You are on page 1of 8

ENFORCEMENT OF A DAB DECISION

THROUGH AN ICC FINAL PARTIAL AWARD

Ing. Giovanni Di Folco Mark Tiggeman How do you enforce a binding but not final “ex parte” Decision of a Dispute Adjudication
Board (“DAB”) under a FIDIC contract?
e-mail: giovanni.difolco@technoeng.ro e-mail: M.Tiggeman@Kennedys-law.com A recent Final Partial Award in an ICC arbitration has, for the first time, provided a timely
mobile: +4 0743 046 910 mobile: +44 (0)7918 131 023 answer to this difficult but important question.

SUMMARY

1. A Contractor referred various disputes arising on


a construction project to a single member DAB
pursuant to a slightly amended FIDIC 1999 Red
Book contract;

2. The Employer refused to participate in any stage


of the DAB process arguing that the DAB had
been improperly appointed and was invalid;
Giovanni Di Folco Mark Tiggeman
is the Senior Partner of is a partner of English
the international 3. The DAB rendered two decisions in favour of the international law firm

Contractor, effectively on an “ex parte” basis,


consulting firm Techno Kennedys. He has over
Engineering & 22 years experience in
Associates. He has over dealing with both liability and quantum dispute resolution,
respectively (the “DAB Decisions”);
25 years experience in 10 years of which
civil engineering, claims specialising in
and dispute resolution, contentious construction
15 years of which
specialising in 4. The Employer failed to pay a substantial sum projects. He is based in
Kennedys' London office
contentious construction awarded to the Contractor under one of the DAB and works throughout
projects worldwide.
Decisions; the world.

5. The Employer itself then referred various disputes


to arbitration and sought, inter alia, a declaration
from the arbitral tribunal that the DAB
appointment was “illegitimate and void” and that
the DAB Decisions were equally flawed;

6. The Contractor applied to the arbitral tribunal for


bifurcated proceedings to enable the legal status
of the DAB Decisions, particularly the issue of
their immediate enforceability, to be heard early in
the arbitration, effectively as preliminary issues;
and

7. The arbitral tribunal ordered bifurcated


proceedings and decided in favour of the
Contractor by granting a Final Partial Award
upholding the validity of the “ex parte” DAB and
8 ordering the Employer, among other things, to
pay the Contractor the money awarded by the
DAB.
Enforcement of a DAB decision Enforcement of a DAB decision
through an ICC final partial award through an ICC final partial award

