You are on page 1of 7

Chemical Engineering Science 54 (1999) 5565}5571

Next generation CFBC


S. Rajaram
Bharat Heavy Electricals Limited, Tiruchirapalli, India

Abstract

CFBC boiler can utilise all grades of coal and lignites in an e$cient and environmentally clean way. Its development was initiated
in the mid 1970s and several CFBC boilers have been installed worldwide. The largest in operation is a 250 MW plant at Gardanne,
France. CFBC designs with lower auxiliary power, lower refractory content, more appropriate support systems and with super critical
steam pressures are being evolved to optimize overall costs. Future generation of power from coal is expected to be from Integrated
Gasi"cation Combined Cycle plants based on Circulating Fluidised Bed Combustion and gasi"cation.  1999 Elsevier Science Ltd.
All rights reserved.

Keywords: CFBC; Coals; Lignites; Super-critical CFBC; CFBC based combined cycle plants; IGCC

1. Introduction India have low sulphur, their high ('45%) ash content
causes operational and maintenance problems like coal
Coal has re-emerged as a major energy source for mill outages, #ame stabilisation problems at lower loads
power generation after having played a subsidiary role to and erosion when used in PF boilers.
oil during the mid 20th century. Today about 40% of all CFBC technology holds a great promise for these
world electricity is generated from coal, almost double high-ash coals since it does not require pulverisation of
that of its nearest competitor, namely hydro (Table 1). the fuel but only crushing, the required ignition energy is
World coal production was about 4630 million tonnes in provided at all loads by the huge solids inventory in the
1996 (Table 2); therefore, coal is the most important fuel CFB combustor and the ash can be handled dry.
source for electricity generation in the world today and Petroleum coke, a solid residue from oil re"neries
would also continue to dominate the power station fuel which have installed coking units to improve the pro"t-
scenario in the foreseeable future. In Asia, coal's share of ability of the re"ning process, is gaining increasing
the total electricity production rose from 26% in 1980 to acceptance as an alternate fuel (Dallas, 1997). Its charac-
42% in 1992 and is projected to increase to about 54% teristics include low volatile content, high sulphur
by 2010. However, realising electric power from coal in (4}8%), very low ash (containing metallic compounds)
an e$cient and environmentally clean way has remained and very high heat value (about 6000 kcal/kg). Conven-
the biggest challenge that nature has imposed on man- tional boilers primarily require add-on desulphurisation
kind. Circulating #uidised-bed combustion (CFBC) equipment that are very expensive and also experience
technology is probably the best solution reached com- fouling and corrosion of heat transfer surfaces. However,
mercially to this challenge posed by nature. CFBC a CFB boiler * with its inherent capability to absorb
e!ectively utilises all grades of coal in an environmentally SO in situ along with the combustion process by the

clean and e$cient way and is therefore expected to out- addition of limestone with the fuel, contain NO to very
V
last conventional coal burning technologies for power low levels because of lower combustion temperature and
production. Most coals available in the US have moder- also due to staging the combustion air * can utilise
ate to high sulphur in them and require expensive add-on Petroleum Coke in a very e$cient and environmentally
gas cleaning equipment to contain SO when utilised in clean way.
V
conventional pulverised fuel (PF) "red boilers. CFBC The total lignite production is 1000 million tonnes in
with its unique in situ SO capturing ability (by the the world today (Table 3). Lignite is a young coal which
V
addition of a sorbent like limestone along with coal) has has undergone less coali"cation than bituminous coal
been able to utilise these coal e!ectively. Although coal in and anthracite. These are characterised by their high

0009-2509/99/$ - see front matter  1999 Elsevier Science Ltd. All rights reserved.
PII: S 0 0 0 9 - 2 5 0 9 ( 9 9 ) 0 0 2 8 8 - 2
5566 S. Rajaram / Chemical Engineering Science 54 (1999) 5565}5571

