You are on page 1of 43

VECO Doc. No.

20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 2 of 30

TABLE OF CONTENTS

1.0 GENERAL......................................................................................................................... 5

1.1 Introduction ....................................................................................................................... 5

1.2 Purpose............................................................................................................................. 5

1.3 Definitions ......................................................................................................................... 5

2.0 INTERNATIONAL CODES AND STANDARDS............................................................... 6

3.0 REFERENCE DOCUMENTS ............................................................................................ 7

4.0 DOCUMENT PRECEDENCE ........................................................................................... 8

5.0 SPECIFICATION DEVIATION / CONCESSION CONTROL ............................................ 8

6.0 QUALITY ASSURANCE / QUALITY CONTROL ............................................................. 8

7.0 DESIGN CONSIDERATIONS ........................................................................................... 9

8.0 DOCUMENTATION - GENERAL ..................................................................................... 9

9.0 SCOPE OF EXECUTION................................................................................................ 10

9.1 Responsibilities of Contractor ......................................................................................... 10

10.0 DESIGN BASIS .............................................................................................................. 11

10.1 General Basis.................................................................................................................. 11

10.2 Current Requirements..................................................................................................... 12

10.3 Performance Criteria ....................................................................................................... 13

11.0 EQUIPMENT AND MATERIALS .................................................................................... 14

11.1 Schedule of Equipment and Materials ............................................................................ 14

11.2 Impressed Current Anodes ............................................................................................. 16

11.3 Sacrificial Anodes............................................................................................................ 16

11.4 Backfill Materials for Pre-Packaged Artificial Anodes...................................................... 17

11.5 Backfill Materials for Impressed Current Beds in Soil ..................................................... 17

11.6 Cables ............................................................................................................................. 17


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 3 of 30

11.7 Solar Array Panels and Storage Batteries ...................................................................... 18

11.8 Terminal Boxes ............................................................................................................... 18

11.9 Test Posts ....................................................................................................................... 19

12.0 SYSTEMS ENGINEERING AND INSTALLATIONS ...................................................... 20

12.1 Qualification of Design Personnel ................................................................................... 20

12.2 Schedule of Cathodic Protection System ........................................................................ 20

12.3 Sacrificial Anode Beds .................................................................................................... 20

12.4 Impressed Current Anode Beds ...................................................................................... 20

12.5 Connection of Cables...................................................................................................... 21

12.6 Electrical Earthing ........................................................................................................... 23

12.7 Electrical Continuity......................................................................................................... 23

12.8 Electrical Isolation ........................................................................................................... 24

12.9 Stray Currents ................................................................................................................. 24

12.10 Installation of Test Stations ............................................................................................. 24

12.11 Remote Monitoring and System Control ......................................................................... 25

13.0 SPECIAL FACILITIES .................................................................................................... 25

13.1 Temporary CP Systems .................................................................................................. 25

13.2 Designs Near High Voltage Power Lines ........................................................................ 26

13.3 Designs in Areas of Lightning Activity ............................................................................. 26

14.0 DOCUMENTATION REQUIREMENTS .......................................................................... 26

14.1 Design Documents.......................................................................................................... 27

14.2 Material Schedules.......................................................................................................... 27

14.3 Installation Procedures.................................................................................................... 28

14.4 Pre-Commissioning Testing and Inspection.................................................................... 28

14.5 Commissioning Procedures ............................................................................................ 28


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 4 of 30

14.6 Cathodic Protection Manual ............................................................................................ 29

14.7 Training ........................................................................................................................... 30

15.0 SAFETY .......................................................................................................................... 30

ATTACHMENT

ATTACHMENT – 1 DESIGN SPECIFICATIONS FOR CPS REMOTE MONITORING


FACILITY

ATTACHMENT - 2 Soil Resistivity - (extract from GEO SCIENCE


ASSOCIATES’s SOIL THERMAL
CONDUCTIVITY/RESISTIVITY SURVEY REPORT)
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 5 of 30

1.0 GENERAL

1.1 Introduction

This specification defines the minimum requirements for the design, procurement,
delivery, testing and commissioning of the cathodic protection system for all buried
flowlines and trunkline pipings at site ME01, ME02, ME03 and Manifold – North of the
Mehar Wellhead Facilities and Gathering Network Project in Pakistan.

1.2 Purpose

This specification supplements the international codes and standards listed in Section
2.0 of this document.

1.3 Definitions

For the purposes of this document, the following definitions shall apply:

COMPANY Petronas Carigali Pakistan LTD. (PCPL) or


any third party assigned by COMPANY.

CONCESSION REQUEST A deviation requested by the


SUBCONTRACTOR or VENDOR, usually
after receiving the contract package or
purchase order. Often, it refers to an
authorization to use, repair, recondition,
reclaim, or release materials, components
or equipment already in progress or
completely manufactured but which does
not meet or comply with COMPANY
requirements. A CONCESSION
REQUEST is subject to COMPANY
approval.

ENGINEER Party which carries out all or part of the


design, engineering of the PROJECT.
Veco Engineering, Abu Dhabi is the
ENGINEER.

PCC CONTRACTOR Party which carries out all or part of the


design, engineering, procurement,
construction, commissioning or
management of the PROJECT. PCC
CONTRACTOR includes his approved
MANUFACTURERS, SUPPLIERS,
VENDORS, and SUBCONTRACTORS.
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 6 of 30

MANUFACTURER/SUPPLIER/VENDOR Party/ies, which manufactures and/or


supplies material, equipment and services
to perform the duties as specified by
CONTRACTOR in the scope of supply.

PROJECT MEHAR WELLHEAD FACILITIES AND


GATHERING NETWORK.

SUBCONTRACTOR/SUBVENDOR The party(s) which carry(s) out all or part of


the design, procurement, installation and
testing & commissioning of the CP
System(s) as specified by the
CONTRACTOR/VENDOR.

SHALL Indicates a mandatory requirement

SHOULD Indicates a strong recommendation to


comply with the requirements of this
document.

A well experienced NACE certified CP


CP SPECIALIST SPECIALIST. His duties are the
supervision of the preparation of detailed
design for MEHAR WELLHEAD
FACILITIES AND GATHERING
NETWORK’s cathodic protection system.

This person shall have minimum five (5)


years practical experience in similar works
and will be subject to approval by the
CONTRACTOR/COMPANY.

2.0 INTERNATIONAL CODES AND STANDARDS

The latest edition of the following international codes and standards shall establish the
minimum standards for the work. SUBCONTRACTOR may use alternate standards that
meet or exceed those listed if approved by COMPANY.

