Client: MUSCAT MUNICIPALITY

Activity ID Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 707d 14-Feb-10 707d 14-Feb-10 707d 14-Feb-10 Finish Jan F 17-May-12 Feb-10 17-May-12 Feb-10 17-May-12 Feb-10 Feb-10 04-Apr-10 12-Mar-12 25-Dec-11 17-May-12 17-May-12 15-Nov-10 19-May-10 15-Nov-10 03-Jun-10 18-Jul-10 18-Jul-10 19-May-10 18-Jul-10 18-Jul-10 03-Aug-10 03-Oct-10 27-Nov-10 Feb-10 01-Jul-10 Feb-10 04-Mar-10 19-Apr-10 09-Jun-10 01-Jul-10 17-May-10 30-Sep-10 30-May-10 30-May-10 28-Jun-10 05-Jul-10 31-Jul-10 07-Aug-10 14-Sep-10 30-Sep-10 03-Jul-10 10-Jul-10 18-Jul-10 25-Jul-10 24-Jul-10 19-Jun-10 24-Jun-10 24-Jun-10 19-May-10 24-Jul-10 19-May-10 01-Jul-10 04-Apr-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

AL ATHAIBAH INTERCHANGE PROJECT


GENERAL
MILESTONES
ENG-DC-0500 GEN-MO-0500 GEN-MO-2000 GEN-MO-2100 GEN-MO-2200 GEN-MO-3000 Appointment of Design Consultant by Contractor Issue of LOI by Client Completion of Flyover Widening Works Completion of Wadi Bridge Works Completion of All Road Works COMPLETION OF OVERALL PROJECT Completion of Mobilization Site Taking Over Submission of Gurantees & Insurances Finalize Engineer's Office Mobilize and Furnish Engineer's Office Finalize and Establish Contractors Office Establish of Site Laboratory Approval and Erection of Project Sign Board Contractor's Labour Camp Set-up Getting all Necessary Approval from Depts.

J Jul 17-May-12 17-May-12 17-May-12

0d 14-Feb-10* 0d 04-Apr-10* 0d 0d 0d 0d 194d 04-Apr-10 40d 04-Apr-10 194d 04-Apr-10 14d 19-May-10 52d 19-May-10 52d 19-May-10 40d 04-Apr-10 52d 19-May-10 52d 19-May-10 105d 04-Apr-10 157d 04-Apr-10 246d 14-Feb-10 119d 14-Feb-10 17d 14-Feb-10 39d 06-Mar-10 44d 20-Apr-10 19d 10-Jun-10 52d 18-Mar-10 116d 19-May-10 10d 19-May-10 10d 19-May-10 28d 27-May-10 6d 29-Jun-10 26d 01-Jul-10 6d 01-Aug-10 27d 15-Aug-10 14d 15-Sep-10 28d 01-Jun-10 6d 04-Jul-10 52d 19-May-10 32d 19-Jun-10 57d 19-May-10 27d 19-May-10 27d 25-May-10 27d 25-May-10

12-Mar-12 25-Dec-11 17-May-12 17-May-12 15-Nov-10

MOBILIZATION
GEN-MO-0750 GEN-MO-1000 GEN-MO-1020 GEN-MO-1040 GEN-MO-1060 GEN-MO-1080 GEN-MO-1100 GEN-MO-1120 GEN-MO-1140 GEN-MO-1160

ENGINEERING
DESIGN DATA COLLECTION
ENG-DC-1000 ENG-DC-1020 ENG-DC-1040 ENG-DC-1060 ENG-DC-1080 ENG-DW-1000 ENG-DW-1020 ENG-DW-1040 ENG-DW-1060 ENG-DW-1080 ENG-DW-1100 ENG-DW-1120 ENG-DW-1140 ENG-DW-1160 ENG-DW-1180 ENG-DW-1200 ENG-DW-1220 ENG-TW-1000 ENG-TW-1020 ENG-TW-1040 Remaining Level of Effort Actual Work Remaining Work Traffic Data Collection and Submission of Report Hydrological Study Geotechnical Investigation and Report Preparation Obtaining Data on Utilities - Electrical, Water, Omantel, Nawras ... Obtaining Data from Ministry of Housing General Plans - Submission to Client Approval from Client (General Plans) Civil Plans - Submission to Client Approval from Client (Civil Plans) Street Lighting Plans - Submission to Client Approval from Client (Street lighting Plans) Traffic Signal Plans - Submission to Client Approval from Client (Traffic Signal Plans) Utility Layout Plans - Submission to Client Approval from Client (Utility Layout Plan) Structural Plans - Submission to Client Approval from Client (Structural Plans) Flyover - Girder Fabrication Drg. Submission Approval from Client / Consultant Wadi Bridge - Girder Fabrication Drg. Submission Critical Remaining Work Milestone Summary

