BWSSB Completed and Ongoing Works as on 01st January 2010

Bangalore North Zone MLA Constituencies

1. Hebbal Constituency

A) BBMP Wards - 08

i. Ward No. 18 - Radhakrishna Temple


ii. Ward No. 19 - Sanjayanagar
iii. Ward No. 20 - Ganganagar
iv. Ward No. 21 - Hebbal
v. Ward No. 22 - Vishwanatha Nagenahalli
vi. Ward No. 33 - Manorayanapalya
vii. Ward No. 34 - Gangenahalli
viii. Ward No. 46 - Jayachamarajendranagar

B) BWSSB service station - 4


i. Sanjayanagar.
ii. R.T.Nagar.
iii. Anandanagar.
iv. BEL Road.

C) No. of water supply connections - 31000


D) Borewells
i. Total No. of Borewells - 358
ii. Borewell with hand pumps - 190
iii. Borewell with Mini Water Tank - 168
iv. New borewells drilled & commissioned - 133
E) Details of water supply and UGD works.

HEBBAL CONSTITUENCY
WATER SUPPLY WORKS 2008-09
SL Particulars Nos. Amount
NO.
1 No. of works completed 8 3,70,40,700/-
2 No. of works under progress 3 1,47,67,000/-
3 No. of works to be taken up 2 89,06,000/-
Total 6,07,67,700/-

HEBBAL CONSTITUENCY
SANITARY WORKS 2008-09
SL Particulars Nos. Amount
NO.
1 No. of works completed 6 1,34,87,000/-
2 No. of works under progress 6 1,83,50,000/-
3 No. of works to be taken up 1 25,00,000/-
Total 3,52,94,000/-

HEBBAL CONSTITUENCY
WATER SUPPLY & SANITARY WORKS 2009-10
SL Particulars Nos. Amount
NO.
1 No. of works sanctioned 41 3,83,82,000/-

table-1
2. Malleshwaram Constituency

A) BBMP Wards - 07

i. Ward No. 35 - Aramanenagar


ii. Ward No. 36 - Mattikere
iii. Ward No. 45 - Malleshwara
iv. Ward No. 64 - Rajmahal Gutahalli
v. Ward No. 65 - Kadu Malleshwara Ward
vi. Ward No. 66 - Subramanyanagar
vii. Ward No. 76 - Gayatrinagar

B) BWSSB service station - 5


i. Malleshwaram,
ii. Sriramapuram,
iii. K.G. Tower,
iv. Yeshwanthpura
v. Bahubalinagara.

C) No. of water supply connections - 24200


D) Borewells
i. Total No. of Borewells - 391
ii. Borewell with hand pumps - 231
iii. Borewell with Mini Water Tank - 160
iv. New borewell drilled & commissioned - 13

E) Details of water supply and UGD works.


MALLESHWARAM CONSTITUENCY
WATER SUPPLY WORKS 2008-09
SL Particulars Nos. Amount
NO.
1 No. of works completed 9 1,79,43,000.00
2 No. of works under progress 1 17,66,000.00
3 No. of works to be taken up 1 11,94,000.00
Total 11 2,09,03,000/-

MALLESHWARAM CONSTITUENCY
SANITARY WORKS 2008-09
SL Particulars Nos. Amount
NO.
1 No. of works completed 27 1,38,45,000.00
2 No. of works under progress 3 16,95,000.00
3 No. of works to be taken up - -
Total 30 1,55,40,000/-

MALLESHWARAM CONSTITUENCY
WATER SUPPLY & SANITARY WORKS 2009-10
SL Particulars Nos. Amount
NO.
1 No. of works sanctioned 41 1,42,14,400/-

table-1
3. Gandhinagar Constituency

A) BBMP Wards - 07

i. Ward No. 77 - Dattatreya Temple


ii. Ward No. 94 - Gandhinagar
iii. Ward No. 95 - Subhashanagar
iv. Ward No. 96 - Okalipura
v. Ward No. 109 - Chickpete
vi. Ward No. 120 - Cottanpete
vii. Ward No. 121 - Binnipete

B) BWSSB service station - 07

i. Bhashyam Park,
ii. LLR
iii. Chicklalbhagh
iv. Rajajinagar
v. Magadi Road.
vi. Kumar Park.
vii. Jayamahal.

C) No. of water supply connections


D) Borewells.

i. Total No. of Borewells - 445


ii. Borewell with hand pumps - 252
iii. Borewell with mini water tanks - 193
iv. New borewell & drilled & commissioned - 23

E) Details of water supply and UGD works.

GANDHINAGAR CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 15 3,37,52,000/-
2 No of works under progress 05 1,89,22,000/-
3 No of works to be taken up 01 15,85,000/-
Total 21 5,42,59,000/-

GANDHINAGAR CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 28 44,05,000/-
2 No of works under progress 01 19,75,000/-
3 No of works to be taken up - -
Total 29 63,80,000/-

GANDHINAGAR CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 74 1,92,09,400/-

table-1
4. Yeshwanthapura Constituency

A) BBMP Wards - 10

i. Ward No. 38 - HMT


ii. Ward No. 42 - Lakshmidevinagar
iii. Ward No. 16 - Jalahalli
iv. Ward No. 17 - J.P.Garden
v. Ward No. 37 - Yeshwanthpura
vi. Ward No. 130 - Ullalu
vii. Ward No. 159 - Kengeri
viii. Ward No. 198 - Hemmigepura
ix. Ward No. 40 - Doddabidarakallu
x. Ward No. 72 - Herohalli

B) BWSSB service station - 3


i. Kengeri,
ii. Yeshwanthpura
iii. Bahubalinagar.
C) No. of water supply connections - 10300
D) Borewells
i. Total No. of Borewells - 189
ii. Borewell with hand pumps - 84
iii. New Borewell drilled & commissioned - 81

E) Details of water supply and UGD works.


YESHAWANTHPURA CONSTITUENCY
WATER SUPPLY WORKS 2008-09
SL Particulars Nos. Amount
NO.
1 No. of works completed 7 12,91,900.00
2 No. of works under progress -
3 No. of works to be taken up -
Total 7 12,91,900.00

YESHAWANTHPURA CONSTITUENCY
SANITARY WORKS 2008-09
SL Particulars Nos. Amount
NO.
1 No. of works completed 2 9,40,000.00
2 No. of works under progress
3 No. of works to be taken up
Total 7 9,40,000.00

YESHAWANTHPURA CONSTITUENCY
WATER SUPPLY & SANITARY WORKS 2009-10
SL Particulars Nos. Amount
NO.
1 No. of works sanctioned 8 17,97,750/-

table-1
5. Mahalaxmi Layout Constituency

A) BBMP Wards - 07

i. Ward No. 43 - Nandhini Layout


ii. Ward No. 44 - Marappanapalya
iii. Ward No. 68 - Mahalakshmipura
iv. Ward No. 74 - Shaktiganapati Nagar
v. Ward No. 67 - Nagapura
vi. Ward No. 75 - Shankaramatta
vii. Ward No. 102 - Vrushabhavathinagar

B) BWSSB service station - 5


i. Mahalaxmi Layout
ii. Nandini Layout
iii. Rajajinagar.
iv. WOC Road.
v. Kamalanagar

C) No. of water supply connections - 32600


D) Borewells
Total No. of Borewells - 514
Borewell with hand pumps - 330
Borewell with Mini Water Tank - 184
No. of borewell drilled & commissioned - 9
E) Details of water supply and UGD works.
MAHALAKSHMI LAYOUT CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 04 2,37,000/-
2 No of works under progress 04 38,31,000/-
3 No of works to be taken up 01 7,89,000/-
Total 09 48,57,000/-

MAHALAKSHMI LAYOUT CONSTITUENCY


SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 23 17,57,000/-
2 No of works under progress 11 53,24,000/-
3 No of works to be taken up - -
Total 34 70,81,000/-

MAHALAKSHMI LAYOUT CONSTITUENCY


WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 30 76,32,000/-
F) General.
It is proposed to provide Diesel Generator 1000 KVA at Srigandakawal pump
house to supply uninterrupted water during power shutdown.

table-1
6. Dasarahalli Constituency

A) BBMP Wards - 08

i. Ward No. 12 - Shettyhalli


ii. Ward No. 13 - Mallasandra
iii. Ward No. 14 - Bagalakunte
iv. Ward No. 15 - T. Dasarahalli
v. Ward No. 39 - Chokkasandra
vi. Ward No. 41 - Peenya Industrial Area
vii. Ward No. 70 - Rajgopalanagar
viii. Ward No. 71 - Hegganahalli

B) BWSSB service station - 2


i. Peenya
ii. Yelahanka

C) No. of water supply connections - 6950


D) Borewells
i. Total No. of Borewells - 498
ii. No. of New Borewell Drilled & commissioned - 151

E) Cauvery Water Serviced in Ward Nos. 7, 11, 13, 22, 24, 25 & 32.
F) Details of water supply and UGD works.
DASARAHALLI CONSTITUENCY
WATER SUPPLY WORKS 2008-09
SL Particulars Nos. Amount
No.
1 No. of works completed 30 32,40,000.00
2 No. of works under progress 02 2,93,600.00
3 No. of works to be taken up - -
Total 32 35,33,600.00

DASARAHALLI CONSTITUENCY
SANITARY WORKS 2008-09
SL Particulars Nos. Amount
No.
1 No. of works completed 03 2,27,300.00
2 No. of works under progress -- -
3 No. of works to be taken up - -
Total 03 2,27,300.00

DASARAHALLI CONSTITUENCY
WATER SUPPLY & SANITARY WORKS 2009-10
SL Particulars Nos. Amount
No.
1 No. of works sanctioned 18 88,70,300/-

G) 474.702 Km distribution pipeline completed 27.58 Km feeder line out of 31.30


Km laid under GBWASP.

table-1
7. Yelahanka Constituency

A) BBMP Wards - 04

i. Ward No. 1 - Kempegowda


ii. Ward No. 2 - Chowdeshwari
iii. Ward No. 3 - Attooru
iv. Ward No. 4 - Yalahanka Satellite Town

B) BWSSB service station - 1


i. Yelahanka S/stn.,

C) No. of water supply connections - 5500


D) Borewells
i. Total No. of Borewells - 215
ii. Borewell with hand pumps - 4
iii. New Borewell drilled & commissioned - 87

E) Cauvery Water Serviced in Ward Nos. 24.


F) Details of water supply and UGD works.

YELAHANKA CONSTITUENCY
WATER SUPPLY WORKS 2008-09
SL Particulars Nos. Amount
NO.
1 No. of works completed - -
2 No. of works under progress - -
3 No. of works to be taken up - -
Total

YELAHANKA CONSTITUENCY
SANITARY WORKS 2008-09
SL Particulars Nos. Amount
NO.
1 No. of works completed 1 13,55,000/-
2 No. of works under progress 2 26,40,000/-
3 No. of works to be taken up - -
Total 3 39,95,000/-

YELAHANKA CONSTITUENCY
WATER SUPPLY & SANITARY WORKS 2009-10
SL Particulars Nos. Amount
NO.
1 No. of works sanctioned 36 25,51,100/-

G) 66.5 Km Distribution. Pipeline laid under GBWASP & 100% completed.

table-1
8. Byatarayanapura Constituency

A) BBMP Wards - 07

i. Ward No. 5 - Jakkuru


ii. Ward No. 6 - Thanisandra
iii. Ward No. 7 - Byatarayanapura
iv. Ward No. 8 - Kodigehalli
v. Ward No. 9 - Vidyaranyapura
vi. Ward No. 10 - Doddabommasandra
vii. Ward No. 11 - Kuvempunagar

B) BWSSB service station - 2


i. Sahakara Nagar,
ii. Vidyaranya pura

C) No. of water supply connections - 5300


D) Borewells
i. Total No. of Borewells - 464
ii. Borewell with hand pumps - 8
iii. Borewell with Mini Water Tank - 35
iv. New Borewell drilled & commissioned - 132

F) Cauvery Water Serviced in Ward Nos. 4, 15 & 19.


G) Details of water supply and UGD works.

BYATARAYANAPURA CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 22 32,14,000/-
2 No of works under progress 23 54,66,000/-
3 No of works to be taken up - -
Total 45 86,80,000/-

BYATARAYANAPURA CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 01 97,000/-
2 No of works under progress 01 5,98,000/-
3 No of works to be taken up - -
Total 02 6,95,000/-

BYATARAYANAPURA CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 03 2,93,100/-

H) 890 Km Distn. Pipeline laid under GBWASP & 100% work completed.

table-1
9. Mahadevapura Constituency

A) BBMP Wards - 08
i. Ward No. 54 - Hoodi
ii. Ward No. 82 - Garudacharapalya
iii. Ward No. 85 - Doddanekkundi
iv. Ward No. 83 - Kadugodi
v. Ward No. 84 - Hagadooru
vi. Ward No. 149 - Varthur
vii. Ward No. 86 - Marathhalli
viii. Ward No. 150 - Bellanduru

B) BWSSB service station - 2


i. AECS Layout.
ii. Hoody
C) No. of water supply connections - 1656
D) Borewells
i. Total No. of Borewells - 449
ii. Borewell with hand pumps - 15
iii. Borewell with energized - 397
iv. New Borewell drilled % commissioned - 116

E) Details of water supply and UGD works.

MAHADEVAPURA CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 06 4,64,400/-
2 No of works under progress 05 80,59,000/-
3 No of works to be taken up 03 1,98,000/-
Total 14 87,21,400/-

MAHADEVAPURA CONSTITUENCY
SANITARY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed - -
2 No of works under progress - -
3 No of works to be taken up - -
Total - -

MAHADEVAPURA CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl. Particulars Nos. Amount
No.
1 No of works sanctioned 03 11,15,000/-

F) 386.221 Km distribution pipeline work completed under GBWASP

table-1
10. Shivajinagar Constituency

A) BBMP Wards - 07

i. Ward No. 9 - Ulsoor


ii. Ward No. 91 - Bharathinagar
iii. Ward No. 92 - Shivajinagar
iv. Ward No. 62 - Ramaswamipalya
v. Ward No. 63 - Jayamahal
vi. Ward No. 93 - Vasanthanagar
vii. Ward No. 110 - Sampangiramanagar

B) BWSSB service station - 2


i. HGR
ii. Coles Park

C) No. of water supply connections - 13400


D) Borewells
i. Total No. of Borewells - 167
ii. Borewell with hand pumps - 132
iii. Borewell with Mini Water Tank - 35
iv. New borewells drilled & commissioned - 6

E) Details of water supply and UGD works.

SHIVAJINAGAR CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 07 94,64,000/-
2 No of works under progress 04 3,13,87,000/-
3 No of works to be taken up - -
Total 11 4.08.51.000/-

SHIVAJINAGAR CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 33 1,31,48,000/-
2 No of works under progress - -
3 No of works to be taken up 03 25,00,000/-
Total 36 1,56,48,000/-

SHIVAJINAGAR CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 14 50,02,800/-

table-1
11. Pulakeshinagar Constituency

A) BBMP Wards - 07

i. Ward No. 31 - Kushalanagar


ii. Ward No. 32 - Kaval Byrasandra
iii. Ward No. 48 - Muneshwarnagar
iv. Ward No. 60 - Sagayapura
v. Ward No. 47 - Devarajeevanahalli
vi. Ward No. 61 - S.K. Garden
vii. Ward No. 78 - Pulakeshinagar

B) BWSSB service station - 2


i. Pillanna Garden.
ii. Machalibetta.

C) No. of water supply connections - 15580


D) Borewells
i. Total No. of Borewells - 184
ii. Borewell with hand pumps - 141
iii. Borewell with Mini Water Tank - 42
iv. New Borewell drilled & commissioned - 17

E) Details of water supply and UGD works.

PULAKESHINAGARA CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 02 1,99,000/-
2 No of works under progress 01 5,12,000/-
3 No of works to be taken up 03 56,51,000/-
Total 06 63,62,000/-

PULAKESHINAGARA CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 19 28,02,200/-
2 No of works under progress 03 34,55,000/-
3 No of works to be taken up 03 25,82,000/-
Total 25 88,39,000/-

PULAKESHINAGARA CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 15 1,94,38,400/-

table-1
12. Sarvagnanagar Constituency
A) BBMP Wards - 08
i. Ward No. 27 - Banasavadi
ii. Ward No. 28 - Kammanahalli
iii. Ward No. 29 - Kacharakanahalli
iv. Ward No. 49 - Lingarajapur
v. Ward No. 59 - Maruti Sevanagar
vi. Ward No. 23 - Nagavara
vii. Ward No. 24 - HBR Layout
viii. Ward No. 30 - Kadugondanahalli

B) BWSSB service station - 6


i. Pillanna Garden.
ii. Machalibetta.
iii. HRBR
iv. HBR-I
v. HBR-II
vi. OMBR.
C) No. of water supply connections - 26396
D) Borewells
i. Total No. of Borewells - 437
ii. Borewell with hand pumps - 250
iii. Borewell with mini Water tank - 180
iv. New Borewell drilled % commissioned - 51

E) Details of water supply and UGD works.


SARVAGNANAGAR CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 02 1,18,100/-
2 No of works under progress 04 18,07,000/-
3 No of works to be taken up 01 1,70,000/-
Total 07 20,95,100/-

SARVAGNANAGAR CONSTITUENCY
SANITARY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed - -
2 No of works under progress 01 11,00,000/-
3 No of works to be taken up 01 10,40,000/-
Total 02 21,40,000/-

SARVAGNANAGAR CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl. Particulars Nos. Amount
No.
1 No of works sanctioned 27 33,01,450/-

table-1
13. K.R.Puram Constituency

A) BBMP Wards - 09

i. Ward No. 25 - Horamavu


ii. Ward No. 26 - Ramamurthinagar
iii. Ward No. 51 - Vijnanapura
iv. Ward No. 52 - K.R.Puram
v. Ward No. 53 - Basavanapura
vi. Ward No. 55 - Devasandra
vii. Ward No. 56 - A. Narayanapura
viii. Ward No. 81 - Vijnanagar
ix. Ward No. 87 - HAL Airport Road

B) BWSSB service station


i. K.R.Puram
ii. Ramamurthy Nagar
iii. AECS Layout.
C) No. of water supply connections - 15
D) Borewells
i. Total No. of Borewells - 421
ii. Borewell with hand pumps - 10
iii. Borewell with energized - 411
iv. New Borewell drilled % commissioned - 173
E) Details of water supply and UGD works.
K.R. PURAM CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 58 39,24,100/-
2 No of works under progress - -
3 No of works to be taken up 01 90,000/-
Total 59 40,14,100/-

K.R. PURAM CONSTITUENCY


SANITARY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 01 40,00,000/-
2 No of works under progress - -
3 No of works to be taken up - -
Total 01 40,00,000/-

K.R. PURAM CONSTITUENCY


WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl. Particulars Nos. Amount
No.
1 No of works sanctioned 21 16,11,700/-

F) 326.95 Km distribution pipeline work completed under GBWASP.

table-1
14. C.V.Raman Nagar Constituency
A) Area - 07

i. Ward No. 80 - Hoysalanagar


ii. Ward No. 88 - Jeevanbhimanagar
iii. Ward No. 113 - Konena Agrahara
iv. Ward No. 50 - Benniganahalli
v. Ward No. 57 - C.V. Raman Nagar
vi. Ward No. 58 - New Tippasandra
vii. Ward No. 79 - Sarvagnanagar

B) BWSSB service station - 7


i. Bhuvaneshwarinagar
ii. Jeevan Bheemanagar
iii. Ulsoor
iv. HAL II Stage
v. Indiranagara
vi. OMBR
vii. Machalibetta
C) No. of water supply connections - 20338
D) Borewells
i. Total No. of Borewells - 487
ii. Borewell with hand pumps - 178
iii. Borewell with Mini Water Tank - 305
iv. New Borewell drilled - 24
v. No. of borewell drilled & commissioned - 28
E) Details of water supply and UGD works.
C.V. RAMAN NAGAR CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 02 11,50,000/-
2 No of works under progress 06 43,14,000/-
3 No of works to be taken up 02 83,20,000/-
Total 10 1,37,84,000/-
C.V. RAMAN NAGAR CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed - -
2 No of works under progress 01 4,22,000/-
3 No of works to be taken up 02 34,84,000/-
Total 03 39,06,000/-

C.V. RAMAN NAGAR CONSTITUENCY


WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 14 2,81,61,500/-

table-1
Bangalore South Zone MLA Constituencies

1. Padmanabhanagara Constituency
A) BBMP Wards - 08
i. Ward No.161 - Hosakerehalli
ii. Ward No. 165 - Ganesh Mandhir
iii. Ward No. 182 - Padmanabhanagar
iv. Ward No. 183 - Chikkalasandra
v. Ward No. 166 - Karisandra
vi. Ward No. 167 - Yadiyooru
vii. Ward No. 180 - Banashankari Temple
viii. Ward No. 181 - Kumarswamy Layout

B) BWSSB service station - 6


i. MNK Park.
ii. Devagiri.
iii. Banashankari.
iv. Kumaraswamy Layout.
v. Hosakerehalli.
vi. Poorna Prajna Layout.
C) No. of water supply connections - 34500
D) Borewells
i. Total No. of Borewells - 262
ii. Borewell with hand pumps - 149
iii. Borewell with Mini Water Tank - 113
iv. New Borewell drilled & commissioned - 6
E) Details of water supply and UGD works.
PADMANABHANAGAR CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 07 27,82,000/-
2 No of works under progress 08 1,66,33,000/-
3 No of works to be taken up 01 5,70,000/-
Total 16 1,99,85,000/-

PADMANABHANAGAR CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 10 39,21,000/-
2 No of works under progress 03 18,90,000/-
3 No of works to be taken up 13 52,10,000/-
Total 26 1,10,21,000/-

PADMANABHANAGAR CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 35 4,20,40,600/-

table-1
2. Basavanagudi Constituency
A) BBMP Wards - 06

i. Ward No. 154 - Basavanagudi


ii. Ward No. 155 - Hanamanthanagar
iii. Ward No. 164 - Vidyapeetha
iv. Ward No. 156 - Srinagar
v. Ward No. 162 - Girinagar
vi. Ward No. 163 - Kattriguppe
B) BWSSB service station - 6
i. MNK Park.
ii. Mount joy.
iii. Nagendra Block
iv. Kathriguppa.
v. V.V. Puram
vi. B.T.R.
C) No. of water supply connections - 30500
D) Borewells
i. Total No. of Borewells - 363
ii. Borewell withhand pumps - 208
iii. Borewell with Mini Water Tank - 155
iv. New Borewell drilled & commissioned - 23
E) Details of water supply and UGD works.
BASAVANAGUDI CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 03 7,30,000/-
2 No of works under progress 04 15,38,000/-
3 No of works to be taken up 12 1,58,36,000/-
Total 19 1,81,04,000/-

BASAVANAGUDI CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 12 22,70,000/-
2 No of works under progress 08 79,50,000/-
3 No of works to be taken up 14 65,21,000/-
Total 34 1,67,41,000/-

BASAVANAGUDI CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-
10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 15 26,59,100/-

table-1
3. BTM Constituency

A) BBMP Wards - 08

i. Ward No. 146 - Lakkasandra


ii. Ward No. 152 - Suddaguntepalya
iii. Ward No. 172 - Madivala
iv. Ward No. 176 - BTM Layout
v. Ward No. 147 - Adugodi
vi. Ward No. 148 - Ejipura
vii. Ward No. 151 - Koramangala
viii. Ward No. 173 - Jakkasandra

B) BWSSB service station - 3


i. Hombegowdanagar
ii. Koramangala
iii. CLR
C) No. of water supply connections - 23100
D) Borewells
i. Total No. of Borewells - 207
ii. Borewell with hand pumps - 128
iii. Borewell with Msini Water Tank - 79
iv. New borewell drilled & commissioned - 13

E) Details of water supply and UGD works.