Table 1 moisture (35}70%) and oxygen contents and their low


World electricity generation in 1988 calori"c value just about half of bituminous coals). Some
of the lignites found in Australia, China, Germany, USA
Fuel Trillion Wh (%)
(Texas), the erstwhile Soviet Union, Yugoslavia and in
Coal 4287 39 the Gujarat region of India have moderate to high sul-
Oil 1271 12 phur in them. As mentioned above, their e!ective utilis-
Gas 1394 13 ation in PF boilers would require very expensive add-on
Hydro, etc. 2182 20 #ue gas conditioning systems while CFB boilers with
Nuclear 1891 17
their in situ SO capturing capability make utilisation of
V
Total 11025 100 these fuels techno-economically very attractive.
CFBC technology can thus utilise a wide range of fuels
Note. Extracted from IEA coal research report. and is therefore quite di!erent from the other coal utilis-
ation technologies such as PF "ring. CFBC can e!ec-
Table 2 tively burn almost all combustible materials * not only
Major coal producing countries * 1996 any type of coal and lignite but also coal washery wastes,
anthracite culm, and other industrial wastes.
Country Production
(million tonnes)

Total coal Hard coal 2. The CFBC boiler system * a description

China 1375 1330 Combustion in a CFB boiler takes place in a vertical


USA 959 878 chamber called the combustor amidst "ne grained solids
India 296 271 suspended in an upward #owing stream of gas.
Russia 255 163
Australia 249 195 The gas is generated by a fuel combustion while intro-
Germany 240 53 ducing about 40}50% of the total air as primary air
South Africa 208 208 through an air distributor at the bottom of the combus-
Poland 202 138 tor and the remaining as secondary air into lower/middle
Kazakhastan 79 75 sections of the combustor to e!ect complete and staged
Canada 76 40
Others 692 309 combustion.
The fuel and sorbent (e.g. limestone, if required) are fed
World 4630 3660 into the combustor without requiring any costly fuel
preparation/distribution system, #uidised and burned at
Sub-bituminous, bituminous, anthracite. temperatures of about 8503C. The sorbent reacts with the
Extracted from IEA coal research report.
sulphur dioxide released from burning the sulphur in fuel,
to form calcium sulphate (gypsum). Due to the "ne par-
Table 3 ticle size of the solids and the high gas velocities in the
Lignite resources and use combustor, a considerable portion of the solids are en-
trained and separated from the #ue gas in one or more
Country Proved Recent Power
recoverable annual prod generation recycling cyclones and are continuously returned to the
(million (million (million combustor via a recycle loop, while the gases exit to
tonnes) tonnes) tonnes) a convection backpass to be cooled and then cleaned and
exhausted to the stack as in conventional boilers.
Australia 36,200 35 33 CFBC boilers can be broadly classi"ed, depending on
Bulgaria 3,700 32 23.5
Canada 2,418 10 9.2 the arrangement of the heat transfer surfaces and the
China 126,500 30 22 hydrodynamics in the combustor, into the following:
Czech 2,860 103 55
FRG 35,150 127 107 E heat transfer surfaces immersed in the combustor *
GDR 21,000 296 188 typi"ed by Ahlstrom pyropower (now Foster Wheeler)
Greece 3,000 32.5 31.5
Hungary 2,883 7.1 5.6 E external #uidised * bed heat exchanger (FBHE) *
India 1,581 7.7 6.9 typi"ed by Lurgi.
Poland 14,400 50.4 49.3
Turkey 4,763 22 12.4 A typical Ahlstrom pyropower CFBC (Fig. 1) boiler has
US 32,709 57 53.5 a combustor in which the heat transfer surfaces are
USSR 94,500 122 76.8
Yugoslavia 15,000 65 65 located in the upper region where heat is absorbed. These
surfaces have tubes of special construction to face the sti!
Note. Extracted from IEA coal research report. combustor environment. The heat in the hot #ue gas
S. Rajaram / Chemical Engineering Science 54 (1999) 5565}5571 5567

Fig. 1. Ahlstrom/FW CFBC arrangement. Fig. 2. Lurgi CFBC arrangement.

Fig. 4. DBW CFBC arrangement.


