Professional Documents
Culture Documents
CT T K
N
i
i
(3.1)
Table 3. Assembly processes by placing M/C and tester
14 Implementation and Line Balancing of Assembly Line of ABS Motor
for Improvement of Assembly Productivity
% 6 . 90 % 100 ) )( (
1
'
CT K T LE
N
i
i
(3.2)
Fig. 8 Alternative of assembly line by line balancing
The indices are used when it is compared that assembly line balancing and work allocation of
more than one. Line efficiency is good value if its value is high, and bad value if its value is low.
If value of smoothness index is low, line balancing improves than value of smoothness index is
high.
In Table 3, line efficiency and smoothness index, which are calculated by standard work
assignment method, are resulted as good value when it produce 5000 motors per month. But
relatively, improved heuristic method is given as bad value because this value is only dependent
on cycle time. Therefore, when motor is produced number of 5000, it is best way to allocate by
using the table of standard work assignment, and then experientially repeating trade-off, that is,
assignment value of workstation in this table. Both of improved heuristic method and Kilbriede-
wester method can be proposed as appropriate heuristic method in case of number of 10,000.
And standard work assignment method and improved heuristic method can be proposed as
appropriate heuristic method in case of number of 15,000, both heuristic methods are show in as
the same results, 90.6% of line efficiency and 11.5% of smoothness index. Though two heuristic
methods have a same value of LE and SI as shown in Table. 3, they have a little difference of
types and number of assembly task that are allocated to the worker.
As shown in Fig. 8, in case of number of 10,000 per month, U-line can be considered as
improved heuristic method and Kilbriede-wester method considering optimal work allocation,
transporting pass of work, type of work and work sequence. As shown in Fig. 8, in case of
15,000 per month, U-line cab be considered as standard work allocation method, optimal work
allocation, transporting pass of work, type of work and work sequence.
5 . 11 ) (
1
max
N
i
i
T T SI (3.3)
Production vol. 15000 /month
CT 54 sec No. of worker 5 CT 81 sec No. of worker 3
Production vol. 10000 /month
Sticker,
packing
Airtight
test
Aging
Load
checker
Magnet
ization
of
magnet
Bolting
Silicone
application,
yoke
insertion
Pig tail
control,
air supply
Bearing
and yoke
assembler
Holder
and yoke
assembler
Magnet
and holder
assembler
Spring
insertion to
brush holder
Grommet
insertion
H
bolting
Rotor
And
bearing
assembler
Air supply,
O- ring
insertion,
grease
1
2
3
Sticker,
packing
Airtight
test
Aging
Load
checker
Magnet
ization
of
magnet
Bolting
Silicone
application,
yoke
Pig tail
control,
air supply
Bearing
and yoke
assembler
Holder
and yoke
assembler
Magnet
and holder
assembler
Spring
insertion to
brush holder
Grommet
insertion
H
bolting
Rotor
And
bearing
assembler
Air supply,
O-ring
insertion,
grease
5
4
2
1
3
Production vol. 15000 /month
CT 54 sec No. of worker 5 CT 81 sec No. of worker 3
Production vol. 10000 /month
Sticker,
packing
Airtight
test
Aging
Load
checker
Magnet
ization
of
magnet
Bolting
Silicone
application,
yoke
insertion
Pig tail
control,
air supply
Bearing
and yoke
assembler
Holder
and yoke
assembler
Magnet
and holder
assembler
Spring
insertion to
brush holder
Grommet
insertion
H
bolting
Rotor
And
bearing
assembler
Air supply,
O- ring
insertion,
grease
1
2
3
Sticker,
packing
Airtight
test
Aging
Load
checker
Magnet
ization
of
magnet
Bolting
Silicone
application,
yoke
Pig tail
control,
air supply
Bearing
and yoke
assembler
Holder
and yoke
assembler
Magnet
and holder
assembler
Spring
insertion to
brush holder
Grommet
insertion
H
bolting
Rotor
And
bearing
assembler
Air supply,
O-ring
insertion,
grease
5
4
2
1
3
BK21LogisticsTeam, July2000 15
Table 4. Work allocation of each worker
If the target product volume is number of 10,000, the cycle time is 81second. And in this time, 3
workers are needed for one motor production. If the target product volume is number of 15,000,
cycle time is 54second. And in this time, 5 workers are needed for one motor production.
