You are on page 1of 7

2004 IEEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong

Kong

A Generalised Approach to Transient Security


Enhancement in Power Markets
X.J. Lin, C.W. Yu, A.K. David, C.Y. Chung
Electrical Engineering Department
The Hong Kong Polytechnic University
Hung Hom, Kowloon, Hong Kong

Abstract-- Ensuring transient security usually requires the stability. The linearity holds for a sufficient range of MW
re-dispatch of generators to eliminate potential transient interchange to make the proposed methodology useful.
instability after a contingency, but this has commercial That is, using linear methods the computational
implications in a power market. A further complication is complexity of the rescheduling algorithms can be
that different candidate contingencies may motivate reduced.
different re-dispatch strategies because the advanced
Section 3 describes how this technical methodology is
generator group is different in each case, or the sensitivity of
the stability margin to power exchanges between generators incorporated into a model of a competitive generation
is different. The paper develops an approach that attempts system, a power market. Many straightforward
to address all of these significant issues in deregulated optimization algorithms have been published for
competitive power systems. rescheduling the operation of a power market to minimize
additional cost, or deviation from the ‘ideal case’, or to
Index Terms-- Generation rescheduling, Transient exhibit transparency and equity. When only one specific
stability, Power market, Global index, Multi-objective contingency is of concem a similar approach is feasible
optimization and this case is examined first [IO].
Since there are many possible contingencies
I. INTRODUCTION (candidates) rescheduling normal system dispatch so as to
It is desired to dispatch generator output strictly improve security for one case may adversely affect
according to bid price in Pool operation, and beyond the another. In particular the advanced generator group may
Pool, bilateral and multilateral contracts should be be different for different potential contingencies. This
serviced without curtailment. Transmission system raises the more complex concem of trade-off between
operating constraints such as voltage limits and equipment conflicting requirements and even the case where no
overloads, or transient security (stability) concerns, may rescheduling scheme can completely satisfy the
however, inhibit system operation. The violation of requirements of all candidate contingencies. Section 4
operating limits, the congestion problem, has been widely formulates a method of attack for this more vexed
studied [l-31 for electric power systems as they existed problem. A way of classifying critical and non-critical
prior to deregulation as well as for the deregulated generator groups corresponding to different candidate
industry. There are also several studies of system contingencies is combined with a two-objective (mini-
operation taking account of transient security for pre- max) optimization formulation to develop the ‘best
deregulation systems [4][5]. The study of transient possible’ answer to this problem. Illustrative examples of
security constrained dispatch in the deregulated the single contingency case and the case when there are
competitive system has, however, received less attention. conflicting candidate contingencies to be considered are
This is because in vertically integrated systems output can included.
be rescheduled between generators, or generators shut
down and others started by a system operator, without HYBRID
11. CORRECTED METHOD
legal implications or commercial liabilities, but this is not
the case after deregulation. This paper is concerned with A. Corrected Hybrid Method
this more complex issue of generator dispatch in The corrected hybrid method is an important and
deregulated, competitive power systems, taking transient effective transient security assessment (TSA) tool
security into account. developed in recent years. It combines time-domain
The first two parts of Section 2 of the paper is an simulation and transient energy analysis and has the
introduction to transient stability assessment by the advantages of providing a system stability index while, if
corrected hybrid method. Although this is a topic on desired, incorporating detailed generator models and
which much has been published [6-91 it is included as a component representations. The method what is called a
useful introduction to the main topic. The third part of corrected transient energy function (CTEF) which
Section 2 is of key importance for the method of attack to represents the energy exchange of system transient
be proposed in subsequent sections. It is shown that the process more exactly than the traditional energy function
corrected transient energy margin (CTEM) as a stability approach [11,12]. From this a definition of corrected
index varies linearly with the amount of power that is transient energy margin (CTEM) has been derived, which
shifted from one generator to another in order to improve is used in this paper as an index to indicate the degree of