THE FACTS Agreement had expired, a DAB could no A NOTE ABOUT THE AUTHORS Mark Tiggeman is a lawyer and partner of
longer be appointed. English international law firm Kennedys. He
A Contractor (the “Respondent” in the The authors were both acting as counsel has more than 20 years experience in
arbitration) had entered into a contract with Unhappy with this position and determined for the Contractor. international dispute resolution, with more
an Employer (the “Claimant” in the to comply with what it perceived to be a than a decade being dedicated to resolving
arbitration) for the construction of new mandatory pre-condition of the Red Book Giovanni Di Folco is the Senior Partner of disputes on construction projects. He has
infrastructure. A slightly amended version Contract, the Contractor relied upon Sub- Techno Engineering & Associates, an practiced in diverse jurisdictions
of the FIDIC 1999 Red Book form of Clause 20.3(a) thereof and applied to the international consulting firm specializing in throughout the world including countries
contract (the “Red Book Contract”) was President of FIDIC (the appointing entity claims and dispute resolution internationally. within the Asia-Pacific region, the Middle
used by the parties. The standard version under the Red Book Contract) to nominate He is a civil engineer with more than 25 East, South America and Europe.
of the Red Book’s Clause 20 was adopted a single member DAB in the face of the years experience of managing multi-
with few amendments; a single member Employer’s continuing refusal to do so. disciplinary civil engine- Mr Tiggeman is
DAB was chosen, as were the ICC Rules of The President duly proceeded to appoint. ering projects around currently based in
Arbitration. The substantive law to be the world, including Kennedys' London
applied was that of the Employer's national The Employer disputed the validity of that Italy, Iran, Libya, South office and continues to
civil law jurisdiction. appointment. It continued to refuse to sign Africa, the Kingdom of work on contentious
the DAB Agreement despite being invited Lesotho, the Sultanate cases internationally.
Disputes arose between the parties during to do so by the Contractor and of Oman, the United He is admitted as a
the course of the Works culminating in the notwithstanding the appointment of the Arab Emirates, Greece barrister and solicitor in
Employer serving a Notice of Termination single member DAB. The Employer and Romania. Australia and as a
on the Contractor for allegedly fundamental maintained that the nomination of the DAB solicitor in England & Wales. He regularly
breaches of contract. The Contractor was not in accordance with the Red Book Mr Di Folco is an expert in project and undertakes advocacy in arbitrations in
considered such Notice to be in breach of Contract because of the expiry of the 42 contract management, contract which he appears, particularly those in
the Red Book Contract and proceeded to Day Period. It said that the 42 Day Period administration, claims preparation and which he represents clients within the
refer that dispute, among others, to the was an “extinctive term” under the defence. He has gained extensive construction industry.
DAB. substantive law of the Red Book Contract experience in both international arbitration
and therefore legally incapable of being and adjudication work whilst acting as
It was not in dispute that the parties had complied with after its expiration. The counsel for a wide variety of clients. In
jointly failed to enter into a DAB Agreement Employer additionally argued that its own particular, he has represented international
within 42 days after the Commencement refusal to participate in the DAB process contractors on more than thirty international
Date for the Works (the “42 Day Period”) as was fatal to its validity. The consequence of dispute adjudication procedures and in
contractually required. What was not all of this, it argued, was that the DAB was many international arbitrations conducted
agreed between them, however, was the improperly constituted and illegitimate, under the ICC Rules relating to disputes
legal consequence of that joint failure. resulting in any decisions it rendered being under the FIDIC Red, Yellow and Silver
void. Books.
In fact, many months had passed since the
expiration of the 42 Day Period. Once The Contractor proceeded to refer various
disputes had arisen the Contractor wrote disputes to the DAB notwithstanding the
(repeatedly) to the Employer seeking a joint Employer’s objections. This effectively
appointment of a single member DAB. The resulted in the DAB proceedings being
Employer refused to do. At first it simply conducted ex parte. The DAB eventually
failed to respond and later argued that, rendered two decisions (on liability and
given that the time for entering into the DAB quantum) in favour of the Contractor. 2 7
Enforcement of a DAB decision Enforcement of a DAB decision
through an ICC final partial award through an ICC final partial award