Table 4 shows an allocating process of worker, work time and movement distance. W is worker,
S is work sequence, P is allocated process and D is movement distance. The number of
allocated process, assembly time and movement distance of each work is different. But total
assembly time and movement distance can be adjusted uniformly by line balancing. Like
automation assembly, in case of automatic assembly and manual assembly is mixed, its total
work time of each work has to similar through line balancing. Specially, movement distance has
to be considered. Because movement distance of figure shows the case of when one motor is
produced. If the number of motor is many, movement distance can be different.
Therefore, it has to accomplish work exchange per time and work reallocation through
determination of movement distance of each work and degree of work fatigue, etc.
Production volume: 10,000units/month
W S P T D W S P T D
1 11 34 2.3 6 7 14 0.7
2 8 28 0.8 7 6 10 0.8
3 2 12 0.7
2
Sum 80 5.3
1
Sum 74 3.8 1 10 10 3.7
1 1 15 1.0 2 12 15 0.7
2 3 8 0.7 3 13 16 0.6
3 9 10 0.7 4 14 15 1.2
4 5 15 0.8 5 15 16 0.5
2
5 4 8 0.6
3
Sum 72 6.7
Production volume: 15,000units/month
W S P T D W S P T D
1 1 15 1.3 1 8 28 0.8
2 2 12 0.6 2 9 10 1.0
3 3 8 0.4 3 10 10 1.0
4 4 8 1.2
3
Sum 48 3.8
1
Sum 43 3.5 1 11 34 1.2
1 5 15 1.2 2 12 15 1.2
2 6 10 0.8
4
Sum 49 2.4
3 7 14 1.0 1 13 16 2.0
2
Sum 39 3.0 2 14 15 0.7
3 15 16 0.8
Unit: time-sec., distance-m
5
Sum 47 3.5
16 Implementation and Line Balancing of Assembly Line of ABS Motor
for Improvement of Assembly Productivity
4 Conclusion
In this research, we implemented a assembly system of final assembly process of automobile
ABS motor. There are 4 subassemblies of ABS motor; yoke, housing, grommet, and armature.
But we can't automate these completely because of their geometric and assembly process
characteristics and some considerations of assembly cost, required place, etc.
So, we constructed mixing form of automation assembly and manual assembly. First, we
established assembly order with grasp of assembly process. Second, we classified the whole
assembly process into each unit and decided the automation possibility of each process. In
manual assembly, we decided methods of transporting, arrangement, feeding and joining, and in
automation assembly, we determined machinery equipment according to assembly mechanism.
And we also make U-line layout for efficient arrangement of assembly equipment that is
decided by unit process.
It helps to minimize time of worker's movement and assembly. Finally, we allocated assembly
work of each worker by realizing assembly line balancing after deciding the number of workers
who can produce the target yield. And we estimated the efficiency of constructed assembly line
with the index of line estimation like as line efficiency and leveling index.
BK21LogisticsTeam, July2000 17
5 Reference
Boothroyd, G., 1991, Assembly Automation and Product Design, Marcel Dekker, Inc., 1991,
pp.181-208.
Elsayed A., Thomas O., 1994, Analysis and Control of Production System, Prentice Hall, pp.
344-402.
Francis, R. L., McGinnis, L. F. and White, J. A., 1992, Facility Layout and Location: An
Analytical Approach, Prentice Hall, pp.27-184.
Frank J., 1996, Assembly Automation, Industrial Press Inc., pp. 47-77.
Lotter, B., 1989, Manufacturing Assembly Handbook, Butterworths, pp.303-383.
Redford, A. and Chal, J., 1994, Design for Assembly, McGraw-Hill, Inc., pp. 75-134.
Rosari, L. M., 1989, Design for Assembly Analysis: Extraction of Geometric Features from a
CAD System Data Base, Annals of the CIRP, vol. 38, No. 1, pp. 13-16h
Schmidt, L. C. and Jackman, J., 1995, Evaluating Assembly Sequences for Automatic Assembly
Systems, IIE Transactions, 27. pp.23-31.
Thomas E., 1991, William L., and Clay W., Manufacturing Planning and Control System,
IRWIN, pp. 120-154.