e Removal of Avtur pump motor AD-P- other Elements, Index 5311 for 6th annual overhaul Evidence Performan Number ce Statement s Covered 20/1/1 A2.1-a The following statement provides E3.3 1 evidence of my competence to: E3.7 1. Diagnose and determine the E3.13 cause of faults in electrical plant and equipment E3.3 2. Remove components from electrical plant and equipment E3.7 3. Establish that an electrical engineering process has been completed to specification E3.13.
This task required the mechanical
technicians to remove the coupling and holding down bolts and me to disconnect and remove the cabling from the motor followed by testing to the circuit cabling using non I.S. instruments.
Prior to commencing work I surveyed
the work site to ensure no other jobs were taking place. I also checked that pump 5310 was available before commencing work; this was to ensure that the disconnection of pump 5311 would not interfere with usual operations. When looking at E3.3-b previous notes from this motor I E3.13-b found that it had been pulling a larger current than specified by the manufacturer and it was not overloaded. A2.1-b E3.3-a Lead technician John Geddes and I permit E3.7-a looked over the permit during a A2.1-c toolbox talk led by myself. This toolbox talk E3.13-a included a risk assessment A2.1-d risk highlighting that the specific job was a assesment cat C meaning the PA sets the work Personal Statement A2.1-a
scenario and us then free to leave the
technician to continue alone. For this specific job the access was awkward due to the pump being in a skid, this was highlighted in the risk assessment and it was noted that great care must be taken when at the worksite due to fixed pipe work and equipment and the restricted pace in and around the skid. We both then agreed all measures were in place and signed onto the permit.
The permit for this job was hot work
Cat 2 meaning spark potential in this case caused by the use of an I.R. tester. This requires a copy of the permit to be placed in the control room for the duration of the work to provide a visual check to the operators of any hot work taking place, it is also used in a GA as the PA’s are required to collect the copies informing the operators which areas have been made safe. Before work commences we had to ensure a gas test had been performed to check the area was safe for spark potential work. Finally a gas detector is to be at the worksite at all times to give sufficient warning of a gas threat.
When returning to the worksite the
gas detector was going off, we immediately checked and it was found to only be a low battery warning. I replaced the gas tester.
Before heading to the worksite I
collected an insulation resistance tester, low ohm resistance meter and a gas detector from the PCF. I visually inspected the equipment and checked their calibration certificates before signing for them and taking them to the worksite. RPE Russell Savage confirmed the calibration of the gas detector so we knew it was in Personal Statement A2.1-a
working order and ready for use. The
IR tester and LOR meter were both intrinsically safe units. This is required to ensure no spark is produced from the unit and also stops hazardous gases from getting into it.
When at the worksite I positioned the
gas tester close to the working area up wind as this is the optimum position for its correct operation. I had also ensured all required tools were present in my kit before commencing saving time and lessening the chance that I would have to leave the worksite before job completion.
John Geddes and I viewed the
isolation at the distribution board ensuring the supply had been cut off and then confirmed the motor had been isolated from the pump.
Now the job was ready to start we
confirmed with the PA and signed on the permit.
I began by removing the securing
screws from the motors wiring E3.7-e terminal, as the motor was old and had been subjected to the elements some of the screws had suffered corrosion, I showed caution when loosening them as to prevent them shearing, the final screw was tight and at risk of shearing so it was left E3.7-b and the cover was pivoted out of the A2.1-e way allowing access to the terminals. diagram
Before removing the connections I
made a diagram so it could be E3.7-c reconnected correctly when the motor is due to be re-installed. I also noted that the motor was configured in delta for future reference. I then proceeded to prove the cores not live and E3.7-d discharged using a Martindale tester E3.13-c and proving unit. Once the terminal connections had been removed I was Personal Statement A2.1-a
able to loosen of the gland using the
correct sized gland spanners that had been inspected and proven in good condition and remove it, I tightened the gland body back round E3.7-f the cable as to not lose it. I noticed at this point that the gas seal on the gland was damaged and so I recorded this so it could be replaced. All phases were terminated down to earth, this is for safety reasons; if for whatever reasons the isolation fails the residual current will be taken down to earth and the system will fail safe, the circuit protective device will activate. Also in the case where cables are ran together a dead cable may have a current induced in it from other live feeds in close proximity. The remaining loose cable was looped into a bag for protection and to E3.7-h prevent a tripping hazard. I then placed a notification tag around the cable so it could be easily identified.
The damaged gland was removed
and discarded in the WEEE container as per government E3.13-d legislation and company policy. E3.3-c E3.3-d Now all cables and connections had been removed and made safe I was able to begin the tests in order as per work order on the motor. I began with the IR test of the motor; this involved connecting a probe to a terminal and one to earth, also testing between phases to ensure there is no breakdown of insulation. The tester was set to five hundred volts as a three phase motor runs at four hundred and fifteen volts this is the closest available setting. The tester runs a voltage through the probes and into the terminal and down to earth this provides an indication of the resistance of the insulation as the E3.3-e voltage cannot create a circuit in E3.3-g Personal Statement A2.1-a
normal operating circumstances. E3.3-f
Acceptable reading is above 2 mega E3.13-e ohms, the actual reading produced was below this showing a breakdown in the insulation on the windings. For this reason the motor was to be removed and shipped onshore for an overhaul. The continuity test involved me testing between the terminals across windings. A reading of around three point five ohms is acceptable as specified in the manufacturer’s book. This test proved as should be. All work required from the electrical department had now been completed so I cleared all tools and equipment away leaving the worksite tidy and E3.7-g hazard free. A notification was passed on to the mechanical team and rigging teak to inform them all isolations and disconnections had E3.3-h been completed and removal of the E3.7-i motor could now commence. The E3.13-f removed motor was labelled and stored in a container ready for shipping.
All readings taken from the tests were
recorded on the work order card; we also noted the connection diagram and removal of the damaged gland here. This form is then logged for history.