SIGNIFICANCE OF THIS RESULT (e.g. under Article 23(1) of the current ICC THE DAB THE ARBITRATION
Rules of Arbitration) is likely to fail.
In deciding this case the arbitral tribunal has In the authors’ opinion, this useful and The DAB decided that: The Employer decided to refer its own
answered a number of potentially difficult timely case should provide some much disputes to arbitration seeking damages
and important questions arising from the needed clarity, if not certainty, regarding the 1. It had jurisdiction to hear the disputes; from the Contractor for alleged breaches of
widespread use of the Red Book form of enforceability of DAB Decisions. It is the Red Book Contract. It also impugned
contract on international construction submitted that all parties involved in 2. The Employer's Notice of Termination the validity and jurisdiction of the DAB and,
projects. international construction projects can have was invalid and unlawful; therefore, its Decisions by repeating its
greater confidence that the DAB process previous objections to the appointment of
The key consequences appear to the will lead to Decisions that will be given 3. A substantial sum was payable by the the DAB.
authors to be: “teeth” by arbitral tribunals. That is so even Employer to the Contractor as damages
when DAB proceedings are forced to be for the invalid and unlawful termination of In its Answer to the Employer’s Request for
1. Parties who include DAB provisions in a conducted on an ex parte basis due to the the Red Book Contract; and Arbitration, the Contractor restated that
contract but fail to comply with them unwillingness of a party to participate. Sub-Clause 20.3 of the Red Book Contract
should (subject to the precise wording of Defaulters beware! 4. Such damages should be paid by the ²Failure to Agree Dispute Adjudication
their contract) expect to find arbitral Employer within 28 days of the delivery Board³ clearly applied in circumstances
tribunals unsympathetic to non The authors will be pleased to answer of the second of the DAB’s Decisions. where the Employer refused jointly to agree
compliance with the DAB procedure, queries that may arise from this article to appoint the DAB and accordingly
including any failure by one of the parties whilst being both mindful and respectful of Notwithstanding that it disputed both the permitted the Contractor to proceed to do
to participate in the DAB process; the need to preserve the confidentiality of validity and jurisdiction of the DAB, the so unilaterally. It also counterclaimed
the arbitration concerned. Employer proceeded to serve Notices of substantial damages against the Employer.
2. Arbitral tribunals are likely to be Dissatisfaction against both DAB
sympathetic to applications to bifurcate Decisions, citing alleged procedural The Contractor also applied for bifurcation
proceedings to hear arguments about irregularities and also dissatisfaction with of the arbitral proceedings seeking a Partial
the enforcement of DAB Decisions as the merits of both DAB Decisions. The Award that, inter alia, the DAB was duly and
soon as possible in the arbitration; Employer's position was that the DAB properly appointed and that its Decisions
Decisions were neither final nor binding were valid, binding and enforceable against
3. Notwithstanding any Notice of and that the matters in dispute should be the Employer forthwith.
Dissatisfaction having been given by decided ab initio by an arbitral tribunal
either or both parties, DAB Decisions are which had the full power to open up, review A brief note as to procedure: a bifurcated
likely to be enforceable by partial or and revise any Decision of the DAB, process was sought by the Contractor to
interim arbitral awards being made early including the parties’ failure jointly to agree allow the arbitral tribunal to decide on the
in an arbitration, albeit usually in on the appointment of the DAB itself. enforceability of the original DAB Decisions
circumstances where they are subject to on an expedited basis. It was intended that
the power of the arbitral tribunal to open The Contractor also served a Notice of the substantive issues disputed by the
up, review and revise any Decision of a Dissatisfaction against the second of the parties, including those that had already
DAB later in the arbitration; and DAB Decisions challenging the sufficiency been decided by the DAB effectively on an
of the quantum of damages awarded. interim basis, be heard and determined in
4. An attempt by an unsuccessful party to due course by the arbitral tribunal under a
avoid compliance with a partial or interim Final Award. Whilst the Employer opposed
award enforcing a DAB Decision by that approach, the arbitral tribunal agreed
seeking an “interim measure” to suspend and ordered that a separate procedural
the effect of such partial or interim award 6 3 timetable be adopted for the early
Enforcement of a DAB decision Enforcement of a DAB decision
through an ICC final partial award through an ICC final partial award