BTM CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 04 46,15,000/-
2 No of works under progress 06 1,06,39,000/-
3 No of works to be taken up 14 1,38,00,000/-
Total 24 2,90,54,000/-

BTM CONSTITUENCY
SANITARY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 09 20,96,000/-
2 No of works under progress 06 42,05,000/-
3 No of works to be taken up 21 40,76,000/-
Total 36 1,03,77,000/-

BTM CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl. Particulars Nos. Amount
No.
1 No of works sanctioned 44 1,11,62,500/-

table-1
4. Chickpet Constituency

A) BBMP Wards - 07

i. Ward No. 118 - Sudhamanagar


ii. Ward No. 119 - Dharmaraya Temple
iii. Ward No. 142 - Sunkenahalli
iv. Ward No. 143 - Vishveshwarapura
v. Ward No. 144 - Siddapura
vi. Ward No. 145 - Hombegowdanagar
vii. Ward No. 153 - Jayanagar

B) BWSSB service station - 4


i. Bannappa Park
ii. V.V.Puram
iii. Hombegowdanagar
iv. Byrasandra
C) No. of water supply connections - 23600
D) Borewells
i. Total No. of Borewells - 252
ii. Borewell with hand pumps - 194
iii. Borewell with Mini Water Tank - 58
iv. New borewell drilled & commissioned - 07

E) Details of water supply and UGD works.

CHICKPET CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 05 1,02,32,000/-
2 No of works under progress 06 80,66,000/-
3 No of works to be taken up 13 96,42,000/-
Total 24 2,79,40,000/-

CHICKPET CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 17 38,99,000/-
2 No of works under progress 08 24,16,000/-
3 No of works to be taken up 18 1,02,42,000/-
Total 43 1,65,57,000/-

CHICKPET CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 25 51,44,500/-

table-1
5. Vijayanagar Constituency
A) BBMP Wards - 08

i. Ward No. 122 - Kempapura Agrahara


ii. Ward No. 123 - Vijaynagar
iii. Ward No. 124 - Hosahalli
iv. Ward No. 134 - Bapoojinagar
v. Ward No. 132 - Attiguppe
vi. Ward No. 133 - Hampinagar
vii. Ward No. 157 - Gali Anjaneya Temple
viii. Ward No. 158 - Deepanjalinagar
B) BWSSB service station - 6
i. Nagendra Block
ii. Kathriguppe
iii. Magadi Road
iv. Mysore Road
v. Hosahalli
vi. Chandra Layout
C) No. of water supply connections - 25,286

D) Borewells
i. Total No. of Borewells - 458
ii. Borewell with hand pumps - 236
iii. Borewell with Mini Water Tank - 222
iv. New borewell drilled & commissioned- 26
E) Details of water supply and UGD works

VIJAYANAGAR CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 06 20,09,000/-
2 No of works under progress 07 53,23,000/-
3 No of works to be taken up - -
Total 13 73,32,000/-

VIJAYANAGAR CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 25 61,53,000/-
2 No of works under progress 07 39,31,000/-
3 No of works to be taken up - -
Total 32 1,00,84,000/-

VIJAYANAGAR CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 21 5,47,97,100/-

table-1
.
6. Jayanagara Constituency

A) BBMP Wards - 07

i. Ward No. 168 - Pattabhiramanagar


ii. Ward No. 169 - Byrasandra
iii. Ward No. 170 - Jayanagar East
iv. Ward No. 171 - Guruppanapalya
v. Ward No. 177 - J.P. Nagar
vi. Ward No. 178 - Sarakki
vii. Ward No. 179 - Shakambarinagar

B) BWSSB service station - 4


i. Devagiri
ii. Jayanagar
iii. Jayanagar IV T Block
iv. Byrasandra
C) No. of water supply connections - 26300
D) Borewells
i. Total No. of Borewells - 137
ii. Borewell with hand pumps - 93
iii. Borewell with Mini Water Tank - 44
iv. New borewell drilled & commissioned - 04

E) Details of water supply and UGD works.

JAYANAGAR CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 05 32,66,000/-
2 No of works under progress 05 96,29,000/-
3 No of works to be taken up 06 1,59,85,000/-
Total 16 2,88,80,000/-

JAYANAGAR CONSTITUENCY
SANITARY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 15 45,35,000/-
2 No of works under progress 07 95,49,000/-
3 No of works to be taken up 15 1,01,43,000/-
Total 37 2,42,27,000/-

JAYANAGAR CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-
Sl. Particulars Nos. Amount
No.
1 No of works sanctioned 21 80,01,000/-

table-1
7. Chamarajpet Constituency

A) BBMP Wards - 07

i. Ward No. 135 - Padarayanapura


ii. Ward No. 136 - Jagajeevanaram Nagar
iii. Ward No. 137 - Rayapura
iv. Ward No. 138 - Chalavaipalya
v. Ward No. 139 - Krishnaraj Market
vi. Ward No. 140 - Chamarajpet
vii. Ward No. 141 - Ajadhanagar

B) BWSSB service station - 2


i. Chamarajpet
ii. J.J.Nagara
C) No. of water supply connections - 24010

D) Borewells
i. Total No. of Borewells - 115
ii. Borewell with hand pumps - 65
iii. Borewell with Mini Water Tank - 50
iv. New Borewell drilled & commissioned - 12

E) Details of water supply and UGD works.

CHAMARAJPET CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 05 19,81,000/-
2 No of works under progress 04 18,11,000/-
3 No of works to be taken up 04 74,35,000/-
Total 13 1,12,27,000/-

CHAMARAJPET CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 36 68,51,000/-
2 No of works under progress 08 56,37,000/-
3 No of works to be taken up 04 33,90,000/-
Total 48 1,58,78,000/-

CHAMARAJPET CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 19 39,51,550/-

table-1
8. Bangalore South Constituency

A) BBMP Wards - 08

i. Ward No. 191 - Singasandra


ii. Ward No. 192 - Beguru
iii. Ward No. 184 - Uttarahalli
iv. Ward No. 185 - Yelechenahalli
v. Ward No. 197 - Vasantapura
vi. Ward No. 194 - Gottigere
vii. Ward No. 195 - Konanakunte
viii. Ward No. 196 - Anjanapura

B) BWSSB service station - 4


i. Poorna Pragna Layout
ii. Kumaraswamy Layout
iii. Banashankari
iv. Kothnur Dinne

C) No. of water supply connections - 1200

D) Borewells
i. Total No. of Borewells - 133
ii. Borewell with hand pumps - 25
iii. Borewell with Energized - 108
iv. New Borewell drilled & commissioned- 67

E) Details of water supply and UGD works.


BANGALORE SOUTH CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works to be taken up 1 4,00,000/-
Total 1 4,00,000/-

BANGALORE SOUTH CONSTITUENCY


WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 1 1,45,000/-

H) 203 Km Distribution pipeline laid under GBWASP.

table-1
9. Shanthinagara Constituency

A) BBMP Wards - 07

i. Ward No. 111 - Shantalanagar


ii. Ward No. 116 - Neelasandra
iii. Ward No. 117 - Shanthinagar
iv. Ward No. 89 - Jogupalya
v. Ward No. 112 - Domlur
vi. Ward No. 114 - Agara
vii. Ward No. 115 - Vannarapeta

B) BWSSB service station - 5


i. CLR
ii. Johnson Market
iii. Ulsoor.
iv. Indiranagara.
v. Domlur.
C) No. of water supply connections - 24780
D) Borewells
i. Total No. of Borewells - 171
ii. Borewell with hand pumps - 94
iii. Borewell with Mini Water Tank - 77
iv. New Borewell drilled & commissioned- 09

E) Details of water supply and UGD works.


SHANTHI NAGAR CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 06 1,33,14,000/-
2 No of works under progress 02 35,62,000/-
3 No of works to be taken up 09 2,03,31,000/-
Total 17 3,72,07,000/-

SHANTHI NAGAR CONSTITUENCY


SANITARY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 07 77,99,000/-
2 No of works under progress 03 25,56,000/-
3 No of works to be taken up 19 1,46,11,000/-
Total 29 2,49,66,000/-

SHANTHI NAGAR CONSTITUENCY


WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl. Particulars Nos. Amount
No.
1 No of works sanctioned 22 78,08,000/-

table-1
10. R.R.Nagara Constituency
A) BBMP Wards - 04
i. Ward No. 160 - Rajarajeshwarinagar
ii. Ward No. 129 - Jnanabharathi
iii. Ward No. 69 - Laggere
iv. Ward No. 73 - Kottigepalya

B) BWSSB service station - 2


i. R.R.Nagara
ii. Nagarabhavi
C) No. of water supply connections - 9400
D) Borewells
i. Total No. of Borewells - 571
ii. Borewell with hand pump - 110
iii.Borewell taken over from BBMP - 333
iv. No. of New Borewell Drilled & commissioned - 96

E) Cauvery Water Serviced in Ward No. 6 & 16

F) Details of water supply and UGD works.


RAJARAJESHWARINAGAR CONSTITUENCY
WATER SUPPLY WORKS 2008-09
SL Particulars Nos. Amount
NO.
1 No. of works completed 43 1,16,63,050.00
2 No. of works under progress 04 17,75,600.00
3 No. of works to be taken up - -
Total 47 1,34,38,650.00

RAJARAJESHWARINAGAR CONSTITUENCY
SANITARY WORKS 2008-09
SL Particulars Nos. Amount
NO.
1 No. of works completed 24 1,38,33,800.00
2 No. of works under progress 04 51,26,100.00
3 No. of works to be taken up 06 5,49,000.00
Total 34 1,95,08,900.00

RAJARAJESHWARINAGAR CONSTITUENCY
WATER SUPPLY & SANITARY WORKS 2009-10
SL Particulars Nos. Amount
NO.
1 No. of works sanctioned 11 1,21,40,300/-

G) 315 Km distribution pipeline completed feeder line work is in-progress under


GBWASP.

table-1
11. Rajajinagar Constituency
A) BBMP Wards - 07
i. Ward No. 99 - Rajajinagar
ii. Ward No. 100 - Basaveshwaranagar
iii. Ward No. 101 - Kamakshipalya
iv. Ward No. 107 - Shivanagar
v. Ward No. 97 - Dayanandanagar
vi. Ward No. 98 - Prakashanagar
vii. Ward No. 108 - Sri Ramamandhir

B) BWSSB service station - 6


i. Rajajinagara
ii. Kethmaranahalli
iii.WCR
iv. Mahalaxmi Layout
v. Nandini Layout
vi. Kamakshipalya
vii. Kamalanagara
C) No. of water supply connections - 23950

D) Borewells
i. Total No. of Borewells - 461
ii. Borewell with hand pumps - 286
iii. Borewell with Mini Water Tank - 175
iv. New Borewell drilled & commissioned- 11

E) Details of water supply and UGD works.


RAJAJINAGAR CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 05 6,44,000/-
2 No of works under progress 06 26,35,000/-
3 No of works to be taken up 02 42,94,000/-
Total 13 75,73,000/-

RAJAJINAGAR CONSTITUENCY
SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 22 23,76,000/-
2 No of works under progress 07 45,63,000/-
3 No of works to be taken up 01 10,53,000/-
Total 30 79,92,000/-

RAJAJINAGAR CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 15 1,21,71,500/-

table-1
12. Govindarajanagara Constituency

A) BBMP Wards - 09

i. Ward No. 103 - Kaveripura


ii. Ward No. 104 - Govindarajnagar
iii. Ward No. 105 - Agrahara Dasarahalli
iv. Ward No. 106 - Dr. Rajakumar
v. Ward No. 125 - Marenahalli
vi. Ward No. 126 - Maruthi Mandhir
vii. Ward No. 127 - Moodalapalya
viii. Ward No. 128 - Nagarabhavi
ix. Ward No. 131 - Nayandahalli

B) BWSSB service station - 3


i. Moodalapalya
ii. Vijayanagara OHT
iii.Chandra Layout

C) No. of water supply connections - 30896


D) Borewells
i. Total No. of Borewells - 408
ii. Borewell with hand pumps - 230
iii. Borewell with Mini Water Tank - 178
iv. New borewell drilled & commissioned - 51

E) Details of water supply and UGD works.

GOVINDARAJ NAGAR CONSTITUENCY


WATER SUPPLY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 08 18,40,000/-
2 No of works under progress 06 63,90,000/-
3 No of works to be taken up 05 31,22,000/-
Total 19 1,13,52,000/-

GOVINDARAJ NAGAR CONSTITUENCY


SANITARY WORKS-2008-09
Sl.
Particulars Nos. Amount
No.
1 No of works completed 55 1,54,03,000/-
2 No of works under progress 13 79,25,000/-
3 No of works to be taken up - -
Total 68 2,33,28,000/-

GOVINDARAJ NAGAR CONSTITUENCY


WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl.
Particulars Nos. Amount
No.
1 No of works sanctioned 18 4,49,12,000/-

table-1
13. Bommanahalli Constituency
A) BBMP Wards - 08
i) Ward No. 173 - HSR layout
ii) Ward No. 175 - Bommanahalli
iii) Ward No. 189 - Hongasandra
iv) Ward No. 190 - Mangammanapalya
v) Ward No. 186 - Jaraganahalli
vi) Ward No. 187 - Puttenahalli
vii) Ward No. 188 - Bilekahalli
viii) Ward No. 193 - Arekere
B) BWSSB service station - 3
i. Kothnur Dinne
ii. J.P.Nagara
iii.HSR Layout.
C) No. of water supply connections - 5400
D) Borewells
i. Total No. of Borewells - 902
ii. Borewell with hand pumps - 200
iii. Borewell with Energized - 682
iv. No. of Borewell drilled
& commissioned - 176

E) Cauvery water serviced in ward No. 11, 19, 26, 27, 28, 29, 30, 31

F) Details of water supply and UGD works.

BOMMANAHALLI CONSTITUENCY
WATER SUPPLY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 03 1,01,85,000/-
2 No of works under progress 03 26,13,000/-
3 No of works to be taken up 02 1,23,28,000/-
Total 08 2,51,26,000/-

BOMMANAHALLI CONSTITUENCY
SANITARY WORKS-2008-09
Sl. Particulars Nos. Amount
No.
1 No of works completed 01 98,000/-
2 No of works under progress 01 3,60,000/-
3 No of works to be taken up 03 42,16,000/-
Total 05 46,74,000/-

BOMMANAHALLI CONSTITUENCY
WATER SUPPLY & SANITARY WORKS SANCTIONED-2009-10
Sl. Particulars Nos. Amount
No.
1 No of works sanctioned 09 17,88,200/-

G) 556 Km Distribution pipeline laid under GBWASP as against 597 Km and feeder
line work is in progress.

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2008-2009.
HEBBAL CONSTITUENCY

Work Completed
Sl Est. cost in
W/S particulars
No Lakhs
Laying and Linking of 8" Feeder Main to improve W/S
to Sultanpalya area, coming under R.T. Nagar
1 Rs. 27.10
S/Station.

replacing of 8" dia PVC by 8" dia MS line in 80 feet


2 road upto Bus Stop in HMT L/O area, R.T. Nagar Rs.23.35
S/Station.
Laying & Linking of 300 mm dia Feeder main line on
CBI Road in Ganga Nagar area, coming under R.T.
3 Rs. 73.70
Nagar S/Station.

Replacement of 110 mm dia PVC old existing line at Part A 13.15


4 AECS L/O, I & II Stage, Vinayaka L/o, coming under
Sanjayanagar S/Station. Part B 12.50
P/L of proposed 150 mm dia DI pipeline from Sanjay
Nagar main Road to Ramana Maharishi Memoral hall
5 Rs. 11.75
& from Poona Bakery to K.E.B. L/O, coming under
Sanjayanagar S/Station.
P/L 100mm dia W/S line in place of 3" dia corroded
line at Hebbal, C.N. Halli, V. Nagena Halli, Babu
6 Rs. 20.55
Reddy L/O, Anand Nagar II Block, coming under
Anandanagar S/Station.
P/L of proposed 150mm dia Feeder Main to Railway
7 colony at Lotte Golla Halli, coming under New BEL Rs. 183.107
Road S/Station.
P/L of proposed 100 mm dia DI pipeline and linking to
200mm dia to 100 mm dia at 4th Cross, 3rd Block to 1st
8 Rs. 5.20
Main, BDA L/O, Chikkamarana Halli, coming under
New BEL Road S/Station.
Total Rs. 370.407

Work under Progress

Sl Est. cost in
particulars
No Lakhs
Shifting of 600mm dia PSC main to 600 mm dia PSC
1 main to 600mm dia MS line at Ballary Main Road & Rs.98.60
Defence area, coming under R.T. Nagar S/Station.
Replacement of 110 mm dia PVC old existing line at
Part C
2 AECS L/O, I & II Stage, Vinayaka L/o, coming under
21.10
Sanjayanagar S/Station.
Providing Laying 100mm dia DI at BEL road & 80’road
3 opp.Ramaiah Hospital & 12th cross near Lakshmi Tent Rs.27.97
MSR Nagar coming under BEL S/Station.
Total Rs. 147.67

Work to be taken up

Sl Est. cost in
particulars
No Lakhs
Replacement of 3' dia CI line by 100mm dia CI line at
AK colony, Sultanpalya, Manorayanapalya, Ganga
1 Rs. 40.00
Nagar, Bhuvaneshwari Nagar, Gangappa Block, Cross
Road Ganga Nagar, Harijan colony, Ganga Nagar, L.D.
table-1
Block, Dena Bank Colony & Krishnappa Block, coming
under R.T.Nagar S/Station.
Work of Replacement of 4’dia PVC pipe by Providing &
Laying 100mm dia DI line at R.T.Nagar HMT Layout 1st
2 & 2nd stage Narayanappa Block ,P & T Colony Rs.49.60
matadahalli for the extention Servicemen Colony HMT
Layout Anandanagar S/Station.
Total Rs. 89.06
Grand Total Rs. 607.677

HEBBAL CONSTITUENCY

Work Under Progress


Sl UGD particulars Est. cost in
No Lakhs
work of P/L 225mm dia SW line in place of 6" dia SW line at
A.K. Colony, J.C. Nagar Board Qtrs, A.K. Ashrama, Mothi
1. Nagar, Rahamath Nagar, Munishwara Block, coming under Rs.24.50
Jayamahal S/Station.

work of P/L 225mm dia SW lines in place of 6" dia SW line at


Lakshmaiah Block,k Ganesh Block, Matada Halli, Burial
Ground, Giddappa Block, Weaver's Colony, Jaki Garden,
Pillappa Block, Ambedkar Slum, Harijan Colony, Ist Block, II
Block, Thimmaiah Garden, Ganga Nagar Extn., Vasanthappa
2 Rs. 84.15
Block, Papanna Block, Krishnappa Block, Matappa Block,
Hebbal Mill, Darmanna Garden, Dinnur Village, Ex-Servicemen
Colony, R.B.I Colony, C.P.V. Block, Lakshmidevamma Block,
Appanna Block, Kempegowda colony, coming under R.T. Nagar
S/Station.
work of P/L 300mm dia RCC NP3 pipeline in place of 225mm
3 dia SW line at KGE L/o, 7th Main, HIG Colony, coming under Rs.11.00
New BEL Road S/Station.
work of P/L 300mm dia SW line linking to Sub-Main at Central
4 Rs. 5.00
Excise L/O, coming under Sanjay Nagar S/Station.
work of Laying and linking of 450mm dia NP3 Sub-Main at
5 V.N. Halli Main Road, Hebbal, coming under Ananda Nagar Rs. 28.85
S/Station.
work P/L 225mm dia SW line in place of 6" mm dia SW line at
Balaji L/O, HMT L/O, Amarajyothi L/O, R.B.I. Colony, S.B.M.
Colony, A.G.S. L/O, S.S.A. L/O, Govt Middle School, Sunrise
6 Rs. 30.00
Colony, Muniyappa L/O, Hebbal, Geddala Halli, Chola Nagar,
Kempe Gowda Nagar, Chamundi Nagar, coming under Ananda
Nagar S/Station.
Total Rs.183.5