American Society for Testing and Materials (ASTM)

ASTM G57 Field Measurement of Soil Resistivity Using the Winner Four-
Electrode Method

ASTM B418 Cast and Wrought Galvanic Zinc Anodes


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 7 of 30

International Electro-technical Commission (IEC)

IEC 449947 PT-2 Semiconductor Converters

IEC 269 (1994) Low Voltage Fuses

IEC 529 Degrees of Protection Provided by Enclosures (IP Code)

IEC 296 Insulation Oils for Transformers and Switchgears

International Standards Organization (ISO)

ISO 8501-1 (Part 1) Preparation Of Steel Substrate Before Application Of Paints And
Related Products-Visual Assessment Of Surface Cleanliness

ISO 9001 Quality Systems- Model for Quality Assurance in


Design/Development, Production, Installation and Servicing

ISO 9003 Quality Systems - Model for Quality Assurance in Final Inspection
and Test

ISO 9004 Quality Management and Quality System Elements Guidelines

British Standard (BS)


BS 7361 Cathodic Protection - Part 1, Code of Practice for Land and
Marine Applications

National Association of Corrosion Engineers (NACE)

NACE RP0169 (1995) Control of External Corrosion on Underground or Submerged


Metallic Piping Systems.

NACE RP0177 Mitigation of Alternating Current and Lightning Effects on Metallic


Structures and Corrosion Control Systems

NACE RP0286 The Electrical Isolation of Cathodically Protected Pipelines.

NACE RP0572 Design, Installation, Operation, and Maintenance of Impressed


Current Deep Ground Beds.

National Electrical Code


NEC NFPA-70
(ANSI-C1 ) National Electrical Code

3.0 REFERENCE DOCUMENTS

The following documents are part of this specification:

A.) Flow Line Alignment Sheet - (Dwg.No. 12-MEPL-P-5010, Sht.1, rev. A)


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 8 of 30

B.) Flow Line Alignment Sheet - (Dwg.No. 12-MEPL-P-5020, Sht.1, rev. A)


C.) Flow Line Alignment Sheet - (Dwg.No. 12-MEPL-P-5030, Sht.1, rev. A) HOLD
D.) Pipeline Alignment Sheet - (Dwg.No. 12-MEPL-P-5040, Sht.1, rev. A)
E.) Pipeline Alignment Sheet - (Dwg.No. 12-MEPL-P-5041, Sht.1, rev. A)
F.) Pipeline Alignment Sheet - (Dwg.No. 12-MEPL-P-5042, Sht.1, rev. A)
G.) Soil Resistivity - MEHAR (extract from GEO SCIENCE ASSOCIATES’s
Soil Thermal Conductivity/Resistivity Survey Report)

4.0 DOCUMENT PRECEDENCE

The CONTRACTOR/SUBCONTRACTOR shall notify the COMPANY of any conflict


between this specification, the related data sheets, the International Codes and
Standards and any other specifications noted herein. Resolution and/or interpretation
precedence shall be obtained from the COMPANY in writing before proceeding with the
design or manufacture.

In case of conflict, the order of precedence shall be:

• Material Requisition and Data Sheets(s);

• Equipment Specification;

• Industry Codes and Standards.

5.0 SPECIFICATION DEVIATION / CONCESSION CONTROL

Any technical deviations to the Specification and it’s attachments including, but not
limited to, the Data Sheets and Narrative Specifications shall be obtained by the
CONTRACTOR/SUBCONTRACTOR only through CONCESSION REQUEST format.
CONCESSION REQUESTS require COMPANY's review/approval prior to
implementation of the proposed changes. Technical changes implemented prior to
COMPANY approval are subject to rejection.

6.0 QUALITY ASSURANCE / QUALITY CONTROL

A copy of the CONTRACTOR/SUBCONTRCATOR's QA/QC program shall be submitted


to the COMPANY with its quotation for review and concurrence prior to award. If
CONTRACTOR's QA/QC program is ISO 9000 certified, then only a copy of the ISO
9000 certificate is required. In addition, if CONTRACTOR's facility is ISO certified, QA
audit requirements will be waived in favor of ISO 9000 registrar audits, unless the
COMPANY's trend analysis program indicates areas of concern.

The CONTRACTOR shall identify in documents to its manufacturers, suppliers,


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 9 of 30

vendors and subcontractors all applicable QA/QC requirements imposed by the


COMPANY, and shall ensure compliance. On request, CONTRACTOR shall
provide objective evidence of its QA/QC surveillance for all levels of its activity.

7.0 DESIGN CONSIDERATIONS

The following climatic conditions shall govern the design of the CPS system:

Table 2.5

Maximum Ambient Temperature 55 ºC (47.5 ºC for fin fan design)


Minimum Ambient Temperature 0.5 ºC
Wet bulb temperature (design) 30 ºC
Relative humidity (Max / Nor /min ) 90 / 65 / 20 %
From South to North (Predominant
Direction of prevailing wind
across the year)
Wind Velocity (Max/Normal) 24 knots at 6m height / 2.9 knots
Elevation above mean sea level 54m (Site-IV)
(GPF)
1001.2 mbara (29.56 inches of
Average barometric Pressure
Mercury)
Ice/Snow None
Zone 2B, upper moderate with
Seismic Zone
ground acceleration of 0.2 (Hold)
Annual Rainfall min. 63.3 mm (year 2006)
Annual Rainfall max. 139.9 mm (year 2005)

Soil Resistivity
- ( see Attachment – 2 )

8.0 DOCUMENTATION - GENERAL

CONTRACTOR/SUBCONTRACTOR shall submit the type and quantity of drawings and


documentation for COMPANY's authorization to proceed.

Mutual agreement on scheduled submittal of drawings and engineering data shall be an


integral part of any cathodic protection project.

Comments made by COMPANY on drawing submittal shall not relieve


CONTRACTOR/SUBCONTRCATOR of any responsibility in meeting the requirements
of the specifications. Such comments shall not be construed as permission to deviate
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 10 of 30

from standard requirements unless mutual agreement is reached and confirmed in


writing.

Each drawing shall be provided with a title block in the bottom right-hand corner
incorporating the following information:

• Official trade name of the company;

• CONTRACTOR/SUBCONTRACTOR's drawing number;

• Drawing title giving the description of contents whereby the drawing can be
identified;

• A symbol or letter indicating the latest issue or revision;

• PO number and item tag numbers.

Revisions to drawings and documents shall be identified with symbols adjacent to the
alterations, a brief description in tabular form of each revision shall be given, and if
applicable, the authority and date of the revision shall be listed. The term "Latest
Revision" shall not be used.

9.0 SCOPE OF EXECUTION

9.1 Responsibilities of Contractor

SUBCONTRACTOR shall execute and provide the detail design and engineering,
supervision, calculation and technical procedures of each and every item of expense
necessary for a complete design package of the Cathodic Protection System for ferrous
materials in contact with soil herein after called WORK which is to be done in Mehar,
Pakistan.

The WORK shall include the following, by way of example but not by limitation, the
following tasks:

Obtain, generate and evaluate necessary information or procedures to perform complete


design, engineering, procedures and documentations of the cathodic protection system
with site supervision if required.