0-7803-8237-4/04/$17.0002004IEEE
65
2004 E E E Intemational Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004)April 2004 Hong Kong

system stability. The main advantage of the CTEM is that enhancement procedures using its sensitivity to changes in
it bears a linear relationship to several operation system parameters. Analytical expressions for the
parameters over a range that is sufficient for control sensitivity of the energy margin to system parameters are
purposes. This feature is useful to model the effect of given in [Ill, but they are useable only for the classical
system parameters on stability and develop useful control model. Considerable previous work by associated
schemes. researchers in our group has established through numerous
simulations over a wide range of operating conditions that
B. Corrected Transient Energy Margin Assessment
the CTEM bears a linear relationship to several operating
The CTEM assessment approach is summarized next parameters which is sufficient for control purpose. Their
using a discussion of Fig. 1. studies have been reported in [7]-[lo]. We have
TRc reconfirmed their findings through simulation studies on
TRQ' other system models. These control parameters include fault
TRQ Ec A
clearing time, pool generation rescheduling (shift of power
from one generator to another) and curtailment of a bilateral
transaction (power input and load reduction, in equal
magnitude). This linearity finding can be expressed as
follows.
ACTEM = As .ACs (1)
where ACTEM is change in transient energy margin,
ACs is change in an operating parameter and A, is
*' sensitivity of the transient energy margin to the parameter.
so SP When CTEM bears a linear relationship to ACs the
Fig. 1 : Illustration of CTEM assessment associated with time domain value of As is a constant and simulation results show that
simulation is true for ACs in fair range. Obviously, a positive value
The line at the top represents the corrected potential of A, benefits transient stability while negative As is
energy boundary surface (CPEBS). So and S, are the stable
harmful. If the transient margin is CTEM" in state A
equilibrium points of the pre-fault and post-fault systems,
then the value in state B is
respectively. TR., is the projection of the sustained fault-on
trajectory on the post fault system angle space in the center CTEM, = CTEM" + A,,, .AC,,, . If the initial
of inertia (COI) fiame. The trajectory starts at So and CTEM" < 0 , and the modified state CTEM, is set to
crosses the CPEBS at exit point E,. TR, and TR, are the zero, then ACA+B is the operating parameter change
projections of the post-fault trajectories corresponding to required to stabilise the system.
stable and unstable cases, respectively. Pa is the corrected
transient potential energy (CTPE) peak point at which 111. SINGLE CONTINGENCY ENHANCEMENT METHODOLOGY
trajectory TR, begins to swing back. E, is the exit point at
which trajectory TR, crosses the CPEBS. The projected This part describes the generation rescheduling scheme
trajectory TR.,' refers to the case when a permanent fault is when only one potentially insecure fault, which would
re-inserted at Pa, dnving the system to instability and lead to system transient instability, needs to be
crossing the CPEBS at Eo'. considered.
The definition of CTEM depends on the post-fault A. Pool model
trajectory simulation. For the unstable case, it is defined
A pool selling or buying transaction is a price-quantity-
as minus one times the value of the corrected transient
based offer to the pool by a Genco (Generation Company)
kinetic energy (CTKE) at the exit point (E, in Fig.1) of
or a buy offer from a Disco (Distribution Company).
the post-fault trajectory on the CPEBS. For the stable case
When a transient stability hazard is detected the IS0 will
the CTEM is defined as the CTPE increment from the
have to intervene. The proposed action must be feasible,
CTPE peak point (Pa) to the exit point E,' on the CPEBS
technically sound and commercially fair to all market
of the re-inserted permanent fault trajectory. In physical
participants. The problem can be formulated in the
terms the stable CTEM gives a measure of how much
following way.
more CTKE the post-fault system can withstand (convert
to CTPE) before going unstable. From the above Min P C t lAPG I (2)
discussion we can conclude that for a given fault: 1) CTEM
subiect to:
is positive if and only if the system is stable 2) CTEM is
negative if and only if the system is transient unstable 3)
when CTEM is zero we say that the system is critical.
P F 5 PG,+ APG,5 P r
C. Sensitivity and Linearity Analpis APGI= 0
CTEM is a quantitative index of system transient
stability and attempts have been made to derive stability