Work Completed
Sl particulars Est. cost in
No Lakhs
work of rectification of 225mm dia SW line at RDMH's at 13th
1. Rs.0.97
cross, Kanakanagar coming under Annandanagara S/Station.
work of P/L 225mm dia SW line in place of 6" dia SW line at
2 Pomme Gowda, Matada Halli, 3rd Cross by the side of burial Rs. 5.90
ground, coming under Jayamahal S/Station.
work of P/L 225mm dia SW lines in place of 6" dia at
3 Rs. 13.75
Munihanumaiah Colony, Venkata Chari Nagar, L.G.Halli,4th, 5th,
table-1
7th & 8th Cross, MSR Nagar, KGE L/O, M.S. Ramaiah L/o, 80'
Road, coming under New BEL Road S/Station.
work of Providing/Laying and linking of 300mm dia NP3 Class
4 Rs. 19.00
at Railway Parallel Road, coming under Ananda Nagar S/S
work of P/L 300mm dia SW lines in place of 225mm dia SW
line at 2nd Cross, Shiva Shankar Block, Jayalakshmi Theater
5 Road, Pillamma Temple Road, 9th Cross, M.R. Garden, Rs. 65.90
Seethappa L/O, Chamundi Nagar, M.S.S. L/O, Akbar Masjid
Road, CIL L/O, coming under Ananda Nagar S/Station.
work laying and linking of 450mm dia NP3 Sub-Main at C.N.
6 Halli Main Road, Cholanayakana Halli, from Hospital to Sub- Rs. 29.35
Main, coming under Anand Nagar S/Sta
Total Rs. 134.87

Work To Be Taken Up

Sl particulars Est. cost in


No Lakhs
work of P/L 300mm dia SW lines in place of 6" dia at 4th & 8th
Cross, Muniramappa Garden, 7th Main, K.E.B. L/O, Geddala
1. Rs. 25.00
Halli, Central Excise L/O, N.T.I. L/O, Vinayaka L/O, L.G. Halli,
coming under Sanjay Nagar S/Station.
Total Rs. 25.00
Grand Total Rs. 352.94

STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS


DURING THE YEAR 2009-2010.
HEBBAL CONSTITUENCY

Sl.
Name of the work Amount
No.
Work of providing & laying 300 mm dia NP3 S & S RCC 4.25
1 pipeline from V. Nagenahalli main road to Guddadahally road
coming under Anandanagar S/s.
Work of providing & laying 450/300 mm dia NP3 S & S RCC 14.00
pipeline from RK Garden to 5th cross, Cholanayakanahalli via
2
New BEL road inplace of 225 mm dia SW pipeline coming under
New BEL road S/s.
Work of providing and laying 300 mm dia NP3 S & S RCC 7.75
3 pipeline / 225 mm dia SW line at Continuity of 80’ road
Ashwathnagar under Sanjayangar S/s.
Work of providing and laying 450 mm dai NP3 S & S RCC 16.20
pipeline inplace of 225 mm dia SW line from 1st main HIG to
4 Basaveshwarangar layout main road Via patel Muniyappa layout
and regarding 225 mm dia SW line at 2nd cross, Patelappa layout
coming under Sanjyanagar S/s.
Work of providing and laying 300 mm dia NP3 S & S RCC 7.40
pipeline inplace of damaged 225 mm dia & 6th cross, 80’ road,
5
RMV 2nd stage, Sanjayanagar to 450 mm dia and sub main near
80’ road, coming under Sanajayangar S/s.
Work of providing and laying 450 mm dia & 300 mm dai NP3 S 40.65
& S RCC pipeline inplce of 225 mm dia SW pipeline from
6
Sanjayuanagar main road to Bhupasandra mainroad via Kalpana
Chawla road under Sanjayanagar S/s.
Work of providing and laying 9” dia SW line at 9th corss, 0.74
7 Adikabir Ashrama Mothingar and Ramaiahnagar Bande area Opp
Mazid under Jayamahal S/s.
8 Work of P/L 9” dia SW line inplace of 6” dia SW line at 0.97
table-1
Ramakrishnappa block 3rd cross, AK colony, Bemmegowda road,
JC nagara under Jayamahal Ss/.
Work of P/L 9” dia SW line inplace of 6” dia SW line at 4th cross, 0.95
9 Bangaragirinagar, W No. 93 of Pulakeshinagara Constituency
under Jayamahal Ss/.
Work of P/L 9” dia SW line inplace of 6” dia SW line at 2nd main, 0.71
10
Chunchappa block under Jayamahal Ss/.
Work of providing and laying 9” dia SW line inplace of 6” dia 0.99
11 SW pipeline at 1st cross, Siddivinayaka layout and RDMH’s
under Sanjaya nagar S/s AEEN-3 sub division.
Work of providing and laying 9” dia SW pipeline inplace of 6” 0.90
dia SW pipeline at 3rd and 4th cross road Krishnappa layout and
12 linking to the existing 450 mm dia sub-main to avoid sewage over
flow in to storm water drain and RDMH’s coming under
Sanjayangar S/s AEEN-3 sub division.
Work of providing and laying 9” dia SW pipeline inplace of 6” 0.99
13 dia SW pipeline at Jaladharshini layout main road and RDMHs
coming under BEL road S/s AEEN-3 sub division.
Work of providing and laying 9” dia SW line inplace of 6” dia 0.99
14 SW pipeline at 3rd main road HIG and RDMH’s coming under
BEL road S/s AEEN-3 sub division.
Work of providing and laying 9” dia SW pipeline inplace of 6” 0.45
15 dia SW pipeline @ 1st cross, R K Garden under New BEL Road
S/stn.,
Work of providing and laying 9” dia SW pipeline inplace of 6” 0.99
16 dia SW pipeline 4th main, AECS L/o to 6th cross, KEB Layout
under Sanjayanagar S/stn.,
Work of providing and laying 9” dia SW pipeline inplace of 6” 0.96
17 dia SW pipeline at 7th cross, RBI colony, Ganganagar under R T
Nagar S/stn.,
Work of providing and laying 9” dia SW pipeline inplace of 6” 0.99
18 dia SW pipeline at 4th cross, 4th main, Vasanthappa Block,
Ganganagar under R T Nagar S/stn.,
Work of providing and laying 9” dia SW pipeline inplace of 6” 0.98
19 dia SW pipeline at 4th cross, L D Block, Ganganagar under RTN
S/stn.,
Work of providing and laying 9” dia SW pipeline inplace of 6” 0.99
20 dia SW pipeline at 5th main, 10th cross,Giddappa Block,
Ganganagar under R T Nagar S/stn.,
Work of providing and laying 9” dia SW pipeline inplace of 6” 0.99
21 dia SW pipeline at 4th main 3rd cross, L D Block, Ganganagar
under R T Nagar S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at 9th 0.73
22 Cross, Adikabir Ashrama Mothinagar and Ramaiahnagar Bande
area Opp. Mazid under Jayamahal S/stn.,
Work of P/L 225 mm dia SW line in place of 150 mm dia SW line 0.93
23 from 3rd Cross, M.R. Garden to Salem Railway Track coming
under Anandanagar S/stn.,
Work of P/L 225 mm dia SW line in place of 150 mm dia SW line 0.63
24
at 3rd Cross, Patel Muniyappa layout under Anandanagar S/stn.,
Work of P/L 9” dia SW line at 12, 13., 14 & 15, 1st Cross, Modi 3.65
25 garden W.No. 95, J.C. Nagar coming under Jayamahal S/stn.,

Work P/L 300 mm dia NP3 class S & S RCC pipeline in place of 15.00
26 existing 150x225 mm dia line at R.T.Nagar Main Road 2nd Main
MLA layout coming under RTN S/stn.,
Work of providing and laying 150 mm dia feeder main at 3rd main 12.11
27
to 4th cross, P & T colony Sanjayangar under Sanjayanagar S/s.
Work of providing and laying 100 mm dia DI line inplace of 110 12.26
28 mm dia PVC line at 5th main, 6th main, and 2nd G main road
NGEF layout Sanjayanagar S/s.

table-1
Work of providing and laying 100 mm dia DI line at 5th, 6th, 7th & 12.11
29
7th A corss UAS layout under Sanjayanagar S/s.
Work of providing and laying 100 mm dia DI line at 1st cross to 11.42
30
4th cross, UAS layout under Sanjayanagar S/s.
Work of providing and laying 100 mm dia DI line at AEC’s 12.07
31
layout under Sanjayanagar S/s.
Work of providing and laying 100 mm dia DI line inplace of 110 11.07
32 mm dia PVC line at 1st to 4th cross, NGEF layout under
Sanjayanagar S/s.
Work of providing and laying 100 mm dia DI line at 4th main, 5th 10.60
33 cross, NGEF layout under Sanjayanagar S/s.

Work of providing and laying 100 mm dia DI line at 1st to 3rd 11.94
34
main, NGEF layout under Sanjayanagar S/s.
Work of providing and laying 150 mm dia DI feeder main at 5th 12.81
35
cross, NGEF layout Sanjayangar S/s.
Work of providing and laying 150 mm dia DE feeder line at 1st to 12.49
36
7th cross, UAS layout Sanjayanagar S/s.
Work of providing and laying 150 mm dia DI line at 7.41
37
Bhoopasandra village 1st, 2nd & 8th cross under Sanjayanagar S/s.
Work of providing and laying 9” dia SW line inplace of 6” dia 40.00
38 SW line from 20th main road to 21st main road, MC layout comes
under Chandra layout S/s.
Work of providing and laying 100 mm dia DI pipeline inplace of 50.20
corroded 3” dia CI line and 110 mm dia PVC line at HMT layout
39
1st cross, 2nd main, 5th main, SBM colony, 2nd cross, SBM colony
and surrounding area under Anandanagar S/s.
Work of supplying, fixing pipeline of 100 mm dia DI line to 6.50
40 linking 300 mm dia CI line at new 80’ road Ashwanthanagar
under Sanjayanagar S/s.
Work of providing and laying 100 mm dia DI line inplace of 100 36.05
mm dia PVC line at 4th, 5th crsso, Vinayaka layout 2nd main,
41 Patelappa layout, 3rd cross, 1st main and 1st A main, CIL layout,
2nd cross, Amarjyothi layout ACEs layout 3rd stage, 2nd cross
under Sanjaynagar S/s.
Total 383.82

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2008-2009.
MALLESHWARAM CONSTITUENCY
Work Completed
Sl Est. cost
Water supply works particulars
No in Lakhs
work of providing and laying 4" dia. DI pipe line by replacing the
damage corroded 3" dia. C.I. pipeline at Subedar palya 6th and
1 Rs.11.70
7th Cross coming under YPR S/Station.(Ward No.7)

work of 100 mm dia W/S line at 11th cross, Kodandarampuram,


2 Rs.3.00
Vyalikaval, coming under Malleswaram S/Station.
P/L of 100 mm dia DI line replacing 3" dia old corroded pipeline
3 at 11th A B & C Cross KR pura, Vyalikaval, Malleswaram. Rs. 4.70

Rs.5.43
work of replacement of 3" corroded CI line by 100mm dia DI line
4 at Malleswaram 2nd 3rd & 4th Cross, by the side of K C G
Hospital & 15th Cross GD Park 1st, 2nd Main Road Malleswaram.
Rs. 7.87

work of replacement of 3" corroded CI line by 100 mm dia CI


line at Rammohanpura Gandigrama Gyatharinagar near Arun
5 Rs. 6.24
Kumar clinic coming under Srirampura S/Station.

work of Replacement of 100mm PVC & 3" dia corroded line by


laying 100mm dia DI line at Palace Gutta halli & surrounding
6 areas, Sadashiva Nagar, Dodda Byrappa street, Vyalikaval Ist & Rs.42.55
IInd Cross, lower Palace arch & Upper Palace arch, coming
under KG Tower S/Station.
P/L 100mm dia DI line in place of 3” dia Corroded line for new
7 W/S connection to 8th main road in between 2nd & 4th cross Rs. 2.75
Sadhashivanagar coming under K.G.T.S/Stn main
Shifting & linking 600mm dia W/S line to foot path by the side of
8 Rs. 94.23
palace compound wall in Ballary main road
Work of Providing & Fixing cobble stones from fly over to
9 Cauvery theater at Ballary Road coming under Kumara Park Rs.0.96
S/Stn.
Total Rs. 179.43

MALLESHWARAM CONSTITUENCY
Work Completed
Sl UGD works particulars Est. cost in
No Lakhs
work replacement of 6"dia SW pipeline by 9" dia SW line at 12th
1. A B, and C Cross, 6th main to 10th main Kodanda Ramapuram Rs.6.58.00
Vyalikaval, coming under Malleshwaram S/Station.
work of providing and laying 9"dia SW line in place of 6" dia
2. SW line at A.K. Colony, Subedar Palya and reconstruction of Rs.9.21
damaged Manholes coming under YPR S/Stn.
work providing & linking to 225mm dia SW line at 33, No.11,
3. No.37/19, No. 45, 2nd main Kempaiah & brothers L/o, RDMH's Rs.0.91
& construction of MH's coming under K.P.S/Station premises.
work of providing and laying 9" dia SW line in place of 6" dia
4. SW line at 1st main, K.B. L/o & RDMH's coming under K.P. Rs.0.98
S/Station premises.
table-1
work of providing and laying 9" dia SW line in place of 6" dia
SW line at 1st cross, K.B. L/o & RDMH's brothers L/0. &
5 Rs.0.97
RDMH's & Construction of MH's coming under K.P. S/Station
premises.
work of providing & laying 9" dia SW line in place of 6" dia SW
6 line at Opp. to # 13th "A" main to Railway Parallel Road, 17th A Rs. 0.99
Cross, MVM & RDMH's coming under MVM S/Station.
work providing & laying 9" dia SW line place of 6" dia SW line
7 at Opp. to 40/3, 3rd main, K.B. L/o & RDMH's coming under Rs. 0.95
K.P. S/Station premises.
work of replacing of 6" dia SW line at SP Extn, 4th Cross, 6th
8 Rs.2.55
Cross, coming under Malleswaram S/Station.
work of replacing of 6" dia SW line by 9" dia SW line at
9 Rs. 6.00
Devarayana Palya in ward No.4, Yeshwanthapura S/Station.
work of replacing of 6" dia SW line by 9" dia SW line P/L at
10 Rs.5.40
Mathikere & Subedar Palya at Yeshwanthapura S/Station.
work of P/L 225mm dia SW line in place of 6" dia SW line at
11 Rs.22.85
Jabber Block & P.G. Halli area, K.G. Tower S/Station.
work of replacement of 6" dia SW line by 9" dia SW line at 5th
12 Cross, 6th Cross S.P. Extension coming under Malleshwaram Rs. 6.00
Service Station.
work of replacement of 6" dia SW line by 9" dia SW line at 13th
13 Cross, Vyalikaval surrounding area coming under Malleshwaram Rs. 3.00
Service Station.
work of replacement of 6" dia SW line by 12" dia SW line at 6th
14 Cross Near S.S.L.C. Board coming under Malleshwaram Service Rs. 2.50
Station.
work providing and laying of 9" dia SW line in place of 6" dia
15 SW line at 7th Main, Gokula 1st Stage, coming under YPR S/Stn. Rs. 0.96

work providing and laying of 9" dia SW line in place of 6" dia
16 SW line at 1st 'E' Cross, Mathikere Extn., coming under YPR Rs. 0.99
S/Stn.
work providing and laying of 9" dia SW line in place of 6" dia
17 SW line at Subhaiah Hospital Main Road, Mathikere, coming Rs. 0.96
under YPR S/Stn.
work of providing and laying 9" dia SW line in place of 6" dia
18 SW line at Muthati Bank, Mathikere Main Road, coming under Rs. 0.99
YPR S/Stn.
work providing and laying of 9" dia SW line in place of 6" dia
19 SW line at Diana beauty Parlor, Mathikere Main Road, coming Rs. 1.00
under YPR S/Stn.
work providing and laying of 9" dia SW line in place of 6" dia
SW line at 8th Main, Devanarapalya & Pampanagar, Gokula 1st
20 Rs. 1.00
Stage, coming under YPR S/Stn.

work providing and laying of 9" dia SW line in place of 6" dia
21 SW line at Srinivasa Kalyana Manthappa, Mathikere Extn., Rs. 0.98
coming under YPR S/Stn.
work of P/L 9" dia SW line in place of 6" dia SW line at 2nd
22 Rs. 0.25
Cross(West) & RDMH's coming under YPR S/Stn.
work of P/L 450mm dia NP3 S & RCC pipe line in place of
225mm dia SW line @ DR. JeevrajAlva road adjacent to sankey
tank & P/L 225mm dia SW line300mm dia lineNP3 S &S RCC
23 Rs. 54.40
pipe line in place of 150mm SW pipe line from 9th cross, RMV
extension linking towards 450mm dia RCC line @ sankey tank
main gate coming under KG tower S/Stn.
table-1
Total Rs. 130.52

Work Under Progress


Sl particulars Est. cost in
No Lakhs
work of replacing of 6" dia SW line by 9" dia SW line P/L at
1. Ankala Parameshwari Temple, 4th Cross, (L.N. Pura) Nagappa Rs. 2. 50
Block.
Total Rs. 2. 50
Grand Total Rs. 133. 02

STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS


DURING THE YEAR 2009-2010.
MALLESHWARAM CONSTITUENCY

Sl.
Name of the work Amount
No.
Work of P/L 9” dia SW line in place of 6” dia SW line at 11th A 0.63
1
Main, D Block, 2nd Stage Rajajinagar under KM Halli S/stn.,
Work of P/L 9” dia SW line in place of damaged 6” dia SW line 0.58
2 at 6th A Main D Block, 2nd Stage Rajajinagar under K.M.Halli
S/stn.,
Work of providing and laying 9” dia SW line inplace of damaged 4.20
3 6” dia SW line between 11th & 12th main, 12th cross, MLM (Opp
Jaggesh house) under MLM S/s.
Work of providing and laying 9” dia SW line inplace of 6” dia 0.664
4 SW line at Opp to Maruthi hospital 1st cross Model colony under
YPR S/s.
Work of providing and laying 9” dia SW line inplace of 6” dia 0.77
5 SW line at Govt Higher school Yeshwanthpura and near Keshav
Talkies under YPR S/s.
Work of providing and laying 9” dia SW line inplace of 6” dia 0.495
6
SW line at No. 393, 414, 6th main, Sadashivangar under KGT S/s.
Wok of P/L of 9” dia SW line at No. 36/3, 5th cross, 7th main, KN 0.495
7
Extension Gokula, 1st phase, 2nd stage under Yeshwanthpura S/s.
Wok of P/L of 9” dia SW line at No. 606, 624, 1st main road, 2nd 0.491
8
cross, Mathikere Yeshwanthpura under Yeshwanthpura S/s.
Wok of P/L of 9” dia SW line at No. 18, 48, 2nd cross, Mathikere 0.491
9
under Yeshwanthpura S/s.
Work of P/L 9” dia SW line inpalce of 6” dia SW line at 0.96
10
Subbaiah hospital MS Ramaiah road under Yeshwanthpura S/s.
Work of P/L 9” dia SW line inpalce of 6” dia SW line at 0.979
11 Muthathi Finance Sri. MS Ramaiah road Mathikere under
Yeshwanthpura S/s.
Work of P/L 9” dia SW line inpalce of 6” dia SW line at Dayana 0.985
12 Beauty Parlour No. 35, Sri. MS Ramaiah road, Mathikere under
Yeshwanthpura S/s.
Work of P/L 9” dia SW line inpalce of 6” dia SW line at 6th 0.431
13
cross, Ayyappanagar under Bahubalinagara S/s.
Work of P/L 9” dia SW line inpalce of 6” dia SW line at near 0.945
14 Chandu’s Hotel,. 8th cross, Malleshwram under Malleshwaram
S/s.
Work of providing , laying and linking 9” dia SW line at New 0.95
BEL Road I/F of newly constructed TATA Institution Building
15 under New BEL Road S/stn.,