Provide detailed design for temporary and permanent cathodic protection systems in
compliance with this Specification and referenced international codes and standards and
suitable for the project’s environmental condition.

Provide detailed design on permanent testing facilities to monitor the cathodic protection
system from the Mehar GPF control room using latest technology available at the time of
system design.

Provide technical procedures for testing, pre-commissioning and commissioning of the


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 11 of 30

CP system to be submitted with the design package.

Design for, locate and mitigate any shorts in the cathodic protection system.

Design for test, evaluate and mitigate possible interference caused by cathodic
protection system on communication and low energy control systems.

Design for, evaluate and mitigate stray currents generated by newly installed cathodic
protection systems.

Provide documentation for CP system design and installation.

Provide an operations manual for system operation and maintenance.

Submit to the COMPANY a detailed cathodic protection design and installation methods
for review and approval. The design data shall include basis, calculations and drawings.

Prepare general cathodic protection system layout. Location of anodes, isolating joints,
or insulating flanges and other details shall be shown on applicable drawings.

10.0 DESIGN BASIS

10.1 General Basis

The design of cathodic protection system shall be based on the following and other
factors which are identified in the COMPANY’s project specification and soil resistivity
report:

• The new pipelines and associated structures shall be considered to have been
coated in accordance with referenced Pipeline Coating Specifications;

• The new pipelines shall be laid underground along the entire route of the
wellheads flowlines and trunkline up to the MEHAR GPF area;

• Equipment, materials, design, installation, testing and commissioning practices


shall conform to the international codes and standards listed in this document,
other requirements stated in this document and all relevant project drawings;

• All design, installation, equipment and materials shall be suitable for continuous
operation under MEHAR, PAKISTAN environmental conditions during the stated
design life of the cathodic protection system.

The design life of the cathodic protection system shall be:

Cathodic protection system for piping: 25 years.

Reference electrodes: 25 years.

Cathodic protection system with shorter design life may be designed subject to
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 12 of 30

COMPANY approval.

• The permanent CPS (cathodic protection system) shall be impressed current


system using the D.C output from Solar Array panels to be installed on the
wellheads location such as ME01 and ME02 (while for site location such as
wellhead ME03 and Manifold – North, the CPS equipment shall be located at the
GPF area including it’s power supply of 415/240V-AC from EMCC and including
all CPS cables to the pipelines) providing enough spare capacity available to
face the current demand of new buried pipelines for the specified design life.

• With the D.C sources available, the primary type of cathodic protection system
shall be impressed current using mixed metal oxide (MMO) anodes consisting of
oxides of iridium, tantalum and titanium on titanium base. The MMO anodes shall
be canister, wire, mesh, rod, tubular, ribbon type or a combination thereof.

• Conductive polymeric cable anodes are also technically acceptable as impressed


current anodes for soil conditions. Sacrificial anode systems shall be considered
secondary or supplementary to the primary impressed current systems or for
temporary CPS during construction period.

• The new cathodic protection systems shall provide corrosion protection to all
buried pipelines at levels of electrical potentials stated in the section 10.3 of this
document.

10.2 Current Requirements

The following minimum current densities shall be used as basis for current requirement
calculations.

a) SubContractor shall verify the current demand and modify the current densities
mentioned here for preliminary current estimation. The actual current drain on the
system shall not exceed 60% of the designed current demand.

Current density (Bare surface)

The following average current densities (based on bare surfaces) can be used to
estimate the current requirement, which shall be increased by 25% per 10°C rise
in temperature of the electrolyte above 30°C.

Bare steel in contact with soil - 22 mA / m2

Bare steel in contact with concrete - 20 mA / m2

Bare steel in fresh water - 30 mA / m2

Bare steel in saline water - 65 mA / m2

The above current densities are for estimation purpose only. The SUBCONTRACTOR
may have to increase current densities if he finds that they are required for the design
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 13 of 30

life.

SUBCONTRACTOR shall take into consideration steel bare coupons for monitoring and
externally coal tar polyurethane coated casing, if any.

b) Current density (Coated Surface)

The following initial and final (end of design life) current densities can be used to
estimate the current requirement for steel equipment, which shall be increased by 25%
per 10°C rise in temperature of the electrolyte above 30°C.

Initial - Final

Coated with coal tar urethanes or FBE - 0.05 - 0.20 mA / m2

Coated with 3-layer system (pipe surfaces ) - 0.005 - 0.25 mA / m2

NOTE: The design of the pipelines are provided with 3 layers of polypropylene coating.

The above current densities are for estimation purpose only, it may be increased as per
design requirement.

The end of life current density should take into account coating deterioration over the
design life and the nature of the soil condition in Mehar environment.

10.3 Performance Criteria

The installed system shall provide the levels of cathodic protection specified in Table 1.
Where such levels of protection are not achievable, and subject to COMPANY approval,
the system shall meet the criteria of the 100 mV polarizations decay as defined in NACE
RP0169 Section 6.

TABLE 1
Cathodic Protection Potentials

INSTANT "OFF" POTENTIALS, mV

REFERENCE ELECTRODE

CU/CUS04(1) Ag/AgCI(:.1)

Steel in soil(3) -950 to -1350 -900 to -1300

Steel in concrete -700 to -1300 -650 to -1250

Steel in water -850 to -1250 -800 to -1200


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 14 of 30

NOTES:

1. CU/CUS04 reference may be used for buried piping when testing with portable
reference electrodes.
2. Ag/AgCI reference electrodes shall be used for permanent installations in soil and
seawater.
3. Minimum protection potential shall not be differentiated for aerobic or anaerobic
environments; anaerobic conditions shall be assumed.

11.0 EQUIPMENT AND MATERIALS

New cathodic protection equipment and materials shall be similar to those existing on
PAKISTAN's pipelines installations.

11.1 Schedule of Equipment and Materials

Equipment and materials specified or referenced by the Manufacturer's name and/or


brand are intended to describe the type and quality level of the equipment and materials
desired and are not intended to be restrictive or to exclude similar items by other
Manufacturers. Alternate equipment and materials of similar quality or better may be
submitted for COMPANY approval.

Unless otherwise approved by the COMPANY, the products listed in Table 2 shall be
used in designing and installing the cathodic protection systems.

TABLE 2
Schedule of Equipment and Materials

MATERIAL /EQUIPMENT BRAND REFERENCE MFGR.

Anode systems for buried CerAnode CPR/CPR- APS


1. piping S with Kynar/HMWPE
insulated cable or

Raychem AnodeFlex Elgard Corporation


1500-01 (Conductive
polymeric cable)

Solar Power Systems R&S (Holland)


2.
BP Solar

3. Zinc ribbon Plattline Platt Brothers

Magnesium anodes (high Dow Galvomag Dow Chemical Mag


4.
potential) Maxmag Corp

5. Cables (Positive) Cathorad Permarad Judd Wire Raychem


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 15 of 30

HMWPE Rome

6. Cables (test) Judd Polvhal Judd Wire

MATERIAL / EQUIPMENT BRAND REFERENCE MFGR.


