Professional Documents
Culture Documents
7.1 Introduction
Kerala Border to Thrissur of NH-47 is an important link providing the most direct
route from Tamilnadu, Karnataka , Andhra Pradesh and other parts of India to
Kerala. In view of this, it is considered part of North-South corridor by NHAI for
capacity augmentation to 4-lanes.
The data for the study has been collected from field surveys as well as from
secondary sources. Vehicle and traffic growth rates have been correlated to the
demographic and economic growth trends of the state to establish future growth
rates. The link-wise travel demand has been projected as per the growth rate
estimates and a traffic diversion procedure has been used to derive traffic on
different links of the road network.
The details on traffic surveys and results from its analysis are presented in this
chapter followed by the derivation of traffic growth rates and traffic diversion
analysis to estimate travel demand on the project road.
7.1.1 Objectives
7.1.2 Surveys
To fulfill these objectives, the following traffic surveys were carried out
7.2.1 Objectives
The intensity of traffic flow at any given section of the road forms the
basis for determining its spatial and structural design requirements. The
collection of traffic data thus assumes utmost significance in the
development of any road project. In order to assess the Average Daily
Traffic at any section of road, classified traffic counts are carried out for a
continuous period of 7 days to average any variation in the short term.
7.2.2 Methodology
The project road was divided into four homogeneous sections based on
preliminary reconnaissance studies in such a way that the traffic intensity
within a particular section will be more or less uniform. Classified traffic
counts were organised at one selected location in each section. The
locations of 7-day continuous traffic count stations are Table 7.1. Data on
the number of vehicles of different categories moving along the road in
both directions are noted by enumerators specially trained for this
purpose. The vehicles are broadly classified into motorised and non-
motorised vehicles, which are further sub divided into specific categories
of vehicles. The traffic counts are generally conducted in accordance with
IRC SP19-2001. However, the groupings of vehicles are further split to
reflect the present day traffic pattern on the project road.
Count
Homogeneous Section Location Survey dates
No.
The summary of ADT, in terms of vehicles and PCU at all the four count
locations is given in Table 7.2. The details pertaining to hourly and day
wise distribution of average daily traffic at the seven count locations are
given in Annexure VII.
It may be noted that there was a general strike of state private bus
operators over entire kerala state from 26th to 30th July 2004, there was a
fall in Mini Bus and Bus traffic during these days. It is therefore
considered to justified to take the 5 days average from 21st to 25th for Mini
bus and Bus traffic at Km 237/000, and 2 days average from 24th to 25th at
km 191/000.
From Table 7.2 and Annexure VII, the following can be observed.
Table 7.2
14000
12000
Non-Motorised vehicles
2000
Analysis has been carried out to understand hourly variation and peak
hour traffic characteristics. The hourly distribution of traffic at various
count locations is illustrated in Annexure VII.
Vehicles Vehicles
1 634 36 939 214 0 495
2 639 14 997 284 0 597
3 628 9 1068 236 0 610
4 915 15 1502 243 0 609
1000
900
800
Motorised Vehicles(Numbers)
700 SC 1
600 SC 2
500
SC 3
400
SC 4
300
200
100
0
10:00 12:00 14:00 16:00 18:00 20:00 22:00 0:00 2:00 4:00 6:00 8:00
Tim e
Fig 7.28 Hourly Variation of Non Motorised Traffic at Different Count Stations
40
35
Non-Motorised Vehicles(Numbers)
30
25
SC 1
20
SC 2
15
SC 3
10
SC 4
0
10:00 12:00 14:00 16:00 18:00 20:00 22:00 0:00 2:00 4:00 6:00 8:00
Tim e
1600
1400
1200
Total Traffic (PCU's)
1000
SC 1
800
SC 2
600
SC 3
400
SC 4
200
0
10:00 12:00 14:00 16:00 18:00 20:00 22:00 0:00 2:00 4:00 6:00 8:00
Tim e
The Peak Hour Factor (PHF) (defined as the ratio between the number of
vehicles counted during the peak hour to the total vehicles counted in a
day) calculated at various count locations is presented in Table 7.4.
From the table and illustrations in the Annexure, it can be observed that
the peak hour traffic volume at different count stations range between
5.33% in section 2 to 5.92% in section 4, the mean peak hour factor being
5.54 % at different survey locations.
