carefully lifted up with the free end securely
buried at least 1 to 2 m inside the fresh concrete to avoid contamination from bentonite. The displaced
bentonite was returned to the storage silos after being cleaned in the separation plant.

4.3 Contact Grouting

In general practice excavation inside the diaphragm walls rarely continues deep to expose the toe of
the wall panels. In the case of HATS, shafts were sunk below the founding levels of the diaphragm
walls and therefore some form of cut off against possible water ingress through the uneven joint at the
wall/rock interface became necessary. This was achieved by drilling at least 5 m below the toe (of the
deepest panel) through pre-installed pipes cast in the wall panels and injecting a stable cement grout
via a single stage packer. This method proved to be effective in stemming any ingress at the wall/rock
interface but despite this two shafts required additional treatment described in Section 9.7.

4.4 Excavation

The excavation of the soft ground inside the diaphragm walls was carried out by a 0.25 to 0.3 m3
capacity backhoe type excavator and loaded into 4 m3 capacity muck skips. The filled skips were
removed to the surface by a crawler crane. Any water that was trapped inside was removed by
pumping into the muck skips as the excavation proceeded. The shaft walls were surveyed for each 1.0
m depth and any projection inside the required internal perimeter was removed by a hydraulic hammer
mounted on the excavator. The reinforcement bars that became exposed during this operation were
coated with anti corrosive paint and protected further by a layer of sprayed concrete.

4.5 Instrumentation and Monitoring

Inclinometer readings to detect any horizontal movement of the wall panels were taken daily when the
upper shaft excavation was in progress. This was necessary to verify that the design assumptions and
confirm the stability. The readings were generally satisfactory overall but occasionally unreliable
readings were detected. In the latter case extensometer pins were installed and additional convergence
readings were taken.

4.6 Water Ingress

The specifications stipulated that the upper shaft shall be watertight. However during excavation
seepage was observed in a few locations, mainly through the wall panel joints and the isolated
bentonite pockets. The leaks through the joints were repaired by drilling and injecting with a chemical
grout. The trapped bentonite pockets were repaired by first removing the loose materials followed by
scabbling back to sound concrete and then backfilling with a repair concrete mix. Any seepage water
was first diverted using pipes during this operation and then grouted after the repair concrete has
reached sufficient strength.

4.7 Progress rates

The diaphragm wall construction and excavation have taken approximately four to six months. The
delay at the Shau Kei Wan D/S can be attributed to the large variation in the rock head level requiring
extensive chiselling. The durations of upper shaft construction activities are summarised in Table 5.

Table 5. Duration of upper shaft construction in calendar days


Shaft Guide walls Diaphragm Toe Soft Ring beam Total
walls grouting excavation duration
SCO D/S 20 41 12 26 24 123
TKW P/S 20 66 16 47 13 162
KTPS D/S 18 46 17 31 22 134
KTPS R/S 23 58 14 48 21 164
TKO P/S 20 56 17 48 27 168
KTPS 21 69 16 60 - 166
CW P/S 22 51 13 24 12 122
SKW D/S 21 110 11 35 12 189

5 CONSTRUCTION OF LOWER SHAFT

The lower shafts were constructed by drilling and blasting and by raise boring methods. A typical
cycle of advance for drilling and blasting consisted of cleaning the face, marking out and drilling shot
holes, charging, blasting, fume clearance, mucking out and support installation. Probing and grouting
was done at a certain frequency as described below.

5.1 Probing and grouting

The ground conditions were explored by two methods during excavation. Advance probing where
holes up to 30 m long were drilled at the four corners of the shaft was the preferred method. The other
method was to drill an approximately 100 mm diameter central hole all the way down to the shaft
bottom using a down the hole hammer.
Where significant water inflow was met in the probe holes further holes were drilled to inject cement
grout. It was common practice to maintain approximately 5 m overlap between fans of probe holes.