27-Nov-10

DESIGN DRAWINGS - PARSONS

30-Sep-10

TEMPORARY WORKS DRAWINGS - IET

Page 1 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID ENG-TW-1060 ENG-TW-1080 ENG-TW-1100 ENG-TW-1120 ENG-TW-1140 ENG-TW-1160 ENG-TW-1180 ENG-TW-1200 ENG-TW-1220 Activity Name Approval from Client / Consultant Flyover - Footing, Pier and Pier Cap, Abut Drg. Subm. Approval from Client / Consultant Wadi Bridge - Pile cap, pier, Pier cap and Abut Drg. Subm. Approval from Client / Consultant Retaining Wall Drg. and Methodology Subm. Approval from Client / Consultant Casting Yard Drg. Submission Approval from Client / Consultant

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 27d 31-May-10 27d 31-May-10 27d 06-Jun-10 27d 06-Jun-10 27d 12-Jun-10 27d 12-Jun-10 27d 17-Jun-10 27d 17-Jun-10 27d 23-Jun-10 63d 19-May-10 54d 19-May-10 54d 19-May-10 51d 02-Jun-10 51d 02-Jun-10 154d 01-Jun-10 142d 01-Jun-10 142d 01-Jun-10 142d 15-Jun-10 142d 15-Jun-10 296d 05-Jun-10 35d 05-Jun-10 14d 15-Jun-10 14d 15-Jun-10 14d 15-Jun-10 9d 30-Jun-10 35d 05-Jun-10 35d 05-Jun-10 14d 15-Jun-10 49d 20-Jun-10 14d 20-Jun-10 14d 26-Jun-10 18d 30-Jun-10 18d 30-Jun-10 27d 15-Jul-10 264d 12-Jul-10 260d 17-Jul-10 120d 12-Jul-10 150d 21-Jul-10 150d 21-Jul-10 150d 16-Aug-10 83d 26-Jun-10 26d 26-Jun-10 78d 01-Jul-10 27d 07-Jul-10 Finish Jan F 30-Jun-10 30-Jun-10 06-Jul-10 06-Jul-10 12-Jul-10 12-Jul-10 18-Jul-10 18-Jul-10 24-Jul-10 31-Jul-10 20-Jul-10 20-Jul-10 31-Jul-10 31-Jul-10 27-Nov-10 13-Nov-10 13-Nov-10 27-Nov-10 27-Nov-10 15-May-11 14-Jul-10 30-Jun-10 30-Jun-10 30-Jun-10 10-Jul-10 14-Jul-10 14-Jul-10 30-Jun-10 15-Aug-10 05-Jul-10 11-Jul-10 20-Jul-10 20-Jul-10 15-Aug-10 15-May-11 15-May-11 28-Nov-10 11-Jan-11 11-Jan-11 06-Feb-11 29-Sep-10 25-Jul-10 29-Sep-10 07-Aug-10 26-Jun-10 12-Jul-10 20-Jun-10 05-Jun-10 05-Jun-10 14-Jul-10 15-Jun-10 01-Jun-10 01-Jun-10 02-Jun-10 19-May-10 19-May-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

SUBMISSION & APPROVAL OF MAS (50 Nos)


Submissions
ENG-MAS-1000 Submission of MAS (50 Nos.) Approval of MAS (50 Nos.)

31-Jul-10 20-Jul-10 31-Jul-10 27-Nov-10 13-Nov-10 27-Nov-10 15-May-11

Approvals
ENG-MAA-1000

SUBMISSION & APPROVAL OF WORK METHODOLOGY (15 Nos)


Submissions
ENG-WMS-1000 Submission of Work Methodology (15 Nos.) Approval of Work Methodology (15 Nos.)

