Professional Documents
Culture Documents
F RO M P OW E R P L A N T S TO DISTRIBU T I O N S U B S TA T I O N S
Charles J. Mozina
Beckwith Electric Company
6190-118th Avenue North • Largo, FL 33773-3724 U.S.A.
Phone (727) 544-2326 • Fax (727) 546-0121 • E-Mail: marketing@beckwithelectric.com
–1–
A
50 51 Winding 1
W1 W1 W1
3I0
51N
W1
IG Winding 2
87 50G 51G
GD W2
87H 87T VG
51N 59G R
W2
50N
BF
24 81U 27
3I0
B
50 50 51 46
BF W2 W2
Standard Function
–2–
Modern overecitation V/Hz protection uses inverse V/ power system maintain voltage within the transformer
Hz curves that can closely match transformer capability. continuous ratings. However, this does not occur dur-
ing abnormal conditions such as the following.
120%
2. A generator voltage regulator “runaway” condi-
110% tion which causes the GSU (generator step-up unit)
100% and the auxiliary transformer to encounter high
voltages. Though this event frequently occurs off-
line, overexcitation can occur with the generator
0.1 1 10 100 1000
and the GSU connected to the power system. V/Hz
Time (Minutes) levels exceeding 1.25 p.u. for such events have
been recorded.
Figure 3 Typical Transformer Power plant transformers, especially GSU and auxil-
V/Hz Short-Time Capability Curve iary transformers, are susceptable to overvoltage for the
reasons cited above. A substantial unbalanced current
will result in the differential circuit due to overexcitation.
Under normal system operating conditions, genera-
If the off-line case is examined, as illustrated below, the
tor voltage regulators and other control devices on the
unbalanced current can exceed 30% of the transformer
rating. An actual in-service case is illustrated in Figure
I=0
4a for off-line voltage regulator “runaway.” Figure 4b
shows the build-up of current for such a condition.
EN
OP
I=0
87U 87T
I = .3 p.u.
24
G Auxiliary
Transformer
I = .3 p.u.
–3–
Figure 4b Off-Line Overexcitation Condition Oscillograph
In cases such as these, the generator transformer dif- during major disturbances, such false operations are not
ferential relay (87T) should restrain and the V/Hz (24) acceptable. In modern digital and static relays, fifth-har-
protection should operate. Electromechanical and static monic is typically used to provide restraint for
differential relays were known to operate and improp- overexcitation conditions. In such cases, a V/Hz (24)
erly indicate an internal transformer fault. Some relay relay needs to be installed to detect overexcitation, since
engineers accepted this as a “good false operation” since these new digital transformer differential relays will re-
it tripped the transformer for a damaging event. For off- strain even for severe V/Hz conditions. In some applica-
line events, this may be acceptable even though it indi- tions, such as the typical gas turbine one-line diagram
cates falsely a transformer failure. But for on-line events, shown in Figure 5, this protection is provided within the
especially those that are triggered by system islanding transformer differential zone to provide V/Hz protection
when the generator is off-line.
–4–
High Voltage Bus
24-2
Auxiliary/Start-Up Auxiliary/Start-Up
EN
OP Transformer Transformer
24-1
G-1 G-2
R R
GSU Ground Transformer Fault Protection The system ground at the low voltage side of the
Figure 6 shows a typical gas turbine one-line. This GSU is provided by the generator neutral grounding trans-
type of arrangement is also used at some hydro plants. former. Ground fault protection is provided by the 64G
relay. However, when the generator is out of service, the
GSU remains in-service to supply the auxiliary trans-
High Voltage Bus former which now acts as the start-up supply for the
plant. For this condition, ground fault protection needs
to be provided in the zone indicated in Figure 6. This
protection is provided by a broken-delta VT connected
to a 59G overvoltage relay. Third-harmonic voltage will
be present across the broken delta when the generator
Ground Fault Zone
protected by 59G Relay is in-service. For this reason, the 59G relay should be
tuned to fundamental (60 Hz) frequency.
