Instructions to Offerors
1.1 Proposal Submittal
Proposal submittals shall be sent to CH2M HILL’s contract administrator Daena Mulleitner at
dmulleit@ch2m.com and/or via mail to CH2M HILL’s Denver office 9191 South Jamaica Street,
Englewood, CO, 80112-5946, USA. The offerer shall submit the following as part of the
proposal package:
• Organization Chart: Identify the site superintendents for each project, as well as any
lower-tier Subcontractors that will be used, and the proposed project management
team
• Preparing and submitting Statement of Qualifications, resumes for key personnel, and all
Health and Safety Plans, as required. All site superintendents conducting work at the site
must have OSHA 30 hour training, or be willing to attend such training at their expense
provided by CH2M HILL at the selected QC Subcontractor’s offices. Certificates of training
must be included in prework submittals if available.
• Providing the necessary supervision, labor, and materials and any supporting
subcontractors to complete the scope of work as identified herein and in the project
drawings and specifications.
• Provide all labor, equipment, and materials to mobilize personnel and equipment to the site
at the beginning of the project and fully demobilize personnel, materials, and equipment
from the site at the end of the project. Subcontractor pricing will include all setup of storage
area and base of operations, acquisition of Personal Protective Equipment (PPE), and all
other tasks to initially prepare for the execution of work at these facilities.
• Performing all field activities (including associated quality control and testing) required to
complete the scope of work identified in this Statement of Work (SOW). The general
description of the work is provided below, but may not be all inclusive.
• Performing all field activities in accordance with US Army Corps of Engineers Health and
Safety manual (EM-385), as well as in compliance with all Host Nation laws, regulations,
and engineering and licensing requirements.
− Identifying a minimum of three capable and experienced D-B Subcontractors for each
project or construction package. Demonstrate Subcontractor qualifications to the
CH2M HILL PM.
− Utilizing the project packages presented with this RFP (Attachment A), prepare
Schedule of Values (SOV), develop and translate conceptual designs that can adequately
serve as the basis for bidding by the nominated D-B Subcontractors, with review by the
CH2M HILL PM. Prepare a cost estimate for each project.
− Coordinating and conducting site walks at each project site, providing necessary
transportation for CH2M HILL personnel.
− Acting as the POC during solicitation activities, directing questions to the CH2M HILL
POC, and providing recommendations for responses.
− Providing any required support in obtaining local permits, establishing MOUs, and
providing support for governmental and stakeholder relations.
− Acting as POC with D-B Subcontractors for distribution of contract amendments, etc.,
and acting as the receipt point for submitted proposals.
− Assisting CH2M HILL in getting contract documents in place, providing any necessary
translation, and facilitating signing of the D-B construction contract.
− Prepare QC Subcontractor Quality Control and H&S plans specific to the projects to be
designed and constructed. Prepare the QC plan in accordance with the CH2M HILL
Construction Quality plan attached to this RFP (Attachment B). Multiple projects may be
included in these plans, as long as site specific issues are properly documented.
− Provide three copies of the approved, final design drawings and specifications to the
CH2M HILL PM.
− Work with the D-B Subcontractors to assist them to develop site specific Health and
Safety (H&S) and Quality Control plans that meet US Army Corps of Engineers
standards. The H&S plan shall include an Accident Prevention Plan and an Activities
Hazard Analysis. It is permissible to include multiple project sites in these plans if being
implemented by the same D-B Subcontractor, and if site specific issues are clearly
identified and documented.
− Assist and guide the D-B Subcontractor in preparing all required work plans, submittal
registers, testing plans for all project work. Provide these for review and comment to the
CH2M HILL PM. Ensure these plans are properly revised in response to CH2M HILL
comments.
− Assist and guide the D-B Subcontractor in preparing final H&S plan, APPs, and AHAs.
Provide these for review and comment to the CH2M HILL PM. Ensure these plans are
properly revised in response to CH2M HILL comments.
− Coordinate with D-B Subcontractor during mobilization to the site, assuring that all
required planning, equipment, materials, etc. have been appropriately mobilized.
Conduct an Operational Readiness Review with the Subcontractor and CH2M HILL PM
to ensure readiness to begin construction work.
− Organize and lead a preconstruction meeting for each project, providing a suitable space
for the meeting. Prepare a meeting agenda and distribute to appropriate parties per
direction from the CH2M HILL PM.
− Ensure that D-B Subcontractor’s activities are completely in accordance with the HSP
and AHAs at all times. Monitor D-B Subcontractor to ensure that daily tailgate meetings
EXHIBIT H TO FORM SFCS – ENVIRONMENTAL REMEDIATION SUPPLEMENT
SHORT FORM CONSTRUCTION SUBCONTRACT
(VERSION 05-03) PAGE 7
are conducted to discuss the day’s activities and the potential H&S issues that may be
associated with those activities. Stop work of D-B Subcontractor if they are performing
in an unsafe manner or refuse to follow H&S plans and protocols.
− Provide full time inspection services during construction in accordance with the QC
Subcontractor’s QC plan and the CH2M HILL Construction Quality plan. Ensure that
the D-B Subcontractor fully implements the approved design and specifications, unless
deviations are approved by the CH2M HILL PM.
− Have access to a cellular phone and be available for discussions with the CH2M HILL
PM on a minimum semi-weekly basis.