7.3.1 Objective
7.3.2 Methodology
The O-D survey elicited passenger mode characteristics like origin and
destination, occupancy, trip purpose and length of trip by mode type. For
goods modes, the survey elicited characteristics like origin and
destination, commodity type and length of trip.
7.3.3 Zoning
The entire country was divided into 38 zones in such a way that the
characteristics of interzonal and intrazonal trips could be clearly analysed
and their influence assessed on the project road. The details of zones are
given in Annexure VIII.
With respect to goods vehicles, the types of goods carried were broadly
grouped into 8 categories, plus empty trucks.
The commodity groupings are as follows:-
Sample Size
The sample size for each category of goods vehicles at both locations are
summarised in Table 7.7. As can be seen in the table, the sample size for
various types of goods vehicles ranges between 15% and 35%.
7.3.4 OD matrices
Trip Distribution
The OD matrices derived from the OD data collected at both locations are
combined into one matrix to obtain OD matrix for the project. The
combined OD matrix is analysed to assess the travel pattern of both goods
and passenger vehicles. The analysis of the travel pattern reveals the
following:
Of the total goods traffic observed on the project road, 12% generates
(including both originating or terminating traffic) at Coimbattore city, 8%
generates in Palakkad, 12% in Thrissur, 19% at Ernakulam, 4% in
Kottayam and Quilon districts, 17% at other parts of Tamilnadu, 4% in
Karnataka 3% in Andhra Pradesh, 2.5 % in other parts of Country and
18.5% other Parts of Kerala State.
Of the total Passenger traffic observed on the project road, about 19%
generates (including both originating or terminating traffic) at
Coimbattore City, 16% generates in Palakkad, 17% in Thrissur, 10% at
rnakulam, 2.5% in Kottayam and Quilon districts, 5% at other parts of
Tamilnadu, 0.5% in other parts of Country, 30% in other parts of Kerala.
Goods Trips
Region-wise Contribution of Trips (in %)
Andhra
Vehicle Type Kerala Tamilnadu Karnataka Pradesh Others
LCV 74.86 22.06 2.43 0.67 0.00
2-Axle Truck 61.94 29.50 4.52 1.28 2.77
3-Axle Truck 50.99 32.09 2.87 12.09 2.27
From the above table it can be seen that the observed goods traffic is
generally a mix of short and long distance traffic whereas most of the
passenger traffic generates within the Kerala and Tamilnadu States.
Figure 7.30 presents the lead distribution for goods vehicles at both the
locations combined. As can be observed, around 12 % of vehicles have a
lead of less than 50 km, 11% have a lead between 51-100 km, 21%
vehicles have a lead between 101-200 km, 20% have a lead in the range
of 201-400 km, 23% have a lead in the range of 401-800 km, 8.5% have a
lead in the range of 801-1600 km, 4% have a lead in the range of 1601-
3200 km and 0.5% vehicles have lead of more than 3200 km. The goods
traffic therefore is a mix of short and long distance traffic with a higher
percentage of long distance traffic.
20.00
% of Vehicles
15.00
10.00
5.00
0.00
<=50 51 to 101 to 201 to 401 to 801 to 1601 to >3200
100 200 400 800 1600 3200
Lead in Km
Figure 7.31 presents the lead distribution for passenger Cars at both the
locations combined. As can be observed, around 30 % of vehicles have a
lead of less than 50 km, 28% have a lead between 51-100 km, 21%
vehicles have a lead between 101-200 km, 12% have a lead in the range
of 201-400 km, 4% have a lead in the range of 401-800 km, 2% have a
lead in the range of 801-1600 km, 2% have a lead in the range of 1601-
3200 km and 1% vehicles have lead of more than 3200 km. The goods
traffic therefore is a mix of short and long distance traffic with a higher
percentage of short distance traffic
35.000
30.000
25.000
% of Vehicles
20.000
15.000
10.000
5.000
0.000
>50 50-100 100-150 150-200 200-250 250-300 300-500 >500
Lead in Km
Table 7.10
Table 7.11
WTP Survey for Truck Operators has been conducted at 2 locations along
with the O-D Survey. Response of car user for various toll levels has
been recorded. The survey has been conducted on random sample basis,
for duration of 24 hours on normal days. The findings of the survey are
reported in Table 7.12
Acceptence
WTP
(%)
0.60 Rs/Km 6.2
0.45 Rs/Km 15.1
0.30 Rs/Km 31.4
0.15 Rs/Km 39.4
0.0 Rs/Km 7.9
Total 100.0
WTP Survey for Truck Operators has been conducted at 2 locations along
with the O-D Survey. Response of Truck Operators for various toll levels
has been recorded. The survey has been conducted on random sample
basis, for duration of 24 hours on normal days. The findings of the survey
are reported in Table 7.13
Acceptence
WTP (%)
2.0 Rs/Km 1.80
1.5 Rs/Km 9.40
1.0 Rs/Km 51.70
0.5 Rs/Km 31.40
0.0 Rs/Km 5.70
Total 100.00
7.5.1 Objective
7.5.2 Methodology
Three locations of high pedestrian activity were chosen for the study. All
these locations are within the village and Towns. These are
i) Km 203.600 – Koothupatta
ii) Km 203.900 – Chandra Nagar Bus Stand
iii) Km 204.600 – Manoothy
The details of pedestrians crossing the Project road at the mid block
sections Survey was conducted between 8.00 am to 8:00 pm. The data has
been tabulated and analysed in order to decide the highest intensity of
pedestrian movement at these locations.
