Professional Documents
Culture Documents
Q210.1 General
This Technical Supplemental Specification provides requirements for welding of ASME B31.1 Power
Piping nonboiler external piping and boiler external piping components, and shall be used in conjunction
with Section Q100 of the Welding Technical Supplemental Specifications.
ASME B31.1 or ASME Section I code cases shall only be permitted for use as specifically approved by
Purchaser.
Note: ASME B31.1 Code Case 183 (use of seamless [9Cr-2W]) is approved, as applicable.
The Gas Metal Arc Welding (GMAW) process shall not be used for welding P-5B (9Cr-1Mo-V), P-15E
(9Cr-1Mo-V), or (9Cr-2W) material.
The GMAW process utilizing the short-circuiting transfer mode shall not be used in any application,
except for carbon steel piping complete penetration butt joint root pass welding, only when permitted by
Table Q210-1. The GMAW process utilizing the globular or short-circuiting transfer mode shall not be
used for branch connections, attachments, fillets, or socket welds.
The weld progression for manual or semiautomatic vertical position welds shall be uphill, except when the
GMAW short-circuiting transfer mode is permitted; then, the progression may be uphill or downhill for the
root pass only.
The Flux Cored Arc Welding (FCAW) process shall only be used with shielding gas.
The FCAW process shall not be used for root pass applications in single welded, complete penetration
weld joints without backing or without backgouging and back welding.
The Shielded Metal Arc Welding (SMAW) process shall not be used for root pass applications in single
welded, complete penetration weld joints of low alloy steel, stainless steel, or nickel alloy steel materials
without backing or without backgouging and back welding.
Backing rings that become a permanent part of the weld shall be made from material of weldable quality,
compatible with the base material, and the sulfur content shall not exceed 0.05 percent.
Nonmetallic retainers or nonfusing metal retainers shall not be used unless specified in the Welding
Procedure Specification (WPS). When used, they shall be removed.
Stainless steel flow nozzles inside carbon steel or low alloy steel pipe shall not be postweld heat treated.
An acceptable alternative is to butter each pipe member by applying weld metal (buttering) to a minimum
thickness of 3/16 inch (5 mm) (after machining), heat treat each pipe member, then weld the two pipe
members together with flow nozzle installed. (Refer to ASME Section IX, Article QW-283 Welds with
Buttering.)
Q210.5.2.1 Interruption of Welding. The conditions for interruption of welding specified in ASME
B31.1, Paragraph 131.6, shall be provided in the WPS or other work control document to ensure that the
minimum preheat temperature is maintained as required.
12 inches (300 mm) for material 6 inches (150 mm) inside diameter or less.
16 inches (400 mm) for material 6 inches (150 mm) through 14 inches (350 mm) inside
diameter.
24 inches (600 mm) for material over 14 inches (350 mm) inside diameter.
If the use of safe ends is not feasible, and if acceptable to Purchaser, then the Supplier shall furnish weld
test coupons for Purchaser's welding procedure qualifications in lieu of safe ends in accordance with the
following requirements:
Material certifications shall be supplied with all material used for weld test coupons.
The weld test coupon material shall be of the same material, chemical composition, and
mechanical properties, type, and/or grade as the equipment connection, such as the
valve or nozzle that it represents.
The material quantity shall be sufficient to complete the required test for the welding
procedure qualification prescribed by the governing ASME code and/or standard. As a
minimum, the weld test coupon material product form shall be of adequate size and
thickness to permit removal of the required test specimens and to qualify the joint
thickness required for the production weld.
The weld test coupon material shall be delivered in adequate time to support the welding
procedure qualification and production schedules as defined by Purchaser.
The difference between major and minor diameters for a distance of 3 inches (75 mm) from the ends of
the pipe shall not exceed 1/8 inch (3 mm) or 1 percent of the nominal diameter, whichever is less.
To ensure satisfactory fit-up for circumferential butt welds in piping systems fabricated of rolled and
welded plate, the following procedures shall be followed:
Concentricity. If weld metal is used to obtain concentricity, the weld deposit shall be free
from porosity or other defects, and the inside surface shall be ground smooth and
blended smoothly into the pipe wall.
Pipe ends for socket-weld connections shall be reamed to full inside diameter to remove all burrs and
obstructions and to ensure proper assembly in accordance with ASME B31.1, Paragraph 127.3(E).
When weld joint details are specified by design documents, they shall be prepared in accordance with
design documents.
Carbon steel stamps shall not be used on stainless steel or nickel base alloy materials.
Stamping shall not damage material or reduce the wall thickness to less than design requirements.
Specifier: Because of ongoing welder or welding operator weld quality issues, project
management should consider adding requirements for random or spot NDE either by the RT or UT
methods. Random or spot RT or UT of a weld joint is recognized as an effective inspection tool
and is considered to aid in quality control. RT or UT of a weld joint directly after a welder or
welding operator has completed a unit of weld proves that the work is or is not being performed
satisfactorily. If the work is unsatisfactory, corrective actions can then be taken to improve the
welding, which should subsequently improve the weld quality. Contact the Materials Applications
Section for assistance in developing project-specific random or spot NDE requirements, as
required.
All circumferential piping butt joint welds in piping directly from the steam generator(s) to
the steam turbine connection(s) shall be 100 percent examined by radiographic testing
(RT) or ultrasonic examination (testing) (UT) and shall meet the acceptance standards of
ASME B31.1.
All piping branch connection joint welds that are over 4 inch (100 mm) nominal pipe size
connecting to piping directly from the steam generator(s) to the steam turbine
connection(s) shall be 100 percent magnetic particle (MT) or liquid penetrant (PT)
examined and shall meet the MT or PT acceptance standards of ASME B31.1.
When the final RT or UT examination of welds is performed prior to PWHT for P-Numbers 15E (9Cr-
1Mo-V) (Grade 91) and unassigned material 9Cr-2W (Grade 92), the applicable welds shall also
require a final MT or PT surface examination after completion of PWHT.
Final VT examination of P-Numbers 3, 4, 5A, and 5B welds shall be performed after PWHT.
The UT equipment used to perform the examination shall record the UT data to facilitate
the analysis of the data by a third party and to ensure repeatability of subsequent
examinations if requested or required by Purchaser. Where physical obstructions
prevent the use of systems capable of recording the UT data, manual UT may be used,
provided Purchaser approval is granted.
The Supplier shall provide Purchaser all required UT equipment clearance dimensions to
ensure that the welds can be properly identified for UT examination and that the UT
examination can be performed with acceptable results.
The Supplier's qualified and certified UT Level III technician shall approve all UT
examination reports.