ID 1

Task Name Snag List

Duration 47.4 days?

Start Sat 2/6/10

Finish Tue 4/13/10

% Complete 16%

Jan 16, '10 Jan 23, '10 Jan 30, '10 Feb 6, '10 Feb 13, '10 Feb 20, '10 Feb 27, '10 Mar 6, '10 Mar 13, '10 Mar 20, '10 Mar 27, '10 Apr 3, '10 Apr 10, '10 WT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTW

Top edge / portion of steel pile supporting concrete platform had severe corrosion, requires cleaning by sand blasting and apply anti-sea weather resistance treatment / paint.

10 days

Sat 2/27/10

Sat 3/13/10

0%

All stainless steel works like hand rail, ladder etc. getting rusted need cleaning / polishing

4 days?

Wed 3/31/10

Mon 4/5/10

0%

Cable tray totally / spoiled need to be replaced by other material which will not have any effect of weather condition with E/M requirements

4 days?

Sat 2/13/10

Wed 2/17/10

100%

All concrete surfaces without any paint or protection, apply paint which should be resistant to severe sea condition.

4 days?

Thu 4/1/10

Wed 4/7/10

0%

Electro-mechanical control room container getting rusted / corrosion from top, edges, corners etc. Need cleaning by sand blasting and apply paint which should be resistant to severe sea condition.

4 days

Wed 3/24/10

Mon 3/29/10

0%

Clamps of dolphin gate have corrosion. Need cleaning by sand blasting and apply paint which should be resistant to severe sea condition.

4 days?

Tue 3/30/10

Sun 4/4/10

0%

All steel piles have severe / heavy corrosion from inside / top edges. Need to remove all caps, cleaning by sand blasting up to 1.0 m below water level and apply paint which should be resistant to severe sea condition.

3 days?

Mon 3/1/10

Thu 3/4/10

0%

Electro-mechanical control room container should be waterproof, dustproof to avoid any leakage of water during rain.

2 days?

Tue 3/30/10

Thu 4/1/10

0%

10

Steel beams, steel plates getting corrosion need proper cleaning and paint

8 days

Sat 3/13/10

Tue 3/23/10

0%

11

Require proper fixation of steel beams to concrete platform

4 days?

Wed 3/24/10

Mon 3/29/10

0%

12

Provide waterproof / weather resistance tagging for each cable as per E/M requirements

1 day?

Sat 2/13/10

Sun 2/14/10

100%

13

Provide temper switch for each panel according to E/M requirements

1 day

Tue 2/23/10

Wed 2/24/10

0%

14

Check up and down tolerance / movement for dolphin gates and also repair the damaged portion.

4 days

Thu 4/8/10

Tue 4/13/10

0%

15

At emergency stop of dolphin gate, no alarm from E/M system

4 days?

Sat 2/27/10

Wed 3/3/10

0%

16

All metallic tags need to be replaced by plastic tags resistant to sea conditions to avoid any corrosion

2 days

Sat 2/13/10

Mon 2/15/10

100%

17

Provide stainless steel caps to close the ends of circular pipe railing of hand rail.

2 days

Mon 3/1/10

Wed 3/3/10

0%

18

Other area not yet checked

18.5 days

Sat 2/6/10

Wed 3/3/10

67%

19

Cracks at berth / craft area

2 days

Mon 3/1/10

Wed 3/3/10

0%

20

Rip-rap stones washed away

4 days

Sat 2/6/10

Wed 2/10/10

100%

Project: snag list v1 Date: Mon 2/22/10

Task Split

Progress Milestone

Summary Project Summary

External Tasks External Milestone Page 1