Table 7.14 Peak hour pedestrian movements across the Project road
Peak Hour
Pedestrian Traffic 206 106 913
(P)
Present Conflict
3.11 3.48 14.09
Level (PV2/2x10^8)
7.6.1 Objective
7.6.2 Methodology
The directional traffic counts were carried out for 12 hours between 8 am
and 8 pm at 15 minutes intervals.
The peak hour flow diagrams are given in Annexure IX. As per IRC:93-
1985 (“Guidelines on Design and Installation of Road Traffic Signals”)
the traffic at intersections will require time separation, i.e., signal control,
when the major road flow is more than 800 vehicles per hour (both
directions) and the minor road flow is more than 250 vehicles per hour
(one direction) for each of any 8 hours of an average day.
i. Km 202/800 – To Pollachi
It is a three-arm junction, with two arms being NH 47 and the
third one Road leading to Pollachi. The peak hour traffic at this
junction is 1724 veh/hr on major road (all directions) and 304
veh/hr on minor road. The total pcu at this junction during peak
hour is 2489 pcu/hr. The traffic on major arm and minor arm
satisfies the IRC specifications for signalisation, assuming an
average growth rate of 8.5% p.a. the junction will require grade
separation by the year 2022.
this junction during peak hour is 1693 pcu/hr. The traffic on major
and minor arms warrants signal control at this junction as per IRC
specifications, assuming an average growth rate of 8.5% p.a. the
junction will require grade separation by the year 2025.
As per the existing traffic and projected volumes for next 5 years or so
erection of traffic signals at the above Intersections/Junctions shall be
justified, however it is felt that to provide uninterrupted and safe flow of
the traffic on the National Highway “Grade Separators” may be
constructed at the following locations along with the widening of the
National Highway.
7.7.1 Objective
7.7.2 Methodology
The details of average travel speeds along the project road morning,
afternoon and evening are indicated in Figure 7.32.
The average speed in the morning along the project road is 41.26 kmph,
which rises to about 43.08 kmph in the afternoon and then falls to 40.19
kmph in the evening.
46.0
44.0
42.0
Speed (Kmph)
Morning
40.0 Afternoon
Evening
38.0
36.0
34.0
Valayar to Palakkad Palakkad-Alathur Alathur-Vadakanchery Vadakanchery-Thrissur
7.8.1 Methodology
Details of traffic accidents which occurred on the project road during the
past 6 years were collected from the Police records and analyzed. The
accident data collected year wise with number of accidents in respective
year has been given Figure 7.33 and Table 7.16.
