Professional Documents
Culture Documents
doc
Suraj_engineer@yahoo.co.uk
Any accountable professional has to carry out any job normally but,
when some job is done based on additional thoughts or research
based performance enriching the grade of the product in terms of
superior quality at cost of normal budget, saving on the cost of
project, saving quantities of expansive material, saving the contract
time based on superior alternatives, excellent methods alternatives
than usual, presenting the project with added service life, allowing
better use flexibility on designs, inducing environment friendly
provisions, adding green use capability of building by saving energy
consumptions, allowing various other benefits for the user or client at
the same or normal cost without risking safety by thoughtful approach
adoption. These benefits amount to the Value addition on the project
in any form, the project proposal overweighs the normal one or
conventional bids. This specially induced quality of performance
Owner has a right to expect best product out of monies spent. Work
should be awarded to a contracting party who corroborates the offer
to work & produce project with Value Engineering. Exclusive price
comparison is not suggestive to be made an exclusive basis for
deciding any contract.
Designer should produce a best design making life of all others easy.
Definitions in a nutshell:
Supervision End:
1. On any supervision level, the engineers are deployed in the
capacity of Resident Engineer to work on behalf of the
Contractual Engineer.
Construction End:
1. Project Manager/Project Engineer downwards the
organization line to Foreman, supervisor & chargehand, work in
any construction contracting company. All these designations
are factually responsible for the achievement of the project
construction execution. In case, project is designated as EPC
i.e. Engineering, Procurement & Construction, various sections
as defined, are integrated to work together with independent
authorities controlled under competent coordination.
Virtually, Resident Engineer & the Site Agent are considered equals
as project site authorities for functional purposes on site organization
from different parties.
d. Site Surveying
e. Site Start or kick off
f. Site Construction
g. Site Quality
h. Site Supervision
i. Site Completion & maintenance
4. In case, the localized soil does not allow the adopted design
parameters, the design should be reconsidered. It is the
responsibility of the Site Engineer to conduct this test in all
major areas of site employing approved laboratory if so required
in contract.
7. All relevant Engineers must sign the Inspection & Testing Plan/
ITP for such activity.
Concrete trial mix should also be carried out so that right quality
required mix from RMC is produced to meet the design requirement.
Piling should be done fully in compliance to the specific design & test
load requirement. Load tests as well as integrity test must be
rightly/satisfactorily conducted. Connections between the piles cut off
level & pile cap should be rightly/satisfactorily made. Test piles
activity must be conducted much in advance.
1. All steel bars details must be produced in the form of BBS Bar
bending schedule prior to giving to fabrication. These should
meet the requirements to avoid the stresses’ localisations. As
far as practicable, overlaps should be avoided. Rings or
stirrups should be fixed in such a way that hooks do not
continue on one side.
13. During EQ, any services too can break due to horizontal
forces which require strong & durable fills around with durable
joints.
15. For higher size bars, overlaps do not work perfectly, Mechanical
connectors / couplers should be used. Generally rebars dia 20
& above work better when mechanically connected / coupled.
16. Hardened concrete is, as a bad practice, cut for passing any
small air conditioning duct already missed. No hardened
concrete should be cut without proper investigation by design
engineer or resident engineer.
24. Curing is not completed for the required period. Do not ignore
curing. Ignorance on concrete curing can cause a major
problem & non conformance report / NCR on this account may
have no solution for closing its validity of action. It is too easy to
pour concrete but, extremely expensive to dismantle & rebuild.
25. Incorrect cut rebars are forced to be placed in & unusually bent
further. Prepare good BBS (bar bending schedule) prior to
starting cutting & bending. BBS can be produced on excel
sheet duly using required formula. Cutting lengths should be
shown with shape codes.
26. Stirrups are not rightly centred. Do proper fixing work. Proper
work of rebars shall help satisfactory concrete pour.
27. Rebars are not centred properly. Do proper fixing work. Proper
work of rebars shall help satisfactory concrete pour.
28. Rebars supporting chairs are not rightly cut & fixed. Check
before fabrication all required dimensions. Do not depend on
steel fixers overconfidently. Rebars fixing is a complex activity.
Make sure that it is carried our correctly.
29. Rebars are not well secured. Bind bars properly without
worrying about the binding wire cost. Check fixing
arrangements over all joints. Check continuity of reinforcement
if feasible, by using voltage or current flow method. It is usually
employed for checking cathodic protection.