66
2004 IEEE Intemational Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong

where pc, and APc, are the per unit bid price and the when the existing transaction schedule is liable to cause
power output change of the i-th generator respectively; system transient security problems is discussed here. The
CTEM, is the energy margin value, which will be following assumptions are made: a) all loads remain
unchanged (that is dispatched in full); b) generation
negative when the system is transient unstable; A and B
rescheduling is executed from critical pool generators and
are the critical (advanced) generator group and the non-
critical bilateral generators to non-critical pool generators
critical group, respectively; m E A and n E B denote the
only, hence c) transaction rescheduling between one
m-th and n-th generators belong to critical group and non-
bilateral contract and another is not considered.
critical group respectively; G,*+" is the generation shift Generation shift from a critical bilateral generator to a
for m-th to the n-th generator and h,,,+" is the sensitivity non-critical pool generator, therefore, means that some
of CTEM to G,,, ; P T , P r a r e i-th generator power bilateral loads may have to buy power from the pool after
rescheduling because their regular suppliers have been
limits. The first constraint imposes the condition that after
generation rescheduling the transient stability index curtailed. We define WJas the j-th bilateral generator's
should be positive and the second ensures that generator willingness to pay to avoid generation change. This value
power limits are not violated. The last constraint ensures can be derived from the set of bilateral transaction
invariance of total generation that is transmission loss is willingness-to-pay factors that this generator enters into
neglected. and may be written,
-
B. Bilateral model w~ = f ~ ( W ~ I ? ' * * ? W ~ (4)
K)
where w JI,... ,w JK are willingness-to-pay factors of
A bilateral transaction is a contract entered into directly
between a Genco-Disco pair. The conceptual model of a individual bilateral transactions entered into by the j-th
bilateral contract is that sellers and buyers enter into bilateral generator and f () is a function of w JI,... ,wJK.
agreements where the quantities and trade prices are at the The optimal curtailment problem is then formulated
discretion of these parties and not a matter for the ISO. as,
The paper does not, for simplicity of presentation, extend
the discussion to the case where a Genco or a Disco
contracts with several partners, but the extension is quite
easy to formulate. Bilateral contracts are brought to the subject to:
attention of the IS0 with a request that transmission
facilities for the relevant amount of power be provided. If
there are no technical infeasibilities the IS0 simply P p IP,, + AP,> I PE"
dispatches all requested transactions and charges a use of C A P G i= 0
system charge for the service. Only when security is
threatened does the IS0 intervene to make decisions on where S , is the generation shift which includes shift from
curtailment. The methodology examined in this paper is both critical pool and critical bilateral generators to non-
when curtailment follows a user-pay philosophy were critical pool generators;Ad is the corresponding set of
"willingness-to-pay not to be curtailed" ( w ) is an sensitivities of CTEM to these shifts; CTEM, , PE",
indicator of the importance that parties to a transaction
place on unfettered dispatch. The problem is illustrated as Pz'" , P,, , APGLare the same as in (2).
following. Discussion:
Spreading any reduction in the permitted dispatch of a
Min z w , A T k (3) bilateral generator among the loads contracted with this
generator can be arranged as follows.
subject to:
= ' ' ' = q,KATjK
C h k ~ ~ k~ICTEM,~ JIATjl