600
500
400
300
200
100
0
2004 (Up
1999 2000 2001 2002 2003
to 31/08)
Palakkad District
Valayar Police Pudussery Police Station Palakkad Police
Station Station
Year Fatal Non-Fatal Fatal Non-Fatal Fatal Non-Fatal
1999 13 39 17 62 3 46
2000 12 47 22 58 6 39
2001 14 45 22 61 12 37
2002 20 54 13 35 14 39
2003 12 51 12 34 10 39
2004 14 38 2 33 4 23
(31.08.2004)
Thrissur District
Peechi Police Station Mannoothy Police Station Total (Thrissur District)
Year Fatal Non-Fatal Fatal Non-Fatal Fatal Non-Fatal
1999 13 61 9 40 22 101
2000 23 77 4 43 27 120
2001 14 65 6 60 20 125
2002 6 69 13 51 19 120
2003 2 70 13 43 15 113
2004 13 34 5 29 18 63
(31.08.2004)
Palakkad District
Thrissur District
7.9.1 General
263/700 in Thrissur district on 7th and 8th August 2004. The studies were
conducted using two calibrated electronic weigh axle load pads, one in
each direction. The studies were carried out for a continuous period of 48
hours at each location covering both directions of traffic. To avoid traffic
bottlenecks at site, the axle load survey was conducted alternatively in
each direction for 3 hours. Two axle, three axle and multi axle trucks and
light goods vehicles (both loaded and empty) were selected at random and
weighed to determine their individual axle weights. A number of buses
were also weighed at each location.
VDF=(AXLj/SXLj)LE
Where,
VDF= Vehicle Damage Factor
LE = Axle load equivalency exponent=4.0
AXLj = Axle load
SXLj = Standard load
Remaining vehicle types were not considered in the analysis since most of
them are too light to provide significant distress to the pavement (e.g cars,
two-wheelers, tractors, etc).
The VDF of the different types of vehicles weighed at the above two
locations and in either directions are indicated in Figure 7.34 and 7.35.
8
6.625
7
6 5.117 5.336
5
V.D.F 3.657 Km 191/000
4 2.871
3 2.166 Km 263/700
2 0.168 0.65
1 0.11 0.533
0
LCV 2 - Axle 3 - Axle Multi Axle Bus
Truck Truck Truck
Types of Vehicles
3.576
4 3.1863.349
3
1.833
1.686
2
1 0.45
0.1480.081 0.305
0
LCV 2 - Axle 3 - Axle Multi Axle Bus
Truck Truck Truck
Types of Vehicles
Location: 190/000
Direction: Kerala Border to Thrissur Direction:Thrissur to TN/Kerala Border
Vehicle Type A.A.D.T VDF ESAL A.A.D.T VDF ESAL
Location: 263/700
Direction: Kerala Border to Thrissur Direction:Thrissur to TN/Kerala Border
From the above analysis the consultants recommendation is for adopting V.D.F.
value as 2.30
7.10.1 Background
Location
(Km) Year Cars/3Wheelers Buses Goods Vehicles TW
1992 3709 1186 3172 2393
1993 4981 2028 4039 3398
1994 5494 1715 4244 3708
1995 5974 2115 4844 4387
1996 6492 2480 5198 4709
191/000
1997 6795 2718 4456 5137
1998 7185 3161 6064 5593
1999 7485 3399 6366 5696
2000 7924 3756 6815 6017
2001 7904 3694 6546 5974
2002 7343 3385 6189 5480
AACGR(%) 1992-2002 7.07 11.06 6.91 8.64
203/000 1992 5251 1592 3516 3467
1993 4312 1756 4832 3824
1994 6011 1858 4911 3914
Vehicle type wise annual growth rates are observed with fluctuations
among the count stations. Hence an attempt was made to calculate
elasticity values for two count stations (km 191/000 and Km 263/000) to
verify its suitability. The economic indicators of Kerala and Tamilnadu
states, which are used for the regression analysis along with traffic data
considered (km 191/000 and Km 263/000), are given in Tables 7.19to
Tables 7.22 and their detailed analysis is presented in Annexure - XI.