resolution of those arguments, effectively been any awards published by the ICC THE PARTIAL AWARD reaching that view the arbitral tribunal made
as preliminary issues. Further, a Partial dealing squarely with this point. This is so it very clear that the subject matter of those
Award, rather than an Interim Award, was notwithstanding that there does seem to be In reaching its Partial Award in the present DAB Decisions is, of course, able to be
sought on the basis that the former was some significant support to be derived from case, the arbitral tribunal considered the opened up, reviewed and revised by the
considered to be more straightforward to analogous awards. priority that should be given to the arbitral tribunal later in the arbitration in
enforce before the courts of the Employer’s documents comprising the Red Book accordance with the express power to do
jurisdiction than the latter, should An example of such support is ICC Case Contract. It found that the Appendix to so granted by Sub-Clause 20.6 of the Red
enforcement become necessary. No. 10619 which dealt with the meaning of Tender took precedence over both the Book Contract. Accordingly, in that sense
the predecessor to Clause 20 of the 1999 Particular and General Conditions of the result is to be treated as interim but,
The Contractor requested the arbitral FIDIC Red Book, namely Clause 67 of the Contract. That was particularly significant nonetheless, immediately enforceable.
tribunal to find that the Employer's refusal Fourth Edition Red Book (1987). In that on the facts as the Appendix to Tender
to agree to the appointment of a DAB itself case the arbitral tribunal granted an contained the 42 Day Period and also
represented a breach of the principle of (interim) award in favour of a Claimant that provided that the President of FIDIC, or his THE “APPEAL”
good faith which applied as part of the was seeking to enforce an Engineer’s nominee, was to be the appointing entity.
applicable substantive law. It was argued decision awarding it money. The case has An interesting “twist” to this case occurred
that acting in good faith implies an been the subject of detailed commentary to The arbitral tribunal also examined the in the form of an application which was
obligation of cooperation between the the effect that1: intentions of the parties with regard to the made by the Employer to the arbitral
contracting parties, including a duty to appointment of the DAB. In particular, it tribunal, purportedly in accordance with
facilitate the performance of the Red Book …the interim award in ICC Case No. noted the numerous requests made by the Article 23(1) of the ICC Rules, to obtain an
Contract. The Contractor also argued that 10619 is directly applicable to a decision Contractor to the Employer to agree that “interim measure” suspending the effects
the effect of Sub-Clause 20.4 of the Red of a DAB under the 1999 FIDIC Books. appointment and also the fact that, at the of the Partial Award. The Employer argued
Book Contract ²Obtaining the Dispute Even if one or both parties have given a time the disputes in question arose on the that such an “interim measure” would
Adjudication Board’s Decision³ is that any notice of dissatisfaction with respect to a project (well after the expiration of the 42 preserve the “status quo” between the
Decision of the DAB is immediately binding decision of a DAB pursuant to Sub- Day period), the Engineer had himself parties as it existed before the Partial Award
upon the parties and, therefore, should be Clause 20.4, each party is bound to give agreed that a DAB should be appointed was made. The Contractor opposed the
fully complied with even if it is not final. This effect to that decision and, if that and had urged the Employer to do so. application on the basis that it was not a
was said to be derived from the relevant Decision calls for a payment to be made genuine interim measure in the sense
wording of the Sub-Clause itself, namely: by one party to the other, then that Ultimately, the arbitral tribunal decided that contemplated by Article 23(1) but, rather,
decision should be enforceable directly the appointment of the DAB was made an attempt to evade the effect of the Final
…The ²DAB³ decision shall be binding by an interim or partial award pursuant to validly and in compliance with the terms of Partial Award.
on both Parties, who shall promptly give the ICC Rules. This is the consequence, the Red Book Contract. In reaching this
effect to it unless and until it shall be the author submits, of the interim award view, the parties’ intentions in choosing to The arbitral tribunal refused to grant the
revised in an amicable settlement or an in ICC Case No. 10619” (emphasis include a DAB dispute resolution process “interim measure” primarily on the ground
arbitral award…(emphasis added) added). were key to giving “effet utile” (proper that the Employer failed to establish that the
effect) to their bargain, being an important relief sought was urgently required in order
Despite the obvious practical importance of The interim award in ICC Case No. 10619, principle enshrined in the substantive law to avoid serious and irreparable harm being
the enforceability of DAB Decisions for among other arguments, was relied upon chosen by the parties to apply to their Red caused to it.
participants in construction projects, it is by the Contractor in the present case under Book Contract.
noteworthy that there do not appear to have consideration.
The arbitral tribunal also agreed with the
Contractor’s primary argument that the
1 Vide “An Engineer’s/Dispute Adjudication Board’s Decision Is Enforceable By An Arbitral Award” by Christopher R. Seppala
DAB Decisions were enforceable directly
published by White & Case in December 2009. 4 5 and finally under a Partial Award. In
Enforcement of a DAB decision Enforcement of a DAB decision
through an ICC final partial award through an ICC final partial award