7. Resin splicing kits Scotch cast Raychem splice 3M Co.
encapsulation kit Raychem
JA Electronics
Hockway
8. Rectifiers VIP Custom Goodall
Universal,
9. Test stations - 8 wire Big Fink Cott Mfg. Co.
(Aboveground)
10 Test stations - Flush Fink Cott Mfg. Co.
belowground
11 Test stations - resistance FinkBonder Cott Mfg. Co.
bonding
12 Test station conduit CottPipe PE Cott Mfg. Co.
13 Shunts CottShunt Cott Mfg. Co.
Holloway
14 Bond box Bond box Model BB Cott Mfg. Co.
.
15 Anode terminal box Anode terminal box Goodall
.
Universal
JA Electronics
16 Remote control system Micro-polatrol CPS
Comanche Borin Mfg. Co.
17 Coke breeze Loresco SC-3 Loresco
18 Copper/copper sulfate Stelth7 SRE-031-CIY Borin Mfg. Co
reference electrode (soil
conditions)
19 Silver/silver chloride Stelth7 SRE-032-SIB Borin Mfg. Co
reference electrode (soil
conditions)
20 Deep well vent AIiVent Loresco
21 Environmental earth seal Permaplug Loresco
22 Electrical isolation flange Polyethylene F.H.Maloney
kits sleeves
23 Surge protectors (Ground Kirk Cell Kirk
cells)
24 Casing seals LinkSeal Model PL Thunderline
25 Coating for cable Belzona 1121 Belzona
connection
26 Casing Centralizers F.H. Maloney
(isolators) PSI
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 16 of 30

11.2 Impressed Current Anodes

Impressed current anodes shall be mixed metal oxides (iridium, tantalum and titanium
oxides) on titanium base or conductive polymeric cable anode.

SUBCONTRACTOR shall submit the following information to the COMPANY for product
approval:

• Composition of anode coating (mixed metal oxides, platinum, etc.);

• Anode core data including dimensional data;

• Anode shape and dimensional data;

• Electrical properties of the anode including internal resistance, attenuation rating


of the anode, current rating and consumption data;

• Cable data;

• Cable to anode connection including sealing materials and methods;

• Any other information that will be subject for COMPANY’s approval.

11.3 Sacrificial Anodes

Zinc anodes shall be ASTM B-418, Type II with the following composition:

AI 0.005 percent max.


Cd 0.003 percent max.
Cu 0.002 percent max.
Fe 0.0014 percent max.
Pb 0.003 percent max.
Zn remainder

Magnesium anodes shall be of the following composition:

AI 0.01 percent
Cu 0.02 percent max
Fe 0.03 percent max
Mn 0.50-1.3 percent
Ni 0.001 percent max
Others 0.30 percent max
Mg Balance

Cast anodes shall be factory prepackaged with backfill. Each anode shall be clearly
marked with the type of material (trade name) and anode weight (without backfill). Full
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 17 of 30

documentation (type, weight, dimensions, chemical analysis and performance data of


the anodes) shall be provided by the SUBCONTRACTOR.

11.4 Backfill Materials for Pre-Packaged Artificial Anodes

Backfill for sacrificial anodes, other than ribbon type, shall consist of a mixture of
Gypsum (75 percent), Bentonite clay (20 percent) and sodium sulfate (5 percent).

11.5 Backfill Materials for Impressed Current Beds in Soil

Maximum resistivity: - 0.10 ohm - cm

Fixed carbon: - 99.77 percent

Ash: - 0.1 percent

Moisture: - 0 percent

Volatiles: - 0 percent

Bulk density: - 1,185 kgs / m3

Particle size: - 1.0mm maximum, dust free.

11.6 Electrical Cables

Impressed current anode cables shall be tin coated stranded copper with Kynar primary
insulation and high molecular weight black polyethylene.

The minimum rating for all cables and wires shall be 600 Volts.

All other cables shall be tin coated stranded copper with HMWPE insulation.

All cables shall be able to withstand the prevailing chemical and mechanical (soil)
conditions. All cables shall be sized such that no excessive voltage drops occur which
reduce the capacity of the system. The minimum cable sizes shall be as follows:

• Positive and negative cathodic protection station cables;

For Solar Array or TR Unit rating up to 50 Amps - 50mm2


For Solar Array or TR Unit rating above 50 Amps - 90mm2

• Zinc earthing electrode cable tail and bonding cable - 16mm2 (AWG#6)

• Equipotential bonding cables - 16mm2 (AWG#6)

• Surge diverter cables - 25mm2 (AWG#4)

• Foreign pipeline crossing bonding cables - 16mm2 (AWG#4)


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 18 of 30

• Polarization coupon bonding cables - 10mm2 (AWG#8)

• Magnesium anode cable tail and bonding cable - 10mm2 (AWG#8)

• Cased crossing carrier and casing bonding cables - 10mm2 (AWG#8)

• Monitoring cables - 10mm2 (AWG#8)

• Permanent reference electrodes cables and bonding cables10mm2 (AWG#8)

All cables shall be properly tagged to identify their function.

11.7 CPS Supply Power (Solar Array Panels and Storage Batteries)

In Mehar wellhead site locations such as ME01 and ME02 where AC power is not
available, solar array panels and including back-up storage batteries (24V-DC system)
shall be provided to supply the required CPS current by others. Vendor to provide
suitable DC-DC converter for the CPS system.

But for wellhead site location as in ME03 and at the Manifold-North, the CPS supply
power shall be coming from 415/240V-AC, 3-Phase, 50Hz of the MCC in the GPF area
including the CPS equipment and associated connection cablings to the u.g. pipelines.

11.8 Terminal Boxes

Terminal boxes shall be of stainless steel type 316L, painted and weatherproofed in
accordance with the minimum degree of protection IP 55 and in accordance with IEC
529.

They shall be provided with a 6 mm thick phenolic panel with appropriate shunts, grid
coil resistors terminals, meters and hardware as indicated by the Vendor's detailed
design. The junction box shall be provided with one or more 75 mm diameter conduit
hub and conduit for cables.

Terminal boxes shall provide sufficient room for heat dissipation (i.e. resistors), control
and test equipment. The boxes shall be provided with hinged doors giving access to all
internal components.

Terminal boxes of suitable sizes with IP-56 degree of protection for stand alone outdoor
purpose shall be provided for the following:

• Anode Junction / Terminals.

• Cathode Junction / Terminal.

• Equipotential Bond / Test Station.

• Road crossing Test Station.


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 19 of 30

• Foreign line crossing Bond /Test Station.

• HT power line crossing Bond/Test Station.

Existing Bond/Test stations on pipeline corridors shall be used to connect the cable
coming from new pipelines. However, new test station shall be installed if existing ones
are found damaged, with not enough space or incorrectly located.