Table 7.19 Data Considered for Regression Analysis (Past Traffic at Km 191/000 and
Kerala Economy)
Per capita
NSDP (Rs. Population NSDP2 Cars/3 Goods
Year Lakhs)2 ('000) (Rs) Wheelers1 Buses1 Vehicles1 TW1
1993-94 2385107 30048 7938 4981 2028 4039 3398
1994-95 2590792 30424 8516 5494 1715 4244 3708
1995-96 2694747 30805 8748 5974 2115 4844 4387
1996-97 2802645 31186 8987 6492 2480 5198 4709
1997-98 2863315 31539 9079 6795 2718 4456 5137
1998-99 2985358 31856 9371 7185 3161 6064 5593
1999-00 3111132 32145 9678 7485 3399 6366 5696
Table 7.20 Data Considered for Regression Analysis (Past Traffic at Km 263/000 and
Kerala Economy)
Per capita
NSDP (Rs. Population NSDP2 Cars/3
2
Year Lakhs) ('000) (Rs) Wheelers1 Buses1 Goods Vehicles1 TW1
1993-94 2385107 30048 7938 2746 1476 3402 488
1994-95 2590792 30424 8516 2915 1483 3051 578
1995-96 2694747 30805 8748 4100 2042 4518 924
1996-97 2802645 31186 8987 5585 2266 5468 1290
1997-98 2863315 31539 9079 5556 1918 4839 1787
1998-99 2985358 31856 9371 6167 2422 5822 1643
1999-00 3111132 32145 9678 6625 2901 6037 1759
Per capita
NSDP (Rs. Population NSDP2 Cars/3 Goods
Year Lakhs)2 ('000) (Rs) Wheelers1 Buses1 Vehicles1 TW1
1993-94 5164169 576872 8952 4981 2028 4039 3398
1994-95 5808144 584109 9944 5494 1715 4244 3708
1995-96 6027459 591436 10191 5974 2115 4844 4387
1996-97 6331673 598261 10583 6492 2480 5198 4709
1997-98 6793632 604442 11240 6795 2718 4456 5137
1998-99 7185175 610207 11775 7185 3161 6064 5593
1999-00 7697144 615574 12504 7485 3399 6366 5696
Table 7.22 Data Considered for Regression Analysis (Past Traffic at Km 263/000
and Tamilnadu Economy)
Per capita
NSDP (Rs. Population NSDP2 Cars/3 Goods
Year Lakhs)2 ('000) (Rs) Wheelers1 Buses1 Vehicles1 TW1
1993-94 5164169 576872 8952 2746 1476 3402 488
1994-95 5808144 584109 9944 2915 1483 3051 578
1995-96 6027459 591436 10191 4100 2042 4518 924
1996-97 6331673 598261 10583 5585 2266 5468 1290
1997-98 6793632 604442 11240 5556 1918 4839 1787
1998-99 7185175 610207 11775 6167 2422 5822 1643
1999-00 7697144 615574 12504 6625 2901 6037 1759
7.10.3 Elasticity’s
Table 7.25 Regression Analysis Results (Past Traffic Data at Km 191.000 with
Tamilnadu Economy)
R2(Co- t - stat.
Dependent Independent relation Elasticity (Statistical test
Variable Variable Period Coefficient) Value Co-efficient)
Table 7.26 Regression Analysis Results (Past Traffic Data at Km 263.000 with
Tamilnadu Economy)
Independent R2(Co-relation Elasticity t - stat.(Statistical
Dependent Variable Variable Period Coefficient) Value test Co-efficient)
log of Population 1993-2000 0.93 14.8 8.28
log of Car Traffic log of PCI 1993-2000 0.85 2.95 5.22
log of Population 1993-2000 0.83 9.67 4.93
log of Bus Traffic log of PCI 1993-2000 0.78 1.96 4.16
log of Population 1993-2000 0.92 22.04 7.75
log of TW Traffic log of PCI 1993-2000 0.85 4.42 5.26
log of Truck Traffic log of NSDP 1993-2000 0.71 1.99 3.49
Table 7.27 Recommended Elasticity for Past Traffic Growth Weighted Average
To have a better idea of projections elasticity values has also been worked
out adopting the procedure as suggested by Indian Roads Congress (IRC:
108-1996). Past data for 7 years from 1993 to 2000 on vehicle type wise
registration and economic variable performance in Kerala and Tamilnadu
States was considered for log-log regression technique. In tune with the
analysis philosophy indicated earlier, as well the past performance and the
composition of Kerala and Tamilnadu economy, the passenger and goods
vehicles growth were regressed with the following economic indicators in
different combinations:
• Population
• Per Capita income (PCI)
• NSDP (Total)
Table 7.28 Data Considered for Regrssion Analysis (Vehicle Registration Data
and Economic Indices for Kerala State)
Per
capita
2
NSDP (Rs. Population NSDP Cars/3 Goods
Year Lakhs)2 ('000) (Rs) Wheelers1 Buses1 Vehicles1 TW1
1993-94 2385107 30048 7938 226806 30370 88455 428641
1994-95 2590792 30424 8516 247605 34862 100252 496873
1995-96 2694747 30805 8748 273922 38177 111762 591923
1996-97 2802645 31186 8987 257048 43030 131311 694242
1997-98 2863315 31539 9079 330603 55482 139145 798982
1998-99 2985358 31856 9371 370964 48884 151082 904961
1999-00 3111132 32145 9678 396874 58888 163443 1020797
AACGR(%)
from 1994- 4.53 1.13 3.36 9.77 11.67 10.77 15.56
2000
Per