Fig. 3. B and W CFBC arrangement.

leaving the high-temperature cyclone is recovered further amount of solids to be passed through external #uid-bed
by a convection pass containing the usual superheater, heat exchangers (FBHE) containing portions of SH/
economiser and airheater surfaces. RH/evaporator surfaces that cool the solids before they
In the Lurgi CFBC boiler (Fig. 2) a mechanical Spiess are returned back to the combustor. FBHE helps separ-
Valve located on the recycle loops permits a controlled ate fuel combustion from primary loop (combustor,
5568 S. Rajaram / Chemical Engineering Science 54 (1999) 5565}5571

cyclone, seal pot, FBHE) heat transfer, thereby enabling sioned in March 1998 and has been in operation for over
the combustor to be maintained at an optimum combus- 2500 h on oil. Coal "ring has just begun and the operat-
tion conditions over wide load ranges and for fuels with ing results are very encouraging.
widely varying qualities. Consequently, the combustion Gujarat Industries Power Company Ltd (GIPCL)
e$ciency increases and the limestone consumption also placed an order on BHEL for 2;125 MWe power plant
reduces. to be located in Mangrol, Surat to burn Gujarat Lignite
Although Foster Wheeler/Ahlstrom pyropower CFBC with a maximum sulphur of 2.5%. Two CFB boilers
and the Lurgi CFBC have the majority of the CFBC rated at 390 t/h, 132 ata, 5403C of SH steam and 350 t/h,
market share, other types of CFBC with various design 32.5 ata, 5403C of RH steam each are nearing completion
features have been developed and are commercially of construction. The units are expected to commence
available. operation by early 1999.
Some typically di!erent CFB designs from the ones
described above are Babcock and Wilcox's Internally
Recirculating CFB design (featuring Studsvik's CFB pro- 4. The future CFBC
cess) (Fig. 3) with U-Beam separator for primary particle
separation, Deutche Babcock and Wilcox's Circo#uid Although present CFBC boiler costs are quite com-
design with low gas velocities with superheater tube petitive as compared to PF boilers while using medium/
bundles arrayed in the upper combustor section (Fig. 4), high sulphur coals warranting add-on emission control
and with gas/solid temperature leaving the combustor at equipment, certain design areas of CFBC boilers still need
300}5003C to relatively cold cyclones. re"nement to outlast the conventional counterparts.

E The present boiler e$ciency levels of CFBC and PF


3. The present CFBC units are comparable. Considering the feasibility to
absorb SO in situ, CFBC boilers can be designed for
V
Development of CFBC boiler technology was initiated lower (10}153C) exit-gas temperatures thereby im-
in the mid 1970s and it gradually increased its share in proving the e$ciency (by 1}1.5%). Although the
the world FBC boiler market in the 1980s. This was due CFBC boiler auxiliary power compares favourably
to its advantages over bubbling FBC, e.g., better combus- with that of PF boilers with add-on emission systems,
tion e$ciency, fewer fuel feed points and therefore it is more by about 10}40% without these systems.
simpler fuel feed system, lower limestone requirement, This is because of the increased power consumed by
lower NO emissions, due to longer gas}solid contact the PA and SA fans of CFBC boilers, although the coal
V
time. The "rst utility size CFB boiler in the world mills o!set it considerably (Table 4).
of 96 MWe capacity with reheat was started up at E!orts to reduce the power consumption of the PA
Stadtwerke Duisburg, Germany in September 1985 by and SA fans by optimising combustor parameters like
Lurgi. The unit was designed to generate 270 t/h, 145 bar, height, velocity and particle size would have to be
5353C of SH steam and 230 t/h, 34 bar, 5353C of RH examined to push the CFBC technology ahead of PF
steam while "ring coal with 20% ash and 1.5% sulphur. boilers.
Several CFB units have been installed in this capacity E Refractory applied in the lower combustor, cyclone
range, which include 2;175 MWe CFBC plant at Texas, and recycle systems is another area which increases
New Mexico, USA by ABB-CE/Lurgi and 165 MWe CBFC boiler installation and maintenance costs be-
Point Aconi Plant at Nova Scotia, Canada, by Pyro- sides restricting start-up and shut-down periods. De-
power which are in operation for several years, all meet- signs are already being evolved (like compact CFB) to
ing the design parameters and sometimes even exceeding
them. The largest CFB unit in operation is the 250 MWe
Provence/Gardanne unit installed in France by GEC Table 4
Alstrom-Stein Industrie of Lurgi design which has been Comparison of auxiliary power (kW) for a typical 210 MWe (estimated)
in commercial operation since April 1996 (Pierre Lucor plant
et al., 1997). It is designed to burn sub-bituminous Gar-
danne Coal with about 3.8% sulphur. Equipment PF CFBC
In India, BHEL Trichy, a leading utility boiler manu- PA fan 967 3670
facturer, sensing the rapid increase in FBC capacity SA fan 580 1220
demanded by the market, entered into a technical collab- Ball mills 3220 *
oration for CFB boilers with Lurgi Lentjes Babcock of Coal feed * 108
Germany. The "rst CFB boiler of 175 t/h, 105 ata, 5253C Others incld. Blowers 2462 3193
was contracted to M/S Sinarmas Pulp and Paper (India) Total 7229 8191
Limited, Poona for burning coal. The unit was commis-
S. Rajaram / Chemical Engineering Science 54 (1999) 5565}5571 5569