• Terminal board shall be easily removable for adding or deleting cables. The
Terminal boards shall be dimensionally stable up to 70°C and resistant to
ultraviolet light. Terminals shall be completely accessible with leads located
under the cover. The Terminal shall be designed to reduce shock hazard.
Maximum height shall be 2 meters with no component requiring adjustment or
monitoring higher than 1.5 meters... The test station post shall be Schedule 40 or
80, 3" ND galvanized steel pipe.

• Lid of the box shall have rubber seals on mating face to make it tight against
moisture ingress and condensing inside box.

• Inside face of lid shall be provided with neat and bold line diagram of all
connections.

• All cables shall be colour coded and tagged.

11.9 Test Posts

The SUBCONTRACTOR shall clearly indicate the type of test post, bond box and
distribution box for each application in the detailed design.

Test posts shall provide sufficient room for the termination of test cables and for the
installation of bonding cables and/or resistors. Test posts head shall be orange color. Big
Fink test station with upright post shall be used in all areas except directly in the traffic
path.

If test stations are required to be installed underground or in traffic areas, they shall be
Flush Fink type provided with a closure to avoid ingress of dirt and have adequate water
drainage facilities.

Test stations shall be provided with lockable access doors or caps, or have external
insulated contacts fitted to allow easy connection of tests clips for regular monitoring.
Cable entry shall be at the bottom through protective tubes.

• Test post shall be provided at every 1 kilometer distance reroute pipeline, across
isolation joints or any other test point.

• The test post shall be Big Fink type 1.5 above ground height, made of, UV
stabilized polyethylene pipe, cast in concrete base 0.5M buried.

• All cables shall be color coded and tagged.


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 20 of 30

12.0 SYSTEMS ENGINEERING AND INSTALLATIONS

12.1 Qualification of Design Personnel

All WORK consisting of stray current analysis, system selection, system design,
technical procedures for installation, testing and commissioning shall be under direct
supervision of SUBCONTRACTOR'S Registered Professional Corrosion Engineer or a
NACE certified Cathodic Protection / Corrosion Specialist.

Education and experience data (CV or resume) of SUBCONTRACTOR's Corrosion


Engineer/Specialist shall be forwarded to COMPANY for approval before work
commences.

12.2 Schedule of Cathodic Protection System

VECO/CONTRACTOR shall provide a schedule of the pipelines to be cathodically


protected and the associated cathodic protection systems to achieve the required
protection levels.

12.3 Sacrificial Anode Beds

Where an impressed current system is not practical or for temporary cathodic protection,
zinc anodes may be used provided the soil resistivity is less than 1,500 ohm-cm and
magnesium anodes if the soil resistivity is between 1,500 ohm-cm and 3,000 ohm-cm. If
the resistivity is more than 5,000 ohm-cm, the SUBCONTRACTOR shall submit a
description of technical options to the COMPANY.

12.4 Impressed Current Anode Beds

Impressed current cathodic protection systems shall use surface (i.e. shallow) or deep
well ground anode beds located 150m distance minimum from buried structures.

The ground beds of an impressed current cathodic protection system shall be designed
such that:

• Its mass and quality are sufficient to meet the maximum current demand and last
for the design life of the system.

• Its resistance to earth allows the maximum calculated current demand to be met
at 80 percent or less of the voltage capacity of the DC source during the design
life of the system.

• The risk of causing interference on other buried structures is minimized.

The selection of the location and the sizing of anode ground beds shall be based on and
take full account of local conditions such as:

• Soil conditions and resistivity at various depths.


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 21 of 30

• Groundwater levels and resistivity.

• Strong seasonal changes in surface soil conditions.

• Available terrain (for surface groundbeds).

• Risk of shielding (especially for parallel pipelines).

• Risk of damage by excavation.

The SUBCONTRACTOR shall include in the basic design a calculation of the ground
anode bed resistance based on the most accurate soil resistivity data available (see soil
resistivity report) using established methods and formula. The SUBCONTRACTOR shall
specify in the detailed design the method of drilling the deep well if required, establishing
the resistivity of the soil at depth during drilling, completion of the borehole and
installation of the anodes and backfill. Resistivity and resistance measurements to
remote earth shall be verified by the SUBCONTRACTOR to confirm the value obtained
in accordance with the design or if more information is required.

Casings for Deepwells

The borehole design and construction shall be such that undesirable transfer between
water bearing formations and pollution of underlying strata from the surface is prevented.

Metal casings may be used at the surface for stabilizing the borehole and in the active
section of the ground bed. Casing at depth shall be electrically isolated from metal
casing and structures at the surface. To achieve such isolation, plastic casing shall be
used.

12.5 Connection of Cables

12.5.1 General

Cables routes shall be clearly marked using cable markers. These shall be installed at
approximately 25 meters intervals and at every change of direction of the cable route.
Markers to indicate CPS cable and include arrow to indicate the direction of cable run.
Cable markers at the sacrificial anodes location shall also include markings to indicate
the location of the sacrificial anodes.

Impressed current anode cable connection shall be insulated using epoxy resin and/or
heat shrinkable insulation sleeves. The cables shall be connected to the positive feeder
cable inside an above ground junction box to enable current monitoring. The cables of
sacrificial anodes shall be connected to the pipe via an above ground distribution box to
allow current monitoring and disconnection. No joint shall be permitted in buried anode
or cathode cables.

12.5.2. Connection methods

The SUBCONTRACTOR shall include in the design detailed procedures of methods to


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 22 of 30

be used for cable connections. Welders shall be fully qualified for the applicable welding
process.

Cable connections shall be designed to ensure adequate mechanical strength and


electrical continuity and to prevent damage to the structure. Connections shall be made
to surfaces which are thoroughly cleaned to the bare metal. Cleaning shall be
accomplished by file or grinders without reducing wall thickness below project
requirements. Wire brushing is not acceptable.

Welding of cable connections shall not be carried out on bends or within 200 mm of
welds.

All below and aboveground electrical connections shall be fully encapsulated with a
coating Belzona 1121 before backfilling. Coating repair at cable connections shall
comply with Project coating specification requirements as applicable.

The following guideline for cable connections selection shall be:

• Pin brazing process for all underground connections except drain points
(negative).

The pin brazing process shall use specially designed cable lugs and brazing pins
to braze the cables to the structure and shall be approved by the CONTRACTOR
and COMPANY.

The brazing materials shall be compatible with the structure material. Penetration
of copper and/or other brazing metals into the structure shall not be deeper than
1 mm and the hardness shall remain inside the original structure requirements.

• Bolted connections for all underground or aboveground connections in particular


at drain points (welded plate + stud).

Bolted connection consists of a stud welded to the surface requiring connection


or a steel plate welded to the surface, a cable terminal with brazed or crimped
lug, washer and double nuts.

Stud material shall be similar to the structure material. Where a stud can not be
welded directly to the structure, a metal plate, 50 x 50 mm minimum, provided
with a welded M 10 threaded stud bolt shall be welded to the structure. The plate
shall be made of material similar to the structure.

