You are on page 1of 2

2004 IEEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong

Kong

System Blackouts: Description and Prevention


Dr Damir Novosel (KEMA T&D Consulting, US)

Blackouts rarely happen and are usually caused by decision and system stabilization response to the
a sequence of low probability disturbances. The operators at the time that the operators have many
sequence of low-probability disturbances is other responsibilities including coordination with
generally not planned by the system designers and neighboring system operators, verification of
is not expected by system operators, making a equipment rating and statuses, identifying
power system more susceptible to a blackout. corrective measures, etc. Prevention of cascading
These types of events most likely occur following by operators is very difficult during a fast
sequential outages on a stressed system, when the developing disturbances.
system is operated marginally in compliance with
The varying nature and types of extreme
planning criteria. If a system is stressed and
disturbances coupled by their anticipated infrequent
system and equipment are removed without
sufficient levels of adjustment or when faults occur, occurrences make it desirable to take automated
the chain of events starts. For example, some actions to stabilize the system which may include
generators and/or lines are out for maintenance, system separation in a controlled and coordinated
line trips due to a fault. Other lines get overloaded manner.
start to sag, and another line gets in contact with a Any investment should consider the long-term
tree and trips. There is a hidden failure in the impact associated with system adjustments, be
protection system (e.g. outdated settings) that backed and preceded by comprehensive system
causes another line or generator to trip. At that studies, followed by frequent coordination studies
stage, power system is faced with overloaded over life cycle, and prudent analysis of the types of
equipment, voltage instability, transient instability, investments most necessary for successful
and/or small signal instability. Based on the power implementation. There is no single solution to
system condition such as the operating reserves and prevent blackouts, but there are general measures
equipment availability, the severity of the than can and should be taken to minimize impact of
disturbance may cause parts of the power system to wide area disturbances. Since any of the above
be islanded, loose synchronism, and even enter a referenced outages were caused by a complex
complete blackout. If fast actions (e.g. load sequence of cascading events, electric utilities,
shedding, system separation) are not proactively industry regulators, and state and Federal
taken, system cascades into unplanned islands. legislators and regulatory bodies should undertake
the recommended steps to determine the root
Evaluation of worldwide disturbances show that
protection systems have been involved in 70% of causes, understand how each disturbance happened,
the blackout events. Inadequate or faulty alarm and and identify measures and support actions to
monitoring equipment, communications, and real- prevent similar occurrences. Some of the actions
time information processing can further exacerbate may require extensive legislative and governmental
disturbances in the system. Human error or slow support due to possible environmental, financial, or
intersystem or multi-national impacts.
operator response are other major contributing
factors leading to cascading outages. Either Step Zero: Analysis & Audits
information is not available or operators are
flooded with alarms, so they cannot make proper Multiple regulatory and government agencies have
decisions fast. Important aspect in designing done an intense analysis of the blackout data to
connected power systems is that individual systems identify what actually happened during 2003
should not allow cascading outages to spread blackouts. In the US, the NERC board adopted
through out the system. recommendations of the NERC Steering Group
including:
There are a number of other contributing factors
that allow a blackout to spread, including Specific actions to correct the deficiencies
interconnection agreements, availability of reactive that led to the August 14 blackout
support, and lack of coordinated response among
control areas. Each region focuses primarily on its Strategic initiatives to strengthen
own transmission system. Each of the individual
compliance with existing standards and to
parts can be very reliable, yet the total connected
system may not be as reliable. While accounting formally track completion of
systems have boundaries, electric power and
recommended actions
critical communications do not obey these
boundaries. Very often, intertie separations are not
pre-planned for severe emergencies, leaving the

0-7803-8237-4/04/$17.0002004IEEE
4
~

2004 IEEE Intemational Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong

Technical initiatives to prevent or mitigate Perform dynamic voltage & transient


the impacts of future cascading blackouts stability studies and use certified system
models
An immediate focus was placed to evaluate chain
of events and investigate possible Operator training, including a coordinated
misoperation/(unnecessary actions) of the control
and protection systems. Inadequate exchange of approach among control areas
information between neighboring control centers
has been scrutinized. It is planned to conduct audits Condition assessment of aging
of planning, operating, and maintenance practices. infrastructure and improved maintenance
Vegetation clearance around transmission lines will
be reexamined and corrected as necessary. Regulatory actions to assure compliance
Fast restoring of power to the users is of paramount with standards
importance after the blackout and can significantly
minimize consequences of outages. It took over a Improve restoration procedures
day to restore the power after the August 14th
blackout in North America. Efficiency of Step Two: Longer-term Investments
procedures and SW tools supporting restoration
Preventing major blackouts will require a
need to be analyzed and audited to identify what
combination of long-term investments in the
improvements are needed.
transmission system and much needed
Step One: Preventive and Corrective Actions improvements in public policy. Significant
investment in transmission hardware will be made
The analysis and audit process identifies the set of in the next decade. The transmission grid must be
actions required to minimize the possibility that upgraded and expanded to handle the increased
outages will happen again. Fundamental upgrades, energy flows and address the operating conditions
such as improved real-time monitoring and subjected to. High-voltage power electronic
diagnostics and training for system operators, are devices would allow more precise and rapid
“low-hanging fruits” in actions to prevent major switching to improve system control and to help
blackouts. In addition, accurate and reliable increase the level of power transfer that can be
monitoring systems with faster detection and wider accommodated by the existing grid. While the new
communication capabilities play a key role towards investment will certainly include some new
a comprehensive system defense plan. transmission lines, it will also encompass new
Following measures should be taken to prevent power delivery technologies, Flexible AC
Transmission Systems (FACTS), and Reactive
blackouts: Power Management, including dynamic VAR
controls.
Implement System Protection Schemes
Today’s communication and computer technologies
and Adaptive Protection; have produced a new revolution in the power
Perform protection coordination studies on industry, especially in the field of power system
control where vertical integration is much
a regular basis as system conditions improved. Computer based relays communicate not
change only with a center, but also with each other. This in
turn facilitates the deployment of overall system-
Identify adequacy of protection wide protection and control philosophy. With an
information infrastructure, it is possible to tie all
application on routine basis and test not the monitoring, control and protection devices
only individual relays but system together through an information network. The key
to a successful solution is fast detection, fast and
protection applications powerful control devices, high-speed reliable
communication infrastructures, and smart
Improve monitoring, diagnostics, and algorithms, in other words “True Wide Area
control center performance Protection and Control System” (WAPC).

Secure real-time operating limits on daily Research and developments on application of new
technology such as energy storage and
basis superconductivity may also be very beneficial.

You might also like