CATJ, = MJ
(6)
:P, I P,, + AP,, I PGy k=l K

where w, is the "willingness-to-pay'' price premium to where qJk= wfx , APJ is the reduction of the j-th
avoid transaction curtailment; AT, is the k-th bilateral / k-IK
Jk

transaction power change, ilk the correspond sensitivity bilateral generator dispatch and ATJk the change in the
of CTEM to this power change; CTEM, , P r , PE'", P,, , individual bilateral transactions entered into by this
APG, and the meaning of the constraints are the same as generator. It is easy to see from (6) that curtailment is
inversely related to transaction willingness-to-pay.
in (2).
C. lntegrated transaction model
In real world open access transmission, as it is now
evolving, pool and bilateral transactions coexist. The issue
for integrating them into a single rescheduling strategy

67
2004 IEEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DWT2004) April 2004 Hong Kong

Iv. GENERATION
RESCHEDULING FOR MULTI-
CONTINGENCY

A. Basic concept
When only one contingency is involved, it is easy to
find an optimal generation rescheduling solution, if it
exists. However it is difficult to find an operating point
that is transient secure for several possible contingencies;
sometimes such an operating point may not exist [ 131.
By shifting power from critical generators to non- Fig. 2a: A, and B, are critical and non-critical sets of fault F,
critical generators we may enhance the system transient
stability. However, the mode of system transient "1
separation is different for different contingencies. r' 62
J
Consequently a generator, which is classified as critical
for one contingency, could be non-critical for another.
This means that the same generation shift will be useful
for some contingencies but maybe harmful for others. In
the remainder of this section only consider critical
contingencies -that is- those violate the stability margin.
Let AJ stands for the critical generator set for the j-th Fig. 2b: and Bj arc cntical and non-critical sets of'fault Fz
contingency and BJ the non-critical generator set. If the
inclusion set of all AJ ( n A , ) is null, then there is no
generation shift that is beneficial for all candidate
contingencies. The same is true if n B , is null. Security
enhancement is impossible in these cases in the sense that
improving security for any contingency makes it worse
for at least one other contingency. In this paper, we
assume the feasible generation shift domain, where a
generation shift beneficial for all candidate critical
Fig. 2c: Feasible generation shift domain
contingencies is possible, is not null. However, this does
not mean that there exists a generation rescheduling But, it should be noted that the sets A and B could,
scheme making all potentially critical contingencies for some F1, F2, (or for some large set of contingencies F1,
completely secure at the same time. Improvement or F2, F3.. .), be empty, making mutual stability enhancement
enhancement of security may be feasible, but complete impossible.
security unreachable. Returning to the example, and noting that (1) is linear, let
As a simple illustration, assume there are two L1 and L2 in Fig.4 be the loci of generation to be shifted
potentially unstable faults F1, F2 in the system. Let the from X and Y to Z to just ensure transient security for
critical generator set for F1 be A I and let B I be the non- faults F1 and Fz respectively. These loci are straight lines
critical generator set. Similarly, let A2 and Bz stand for the by virtue of the linearity properties. Transient stabilization
critical and non-critical generator sets of fault F2. These
sets are shown in Fig.2a and Fig.2b .The inclusion set of
I
implies ACTEM I = ICTEM and ACTEM = ICTEM aI
A , and A2 (A= A,&?) and the inclusion set of B, and B2 along L1 and L2 respectively. Now let the line L3 represent
(B= BlnB2) are then shown in Fig.2~.Only generation the generator Z output limit (maximum power that X and Y
together can transfer to 2'). The domain enclosed by the
rescheduling from region A to region B can improve
stability for both faults F1 and F2. Now suppose A two axes and L3 is the feasible domain of (G,,, ,G,+,).
contains two generators X and Y and B contains only one Then, when ( GX,, ,Gy,,)ED,is true, contingency F,
generator Z . Then there are two available generation shift can be stabilized by generation rescheduling. Similarly,
patterns; one is power shift from X to Z ( G),,, and when ( G x + , , G y + , ) ~ D 2is true, contingency F2 can be
another is from Y to Z ( GY+,). Then the effect of the two stabilized by generation rescheduling. However, there is
generation shifts can be written as: no inclusion domain for both F1 and F2 in the case
ACTEM' =A.',,, .G,,, +h'Y+z.G,+, (7) illustrated in Fig.3, that is D, n D2 be empty. Hence no
ACTEM' =A.$,, .G,,, +A.:+, .G,,, generation rescheduling scheme will stabilize the system
(8)
for both contingencies. These concepts can be extended to
cases with lager numbers of generators and more than two
critical contingencies.