30. Tie bolts are not tightened properly. Use correct dimension tie
bolts & fix properly as required. Fabrication of these bolts must
be done exactly to requirements.
32. Extra previous laid concrete is not chipped out. Site should be
kept tidy in all respects. Chip all surplus required concrete.
Produce good & effective construction joints.
33. Holes are not left for cleaning out dust from the forms. It is
practically required to dust out the preparatory works. Use
compressor to clean out the preparatory works.
38. Remedial actions on the defects are cared by site staff without
even informing site engineer. Keep an eye on foreman /
supervisor & other persons responsible. It is too significant an
issue. Site Agent could be removed doing such negligence on
supervision.
39. Formwork is struck before the defined time limit. Record the
dates in the concrete register for all pours. Record all test
results. Record all curing dates.
41. Class one bricks are not procured or even not available.
Procure good bricks or blocks. Avoid using weak bricks. Do not
include inferior bricks below ground level or in foundations.
42. Wooden planks are used for formwork with leaking joints. Better
suggested to use ply for good results. Plywood can be
economically used repetitively. Decide for number of elemental
sets for formwork repetition judiciously.
43. Formwork is not correctly leveled. Set out the form work
properly. Check all lines & levels truly. Check all feasible as well
as necessary controls. Checking controls is a cumbersome
activity.
44. Grouting for the structural steel bases that are designed
generally RCC foundations, requires a good control as it is
cement based material. Similarly, grouting for under the
anchorage plates requires good controls. Epoxy grouting under
base plates of vibratory equipment should be carried out
complying with specified requirements.
45. Do not go ahead for any work where doubts exist either in
specifications or in design. Obtain clarified answers in the form
of Site Technical Queries before carrying out ambiguous items.
b. Patience pays on site. Panic harms the works. Plan properly all
day to day activities. Progress is required but not at quality cost.
Safety first & Quality must slogan has to be promoted as well
as applied in all respects. Safety is responsibility of one & all.
Seismic Retrofitting:
The structural modifications to upgrade the strength, ductility
and energy dissipating ability of seismically deficient or earthquake-
damaged structures with a mission to rehabilitate can be termed as
Retroffiting.
Seismic Strengthening:
The process of enhancing or augmenting the strength of existing
structures to make them resistant to seismic activity, ground motion
or soil failure due to earthquakes from the original design status
with or without including EQ forces, to be used for further
higher stresses to extend service life of structure can be
termed as Strengthening.
Identifications:
2. All details from site observations & samples collected from sites
can be reported to the laboratories as well as to the relevant
authorized engineer.
2. Aviation Helicopters/Cranes/
Mission
To formulate Guidelines for the preparation of plans to reduce
earthquake risk, and minimise these, impacts, losses of lives and
damages to properties caused by earthquakes.
Term Definitions:
Disaster
A catastrophe, mishap, calamity or grave occurrence in any area,
arising from natural or manmade causes or by accident or by
negligence which results in substantial loss of life or human suffering
or damage and destruction of property or damage and degradation of
environment and is of such a nature or magnitude, beyond coping
capacity of the community of the affected area
Hazard
A threatening event or the probability of occurrence of a potentially
damaging phenomenon (an earthquake, a cyclonic storm or a large
flood) within a given time period and area.
Disaster Management
A continuous and integrated process of planning, organising,
coordinating and implementing measures which are necessary or
expedient for prevention of danger or threat of any EQ caused
disaster.
Preparedness
Risk
The expected number of lives lost, persons injured, damage to
property and disruption of economic activity due to a particular natural
phenomenon.
Risk Assessment
The determination of the nature and extent of risk by analysing
potential hazards and evaluating existing conditions of vulnerability
that could pose a potential threat or harm to people, property,
livelihoods, and the environment.
Risk Management
The systematic process of using administrative decisions,
organisation, operational skills and capacities to implement policies,
strategies and coping capacity of the society and communities to
lessen the impact of hazards.
Specific Risk
The expected degree of loss due to particular natural phenomenon.
EQ risk can be assessed in any area.
Seismic Retrofitting
The structural modifications to upgrade the strength, ductility and
energy dissipating ability of seismically deficient or earthquake
damaged structures.
Seismic Strengthening