Approvals
ENG-WMA-1000

PROCUREMENT
BULK MATERIAL - FINALISATION
PRO-BMF-1000 PRO-BMF-1020 PRO-BMF-1040 PRO-BMF-1060 PRO-BMF-1080 PRO-BMF-1100 PRO-BMF-1120 PRO-LLI-1000 PRO-LLI-1020 PRO-LLI-1040 PRO-LLI-1060 PRO-LLI-1080 PRO-LLI-1500 PRO-LLI-1520 PRO-LLI-1540 PRO-LLI-1560 PRO-LLI-1580 PRO-FAB-1000 PRO-FAB-1020 PRO-FAB-1040 Remaining Level of Effort Actual Work Remaining Work Borrow Material Granular Sub Base (GSB) Crushed Aggregate Base Course (CABC) Asphalt Concrete Steel Rip Rap Prestressing Strands Elastomeric Bearings Pot Bearings Expansion Joint Material Guard Rail Prestressing Strands (Progressive Delivery) Elastomeric Bearings (Manufature & Final Delivery) Pot Bearings (Manufature & Final Delivery) Expansion Joint Material (Manufature & Final Delivery) Guard Rail (Manufature & Final Delivery) Girder Shutters for Flyover (2 Sets) Girder Shutters for Wadi Bridge (4 Sets) Pier Column Shutter for Flyover Critical Remaining Work Milestone Summary

LONG LEAD ITEMS - FINALISATION

15-Aug-10

LONG LEAD ITEMS - DELIVERY

15-May-11

FABRICATED ITEMS - FINALISATION & DELIVERY

29-Sep-10

Page 2 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID PRO-FAB-1060 PRO-FAB-1080 PRO-FAB-1100 Activity Name Pier Column Shutter for Wadi Bridge Reinforced Concrete Wall Shutter New Jersey Barrier Shutter

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 27d 13-Jul-10 27d 19-Jul-10 27d 25-Jul-10 585d 01-Jun-10 388d 01-Jun-10 229d 01-Jun-10 45d 01-Jun-10 Finish Jan F 12-Aug-10 18-Aug-10 24-Aug-10 12-Apr-12 27-Aug-11 22-Feb-11 22-Jul-10 15-Jul-10 15-Jul-10 22-Jul-10 13-Jul-10 15-Aug-10 08-Aug-10 24-Jul-10 26-Jul-10 27-Jul-10 29-Jul-10 01-Aug-10 03-Aug-10 04-Aug-10 07-Aug-10 08-Aug-10 08-Aug-10 08-Aug-10 25-Jul-10 26-Jul-10 27-Jul-10 29-Jul-10 01-Aug-10 03-Aug-10 04-Aug-10 07-Aug-10 08-Aug-10 08-Aug-10 15-Aug-10 26-Jul-10 27-Jul-10 28-Jul-10 05-Aug-10 08-Aug-10 10-Aug-10 11-Aug-10 14-Aug-10 15-Aug-10 15-Aug-10 26-Jul-10 25-Jul-10 24-Jul-10 24-Jul-10 01-Jun-10 01-Jun-10 01-Jun-10 01-Jun-10 22-Jul-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

CONSTRUCTION
PRECASTING
FLYOVER WIDENING Precast Yard Setup
PCY1-10000 PCY1-10100 PCY1-10200 PCY1-10300 Girder - 01 C01B011000 C01B011020 C01B011040 C01B011060 C01B011080 C01B011100 C01B011120 C01B011140 C01B011160 C01B011180 Girder - 02 C01B021000 C01B021020 C01B021040 C01B021060 C01B021080 C01B021100 C01B021120 C01B021140 C01B021160 C01B021180 Girder - 03 C01B031000 C01B031020 C01B031040 C01B031060 C01B031080 C01B031100 C01B031120 C01B031140 C01B031160 C01B031180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Manufacturing and Availability of Beam Shutters Preparation of Precasting Yard Facilities Preparation & Fixing of Beds (6 Beds) Finalization and Mobilization of Prestressing Agency

12-Apr-12 27-Aug-11 22-Feb-11

39d 01-Jun-10 26d 16-Jun-10 6d 17-Jul-10 18d 23-Jun-10 20d 24-Jul-10 14d 24-Jul-10 1d 24-Jul-10 1d 26-Jul-10 1d 27-Jul-10 2d 28-Jul-10 2d 31-Jul-10 1d 03-Aug-10 1d 04-Aug-10 1d 07-Aug-10 6d 02-Aug-10 1d 08-Aug-10 13d 25-Jul-10 1d 25-Jul-10 1d 26-Jul-10 1d 27-Jul-10 2d 28-Jul-10 2d 31-Jul-10 1d 03-Aug-10 1d 04-Aug-10 1d 07-Aug-10 6d 02-Aug-10 1d 08-Aug-10 18d 26-Jul-10 1d 26-Jul-10 1d 27-Jul-10 1d 28-Jul-10 2d 04-Aug-10 2d 07-Aug-10 1d 10-Aug-10 1d 11-Aug-10 1d 14-Aug-10 6d 09-Aug-10 1d 15-Aug-10