16 Work of providing and laying 9” dia SW pipeline inplace of 6” 0.997


table-1
dia SW pipeline @ 7th cross, MSR Nagar under New BEL Road
S/stn.,
Work of providing and laying 9” dia SW pipeline inplace of 6” 0.981
17 dia SW pipeline at 4TH cross MSR Nagar (pipeline road under
BEL Road S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at 6th 0.43
18
Cross, Ayappa Nagar coming under Bahubalinagar S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at near 0.94
19 Chandra Hotel, 8th Cross, malleshwaram coming under
Malleshwaram S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at near 6th 0.95
20
Cross, Ayappanagar under Bahubalinagar S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at Opp. to 0.66
21
Maruthi Hospital 1st Cross Model Colony under YPR S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at Govt. 0.77
22 High School, Yeshwanthapura and Keshav Talkies near under
YPR S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at No. 393, 0.49
23
414, 6th Main, Sadashivanagar under KGT S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at Masjid 0.75
24
Road, Diwanara Palya W.No. 4 under YPR S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at Gokul 0.76
25
Fly over under YPR S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at 1st B 0.99
26
Main, Mathikere under YPR S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at No. 610, 0.84
27
1st D Cross, Mathikere, Bangalore.
Work of P/L 9” dia SW line in place of 6” dia SW line at 482/A, 0.98
28
19, Revathi Nilaya, 5th Main, 3rd cross under YPR S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at 18, 1st B 0.87
29
Cross, Ramakrishna Nilay Mathikere under YPR S/stn.,
Work of P/L 300 mm dia RCC NP3 S & S pipeline in place of 7” 12.70
30 dia SW line linking to 450 mm dia RCC sub main at 15th Cross B
/ W 4th to 6th Main Malleshwaramf under MLM S/stn.,
Work of replacement of 6” dia by 9” dia SW line at 10th Main, 3.45
31
11th Main & 6th Cross Mariyappanapalya under Srirampura S/stn.,
Work of P/L of 9” dia SW line in place of 6” dia SW line at 1st 31.58
32 Stage, 1st Phase to 4th Phase Gokul coming under
Yeshwanthapura S/stn.,
Work of P/L 450/300 mm dia NP3 S & S RCC pipeline from 25.20
Nethaji road to Laxmi Tent Road in place of 225 mm dia
damaged SW pipeline and linking 225 mm dia SW line in various
33
cross at Sampangappa layout under New BEL Road S/stn.,

Work of P/L of 9” dia SW line in place of 6” dia SW line at Photo 6.00


34 plash to Jayaram Slum 3rd Main, HMT Main Road, Mathikere
Extension Mathikere under JPR S/stn.,
Work of providing and laying 100 mm dia DI pipeline inplace of 6.47
35 3” dia corroded pipeline at 6th to 7th main, 2nd cross,
Subedarapalya under Yeshwanthapura S/s.
Work of replacement of corroded 3” dia CI line by 4” dia at 2.63
36 between 9th & 10th main, 12th C corss, Vyalikaval comes under
Malleshwaram S/s.
Work of providing and laying 100 mm dia DI water supply line 6.81
37 inplace of 110 mm dia PVC damaged water supply line at 5th
cross, Nagappa block, 7th cross, LN Pura under Srirampuram S/s.
Work of providing and laying 100 mm dia DI line inpalce of 8.05
38
corroded 3”dia CI line at 3rd main Mathikere Yeshwanthpura S/s.
Work of P/L 100 mm dia DI line in place of 3” dia corroded 4.11
39
pipeline and 75 mm dia PVC line at 1) L.N. Colony, 1st D Cross
table-1
road 5th Main, 2) Bandappa street 8th A Cross 3) Model Colony 1st
Cross, W.No. 3 under YPR S/stn.,
Work of providing and laying of missing bit 150 mm dia DI line 2.80
40 from 3rd main, 50, 5th main, Mathikere extension Yeshwanthapura
S/s.
Work of P/L of 250x250 mm dia DI line at Binnya layout to 1st 6.87
41 Main Bhuvaneshwarinagar in W.No. 31 coming under JJ Nagar
S/stn.,
Total 142.144

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2008-2009.
GANDHINAGAR CONSTITUENCY

Work Under Progress


Sl Est. cost in
W/S Particulars
No Lakhs
Shifting of existing 300mm dia MS line & specials for
1 improving water supply to I, II,III main Seshadripuram Rs. 63.80
& surrounding areas under K.P S/Stn
Total Rs. 63.80

Work To be Taken Up
Sl Est. cost in
W/S particulars
No Lakhs
Laying of 100 mm dia DI line in place of 3” dia
Corroded line for new W/S connection to Anjaneye
1 Rs. 15.85
temple I & II street & II main Seshadripuram coming
under K.P.S/Stn
Total Rs. 15.85
Grand Total RS.79.65

GANDHINAGAR CONSTITUENCY

Work Under Progress

Sl UGD particulars Est. cost in


No Lakhs
work of P/L 225mm dia SW line in place of 6" dia SW line at
1. Muneshwara Block, Ramakrishna Block, Nagappa Block, Putta Rs.19.75
Nagamma L/O, coming under Kumara Park S/Station.
Total Rs.19.75

Work Completed

Sl UGD particulars Est. cost in


No Lakhs
work of replacement of 6" dia SW line by 9" dia SW line from
1. 5th Cross to Sampige Talkies along Mr. Raghupathi House, Rs. 5.30
coming under Malleswaram S/Station.
Total Rs.5.30
Grand Total Rs.25.05

STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS


DURING THE YEAR 2009-2010.
GANDHINAGAR CONSTITUENCY

Sl.
Name of the work Amount
No.
1 Estimate for the work of providing & laying 100 mm dia DI line to 3.00
improve water supply line at 3rd Cross, Velumuruganpura under CLB
S/stn.,
2 Estimate for the work of replacement of 110 mm dia 3” dia corroded 18.00
line by 100 mm dia water supply line at 6th, 7th & 1st to 5th Cross upto
Sirur & 8th to 15th Cross 8th Main Ward No. 6 & 7 under Malleshwaram
S/stn., under Gandhinagar constituency.
3 Estimate for the work of providing & laying 150 mm dia & 100 mm dia 3.20
MS pipeline to shifting the existing system supplying water to
table-1
Gandhinagar and surrounding area Opp. DIG (Prisons) office on
Seshadri road under LLR S/stn.,
4 Estimate for the work of replacement of corroded 3” dia CI line by 4” 5.00
dia DI line at 2nd Main to 3rd Main along with 4th Cross, R.C.Puram,
linking of 100 mm dia DI line at 1st Cross, 2nd Main, RC Puram comes
under BP S/stn.,
5 Work of replacement of corroded 3” dia CI line by 4” dia DI line at 1st, 6.00
2nd & 3rd Cross Bhashyam Nagar, under Bhashyam Park S/stn.,
6 Work of replacement of corroded 3” dia CI line by 4” dia DI line at 3rd, 5.40
4th & 5th Cross Dayananda nagar & P/L of 4” dia DI line 11th Cross,
L.N.Puram comes under B.P S/stn.,
7 Work of P/L 100 mm dia DI line to improve water supply line at 3rd 1.94
Cross, Velumuruganapura under CLB S/stn.
8 Work of P/L 9” dia SW line at 5th Cross, Vivekananda Colony, 1st Main
2.50
Road, Railway line coming under Bhashyam Park S/stn.,
9 Work of P/L 9” dia SW line in place of silted up 6” dia SW line at OTC
Road Cross, Park road & surrounding areas & reconstruction of 8.00
damaged manholes coming under CLB S/stn.,
10 Work of P/L 9” dia SW line inplace of silted up 6” dia SW line at SDM
lane & Sultanpet Cross & Sultanpet Cross & surrounding areas & 5.00
reconstruction of damaged manholes coming under CLB S/stn.,
11 Work of P/L 9” dia SW line inplace of silted up 6” dia SW line at
Kurubarapet, Veerabhadranayaka Galli and surrounding area & 20.00
reconstruction of damaged manholes coming under CLB S/stn.,
12 Work of P/L 9” dia SW line inplace of silted up 6” dia SW line at Mill
6.00
Road & reconstruction of damaged manholes coming under CLB S/stn.,
13 Work of P/L 9” dia SW line in place of silted up 6” dia SW line at
Akkipet Cross, S.D.Lane, Manvarthpet & surrounding area &
4.00
reconstruction of damaged manholes under CLB S/stn.,

14 Work of providing and laying 9” dia SW pipeline inplace of 6” dia SW 0.96


pipeline at # 20, G main road, Muneshwara block (Maramma temple)
and reconstruction of damaged manholes coming under Kumara Park
S/s premises.
15 Work of providing and laying 9” dia SW pipeline inplace of 6” dia 0.97
SW pipeline at # 22, 7th cross road pipeline, Muneshwara block and
reconstruction of damaged manholes coming under Kumara Park S/s
premises.
16 Work of 9” dia SW line at RC puram 1st Main road, behind Maramma 0.96
temple coming under Bashyam Park S/stn.,
17 Work of providing 9” dia SW line at inplace of damaged 7 silted up 7” 0.96
dia SW line at 1st Main Road, Opp. No. 131, R.C. Puram Roberstson
Block coming under Bashyam Park S/stn.,
18 Work of rectification of 9” dia SW line at No. 16, 1st cross road, 0.81
Hanumanthappa colony (Ambedkar Bhavan) and reconstruction to the
damaged manholes coming under Kumara Park S/s premsises
19 Work of reconstruction of damaged collapsed manholes at CK street, 0.475
Palace Orchard Vyalikaval and P.G Halli surrounding areas coming
under KG Tower S./s premises.
20 Work of rectification of 9” dia SW line at No. 35, 1st cross, 0.755
Muneshwara block No. 25, 2nd cross D main Muneshwara block and
reconstruction to the damaged manholes coming under Kumara Park
S/s premises.
21 Work of rectification of 9” dia SW line at 1st main, Anjenaya block 0.975
and 1st cross, Muneshwara block and reconstruction to the damaged
manholes coming under Kumara Park S/s premises
22 Work of rectification of 9” dia SW line at N. 21, BBMP drivers 0.49
platform road, Seshadripuram and reconstruction to the damaged
manholes coming under Kumara Park S/s premises.
23 Work of replacement of 6” dia SW line by 9” dia SW line at E -283, 0.86
R.C Puram, 3rd cross, 3rd main, Brahmapuram, & reconstruction of

table-1
damaged manholes coming under Bhashyam park S/s.
24 Work of replacement of 6” dia SW line by 9” dia SW line at 4th main, 0.656
4th cross, Brahmapuram, Opp House NO. F-51 & reconstruction of
damaged manholes coming under Bhashyam park S/s.
25 Work of replacement of 6” dia SW line by 9” dia SW line at 6th main, 0.844
RGI colony, coming under Bhashyam park S/s.
26 Work of P/L of 9” dia SW line inplace of 6” dia SW ine @ D NO. 12 0.497
‘M’ block, Jakkarayanakere Seshadripuram and reconstruction of
damaged manholes under Kumara Park S/s.
27 Work of rectification of 9” dia SW line at No. 25, 4th cross, 0.498
Muneshwara block and No. 234, Muneshwara block pipeline and
reconstruction of the damaged manholes under Kumara Park S/s.
28 Work of desilting of circular manholes ranging from 1.00 m 2.00 m 0.386
depth of various locations under Kumara Park S/s under AEEN-2 sub
division.
29 Work of providing 9” dia SW line at inplace of damaged & silted up 7”
dia SW line at 1st Main Road, Opp. No. 131, R.C.Puram, Roberstson 0.96
Block coming under Bashyam Park S/stn.,
30 Work of replacement of 6” dia SW line by 9” dia SW line at E-283,
R.C.Puram, 3rd Cross, 3rd Main, Brahmapuram & reconstruction of 0.86
damaged manholes coming under Bhashyam Park S/stn.,
31 Work of replacement of 6” dia SW line by 9” dia SW line at 4th Main,
4th Cross, Brahmapuram Opp. House No. F-51 & reconstruction of 0.65
damaged manholes coming under Bhashyam Park S/stn.,
32 Work of replacement of 6” dia SW line by 9” dia SW line at Robertson
block, 2nd Cross, 1st Kalappa block & Okalipuram Conservancy &
0.95
reconstruction of damaged manholes coming under Bahsyam Park
S/stn.,
33 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 4th
0.96
Cross, Kalappa block comes under B.P. S/stn.,
34 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 7th
0.97
Cross, conservancy 9th Main, S.R.Puram comes under B.P. S/stn.,
35 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 3rd B
Cross, new Kalappa block & 2nd Cross, Pillamma block comes under 0.98
Bhashyam Park S/stn.,
36 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 3rd B
0.99
Cross, New Kalappa block comes under Bhashyam Park S/stn.,
37 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 4th
0.97
Main, 1st Cross, Brahmapura comes under Bhashyam Park S/stn.,
38 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at
0.98
M.R.Lane Parchalla Ankanna lane M.R. Lane cross CLB S/stn.,
39 Work of replacement of damaged silted up 6” dia SW line by 9” dia
SW line at M.R.Lane near Maruthi temple, Police road cross 0.94
Mahavarthpet CLB S/stn.,
40 Work of replacement of 6” dia SW line by 9” dia at Maramma temple
2nd cross, DK Lane & reconstruction of damaged manholes coming 0.60
under CLB S/s
41 Work of replacement of 6” dia SW line by 9” dia at R.T.Street, 27th
cross, Huriopet & reconstruction of damaged manholes coming under 0.70
CLB S/s
42 Work of replacement of 6” dia SW line by 9” dia at Opp. 2B,
D.K.Lane, Opp. Jalaram market & reconstruction of damaged 0.81
manholes coming under CLB S/s
43 Work of replacement of 6” dia SW line by 9” dia at R.T.Street, 2nd
0.67
cross & reconstruction of damaged manholes coming under CLB S/s
44 Work of P/L 9” dia SW line in place of existing 6” dia SW line at
MM Lane , 1st cross MM Lane, 2nd cross & reconstruction of 0.497
damaged manholes coming under CLB S/s
45 Work of P/L 9” dia SW line in place of existing 6” dia SW line at
Munsooria lane Akkipet market & reconstruction of damaged 0.492
manholes coming under CLB S/s
table-1
46 Work of P/L 9” dia SW line in place of existing 6” dia SW line at
Veerbhadra naik lane & reconstruction of damaged manholes 0.497
coming under CLB S/s
47 Work of P/L 9” dia SW line in place of existing 6” dia SW line at
Mill road cross & reconstruction of damaged manholes coming under 0.489
CLB S/s
48 Work of P/L 150 mm dia & 100 mm dia MS pipeline to shifting the 3.20
existing system supplying water to Gandhinagar and surrounding area
Opp. DIG (Prisons) Office on Seshadri Road under LLR S/stn.
49 Work of replacement of corroded 3” dia CI line by 4” dia DI line at 2nd Main 5.00
to 3rd Main along with 4th Cross, R.C.Puram linking of 100 mm dia DI line at
1st Cross, 2nd Main, RC Puram comes under BP S/stn.
50 Work of linking 300x150 mm dia line to improvement of water supply 4.87
facilities to Achepet main road from Avenue road under CLB S/stn.
51 Work of P/L 100 mmd ia water supply line inplace of 3” dia corroded 9.60
line for improvement of water supply at Kurubarapet, Veerabhadra
Nayaka lane coming under CLB S/stn.,
52 Work of providing & linking 100x100 mm dia DI pipe & check valve at 0.31
3rd Cross, Christain Colony to improve water facility coming under BP
S/stn.,
53 Work of providing & linking 150x100 mm dia DI line at 5th Main, Sri 0.98
rampuram near Sunrise Circle to improve water supply to Nagendra
garden comes under BP S/stn.,
54 Work of providing & linking of 100 mm dia CI line along Lakshman 0.36
Rao road, Bangalore.
55 Work of providing & linking of 150x100 mm dia DI line at 5th Main, 0.56
Srirampuram near Harinivas hotel to improve water supply facility too
1st Main, Okalipuram comes under BP S/stn.
56 Work of providing and laying 9” dia SW line inplace of 6” dia SW line 4.95
at 12th A cross, 13th, 14th & 15th cross roads at Magadi road S/s.
57 Work of providing 100 mm dia DI line in place of 110 mm dia PVC 7.13
line to IWSF and deviation of 100 mm dia DI line at Balaji Temple
Road at NTY layout, under Mysore Road S/stn.,
58 Work of linking 100x100 mm dia DI line at 3rd Cross, Gopalapura to 1.344
IWSF to ABCD crosses behind Minerva mill coming under Magadi
Road S/stn.,
59 Work of providing and laying 300 mm dia RCC sub main and 225 mm 10.12
dia SW line in RV layout surroundings coming under Kumarapark S/s.
60 Work of providing and laying 9” dia SW line inplace of 6” dia SW line 0.691
at inbetween link road and Sirur park road, conservancy opp to Nataraj
S/s under Kumarapark S/s.
61 Work of providing and laying 9” dia SW line inplace of 6” dia SW line 0.863
at Ganesh block slum opp to Anuraga Nurshing home Vinayaka circle
under Kumarapark S/s

62 Work of providing and laying 9” dia SW line inplace of 6” dia SW 0.96


pipeline at # 20 G main road, Muneshwra Block ( Maramma Temple)
under Kumara Park S/stn.,
63 Work of providing and laying 9” dia SW line inplace of 6” dia SW 0.97
pipeline at # 22, 7th cross road, Muneshwra Block under Kumara Park
S/stn.,
64 The work of providing and laying 9” dia SW line inpalce of 6” dia SW 0.497
line @ D No. 12 ‘M’ block, Jakkarayanakere Seshadripuram under
Kumara Park Ss/.
65 Work of P/L 9” dia SW line inplace of 6” dia SW line at No. 34 Ganesh 0.982
block, & 1st main, conservancy under Kumara park Ss/.
66 Work of P/L 9” dia SW line inplace of 6” dia SW line at 1st cross, 0.985
Krishnamma block conservancy under Kumarapark S/s.
67 Work of P/L 9” dia SW line inplace of 6” dia SW line at 3rd main, 0.965
Sriramapuram under Kumarapark S/s.
68 Work of P/L 9” dia SW line inplace of 6” dia SW line at 1st main, 0.97
table-1
Sripura under Kumarapark S/s.
69 Work of P/L 9” dia SW line in place of 6” dia SW line at 1st Cross, 0.98
Krishnamma Block, Conservancy under Kumara Park S/stn.,
70 Work of P/L 9” dia SW line in place of 6” dia SW line at 3rd Main 0.96
Road, Srirampuram under Kumarapark S/stn.,
71 Work of P/L 9” dia SW line in place of 6” dia SW line at 1st Main, 0.97
Srirampura under Kumara Park S/stn.,
72 Work of P/L 9” dia SW line in place of 6” dia SW line at in between 0.69
line road and Sirus Park road, conservancy opp. to Nataraj S/stn., under
Kumara Park S/stn.,
73 Work of P/L 9” dia SW line in place of 6” dia SW line at Ganesh Block .086
Slum, Opp. to Anuraga Nursing Home, Vinayaka Circle coming under
Kumara Park S/stn.,
74 Work of replacement of 110 mm dia 3” dia corroded line by 100 mm 18.00
dia water supply line at 6th, 7th & 1st to 5th cross upto Sirur and 8th to
15th cross, 8th main W No. 6 & 7 under Malleshwaram S/s under
Gandhinagar constituency
Total 192.094

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
YESHWANTHAPURA CONSTITUENCY

Sl.
Name of the work Amount
No.
1 Work of providing & laying of 12” dia SW line and construction of new 5.57
manholes at Thanniranahalli, Yeshwanthpura under Yeshwanthapura S/stn.,
2 Work of providing & laying 100 mm dia DI pipeline in place of 3” dia 6.47
corroded pipeline at 6th to 7th Main, 2nd Cross, Subedarapalya under
Yeshwanthapura S/stn.,
3 Work of P/L of 9” dia SW line in place of damaged silted 6” dia SW line 0.9975
@ 7th cross, MSR Nagar coming under BEL Road S/stn.,
4 Work of P/L 225 mm dia SW line in place of 150 mm dia SW line lowering 0.99
& deviation in f/o No. 1670/28, 5th Cross, Sahidanandanagar, 6th Main,
KST S/stn.,
5 Work of P/L 225 mm dia SW line in place of 150 mm dia SW line by 0.99
regarding in f/o No. 2236, near Ganesh Temple 1st Main road KST S/stn.,
area.
6 Work of P/L 225 mm dia SW line in place of 150 mm dia SW line in 0.99
conservancy from 7th Main H.No. 688 to 611, EWS House (connected to 6th
B Main) at KST S/stn.,
7 Work of P/L 225 mm dia SW line in place of 150 mm dia SW line at in f/o 0.98
No. 14, W.No. 12 of Kengeri TMC near Bethedra church in KST S/stn.,
W.No. sub division
8 Work of rectification of existing 9” dia SW line at inside the SWD (Nala) 0.99
in between Dubasipalya and Jnanabharathi BDA layout 1st Block in KST
S/stn., area under W.5 sub divison.
Total 17.9775

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
MAHALAKSHMI LAYOUT CONSTITUENCY

Sl.
Name of the work Amount
No.
1 Work of damaged collapsed manholes at G.G. Palya, Nandini layout and 0.53
surrounding area comes under Nandini layout S/stn.,
2 Work of rectification of 12” dia SW line at Shankaranagar main road, 0.439
Martha Medical D.No. 11 & Deepak Enterprises coming under Nandini
layout S/stn.,
3 Work of rectification of 9” dia SW line at 7th main road, Opp D No-59 0.345
to No. 71 & 74, Jai Maruthinagar coming under Nandini layout S/s.
4 Work of rectification of 9” dia SW line at 7th main road, 4th block, 0.432
Nandini layout and construction of damaged manholes coming under
Nandini layout S/s.
5 Work of rectification of 9” dia SW line at 10th cross, and 8th cross, JC 0.885
nagar under Mahalakshmi layout S/s area of No-2 W sub division
6 Work of replacement of existing 9” dia SW line by 12” dia SW line along 6.70
5th cross, Prakahsnagar and linking to the existing 36” & RCC sub main
Opp Sree Uma Shankar Timber Traders at 3rd main under Rajajinagar S/s.
7 Work of providing and laying with deviation of 9” dia SW line inplace of 3.05
6” dia SW line at 1st A corss 3rd stage, 4th block, Basaveshwarangar under
WCR-II S/s
8 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 33.70
1st to 13th cross, Indiranagar slum, near Modi hospital main road under
WCR-I S/s.
9 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.924
4th main, 1st phase, Manjunathangar under WCR-I S/s.
10 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.812
5th cross, 2nd phase, Manjunathangar under WCR-I S/s.
11 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.918
8th cross, 2nd phase, Manjunathangar under WCR-I S/s.
12 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.859
16th main to 7th main, S.G Halli 3rd stage, 3rd block, B.Nagar under WCR-
I S/s.
13 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.642
H NO. 273/B to 288 9th main, 3rd stage WOC Manjuanthanagar
14 Work of providing house connection at 4th block, 4th cross, 0.495
Guraguntepalya 1st main, 7th cross, Sreekantheshwaranagar 1st cross,
Kanteeravanagar slum near Oil Mill road of Shankaranagar main road,
and exports Syndicate Opp Praseed Film lab under Nandini layout S/s.
15 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.856
2nd block, 2nd cross, infront of H No. 87, (Padmavathi Nilay) Nandini
layout under Peenya S/s.