59G
Auxiliary/Start-Up Auxiliary/Start-up and Industrial Transformer Protection
Transformer
Auxiliary and start-up transformers at power plants,
as well as transformers at industrial facilities, are gener-
EN
OP
–5–
which is typical of these systems. Thus, motors are not TRANSMISSION SUBSTATION
“shaken-off” due to voltage dips caused by line-to-ground TRANSFORMER PROTECTION
faults.
Overexcitation (V/Hz) Protection
This type of grounding reduces the ground fault cur- Power plant transformers, as described in the previ-
rent within the secondary-winding transformer-differ- ous section of the paper, are not the only transformers
ential zone. This current can be below the threshold of that can be subjected to overexcitation conditions. Au-
operation of the traditional 87T transformer differential totransformers tapped onto EHV lines have been known
relay. Figure 7 illustrates the zone of operation where to sustain prolonged overvoltage. Figure 8 illustrates
the 87T relay may not detect a ground fault. In many such a one-line configuration.
cases, the 51G neutral time overcurrent relay provides
time delay protection for faults in this zone.
Digital Multifunction
Transformer Relay
{
IN
Shunt Reactor 24
51G 87 81T
GD
Zone of R
100 A
to
See Note
Iop=(-3I0)INcosφ
–6–
the gas evolves, the oil, being incompressible, is dis- The physical size and volume of EHV transformers,
placed upward—compressing the gas in the gas cush- coupled with the high fault current levels available on
ion and thereby causing a rate-of-change of pressure. today’s EHV systems, create forces within the trans-
This rate-of-change of pressure is a function of arc cur- former during a through-fault. These forces can cause
rent magnitude and time. The SPR is sensitive enough winding movement or tank-wall deflection of sufficient
to respond to the pressure increase caused by turn-to-
magnitude to cause oil displacement. This, in turn, com-
turn faults and will respond very quickly to severe inter-
nal faults. presses the gas cushion causing a sufficient rate-of-
change of pressure to gas- or oil-type SPR relays. The
A cutaway view of the Westinghouse SPR relay is SPR cannot distinguish between the rate-of-change of
shown in Figure 9. It is mounted in the gas space at the pressure caused by a through fault or a legitimate inter-
top of the transformer tank. Normal pressure changes nal fault. The experience of many utilities confirms that
created by a change in loading or ambient temperature SPR false operations can occur due to through-faults.
are equalized by a small port between the transformer
and the relay chamber. A rate-of-pressure change in ex- The speed of the SPR operation is proportional to the
cess of the normal rate (0.29 to 0.44 psi per second) rate-of-change of pressure that occurs within the trans-
creates a pressure differential across the bellows. The former. Figure 11a indicates the operating time as a func-
bellows actuate the microswitch, shown in Figure 10, tion of rate-of-change of pressure. It is believed that
which picks up a high-speed auxiliary relay (63X) that
most through-faults develop a pressure change in the
initiates tripping of the transformer.
10 to 20 psi per second range. Once actuated, the SPR
MOUNTING BOSS will not immediately reset since the pressure oscillation
(PART OFMOUNTING
TANK WELL)BOSS
(PART OF TANK WELL) continues within the transformer keeping the relay picked-
up. Reset times are shown in Figure 11b. Reference 3
EQUALIZER
EQUALIZER provides a more detailed discussion of SPR operating/
BELLOWS
BELLOWS
MICRO-SWITCH
reset times and includes information on the responses
MICRO-SWITCH
of oil pressure SPR relays.
