ANNEX 6 Management Information System and Monitoring and Evaluation Framework (MIS/M&E)
Background, Issues and Process
Hanoi
June 2003
Table of Contents
1. INTRODUCTION ..................................................................................................................3 2. MONITORING AND EVALUATION .....................................................................................3 2.1 Definitions ........................................................................................................................................ 3 2.2 Setting up the M&E......................................................................................................................... 4 2.3 Indicators ......................................................................................................................................... 5 3. MANAGEMENT INFORMATION SYSTEM .........................................................................7 3.1 Reporting.......................................................................................................................................... 7 Monitoring risk.................................................................................................................................... 7 3.2 Database and data processing ........................................................................................................ 8 3.3 Management system ........................................................................................................................ 8 3.4 Capacity building............................................................................................................................. 8 4. EXPERIENCES IN SIMILAR PROGRAMMES ....................................................................9 5. IMPLICATIONS FOR THE PAP MIS .................................................................................10 5.1 Findings from consultations ......................................................................................................... 10 5.2 System design ................................................................................................................................. 11 5.3 Reporting........................................................................................................................................ 12 5.4 Structure of management ............................................................................................................. 12 5.5 Capacity building........................................................................................................................... 13 6. CONCLUSIONS FOR THE INCEPTION PERIOD.............................................................13
Attachments: Draft Quarterly Report national level Draft Quarterly Report provincial level Monitoring format overall progress -draft Monitoring format provincial level - draft
1. Introduction
Monitoring and Evaluation (M&E) and Management Information Systems (MIS) are concepts that often are used interchangeably to describe how information on the progress of a project is used for follow-up and management. In this section the term M&E is used to define the way that progress information is made available to find out if the programme is implemented as planned and is achieving its objectives. The MIS describes the how the subsequent database is organised, updated and applied for management of the project. This attachment deals first with the general definitions and methods for setting up of monitoring and evaluation, and then describes how the database should be structured and managed. It comments briefly on MIS used in similar programmes in Vietnam, and concludes with specifications that must be observed when the MIS for Chia Se defined and taken into use.
It is very important that the M&E is based on a participatory methodology. The key issues for participation are outlined below:
4 Participation Negotiation All stakeholders participate in selection of indicators and data analysis. Stakeholders negotiate what will be monitored and evaluated, how and when data will be collected and analysed, what the data mean, and how it will be shared and action taken. Participation and negotiation lead to collective learning, ownership and investment in key findings by those most able to use the results for corrective action. As learning improves and may provoke changes in implementation or the strategic approach, which calls for a flexible approach to management and monitoring.
Learning
Flexibility
Planning
Preparation
Design and test any data collection records; Prepare forms for data presentation; Train people who is responsible for monitoring; Produce a manual for monitoring with functional areas and accountability.
Design data collection tools (survey forms, interview guidelines,); Decide how to select the sample; Pretest and revise data collection tools; Train evaluation staff; Make arrangements for evaluation in villages;
Data Collection
Collect the agreed upon information on a routine basis; Monitor the functioning of the system;
Collect and study existing information (reports, proposals,); Select households / sites/ ; Conduct the interviews / observations /; Start data processing.
Compare collected data with agreed indicators, and note differences; Identify any other issues; Look for cause of any problems, and identify options for action.
Tabulate data; Interpret the results and draw conclusions; Decide on recommendations; Check analysis with key informants.
Reporting of Results
Document data and findings; Provide feedback to project management and stakeholders.