The cable shall be connected to the threaded stud bolt using crimped or brazed
cable lugs, double nuts and serrated washers.

Stud welding may be done using an electrical (resistance welding) or mechanical


(friction welding) process which shall be approved by the CONTRACTOR and
COMPANY.

The stud material and consumable shall be compatible with the structure
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 23 of 30

material. The process shall not influence the structure material properties to fall
outside from original specification.

• Cadwelding process when suitable with level grade for underground connections.

Cadwelding process, when suitable with steel pipe grade, shall be such that
copper penetration into the pipeline material shall not be deeper than 1 mm and
that the hardness shall meet the original pipeline requirements. Cadweld charges
shall not be greater than CA 15 for steel pipe and cable cores shall not be
heavier than 16 mm2. If heavier cables need to be attached, the core shall be
separated into smaller strands of less than 16 mm2 each and welded separately.
Charges for cast and ductible iron pipe shall not exceed CA32XF19. Cadwelding
shall not be used for austenitic stainless steel and duplex steel surfaces.

Cadwelds shall be visually inspected and gently impact tested with a hammer.

The welds shall be tested for electrical resistance using an electrical multi meter,
and shall have zero resistance. Any weld which does not meet these
requirements shall be discarded and the cable shall be re-welded. At connection-
to-pipe, half meter cable length shall be secured on top of the pipe.

The materials to be used and the connection procedure shall be approved by the
COMPANY.

12.5.3. Cables installation

All cables shall be laid without coils or kinks, buried in sand at a depth of at least 0.75 m,
provided with cable protection tiles and warning tape installed 250 mm above the cable.
Where cables are to be routed in areas of hydrocarbons spillage, etc., a special
protection shall be specified.

All buried cables shall be of one continuous length without splices. Cable to cable
connections should be made aboveground inside test stations to reduce the risk of
damage and to allow monitoring.

12.6 Electrical Earthing

Electrical safety earthing of the pipelines and associated structures and equipment shall
be made compatible with the cathodic protection systems.

Subject to COMPANY's approval, particular devices and earthing shall be installed at


locations where A.C. influence may have adverse effect. They shall protect the structure,
cathodic protection systems and personnel against AC fault currents, lightning, AC
induction and power switching surge currents.

12.7 Electrical Continuity

Bonding cables shall be installed to maintain electrical continuity at locations such as


non-welded joints, mechanical joints, flanges, couplings, and locations where there is no
electrical continuity within the piping system to be cathodically protected.
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 24 of 30

12.8 Electrical Isolation

Cathodically protected surfaces shall be electrically isolated from existing structures or


earthing systems and at pipeline ends in accordance with NACE RP0169 using isolating
joints or flanges.

The resistance across isolating joint shall be measured immediatly before welding onto
the pipeline and found 1 M ohm minimum.

All isolation materials shall be resistant to the product/service inside the pipe.

Isolating joints shall not be buried.

Common metal pipe supports shall be avoided or electrically isolated from the pipelines.

Safety or instrument earthing shall be compatible with the cathodic protection system.

Isolating joints should be painted or striped in a contrasting color for easy identification.
The color should be consistent in one area. The paint shall be compatible with the
pipeline coating. Paints containing metallic pigments (such as zinc or aluminium) shall
not be used for top-coating on isolating joints.

12.9 Stray Currents

The CONTRACTOR shall carry out a survey for stray currents generated by the newly
installed cathodic protection systems.

Stray currents generated by the newly installed cathodic protection systems shall be
eliminated at the source by suitable insulation or other means. If this is not economically
feasible, other measures such as installation of a current drainage system shall be
designed and installed.

Stray currents above 20 mV on new pipelines from surroundings, or on nearby buried


structures or civil foundations due to CP on new pipelines, measured by interrupting CP
current shall be informed and mitigated with Company's approval.

12.10 Installation of Test Stations

Sufficient number of test stations shall be installed to locally or remotely to monitor the
system performance:

• Anode output - Individual anode circuits shall be provided with shunts to


measure anode current outputs. Sacrificial anode cables shall be connected to
the pipeline via a bond box and shunts inclusive blocking diodes to allow anode
current monitoring. For magnesium anodes, a resistor may be required in the
anode circuit to limit the protection levels to within the protection criteria.

At the drain points, each negative connection to the pipe shall be provided with current
measurement facilities. For single pipes, the ammeter built into the current source may
suffice. Where multiple negative connections are installed, separate shunts grid coils
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 25 of 30

and blocking diodes shall be provided complete with ammeter and selector switch
installed in a distribution box.

At the drain point, a potential monitoring station shall be installed using a separate test
cable connected to the pipe for measurement of the drain point potential.

• Cathodic interference - Test stations shall be installed at the crossings of


foreign structures. At crossings with foreign structures, a bonding facility shall be
provided, consisting of two separate cables attached to each pipeline,
terminating in a test post with suitable facilities to install direct or resistive bonds.
The cables to each structure shall be identified by properly marked stainless
steel tags. A permanent location for portable reference electrode shall be
provided above or asides each pipeline so that electrode be located at required
maximum distance. White color of cable shall be used for foreign pipeline
connection on crossing.

• Electrical continuity - Anode terminal boxes and test stations shall be installed
for bonding current carrying cables (including bonds between pipelines/
structures or across isolation joints). These test stations shall be located outside
hazardous areas. If this is not practical, a box approved for the relevant area
classification shall be used

• Electrical isolation - Each isolating joint and isolating flange shall be provided
with test facilities. At all isolating joints flanges, two cables shall be connected to
each side of the joint or flange. All cables shall be separately terminated in one
test post with suitable facilities to install direct or resistive bonds. The cables to
each side of the isolating joint shall be identified by stainless steel tags.

12.11 Remote Monitoring and System Control

SUBCONTRACTOR shall submit for COMPANY approval, details of a fully operational


remote monitoring system which shall be supplied and installed by the CONTRACTOR.

Remote monitoring equipment shall be installed at all C.P Stations and include output
voltage, output current, drain point potential of each pipeline and alarms. Remote
monitoring at each C.P Station shall include a reference electrode located close to the
pipe surface at the drain point.

Please refer to Attachment -1 for CP Remote Monitoring Facility

13.0 SPECIAL FACILITIES

13.1 Temporary CP Systems

In the case that the installation of the permanent cathodic protection system cannot be
finalized before the pipe is buried, or if specified by the COMPANY, a temporary
cathodic protection system shall be installed. Such a system shall be designed in the
same way as a permanent cathodic protection system with the exception that material
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 26 of 30

quantities and quality shall be adequate to cover a lifetime equal to the time of the
pipeline construction until the expected commissioning of the permanent cathodic
protection system. In case of sacrificial anodes system, anode connections shall be
constructed such that they can easily be connected / disconnected when commissioning
of the permanent system.

For temporary cathodic protection system to be used for protection during construction
before power is available, other DC sources may be used such as batteries.