5.2 Drilling and blasting

The lower shaft excavation was carried out generally by drilling and blasting. Immediately below the
toe of the diaphragm walls 1.5 m long blasting holes were drilled. At each shaft a trial blast was
conducted to confirm the blast design, to demonstrate compliance with the Mines Department
regulations and to prove that blasting induced vibrations were below the permissible limits. As the
ground conditions improved with the depth of excavation the shot hole length was increased to 2.4 m.
Two types of full face blasting patterns namely ‘wedge cut’ and ‘parallel hole cut’ were used. Where
the water inflow was high the shaft blasting was done in two halves so that the lower half was used as
a temporary sump while drilling was carried out in the upper half.

A typical cycle began with the cleaning the rock face after mucking out and marking the centre of the
shaft by lowering a plumb bob from a steel beam temporarily placed over the shaft top. The outer
perimeter of the excavation was then marked out by spray paint taking account of the primary support
thickness. The locations of individual blast holes were marked out as dots of spray paint. The holes for
the wedge cut were drilled at an inclination dipping towards the shaft centre. The ring of holes
immediately in front of the perimeter holes were drilled vertically down and the perimeter holes were
drilled at a slight angle dipping away from the shaft center. With the parallel hole cut, relief holes
approximately 100 mm in diameter were drilled near the shaft center and all blast holes were drilled
vertically downward. It was important to drill the wedge cut holes accurately to maintain an even
spacing of the rings at the toe of the holes. This became particularly important in massive granite with
few joints. On occasions blast hole numbers were increased where such conditions were encountered.

The blasting vibration can be estimated using the equation given in Geoguide 4, GEO Hong Kong
(1992):

A = KQdR-b (1)

where A= predicted particle velocity in mm/s; Q = maximum charge weight per delay in kilograms;
R= distance between the blast and the measuring point in metres; K= rock constant; d= charge
exponent; and b= attenuation exponent. However the Mine’s Department equation (2) for calculating
the peak particle velocity (PPV) was more widely used:

PPV = K(R/Q0.5)B (2)

The site specific constants K=644 and B=-1.22 were derived from a regression curve representing a
large number of measurements taken at various locations in Hong Kong.

5.3 Spoil Removal

The spoil removal commenced soon after blasting and smoke clearance. The equipment used was the
same as that used for the upper shaft with the exception of a 15 tonne Hagglund gantry crane replacing
the crawler crane. The skips were only 75% loaded to avoid the risk of falling rock.

5.4 Primary Support

The contractor proposed certain changes to the typical primary support types stated in the contract
documents and these were accepted by the Engineer. The main changes are as follows:

Type A – replacement of chain link mesh with 20 mm sprayed concrete since there was a risk of fly
rock from blasting being temporarily caugt in the mesh.
Type D – replacement of the steel arch ribs with a mesh reinforced sprayed concrete beam.

5.5 Progress Rates

The excavation was carried out in two 12 hour shifts. The planned and actual rates of progress for rock
classification/ primary support types are compared in Table 6.

Table 6. Average excavation progress per week


Rock-Mass Support Planned Progress Actual Progress
Classification “Q” Type Rate (m/week) Rate (m/week)
>4 A 10.3 8.1
0.4 – 4 B 9.3 6.3
0.1 – 0.4 C 4.7 3.8
<0.1 D 3.9 2.4

6 UNUSUAL DIFFICULTIES

A number of difficulties were encountered during the construction of the shafts. These ranged from
coordinating the construction activities with the 24 hour operation of the treatment works, dealing with
landfill materials present in the soft ground, substantial variations in the rock head levels, ground water
leakage and ground loss, constraints imposed by explosives delivery and limitations on blasting
periods, environmental restrictions and the necessity to complete the works in a timely manner so as to
avoid delays to the following on tunnelling works. Some such difficulties were not anticipated by the
contractors and therefore different mitigation measures were tried starting with the simple and
progressing to the more complex based on the success. As a result significant delays were encountered
even though almost all the problems were resolved successfully.