68
2004 IEEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong

GI is an overall indicator of the role of the generation


rescheduling scheme for stability enhancement.
Furthermore, by adjusting weight coefficient p' , a trade-
off among contingencies can be examined.
The higher the value of GI, the better is the scheme
from a purely technical point of view. However, in power
market conditions, equity and economics are also very
important. That is to say, the scheme should be
commercially fair. As in the single contingency condition,
assume that the original generation dispatch is the most
Fig. 3: Illustration of effect of power shift on different contingency economic. The consequence of rescheduling (away from
this economic dispatch state) is an increase of cost. The
B. Global index (GI) and its application to generation
core of the problem is how to get the best control effect
rescheduling
(the highest GI) at minimum cost. In other words, the
Improvement of CTEM denotes stability enhancement optimization problem has two objectives which can be
only for a particular fault but when there is more than one formulated as follows:
potentially unstable contingency it is necessary to develop
a sounder index. It is impossible to compare the effect of MinCpGnlapG,I Max c c m + n Gm+n (13)
mtA.neB

different control schemes on stability enhancement subject to:


without such an index. Furthermore, the index should be P T 5 P,, + AP,, IP;"
capable of dealing with the problem of trade-off among
contingencies. It is especially useful for the case when no
scheme can completely satisfy all the candidate
c4 =O
As a technical objective is competing with an economic
contingencies simultaneously as illustrated the in last part. objective, there is no unique solution to the problem.
Instead, the concept of noninferiority [ 141 (also called
Define an energy margin change rate 'R forj-th fault as:
Pareto optimality [15]) can be used to characterize the
solution. A noninferior optimization point is one at which
an improvement in any one objective requires a
where CTEM', is the corrected transient energy margin degradation of at least one other. In the multi-contingency
of the initial state (before generation rescheduling) and "j" case, there may not exist a control scheme that makes all
is an index over the set F of all potentially transient of the candidate contingencies simultaneously secure.
unstable contingencies. Comparing the energy margin However, by comparing the GI value of different
change rate for different contingencies the effect of the rescheduling schemes the best comprehensive stability
various rescheduling strategies on different contingencies enhancement schedule can be determined. In addition,
can be appreciated. For the purpose of trade-off among using different weight coefficient p J, the problem of
contingences, the global index should be able to reflect trade-off among the contingencies can be examined.
the severity of different contingencies. This can be
achieved by using a weight coefficient (p). The weight V. CASESTUDY
coefficient p depends on many factors such as frequency These procedures for improving transient security have
of the contingency, duration of the outage and financial been tested using New England 39-bus system data [16].
loss caused by the contingency. It has to be chosen by The system has 10 generators, 39 buses and 46 tie-lines.
engineering judgment based on these concerns. Hence the Bus 31 has been chosen as the slack bus designated to
global index of stability enhancement for a particular make good transmission losses and is not involved in
control scheme is developed as follows. Let, generation.rescheduling. Because of the space limitation,
G I = ~X R~' J (10) only simulation results of multi-contingencies are
J ~ F discussed here. Simulation results of single contingency
From ( 5 ) and (9), (10) can be written as: case can be found in [lo]. All the generators except that
attached to the bus 31 (slack bus), which is not involved
in generation rescheduling, are assumed as pool
generators and all loads buy power from the pool. Two
severe candidate contingencies Fi, F2 are selected. F1 is a
where: three-phase short circuit at bus-25 cleared by tripping line
25-26 in 0.22s. F2 is a three-phase short circuit at bus-27
cleared by tripping line 26-27 in 0.22s. For Fi, only the
generator at bus-39 is non-critical, the remaining
where A ; B, m and n are same as (2). Observe that in (1 l), generators are all critical, but for F2, all generators expect
GI has a similar style to ACTEM . We can call C,,,+othe those at bus-37 and bus-38 are non-critical. Hence
sensitivity of generation shift to the global index. generation shifts useful to both faults are from the

