Professional Documents
Culture Documents
CHAPTER 6
6-1
TM 5-811-6
considerable control. Increases in the inlet air fric- sembled into three or more skid mounted modules,
tion cause a significant reduction in power output. each with its own weatherproof housing the sepa-
The total inlet pressure loss will not exceed 2 inches rate modules have wiring splits, piping connections,
of water and will be as close to zero as space limita- and housing flanges arranged so that the modules
tions and economics will permit. Additional duct- may be quickly assembled into a unit on a reinforced
work costs will be quickly amortized by operating concrete pad in the field. Supplementing these main
fuel savings. Dust, rain, sand and snow will be pre- modules are the inlet and exhaust ducts, inlet si-
vented from entering the combustion air inlet of the lencer and filters, exhaust silencer, fuel tanks, unit
engine. Inlet air filter design will preclude entrance fuel skid, and unit auxiliary transformer which are
of these contaminants with minimal pressure loss. connected by piping and cables to the main as-
The air inlet will be located to preclude ingestion of sembly after placing on separate foundation as
combustion products from other turbines or a near- may be required.
by boiler plant, or hot, humid discharge from any (b) The other outdoor sub-type is a similar
cooling towers. package unit except that the weatherproof housing
e. Outlet losses. Outlet friction losses also result is shipped knocked down and is, in effect, a prefabri-
in a decrease of turbine-generator output and will be cated building for quick field assembly into a clo-
accounted for in the unit design. The major factor in sure for the main power plant components.
outlet losses is the requirement to attenuate noise. (c) Outdoor units to be provided with all com-
More effective silencers typically have higher pres- ponents, auxiliaries and controls assembled in all-
sure losses. Exhaust back pressure has a smaller weather metal enclosures and furnished complete
overall effect on performance than inlet losses but for operation will be specified for Class “B” and “C”
will be kept as low as possible, and will be less than power plants having a 5-year anticipated life and re-
6 inches of water. Since increasing exhaust silencer quiring not more than four generating units.
size costs considerably more than ductwork design (2) Indoor. An indoor type unit will have the
improvements, the return on investment for a low compressor-turbine-generator mounted at grade
pressure loss exhaust is significantly longer. floor level of the building on a pad, or possibly
raised above or lowered below grade floor level to
6-3. Fuels provide space for installation of ducts, piping and
Each manufacturer has his own specification on fuel cabling. Inlet and exhaust ducts will be routed to
acceptable for his turbine. The high grade liquid the outside through the side wall or the roof; the side
fuels such as Diesel No. 1 or 2 and JP-4 or JP-5 will wall is usually preferable for this so that the turbine
likely be acceptable to all manufacturers. Use of room crane can have full longitudinal travel in the
heavier oils is possible with a specially designed tur- turbine generator bay. Filters and silencers may be
bine. The heavy oil will have to be cleaned up to re- inside or outside. All heat rejection equipment will
duce corrosive salts of sodium, potassium, vana- be mounted outside while fuel oil skids may be in-
dium, and sulfur–all of which will elevate the cost side or outside. Unit and distribution switchgear
of the fuel. Storage and handling at the site will also and motor control centers will be indoors as in a con-
be more costly, particularly if a heavy oil such as ventional steam power plant. Figure 6-1 shows a
No. 6 was involved because of the heating require- typical indoor unit installation with the prime mov-
ment. No. 4 oil will increase transfer pumping costs er mounted below grade floor level.
a bit but, except in extremely cold regions, would
not require heating. 6-5. Waste heat recovery
Waste heat recovery will be used wherever cost ef-
6-4. Plant arrangement fective. If the turbine unit is to be used only inter-
a. General. Turbine generator units are frequent- mittently, the capital cost of heat recovery must be
ly sold as complete packages which include all com- kept down in order to be considered at all. Add-on or
ponents necessary to operate, ready for connection sidestream coils might provide a temporary hot
to the fuel supply and electrical distribution system. water supply for the period of operation—for one ex-
This presents the advantages of faster lead time, ample. Care must be exercised due to the high ex-
well matched components and single point of perfor- haust gas temperature. It may prove feasible to
mance responsibility y. flash steam through the jacket of a small heat ex-
b. Outdoor vs. indoor. changer. In the event that a long term operation is
(1) Outdoor. Outdoor units can be divided into indicated, the cost trade off for heat recovery equip
two sub-types. ment is enchanced, but still must be considered as
(a) The package power plant unit is supplied an auxiliary system. It will take a sizable yearly
with the principal components of the unit factory as- load to justify an exhaust gas heat recovery boiler.
6-2
, TM 5-811-6
L.
r AIR INTAKE WET CELL
WASHER OR FILTER I
Rs
1
T I
2s’-0’
T
w w
A
. I
STACK
ExHAuST
\ A
. I Q
~ n 1
,1
n Ii
,
L 1 r
l?$dLEJ%/ &~a\
,! I
‘ :. l-w
;r .-. . ,.
.
... .
“’-’”A’&?yBAsEMENTk~;fl
lNTi4KE
. . . . .
FLOOR
,------
.7. -...
, NAVFAC DM3
Turbine efficiency loss due to back pressure is also a gas turbine power plant, including the generator,
factor to be considered. switchgear, switchyard, transformers, relays and
controls. Chapter 2 describes the pertinent civil fa-
6-6. Equipment and auxiliary systems cilities.
a. GeneraL The gas turbine package is a complete c. Scope. The scope of a package gas turbine gen-
power plant requiring only adequate site prepara- erator for purchase from the manufacturer will in-
tion, foundations, and support facilities including clude the following
fuel storage and forwarding system, distribution (1) Compressor and turbine with fuel and com-
switchgear, stepup transformer, and switchyard. If
bustion system, lube oil system, turning gear, gov-
the fuel to be fired is a residual oil, a fuel washing
ernor, and other auxiliaries and accessories.
and treating plant is also required.
‘L b. References. Chapter 4 sets forth guidelines for (2) Reduction gear.
the design of the electrical facilities required for a (3) Generator and excitation system.
6-3
TM 5-811-6
(4) AC auxiliary power system including (9) Unit fuel skid (may be purchased separately
switchgear and motor controls. if desired).
(5) DC power system including battery, charg- (10) Intake and exhaust ducts.
er, and inverter if required. (11) Intake air filters.
(6) External heat rejection equipment if re- (12) Acoustical treatment for intake and ex-
quired. haust ducts and for machinery.
(7) All mechanical and electrical controls. (13) Weatherproof housing option with appro-
(8) Diesel engine or electric motor starting sys- priate lighting, heating, ventilating, air condition-
tem. ing and fire protection systems.
6-4