You are on page 1of 2

Ammar bin Yasir street Nazir Colony Bahawalnagar, Punjab, Pakistan Khuram_fayyaz@yahoo.

com, Phone # 0092-333-6307785

: Looking for a highly challenging position as a mechanical engineer that will not only

provide me with a rewarding experience of working with the best minds of the profession but also allow me to contribute my very best to the organization.

:
Aug-2010 Present

Nishat Chunian Power Limited is a Combined Cycle, Independent Power Plant supplying electricity to national grid of Pakistan. The plant has a gross capacity of 200MWe that includes 11 x W18V46 reciprocating engines of Wartsila (17.4MWx11) 11x HRSG boilers of Alborg having a total steam generation capacity of 80 ton/hr 1 steam turbine of Dresser Rand. (14MW) 1 black start unit of Volvo Penta to start up the plant in case of black out (450KW) 6 Fuel oil separators of Alfa Laval. Each engine has associated lube oil purifier of Alfa Laval. Water treatment unit (Reverse Osmosis Plant) Oily water treatment Unit Central HVAC system Fire fighting System I joined NCPL as a Trainee Engineer in Aug, 2010. After successful completion of trainee period I was promoted to Assistant Engineer Mechanical. Worked as Assistant Mechanical Engineer since Dec, 2010.Promoted to Mechanical Engineer in August 2011 and since then Working as a Mechanical engineer in this power plant. Helping maintenance department in equipment maintenance. Managing total plant equipment health and make changes to improve performance of plant. Keeping up preventative maintenance work schedule. Responsible for project management. Initiate, suggest and adopt best practices. Completed documentation and project planning to plant maintenance personnel and oversee fabrication of those projects. Maintained and modified different systems of plants to enhance reliability and efficiency. Prepared budgetary estimates for projects. Forecasted, supervised and encouraged minimal usage of campus energy. Documented and coordinated power purchaser related activities. Prepare daily and monthly reports, energy and capacity payment invoices according to Power purchase agreement. Analyze plant data to discover and fix problem areas. Manage and control spare parts inventory and consumables. Here I have following hands on work experience.
Performed 1K,2K,3K,4K,6K,8K,10K,12K hours maintenance & major overhaul of W18V46. Performed first year annual inspection of STG. Performed and supervised periodic inspection and necessary maintenance of HRSG boiler. Performed periodic inspection and overhaul of lube and fuel oil separators of Alfa Laval.

Worked on screw type instrument air compressor of Gardner Denver. Worked on reciprocating type starting air compressor of Sperre. Worked on the different types of pumps like HRSG feed water and circulation pumps, cooling tower circulation pumps, lube oil and fuel oil pumps.

Mechanical Engineer CDMPAK

September, 2009 July, 2010

CDMPAK is a consultancy firm that advised and guided various industries on instituting impreovements specifically regarding productivity and efficiency; devised solutions that reduce emissions and wastes throughout plant facilities. Served as liaison between clients, vendors, co- workers, and all other key players.Transformed complex company ideas into innovative solutions. I had given the following key responsibilities at the CDMPAK. Technical Evaluation of the proposed project Development of the Project Design Document Project management Energy Audits, and CDM Cycle Consultancy

Education
Bachelor of Science in Mechanical Engineering University of Engineering & Technology Taxila, Paksitan 2009

Professional Trainings
Energy Audit Heat rate improvement of combined cycle power plant October, 2009 October, 2011

Key Skills Strong team management abilities and capable of managing a team of twenty-five Proficient to handle a project individually as per requirements of the client Excellent coordinating and communicating skills that can convince the client to invest in the product Good knowledge of the updated techniques and strategies used in maintenance planning for the enhancement of process of production Capable of training the newly joined employees and acquainting them with the rules and regulations of the organization Brilliant awareness of all the Mechanical Engineering work related computer applications like AutoCAD, Pro-E, Catia, Fluent, Leap, Cool pack and Microsoft Word, Microsoft Excel and Microsoft PowerPoint applications Internship Tripack films Limited Fecto Cement Plant References: Available on request September, 2008 March,2009