Precasting - 1st Cycle (4 Girders)

15-Aug-10 08-Aug-10

08-Aug-10

15-Aug-10

Page 3 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 04 C01B041000 C01B041020 C01B041040 C01B041060 C01B041080 C01B041100 C01B041120 C01B041140 C01B041160 C01B041180 Girder - 05 C01B051000 C01B051020 C01B051040 C01B051060 C01B051080 C01B051100 C01B051120 C01B051140 C01B051160 C01B051180 Girder - 06 C01B061000 C01B061020 C01B061040 C01B061060 C01B061080 C01B061100 C01B061120 C01B061140 C01B061160 C01B061180 Girder - 07 C02B071000 C02B071020 C02B071040 C02B071060 C02B071080 C02B071100 C02B071120 C02B071140 C02B071160 C02B071180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 17d 27-Jul-10 1d 27-Jul-10 1d 28-Jul-10 1d 29-Jul-10 2d 04-Aug-10 2d 07-Aug-10 1d 10-Aug-10 1d 11-Aug-10 1d 14-Aug-10 6d 09-Aug-10 1d 15-Aug-10 28d 28-Jul-10 22d 28-Jul-10 1d 28-Jul-10 1d 29-Jul-10 1d 31-Jul-10 2d 11-Aug-10 2d 14-Aug-10 1d 17-Aug-10 1d 18-Aug-10 1d 21-Aug-10 6d 16-Aug-10 1d 22-Aug-10 21d 29-Jul-10 1d 29-Jul-10 1d 31-Jul-10 1d 01-Aug-10 2d 11-Aug-10 2d 14-Aug-10 1d 17-Aug-10 1d 18-Aug-10 1d 21-Aug-10 6d 16-Aug-10 1d 22-Aug-10 18d 09-Aug-10 1d 09-Aug-10 1d 10-Aug-10 1d 11-Aug-10 2d 18-Aug-10 2d 21-Aug-10 1d 24-Aug-10 1d 25-Aug-10 1d 28-Aug-10 6d 23-Aug-10 1d 29-Aug-10 Finish Jan F 15-Aug-10 27-Jul-10 28-Jul-10 29-Jul-10 05-Aug-10 08-Aug-10 10-Aug-10 11-Aug-10 14-Aug-10 15-Aug-10 15-Aug-10 29-Aug-10 22-Aug-10 28-Jul-10 29-Jul-10 31-Jul-10 12-Aug-10 15-Aug-10 17-Aug-10 18-Aug-10 21-Aug-10 22-Aug-10 22-Aug-10 22-Aug-10 29-Jul-10 31-Jul-10 01-Aug-10 12-Aug-10 15-Aug-10 17-Aug-10 18-Aug-10 21-Aug-10 22-Aug-10 22-Aug-10 29-Aug-10 09-Aug-10 10-Aug-10 11-Aug-10 19-Aug-10 22-Aug-10 24-Aug-10 25-Aug-10 28-Aug-10 29-Aug-10 29-Aug-10 09-Aug-10 29-Jul-10 28-Jul-10 28-Jul-10

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

2010 M Apr M J Jul A S Oct N 27-Jul-10 15-Aug-10

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 2nd Cycle (4 Girders)