The permanent monitoring facilities connected to the pipeline shall be constructed


simultaneously with the pipeline to allow monitoring of the performance of the temporary
system.

13.2 Designs Near High Voltage Power Lines as Applicable

If the pipeline runs in the vicinity of high voltage power lines, the SUBCONTRACTOR
shall investigate whether high AC voltages can be present on the pipeline by induction or
otherwise and whether devices need to be installed for protection of the pipeline and
personnel.

The SUBCONTRACTOR shall show (by calculation or otherwise) that no harmful


voltages can be present or design additional facilities to prevent excessive voltages.
Such facilities may consist of dedicated pipeline earthing.

13.3 Designs in Areas of Lightning Activity

The SUBCONTRACTOR shall install suitable lightning protection to protect the pipeline
isolation and cathodic protection equipment. This shall consist of suitably rated surge
arrestors and/or earthing. Surge arrestors shall be mounted across isolating joints.

Surge arrestors required to prevent elevated voltages due to faults in adjacent electrical
power systems or lightning shall be of the spark gap type and shall be designed such
that:

• The impulse breakdown voltage of the arrestor is lower than that of the isolating
joint across which they are mounted.

• The spark gap is capable of discharging the expected lightning currents without
sustaining damage.

The spark gaps are fully encapsulated to prevent sparks in open atmosphere and to
protect the spark gaps from moisture.

14.0 DOCUMENTATION REQUIREMENTS

Note: Where COMPANY approval is required, documentation shall be submitted by the


VENDOR to the CONTRACTOR. The CONTRACTOR shall review the documentation
and supporting data for completeness and forward it to the COMPANY with a brief
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 27 of 30

summary and recommendation.

14.1 Design Documents

The basic design documents shall be submitted for approval by the COMPANY,
covering the following requirements:

• Results of any site surveys and soil investigations that have been carried out;

• Calculations of current requirements, pipeline attenuation, resistance and;

• current output of ground beds;

• A summary of the used formula and standards;

• A schematic diagram of the proposed cathodic protection system;

• A list of the estimated number and types of cathodic protection monitoring


facilities;

• The civil works required to install the cathodic protection system. Such works
include transformer/rectifier plinths, anode ground beds, mounting details of
distribution boxes and test posts, cable trenches, security fencing, etc.

• Any sensitivity in the proposed cathodic protection system that requires special
attention.

The following detailed design documents shall be submitted by SUBCONTRACTOR to


the COMPANY for approval before construction starts:

• A schedule of materials including a complete set of material and equipment


specifications.

• A complete set of design drawings.

• Installation procedures.

• Commissioning procedures.

• Operation and maintenance instructions

14.2 Material Schedules

This schedule shall include the descriptions and quantities of all materials to install the
cathodic protection system.

The SUBCONTRACTOR shall also include in the material schedule a list of proposed
monitoring equipment (hardware and software) required to carry out regular surveys of
the cathodic protection system.
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 28 of 30

The SUBCONTRACTOR shall also include a list of proposed tools and spare parts
required for maintenance of the system during the first 5 years of operation.

14.3 Installation Procedures

Full construction details and installation procedures of the cathodic protection system
shall be submitted to the COMPANY for review and approval.

These shall include:

• Written procedures for the installation of DC voltage sources, anode ground


beds, cables, test facilities and all civil works and other procedures for cable
connections to the structures.

• A time schedule for the installation of the system, where required in relation to
the construction schedule of the structures.

• Written procedures of all tests required to demonstrate the specified quality of


installation.

• All relevant construction drawings including but not limited to plot plans, locations
of cathodic protection stations and test facilities, cable routing, single line
diagram, schematics and wiring diagrams, anode ground bed construction and
civil works.

• Written procedures to ensure safe working practices during the installation and
operation of the cathodic protection system.

The installation of the cathodic protection system shall start only after approval of the
installation procedures by the COMPANY.

14.4 Pre-Commissioning Testing and Inspection Procedures

The SUBCONTRACTOR shall provide all pre-commissioning, tests and inspections


procedures to the COMPANY for the confirmation of satisfactory installation and
operation of all equipment at site. Such tests shall include trial operation of power
sources to their maximum capacity and measurement and checking of all cathodic
protection circuits to confirm satisfactory connection and identification. Test shall include
resistance to earth tests of new ground bed anodes and zinc earthing electrodes,
calibration checks of permanent reference electrodes, testing of isolation joints and
insulated flanges, coating inspection survey upon hydrostatic testing and dewatering
using D.C voltage gradient technique.

SUBCONTRACTOR shall provide procedures for documenting the results of all tests for
inclusion in the commissioning manual.

14.5 Commissioning Procedures

Commissioning procedures are required to prove that the installed integrated cathodic
VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 29 of 30

protection system is in accordance with the design. The system shall be considered
satisfactory when the cathodic protection cirteria is met at test stations and any other
accessible points of the MEHAR WELLHEAD FACILITIES pipelines location where
COMPANY requires tests to confirm effectiveness of CP system. During CP testing if
interference is highlighted the SUBCONTRACTOR shall carry out investigation to
determine cause and perform any work required to mitigate the same.

The commissioning procedures document shall include as a minimum:

• Procedures for the testing of pipeline isolation.

• Procedures for natural potential surveys.

• Procedures for energizing and de-energizing cathodic protection hardware.

• Procedures for full ON - instant OFF close potential surveys.

• Procedures for interference testing and interference mitigation.

• Requirements for polarization of pipeline.

• Procedures for interference testing if applicable.

• A time schedule for the commissioning of the system, where applicable in


conjunction with the construction or commissioning schedule of pipeline.

• Procedures for isolating structures.

• Procedures for testing and adjustment of structure to electrolyte potential.

14.6 Cathodic Protection Manual

A cathodic protection manual is required to ensure that the as-built cathodic protection
system is fully documented and that operating and maintenance procedures are
available for the future operation and maintenance works.

This document shall contain:

• A description of the system and system components and their purpose.

• Pre-commissioning results.

• The commissioning report which shall include copies of the relevant as-built
drawings marked up to show the location (with reference number) of all test
locations used during commissioning.

• As-built drawings.

• VENDORS's documentation for equipment and materials installed.


VECO Doc. No. 20298-11-EE12-104
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 MGDP E 1000 0 30 of 30

• A schedule of all monitoring facilities.

14.7 Training

SUBCONTRACTOR shall include the requirement in the design package for the
presence of COMPANY operating personnel during installation, pre-commissioning,
commissioning and close interval potential survey of the cathodic protection system. The
SUBCONTRACTOR shall include for training of COMPANY personnel in the operation
and maintenance of the cathodic protection system with particular attention being paid to
any special features of the system and troubleshooting.