6.1 Proximity to the sea

All shafts were located close to the sea. Three were located within 10 m of the sea wall and two of the
outfall risers were in fact constructed below the sea bed. During the excavation of the upper shaft of
Chai Wan and Shau Kei Wan shafts which are located very close to the sea wall several large size (up
to 1.5 m long) rock backfill that was placed previously to construct the sea wall were encountered.
These could not be plucked out by the clam shell grab and therefore a cactus type grab was used
instead. In addition substantial losses of bentonite slurry also occurred through this medium. This
problem was overcome by backfilling the excavated trenches with completely decomposed granite and
re-excavating through it. Furthermore only one panel was excavated at any one time.

The surcharge loading within a 10 m zone behind the sea wall was restricted to 10 kN/m2. This
limitation made it difficult to install bentonite slurry silos and gantry crane foundations near the shaft
and special dispensation was sought for the Shau kei Wan diversion chamber shaft to install the slurry
tanks immediately behind the sea wall because of limited land space. There was sufficient redundancy
available in the sea wall designs to accommodate additional temporary loading but systematic
settlement monitoring of the sea wall coping was undertaken to demonstrate that the excess surcharge
loading did not have any adverse effect.

6.2 Working on Reclaimed Land

The shafts were constructed on land that was reclaimed from sea. The fill material and placing
methods in the case of old reclamations were not as strictly controlled as those new. At Kwun Tong
shaft site there was evidence of household refuse in the land fill. In addition that site was previously
used as a fuel farm for unloading fuel from ships and storing there temporarily. Upon close
investigation contamination from the fuel was found to be limited since additional fill material had
been placed over the site and the surface runoff has washed away and diluted the fuel concentration in
the ground. However during the excavation of the upper shaft through the land fill material bubbling of
gases was observed. Gas monitoring was carried out to detect hydrogen sulphide and explosive gases
and forced ventilation was set up. The natural ventilation was found to be sufficient to disperse the
hazardous gases since they occurred at a relatively high elevation.

At Tseung Kwan O the shaft was located in an old land fill and at the foot hills of a recent waste
dumping site. During the excavation of the upper shaft leachate was encountered. This was carefully
removed and disposed off site. Frequent gas monitoring readings were taken to check for explosive gas
content. The gas concentration measured was sufficiently low after dispersal by forced ventilation.

Since the diaphragm walls were watertight in the case of both shafts the hazardous gases problem was
resolved once the layer containing decaying waste was removed.

6.3 Variations in rock head level and deep weathering

One borehole was drilled at the centre of each shaft during pre-tender site investigation. Since the foot
print of a shaft is relatively small significant variations in the rock head levels were not anticipated and
a variation of less than 1m was expected. However during the detailed design of the upper shaft
diaphragm walls three or more boreholes were drilled and substantial variation in the rock head levels
between different panels was discovered for Stonecutters Island riser shaft, To Kwa Wan production
shaft and Shau Kei Wan shafts. The largest variation of 7.5 m between the highest at and lowest toe
level was met at the Shau Kei Wan Diversion chamber shaft. In the case of the Stonecutters Island
Riser Shaft and To Kwa Wan production shaft deep weathering compounded the difficulties taking the
diaphragm walls to some 50 to 60 m deep. A hydro-fraise type diaphragm wall trench cutter was used
to ensure the verticality of the deep wall panels. In addition deep toe level ring beams were constructed
to compensate for the variations in the rock head level.

There was not sufficient space inside the Shau Kei Wan diversion chamber to install a ring beam and
in any case this shaft was not required to be deep. The panels were dowelled into rock with a bundle of
4 x 50 mm cement grouted reinforcement bars. Inclinometer and convergence measurements were
taken during the shaft excavation to verify the stability and no adverse trends were observed.

6.4 Marine mud ingress into Diaphragm wall excavation

While the upper section of the Stonecutters Riser shaft was being excavated a sudden inrush of marine
mud from the toe of a diaphragm wall panel occurred. This loss of ground through gaps in between
undetected corestones caused a depression in the ground surface. Since the location of the ground loss
was situated close to a 60 m diameter shaft and in an area planned for the construction of an adit
linking the two shafts, serious concerns arose when this incident occurred. The contractor proposed to
fill the shaft with water immediately to contain the mud flow by equalising the hydrostatic pressure,
install another diaphragm wall panel behind that affected and then undertake jet grouting from the
surface to strengthen the collapsed ground. These remedial works were successful but caused a major
delay to the completion of the shaft excavation. In addition the method of excavation of the adit was
changed to open cut from bored tunnelling by installing additional diaphragm wall panels between the
jet grouted area and the 60 m shaft.