Table 5
Present range of gaseous emissions

Country SO ppm(v) NO ppm(v)


 V
New Existing New Existing

Australia * * 260}420 *
Canada 250 * 356 *
Czech Rep Slovakia 175}875 175}875 320 320
European Union 140}700 * 320}635 *
France 140}700 140}700 320}635 320}635
Germany 140}700 140}700 100}195 100}640
Korea 700}1200 250}1200 355 355
Netherlands 70}245 140 50}320 320}540
Poland 190}615 235}1455 45}225 45}655
Sweden 55}190 55}320 40}265 65}265
UK 140}1050 700}1050 245}320 245}320
USA 260}520 520 340}480 270}300

Also based on annual totals.


Guidelines.
Extracted from IEA coal research report 1994.

drastically reduce the refractory content by integrating 4.1. Super critical CFB design
these into the boiler steam/water circuits. This also
improves their structural rigidity and eliminates many Super critical CFB design improves plant e$ciencies
expansion joints on their interconnections with the thereby reducing operating (fuel) costs of the plant. Once
combustor. E!orts are also underway to develop ap- through PF "red steam generators designed for super
propriate refractories that are abrasion resistant and critical steam conditions (241 bar/5383C) also capable of
with high conductivity (to facilitate heat transfer to cyclic variable pressure duty, have been available in the
enclosing membrane water walls) requiring least main- last decade. Adoption of these steam cycles for CFB
tenance so that cost-e!ective, maintenance-free CFBC boiler based power plants appears feasible, especially
designs can be o!ered. considering the following inherent advantageous features
E Considering the large weight of bed material and the of the CFB combustion process (Skowyra et al., 1995):
refractory in the lower combustor, CFBC designs with
a combination (top and bottom) of support points E Low heat yux: The plan area of a CFB combustor is
have been evolved. But this leads to the inclusion of larger than a PF boiler of equivalent rating. This
a large number of expansion joints between the com- results in a lower heat input/plan area or lower heat
bustor and its connected systems besides increasing #ux. The average net heat input/plan area (NHI/PA)
the erection time. CFBC designs with appropriate for a typical CFB boiler is about one third that of the
boiler support systems that can optimise on overall PF boiler.
costs are also being evolved. E Heat yux proxle: In a CFB combustor the solids den-
E The present gaseous emission levels (Table 5) are ex- sity and therefore heat transfer rate is maximum at the
pected to be further reduced, neccesciating design up- bottom of the combustor and decreases gradually with
dating. Although su$cient work has already been increase in combustor height. The peak heat #ux is
done in determining the mechanism of SO capture, therefore near the bottom of the combustor, where
V
the sorbent's (limestone) interaction with NO reduc- however, the #uid temperature is the lowest as it just
V
tion is still under scrutiny. Further reduction of NO enters the combustor at this place.
V
levels by optimally sizing the lower combustor region, E This situation therefore creates a very favourable con-
improving the secondary air admission system to- dition from wall metal temperature considerations.
gether with spraying of NO absorbents in the upper Moreover, in addition to the lower temperature faced
V
combustor are being examined. in the combustor as compared to PF boiler, the tem-
peratures are also uniform along the height of the
CFBC design development has reached a mature stage. combustor.
However, constant review on the cycles adopted for con- E Cleaner combustor wall: Due to lower combustion
version of coal to power are continuously made. Some of temperatures, the ash does not fuse, and there are no
them are presented in the following two paragraphs: ash deposits on the combustor walls. Due to the
5570 S. Rajaram / Chemical Engineering Science 54 (1999) 5565}5571

Fig. 5. First generation IGCC plant schematic.