29-Aug-10 22-Aug-10

22-Aug-10

29-Aug-10

Page 4 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 08 C02B081000 C02B081020 C02B081040 C02B081060 C02B081080 C02B081100 C02B081120 C02B081140 C02B081160 C02B081180 Girder - 09 C02B091000 C02B091020 C02B091040 C02B091060 C02B091080 C02B091100 C02B091120 C02B091140 C02B091160 C02B091180 Girder - 10 C02B101000 C02B101020 C02B101040 C02B101060 C02B101080 C02B101100 C02B101120 C02B101140 C02B101160 C02B101180 Girder - 11 C02B111000 C02B111020 C02B111040 C02B111060 C02B111080 C02B111100 C02B111120 C02B111140 C02B111160 C02B111180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 18d 09-Aug-10 1d 09-Aug-10 1d 10-Aug-10 1d 11-Aug-10 2d 18-Aug-10 2d 21-Aug-10 1d 24-Aug-10 1d 25-Aug-10 1d 28-Aug-10 6d 23-Aug-10 1d 29-Aug-10 24d 16-Aug-10 18d 16-Aug-10 1d 16-Aug-10 1d 17-Aug-10 1d 18-Aug-10 2d 25-Aug-10 2d 28-Aug-10 1d 31-Aug-10 1d 01-Sep-10 1d 04-Sep-10 6d 30-Aug-10 1d 05-Sep-10 18d 16-Aug-10 1d 16-Aug-10 1d 17-Aug-10 1d 18-Aug-10 2d 25-Aug-10 2d 28-Aug-10 1d 31-Aug-10 1d 01-Sep-10 1d 04-Sep-10 6d 30-Aug-10 1d 05-Sep-10 18d 23-Aug-10 1d 23-Aug-10 1d 24-Aug-10 1d 25-Aug-10 2d 01-Sep-10 2d 04-Sep-10 1d 07-Sep-10 1d 08-Sep-10 1d 11-Sep-10 6d 06-Sep-10 1d 12-Sep-10 Finish Jan F 29-Aug-10 09-Aug-10 10-Aug-10 11-Aug-10 19-Aug-10 22-Aug-10 24-Aug-10 25-Aug-10 28-Aug-10 29-Aug-10 29-Aug-10 12-Sep-10 05-Sep-10 16-Aug-10 17-Aug-10 18-Aug-10 26-Aug-10 29-Aug-10 31-Aug-10 01-Sep-10 04-Sep-10 05-Sep-10 05-Sep-10 05-Sep-10 16-Aug-10 17-Aug-10 18-Aug-10 26-Aug-10 29-Aug-10 31-Aug-10 01-Sep-10 04-Sep-10 05-Sep-10 05-Sep-10 12-Sep-10 23-Aug-10 24-Aug-10 25-Aug-10 02-Sep-10 05-Sep-10 07-Sep-10 08-Sep-10 11-Sep-10 12-Sep-10 12-Sep-10 23-Aug-10 16-Aug-10 16-Aug-10 16-Aug-10 M Apr M 2010 J Jul A 09-Aug-10

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N 29-Aug-10

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 3rd Cycle (4 Girders)

12-Sep-10 05-Sep-10

05-Sep-10

12-Sep-10

Page 5 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 12 C02B121000 C02B121020 C02B121040 C02B121060 C02B121080 C02B121100 C02B121120 C02B121140 C02B121160 C02B121180 Girder - 13 C03B131000 C03B131020 C03B131040 C03B131060 C03B131080 C03B131100 C03B131120 C03B131140 C03B131160 C03B131180 Girder - 14 C03B141000 C03B141020 C03B141040 C03B141060 C03B141080 C03B141100 C03B141120 C03B141140 C03B141160 C03B141180 Girder - 15 C03B151000 C03B151020 C03B151040 C03B151060 C03B151080 C03B151100 C03B151120 C03B151140 C03B151160 C03B151180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 18d 23-Aug-10 1d 23-Aug-10 1d 24-Aug-10 1d 25-Aug-10 2d 01-Sep-10 2d 04-Sep-10 1d 07-Sep-10 1d 08-Sep-10 1d 11-Sep-10 6d 06-Sep-10 1d 12-Sep-10 24d 30-Aug-10 18d 30-Aug-10 1d 30-Aug-10 1d 31-Aug-10 1d 01-Sep-10 2d 08-Sep-10 2d 11-Sep-10 1d 14-Sep-10 1d 15-Sep-10 1d 18-Sep-10 6d 13-Sep-10 1d 19-Sep-10 18d 30-Aug-10 1d 30-Aug-10 1d 31-Aug-10 1d 01-Sep-10 2d 08-Sep-10 2d 11-Sep-10 1d 14-Sep-10 1d 15-Sep-10 1d 18-Sep-10 6d 13-Sep-10 1d 19-Sep-10 18d 06-Sep-10 1d 06-Sep-10 1d 07-Sep-10 1d 08-Sep-10 2d 15-Sep-10 2d 18-Sep-10 1d 21-Sep-10 1d 22-Sep-10 1d 25-Sep-10 6d 20-Sep-10 1d 26-Sep-10 Finish Jan F 12-Sep-10 23-Aug-10 24-Aug-10 25-Aug-10 02-Sep-10 05-Sep-10 07-Sep-10 08-Sep-10 11-Sep-10 12-Sep-10 12-Sep-10 26-Sep-10 19-Sep-10 30-Aug-10 31-Aug-10 01-Sep-10 09-Sep-10 12-Sep-10 14-Sep-10 15-Sep-10 18-Sep-10 19-Sep-10 19-Sep-10 19-Sep-10 30-Aug-10 31-Aug-10 01-Sep-10 09-Sep-10 12-Sep-10 14-Sep-10 15-Sep-10 18-Sep-10 19-Sep-10 19-Sep-10 26-Sep-10 06-Sep-10 07-Sep-10 08-Sep-10 16-Sep-10 19-Sep-10 21-Sep-10 22-Sep-10 25-Sep-10 26-Sep-10 26-Sep-10 06-Sep-10 30-Aug-10 30-Aug-10 30-Aug-10 M Apr M 2010 J Jul A 23-Aug-10

