Professional Documents
Culture Documents
Subject: Turnkey Interior Design of Ante room, Entrance Hall and Dining Hall of Artillery
Mess-1
Dear Sir,
We are grateful and appreciate for considering us to execute the captioned work. We are writing you with
reference to the meeting convened by the committee at Chaklala Garrison Rawalpindi on August 7th 2006 for
giving a comprehensive & detailed presentation of the Interior Design Project.
We remained in touch with your team regarding this project since June 15, 2006 and have made all possible
efforts to reach the current status. In this context we made several visits at your desired locations to have
detailed discussions and delivered a number of presentations to materialize the project. In the past three
years we achieved a mile stone of the project by accomplishing the master plan of the whole project.
On July 22 2006, we gave a final presentation of master plan to the committee, comprised of 3 D view plan
and elevation of the building which were duly approved by the committee.
S No Particulars Remarks
1 Ante room
2 Entrance Hall
3 Dining Hall
4 BOQ
As asked by the committee, we will submit the working drawings of the whole project on July 24, 2006
Subject to issuing us the Letter of intent and an agreement with us for our professional services and
for the construction and Interior work awarded to us.
1. Ante room
• Architectural plan
• Structural plan
• Electrical
• Havoc
• Furnishing
2. Entrance Hall
• Architectural plan
• Structural plan
• Electrical
• Furnishing
3. Dining Hall
• Architectural plan
• Structural plan
• Electrical
• Furnishing
Note: - cost of painting and mural is not included in the above amount
As per the decision of the committee we again request you to issue us initially the LOI or any relevant
document confirming the work as awarded to us in order to expedite the pace of work.
We are again thankful for extending your trust upon us, we assure that we will put all our efforts to complete
the work to your entire satisfaction.
Seema Andleeb
Agreement(Contract)
Advance lump sum amount of Rs 1200, 000/= received on 07th August 2006. Distribution is as under.
2. Furniture Cost:
14 Switch Sockets
(1) Supply, Installation and testing of Nos 7 725 5075
15 Amp 3 pin switch socket unit.
(Tenby or equivalent.)
(2) Same as above but 5Amp switch Nos 30 625 18750
socket unit
(3) Supply Installation and testing of Nos 9 5000 45000
15 Amp switch socket for A/C
unit wiring with 6mm cable run
in PVC conduit
D.Bs
HVAC
AC unit (Sabro)
I. 4 tones cabinet type unit NOS 6 91,30 547,800
(heat and cool.) 0
II. 2 tones walls mutated unit NOS 2 89,100
(heat and cool) 44,55
0
Light Fixture
Supply, installation connection of the
following light fixture with 1.5 mm2,
1.5mm earth and all genine components
as starter capacititor, holder, lamps,
cable (Pakistan cable and new age) etc.
complete in all respect.
V. TBS 82 or 84 of tube light
(warm/cool) as approved by the NOS 113 950 107,350
architect.
Grand Total
Throughout each project life cycle, lessons are learned and opportunities for improvement are discovered.
As part of a continuous improvement process, documenting lessons learned helps the project team discover
the root causes of problems that occurred and avoid those problems in later project stages or future projects.
Data for this report was gathered by using Project Lessons Learned Record sheets and is summarized in the
table.
The objective of this report is gathering all relevant information for better planning of later project stages
and future projects, improving implementation of new projects, and preventing or minimizing risks for
future projects.
• What worked well—or didn’t work well—either for this project or for the project team?
• What needs to be done over or differently?
• What surprises did the team have to deal with?
• What project circumstances were not anticipated?
• Were the project goals attained? If not, what changes need to be made to meet goals in the future?
3 Project Highlights
Prepared by:__________________________________
Project Manager
______________________________
Executive Sponsor
______________________________
Client Sponsor
Letter of Intent...............................................................................................1
Cost of Entire Project:...................................................................................2
0.1 Mode of Payment:.................................................................................................3
0.2 BOQ of Furniture Items.......................................................................................11
0.3 Ante Room..........................................................................................................11
0.4 Dining room.........................................................................................................12
1 Lessons learned purpose and objectives...............................................13
2 Lessons learned questions......................................................................13
3 Project Highlights......................................................................................13
3.1 Top 3 Significant Project Successes...................................................................13
3.2 Other Notable Project Successes........................................................................14
3.3 Project Shortcomings and Solutions....................................................................14
4 Approvals...................................................................................................15
1. General Information.................................................................................16
2. Milestone 1 Review Summary.................................................................17
3. Milestone 1 Review Criteria.....................................................................17
4. Milestone 1 Review Check-list.................................................................17
1. General Information
The milestone is passed – minor outstanding items Interior design and from18/09/
remain. renovation of ante, entrance 2006 to
hall and dining hall 14/11/2006
The milestone is not passed – major outstanding items Car porch* 25/10/2006
remain.