resolution of those arguments, effectively been any awards published by the ICC THE PARTIAL AWARD reaching that view the arbitral tribunal made
as preliminary issues. Further, a Partial dealing squarely with this point. This is so it very clear that the subject matter of those
Award, rather than an Interim Award, was notwithstanding that there does seem to be In reaching its Partial Award in the present DAB Decisions is, of course, able to be
sought on the basis that the former was some significant support to be derived from case, the arbitral tribunal considered the opened up, reviewed and revised by the
considered to be more straightforward to analogous awards. priority that should be given to the arbitral tribunal later in the arbitration in
enforce before the courts of the Employer’s documents comprising the Red Book accordance with the express power to do
jurisdiction than the latter, should An example of such support is ICC Case Contract. It found that the Appendix to so granted by Sub-Clause 20.6 of the Red
enforcement become necessary. No. 10619 which dealt with the meaning of Tender took precedence over both the Book Contract. Accordingly, in that sense
the predecessor to Clause 20 of the 1999 Particular and General Conditions of the result is to be treated as interim but,
The Contractor requested the arbitral FIDIC Red Book, namely Clause 67 of the Contract. That was particularly significant nonetheless, immediately enforceable.
tribunal to find that the Employer's refusal Fourth Edition Red Book (1987). In that on the facts as the Appendix to Tender
to agree to the appointment of a DAB itself case the arbitral tribunal granted an contained the 42 Day Period and also
represented a breach of the principle of (interim) award in favour of a Claimant that provided that the President of FIDIC, or his THE “APPEAL”
good faith which applied as part of the was seeking to enforce an Engineer’s nominee, was to be the appointing entity.
applicable substantive law. It was argued decision awarding it money. The case has An interesting “twist” to this case occurred
that acting in good faith implies an been the subject of detailed commentary to The arbitral tribunal also examined the in the form of an application which was
obligation of cooperation between the the effect that1: intentions of the parties with regard to the made by the Employer to the arbitral
contracting parties, including a duty to appointment of the DAB. In particular, it tribunal, purportedly in accordance with
facilitate the performance of the Red Book …the interim award in ICC Case No. noted the numerous requests made by the Article 23(1) of the ICC Rules, to obtain an
Contract. The Contractor also argued that 10619 is directly applicable to a decision Contractor to the Employer to agree that “interim measure” suspending the effects
the effect of Sub-Clause 20.4 of the Red of a DAB under the 1999 FIDIC Books. appointment and also the fact that, at the of the Partial Award. The Employer argued
Book Contract ²Obtaining the Dispute Even if one or both parties have given a time the disputes in question arose on the that such an “interim measure” would
Adjudication Board’s Decision³ is that any notice of dissatisfaction with respect to a project (well after the expiration of the 42 preserve the “status quo” between the
Decision of the DAB is immediately binding decision of a DAB pursuant to Sub- Day period), the Engineer had himself parties as it existed before the Partial Award
upon the parties and, therefore, should be Clause 20.4, each party is bound to give agreed that a DAB should be appointed was made. The Contractor opposed the
fully complied with even if it is not final. This effect to that decision and, if that and had urged the Employer to do so. application on the basis that it was not a
was said to be derived from the relevant Decision calls for a payment to be made genuine interim measure in the sense
wording of the Sub-Clause itself, namely: by one party to the other, then that Ultimately, the arbitral tribunal decided that contemplated by Article 23(1) but, rather,
decision should be enforceable directly the appointment of the DAB was made an attempt to evade the effect of the Final
…The ²DAB³ decision shall be binding by an interim or partial award pursuant to validly and in compliance with the terms of Partial Award.
on both Parties, who shall promptly give the ICC Rules. This is the consequence, the Red Book Contract. In reaching this
effect to it unless and until it shall be the author submits, of the interim award view, the parties’ intentions in choosing to The arbitral tribunal refused to grant the
revised in an amicable settlement or an in ICC Case No. 10619” (emphasis include a DAB dispute resolution process “interim measure” primarily on the ground
arbitral award…(emphasis added) added). were key to giving “effet utile” (proper that the Employer failed to establish that the
effect) to their bargain, being an important relief sought was urgently required in order
Despite the obvious practical importance of The interim award in ICC Case No. 10619, principle enshrined in the substantive law to avoid serious and irreparable harm being
the enforceability of DAB Decisions for among other arguments, was relied upon chosen by the parties to apply to their Red caused to it.
participants in construction projects, it is by the Contractor in the present case under Book Contract.
noteworthy that there do not appear to have consideration.
The arbitral tribunal also agreed with the
Contractor’s primary argument that the
1 Vide “An Engineer’s/Dispute Adjudication Board’s Decision Is Enforceable By An Arbitral Award” by Christopher R. Seppala
DAB Decisions were enforceable directly
published by White & Case in December 2009. 4 5 and finally under a Partial Award. In
Enforcement of a DAB decision Enforcement of a DAB decision
through an ICC final partial award through an ICC final partial award