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N D Jan F 12-Sep-10

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 4th Cycle (4 Girders)

26-Sep-10 19-Sep-10

19-Sep-10

26-Sep-10

Page 6 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 16 C03B161000 C03B161020 C03B161040 C03B161060 C03B161080 C03B161100 C03B161120 C03B161140 C03B161160 C03B161180 Girder - 17 C03B171000 C03B171020 C03B171040 C03B171060 C03B171080 C03B171100 C03B171120 C03B171140 C03B171160 C03B171180 Girder - 18 C03B181000 C03B181020 C03B181040 C03B181060 C03B181080 C03B181100 C03B181120 C03B181140 C03B181160 C03B181180 Girder - 19 C04B191000 C04B191020 C04B191040 C04B191060 C04B191080 C04B191100 C04B191120 C04B191140 C04B191160 C04B191180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 18d 06-Sep-10 1d 06-Sep-10 1d 07-Sep-10 1d 08-Sep-10 2d 15-Sep-10 2d 18-Sep-10 1d 21-Sep-10 1d 22-Sep-10 1d 25-Sep-10 6d 20-Sep-10 1d 26-Sep-10 24d 13-Sep-10 18d 13-Sep-10 1d 13-Sep-10 1d 14-Sep-10 1d 15-Sep-10 2d 22-Sep-10 2d 25-Sep-10 1d 28-Sep-10 1d 29-Sep-10 1d 02-Oct-10 6d 27-Sep-10 1d 03-Oct-10 18d 13-Sep-10 1d 13-Sep-10 1d 14-Sep-10 1d 15-Sep-10 2d 22-Sep-10 2d 25-Sep-10 1d 28-Sep-10 1d 29-Sep-10 1d 02-Oct-10 6d 27-Sep-10 1d 03-Oct-10 18d 20-Sep-10 1d 20-Sep-10 1d 21-Sep-10 1d 22-Sep-10 2d 29-Sep-10 2d 02-Oct-10 1d 05-Oct-10 1d 06-Oct-10 1d 09-Oct-10 6d 04-Oct-10 1d 10-Oct-10 Finish Jan F 26-Sep-10 06-Sep-10 07-Sep-10 08-Sep-10 16-Sep-10 19-Sep-10 21-Sep-10 22-Sep-10 25-Sep-10 26-Sep-10 26-Sep-10 10-Oct-10 03-Oct-10 13-Sep-10 14-Sep-10 15-Sep-10 23-Sep-10 26-Sep-10 28-Sep-10 29-Sep-10 02-Oct-10 03-Oct-10 03-Oct-10 03-Oct-10 13-Sep-10 14-Sep-10 15-Sep-10 23-Sep-10 26-Sep-10 28-Sep-10 29-Sep-10 02-Oct-10 03-Oct-10 03-Oct-10 10-Oct-10 20-Sep-10 21-Sep-10 22-Sep-10 30-Sep-10 03-Oct-10 05-Oct-10 06-Oct-10 09-Oct-10 10-Oct-10 10-Oct-10 20-Sep-10 13-Sep-10 13-Sep-10 13-Sep-10 M Apr M

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

2010 J Jul A S Oct N D Jan F 06-Sep-10 26-Sep-10

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 5th Cycle (4 Girders)