16 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.767
Vivekanada layout 1st G cross and at 4th main, 1st stage, BEML layout in
F/o Ward office under Kamalanagar S/s.
17 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.706
1st cross, SBI staff colony under Kamalanagar S/s.
18 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.987
KHB colony D No. 58 Krishnandangar Mazeed road under Nandini
layout S/s.
19 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.712
Tulsi house No. 36 & 27, Nandini layout LR 16 & Ramakrishna nagar
Ganesh Temple 1st main road, D No. 257 under Nandini layout S/s.
20 Work of providing and deviation of 9” dia SW line at 1st A cross, 3rd 0.765
stage, 4th block, B.Nagar under WCR-II S/s.
21 Work of replacing 6” dia by 9” dia Sw line at 7th & 8th main JC nagar 3rd 0.886
stage, 4th block, B Nagar under WCR-II S/s.
22 Work of replacement of 6” dia by 9” dia SW line at Sakamma Badavane 0.55
table-1
near SWD and at JC nagar 11th cross, near Dram under NLO S/s.
23 Work of providing and laying 9” dia SW line infront of Mysore Juice 0.94
Factory further extension of Mahalaxmi layout under Mahalaxmi layout
S/s.
24 Work of P/L 9” dia SW line in place of 6” dia SW line at 3rd Cross, 3rd 0.99
Main, VHBCS layout and pipeline road (Kurubarahalli) under WCR-II
S/stn.,
25 Work of P/L 9” dia SW line in place of 6” dia SW line at 11th A Cross, 5th 0.97
& 4th Main, Nagpura W.No. 14 coming under WCR-I S/stn.,
26 Work of P/L of 9” dia SW line in place of 6” dia SW line at 2nd Main 0.69
Sreekanteshwaranagar Opp. H. No. 14/2 coming under NLO S/stn.,
27 Work of P/L 9” dia SW line at Sakamma Badavane, 30th, 31st and 32nd 4.00
Cross coming under Nandini layout S/stn.,
28 Work of P/L 12” dia RCC P/L at 8th Main Road & P/L 9” dia SW line in 2.10
place of exislting 6” dia SW line at 2nd Cross & 7th Main Road,
Basaveshwaranagar, 3rd Stage, 3rd Block (W.No. 19) coming under WCR-
I S/stn., of AEEW-4 sub division.
29 Work of linking and laying of 100 mm dia DI line at 14th cross, JC Nagar 1.42
coming under Mahalaxmi layout S/s.
30 Work of P/L 4” dia water line at Sakamma Badavane 30th, 31st & 32nd 8.25
Crosses coming under Nandini layout S/stn.,
Total 76.32

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2008-2009.
DASARAHALLI CONSTUTUENCY

Work Completed

Sl Est. cost in
W/S particulars
No Lakhs
Work of providing additional 150mm & 100mm dia
1 Rs. 5.30
valve to New CMC wards.
Total Rs. 5.30

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
DASARAHALLI CONSTITUENCY

Sl.
Name of the work Amount
No.
1 Work of P/L 50 mm dia GI pipeline at main road and 63 mm dia PVC 0.993
pipeline at Om Shakthi temple road 1st cross to 4th cross Rajgopalanagar
W.No.24 of Dasarahalli CMC under Peenya S/stn.
2 Work of providing & laying 50 mm dia GI pipeline at Main road and 63 0.988
mm dia PVC pipelien at OM Shakthi temple road 5th cross to 8th cross,
Rajgopalnagar W NO. 24 of Dasarahalli CMC under Peenya S/s
3 Work of providing & laying 63 mm dia PVC pipeline and 50 mm dia GI 0.992
pipe from borewell to the area at Rajagopalnagar W. No. 28 under Peenya
S/stn.,
4 Work of providing & laying 50 mm dia GI pipeline at borewell point to 0.775
Kasturi Badavana Rajagopalnagar W.No. 24 of Dasarahalli CMC under W.
No. 6 sub division.
5 Work of P/L of PVC pipeline 50mm dia GI pipe from borewell point to 0.905
main road near Temple Ramaiah L/o, Ward No.24,Dasarahalli CMC under
Peenya S/s.
6 Work of P/L of PVC pipeline 50mm dia GI pipe from borewell to the area 0.999
at Ramaiah Badavane , 3rd main, Peenya 2nd stage Ward No.24 under
Peenya S/s.
7 Work of providing & laying of PVC pipeline at W.No. 24 63 mm dia PVC 0.991
pipeline 50 mm dia GI pipe from Borewell to the area at Rajagopalanagar
near Maruthinagar, Bangalore under Peenya S/stn.,
8 Work of P/L 63 mm dia PVC pipeline at Kasturi Badavane main road 0.999
Right Side from 1st cross to 8th cross, Rajagopalanagar Ward No.24 of
Dasarahalli CMC coming under Peenya S/stn., of W-6 sub division.
9 Work of P/L 63 mm dia PVC pipeline at Kasturi Badavane main road 0.995
Right Side from 1) 6th & 5th Cross near Ashrama, 2) St. Mary’s School 3)
Backside Ashrama 5th A Cross Swathantrayodharanagar w.no. 31 of
Dasarahalli CMC
10 Work of providing and laying 63 mm dia PVC pipeline and 50 mm dia GI 0.79
pipeline at Hoysalanagar Sunkadakatte W No. 33, Dasarahalli, CMC
coming under Peenya S/s of W-6 sub division.
11 Work of providing and laying 63 mm dia PVC pipeline at W NO. 4 & 8 of 0.497
Dasarahalli CMC coming under AEEN-4 sub division.
12 Work of providing and laying 63 mm dia PVC pipeline at W NO. 8 of 0.48
Dasarahalli CMC coming under AEEN-4 sub division.
13 Work of providing and laying 63 mm dia PVC pipeline at W NO. 7,8,14 & 0.492
16 of Dasarahalli CMC coming under AEEN-4 sub division.
14 Work of providing and laying 63 mm dia PVC pipeline from 1st main to 0.861
2nd cross and 2nd, 3rd main of Goyal nagar Rajareddy layout at W NO. 8
of Dasarahalli CMC coming under AEEN-4 sub division.
15 Work of providing and laying 63 mm dia PVC pipeline at W NO. 6 of 0.871
Dasarahalli CMC coming under AEEN-4 sub division.
16 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 74.70
Jai Bhuvaneshwarinagar under Peeyna S/s.
17 Work of construction of damaged / collapsed manholes at Laxmidevinagar 0.665
Kaverynagar and Peeyna Industrial estate and surrounding areas under
Peenya S/s.
18 Work of P/L 63 mm dia PVC pipeline at 5th, 6th & 7th Main, Rukmininagar, 0.71
Nelagadarahalli Main Road, W.No. 18 under Peenya S/stn.,
Total 88.703

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2008-2009.
YELAHANKA CONSTITUENCY

Work Under Progress


Sl UGD Particulars Est. cost in
No Lakhs
work of Replacement of 6" dia SW line to 9" dia SW line KHB
1. Rs. 23.40
'A' & 'B' Sector Yelahanka.
work P/L 9" dia SW line Slum Board Chikkabomma Sandra at
2 Rs. 3.00
Yelahanka.
Total Rs.26.40

YELAHANKA CONSTITUENCY
Work Completed

Sl UGD particulars Est. cost in


No Lakhs
work of P/L 9" dia SW line in place of 6" dia SW line at H.No.
376 to 394, 623 to 647, 1173 to 1179 & 2265 to 2275 'B' Sector
1. Rs. 13.55
Yelahanka.

Total Rs.13.55
Grand Total Rs.39.95

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
YELAHANKA CONSTITUENCY

Sl.
Name of the work Amount
No.
1 Work of providing and laying of 75 mm dia PVC line inplace of damaged 0.827
pipe PVC pipeline to W No. 4,8,9 Yelahanka, coming under Yelahanka S/s.
2 Work of providing and linking of new borewell at Akshaya Dhaba to 0.941
NLIG 5th phase, W No. 29 of Yelahnka CMC under Yelahanka S/s.
3 Work of providing and linking 63 mm dia PVC line from new borewell to 0.776
existing 63 mm dia PVC lines at I/F of H No. 686, W No. 23, Judicial
Layout coming under Yelahanka S/s.
4 Work of attending water supply leaky joints on 63 mm dia, 90 mm dia 0.495
PVC lines at Ward No. 9,10,11,12 & Sugappa layout of Yelahanka CMC
coming under Yelahanka S/s for the month of March 2009.
5 Work of attending water supply leaky joints on 63 mm dia, 90 mm dia 0.494
PVC lines at Ward No. 5,6,7,8 of Yelahanka CMC coming under
Yelahanka S/s for the month of March 2009.
6 Work of linking of 75 mm dia new borewell at Maheshwaram temple 0.425
w.no. 29 of YNK CMC undler YNK S/stn.,
7 Work of attending water supply leaky joints on 63 mm dia PVC lines at 0.491
Ward NO. 1,2,3,4 of Yelahanka CMC coming under Yelahanka S/s for the
month of March 2009.
8 Work of providing & linking 63 mm dia PVC lines at 4th main, House No. 0.494
1629, Jidicial layout coming under Yelahanka S/s.
9 Work of attending water supply leaky joints on 63 mm dia PVC lines at 0.494
Ward No.28,29,30,31 of Yelahanka CMC coming under Yelahanka S/s for
the month of March-2009
10 Work of attending water supply leaky joints on 63 mm dia PVC lines at 0.49
Ward No.24,25,26, 27 of Yelahanka CMC coming under Yelahanka S/s for
the month of March 2009
11 Work of attending water supply leaky joints on 63 mm dia PVC lines at 0.485
Ward No.15, 21, 22, 23 of Yelahanka CMC coming under Yelahanka S/s
for the month of March 2009
12 Work of providing and laying 75 mm dia PVC pipeline in place of 0.489
damaged PVC pipeline No.920, EWS 2nd Phase,at Ward No. 30 of
Yelahanka CMC coming under Yelahanka S/s for the month of March
2009.
13 Work of providing and linking 63 mm dia PVC pipeline from new existing 0.494
63mm dia PVC lines at I/F of Sri Prabhu Vihara Hotel Road Ward No. 23
of Yelahanka CMC coming under Yelahanka S/s
14 Work of providing and linking 63 mm dia,75mm dia PVC lines at 0.492
Chikkabommasandra Ward No. 24 Ambedkaranagar W. No.25 of
Yelahanka CMC coming under Yelahanka S/s

15 Work of construction of compound wall to the BWSSB premises on 0.984


backside of quarters No. 1 & 2 of AEEN-4 sub division coming under
Yelahanka S/stn.,
16 Work of P/L 9” dia SW line in place of 6” dia SW line at 1st Main Road, 0.975
2nd Cross, Sihe Neru Road, Bommasandra coming under Yelahanka S/stn.,
17 Work of P/L 9” dia SW line in place of 6” dia SW line at H.No. 2549 to 0.955
2552, LIG 3rd Phase coming under Yelahanka S/stn.,
18 Work of P/L 9” dia SW line in place of 6” dia SW line at 707, SFS 4th 0.871
Phase I/F H.No. 453 coming under Yelahanka S/stn.,
19 Work P/L 9” dia SW line in place of 6” dia SW line at 1st Main, 1st Cross, 0.952
Bommasandra coming under Yelahanka S/stn., premises.
20 Work of construction of compound wall to the BWSSB premises on North 0.984
East Corner of AEEN-4 sub division coming under Yelahanka S/stn.,
premises.
21 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.486
Someshwaranagar main road coming under Yelahanka S/s.
table-1
22 Work of providing and laying 90 mm dia PVC pipeline from 1) Ayyappa 0.472
Temple road 2) Burial Ground 3) Surabhi layout main road W No. 10 of
Yelahanka CMC coming under Yelahanka S/s.
23 Work of attending water supply leaky joints on 63 mm dia PVC lines at W 0.488
No. 13, 14, 15 of Yelahanka CMC coming under Yelahanka S/s for the
month of January-2009
24 Work of attending water supply leaky joints on 63 mm dia PVC lines at W 0.483
No. 19, 20, 21 of Yelahanka CMC coming under Yelahanka S/s for the
month of January 2009
25 Work of attending W/s leaky joints on 63mm , 75mm dia PVC lines at 0.47
W.No.18,19,20 & Surabhi L/o of YNK CMC under YNK S/stn.
26 Work of P/L 110mm dia PVC line in place of damaged 110mm dia PVC 0.94
pipeline at W.No.16 from Sapthagiri L/o to Papanna L/I, under YNK S/stn.
27 Work attending W/s leaky joints on 63mm dia PVC lines at 0.491
W.No.13,14,16,17 of YNK CMC under YNK S/stn.
28 Work of P/L 9” dia SW line in place of 6” dia SW line at 1st Main Road, 0.975
2nd Cross, Sihe Neru Road, Bommasandra coming under Yelahanka S/stn.,
29 Work of P/L 9” dia SW line in place of 6” dia SW line at H.No. 2549 to 0.955
2552, LIG 3rd Phase coming under Yelahanka S/stn.,
30 Work of P/L 9” dia SW line in place of 6” dia SW line at 707, SFS 4th 0.871
Phase I/F H.No. 453 coming under Yelahanka S/stn.,
31 Work P/L 9” dia SW line in place of 6” dia SW line at 1st Main, 1st Cross, 0.952
Bommasandra coming under Yelahanka S/stn., premises.
32 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.486
Someshwaranagar main road coming under Yelahanka S/s.
33 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.92
Sanitary Core in f/o H No.1471 to 1463 Conservancy under Yelahanka
S/stn.,
34 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.999
Sanitary Core in f/o H No.1363 Conservancy under Yelahanka S/stn.,
35 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.965
EWS H. No.675 to 696 under Yelahanka S/stn.
36 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 0.95
EWS H.No.707 under Yelahanka S/stn.,
Total 25.511

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2008-2009.
BYATARAYANPURA CONSTITUENCY

Work Completed

Sl Est. cost in
W/S Particulars
No Lakhs
work of providing 150mm dia DI feeder main to
1 Rs. 22.90
Sahakara Nagar from Kodige Halli Main Road.
Total Rs. 22.90

BYATARAYANAPURA CONSTITUENCY

Work Under Progress

Sl UGD particulars Est. cost in


No Lakhs
work of P/L 9" dia SW line in place of 6" dia SW line at BEL
1. Rs. 5.98
layout Vidyaranyapura.
Total Rs. 5.98

BYATARAYANAPURA CONSTITUENCY

Work Completed
Sl UGD particulars Est. cost in
No Lakhs
work of rectification & regarding on 9" dia SW line at No. 1820
1. to 2290 C block Shakaranagar coming under Shakaranagar Rs.0.97
S/Station.
Total Rs.0.97
Grand Total Rs.6.95

STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS


DURING THE YEAR 2009-2010.
BYATARAYANAPURA CONSTITUENCY

Sanction
Sl.
No. & Name of the work Amount
No.
Date
1 95 Estimate for the work of attending water supply leaky 98,000/-
21.5.09 joints on 63 mm dia PVC lines at W No. 1 to 6 of
Yelahanka CMC coming under Vidyaranyapura S/s for
the month of February 2009
2 96 Estimate for the work of attending water supply leaky 99,100/-
21.5.09 joints on 63 mm dia PVC lines at W No. 7 to 12 of
Yelahanka CMC coming under Vidyaranyapura S/s for
the month of February 2009
3 113 Estimate for the work of P/L 75mm dia PVC line in 96,000/-
26.5.09 new borewell to existing 75mm dia PVC line at
W.No.18, Kogilu L/o, under Sahakaranagar S/stn.
Total 2,93,100/-

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2008-2009.
PULAKESHI NAGAR CONSTITUENCY

Work To Be Taken up

Sl Est. cost in
W/S particulars
No Lakhs
work of P/L 100mm dia line to left out portions for linking to Modi
1 Rs.1.00
garden area coming under Jayamahal S/Stn.
Total Rs.1.00

PULLIKESHI NAGAR CONSTITUENCY

Work Under Progress


Sl UGD Particulars Est. cost in
No Lakhs
work of P/L 225mm dia SW line in place of 6" dia SW line at
Atmananda Colony, K.B.Sandra, Hanumanthappa L/O,
Doddamma L/O, Nagamma L/O, Rathan Singh L/O, Bheemanna
Garden, Munivenkatappa Gardeer, Manorayana Palya, Cauvery
1. Rs. 20.00
Nagar, Brundavan L/O, Indrajeet L/o, H.M. L/O, Adrash Nagar,
Gandhi Nagar, S.H. L/O, Ambedkar College Main, Shampura
Village, N.G. L/O, in Sultanpalya area, coming under R.T. Nagar
S/Station.
Total Rs. 20.00

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2008-2009.
PULKESHI NAGAR CONSTITUENCY

Sl Est. cost in
Particulars
No Lakhs
1 Estimate for the work of shilting of 675mm dia PSC/CI line by
600mm dia MS line from Millers road along Bore bank road up to 163.00
Pottery Town coming Frazer town Service station.
2 P/L 100mm dia DI pipeline for inmprovement of water ways supply
facilities to Kasturi Bai Nagar under pillanna garden Service station. 3.20
3 Work of providing & linking 100x100 mm dia water supply linking 0.40
behind ex-counciller ouse, DJ Halli main road, Masjid road and
providing 100 mm dia DI pipe and assest the leakage at 16th Cross,
Jannary road coming under Pillanna Garden S/stn., No. 63 dt:
17.4.09, NO. 66 dt: 18.4.09 and No. 90 dt: 3.5.09.
4 Work of providing & fixing 150x100 mm dia central valve at New 0.88
Bagalur layout, Lingarajpura, Vinayaka temple road Kushanagara,
Vinobhanagar, Modiroad, Gandhinagara coming under No. 4 dt:
1.4.09 & No. 82 dt: 3.5.09 Pillanna garden S/stn.,
5 Work of providing & linking 150x100 mm dia DI line at 4th Cross, 0.57
Basavanagar W.No. 94 coming under Pillanna Garden S/stn.,
6 Work of providing & linking 100x100 mm dia DI line at 0.98
Narasimhaiah layout and Makka Masjid Cross Road W.No. 94
coming under Pillanna Garden S/stn.,
7 Work of providing & fixing contral valve at Arogyamma layout, 0.89
Makka Masjid BM layout, Vinobha nagara, Old & new Bagalur
layout, Lingarajpura, W.No. 94 coming under Pillanna Garden S/stn.,
8 Work of P/L 100 x 100mm dia W/S liking behind Ex-Councillor 0.40
house, DJ Halli main road, Masjid road & providing 100mm dia
DIpipe and arrest the leakage at 16th cross, Tannary road, coming
under Pillanna garden S/s (I.No.63dt.17.4.09 No.66 dt.18.4.09 and
I.No.90 dt.3.5.09)
9 Work of P/L 150 x 100mm dia DI line at 4th cross , Basavanagar 0.57
W.No.94 coming Pillanna garden S/s
10 Work of P/L 100 x 100mm dia DI line at Narasimhaiah L/o and 0.984
Masjid cross road W.No.94 coming under Pillanna Garden S/s
11 Work of linking 100x100 mm dia DI line at 6th Cross, 2nd B Main, 0.67
Gandhinagar under Pillanna Garden S/stn.,
12 Work of linking 100x100 mm dia DI line at 2nd A Main, K.G.Halli 0.62
under Pillanna Garden S/stn.,
13 Work of linking 100x100 mm dia DI line at 3rd Cross, A.K.Colony, 0.72
Sagayapura W.No. 90, Pillanna Garden S/stn.,
14 Work of P/L of 225 mm dia SW line at Idgah Mohall & surroundings 8.10
Bangaragirinagar under Jayanagar S/stn.,

15 Work of P/L of 225 mm dia SW pipeline & construction of new 12.40


manholes in Banagirinagar surrounding & replacement of 150 mm
dia silted up line by 225 mm dia SW pipes in
Banaragirinagarsurrounding coming under Jayamahal S/stn.,
Total 194.384

table-1
STATEMENT SHOWING THE LIST OF WORKS CARRIED OUT UNDER
SARVAGNA NAGAR CONSTITUENCY

Sanction
Sl.
No. & Name of the work Amount
No.
Date
1 83/2.7.09 Work of linking providing control valves, cleaning 3,60,000/-
of pipe at various places for improvement of water
supply facilities under HBR S/stn.,
TOTAL 3,60,000/-