cleaner walls the heat absorption is nearly uniform. the combustor after cooling a part of these in the FBHE.
The heat absorption patterns change little laterally The #ue gas at about 8503C is cleaned in special "lters
with load, and tends to become compressed vertically before admission into the gas turbine (GT) for expansion
due to lower velocities, at part loads. and power generation. A heat recovery steam generator
(HRSG) located at the back end of the GT cools the gas
Developing CFB boiler design for super critical condi- by producing steam which is further heated in the FBHE
tion therefore becomes more attractive. of the CFB boiler, before expansion in the steam turbine
to complete the combined cycle power plant.
Advanced IGCC plants based on integrated CFB gasi-
4.2. CFB-based combined cycle plants "cation and combustion is given in Fig. 6. Fuel and
sorbent are admitted in a carbonisor along with air from
The liberal allotment of oil/gas/naptha, lower capital the GT compressor, volatiles in the fuel are liberated in
costs, shorter installation schedules and higher cycle ef- a controlled atmosphere, to produce fuel gas which after
"ciencies are resulting in a sudden increase in premium cleaning in a "ler is burnt in a topping combustor before
fuel-based combined cycle power plants. Considering admission into the GT for expansion. The residual char
that these premium fuels are not expected to last beyond from the carboniser is tapped o! to a pressurised CFB
a few decades these combined cycle plants would have to combustor where it is burnt along with air from the
depend on coal as its fuel. Integrated gasi"cation com- GT compressor. The primary loop of the CFB boiler
bined cycle (IGCC) power plant based on pressurised collects the solids in a cyclone and these are recirculated
CFB combustion and gasi"cation are therefore expected back into the combustor via FBHE. The hot gases leav-
to be the future electric power generation technologies ing the cyclone are further cleaned before admission to
from coal. BHEL through its in-house R and D e!orts the topping combustor and GT for expansion. A heat
have already commissioned a 6 MW combined cycle recovery steam generator recovers heat from the GT
power plant based on coal with a pressurised #uidised- exhaust, as already explained, for expansion in a steam
bed gasi"er of the bubbling bed type. turbine generator and completing the combined cycle
The schematic of the "rst generation IGCC plant with plant. These advanced combined cycle plants together
a pressurised CFB combustor is given in Fig. 5. Coal and with advanced gas turbines with steam-cooled rotor
sorbent are introduced into the pressurised CFB com- blades are expected to be the future power generation
bustor, which is fed by air from the GT compressor. The technologies based on coal with overall e$ciencies ex-
solids are separated in a primary cyclone, and returned to ceeding 50%.
S. Rajaram / Chemical Engineering Science 54 (1999) 5565}5571 5571

Fig. 6. Advanced IGCC plant schematic.

5. Conclusion References

Coal is expected to outlast its fossil counterparts as IEA coal research reports: Lignite resources and characteristics; De-
a fuel source for electric power generation due to its cember 1988.
IEA coal research reports: Power station coal use: Prospects to 2000;
abundance. However, its utilisation has placed innumer- October 1991.
able challenges in its e$cient and environmentally IEA coal research reports: Major coal xelds of the world; January 1993.
friendly utilisation for power generation. CFB boiler IEA coal research reports: Environmental performance of coal xred FBC;
technology o!ers a unique solution for coal conversion November 1994.
to electric power. The successful commercial operation of IEA coal research reports: Coal prospects in India } perspectives; Octo-
ber 1997.
the Provence 250 MWe CFBC-based power plant at Dallas, W. T. et al. (1997). An update of operating experiences burning
Gardanne, France has demonstrated its entry into the petroleum Coke in a utility scale CFB } The NISCO Co generation
large size utility market. Looking further ahead into the project. International Conference on FBC * ASME.
next century, CFBC-based Combined Cycle Power plant Pierre Lucor et al. (1997). Large CFB boilers: With Provence/gardanne
utilising coal is expected to be the ultimate solution to start-up. (This novel technology has now passed the 250 MWe
mark). International Conference, Green Power * the need for the 21st
electricity production from coal. Century.
Skowyra, R.S. et al. (1995). Design of super critical sliding pressure
circulating #uidised-bed boiler with vertical water walls. Interna-
Acknowledgements tional Conference on FBC * ASME.

The author wishes to thank the management of BHEL


for having given permission to publish this paper and to
the colleagues in his group for their assistance.

You might also like