− Prepare daily and weekly reports in a typed format per the QC plan. Provide
photographic documentation of key activities with each report. Submit reports to
CH2M HILL on a daily basis unless otherwise directed by the CH2M HILL PM.
− If unforeseen conditions arise, Requests for Information (RFIs) are submitted by the D-B
Subcontractor, or a Change Order is requested by the D- B Subcontractor, the QC
Subcontractor shall research the issue, provide a written description and
recommendation for resolution to the CH2M HILL PM, and track the issue until it is
fully resolved. Maintain a tracking log of all RFIs and Change Orders.
− Do not waive contract provisions, make or authorize changes to the contract design or
specifications, dictate the construction Subcontractor operations, allow the construction
Subcontractor to perform in an unsafe manner, or accept work not meeting contract
requirements without coordination with and specific written approval from CH2M
HILL PM.
− Immediately notify the CH2M HILL PM of any situation that may result in a contract
dispute, require a modification to the contract, or require issuing a stop work order to
the D-B Subcontractor. In any event, a complete record of the facts shall be developed
and submitted to the CH2M HILL PM.
− Provide an update of the Subcontractor’s schedule and testing plan by the 25th of each
month.
− Review as-built drawings on a minimum weekly basis and provide final review of as-
builts prepared by the D-B Subcontractor at the conclusion of the project. Furnish the as-
builts for CH2M HILL review, and ensure that all comments are properly incorporated.
Ensure that any warranty, O&M, material or equipment specifications are submitted to
the CH2M HILL PM. Provide three copies of the final as-builts and other materials, with
one copy in an electronic format, preferably CAD.
− The QC Subcontractor shall review and verify all requests for progress payments to
ensure the request accurately represents work accomplished satisfactorily. The QC
Subcontractor shall complete and sign the pay request certification form that will be
forwarded to the CH2M HILL Contract Administrator (KA) for payment. The final
request for payment shall contain, in addition to a completed and signed pay request
form, a listing which depicts the final document submittals (i.e. as-builts, operation and
maintenance manuals, etc.) as well as the date of acceptance of these documents. The
listing shall be dated and signed by the construction Subcontractor and the QC
Subcontractor.
• Traffic controls
• Maintaining appropriate security (i.e., safety barricades with fencing and barricades, and
appropriate warning signage. Properly securing site at the end of each day.
• Keeping all work areas clean, neat, and maintained at all times.
• Protecting existing security fence/gates, structures, surface features, service operations and
the general site environment.
• Identifying and protecting all utilities, above and below ground, in the designated work
areas. Utilities shall be identified by reviewing appropriate drawings, conducting utility
toning, and performing site visits with appropriate Base utility representatives.
EXHIBIT H TO FORM SFCS – ENVIRONMENTAL REMEDIATION SUPPLEMENT
SHORT FORM CONSTRUCTION SUBCONTRACT
(VERSION 05-03) PAGE 9
• Implementing a lock-out/tag-out program on all utilities to be cut to facilitate work
activities, including temporary diversion of storm water run-off. Care shall be taken to close
all upgradient valves on product supply lines prior to cutting and draining activities.
4.2 Supervision
The QC Subcontractor shall identify a Project Manager (PM) to manage this project from project
award through project completion. The PM shall be the primary POC for correspondence
related to cost, schedule, and scope, as well as for providing all required submittals.
During construction, the QC Subcontractor shall maintain adequate on-site supervision at all
times when work is being performed. A designated Site Superintendent shall be identified for
each project site who shall be responsible for field execution and safety of all work being
conducted. The Site Superintendent shall have at least 2 years of previous experience with
similar construction projects, preferably with HA projects in Indonesia.
Resumes for the PM and Superintendent shall be provided with the proposal, and shall
document experience for each person managing and overseeing similar construction projects.
Personnel changes of the PM and Superintendent shall only be made upon prior approval from
CH2M HILL.
• The response should include a narrative explanation of the resolution and attach any
drawings or specifications required to complete the work.
• Reviewing and certifying all submittals for compliance with the project plans, drawings,
and specifications
On a weekly basis (during weekly progress meetings), the QC Subcontractor shall provide a
summary of work accomplished, a two-week look ahead projection, and a revised construction
schedule reflecting any changes that have been identified during the week. This shall also
include copies of any test reports, material receiving reports/receipts/packing slips (as required
to verify the quality of the materials received), and waste disposal tickets (if applicable).
7.0 Schedule
The Subcontractor shall submit a construction schedule for performing the various activities
required to complete all work required.
QC Subcontractor support for D-B Subcontractor procurement will begin immediately upon
award, and must be completed within 2 months. The submittal of the Work Plan will be
required within 45 days of notice to proceed. Design work must be completed within 4 months
of NTP. CH2M HILL requires that all work be completed over a maximum 15 month period of
EXHIBIT H TO FORM SFCS – ENVIRONMENTAL REMEDIATION SUPPLEMENT
SHORT FORM CONSTRUCTION SUBCONTRACT
(VERSION 05-03) PAGE 16
time. The Subcontractor shall notify CH2M HILL if this schedule is not acceptable, prior to
accepting the Subcontract. Exceptions to this schedule preference must be made as part of the
cost proposal. The final schedule must be closely coordinated with CH2M HILL to ensure
minimal unanticipated disruptions are experienced.