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
SARVAGNANAGARA CONSTITUENCY

Sl
Particulars Amount
No.
1 Estimate for the work of p/l 100 mm dia DI w/s line at
Mutyalamma Temple street, A.K. Colony and surrounding area 7.00
ward-94 under pillanna garden Service station.
2 Estimate for the work of linking, providing control valves,
cleaning of pipe at various places for improvement of w/s 3.60
facilities under HBR Service station.
3 Work of linking 150x150 mm dia pipeline at 80’ Road 2nd block, 0.974
HBR layout under HBR S/stn.,
4 Work of linking 100x100 mm dia water supply line at Chairman 0.99
layout to 2nd ‘C’ Main & Keerthi layout & fixing of valve at
HRBR-3rd Stage under HRBR S/stn.,
5 Work of shifting 300mmd ia valve from buststop Nagavara 0.52
main road to opp K.G.Halli Police station Nagavara main road
under Pillanna garden S/s
6 Work of linking 200 x 100 x 100 at Nehru road & 250 x
150mm dia W/S line at 9th main 1st block, HRBR L/o, under
HRBR S/s 0.97
7 Work of linking 150 x 150mm dia pipeline at 80’ road 2nd
block HBR L/o, under HSR L/o S/s 0.974
8 Work of linking 100 x 100mm dia W/S line at Chairman L/o,
to 2nd C main & Keerthi L/o, & fixing of valve at HRBR –III
stage under HRBR S/s 0.99
9 Work of Proviidng & fixing 150 x 100mm dia control valve at
new bagalur L/o, Lingarajapura, Vinyaka temple road,
Kushanagara, Vinobhanagar, Modi road , Gandhinagara coming
under (I.No.4 dt.1.4.09 & I.No.82 dt.3.5.09) Pillanna garden
S/s 0.883
10 Estimate for the work of P/L 9’ dia SW line in place of 7’ dia 0.49
SW line at Kulappa lane, & D costa Layout, 2nd cross C.C.B.I.
Centre & reconstruction of damaged manholes coming under
Machalibetta S/S
11 Estimate for the work of replacement of 225mm dia SW line by 0.48
300mm dia SW line at 2nd main road, NGEF L/O under OMBR
S/S area coming under OMBR S/S
12 Estimate for the work of P/L 9’ dia SW line at 12th cross, 0.88
Bharathmatha layout, Pillanna garden, under W.No.94, coming
under Pillanna garden S/S
13 Estimate for the work of replacement of 9’ dia SW line inplace 0.98
of existing 6’ dia SW line at 9th main, Pillanna garden 3rd stage,
coming under Pillanna garden S/S
14 Estimate for the work of P/L 9’ dia SW line in place of 6’ dia 0.99
SW line at 3rd stage, KEB office & reconstruction of damaged
manholes coming under Pillanna Garden S/S
15 Estimate for the work of P/L & linking of 225mm dia SW line at 0.96
3rd main cross road & 3rd main of OMBR Layout under OMBR
S/S
16 Estimate for the work of removing 9’ dia SW line & laying 12’ 0.97
dia SW line at 6th cross, Old Mill road under HRBR Layout S/S
17 Estimate for the work of removing 9’ dia SW line & laying 12’ 0.99
dia SW line at Aravanda nagar cross road under HRBR L/O S/S
18 Estimate for the work of removing 6’ dia SW line & laying 0.98
225mm dia SW line at 80 ft road, 2nd Block, HBR Layout under
HBR L/O S/S
19 Estimate for the work of P/L & linking of 225mm dia SW line at 0.99
service road, Near BDA Park under HRBR S/S

table-1
20 Estimate for the work of replacing 9’ dia SW line by 12’ dia SW 0.99
line at 5th cross, K.M.Nagar, K.G.Halli coming under P.G S/S
21 Estimate for the work of replacing 9” dia SW line by 12” dia SW 0.97
line Harifa Mazid road K.G.road coming under P.G. S/S
22 Work of P/L & linking of 225 mm dia SW line at 4th Cross, 5th 0.992
Main, 4th Block & backi side road, Petrol bunk 3rd block, HBR
layout under HBR S/stn.,
23 Work of removing & laying 225 mm dia SW line at 0.864
Nandhinagar 2nd B Main under Pillanna Garden S/stn.,
24 Work of removing & laying 9” dia SW line at Bilal Nagar 2nd 0.70
Cross, K.G.Halli under Pillanna Garden S/stn.,
25 Work of removing 6” dia by laying 9” dia SW line at 2nd Main, 0.9975
Pillanna Garden 1st Stage under Pillanna Garden S/stn.,
26 Estimate for the work of P/L & linking of 225mm dia SW line at 0.99
5th A cross, 2nd Block, HRBR Layout under HRBR S/S
27 Estimate for the work of P/L 9’ dia SW line in place of 6” dia 0.90
SW line at Smadhana nagar, 2nd cross K.G.Halli construction of
new manholes and reconstruction of damaged manholes coming
under P.G. S/S
Total 33.0145

table-1
Jayamahal Constituency wise statement

Sl
Particulars Amount
No.
1 Estimate for the work of raising & reconstruction of 0.71
damaged/collapsed manholes at Muddamma garden, Chinnappa
garden St John’s Church road, Byadarahalli, Benson town &
surrounding area coming under F.T. S/S

Shanthinagara Constituency wise statement

Sl
Particulars Amount
No.
1 Estimate for the work of P/L 9” dia SW line inplace of 6’ dia 0.87
SW line at 2nd cross, 2nd main., Mottappa palya & reconstruction
of damaged manholes coming under Indiranagar S/S

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2008-2009.
RAJARAJESHWARI NAGAR CONSTITUENCY

Work Completed
Sl Est. cost in
W/S particulars
No Lakhs
work of providing and laying 4" dia. DI pipe line by
1 replacing the damage corroded 3" dia. C.I. pipeline at Rs.3.42
B.K. Nagar Ist Main coming under YPR S/Station.
Total Rs.3.42

RAJARAJESHWARINAGAR CONSTITUENCY

Work Completed
Sl UGD particulars Est. cost in
No Lakhs
work of replacing of 6" dia SW line by 9" dia SW line P/L at
1. Rs.4.25
L.N. Colony & Model colony of Yeshwantapura S/Station.
work of replacing of 6" dia SW line by 9" dia SW line at
Mariyappanapalya coming under Srirampuram S/Station. Rs.4.32

Total Rs.8.57

Work To Be Taken up

Sl UGD particulars Est. cost in


No Lakhs
work providing and laying of 9" dia SW line in place of 6" dia
1. SW line at Opp to 6th Cross, 16th Main, HMT L/o, coming under Rs.0.98
YPR S/Stn. (Ward No. 03)
work providing and laying of 9" dia SW line in place of 6" dia
2 SW line at 2nd Main Road, LIC Colony near BMP Park, coming Rs. 0.95
under YPR S/Stn. (Ward No. 03)
work providing and laying of 9" dia SW line in place of 6" dia
3 SW line at Opp to NMS Land mark, 6th Cross, HMT L/o, coming Rs. 0.90
under YPR S/Stn.
work providing and laying of 9" dia SW line in place of 6" dia
4 SW line at BBMP maternity hospital, 1st Cross, Model Colony, Rs. 0.90
coming under YPR S/Stn. Ward No. 03.
work providing and laying of 9" dia SW line in place of 6" dia
5 Rs. 0.80
SW line at Gokula Fly over, coming under YPR S/Stn.
work providing and laying 9" dia SW line at Samudhaya
6 Rs. 0.96
Bhavan, Peenya 4th Block, coming under Bahubalinagar S/Stn.
table-1
Total Rs.5.49
Grand Total Rs.14.06

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
R.R.NAGAR CONSTITUENCY

Sl.
Name of the work Amount
No.
Work of providing and laying 225 mm dia SW line inplace of old / 2.55
1 damaged 150 mm dia SW line at 12th A cross, and 17th main road, Ideal
Homes Society in Ideal Homes S/s.
Work of providing and laying 225 mm dia SW line to newly formed 16.80
2
roads at Krishnandanagar of Malagala under RR Nagar S/s.
Work of providing and laying 225 mm dia SW line of Jnanaganganagar 27.40
3
unde RRNagar CMC of W-5 sub div
Work of providing and laying 225 mm dia SW line at 14.85
4 Annapoorneshwarinagar, Rajarajeshwari Co-operative society
Chandrashekar layout, Chandana Badavane under Nagarabhavi S/s.
Work of providing and laying 9” dia SW line inplace of 6” dia SW line 0.736
5 at 8th main, 2nd block, and 1st main, Holly Mother Convent No. 55/A,
3rd cross, Nandini layout under Nandini layout S/s.
Work of P/L 225 mm dia SW pipe line to PUGDF to the Guragunte 4.25
6
palya Slum comels under Nandini layout S/stn.,
Work of P/L 300 mm dia RCC NP3 class pipeline at back side of 4.67
7 wackhard Hospital (NGEF layout) 12th Cross, 9th Block and at 5th Cross
Pattegarapalya under Nagarabhavi S/stn., of W.5 sub division.
Work of construction of 1000000 ltrs of sump at Laxmidevinagar slum 37.40
8
near OHT Nandini layout under Peenya S/s.
Work of P/L 150 mm dia DI line at ESI hospital to Peenya Village 11.23
9
comes under Peenya S/stn.,
Work of P/L 9” dia SW line inpalce of 6” dia SW line at 6th Cross, 0.957
10
Iyyappa Nagar under Bahubalinagar S/stn.,
Work of P/L 9” dia SW line in place of 6” dia SW line at Opp. No. 2/1, 0.56
11
5/10, 12/615 under Nandini layout S/stn.,
Total 121.403

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
VIJAYANAGAR CONSTITUENCY

Sl.
Name of the work Amount
No.
1 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 11.70
Vijayanagar 9th main to 13th main in between Vijayanagar Chord road
Service road and 5th cross road under Hoshalli S/s.
2 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 12.00
Vijayanagar 2nd to 6th main in between 4th cross to pipeline main road under
Hosahalli S/s.
3 Work of providing and laying 9” dia SW line at conservancy road behind 1.00
Thirumala Bar, Kamashipalya bus stop under Vijaynagar OHT S/s.
4 Work of providing and laying 150 mm dia DI feeder main to improvement 10.80
the water supply to 6th to 8th main road, Vijaynagar comes under W-1 sub
div
5 Work of providing & laying 100 mm dia CI line inplace of 110 mm dia PVC 3.55
line to improve the water supply facilities from Telecom layout junction to 1st
and 2nd cross, Raghavanagar upto Kalyana tiles coming under Mysore road
S/s.
6 Work of providing & laying 457 mm dia MS pipeline from junction of Chord 432.30
road & Mysore road upto Magadi road GLR via Sircy circle along Mysore
road & Binny Mill road coming under AEEW-3 sub division.
7 Work of providing and laying 457 mm dia MS pipeline from junction of 3.82
Chord road and Mysore road upto Magadi road GLR via Sirsi circle along
Mysore road and Binny mill road coming under AEEW-3 sub div
8 Work of providing and laying 9” dia SW line inplace of 6” dia SW line from 40.00
20th main road to 21st main road, MC layout comes under Chandra layout S/s.
9 Work of providing & laying of linking 250 mm dia DI pipeline from 400 mm 12.00
dia F/M to IWSF from 2nd Cross to 7th Cross, Magadi Road (lift side) under
Magadi Road S/stn.,
10 Work of P/L and linking of 150 mm dia DI pipeline fromf 250 mm dia F/M 3.765
to IWSF to 6th Main, 7th Main, & 8th Main, Bhuvaneshwarinagar under
Magadi Road S/stn.,
11 Estimate for the work of Replacing 6” dia SW line with 9” dia SW line at 4.60
Vinobha Badavane, Avalahalli under Nagendra block S/s.
12 Estimate for the work of Shifting water supply lines which are passing 4.77
through UGD line / passing adjacent to UGD lines result in contamination of
water supply at Masti Venkatesh Iyengar road, Conservancy, Siddartha
Badavane, Avalahalli & Raghavendra block, 1st main coming under Mount
joy & Nagendra block S/s.
13 Estimate for the work of providing 9” dia SW line in place of existing 6” dia 0.86
SW line along K.K.Hebbar road, 4th cross, Hanumathanagar coming under
Mount Joy S/S of AEEES-4 S/D
14 Estimate for the work of providing 9’ dia SW line in place of existing 6” dia 0.88
SW line at 7th main, 7th cross, Ramanjaneya road, Hanumanthanagar coming
under Mount Joy S/S of AEES-4 S/D
15 Estimate for the work of replacing 6” dia SW line by 9” dia SW line at 2nd 0.89
cross and 3rd cross, Bhuvaneshwarinagar, Dhobighat, coming under
Nagendra Block, S/S of AEES-4 S/D
16 Estimate for the work of P/L 9” dia SW Line in palce of existing 6” dia 0.49
SW line at Patalamma street, Basavanagudi (Mohammaden block) coming
under MNK S/s area of AEES-4 Sub-Dvn
17 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 1st Cross, 0.80
Adarsha Nagara coming under Chamarajpet S/stn., area of AEES-4 sub
division.
18 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 3rd Main 0.996
Road, Adjacent to 50 feet road BSK 1st Stage, 2nd Block, behind
Mahadeshwara temple & 4th Cross, Avalahalli village, A.K. Colony coming
under Mount Joy S/stn.,
table-1
19 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 6th & 7th 0.76
Cross Muneshwara block coming under Nagendra block S/stn, area of AEES-
4 sub division.
20 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 14th Main 0.994
Road Chikka Devaraya road (Behind Rajiv Gandhi Stadium) Pipeline,
Srinagara coming under Nagendra Block S/stn., area of AEES-4 sub division.
21 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 2nd A Cross, 0.996
Raghavendra Block & Avalahalli Main Road coming under Nagendra Block
S/stn. Area of AEES-4 sub division.
Total 547.971

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2008-2009.
SHIVAJINAGAR CONSTITUENCY

Work Completed
Sl Est. cost in
W/S particulars
No Lakhs
work of Replacement of 100mm dia PVC & 3" dia CI
line by laying 100mm dia DI line at Ist Main, II nd
1 Main, IIIrd Main, Jayamahal, Miller's Road, Nandi Rs. 25.75
durga Extn, IIIrd & Ist Cross, Pemmegowda Road,
Rehamath Nagar, coming under Jayamahal S/Station.
Total Rs. 25.75

SHIVAJI NAGAR CONSTITUENCY

Work Completed
Sl UGD particulars Est. cost in
No Lakhs
work of P/L of 9” dia SW line in place of 6” dia SW line @ opp
1. No72/1 Muniswamappa road & RDMHS coming under Rs.0.98
Jayamahal S/Stn.
work of P/L of 9” dia SW line in place of 6” dia SW line @
2 Opp 57 & 54 Muniswamappa road & RDMHS coming under Rs. 0.99
Jayamahal S/Stn
work of P/L of 224mm dia SW line in place of 6” dia SW line @
3 Pemmegowda road near Burial ground @ Jayamahal coming Rs. 5.92
under Jayamahal S/Stn
work of P/L 9" dia SW line at Chamundipura Block Main Road,
4 Opp to Poona Bakery in place of 6" dia SW line coming under Rs. 0.76
Jayamahal S/Stn.
work of P/L 9" dia SW line at 2,27, 28, 9 ND Road Extn., 6th
5 Cross & RDMH's coming under Jayamahal S/Stn. Rs. 0.76

Total Rs.9.41

Work To Be Taken up

Sl UGD particulars Est. cost in


No Lakhs
work of P/L 450mm dia RCC NP-3 class pipeline in place of
1. existing 9" dia SW pipeline and RCMH in Nandidurga Road, Rs. 10.00
coming under JM S/Station
Total Rs. 10.00
Grand Total Rs.19.41

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
SHIVAJINAGAR CONSTITUENCY

Sl.
Name of the work Amount
No.
1 Estimate for the work of P/L 9’ da SW line in place of 6’ dia SW line at 0.99
Guptha L/O, 1st cross & reconstruction of damaged manholes coming
under Ulsoor S/S
2 Work of P/L 300 mm dia NP3 S & S RCC pipeline from 7th Main,
Vasanthanagar to 2nd Main, Vasanthanagar coming under High Grounds 5.00
S/stn.,
3 Work of P/L 300 mm dia NP3 S & S RCC pipeline inplace of 7” dia SW
7.00
pipeline at Jain temple road coming under HGR S/stn.,
4 Work of P/L 300 mm dia NP3 S & S RCC pipeline inplace of 225 mm
dia SW pipeline at Veera Pillai Street to link sewer line at Kamaraj Road 3.00
coming under HGR S/stn.,
5 Work of P/L 225 mm dia SW pipeline along station road, Shivajinagar
4.00
under HGR s/stn.,
6 Work of P/L 300 mm dia NP3 S & S RCC pipeline inplace of 9” dia SW
line at Narayana Pillai street (Dispensary road to Veera Pillai street) 6.00
coming under Coles Park S/stn.,
7 Work of P/L 300 mm dia NP3 S & S RCC pipeline inplace of 150 mm
6.25
dia & 175 mm dia at Ebrahim Saib street coming under Coles park S/stn.,
8 Work of P/L of 300 mm dia NP3 class S & S RCC pipeline in place of
150 mm dia SW pipeline to link 450 mm dia RCC sewer line at 11.60
commercial street, Shivajinagar under HGR S/stn.,
9 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 1st Main
Road Cross, S.R.nagar, Yelemallige Anandappa Galli & construction of
0.96
new manholes & reconstruction of damaged manholes under Banappa
Park S/stn.,
10 Work of rectification of 9” dia SW line at Lakshmi Slum Street, Johns
0.49
road comes under Coles Park S/stn.,
11 Work f rectification of 9” dia SW line D.No. 158 & 156 Chick Bazar road
0.48
& D.No. 18, Muthyalamma Street comes under HGR S/stn.,
12 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 7th
0.97
Cross, Conservancy 7th Main, S.R.Puram comes under B.P. S/stn.,
13 Work of P/L 300 mm dia RCC line in f/o kings crest, Apartment Millers 2.30
Road near BBMP under Pass bridge under Jayamahal S/stn.,
14 Work P/L 9” dia SW line in place of damaged SW line at 2nd Cross, 6th 0.988
Cross, Arundathinagar backside, Doddanna house to Ramanna House
under Chandra layout S/stn.,
Total 50.028

STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS


DURING THE YEAR 2009-2010.
CHIKKAPET CONSTITUENCY

Sl
Particulars Amount
No.
1 Work of P/L 9” dia SW line inplace of 7” dia SW line at Mosque lane Opp.
2.50
Kalasipalya police station under the jurisdiction of V.V.Puram S/stn.,
2 Work of P/L 300 mm dia SW line inplace of 7” & 9” dia SW line from Sajjan
Rao Road to diagonal road along Burgal Mutt road under the jurisdiction of 4.00
V.V.Puram S/stn.,
3 Work of P/L 12” dia SW line to replace 7” dia SW line from Lalbagh Fort
3.15
Road to Diagonal road along Anjaneya temple street under V.V.Puram S/stn.,
4 Work of lowering & laying 9” dia SW line to replace existing 7” dia SW line
0.99
at Pampa Mahakavi road coming under V.V.Puram S/stn.,
5 Work of P/L 9” dia SW line inplace of 6” dia SW line at Diagonal road Cross, 0.96
table-1
S.B.Road, V.V.Puram under V.V.Puram S/stn.,
6 Work of P/L 9” dia SW line inplace of 6” dia SW line at C.K.C. Garden, 1st
Cross, 1st A Cross & reconstruction of damaged manholes coming under 1.00
Bannappa Park S/stn.,
7 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at behind
Lalbagh Fort Road, conservancy & reconstruction of damaged manholes 0.94
coming under V.V.Puram S/stn.,
8 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at Papaiah
street conservancy Mavalli & reconstruction of damaged manholes coming 0.99
under V.V.Puram S/stn.,
9 Work of raising & reconstruction of damaged manholes at Anjaneya temple
street, KAS lane, Ganigar lane & surrounding areas under Banappa Park 0.97
S/stn.,
10 Estimate for the work of P/L 300mm dia and 225mm dia SW line in place of
6” dia and 7” dia SW line at Khuddur L/O , Jyoti Nursing Someshwarnagar
and R/C DMH’s coming under HBGN Service station. 3.25
11 Estimate for the work of P/L 300mm dia SW line in place of 6”dia and 7”dia
SW line at Dayanada slum, Venkatareddynagar, Jayanagar 1st Block, and R/C
of damaged manholes coming under Hombegowdanagar Service station 6.70
12 Work of replacement of 6” dia SW line by 9” dia SW line at 7th Main, 0.97
Lakkasandra coming under HBGN S/stn.,
13 Work of replacement of 6” dia SW line by 9” dia SW line at st Main, 0.97
Gopalappa layout, Lakkasandra coming under HGBN S/stn.,
14 Work of replacement of 6” dia SW line by 9” dia SW line at 1st Cross, 0.97
Chinnayya palya coming under HBGN S/stn.,
15 Work of replacement of 6” dia SW line by 9” dia SW line at 11th Cross & 17th 0.97
Cross, Wilson Garden coming under HGBN S/stn.,
16 Work of replacement of 6” dia SW line by 9” dia SW line at 8th Cross, 0.97
Someshwaranagar coming under HBGN S/stn.,

