Appendix-A
Page 1 of 6
Sl.No.
Description
Volt. (KV)
Type SC/DC
No. of E/W
Origin
Destination
Nominal Span
Wind Span
Design Tension at Every Day Temp(32 0C) and full wind condition Cond. E/wire (kg) (kg)
1 2 3 4 5 6 7
Vapi 400 Boiser 400 Kolhapur 400 400kV Raigarh s/s Parli 400 Vapi 400 Seoni 765
Boisar 400 Phadge 400 Mapusa 400 400kV Raipur s/s Bhadravati 400 Navi Mumbai 400 Wardha 765
2 2 2 2 2 2 2
32 0C 32 0C 32 0C 32 0C 32 0C 32 0C 32 0C
32 0C 32 0C 32 0C 32 0C 32 0C 32 0C 32 0C
Appendix-A
Page 2 of 6
Sl.No. Origin
Description Destination Ref. I.S. TOWER Wind Zone Every day (kg/m2 ) temp.(0 C) Max.
DESIGN CONDITION CONDUCTOR Max. wind pressure (in kg/m2) GR. WIRE Name
Details of Conductor Size UTS (kgf) Weight Overall (kg/km) dia (mm)
1 2 3 4 5 6 7
Vapi 400 Boiser 400 Kolhapur 400 400kV Raigarh s/s Parli 400 Vapi 400 Seoni 765
Boisar 400 Phadge 400 Mapusa 400 400kV Raipur s/s Bhadravati 400 Navi Mumbai 400 Wardha 765
3 3 3 2 3 3 4
Appendix-A
Page 3 of 6
Sl.No. Origin
Description Destination
Details of Earth Wire Conductor Size (mm) UTS (kgf) Weight (kg/km) Overall dia (mm) A1
Year of Commissioning
1 2 3 4 5 6 7
Vapi 400 Boiser 400 Kolhapur 400 400kV Raigarh s/s Parli 400 Vapi 400 Seoni 765
Boisar 400 Phadge 400 Mapusa 400 400kV Raipur s/s Bhadravati 400 Navi Mumbai 400 Wardha 765
Appendix-A
Page 4 of 6
NOTE: A1 B1 C1 Minimum clearance between conductor and ground (in meters) Minimum clearance between two phase conductors (in meters) vertical in case of D/C towers and horizontal in case of 400 KV S/C towers. Minimum clearance between conductor and earth wire (in meters)
Appendix-A
Page 5 of 6
Implementation Schedule
S.N.
Description of Work Survey, planning, regional transportation, unloading, transit insurance, delivery at site, handling, storage, installation, termination, testing, demonstration for acceptance, commissioning and documentation of OPGW Package.
Appendix-A
Page 6 of 6