10-Oct-10 03-Oct-10

03-Oct-10

10-Oct-10

Page 7 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 20 C04B201000 C04B201020 C04B201040 C04B201060 C04B201080 C04B201100 C04B201120 C04B201140 C04B201160 C04B201180 Girder - 21 C04B211000 C04B211020 C04B211040 C04B211060 C04B211080 C04B211100 C04B211120 C04B211140 C04B211160 C04B211180 Girder - 22 C04B221000 C04B221020 C04B221040 C04B221060 C04B221080 C04B221100 C04B221120 C04B221140 C04B221160 C04B221180 Girder - 23 C04B231000 C04B231020 C04B231040 C04B231060 C04B231080 C04B231100 C04B231120 C04B231140 C04B231160 C04B231180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 18d 20-Sep-10 1d 20-Sep-10 1d 21-Sep-10 1d 22-Sep-10 2d 29-Sep-10 2d 02-Oct-10 1d 05-Oct-10 1d 06-Oct-10 1d 09-Oct-10 6d 04-Oct-10 1d 10-Oct-10 24d 27-Sep-10 18d 27-Sep-10 1d 27-Sep-10 1d 28-Sep-10 1d 29-Sep-10 2d 06-Oct-10 2d 09-Oct-10 1d 12-Oct-10 1d 13-Oct-10 1d 16-Oct-10 6d 11-Oct-10 1d 17-Oct-10 18d 27-Sep-10 1d 27-Sep-10 1d 28-Sep-10 1d 29-Sep-10 2d 06-Oct-10 2d 09-Oct-10 1d 12-Oct-10 1d 13-Oct-10 1d 16-Oct-10 6d 11-Oct-10 1d 17-Oct-10 18d 04-Oct-10 1d 04-Oct-10 1d 05-Oct-10 1d 06-Oct-10 2d 13-Oct-10 2d 16-Oct-10 1d 19-Oct-10 1d 20-Oct-10 1d 23-Oct-10 6d 18-Oct-10 1d 24-Oct-10 Finish Jan F 10-Oct-10 20-Sep-10 21-Sep-10 22-Sep-10 30-Sep-10 03-Oct-10 05-Oct-10 06-Oct-10 09-Oct-10 10-Oct-10 10-Oct-10 24-Oct-10 17-Oct-10 27-Sep-10 28-Sep-10 29-Sep-10 07-Oct-10 10-Oct-10 12-Oct-10 13-Oct-10 16-Oct-10 17-Oct-10 17-Oct-10 17-Oct-10 27-Sep-10 28-Sep-10 29-Sep-10 07-Oct-10 10-Oct-10 12-Oct-10 13-Oct-10 16-Oct-10 17-Oct-10 17-Oct-10 24-Oct-10 04-Oct-10 05-Oct-10 06-Oct-10 14-Oct-10 17-Oct-10 19-Oct-10 20-Oct-10 23-Oct-10 24-Oct-10 24-Oct-10 04-Oct-10 27-Sep-10 27-Sep-10 27-Sep-10 M Apr M

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

2010 J Jul A S Oct N D Jan F 20-Sep-10 10-Oct-10

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 6th Cycle (4 Girders)