SIGNIFICANCE OF THIS RESULT (e.g. under Article 23(1) of the current ICC THE DAB THE ARBITRATION
Rules of Arbitration) is likely to fail.
In deciding this case the arbitral tribunal has In the authors’ opinion, this useful and The DAB decided that: The Employer decided to refer its own
answered a number of potentially difficult timely case should provide some much disputes to arbitration seeking damages
and important questions arising from the needed clarity, if not certainty, regarding the 1. It had jurisdiction to hear the disputes; from the Contractor for alleged breaches of
widespread use of the Red Book form of enforceability of DAB Decisions. It is the Red Book Contract. It also impugned
contract on international construction submitted that all parties involved in 2. The Employer's Notice of Termination the validity and jurisdiction of the DAB and,
projects. international construction projects can have was invalid and unlawful; therefore, its Decisions by repeating its
greater confidence that the DAB process previous objections to the appointment of
The key consequences appear to the will lead to Decisions that will be given 3. A substantial sum was payable by the the DAB.
authors to be: “teeth” by arbitral tribunals. That is so even Employer to the Contractor as damages
when DAB proceedings are forced to be for the invalid and unlawful termination of In its Answer to the Employer’s Request for
1. Parties who include DAB provisions in a conducted on an ex parte basis due to the the Red Book Contract; and Arbitration, the Contractor restated that
contract but fail to comply with them unwillingness of a party to participate. Sub-Clause 20.3 of the Red Book Contract
should (subject to the precise wording of Defaulters beware! 4. Such damages should be paid by the ²Failure to Agree Dispute Adjudication
their contract) expect to find arbitral Employer within 28 days of the delivery Board³ clearly applied in circumstances
tribunals unsympathetic to non The authors will be pleased to answer of the second of the DAB’s Decisions. where the Employer refused jointly to agree
compliance with the DAB procedure, queries that may arise from this article to appoint the DAB and accordingly
including any failure by one of the parties whilst being both mindful and respectful of Notwithstanding that it disputed both the permitted the Contractor to proceed to do
to participate in the DAB process; the need to preserve the confidentiality of validity and jurisdiction of the DAB, the so unilaterally. It also counterclaimed
the arbitration concerned. Employer proceeded to serve Notices of substantial damages against the Employer.
2. Arbitral tribunals are likely to be Dissatisfaction against both DAB
sympathetic to applications to bifurcate Decisions, citing alleged procedural The Contractor also applied for bifurcation
proceedings to hear arguments about irregularities and also dissatisfaction with of the arbitral proceedings seeking a Partial
the enforcement of DAB Decisions as the merits of both DAB Decisions. The Award that, inter alia, the DAB was duly and
soon as possible in the arbitration; Employer's position was that the DAB properly appointed and that its Decisions
Decisions were neither final nor binding were valid, binding and enforceable against
3. Notwithstanding any Notice of and that the matters in dispute should be the Employer forthwith.
Dissatisfaction having been given by decided ab initio by an arbitral tribunal
either or both parties, DAB Decisions are which had the full power to open up, review A brief note as to procedure: a bifurcated
likely to be enforceable by partial or and revise any Decision of the DAB, process was sought by the Contractor to
interim arbitral awards being made early including the parties’ failure jointly to agree allow the arbitral tribunal to decide on the
in an arbitration, albeit usually in on the appointment of the DAB itself. enforceability of the original DAB Decisions
circumstances where they are subject to on an expedited basis. It was intended that
the power of the arbitral tribunal to open The Contractor also served a Notice of the substantive issues disputed by the
up, review and revise any Decision of a Dissatisfaction against the second of the parties, including those that had already
DAB later in the arbitration; and DAB Decisions challenging the sufficiency been decided by the DAB effectively on an
of the quantum of damages awarded. interim basis, be heard and determined in
4. An attempt by an unsuccessful party to due course by the arbitral tribunal under a
avoid compliance with a partial or interim Final Award. Whilst the Employer opposed
award enforcing a DAB Decision by that approach, the arbitral tribunal agreed
seeking an “interim measure” to suspend and ordered that a separate procedural
the effect of such partial or interim award 6 3 timetable be adopted for the early
Enforcement of a DAB decision Enforcement of a DAB decision
through an ICC final partial award through an ICC final partial award