When the shaft was re-excavated after the remedial works frequent inclinometer and extensometer
readings were taken to monitor the convergence and verify the stability.

6.5 Flooding incidents in the upper shaft

At the Stonecutters Island outfall shaft an unexpected inrush of water was met at the initial stages of
rock excavation works immediately under the toe of the diaphragm walls. During the time of the
incident an excavator was cleaning the shaft bottom making it ready for the next round of blasting.
There was sufficient time to rescue the excavator operator before the shaft completely flooded.
According to his account the water entered through a clay seam in the rock. It was decided to
undertake tube-a-manchette grouting from outside the shaft over the zone of the leak. After completion
of grouting the shaft was pumped out dry and no further leakage was met. It was later discovered that
the water leak occurred through the clay matrix in between two large corestones. This area was
strengthened by applying sprayed concrete before undertaking further excavation.

A similar incident occurred as well at the foot of the diaphragm wall of the Tseung Kwan O shaft. The
pumping system was able to cope with the inflow and therefore it was decided to grout the leaks from
inside the shaft. First deep holes were drilled to intercept the leaks some distance behind the shaft wall
and mechanical packers were installed in these holes. After channeling the water to pipes set in rapid
hardening cement, a layer of sprayed concrete was applied to the closely jointed shaft wall and the
packers were grouted up under pressure as soon as the sprayed concrete has reached sufficient
strength. Eventhough the remedial method was successful in staunching majority of the inflow there
was residual leakage from this area which persisted until the permanent lining was installed.

6.6 Wide Clay filled sub-vertical joint in rock

At the Stonecutters riser shaft an approximately 1 m wide clay filled hydro-thermically altered joint
was met immediately below the diaphragm wall panels. The rock mass quality was substantially
reduced by the presence of this weak material and it was decided to adopt Type D primary support
which is based on steel arch ribs and sprayed concrete. The sub-vertical joint persisted for up to about
30 m deep before disappearing into the side wall and out side the foot print of the shaft. The steel arch
ribs were continued until the influence of this joint on the shaft was no longer significant.

6.7 Plant breakdown

The high humidity, constantly wet and salty environment in the shaft lead to higher than normal wear
and tear of mechanical plant and equipment. The excavator, water pumps and shotcrete pumps
suffered from frequent breakdown. On occasions the gantry crane also broke down contributing to the
average lost time of approximately 20%. Even though the direct loss of time from plant break down
can be averaged out as 5 hours per day its effect in terms of the 10 hour window available for blasting
was very serious since a lost blast meant that the whole day’s production was lost.

6.8 Delivery of explosives

The storage, transportation and use of explosives were strictly controlled to prevent both misuse and
mishaps. The proximity of the shaft site in relation to the Mine’s Department magazine generally
governed the time of arrival of explosives on site. The earliest delivery was received at the shafts
nearest to the magazine at around 9 to 10 am and the furthest shafts where transportation also included
use of a boat received deliveries by noon. This was satisfactory for undertaking one blast a day but not
for two. As the excavation works were falling behind programme the contractor attempted to do two
blasts a day without success. With help from the client special dispensation was obtained for delivery
of explosives and blasting on Sundays and Public Holidays. This proved to be effective and resulted in
a 15% improvement in production.

6.9 Shaft/tunnel junctions

The forming of junctions between shafts and tunnels were undertaken without difficulties in the rock
though several of these junctions incorporated a chamfer to permit lowering of the tunnel boring
machine components. However this activity proved to be very difficult in the upper shaft through the
soft ground. During the construction of the Kwun Tong pumping station shaft/adit tunnel junction a
sudden inrush of sand and ground water occurred. The remedial works necessitated the use of liquid
nitrogen freezing to form an impermeable plug in the soil while the tunnel eye opening was made in
the diaphragm wall, Pakianathan et al (2002). At Shau Kei Wan drop shaft soil grouting followed by
the installation of a circular fan of closely spaced horizontal grouted pipe piles was put in place before
making the tunnel eye opening in the diaphragm wall to construct an adit tunnel. The presence of a
water retaining box culvert directly above the this junction made the task even more difficult. This
junction opening was formed without incident or adverse settlement to the structure above.

