Professional Documents
Culture Documents
? Short Questions
1: A company has planned to produce 5,200 units of Product X next month and has allowed a total
standard time for this level of production of 325 hours. The actual output for the month was 5,616
units, which was actually achieved in 357 hours.
What was the efficiency ratio (to the nearest two places of decimals)?
2: A company has calculated that its activity (volume) ratio is 99% and that its efficiency ratio is 110%.
What was the capacity ratio (to the nearest whole number)?
3: The activity (volume) ratio for a given month was 110% and the efficiency ratio was 99%.
What was the capacity ratio (to the nearest whole number) for the same month?
5 Sales Variances
Example:
You are the accountant of company which sells three products. The sales budget for June was:
Product A B C
Budget sales (units) 300 200 150
Actual sales (units) 360 230 100
Standard cost per unit $28 $37 $81
Standard variable cost per unit $16 $22 $66
Standard selling price per unit $40 $60 $100
Actual selling price per unit $38 $65 $120
-1-
CAT T7 Planning, Control and Performance Management
Illustration 8:
A company is reviewing actual performance to budget to see where there are differences. The following
standard information is relevant:
$ per unit
Selling price 50
Prime Costs 20
Variable production overheads 11
Fixed production overheads 5
Fixed selling costs 1
Budgeted sales units were 3,000. Actual units sold in the period were 3,500 at a price of $46 per unit.
What was the sales volume variance and sales price variance using marginal costing?
Sales variances
AO x SC 3,500 x 15 = 52,500
~ BO x SC ~ 3,000 x 19 = 57,000
= 4,500 (A)
-2-
CAT T7 Planning, Control and Performance Management
Illustration 11:
(a) Calculate price and usage variances for each of the direct materials A and B.
(b) Calculate rate and efficiency variances for the direct labour employed by each of
Departments 1 and 2.
Department 1 Department 2
(i) Production volume ratio
Standard hour for AO 8 x 400 5 x 400
x 100 x 100
Budgeted hour 3,400 2,600
= 94.12% = 76.92%
Department 1 Department 2
(ii) Efficiency ratio
Standard hour for AO 8 x 400 5 x 400
x 100 x 100
Actual hour 3,000 2,400
= 106.67% = 83.33%
-3-
CAT T7 Planning, Control and Performance Management
Q2:
(a) Calculate the standard cost of a single metal container.
Material A (6 x 5.00) 30.00
Labour (2 x 4.50) 9.00
Variable overheads (2 x 7.50) 15.00
Fixed overheads (2 x 12.00) 24.00
78.00
-4-
CAT T7 Planning, Control and Performance Management
Q3:
(b) For the most recent production period calculate the following variances:
(i) Material price variance
(ii) Material usage variance
(iii) Labour rate variance
(iv) Labour efficiency (or utilisation) variance
(c) For the most recent production period calculate the following variances:
(i) Total variable overhead variance
(ii) Total fixed overhead variance
-5-
CAT T7 Planning, Control and Performance Management
(d) Give two possible reasons for each of the 4 variances calculated in Part (b) above. You
should ensure that the reasons given relate to the fact that the variances calculated in Part
(b) were favourable or adverse.
(refer notes)
(e) Explain the difference between an ‘ideal standard’ and an ‘attainable standard’.
Ideal standard is a based on a budget prepared for a work condition without losses, wastages. The
standards set will be too difficult to be achieved.
Attainable standard is based on a budget prepared with allowance for unavoidable losses and
wastages. The standard set will be achievable, though would be a challenging task.
Ideal standard is to be used for developmental purpose. Ideal standard will be compared to current
standard to determine areas/ room for improvement for future standards.
Attainable standard is used for day-to-day operations. The attainable standard will be compared to the
actual results to determine areas/ room for improvement in terms of future actions/ standards.
For the most recent accounting period the following information has been extracted from the accounting
records of the company:
-6-
CAT T7 Planning, Control and Performance Management
(b) Briefly identify any relationship between the variances that may be revealed by:
(i) the material price and material usage variances calculated in your answer to part (a).
(ii) the labour rate and labour efficiency variances calculated in your answer to part (a).
(i) Material price variance = $950 (A), material usage variance = $1,250 (F)
Better quality materials were bought which resulted in adverse material price variance. Total
material wastage was less than expected when better quality materials were used.
Besides that, adverse material price variance could be due to a different grade of material
purchased. Change of material grade could have affected the quantities used.
(i) Labour rate variance = $850 (A), labour efficiency variance = $450 (F)
Well trained labour have been hired, and thus, higher wages paid. As they are well trained, the
total hours taken to complete the production would be lower.