THE FACTS Agreement had expired, a DAB could no A NOTE ABOUT THE AUTHORS Mark Tiggeman is a lawyer and partner of
longer be appointed. English international law firm Kennedys. He
A Contractor (the “Respondent” in the The authors were both acting as counsel has more than 20 years experience in
arbitration) had entered into a contract with Unhappy with this position and determined for the Contractor. international dispute resolution, with more
an Employer (the “Claimant” in the to comply with what it perceived to be a than a decade being dedicated to resolving
arbitration) for the construction of new mandatory pre-condition of the Red Book Giovanni Di Folco is the Senior Partner of disputes on construction projects. He has
infrastructure. A slightly amended version Contract, the Contractor relied upon Sub- Techno Engineering & Associates, an practiced in diverse jurisdictions
of the FIDIC 1999 Red Book form of Clause 20.3(a) thereof and applied to the international consulting firm specializing in throughout the world including countries
contract (the “Red Book Contract”) was President of FIDIC (the appointing entity claims and dispute resolution internationally. within the Asia-Pacific region, the Middle
used by the parties. The standard version under the Red Book Contract) to nominate He is a civil engineer with more than 25 East, South America and Europe.
of the Red Book’s Clause 20 was adopted a single member DAB in the face of the years experience of managing multi-
with few amendments; a single member Employer’s continuing refusal to do so. disciplinary civil engine- Mr Tiggeman is
DAB was chosen, as were the ICC Rules of The President duly proceeded to appoint. ering projects around currently based in
Arbitration. The substantive law to be the world, including Kennedys' London
applied was that of the Employer's national The Employer disputed the validity of that Italy, Iran, Libya, South office and continues to
civil law jurisdiction. appointment. It continued to refuse to sign Africa, the Kingdom of work on contentious
the DAB Agreement despite being invited Lesotho, the Sultanate cases internationally.
Disputes arose between the parties during to do so by the Contractor and of Oman, the United He is admitted as a
the course of the Works culminating in the notwithstanding the appointment of the Arab Emirates, Greece barrister and solicitor in
Employer serving a Notice of Termination single member DAB. The Employer and Romania. Australia and as a
on the Contractor for allegedly fundamental maintained that the nomination of the DAB solicitor in England & Wales. He regularly
breaches of contract. The Contractor was not in accordance with the Red Book Mr Di Folco is an expert in project and undertakes advocacy in arbitrations in
considered such Notice to be in breach of Contract because of the expiry of the 42 contract management, contract which he appears, particularly those in
the Red Book Contract and proceeded to Day Period. It said that the 42 Day Period administration, claims preparation and which he represents clients within the
refer that dispute, among others, to the was an “extinctive term” under the defence. He has gained extensive construction industry.
DAB. substantive law of the Red Book Contract experience in both international arbitration
and therefore legally incapable of being and adjudication work whilst acting as
It was not in dispute that the parties had complied with after its expiration. The counsel for a wide variety of clients. In
jointly failed to enter into a DAB Agreement Employer additionally argued that its own particular, he has represented international
within 42 days after the Commencement refusal to participate in the DAB process contractors on more than thirty international
Date for the Works (the “42 Day Period”) as was fatal to its validity. The consequence of dispute adjudication procedures and in
contractually required. What was not all of this, it argued, was that the DAB was many international arbitrations conducted
agreed between them, however, was the improperly constituted and illegitimate, under the ICC Rules relating to disputes
legal consequence of that joint failure. resulting in any decisions it rendered being under the FIDIC Red, Yellow and Silver
void. Books.
In fact, many months had passed since the
expiration of the 42 Day Period. Once The Contractor proceeded to refer various
disputes had arisen the Contractor wrote disputes to the DAB notwithstanding the
(repeatedly) to the Employer seeking a joint Employer’s objections. This effectively
appointment of a single member DAB. The resulted in the DAB proceedings being
Employer refused to do. At first it simply conducted ex parte. The DAB eventually
failed to respond and later argued that, rendered two decisions (on liability and
given that the time for entering into the DAB quantum) in favour of the Contractor. 2 7
ENFORCEMENT OF A DAB DECISION
THROUGH AN ICC FINAL PARTIAL AWARD