6.10 Substantial water ingress

The Chai Wan production shaft was located in Volcanic Ash Tuffs within the zone of influence of the
Chai Wan fault. The water ingress progressively increased from 80 l/min at 35 m depth to 1400 l/min
at 96 m despite pregrouting. Majority of the grouting holes turned out to be dry and ineffective in
intercepting water making joints which were tight and closely spaced. Initially an OPC cement grout
mix at varying water cement ratio (from 5:1 to 1:1) with 2% bentonite was used at a maximum back
pressure of 30 bar. When this was found not very effective Rheocem 650 microcement with 3%
Rheobuild 1000 at a water cement ratio of 3:1 was tried at the same pressure. This resulted in higher
grout take but the progress became very slow and water inflow continued. As the overall project time
table could not be met at the rate of progress being acheived it was decided to reverse the direction of
the TBM drive and abandon this shaft.

Upon completion of the shafts the total inflow rates at the bottom of the shafts were measured before
handing over to the tunnelling contractors. These rates are given in Table 7. Inflow rates from all
shafts with the exception of the abandoned Chai Wan production shaft were well below the 300 l/min
limit set for dewatering purposes.

Table 7. Ground water ingress after completion of shaft excavation


Shaft Depth of Total Inflow rate per Inflow rate per square
shaft inflow rate metre of shaft metre of shaft
(m)## (l/min) (l/min/m) (l/min/m2)
Tsing Yi 140( 129) 69 0.5 0.020
Tseung Kwan O 95 (63) 36 0.6 0.024
Stonecutters Outfall 107 (97) 18 0.2 0.008
Kwun Tong Riser 83 (50) 54 1.0 0.040
KwunTong Drop 151 (114) 60 0.5 0.020
To Kwa Wan 138 (83) 160 1.9 0.076
Chai Wan# 96 (75) 1400 18.7 0.744
#-
Shaft excavation was discontinued before completion
##
- Depth of shaft in rock is shown in brackets where nominal water seepage was permitted

7 GROUND SURFACE SETTLEMENT

The ground surface settlement from the excavation was monitored around the shafts to ensure that it
did not exceed the specified maximum value of 25 mm including the measurements taken on seawall
copings adjoining the shafts. In general this limit was not exceeded but at Chai Wan production shaft
where there was a high ingress of water into the shaft the settlement values were more than 25 mm.
This shaft was located on land recently reclaimed from the sea and the long term consolidation
settlement was still in progress at the time of excavation. It was therefore difficult to conclude whether
the contribution from shaft excavation alone was responsible for the excess settlement. In any event
there was no sensitive structure around this shaft at the time apart from the gantry crane foundations
which were underpinned to compensate for the subsidence.

8 CONCLUSIONS

The aim of this paper is to present the design and construction aspects of the deep shafts in Hong Kong
SAR as a case study with particular emphasis on ground related difficulties and how these were dealt
with in order to complete the works successfully. It is hoped that the problems highlighted and the
solutions described in this paper could provide valuable documented experience to the construction
planning of similar shafts in the future.

REFERENCES

Barton N., Lien R. & Lunde J. (1974) Engineering classification of rock masses for the design of
tunnel support. Rock Mechanics, Vol. 6, No. 4, pp. 183-236.

GEO, Geoguide 4 (1992), Guide to Cavern Engineering, Geotechnical Engineering Office, Civil
Engineering Department , Kong Kong, pp. 76-78.

Pakianathan L. J., Kwong A. K. L., McLearie D.D., Chan W. L. (2002). Pipe Jacking: Case Study on
Overcoming Ground Difficulties in the Hong Kong SAR Harbour Area Treatment Scheme. Trenchless
Asia 2002, 12-14 November 2002, Hong Kong.

You might also like