Antenna System (on Tower)

Installation Standard Model

Issue: 03
Part Number: 31504647
Date: 2009-03-25

HUAWEI TECHNOLOGIES Co., Ltd.


Installation Tools

Some of the installation tools can be adjusted to fit to the site situation.

Flat-head screwdriver Phillips screwdriver Snap-off knife Open-end wrench Adjustable


(M4 / M6) (M4 / M6) (13 mm -- 32 mm) wrench

Cable cutter Diagonal pliers Pincer pliers Hacksaw File

Ladder Rope Brush Heat blower Feeder cutter

Measuring tape Steel tape Compass Inclinometer Fixed pulley

Insulation tape Waterproof tape Color ring tape VSWR tester

1
Antenna System Installation Procedure

1. This guide describes the procedure for installing three directional


antennas (with main and diversity and using fixed-length jumpers) on a
tower that is 40 m high. 40 m feeders are used for the installation.
2. Four installers are required for the installation. Two installers should be
qualified for climbing the tower.

Start

00:00-00:10
Assemble the antenna

00:10-00:25
Connect jumpers to the
Antenna

00:25-00:55
Lift the antenna

00:55-01:45 00:55-01:45
Install the antenna Make feeder connectors

01:45-02:15
Lift the feeder

02:15-02:45
02:15-02:45
Connect feeders to
Fix feeder fasteners
jumpers of the antenna

02:45-05:25
Install and ground outdoor feeders

05:25-05:45
Install feeders into the equipment room

05:45-06:25
Install indoor feeders and jumpers

06:25-06:40
Check the antenna system

End

2
Standard Model of Antenna System Installation

3
1 Assemble the Antenna Installers: A\B\C\D (10 minutes)

1. The antenna described in this guide is an 800 M FET antenna of Huawei.


For installation of other antennas, see the relative manuals.
2. The assembly of three antennas is complete on the ground.

a Assemble the support

Assemble the upper support Assemble the lower support

b Fix the support onto the antenna

4
2 Connect Jumpers to the Antenna
Installers: A\B\C\D (15 minutes)

a Connect jumpers

1. Use six jumpers with fixed length.


2. (Optional) If no jumper with a fixed
length is available, cut a jumper
into proper lengths and fix DIN
male connectors to both ends of
Optional the jumpers.

b Stick color rings

Ensure that the color rings are


in the correct direction and
positions. Wrap the jumpers
with 2 or 3 layers of tape to
make the color rings. The
distance between neighboring
color rings is 10 mm to 15 mm.

c Seal the connectors

Wrap three layers of Wrap three layers of Fix cable ties Finished
waterproof tape insulation tape

1. When wrapping the tape, ensure that the upper layer covers more than 50% of the lower
layer. Wrap each layer around the jumpers tightly. Before wrapping the waterproof tape,
stretch the tape till the width of the tape becomes 1/2 of the original.
2. Wrap the metal connector using waterproof tape with extended lengths about 20 mm,
and wrap the waterproof tape using insulation tape with extended lengths about 10 mm.

5
3 Lift the Antenna Installers: A\B\C\D (30 minutes)

1. Installers A and B climb onto the tower. Installer B fixes the fixed pulley onto the
support of the tower platform and puts the lifting rope through the fixed pulley.

2. Installer D uses plastic bags or tape to wrap the jumper connectors and then
coils the jumpers. Fasten the lifting rope to the upper support of the antenna
and the traction rope to the lower support.

3. Installer C pulls down the lifting rope, and installer D pulls the traction rope
outwards to prevent the antenna from hitting the tower.

4. Installers A and B hold the antenna and unfasten the ropes.

5. After three antennas are lifted onto the platform, do not remove the fixed pulley,
because the feeder needs to be lifted later.

6
4 Install the Antenna Installers: A\B (50 minutes)

a Install the antenna on a pole

Do not overtighten
the screws of the
upper and lower
supports. But the
screws can not be
too loose, or the
antenna may slide.

b Make the waterproof curve of jumpers

Bind the jumpers at several positions on the


pole and tower platform.

c Adjust the azimuth of the antenna

The operation must be


performed by two personnel.
The personnel under the
tower use the compass at
the position where is 10 m
to 20 m away from the
tower. The personnel on the
tower adjust the antenna.
After the azimuth reaches
the requirement, tighten
screws of the upper and
lower supports.

7
4 Install the Antenna Installers: A\B (50 minutes)

d Adjust the downtilt angle of the antenna


Method 1: Using the scale on the upper support

Push the antenna forward and backward till the scale is adjusted properly.
After the downtilt angle reaches the requirement, tighten screws of the scale.

Method 2: Using the inclinometer

Before adjusting the downtilt angle, adjust the angle of the inclinometer to the desired
angle. Push or pull the antenna till the bead in the inclinometer is located in the middle
horizontally. After the downtilt angle reaches the requirement, tighten screws of the scale.