Use of Results
2.3 Indicators
Indicators are realistic and measurable criteria of project progress. They must be defined before the project starts, and they allow stakeholders to monitor or evaluate whether the project does what it said it would do. In project planning, indicators form the link between theory and practice. Indicators are either quantitative, qualitative or time-based. Preferably an indicator should express all three aspects, (the expected Quantity, Quality and Time), or simply QQT. . Quantitative Indicators can be expressed as a number. For example, the number of people attending a training, the number of wells constructed, the average rice harvest per hectare, the cost of fertilizer. Qualitative Indicators indicate the quality of something, and they cannot normally be expressed as a number. For example, Womens participation in decision making in the village planning meeting, or improved working relations among staff. Because qualitative indicators are hard to measure directly, it may often be necessary to measure something else instead. For example, instead of measuring improved participation directly, one can look at the number of meetings organised by the village, how many people attended, if there was a women majority in the meeting, what decisions were made, and who made them. This kind of information then gives an idea of the increase in participation in decision-making. (The indicators we measure instead of the qualitative information are then called proxy indicators or indirect indicators). Time-based indicators state when a result is planned to be achieved and aims at revealing if there are any delays in project implementation, which is a signal that there are problems in the implementation of certain activities. Generally speaking, a good indicator is: Relevant, which means it measures an important part of an objective or output; Objective. If two people measure the same indicator using the same tool, they should get the same result. The indicator should be based on fact, rather than feelings or impressions (another way to say this is to say that it should be Measurable); Available. Indicators should be based on data that is readily available, or on data that can be collected with reasonable extra effort as part of the implementation of the (sub-)project. Realistic. It should not be too difficult or too expensive to collect the information (related to the next one in the list); Specific, which means that the measured changes should be attributable to the project, and they should be expressed in precise terms;
6 The Chia Se has been developed in close consultation with stakeholders and analyzed from problems and main constraints to a sustainable livelihood using a logframe format to address the logical relations between activities and outputs leading to poverty alleviation. In the logic of the logframe, inputs are used to implement activities, activities produce specific outputs, the outputs contribute to the project objective, and the project objective contributes to the programme objective. This is shown schematically in the drawing below.
Indicators Program for ObjectivesObjective Indicators are mainly used for evaluation.
Project Indicators Objective Indicators for Outputs are Indicators Outputs mainly used for monitoring. No separate indicators are Activities Inputs set for activities or inputs.
Monitoring tells whether activities are being implemented as planned, and whether the envisaged outputs in terms of establishing LPMD, LDF, effective structures etc are being produced as a result of the activities. This means that the monitoring system should concentrate on the indicators set for outputs. Evaluation tells whether the outputs result in poverty alleviation, and so concentrates more on indicators set at the objective level (although monitoring information is often also input for evaluation as well).
Stage Monitoring
(measures planned outputs against actual outputs)
Type of Indicator Focus on outputs Mostly quantitative, and often available as part of daily work Focus on objectives. Often qualitative, and needs special effort to collect
Sources of data Progress reports Field visits Observation Reports, plans Surveys Observation
Evaluation
(measures effect, or impact)
The table shows that it is important to make a distinction between impact indicators and progress indicators. Impact indicators are used to measure overall impact and effectiveness of the program during occasional evaluations (normally once per year). These indicators will help the management committees to ensure that the project is leading to poverty alleviation, as defined by the impact indicators. Progress indicators are used for the monitoring of implementation, and reported monthly or quarterly in the progress reports. In addition, they serve as input for project evaluations. Progress indicators are defined for outputs only; they are used to ensure that the defined outputs are being
7 reached. Although progress reports include information on activities, no separate indicators are defined for those.
3.1 Reporting
Implementation of activities are normally reported on a recurrent basis (as they happen), whereas consolidated analysis of the pace of project implementation should be done based on quarterly progress reports to the relevant management levels. The annual report summarises achievements in relation to budgets and outputs on an annual bases. It should be complemented with regular annual evaluations of the objectives and/or special evaluations of conditions in the project that needs a closer look. The most fundamental requirement of the reports from the MIS is that is should provide management structures with timely information that the project is performing according to plans and budgets. Having said that, it is of course equally important that the MIS provides information when (parts of) the project is not performing as envisaged as a means to address and review weaknesses in the project implementation framework or in the project strategy. It is important to understand that the MIS (and the logframe it is built on) is not a blueprint for project steering. On the contrary, the MIS must be regarded as an instrument for continuous learning that will provide feed back throughout the whole project period. It should be used for regular updating of both progress and impact indicators as knowledge increases about their accuracy, and the relations between outputs and objectives. It may turn out that these relations are not clear in reality, which then will call for a review in the overall strategy. The MIS expresses the intricate relationship between budgets, activities, outputs and the various progress and impact indicators, and it is highly unlikely, in fact impossible, that the assumptions made at the start of the project as regards these relations would remain the same during implementation. All decisions that will subsequently be taken on changes and adaptations of the logframe is, in fact, the expression of learning. They should be recorded by the management committees so that the learning process can be backtracked and documented. In this respect the information provided to the MIS must clearly indicate the demonstrated performance at the output and objectives level, not intentions or estimations. This will allow the management committee to assess the effectiveness of the project strategy. The information fed back from the MIS and the analysis made of it may provoke the management committee to decide on reallocations that will help increase the overall impact of the project. Reallocations implies that resources are reduced in implementing activities that prove to be less effective (unless external factors impede more negatively than expected see risk below), and likewise that resources are increased areas where demonstrated performance is better than expected and where there is room for expansion or replication of activities or components. It is crucial that this type of flexibility is maintained, particularly in the Chia Se, which is experimental in its strategy and must be totally open for learning at all levels.