Operating Time - Cycles
TESTPLUG
TEST PLUG
PRESSTIGHT
PRESS TIGHT CONNECTOR
CONNECTOR
{
50 63RS Pressure Rate of Rise PSI/SEC)
Manual
Blocking Reset 50 Blocking
63X
Trip
63 63X
Voltrap Figure 11a SPR Operating Time (gas type)
SPR
Microswitch
DC Supply
{
63X 63X
63X
Alarm
R1 63X
63 SPR Microswitch
63X SPR Seal-In Relay
63RS SPR Reset Switch
50 Blocking Fault Detector
–7–
Digital Multifunction Transformer Relay
87T
OR NOT
87H
Rate of Rise of Pressure (PSI/SEC)
63
AND Block
50
Faced with the above situation, only two alternatives DISTRIBUTION SUBSTATION
were initially available to relay engineers: TRANSFORMER PROTECTION
• remove the tripping by SPR relays;
Underfrequency/Undervoltage Load Shedding
• retain the tripping and accept the risk of misoperation. (see Figure 13)
The development of current supervision schemes pro- Underfrequency load shedding is widely implemented
vided a third option which retains sensitive transformer at distribution substations. With multiple output con-
protection, while increasing through-fault security. This tacts available on most digital transformer protection
supervision scheme can now be integrated into a digital packages, there is no reason not to incorporate load
transformer relay package. Figure 12 shows the logic for shedding within these relays. Undervoltage load shed-
such an application. ding, however, has been implemented only in a few loca-
tions within the U.S. As U.S. power systems experience
more voltage collapse events, this practice will probably
138 KV become more common. Just as underfrequency is a mea-
sure of the degree of megawatt overload on the power
system, undervoltage is a measure of the degree of the
deficient VArs. If VArs are not available, the voltage
drops and can even drop to the point of collapsing the
Supervises
(63) power system.
–8–
• blocking of LTC’s during declining system voltage taken place. The scheme provides relatively high-speed
as is done by many European utilities; bus fault protection without the addition of separate
• undervoltage load shedding. bus differential relaying.
Undervoltage relays for this application must be de-
signed to restrict their operation to a narrow bandwidth
or range and then to a specific value within that band- Digital Multifunction
width to avoid false operation under fault conditions. In Transformer Relay Programmable
Trip B
Outputs
some cases, the voltage load shedding and LTC block-
ing is put in service only when the power system is in a 50 Programmable
Inputs
high-stress condition. This is accomplished via a SCADA
command for the central dispatch center.
B
Digital Multifunction
Transformer Relay
Setpoint Setpoint Setpoint
#1 #2 #3
81U 1 2 3 4
*
VT
27 C B A
ip ip ip 50-1 50-2 50-3 50-4
*SCADA Enable Tr Tr Tr
(optional)
er er er
er
d d d
ed
ee ee ee
Fe
F F F
Digital Multifunction Transformer Relay
Timer
Figure 13 Underfrequency / Undervoltage 50-1
50-2
Load Shedding 50-3 OR NOT AND Trip B
50-4
–9–
Digital Multifunction
Transformer Relay
Programmable
Inputs
1 2 3 4
Digital Feeder
Protection--
Self-Test
Failure
{ R-1 R-2 R-3
Self-Test Failure
R-4
R-1 Alternate
Self-Test Setting Group
R-2 Programmable
Failure
Feeders R-3 OR --Failed
Feeder
Condition
Output
R-4
Feeder Relay
Trip Contacts
R-1 R-2 R-3 R-4
Feeder Relay
Self-Test
Contacts
–10–
Normal Alternate Setting Group Two-Bank Substation Load Shedding
Failed Feeder Condition Increasing the utilization of two-bank distribution
substations can provide a substantial economic benefit
to a utility. Figure 16a shows a typical two-bank substa-
tion. It is common practice to operate under normal con-
TIME
TIME
ditions with the bus tie breaker open to reduce duty for
Transformer Transformer
Backup Failed Feeder
feeder faults. On the loss of a transformer, or in some
Feeder Feeder cases also the supply line, the affected bank breaker (A
CURRENT CURRENT or C) is opened and the bus tie breaker (B) is closed to
automatically transfer the outage bus section to the com-
Figure 15c Feeder Digital Relay Failure panion bank. To accommodate this type of automatic
restoration, the loading of the two-bank substation is
Backup-Use of Alternate Setting
limited to the N-1 rating of one transformer. This is typi-
Group cal of values above the nameplate rating of one trans-
former and is a short-time rating. The time involved in
establishing this rating is usually based on the utilities
estimate of how quickly (typically one day) load can be
relieved through load shifts to other substations or
through the installation of a mobile substation trans-
former.