Method 3: Adjust the electrical downtilt angle (only for the MET antenna)

Turn the adjustment


tool until it aligns with
the scale on the ruler.

8
5 Make Feeder Connectors Installers: C\D (50 minutes)

Measure and cut six feeders (40 m), unwind the feeders, make feeder
connectors, and stick color rings to the feeders on the ground.

a Cut feeders

Cut feeders according to the Rotate the feeder cutter till the inner and
length identifiers on the feeders. outer conductors are completely cut.

b Make feeder connectors / Stick color rings

1. Fix a DIN female


connector to one end of
the feeder.
2. Stick color rings at one
end of the feeder.
Ensure that the first color
ring is at the position 200
mm away from the
feeder connector.
3. Stick color rings at the
other end of the feeder.
Ensure that the first color
ring is at the position 200
mm away from the
feeder end.

9
6 Lift the Feeder Installers: A\B\C\D (30 minutes)

1. Installer D wraps the feeder connectors with plastic bags and tape, fasten the
lifting rope to the feeders at the position 0.4 m away from the feeder
connectors and fasten the traction rope at the position 4.4 m away from the
feeder connectors.
2. Installer C pulls down the lifting rope, and installer D pulls the traction rope
outwards to prevent the feeders from hitting the tower.
3. Installers A and B hold the feeders, unfasten the ropes, and fasten the feeders
onto the tower platform to prevent them from falling down to the ground.
4. After six feeders are lifted onto the tower one by one, installer B removes the
fixed pulley.

10
7 Connect Feeders to Jumpers of the Antenna
Installers: A\B (30 minutes)

On the tower platform, connect the feeders and jumpers with the same color
rings. Seal the connectors.

Wrap three layers of Wrap three layers of Fix the Finished


waterproof tape insulation tape cable ties

8 Fix Feeder Fasteners Installers: C\D (30 minutes)

1. The installation spacing of the


clips for the feeder (7/8 inch) is
1.5 m to 2 m. The installation
spacing of the clips for the
feeder (larger than 7/8 inch)
can be extended.
2. If multiple rows of feeder
fasteners need to be fixed,
arrange the fasteners properly
to keep a neat appearance.

Do not tighten the bolts, so that


feeders can go through the bolts.

11
9 Install and Ground Outdoor Feeders
Installers: A\B\C\D (160 minutes)

Feeders should be fixed from top to bottom. Sort out the feeders and fix them through
feeder fasteners. Install feeder grounding clips at the grounding point of the feeders
and then fix the feeders.

Stick color rings to


the feeders within
1 m from the
position where the
feeders leave the
tower.

12
9 Install and Ground Outdoor Feeders
Installers: A\B\C\D (160 minutes)

a Strip the feeders

The stripped part of the feeder should have the same length as the metal jacket of
the grounding clip.

Metal jacket of the grounding


clip of the feeder

b Install grounding clips of the feeders

Install the metal Seal the joint points Bind the grounding Fix grounding cables to
jacket (three layers of cables the grounding bar
waterproof tape +
three layers of
insulation tape)

13
10 Install Feeders into the Equipment Room
Installers: A\B\C\D (20 minutes)

Feeders should be led into the


equipment room by one person in the
equipment room and one person
outside to avoid damage to equipment.

a Lead the feeder b Make the waterproof curve

c Stick color rings d Seal the feeder window

Stick color rings to the feeders After putting all feeders through the
at the position 1 m away from feeder window, screw the fasteners
the feeder window. to seal the feeder window

14
11 Install Indoor Feeders and Jumpers
Installers: A\B\C\D (40 minutes)

a Make indoor feeder connectors

1. Cut the redundant indoor feeders and ensure that the length of each indoor feeder
is about 1 m. Remove all the color rings.
2. Fix DIN female connectors to the feeders. Stick the same color rings as the
original ones at the position 200 mm away from the feeder connectors.

b Make indoor jumper connectors

1. After length of the jumpers to be


distributed is determined, cut six
jumpers and fix DIN male connectors
to both ends of the jumpers.
2. Stick color rings corresponding to the
sectors at one end of the jumper
(connected to the feeder) at the
position 200 mm away from the
jumper connector.

c Connect feeders and jumpers d Bind the indoor jumpers

Connect the feeders to the jumpers with Route the jumpers along the indoor cable
the same color rings. rack and bind the jumpers with cable ties.

15
12 Check the Antenna System Installers: A\B\C\D (15 minutes)

After the installation is complete, check the antenna system according to the following
table. Then, correct the items that do not meet the requirements.

Item Requirement

VSWR of the Use a VSWR tester to measure the VSWR at the indoor jumper. The
antenna system VSWR should be less than 1.5 or the value required by the project.

The antenna should be installed at the position as specified by the


design and securely fixed to the pole.
The error of the antenna azimuth should not be bigger than 5o, and the
error of the tilt angle should not be bigger than 0.5o.
Antenna
In the forward direction of the antenna, the antenna is not obstructed by
the tower body.
The antenna should be in the protection range of the lightning rod
(within the tilt angle of 45o under the lightning rod).