69
2004 IEEE Intemational Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong

problem is improved to some degree after rescheduling. If


the p x 2 ranges from 114 to 112, the optimization

Bus-Name Output (MW) Bid Price ($/MWh) procedure reschedules both generators at bus-37 and bus-
38. Outside this range the procedure makes use of only
30 250 16 one or the other these generator generators. When F1 is
32 650 8 more important than FZ,the scheme prefers to use G37-t39
33 632 7 because of its lower cost and better effect on the technical
I 34 I 508 I 12 I parameters. As the importance of F2 increases, the scheme
I
I
35
36
37
I
I
650
560
540
I
I
8
9
4
1
I
makes greater use of G38+39.When p
x ~ is one fifth or
less, the favorable technical effect of G,,,,, exceeds the
favorable economic effect of G37+,39.In this case, the
38 830 15
scheme only uses G38+39 for stability enhancement.
39 1000 3

VI. CONCLUSION
4 - 3 9 4 - 3 9 I CTEM, I The paper develops a transient security enhancement
F1 2.821 0.573 -1.147 approach for a power market. The approach relies on a
F2 0.362 1.978 -0.86 1 stability index, the transient energy margin computed by
the corrected hybrid method, which bears a linear
relationship to certain system operating variable changes
such as power exchanges between generators or bilateral
CTEM; contract curtailments. It has been shown that this property
makes it possible to design a price driven auction
>5 (0.5,0.0000) 3.5 0.2638 -0.6802
mechanism, which will optimize generation rescheduling,
51 1 (0.5, 0.0000) 3.5 0.2638 -0.6802 and transaction curtailment for transient security
3.5 0.2638 -0.6802 enhancement in a power market environment. A global
411 (0.5,O.OOOO)
index developed can affect the global stability
311 (0.5, 0.0000) 3.5 0.2638 -0.6802
enhancement and deal with trade-off problem for multi-
211 (0.5, 0.0000) 3.5 0.2638 -0.6802 contingency condition. Then, according to the rule of
-0.6802 power market, technical sound and economical fair,
111 (0.5, 0.0000) 3.5 0.2638
develops an approach optimizing the generation
1/2 (0.5,0.0299) -0.62 I O
4.038 o.2810 rescheduling scheme for the cases that several potentially
1/3 (0.5,0.0660) 4.688 0.3017 -0.5495 unstable contingencies should be taken into consideration.
0.3126 -0.5 120
The approach is especially useful when there do not exist
1I4 (0.5,0.0850) 5.031 a scheme which can rescue all the candidate faults.
1/5 (0.0, 0.2880) 5.184 -0.9818 -0.2907
VII. ACKNOWLEDGEMENT
116
<1/6
(0.0, 0.2889)
(0.0, 0.2889)
5.200
5.200
II -0.9814

-0.9814
-0.2890

-0.2890 Financial support from the Research Committee of


H.K. Polytechnic University is gratefully acknowledged.
It is convenient to set the weight coefficieint of F2 ( pz)
to a constant value of unity and to deal with trade-off by VIII. REFERENCES
adjusting the weight coefficient of F1 (p’).In Table 3, the [I]. A. MONTICELLI, M.V.F. PEREIRA and S. GRANVILLE,
fourth column ( CTEM ) and the fifth column ( CTEM ) “Security-constrained optimal power flow with post-contingency
corrective rescheduling,” IEEE Trans. on Power Systems, 1987,
are the CTEM values after generation rescheduling. The 2(1), pp.175-182
example shows that there exist no schemes that can A.K. DAVID and R.S. FANG, “Security-based rescheduling of
[2].
stabilize the system for both potential contingencies F1 transactions in a deregulated powcr systcm,” IEE Proc-Gener.
and F2 at the same time. It can be seen that: 1) when Trunsm. Dishib., 1999, 146 (I), pp.13-18