Ing. Giovanni Di Folco Mark Tiggeman How do you enforce a binding but not final “ex parte” Decision of a Dispute Adjudication
Board (“DAB”) under a FIDIC contract?
e-mail: giovanni.difolco@technoeng.ro e-mail: M.Tiggeman@Kennedys-law.com A recent Final Partial Award in an ICC arbitration has, for the first time, provided a timely
mobile: +4 0743 046 910 mobile: +44 (0)7918 131 023 answer to this difficult but important question.

SUMMARY

1. A Contractor referred various disputes arising on


a construction project to a single member DAB
pursuant to a slightly amended FIDIC 1999 Red
Book contract;

2. The Employer refused to participate in any stage


of the DAB process arguing that the DAB had
been improperly appointed and was invalid;
Giovanni Di Folco Mark Tiggeman
is the Senior Partner of is a partner of English
the international 3. The DAB rendered two decisions in favour of the international law firm

Contractor, effectively on an “ex parte” basis,


consulting firm Techno Kennedys. He has over
Engineering & 22 years experience in
Associates. He has over dealing with both liability and quantum dispute resolution,
respectively (the “DAB Decisions”);
25 years experience in 10 years of which
civil engineering, claims specialising in
and dispute resolution, contentious construction
15 years of which
specialising in 4. The Employer failed to pay a substantial sum projects. He is based in
Kennedys' London office
contentious construction awarded to the Contractor under one of the DAB and works throughout
projects worldwide.
Decisions; the world.

5. The Employer itself then referred various disputes


to arbitration and sought, inter alia, a declaration
from the arbitral tribunal that the DAB
appointment was “illegitimate and void” and that
the DAB Decisions were equally flawed;

6. The Contractor applied to the arbitral tribunal for


bifurcated proceedings to enable the legal status
of the DAB Decisions, particularly the issue of
their immediate enforceability, to be heard early in
the arbitration, effectively as preliminary issues;
and

7. The arbitral tribunal ordered bifurcated


proceedings and decided in favour of the
Contractor by granting a Final Partial Award
upholding the validity of the “ex parte” DAB and
8 ordering the Employer, among other things, to
pay the Contractor the money awarded by the
DAB.

You might also like