15.0 SAFETY

The SUBCONTRACTOR shall address in his design all safety related topics regarding
the cathodic protection systems and indicate, in the installation and operating
documentation, procedures to ensure safe working practices. The SUBCONTRACTOR
shall be familiar with local safety rules and practices and implement these in his work.
Related safety topics are:

• General safety requirements for electrical equipment.

• Hazardous area classification.

• Accidental sparking.

• Isolation flange protectors.

• Hydrogen and chlorine evolution.


VECO Doc. No. 20298-11-EE12-001
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 ME01 E 1000 0 ATTACHMENTS

ATTACHMENT 1

DESIGN SPECIFICATION FOR CPS REMOTE MONITORING FACILITY


VECO Doc. No. 20298-11-EE12-001
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 ME01 E 1000 0 ATTACHMENTS
PART 1 GENERAL

Specification covers the requirements for design, manufacture, supply, installing and
commissioning a CPS remote monitoring facility for cathodic protection system’s
related monitoring.

PART 2 REMOTE MONITORING UNITS

2.0 REMOTE MONITORING FEATURES

The CPS Remote Monitoring Facility shall be designed to do cathodic protection


system related monitoring. The main monitoring features shall be to:

Monitor the values of analog signals such as Solar Array powered CPS unit DC
voltage, DC current, potential of permanent reference electrodes, soil to pipe
potential 'ON' and instant 'OFF'.

Generate alarms if monitored signals go outside of programmed set points, at


specific time interval and when DC power fails.

2.1 Monitoring

Catholic Protection System Monitoring

Standard cathodic protection system parameters shall be monitored. The typical


inputs for cathodic protection system monitoring shall be: the CPS DC output
voltage, the output current and the permanent reference electrode.

DC Power Monitoring

The presence of DC power before and after the circuit breaker at the charge
controller unit and battery shall be monitored.

Temperature Monitoring

The CPS Remote Monitoring Facility shall be able to monitor the temperature where
typical sensing points shall be in CPS output unit and storage battery.

3.0 REMOTE MONITORING HARDWARE

3.1 Packaging

The CPS Remote Monitoring Facility shall be packaged in a NEMA 4X enclosure.


This type of designation shall provide corrosion and water protection to the electronic
circuits. There shall be a flexible watertight conduit to connect to the rectifier that
comes supplied with the unit.

3.2 Power

The CPS Remote Monitoring Facility shall be powered from 24 volts DC distribution
board, enabling the use of the new solar array power available at ME01 and ME02
VECO Doc. No. 20298-11-EE12-001
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 ME01 E 1000 0 ATTACHMENTS
wellhead site location.

For wellhead site location such as ME03 and Manifold–North, the CPS Remote
Monitoring Facility shall be powered from the 415/240V-AC mcc at GPF switch
room.

3.3 Back Up Power

The power shall use a rechargeable battery for internal backup. The battery shall be
sized to insure that the CPS Remote Monitoring Facility can generate alarm calls in
case of power failure. The battery shall always be kept at optimum charge when
power is available. In the event of power loss, the battery shall take over for a
minimum of one hour (1) to insure continuous operation.

When the battery voltage drops below a specified level, the whole system shall turn
OFF. Normal operation shall resume only after the power is restored to a normal
level.

In addition, the data memory shall also be equipped with an independent back up
system to protect the integrity of the data recorded when no power is applied to the
system.

3.4 Surge Protection

The CPS Remote Monitoring Facility shall be protected against surges of up to 1,000
Volts @ 10,000 Amps coming from the analog inputs, AC power lines and telephone
lines.

3.5 Analog Inputs

All of the analog input channels shall be sampled simultaneously, not sequentially.
Inputs used for reference cell measurement shall have input impedance of at least
10 M ohms.

Each analog input shall be able to be remotely configured to any of the following
ranges:

± 100 millivolts with 12 K ohm input impedance

± 10 Volts with 22 mega ohm input impedance

to 0-100 Volts @ 22 M Ohms

to 0-350 Volts @ 22 M Ohms

3.6 Digital Inputs

The status of at least two digital inputs from dry contacts or optically isolated devices
shall be monitored.

3.7 Digital Outputs


VECO Doc. No. 20298-11-EE12-001
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 ME01 E 1000 0 ATTACHMENTS
There shall be one digital output to control the CPS operation. This output shall be
used to turn the CPS output OFF and back ON for depolarization and Instant "OFF"
readings (an independent circuit shall be used for interruption cycles). The same or
independent circuit will be utilized for continuous control of CPS unit in "Manual
control mode"

3.8 Operating Environment

The CPS Remote Monitoring Facility shall be able to operate in a range of -40 C to
+70 C.

3.9 Communication Interface

Local Communication

The CPS Remote Monitoring Facility shall have an optically isolated RS232 or 485
port for local communication using a portable computer or hand held data logger.
This local port shall provide access to all functions and settings of the Remote
Monitoring system and communicate with the RTU panel of instrumentation.

Remote Communication

The remote communication port shall be used for communicating with the Remote
Monitoring system of the GPF area via the RTU panel. The port shall be configured
to interface with the different possible communication links. They shall specify and
may be of the following link (and coordinated with instrumentation discipline) as
below:

• Modem connected to a standard telephone line or FOC;

• Modem connected to or inside a cellular telephone;

• Radio modems;

3.10 Memory

Data

The data memory shall be used to store historical information and the configuration
of the Remote Monitoring system. It shall consist of a minimum of 10 Kbytes, to a
maximum of 6 MB of CMOS static Random Access Memory with local internal
battery back up.

System

The CPS Remote Monitoring Facility shall be designed so that the operating
software can be upgraded remotely by using the existing communication channel.
VECO Doc. No. 20298-11-EE12-001
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 ME01 E 1000 0 ATTACHMENTS
PART 3 REMOTE MONITORING SOFTWARE

4.1 General

The operating software shall be designed to run in the Microsoft Windows


environment. It shall provide access to all the functions of the Remote Monitoring
System and communicate with the RTU panel of instrumentation. It shall have
mapping software for a user-friendly interface.

4.2 Site Programming

This module shall provide basic data entry for an individual site. All information
concerning the location, rectifier and monitored signals shall be entered through
this module. The other modules of the program shall then use this basic
information to call the CPS Remote Monitoring Facility and generate reports.

4.3 Group Programming

Once the basic programming is complete, the grouping module shall have the
capability to group any number of sites together. The communication module shall
then automatically generate calls to all sites within a group and generate
appropriate reports.

4.4 Communication

Calls to the Remote Monitoring Systems

The communication software shall allow communication to the Remote Monitoring


system.
VECO Doc. No. 20298-11-EE12-001
Project Title

MEHAR GAS DEVELOPMENT PROJECT


Area Location Discipline Document No. Rev. Page
12 ME01 E 1000 0 ATTACHMENTS

ATTACHMENT 2

Soil Resistivity - MEHAR


(extract from GEO SCIENCE ASSOCIATES’s
SOIL THERMAL CONDUCTIVITY/RESISTIVITY SURVEY REPORT)

You might also like