17 Work of replacement of 6” dia by 9” dia SW line at 9th Main, to 15th Cross, 0.90
Wilson Garden coming under HBGN S/stn.,
18 Work of replacement of 6” dia by 9” dia SW line by 12” dia SW line at Opp. 0.93
To Chowdeshwari temple, Lakkasandra coming under HBGN S/stn.,
19 Estimate for the work of replacing 6” dia SW line by 9” dia SW line which is 2.57
running by the side of 4” dia Water supply line at 14th cross, Shastrinagar main
road , BSK 2nd stage under Devagiri S/s.
20 Estimate for the work of Shifting Water supply lines which are passing 12.47
through UGD Manhole adjacent to UGD lines result in contamination of water
supply at 3rd cross, Byrappa block, 14th cross, Shastrinagar & Shasatrinagar 2nd
cross coming under MNK Park S/s.
21 Estimate for the work of P/L 250mm dia CI pipe line crossing & construction 0.39
of 1.2 mm dia manholes and reconstruction of damaged manholes behind H.B.
Samaja conservancy coming under MNK Park S/S
22 Estimate for the work of P/L 9” dia SW line & 10” dia CI pipe line for drain 0.93
crossing and construction of 1.2mm dia manholes & reconstruction of
damaged manholes to avoid flow of sewage inside SWD at behind Vidyarthi
Bhavan Gandhi Bazar coming under MNK Park S/S of AEES-4 S/D
23 Estimate for the work of P/L 9” dia SW line & construction of manholes at 1st 0.99
cross, Guptha layout, near Sunana college coming under MNK Park S/S
24 Estimate for the work of P/L 9” dia SW line & construction of manholes at 2nd 0.98
cross, Guptha layout coming under MNK Park S/S
25 Estimate for the work of replacement of 6” dia SW line by 9” dia SW line 0.985
at No.40, L.Reddy main Kamila apartment No.36 & 35 Kavery L/o,
W.No.66, B’lore-29 coming under BTM L/o S/s
Total 51.445

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
C.V.RAMAN NAGAR CONSTITUENCY
Sl
Particulars Amount
No.
1 Estimate for the work of P/L 225mm dia SW line at temple road Krishnaiah 1.50
Palya & reconstruction of new manholes coming under Sadanandanagar S/s of
E-5 S/d
2 Estimate for the work of P/L 9” dia SW line in place of 6” dia SW line at 0.85
Annayappa garden, Opp MLA office road & reconstruction of damaged manholes
under JBN S/S
3 Estimate for the work of P/L 9” dia SW line in place of 6” dia SW line at 5th cross, 0.86
Old Binnamangala, Indiranagar, 1st stage & reconstruction of damaged manholes
coming under HAL 2nd stage S/S
4 Estimate for the work of replacing 9’ dia SW line in place of existing 6’ dia SW 0.84
line at 6th main, Opp to LIC Building, HAL 3rd stage & Puttappa Matta road, 1st
cross coming under JBN S/S
5 Estimate for the work of replacement of 6’ dia SW line by 9’ dia SW line at 4th & 0.49
3rd cross, Channasandra village, under OMBR S/S area coming under OMBR S/S
6 Estimate for the work of replacement of 6’ dia SW line by 9’ dia SW line at 3rd 0.85
cross, Channasandra village, under OMBR area coming under OMBR S/S
7 Estimate for the work of P/L 9’ dia SW line in place of 6’ dia SW line at Murphy 0.98
Town, near ward office (W.No.82) & reconstruction of damaged manholes
coming under Ulsoor S/S
8 Estimate for the work of P/L 9’ dia SW line in place of 6’ dia SW line at Kullappa 0.92
colony, 5th cross & reconstruction of damaged manholes coming under JBN S/S
9 Estimate for the work of P/L 9’ dia SW line in place of 6’ dia SW line at 7th cross, 0.95
JBN & 3rd cross, Kullappa colony, & reconstruction of damaged manholes coming
under JBN S/S
10 Estimate for the work of P/L 9’ dia SW line in place of 6’ dia SW line at 2nd main, 0.99
Thippasandra, BGR Lane, G 4th cross & reconstruction of damaged manholes
coming under JBN S/S
11 Estimate for the work of replacement of 6’ dia SW line by 9’ dia SW ine at 0.96
Shivalinga colony, 3rd cross, 4th cross, 5th cross & reconstruction of damaged
manholes coming under JBN S/S
12 Estimate for the work of P/L & linking of 225mm dia SW line from 6th A cross to 0.99
Old Channasandra road & Sapthagiri Tent Road, Banaswadi village, under OMBR
S/S
13 Estimate for the work of providing & laying of 225mm dia SW P/L with
construction of new manholes at 2nd A cross near Motappa compound 0.435
Byrasandra under Bhuvaneshwarinagar S/s under E-4 Sub-Dvn
14 Estimate for the work of shilting of 675mm dia PSC/CI line by 700mm dia MS
line from Manipal Center up to Aero engine along Ulsoor main road old Madras
road etc., coming under Ulsoor Service station. 270.00
Total 281.615

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
PADMANABHA NAGAR CONSTITUENCY
Sl
Particulars Amount
No.
1 Estimate for the work of P/L 9” dia SW line at 10th cross & 9th cross 3.00
Mudamabikanagara & construction of new manholes coming under
Hosakerehalli S/s
2 Estimate for the work of P/L 9” dia SW line at Anjaneya nagar adjacent to 3.00
BDA L/o, Ittamadu under Hosakerehalli S/s
3 P/L 9” dia SW line in place of 6” dia SW line at AG’s L/o, 17th main road, 2.36
PP Layout coming PP Layout S/s
4 Estimate for the work of P/L 400/450mm dia sewer line from 45.90
Sharadanagar near Sathyan Kunte & linking to truck sewer main at Vasantha
Kalyana Mantapa near Saibaba temple Opp. to Vasanthapura main road
5 Estimate for the work of P/L 225mm dia SW line by 300mm dia NP3 class 27.60
S & S pipe linking to sub main at near storm water drain Chikkalasandra
main road, Padmanabhanagar to avoid the disposal at sewage in open drain
at Gumaiah L/o
6 Estimate for the work of replacing 6” dia SW line by 9” dia SW lien which is 3.56
running by the side of 12” dia Feeder main & 4” dia Water supply line at Ring
road, Bhava ninagar under Devagiri S/s.
7 Estimate for the work of P/L 9” dia SW lien & 12” dia SW line to avoid flow 4.45
of sewage in storm water drain at Dobhighat 23rd main, BSK 2nd stage under
Devagiri S/s.
8 Estimate for the work of Rectification of 9” dia SW line at Hari colony to 0.74
avoid contamination of water due to stagnation of sewage.
9 Estimate for the work of P/L 9”dia SW line at 10th Cross and 9th Cross
Moodambikanagar and Construction of new manholes coming under 3.00
Hosakerihalli Service station.
10 Estimate for the work of P/L 9” dia SW line at Anjaneya Nagar adjacent to
BDA L/O, Ittamadu under Hosakerihalli Service station. 3.00
11 PIL 9” dia SW line inplace of 6” dia SW line at AG’s L/O 17th main road, PP
L/O coming under PP L/o Service station. 2.36
12 Estimate for the work of P/L 400/450mm dia sewer line from Shnadanagar
near Sathyane Kunte and linking to truck sewer main at vasantha kalyana
matapa near Saibaba temple Opp to Vasantapura main road. 50.00
13 Estimate for the work of P/L 9” dia SW line at 4th & 5th cross, 8th main, Guraj 0.98
Layout, BSK 3rd stage & Shivaramakaranth road near BMTC Bus stop
Chikkalasandra coming under BSK S/S of AEES-2 S/D
14 Estimate for the work of P/L and linking 9” dia SW line at 7th main, 5th Block, 0.99
BSK 3rd stage, & 8th main, Ittamadu coming under Hosakerehalli, S/S
15 Estimate for the work of P/L & linking 9” dia SW line at 1st cross, 1st main, 0.84
Sharadamma Garden, Kanka Layout under BSK-I S/S

16 Estimate for the work of P/L & linking 9” dia SW line at Maruthinagar Slum, 0.95
2nd main & 3rd cross, Anganvadi School road, Maruthinagar Slum coming
under Hosakerehalli S/S
17 Estimate for the work of providing 9” dia SW pipe line Opp to H.No.39, Near 0.83
Ganapathi Engineering works Hanumagiri Layout, Chikkalasandra under
BSK-2 S/S
18 Estimate for the work of P/L 9” dia SW pipe line at Om Shakthi Temple road 0.75
Opp to H.No.01, Hanumagiri Layout, Chikkalasandra under BSK-II S/S
19 Estimate for the work of replacing 6” dia by 9” dia SW lie at 12th main & 13th 0.86
main, Kalappa Block, Sreenagar coming under Nagendra Block, S/S of AEES-
4 S/D
20 Work of replacing 6” dia by 9” dia SW line at 9th Main, Kumarswamy layout 0.755
1st Stage coming under K.S.Layout S/stn.,
21 Work of construction of new manholes at 2nd Main Road, Vinobha nagar, 0.461
K.G.Halli coming under Pillanna Garden S/stn.,
22 Work of replacement of existing 9”dia SW line by 12” dia SW line at premises 0.99
table-1
No. 215 upto the premises No. 95, 4th Main, 8th Cross of JHBCS coming under
BSK-I S/stn.,
23 Estimate for the work of replacement of 100mm dia DI PVC w/s line by
100mm dia DI w/s line at 50ft road (Vyasaraya Ballal road) Kumarswamy L/o 73.60
under Kumarswamy L/o Service station.
24 Estimate for the work of PIL 100mm dia DI distribution w/s line Intrent of
H.no.64/3, opp to Komarla Bridge Apartment on Aubramanyapura main road, 1.45
chikkalasandra under BSK Service station.
25 Estimate for the tender work of plinking 100mm dia DI line from existing
100mm dia DI line linking to existing village panchayat water tank through
Bulk meter water supply facilities to uttarahalli village under PP L/o Service 5.00
station.
26 Estimate for the work of PIL 150mm dia feeder main branching from 300mm
dia feeder main at Anjeneyanagar & 100mm dia DI distribution line at Ravi
hills, Anjeneyanagar BDA L/o Ittamadu coming under Hosakerihalli Service 10.00
station.
27 Estimate for the work at 110mm dia PVC line by 100mm dia & DI pipeline
from 50ft road to 14th & 15th Cross to 25th Cross, 1st Stage, Kumarswamy L/o 45.00
Service station.
28 Estimate for the work of replacing 110mm dia PVC line by 100mm dia DI
pipeline from 50ft road to 6th main & 7th Cross to 11th Cross Opp D.S.Hospital
road 1st stage Kumarswamy coming under Kumarswamy L/o Service station. 45.00
29 Estimate for the work of replacement of 110mm dia PVC line by 100mm 22.00
doa DI P/L from 58th cross to 8th mian & 8th cross to 13th cross 2nd stage
Kumaraswamy L/o coming Kumaraswamy L/o S/s
30 Estimate for the work of replacing of 100mm dia PVC water supply line by 15.00
100mm dia DI distribution W/S at 11th main, 13th main near Arogya Kendra,
Kumaraswamy L/o, 1st stage, Kumaraswamy l/o S/s

31 Estimate for the work of replacing of 100mm dia PVC water supply line by 16.00
100mm dia DI distribution W/S at 1st main, 7th main, (Sunnadagudu),
Kumaraswamy L/o, 1st stage, Kumaraswamy l/o S/s
32 Estimate for the work of replacement of 110mm dia PVC line by laying 25.00
100, 150mm dia W/S line at Hanumanthanagara shifted slums at
Chandranagara P/L road 2nd stage, Kumaraswamy L/o coming
Kumaraswamy L/o S/s
33 Re-Sanctioning the estimate for the work of P/L 100mm dia W/S line at 3.50
5th cross, 1st stage, KS Layout & 67th cross, 2nd stage, KS Layout coming
under Kumaraswamy L/o S/s
34 Work of P/L 100 mm dia DI water supply near H.No. 2397/38, 18th Main, 2nd 0.74
Stage, KS. Layout under KS S/stn.,
35 Work of P/L 100mm dia DI water supply line near H.No.2397/38, 18th 0.74
main, 2nd stage, K.S.Layout under K.S.Layout S/s
Total 420.406

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
CHAMARAJPET CONSTITUENCY
Sl
Particulars Amount
No.
1 Estimate for the work of Providing 9” dia SW line in place of 6” dia SW line 0.97
at Sirsi circle, Conservancy (between Sirsi road & 1st main, C.Pet ) under
C.Pet S/s.
2 Estimate for the work of Providing 9” dia SW line in place of 6” dia SW line 0.82
at 1st cross, 4th main, Kasturba nagar under C.Pet S/s.
3 Estimate for the work of Providing / shifting 9” dia SW line by 6” dia SW line 1.04
at 3rd main, near South end school, Kasturba nagar & 6th main, Kasturba nagar
under C.Pet S/s.
4 Estimate for the work of Providing / shifting 9” dia SW line by 6” dia SW line 1.05
at 4th & 5th main, 5th cross, behind Venlac hospital , 5th & 4th main,
conservancy under C.Pet S/s.
5 Estimate for the work of Shifting water supply lines which are passing through 7.19
MH’s/ passing adjacent to UGD lines result in contamination of water supply
at 2 ½” & 3” dia CI line with 4” CI line at Fort area , kalasipalya.
6 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 17th Main, 0.997
Srinagara coming under Nagendra Block S/stn.,
7 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 1st Cross, 0.996
Nanjamma agrahara coming under Chamarajpet S/stn., areaof AEEW-4 sub
division.
8 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 2nd Cross, 0.79
Adarsha Nagara coming under Chamarajpet S/stn., area of AEES-4 sub
division.
9 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 16th Main & 0.998
10th Cross junction, Srinagara coming under Nagendra Block S/stn.,
10 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 3rd & 4th 0.9985
Cross, Najamba Agrahara & Baba lane, Mysore road coming under
Chamarajpet S/stn., of AEES-4 sub division.
11 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 2nd Main 0.995
Road, Vittalanagara & 1st Cross, Muneshwara Nagar coming under
Chamarapet S/stn., area of AEES-4 sub division.
12 Work of replacement of 6” dia SW line by 9” dia SW line at L.No. 7th Street, 0.993
K.No. 3rd Street & Periyar koil street coming under CLR S/stn.,
13 Work of P/L 9” dia SW line inplace of 6” dia SW line at 6th Cross, 1st Main, 0.92
Valmikinagar & reconstruction of damaged manholes coming under
Chamarajpet S/stn.,
14 Work of P/L 9” dia SW line inplace of 6” dia SW line at 5th Cross, 2nd Main, 0.81
Valmikinagar & reconstruction of damaged manholes coming under
Chamarajpet S/stn.,

15 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 5th Main, 3rd 0.998
Cross, K.B.Nagar coming under Chamarajpet S/stn. Area of AEES-4 sub
division.
16 Work of P/L 9” dia SW line inplace of 6” dia SW line at Kasturibanagar, 0.79
Valmikinagar, Kalasipalya & reconstruction of damaged manholes coming
under Chamarajpet S/stn.,
17 Estimate for the work of providing and laying of 100mm dia DI line at Bande
slum valmikinagar 3rd main coming under chamarajpet Service station. 2.22
18 Estimate for the work of P/L 150mm dia feeder main tapping from 14.00
300mm dia CI line at 1st cross, 1st main Valmikinagar & 100mm dia missing
line at for 1st main 1st cross, Valmikinagara & Tole gate Mysore road coming
under Chamarajpet S/
19 Work of P/L 100 mm dia DI line to improve water supply line at 3rd Cross, 1.94
Velumurugan Pura comes under CLB s/stn.,
Total 39.5155

table-1
table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
BTM CONSTITUENCY
Sl
Particulars Amount
No.
1 Estimate for the work of replacing damaged 225mm dia SW line at 4th cross, 0.63
Bismillanagar under BTM S/s.
2 Estimate for the work of replacement of 6” dia SW line by 9” dia SW line at 0.97
Opp No.20, 4th cross, 7th B main, BTM 1st stage coming under BTM S/S
3 Estimate for the work of replacement of 6” dia SW line by 9” dia SW line at 0.95
back side conservancy No.11, 19th B cross, N.S.Palya, BTM 2nd stage, coming
under BTM S/S
4 Estimate for the work of P/L 9” dia SW line in place of 6” dia SW line at 2nd 0.90
main, 9th cross, Abbayappa Layout, N.S.Palya under BTM S/S
5 Estimate for the work of P/L 9” dia SW line in place of 6” dia SW line at 1st 0.95
main, MICO Layout, BTM 2nd stage under BTM S/S
6 Estimate for the work of replacement of 6” dia Silted up line by 9” dia SW 0.98
line at Opp No.35/36, 1st main, 3rd cross, New Gurappanapalya, Jhada road
coming under BTM Layout, S/S
7 Estimate for the work of replacement of 6” dia Silted up line by 9” dia SW 0.99
line at Opp No.9/12, 20th main, Maruthinagara, Opp to 20th main,
Maruthinagar at Shivashakthi, Refreshment, 20th main, Maruthinagara,
Madivala & opp to 19th cross, Shanthian Ladies Hostel, coming under BTM
Layout S/S
8 Estimate for the work of replacement of 6” dia silted up line by 9” dia SW line 0.97
at opp No.23, 1st main, 3rd cross, New Gurappanapalya, Jhanda road coming
under BTM Layout S/S
9 Estimate for the work of replacement of 6” dia silted up line by 9” dia SW line 0.99
at Opp No.32, 7th cross, Maruthinagara, Madivala coming under BTM Layout
S/S & construction of damaged manholes at No.6/2, 8th main, 18th cross,
N.S.Palya, BTM 2nd stage, coming under BTM S/S
10 Estimate for the work of replacement of 6” dia silted up line by 9” dia SW line 0.92
at opp No.34, 1st main, 3rd cross, Near Gurappanapalya, Jhanda road coming
under BTM Layout, S/S
11 Estimate for the work of P/L 9” dia SW line at No.3/8, D cross, Bismillanagar, 0.73
BTM 1st stage, under BTM S/S
12 Estimate for the work of replacing of 6” dia SW line by 9” dia SW line at 5th 0.98
cross, Abbayappa L/O, N.S.Palya, BTM 2nd stage, under BTM S/S
13 Estimate for the work of replacing of 6” dia SW line by 9” dia SW line at 4th 0.99
cross, Abbayappa Layout, N.S.Palya, BTM 2nd stage, under BTM S/S
14 Estimate for the work of replacing of 6” dia silted up line by 9” dia SW line at 0.34
opp No.46/3, New Gurappanapalya opp No.48/A, 7th A main, 1st cross, behind
Divya street tower coming under BTM Layout, S/S

15 Estimate for the work of replacing of 6” dia silted up line by 9” dia SW line at 0.86
Opp No.14, New QH, Maddmamma colony, & No.63, 1st main Maddmamma
colony coming under BTM Layout S/S
16 Estimate for the work of replacing of 6” dia silted up line by 9” dia SW line at 0.88
Opp No. C.P.Ramachandra, 31, 3rd cross, 3rd main, Balajinagar, coming under
BTM Layout S/S
17 Estimate for the work of replacing of 6” dia silted up line by 9” dia SW line at 0.66
Opp Madduramma slum, Mask back side, Tavarekere opp No.61, slum board,
Govt under school, Tavarekere opp No.1175, 8th cross, BTM 1st stage, 1st
phase coming under BTM Layout S/S
18 Estimate for the work of replacing of 6” dia silted up line by 9” dia SW line at 0.81
opp No.156, Madduramma colony & opp No.under school Madduramma
slum, Madeena Majid , BTM 1st stage, coming under BTM Layout, S/S
19 Estimate for the work of replacing of 6” dia silted up line by 9” dia SW line by 0.78
9” dia SW line at opp No.147 & 133, Tavarekere Madduramma colony, near
Madeena Majid, coming under BTM L/O, S/S
table-1
20 Estimate for the work of replacing of 6” dia silted up line by 9” dia SW line at 0.94
opp No.Gulab-140 Madduramma colony, Madeena Majid road, Tavarekere &
135, Madduramma colony, Maddena majid road, Tavarekere coming under
BTM Layout, S/S
21 Estimate for the work of replacing of 6” dia silted up line by 9” dia SW line at 0.70
opp No.7, T.D. Davis, 2nd main, 5th cross, Balaji Nagar, B.M.Puttaswamu
shetty, No.65/9, 5th cross Balajinagar, 2nd main road coming under BTM
Layout S/S
22 Estimate for the work of P/L 225mm dia UGD line frm 8th cross to 9th 0.82
cross & linking with existing 300mm dia SW line at 8th cross, JHBCS L/o,
coming under BSK-I S/s
23 Estimate for the work of replacement of 6” dia SW line by 9” dia SW line 0.98
at No.22, Ayappa temple Taverkere main road, # 32, cristain hostel
Shanthidama Kaveri L/o, coming under BTM L/o S/s
24 Estimate for the work of replacement of 6” dia SW line by 9” dia SW line 0.85
at No. 12, Shiva Sai Nivas, Balajinagara, 2nd cross, Near Krishnamurthy L/o,
coming under BTM L/o S/s
25 Estimate for the work of replacement of 6” dia SW line by 9” dia SW line 0.958
at No.58, 3rd cross, masjid road, Bismillanagar B.G. Road, A.K. Entp
coming under BTM L/o S/s
26 Estimate for the work of replacement of 6” dia SW line by 9” dia SW line 0.957
at No.23/18, 6th cross, 1st B main Balajinagar near K.M.Bakery coming under
BTM L/o S/s
27 Work of P/L 9” dia SW line inplace of 6” dia SW line at Petloom pet 3rd 0.83
Cross, Kalasipalya & 6th Cross, Valmikinagar & reconstruction of damaged
manholes coming under Chamarajpet S/stn.,
28 Work of extending 100 mm dia DI pipe line at 3rd Cross, Balajinagar coming 0.65
under BTM layout S/stn.,