P x 2 is greater to one fourth, the optimum solution [3]. A.K. DAVID, “Dispatch methodologies for open access
transmission systems,” IEEE Trans. on Power Systems, 1998,
completely stabilize the system for F1 but only partially 13(1), pp.46-53
for Fz; 2) no optimization schemes can completely satisfy
the stabilization needs of F2 because G,,,,, , which plays [4]. A.A. FOUAD and J. TONG, “Stability constrained optimal
rescheduling of generation,” IEEE Trans. on Power $?isfenis,
a more important role than G,g,,9, costs too much; 3) 1993, 8(l),pp.105-112
with the decrease of w’,the solution moves in a direction
more beneficial for F2; 4) for both faults, the security

70
2004 IEEE International Conference on Electric Utility Deregulation, Restructuring a n d Power Technologies (DRPT2004) April 2004 Hong Kong

D.H. KUO and A. BOSE, “A generation rescheduling method to


increase the dynamic security of power system,” IEEE Trans. on
Power Systems, 1995, 1 O( I), pp.68-76

D.Z. FANG, T.S. CHUNG and A.K. DAVID, “Improved


techniques for hybrid method in fast transient stability margin
assessment,” IEE Proc.-Gener. Trunsm. Distrib., 1997, 144(2),
pp. 107-112

D.Z. FANG, T.S. CHUNG and Y . ZHANG, “Corrected transient


energy function and its application to transient stability margin
assessment,” 4th lntemational Confcrencc on Advances in Powcr
System Control, Operation and Management, APSCOM97,
November 1997, Hong Kong, P.R.C., pp.310-313

D.Z. FANG, T.S. CHUNG and A.K. DAVID, “Fast transient


stability estimation using a novel dynamic equivalent reduction
technique,” IEEE Trans. on Power Svstents, 1994, 9(2), pp.995-
1001

D.Z. FANG, “On-line algorithms for transient stability assessment


and control,” Ph.D. Dissertation, Department of Electrical
Enginccring, the Hong Kong Polytechnic University, Hong Kong,
1995

A.K. DAVID and X.J. LIN, “Dynamic security enhancement in


powcr-market systems,” IEEE Trans. on Power Systems, 2002,
17(2), pp.43 1-438

A.A. FOUAD, “Transient stability margin as a tool for dynamic


security assessment,” Final report for EPRI project EL-1755,
March 1981

[ 121. A.A. FOUAD and V. VlTTAL, “Power System Transient Stability


Analysis Using Transient Energy Function Method,” Prenticc Hall,
New Jersey, 1990

[13]. V. MINANDA, J.N. FIDALGO, J.A.P. LOPES and V.


MIRANDA, “Real time preventive actions for transient stability
enhancement with a hybrid neural network - optimization
approach,” IEEE Trans. on Power Sysrems, 1995, 10(2), pp. 1029-
1035

[ 141. L.A. ZADEH, “Optimality and nonscalar-valued performance


criteria,” IEEE Trans. on Automation and Control, 1963, 8(1),
pp.59-60

[IS]. Y . CENSOR, “Parcto optimality in multiobjective problems,”


Applied Mathemutics and Optimization, 1977,4( I), pp.41-59

[ 161. T. ATHAT, R. PODMORE and S. VIRMANI, “A practical method


for direct analysis of transient stability,” IEEE Trans. on Power
Appurutus undSjstems, 1979,98(2), pp. 573-584

71

You might also like