-7-
CAT T7 Planning, Control and Performance Management
The activity ratio measures the standard hours of work, by professional staff on client business, as a
proportion of the total hours worked by the professional staff. The efficiency ratio measures the relationship
between the standard and the actual professional staff hours spent on client business. The capacity ratio
measures the actual professional staff hours spent on client business as a proportion of their total hours
worked.
During a period, the actual hours worked by professional staff totalled 3,630 of which 3,471 hours were
spent on client business. The standard hours for the work totalled 3,502.
(a) Calculate appropriate control ratios for the period (each to one decimal place of a per cent).
Activity ratio
Standard hours of work = 3,502
x 100 x 100 = 96.47%
Actual hours worked 3,630
Efficiency ratio
Standard hours of work = 3,502
x 100 x 100 = 100.89%
Actual hours on client business 3,471
Q6:
Variable overhead expenditure variance
AVOH = 24,250
~ VOAR x AO ~ 17,500/ 60 x 75 = 21,875
= 2,375 (A)
Or
Variable overhead expenditure variance
AVOH = 24,250
~ VOAR x Ahr ~ 17,500/ 6,000 x 7,150 = 20,854
= 3,396 (A)
-8-
CAT T7 Planning, Control and Performance Management
Q7:
Direct materials price variance
AP x AQ = 8,450
~ SP x AQ ~ 21 x 420 = 8,820
= (370)
-9-
CAT T7 Planning, Control and Performance Management
Q8:
Riki Ltd produces and sells one product only. The standard cost and price for one unit being as follows:
$
Direct material A 10 kg @ $12 per kg 120
Direct material B 6 kg @ $5 per kg 30
Direct wages 5 hours @ $8 per hour 40
Fixed production overhead 5 hours @ $12 per hour 60
Total standard cost 250
Standard gross profit 50
Standard selling price 300
The fixed production overhead included in the standard cost is based on an expected monthly output of 750
units. Riki Ltd uses an absorption costing system based on direct labour hours.
Operating statement
Budgeted Profit (50 x 750) 37,500
Sales margin volume variance (700 – 750) 50 2,500 A
Standard Profit for AO 35,000
Adjustments:
Sales price variance (320 – 300) 700 14,000 F
Material price variance :A (91,500 – (12 x 7,500) 1,500 A
:B (20,300 – (5 x 3,500) 2,800 A
Material usage variance :A (7,500 – (10 x 700)) 12 6,000 A
:B (3,500 – (6 x 700)) 5 3,500 F
Labour rate variance (27,880 – 8 x 3,400) 680 A
Labour efficiency variance (3,400 – 5 x 700) 8 800 F
FOH expenditure variance (37,000 – 45,000) 8,000 F
FOH efficiency variance (3,400 – 5 x 700) 12 1,200 F
FOH capacity variance (3,400 – 3,750) 12 4,200 A
Net variances 12,320 F
-10-
CAT T7 Planning, Control and Performance Management
Q9:
Operating statement
Budgeted Profit (1,660 x 40) 66,400
Sales margin volume variance (1,350 – 1,660) 40 12,400 A
Standard Profit for AO (1,350 x 40) 54,000
Adjustments:
Sales price variance 391,500 – 273 x 1,350 22,950 F
Material price variance 90,625 – 7 x 12,500 3,125 A
Material usage variance (12,500 – 10 x 1,350) 7 7,000 F
Labour rate variance 98,600 – 12 x 8,500 3,400 F
Labour efficiency variance (8,500 – 6.5 x 1,350) 12 3,300 F
VOH expenditure variance 90,000 – 65 x 1,350 2,250 A
FOH expenditure variance 28,000 – 20 x 1,660 5,200 F
FOH volume variance (1,350 – 1,660) 20 6,200 A
Net variances 30,275 F
Q10:
Operating statement
Budgeted Profit (10,000 x 8) 80,000
Sales margin volume variance (9,500 – 10,000) 8 4,000 A
Standard Profit for AO (9,500 x 8) 76,000
Adjustments:
Sales price variance 588,500 – 60 x 9,500 18,500 F
Material price variance 120,000 – 3 x 37,000 9,000 A
Material usage variance (37,000 – 4 x 9,500) 3 3,000 F
Labour rate variance 200,000 – 4 x 49,000 4,000 A
Labour efficiency variance (49,000 – 5 x 9,500) 4 6,000 A
VOH expenditure variance 47,000 – 5 x 9,500 500 F
FOH expenditure variance 145,000 – 3 x 5 x 10,000 5,000 F
FOH efficiency variance (49,000 – 5 x 9,500) 3 4,500 A
FOH capacity variance (49,000 – 50,000) 3 3,000 A
Net variances 500 F
-11-