29 Estimate for the work of P/L 300mm dia SW pipeline for missing bits in grape
garden L/o 21st Cross, 10th Cross, RA road Ejipura area in ward No.68 of 9.68
BBMP under CLR Service station.
30 Work of replacement of 6”dia SW line by 9” dia SW line at 17th B main , 6th 4.00
Block, KML, Bangalore.
31 Estimate for the work of P/L 225mm dia SW line in place of 6” dia SW line at 2nd
Main Lalaji L/O to 7th Cross, S.R nagar, B.G.Road, and R/c of damaged manholes
coming under Hombegowdanagar Service station 3.56
32 Work of replacement of 6” dia SW line by 9” dia SW line at 2nd & 3rd Main, 0.97
Guptha layout, B.G.Road coming under HBGN S/stn.,
33 Work of replacement of 6” dia by 9” dia SW line at Bande Slum, conservancy 0.96
road coming under HBGN S/stn.,
34 Work of replacement of 6” dia SW line 9” dia SW line at 2nd Main, Nanjappa 0.96
layout, Adugodi coming under HBGN S/stn.,
35 Work of replacement of 6” dia by 9” dia SW line at conservancy road behind 0.92
Kirloskar apartments, Hosur road coming under HBGN S/stn.,
36 Work of replacement of 6” dia by 9” dia SW line at conservancy road, 0.97
Mahalingeshwara Slum, Hosur road coming under HBGN S/stn.,
37 Revised estimate for the work of providing 150mm dia water supply DI line to
improve w/s facilities to Lalajinagar coming under HBGN Service station. 12.10
38 Estimate for the work of P/L 100mm dia DI line for missing bits in grape
garden L/O in 2nd Cross, Ejipura area in ward No.68 of BBMP under CLR 18.00
Service station.
39 Estimate for the work of replacement of old corroded line at Dayanada slum
and providing missing line at 4th A cross, Lalaji nagar and 7th cross SR nagar 8.70
coming HBGN Service station.
40 Estimate for the work of providing 100mm dia water supply line in place of
80mm dia corroded CI line at Chikkalakshmaiah layout and Mahalingeshwara
Badavane coming under HBGN Service station. 6.70
41 Estimate for the work of linking 100 x100mm dia DIpipe to improve W/S 1.82
facilities to Teachers colony, Service road, KML under KML S/s
table-1
42 Estimate for the work of P/L 150mm dia DI W/S line at Basavana temple 8.87
street, Adugodi village main road, AK colony Balayya L/o, Kendriya Sadana
main road, 2nd stage, Koramangala near masjid road coming under KML S/s
43 Estimate for the work of P/L 150mm dia DI line to improve water supply 6.35
from Sri.Rama road to JJ Church road, Aradhana L/o, & Srirama road 1st
cross at Ejipura under CLR S/s
44 Estimate for the work of linking 100 x 100mm dia DJ pipe to improve 3.10
water supply facilities to Siddartha colony KML under KML S/s
Total 111.625

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
RAJAJINAGAR CONSTITUENCY
Sl
Particulars Amount
No.
1 Work of providing and laying 9” dia SW line and construction of manholes at 5.05
Dr. Rajkumar road near Rajajinagar entrance 4th N block, Rajajinagar under
Rajajinagar S/s.
2 Work of providing and laying 9” dia SW line inplace of 6” dia SW line at 3rd 3.00
main road, 56th to 58th cross, 4th B block, Rajajingar under Rajajinagar S/s.
3 Work of replacement of existing old 6” dia SW sewer flines by new 9” dia SW 0.78
pipes at 4th Cross, Prakashnagar and laying of new 9” dia SW line at
Mahalingan House (conservancy) 5th Cross Prakash Nagar under Rajajinagar
S/stn.,
4 Work fo replacement of existing old 6” dia SW line by 9”d ai SW pipes at 5th 0.98
main (Old 5th Cross) Prakashnagar in between 3rd Main up to and Opp. Mohan
Tailors D.No. 189/B under Rajajinagar S/stn.,
5 Work fo replacement of existing old 6” dia SW line by 9”d ai SW pipes at 1) 063
Conservancy back side of BBMP Tailoring Training Centre, 4th N Block,
Rajajinagar & 2) 19th main 1st K Block, Rajajinagar near Akshaya Mini Bazar
under Rajajinagar S/stn.,
6 Work fo replacement of existing old 6” dia SW line by 9”d ai SW pipes at 3rd 0.89
Main, 4th Cross (Old 5th Main 5th Cross) in between Balaji Enterprises, D.No.
54/4A and 4th Cross under Rajajinagar S/stn.,
7 Work fo replacement of existing old 6” dia SW line by 9”d ai SW pipes at 5th 0.96
Main, (Old 5th Cross) Prakashanagar in between 5th Main Opp. Poornima
Clinic to 2nd Main Opp. Akshaya Enterprises & Hamsa Bakery under
Rajajinagar S/stn.,
8 Work fo replacement of existing old 6” dia SW line by 9”d ai SW pipes at 0.83
Opp. to Bhavya House, 3rd Cross, 9th Main, Prakashanagar under Rajajinagar
S/stn.,
9 Work fo replacement of existing old 6” dia SW line by 9”d ai SW pipes at E 0.87
Cross Opp. to Canara Sri Vinayaka Jewellary works & at 1st Main, 9th Cross,
Opp. to Sri Balaji Engg Works Prakashnagar under Rajajinagar S/stn.,
10 Work of deviation, providing & laying 9” dia SW line at near BBMP market, 0.87
11th Main Road to 10th Main Road, 60th Cross, 5th Block, Rajajinagar under
Rajajinagar S/stn.,
11 Work of P/L 300 mm dia RCC pipeline (NP3 class) in place of 175 mm dia 0.73
SW line and raising & damaged manholes at Dr. Rajkumar Road junction 1st
Main road, 36th Cross 2nd Block, Rajajinagar under Rajajinagar S/stn.,
12 Work of providing & laying 100 mm dia DI line at Dr. Rajkumar road, near 5.035
Rajajinagar entrance 4th N block, Rajajinagar under Rajajinagar S.s of W-2 sub
div

13 Work of providing & laying 150 & 100 mm dia line feedermain to IWSF near 28.00
Ramkumar Mills 1st to 5th cross, SSI area 4th block, Rajajinagar under
Rajajinagar S/s.
14 Work of providing & laying 100 mm dia DI line at 20th cross, near Navaranga 2.37
theatre, 17th main to 19th main, 2nd block, Rajajinagar under Rajajinagar S/s.
15 Work of providing & laying 100 mm dia DI line at 7th main road, Siddaramana 8.35
Dinne, 4th block, Rajajiangar coms under Rajajiangar S/s.
Total 121.715

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
GOVINDARAJNAGAR CONSTITUENCY
Sl
Particulars Amount
No.
1 Work of providing and laying 9” dia SW line inpalce of 6” dia SW line at 25.80
Sarvbhoumanagar behind the club area under Chandra layout S/s.
2 Work of providing and laying 9” dia SW line all along the 5th main, 14.30
Nagarabhavi main road under Chandra layout S/s.
3 Work of providing and laying 9” dia SW line inplace of 6” dia SW line from 18.82
9th to 14th cross, MC layout Vijayanagar under Hoshalli S./s
4 Work of providing and laying 9” dia SW line inplace of 6” dia SW line from 8.30
20th main road to 21st main road, MC layout comes under Chandra layout S/s.
5 Work of providing and laying 9” dia Sw line inpalce of 6” dia SW line at old 9.90
Moodalapalya village under W-5 sub div
6 Work of providing and laying 300 mm dia RCC NP3 pipeline from 27.75
Moodalapalya circle to sub main at 1st main, Shivanandanagar and from 4th E
cross, SVG nagar to sub main, Kanakanagar under Nagarabhavi S/s,.
7 Work of providing and laying 9” dia SW line inplace of 6” dia SW line from 23.70
1st to 8th cross road MC layout (Udaya school) under Chandra layout S/s.
8 Work of providing and laying 9” dia SW line inplace of 6” dia SW line from 24.35
Magadi road Housing Board colony under Vijayanagar OHT S/s.
9 Work of providing and laying 400 mm dia RCC NP3 class pipeline inplace of 36.80
300 mm dia / 225 mm dia SW line and 225 mm dia SW line inplace of 150
mm dia SW line at Pipeline mainroad coming under Hoshalli S/s.
10 Work of providing and laying UGD facilities to missing bits at Flower garden 2.50
Mysore road Opp to BHEL W No. 41 coming under CLO S/s.
11 Work of providing and laying UGD facilities to missing bits at conservancy at 4.35
Pantharapalya Mysore road under CLO S/s.
12 Work of providing and laying 9” dia SW line at Venkateshwara layout 1.00
Attiguppe under Chandra layout S/s.
13 Work of providing & laying 100 & 150 mm dia DI pipeline inpalce of existing 16.10
100 mm dia & 150 mm dia PVC pipes at Revanna garden comes under
Chandra layout S/s.
14 Work of replacement of corroded 80 mm dia CI line by laying 100 mm dia DI 31.90
pipes from 9th to 14th cross, MC layout, Vijayangar under Hoshalli S/s.
15 Work of providing & laying 100 mm dia DI pipeline inplace of leaky 80 mm 56.60
dia corroded CI pipe / 110 mm dia PVC lines from 15th to 19th main, MC
layout under W No. 35 of Govindarajanagar constituency of W-1 sub div
16 Work of replacement of corroded 80 mm dia CI line by laying 100 mm dia DI 46.30
pipes from 1st to 8th cross, MC layout Opp Naveen park Vijayangar under
Hosahalli S/s.
17 Work of providing & laying 100 mm dia DI line inplace of 80 mm dia CI 61.80
corroded pipe / 110 mm dia PVC pipe from 20th to 22nd main, MC layout
under Govindarajanagar constituency
18 Work of providing & laying 100 mm dia & 150 mm dia DI line inplace of 110 38.85
mm dia PVC pipe line at Sarvabhomanagar behind club area comes under
CLO S/s.
Total 449.12

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
BASAVANAGUDI CONSTITUENCY
Sl
Particulars Amount
No.
1 P/L of 9” dia SW line in place of 6” dia SW line at 3rd cross, 5th cross, BSK 3rd 0.97
stage, 3rd phase, 3rd Block, & construction of new manholes
2 Estimate for the work of P/L 9” dia SW line in place of fully chocked up 6” 0.96
dia SW line of non gradiented SW line at near Sri Krishna temple road, BSK
3rd stage, 3rd Phase, 4th cross road coming under KTG S/S
3 Estimate for the work of P/L 9” dia SW line in place of damaged 6” dia SW 0.92
line Dattatreyanagar, flag road, coming under BSK S/S
4 Work of Laying of 100mm dia DI pipe in place of fully damaged 90mm dia
PVC pipe at Ramarao area L/o field, BSK 3rd Stage, coming under KTG 3.00
Service station.
5 Work of replacement of laying of 100 mm dia DI pipe at ITI layout dead end 0.89
of Anjaneyaswamy street coming under Kathriguppe S/stn.,
6 Work of replacement of laying of 100mm dia DI pipe at ITI layout dead 0.891
end of Anjaneyaswamy street coming under Kathriguppe S/s
7 Work of P/L 300 mm dia S/S NP3 class spun pipes from 5th Main,
Bhavaninagar, Shanimahathma temple & linking to sub main at Kempambudi
6.00
lake to prevent flow of sewer water into Kempambudi lake under V.V.Puram
S/stn.,
8 Work of P/L 12” dia SW line from Subanna Garden Storm water drain &
linking to sub main at Sameerpura main road to prevent flow sewer water line 6.00
the Kempambudi lake under athe jurisdiction of V.V.Puram S/stn.,
9 Work of P/L 9” dia SW line inplace of existing 6” & 7” dia SW line at
Ranadheera Kanteerava road, Gavipura Guttahalli coming under V.V.Puram 0.99
S/stn.,
10 Work of P/L 9” dia SW line inplace of existing 6”& 7” dia SW line at
0.99
Vidhyarayana road, Gavipura Guttahalli coming under V.V.Puram S/stn.,
11 Work of P/L 9” dia SW line inplace of existing 6”& 7” dia SW line at Echama
1.00
Nayaka road, Gavipura Guttahalli coming under V.V.Puram S/stn.,
12 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at
Chandrashekar Azad Road, Gavipura Guttahalli coming under V.V.Puram 1.00
S/stn.,
13 Work of P/L 9” dia SW line inplace of existing 6”& 7” dia SW at Kithooru
1.00
Rani Channamma Road, Gavipura Guttahalli coming under V.V.Puram S/stn.,
14 Work of P/L 9” dia SW line inplace of existing 6” & 7” dia SW line at
1.00
Kumara road, Gavipura Guttahalli coming under V.V.Puram S/stn.,
15 Work of P/L 9” dia SW line inplace of existing 6” & 7” dia SW line at 10th
0.98
Cross, Laxmipura, Gavipura Guttahalli coming under V.V.Puram S/stn.,
Total 26.591

STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS


DURING THE YEAR 2009-2010.
SHANTHINAGARA CONSTITUENCY

Sl
Particulars Amount
No.
1 Estimate for the work of P/L 9” dia SW line inplace of 6’ dia 0.87
SW line at 2nd cross, 2nd main., Mottappa palya & reconstruction
of damaged manholes coming under Indiranagar S/S
2 Estimate for the work of replacing 225mm dia SW line by
300mm dia SW line on Church road from Brigade road to 15.60
Museum road under CLR Service station
3 Estimate for the work of replacing existing 175 & 225mm dia
SW line by laying 300mm dia SW line at 5th A Cross, 6th Cross,
7th Cross, 9th Cross and 10th Cross roads at Anepalya under 17.00
Johnson market Service station
table-1
4 Estimate for the work of P/L 225mm dia SW line at Bethal L/o, 4.60
(BCC Qts) Berlie street, cross under J/M S/s
5 Estimate for the work of P/L 225mm dia SW line at H street & 3.21
G street, Shanthinagar coming under J/M S/s Shanthinagar
Assembly Constituency.
6 Work of replacing blocked 150 mm dia SW line by 225 mm dia 0.82
SW line at 2nd Main, 7th A cross & 7th B cross, Vinayaka nagar
coming under Johnson market S/stn.,
7 Work of replacement of 6” dia SW line by 9” dia SW line at 5th 0.97
Cross, Rose Garden apartments, Cubra Fancy store coming
under JM S/stn.,
8 Work of replacement of 6” dia SW line by 9” dia SW line at 4th 0.97
Main, Austin Town under JM S/stn,.,
9 Work of replacement of 6” dia SW line by 9” dia SW line at 6th 0.97
A Main, Austin Town, Opp. To B-14 & B-15 BDA Qtrs, Austin
Town coming under JM S/stn.,
10 Work of replacement of 6” dia SW line by 9” dia SW line at 0.97
Bazar street 5th Cross, Neelasandra, Opp. D.No. 26 coming
under JM S/stn.,
11 Work of replacement of 6” dia SW line by 9” dia SW line at 0.98
J.K.Pura Cross Road, Vinayakanagar coming under JM S/stn.,
12 Work of construction of new manholes at M.G.Garden & E 0.98
Street, Neelasandra coming under JM S/stn.,
13 Work of construction of new manholes at 6th Cross & Rose 0.98
Garden & Baniyan Basha road coming under JM S/stn.,
14 Work of construction of new manholes at 2nd Main road, 0.97
Vinayakanagar & JK Pura coming under JM S/stn.,
15 Work of P/L 225 mm dia SW line in place of 150 mm dia SW 0.80
line at NO. 10 & 27, 2nd Main, Bazar street Cross road & R/C of
DMH’s coming under Johnson market S/stn.,
16 Work of P/L 225 mm dia SW line in place of 150 mm dia SW 0.82
line at 1st Main, 7th Cross, D No. 105, Rose Garden & R/C of
DMH’s coming under Johnson Market S/stn.,
17 Work of providing 9” dia SW line in place of existing 6” dia SW 0.99
line at 6th Cross, Rose Garden & R/C of damaged manholes
coming under Johnson Market S/stn.,
18 Estimate for the work of replacing 75mm dia CI line by 100mm
dia DI line w/s at Rest house cresent road to improve w/s at Rest 10.00
house park area under CLR Service station.
19 Estimate for the work of P/L 100mm dia DI line & linking 1.61
200 x 100mm dia DI line at Rangaswamy compound, Basappa
road, SHanthinagar coming under Johnson market S/s
Shnathinagar Assembly constituency
20 Estimate for the work of P/L 150mm dia DI feeder line to 12.00
improve W/S to EWS Qts, Ambedkarnagar, Shanthinagar
coming under Johnson market S/s Shanthinagar Assembly
constituency
21 Work of deviation of 100 mm dia water supply at Barian Basha 0.99
Road, Anepalya main road coming under J.M. S/stn.,
22 Work of deviation of 100 mm dia water supply at JK Pura & 0.98
Vinayaka Nagara Cross Roads coming under J.M. S/stn.,
Total 78.08

table-1
STATEMENT SHOWING THE ESTIMATE SANCTIONED FOR THE WORKS
DURING THE YEAR 2009-2010.
JAYANAGARA CONSTITUENCY

Sl
Particulars Amount
No.
1 Estimate for the work of linking 100mm dia DI line at 4th Cross,
LIC Colony coming under Byrasandra Service station. 4.00
2 Estimate for the tender work of PIL 100mm dia DI w/s line in
place of PVC at 15th Cross, JP Nagar 1st Phase, coming under JP 9.10
Nagar 1st Phase Service station.
3 Estimate for the tender work of PIL 100mm dia & DI w/s line in
place of PVC at 15th Cross JP Nagar 6th Phase, under JP Nagar 10.00
Service station.
4 P/L 9” dia SW line in place of existing 7” dia SW line at
prasiddi fast food veg,26th main road, coming under T Block 3.50
Service station
5 P/L 9” dia SW line in place of existing 7” dia SW line at 16th A
Main road, 36th Cross, 4th T Blocl, coming under T Block 3.50
Service station
6 Estimate for the work of replacing of 7”dia SW line by 250mm
dia HDPE pipe by trenches technology at 10th Main road, 27.00
Jayanagar 3rd Block Bangalore
7 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 0.80
(1) 11th Main, 5th Block, Jayanagar, 2), 11th Main, 38th Cross,5th
Block, Jayanagar (3) East End Main road (4) Thilaknagar
coming under T Block S/stn.,
8 Work of P/L 9” dia SW line inplace of existing 6” dia SW line at 0.79
39th Cross, 11th Main coming under T Block S/stn.,
9 Work of providing 9” dia SW line at 11th A & B Main 5th Cross, 0.85
Jayanagar, 5th Block coming under 4th ‘T’ Block S/stn.,
10 Work of providing 9” dia SW line at various locations of 0.99
Jayanagar, 5th Block, jayanagar coming under T Block S/stn.,
11 Work of providing 9” dia SW line SW line at various locations 0.97
of Marenahlli tank bund 5th Block, Jayanagar coming under T
Block S/stn.,
12 P/L 9” dia SW line at 18th main near Girl apartment 2nd phase, 4.00
JP Nagar under J.P.Nagar S/s
13 Estimate for the work of P/L 12” dia SW line in place of 6” dia 4.05
SW lien at KSRTC L/O , JP Nagar under JP Nagar S/s.
14 Estimate for the work of PIL 9” dia SW line at 18th main near
Giri apartment 2nd Phase, J.P.Nagar under JPN-II Service 4.00
station.
15 Estimate for the work of P/L 9” dia SW line in place of 6” dia 0.87
SW line at the junction of 1st A cross and 1st cross, Marenahalli,
J.P.Nagar 2nd phae, under JPN S/S
16 Estimate for the work of replacement of 6” dia SW line by 9” dia 0.91
SW line at Navodaya Layout, 3rd main, 2nd main, 16th cross, 4th
phase, 4th main, Shakambari Nagar, K.P.Road coming under
J.P.Nagar S/S
17 Estimate for the work of P/L 9” dia SW line at near Anganavadi, 0.90
Kendra, KSRTC L/O, 3rd cross, J.P.Nagar, under J.P.Nagar S/S
18 Estimate for the work of replacing 6” dia by 9” dia SW line at 0.92
No.121, Marenahalli Palya, 2nd phase, J.P.Nagar & KSRTC L/O,
6th main, J.P.Nagar, 2nd phase under J.P.Nagar S/S
19 Estimate for the work of replacing of 6” dia SW line by 9’ dia 0.98
SW line at No.70, 21st A main, Marenahalli, J.P.Nagar 2nd phase,
under J.P.Nagar S/S
20 Estimate for the work of replacing of 6” dia SW line by 9” dia 0.99
SW lineat 8th cross, 18th main, junction J.P.Nagar 2nd phase
under J.P.Nagar S/S

table-1
21 Estimate for the work of replacing of 6” dia SW line by 9” dia 0.99
SW line at the junction of 7th cross, 18th main, 2nd phase,
J.P.Nagar under J.P.Nagar S/S
Total 80.11