Transformer #1
Transformer #2
Digital Multifunction
Transformer Relay
50
A C
Normally-Open
Tie Breaker
1 2 3 4 5 6
–11–
Digital Multifunction Transformer Relay Logic Example:
Programmable
Input N-1 Rating 30 MVA Bank 40 MVA
Full Capacity (30 MVA x2 ) 60 MVA
Tie CB Programmable
52a Outputs Loading Increase 20 MVA
CLOSED
AND Timer TRIP Feeder 1
50*
Timer TRIP Feeder 2
As shown in the example in Figure 16b, loading the 2. “Survey of the Voltage Collapse Phenomenon,” North
distribution substation to the combined rating of both American Electric Reliability Council, August 1991.
transformers can provide a significant load capacity in- 3. “Current Supervision of Fault Pressure Relays on Large
crease. Typically, distribution peak loads occur only dur- EHV Transformers”, C.J. Mozina and D.E. Grimes, PEA,
ing a small percentage of time each year. Thus, the con- February 1977.
current loss of a transformer or supply line at peak load 4. “Increasing the Utilization of Two-Bank Distribution
is a fairly rare event. Reference 4 provides an analytical Substations” C.J. Mozina, PEA, September 1980.
method of evaluating the impact of this type of planning 5. “Microprocessor Transformer Differential Relays Ap-
philosophy on customer reliability. A logic scheme can plication and Operating Experiences”, B.W. Jackson,
be implemented within a digital transformer relay pack- S.B. Ladd, Duke Power Co., Georgia Tech Relay Con-
age that can trip feeders to shed load to protect the ference, May 1997.
remaining transformer from being exposed to loads above
its N-1 short-time rating. The increase in distribution ABOUT THE AUTHOR
capacity by adopting such a planned protection phi- Chuck Mozina is Manager of Application Engineer-
losophy can be significant. ing for Protection and Protection Systems for Beckwith
Electric Co. He is responsible for the application of
CONCLUSION Beckwith products and systems used in generator pro-
tection and intertie protection, synchronizing and bus
With the advent of more powerful microprocessor- transfer schemes.
based digital transformer relays, integration of additional
functions beyond transformer differential and overcurrent Chuck is an active member of the IEEE Power System
relaying is possible within these relay packages. Func- Relay Committee and is the past chairman of the Rotat-
tions such as V/Hz overexcitation, neutral overvoltage, ing Machinery Subcommittee. He is the U.S. representa-
ground differential and underfrequency/undervoltage load tive to the CIGRE Study Committee 34 on System Pro-
shedding add enhanced protection features within the tection and chairs a CIGRE working group on generator
transformer protective zone. User-selectable functions protection. He also chaired the IEEE task force which
allow these relays to be configured to meet specific pro- produced the tutorial The Protection of Synchronous
tection application requirements. Schemes that integrate Generators, which won the PSRC’s 1995 Outstanding
the logic of the transformer and digital feeder relays fur- Working Group Award. Chuck is the 1993 recipient of
ther enhance user benefits. This paper outlined a num- the PSRC’s Career Service Award.
ber of specific applications and logic schemes that can
benefit users. Chuck has a bachelor of science in electrical engi-
neering from Purdue University and has authored a number
of papers and magazine articles on protective relaying.
REFERENCES He has over 25 years of experience as a protective engi-
1. ANSI/IEEE C57.12 “Standard General Requirements neer at Centerior Energy, a major investor-owned utility
for Liquid-Immersed Distribution, Power and Regu- in Cleveland, Ohio. He is also a former instructor in the
lating Transformers.” Graduate School of Electrical Engineering at Cleveland
State University.
–12–