Monitoring risk
It is not unusual that evaluation reports find that there is a gap between project outputs and objectives, implying that projects can be assessed to deliver services and goods according to plan, without
8 apparently having an impact at objectives level. For instance, regular evaluations may prove that the poverty situation is not improved even though most of the activities are implemented and most outputs are achieved. In such cases there is either a flaw in the logframe structure between what has been defined as outputs and objectives, or (and more likely) an underestimation of the external factors that may influence the project, negatively or positively. The logframe analysis includes an assessment of external factors and important assumptions, and suggests the way in which they need to be monitored during implementation.
10
2 3
In the following text the term MIS will be used for the compound concepts MIS and M&E This is the case even if the UNCDF generic MIS can be acquired.
11 The computer capacity at provincial government level is weak, but gradually improving through systems development and training. Financial management is done at district level, but accounts are reviewed and reconciled at provincial level.
12
As regards the LDF, the criteria for use of the funds will serve as one type of baseline to be referred to in LDF evaluations. Recorded high fulfilment of criteria is one factor in assessments of possible increases for future resource allocations toLDFs. As regards decentralisation, which is not formulated as an outright objective but as a project strategy, a special research project should be considered focusing on the policy formulation function in the provinces. In a decentralised regime, the policy issues concerning livelihood issues in the province should increasingly be formulated in a bottom up perspective, based on the actual constraints for poverty alleviation. This implies that a baseline needs to be established also in this respect. It would make sense to include this function, and other special studies that may be justified, in the mandate for the Programme Advisory Group.
5.3 Reporting
The following specifications should be followed when the MIS is being developed: Data should be collected and reported on standardised and unified forms. Data should be collected at source and be transferred to and reviewed at the relevant management level (Village Meeting, CPMU, DPMU and PSC); One copy of form should be kept at collection level, and one copy sent to nearest higher level for data aggregation and report compilation - duplication of data collection must be avoided; Computerisation of data should be done at level where there is a suitable IT environment (presently not lower than provincial level, but capacity should be developed at district level to computerise data for better management);
Eventually, when activities at village level are becoming more diversified and complex to follow in a manual system, also the village progress reports will be sent for computerisation. At national level, the Quarterly Progress Reports from each project provincial and national are compiled into the PAP Quarterly Progress Report to be discussed by the Joint Working Group.
13 Each management level has its management agenda, which becomes increasingly more integrated the higher the management level is. Each level has its responsibility and is accountable for project implementation. Overall programme management is the responsibility of the Joint Working Group. Over the programme period the conditions for computerised data processing at lower levels shall be improved.
Set up the MIS to mirror the LFA. This step includes both system specifications and software development. Define baselines for all outputs and objectives. Define progress and impact indicators Define and test all information cards or sheets per activity Develop plan for computerisation and computer resources and organisation Develop Job descriptions for all persons involved in MIS activities Develop a Manual for Programme Management Develop a Manual for Decentralised Project Management Initiate capacity building
A special action and time plan needs to be set up for each project (please refer to the relevant project documents for Quang Tri, Yen Bai, Ha Giang and the national components)