Feeders are distributed neatly without any cross. No bare conductor


inside the feeders is exposed.

Ensure that feeders and jumpers are in good conditions.

Each feeder is connected to the jumper with the same color rings.

Color rings are sticked to the correct positions.

Proper grounding measures are taken at three positions on the outdoor


feeders.
Feeder and jumper
Ensure that the connectors of feeders and jumpers are installed
securely and correctly.

Ensure that all outdoor connectors are sealed for waterproof purpose
and that the sequence of wrapping taps is correct.

Waterproof curves are made for jumpers at the antenna side and
outdoor feeders near the feeder window.

No unnecessary adhesive tape or cable tie is left on the feeders and


jumpers.

16
Appendix 1 Stick Color Rings

1. By sticking color rings of different colors and different quantities to the feeders
and jumpers, you can distinguish sectors and RF paths.
2. Principle for color rings: Planning -> Sticking -> Checking

a Positions for color rings

Positions for color rings:


1. 200 mm away from outdoor
jumper connectors
2. 200 mm away from outdoor
feeder connectors
3. Within 1 m from the position
where the feeder leaves the
tower
4. 1 m away from the feeder
window before the feeder
enters the equipment room
5. 200 mm away from indoor
feeder connectors
6. 200 mm away from indoor
jumper connectors

b Stick color rings

Wrap the color ring tape in


the same direction and wrap
two to three layers for each
color ring. The distance
between neighboring color
rings is 10 mm to 15 mm. Finished

17
Appendix 1 Stick Color Rings
c Configuration of color rings

Typical configuration

Sector Main Diversity

1 Red, two rings Red, one ring

2 Yellow, two rings Yellow, one ring

3 Blue, two rings Blue, one ring

Other configurations

If two antennas share the same site, the configuration of the second antenna
is as follows:

Sector Main (antenna 2) Diversity (antenna 2)

1 Red, four rings Red, three rings

2 Yellow, four rings Yellow, three rings

3 Blue, four rings Blue, three rings

If multiple antenna systems share the same site, the configuration of the
second antenna system is as follows:

Sector Main (antenna system 2) Diversity (antenna system 2)

1 One white ring + two red rings One white ring + one red ring

2 One white ring + two yellow rings One white ring + one yellow ring

3 One white ring + two blue rings One white ring + one blue ring

If an antenna system has six sectors, the color rings for sectors 4, 5, and 6 are
purple, orange, and green respectively.

18
Appendix 2 DIN / N Connector
a DIN Connector

DIN straight connector (male) DIN straight connector (female) DIN angle connectors (male)

b N Connector

N angle connector (male) N straight connector (male)

c Difference between connectors


Difference between male and female connectors

Thread: Central conductor:

Internal thread (male) External thread (female) Pin conductor Socket conductor
(male) (female)

Difference between DIN and N connectors

Size: N connector are smaller


than DIN connector.
DIN connector

N connector

19
Appendix 3 Make the Jumper Connector

This appendix describes


the procedure for making
the DIN straight male
connectors of HuaXing to
jumpers. How to make
DIN straight male other connectors, see
connector relative manuals.

a Cut the jumper

Install the heat-shrinkable


b tube and O-ring seal

Finished

20
Appendix 3 Make the Jumper Connector
c Fix the rear and front sockets

d Fasten the front and


rear sockets e shrink the heat-shrinkable tube

Keep the wrench unmoved

21
Appendix 4 Make the Feeder Connector

DIN straight female connector

This appendix describes the procedure for making


the DIN straight female connectors of Andrew to
7/8" feeders. How to make other connectors, see
7/8" feeder relative manuals.

a Strip the feeder b Cut the feeder

b Cut the feeder

Rotate the feeder cutter till the inner and Cut the broken covering
outer conductors are completely cut. of the feeders.

22
Appendix 4 Make the Feeder Connector
c Fix the O-ring seal d Fix the rear socket

e Stretch the conductor of the feeder

Insert the feeder into the feeder


cutter, rotate the cutter to stretch
the outer conductor. Use a hand
to draw the rear socket, ensure
that the rear socket does not
come off from the feeder.

f Fix the front socket g Fasten the front and rear sockets

Keep the wrench unmoved

23
Appendix 5 Install Accessories on RET Antenna

The following describes how to install the RCU of Huawei and the SBT of Kathrein on
the 800 M RET antenna.

RET antenna and accessories

RET antenna (bottom) RCU SBT AISG control cable


(0.5 m)

a Install the RCU

Adjust the electrical


downtilt to 0°

b Install the SBT

24
Appendix 5 Install Accessories on RET Antenna
c Install the AISG control cable

d Seal the connectors e Install jumpers

Seal the two


connectors
shown in this
figure.

25
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Industrial Base Bantian Longgang
Shenzhen 518129
People’s Republic of China
www.huawei.com