NSDP capita
(Rs. Population NSDP2 Cars/3 Goods
Year Lakhs)2 ('000) (Rs) Wheelers1 Buses1 Vehicles1 TW1
Table 7.30 Regression Analysis Results (Vehicle Registration Data with Kerala
Economy)
R2(Co-
Dependent relation Elasticity t - stat.(Statistical
Variable Independent Variable Period Coefficient) Value test Co-efficient)
Table 7.32 Recommended Elasticity for Vehicle Registration Growth Weighted Average
Weighted Weighted
Average* Average*
Elasticity for Elasticity for Recommended Elasticity(Weighted Average)*
1993- Economic 1993- Economic
2000(Presen variable 2000(Presen variable 2015 and
Vehicle Type t Study) considered t Study) considered 2005-2009 2010-2014 beyond
• 2005 – 2009
• 2010 – 2014
• 2015 and beyond
We feel, any projection beyond 10-15 years will have little relevance in
current context, and no further projection is attempted. Hence, the entire
period beyond 2015 has been kept as one slab. The consideration of time
periods is mainly based on the Five Year Plan periods practiced at
national and state levels.
Based on the performance of the economy and the near term economic
development contemplated in the states, the future growth pattern of
Kerala and Tamilnadu states economy is likely to follow the growth rates
indicated below:
Kerala State
Tamilnadu State
Passenger Vehicles
Where,
Tgr – Traffic growth rate
Pgr – Population growth rate
PCIgr – Per capita income growth rate
E – Elasticity value
Above passenger vehicles model assigns equal weightage to the economic
variables of population and per capita income.
Goods Vehicles
Tgr = ( NSDPgr) x E
Where,
The forecast of the traffic has been based further analyzed under three
scenarios as follows:
For the project road traffic growth rates were arrived on weighted average
basis. To assess the effect of individual state’s economy on the project
road from the states within the project influence area, traffic composition
weight for different vehicle types from different states were arrived from
origin – destination surveys. Based on the recommended elasticity’s and
the weighted economy, growth scenarios for different vehicle types on the
Project Road are presented in Table 7.33.
2015 and
S.No Vehicle Type 2005-2009 2010-2014 beyond
1 Car 8.41 8.34 7.03
2 Goods Vehicles 6.56 5.86 4.53
3 Bus 5.85 5.25 3.87
4 TW 7.8 7.11 6.17
Agri
5 Tractor/Trailor 5.86 4.53 3.87
Post evaluation studies carried out along few completed four lane roads as
well the actual observations on similar completed roads indicate that
following completion of the road improvements, new developments have
occurred along the road which includes industry, educational institutions,
commercial and residential buildings. As a result of this development,
generated traffic can be expected but as yet not has been quantified. Thus
the proposed 4 lane divided highway facility for the Project Road is also
likely to attract generated and diverted traffic in view of its better
performance characteristics such as higher operating speeds and better
riding quality. However, in the absence of precise information regarding
future growth factors of parallel transport facilities such as railways, it is
reasonable to assume a notional increase in the road traffic due to
generated/diverted traffic. This generated traffic could be expected to add
to the normal traffic during the initial years when the 4-lane road facility
becomes operational. Accordingly, the generated/diverted traffic is
assumed in a phased manner as follows:
Year 1 - 1%
Year 2 - 2%
Year 3 - 3%
The mode-wise AADT has been projected in vehicles and PCUs for
different years and sections of the project road under different growth
scenarios and is presented in Annexure-XI. The Summary of projected
motorized traffic at different locations given at Table 7.34
7.10.11Lane Requirements
The IRC guidelines (IRC: 64-1990) stipulates the daily capacity for two and
four lanes highways as follows:
capacity, i.e. 15000 PCU/day for 2 lane road and 40,000 PCU/day for 4 lane
road) as design capacity.
Based on the above capacity criteria, the lane configuration for the project
road during the analysis period is worked out and results of same are
summarized in Table 7.35
As shown above, all the sections of the project road are eligible for
widening to 4-lane configuration.