24-Oct-10 17-Oct-10

17-Oct-10

24-Oct-10

Page 8 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 24 C04B241000 C04B241020 C04B241040 C04B241060 C04B241080 C04B241100 C04B241120 C04B241140 C04B241160 C04B241180 Girder - 25 C05B251000 C05B251020 C05B251040 C05B251060 C05B251080 C05B251100 C05B251120 C05B251140 C05B251160 C05B251180 Girder - 26 C05B261000 C05B261020 C05B261040 C05B261060 C05B261080 C05B261100 C05B261120 C05B261140 C05B261160 C05B261180 Girder - 27 C05B271000 C05B271020 C05B271040 C05B271060 C05B271080 C05B271100 C05B271120 C05B271140 C05B271160 C05B271180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 18d 04-Oct-10 1d 04-Oct-10 1d 05-Oct-10 1d 06-Oct-10 2d 13-Oct-10 2d 16-Oct-10 1d 19-Oct-10 1d 20-Oct-10 1d 23-Oct-10 6d 18-Oct-10 1d 24-Oct-10 24d 11-Oct-10 18d 11-Oct-10 1d 11-Oct-10 1d 12-Oct-10 1d 13-Oct-10 2d 20-Oct-10 2d 23-Oct-10 1d 26-Oct-10 1d 27-Oct-10 1d 30-Oct-10 6d 25-Oct-10 1d 31-Oct-10 18d 11-Oct-10 1d 11-Oct-10 1d 12-Oct-10 1d 13-Oct-10 2d 20-Oct-10 2d 23-Oct-10 1d 26-Oct-10 1d 27-Oct-10 1d 30-Oct-10 6d 25-Oct-10 1d 31-Oct-10 18d 18-Oct-10 1d 18-Oct-10 1d 19-Oct-10 1d 20-Oct-10 2d 27-Oct-10 2d 30-Oct-10 1d 02-Nov-10 1d 03-Nov-10 1d 06-Nov-10 6d 01-Nov-10 1d 07-Nov-10 Finish Jan F 24-Oct-10 04-Oct-10 05-Oct-10 06-Oct-10 14-Oct-10 17-Oct-10 19-Oct-10 20-Oct-10 23-Oct-10 24-Oct-10 24-Oct-10 07-Nov-10 31-Oct-10 11-Oct-10 12-Oct-10 13-Oct-10 21-Oct-10 24-Oct-10 26-Oct-10 27-Oct-10 30-Oct-10 31-Oct-10 31-Oct-10 31-Oct-10 11-Oct-10 12-Oct-10 13-Oct-10 21-Oct-10 24-Oct-10 26-Oct-10 27-Oct-10 30-Oct-10 31-Oct-10 31-Oct-10 07-Nov-10 18-Oct-10 19-Oct-10 20-Oct-10 28-Oct-10 31-Oct-10 02-Nov-10 03-Nov-10 06-Nov-10 07-Nov-10 07-Nov-10 18-Oct-10 11-Oct-10 11-Oct-10 11-Oct-10 M Apr M

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

2010 J Jul A S Oct N D Jan F 04-Oct-10 24-Oct-10

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 7th Cycle (4 Girders)

07-Nov-10 31-Oct-10

31-Oct-10

07-Nov-10

Page 9 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 28 C05B281000 C05B281020 C05B281040 C05B281060 C05B281080 C05B281100 C05B281120 C05B281140 C05B281160 C05B281180 Girder - 29 C05B291000 C05B291020 C05B291040 C05B291060 C05B291080 C05B291100 C05B291120 C05B291140 C05B291160 C05B291180 Girder - 30 C05B301000 C05B301020 C05B301040 C05B301060 C05B301080 C05B301100 C05B301120 C05B301140 C05B301160 C05B301180 Girder - 31 C06B311000 C06B311020 C06B311040 C06B311060 C06B311080 C06B311100 C06B311120 C06B311140 C06B311160 C06B311180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 18d 18-Oct-10 1d 18-Oct-10 1d 19-Oct-10 1d 20-Oct-10 2d 27-Oct-10 2d 30-Oct-10 1d 02-Nov-10 1d 03-Nov-10 1d 06-Nov-10 6d 01-Nov-10 1d 07-Nov-10 24d 25-Oct-10 18d 25-Oct-10 1d 25-Oct-10 1d 26-Oct-10 1d 27-Oct-10 2d 03-Nov-10 2d 06-Nov-10 1d 09-Nov-10 1d 10-Nov-10 1d 13-Nov-10 6d 08-Nov-10 1d 14-Nov-10 18d 25-Oct-10 1d 25-Oct-10 1d 26-Oct-10 1d 27-Oct-10 2d 03-Nov-10 2d 06-Nov-10 1d 09-Nov-10 1d 10-Nov-10 1d 13-Nov-10 6d 08-Nov-10 1d 14-Nov-10 18d 01-Nov-10 1d 01-Nov-10 1d 02-Nov-10 1d 03-Nov-10 2d 10-Nov-10 2d 13-Nov-10 1d 16-Nov-10 1d 17-Nov-10 1d 20-Nov-10 6d 15-Nov-10 1d 21-Nov-10 Finish Jan F 07-Nov-10 18-Oct-10 19-Oct-10 20-Oct-10 28-Oct-10 31-Oct-10 02-Nov-10 03-Nov-10 06-Nov-10 07-Nov-10 07-Nov-10 21-Nov-10 14-Nov-10 25-Oct-10 26-Oct-10 27-Oct-10 04-Nov-10 07-Nov-10 09-Nov-10 10-Nov-10 13-Nov-10 14-Nov-10 14-Nov-10 14-Nov-10 25-Oct-10 26-Oct-10 27-Oct-10 04-Nov-10 07-Nov-10 09-Nov-10 10-Nov-10 13-Nov-10 14-Nov-10 14-Nov-10 21-Nov-10 01-Nov-10 02-Nov-10 03-Nov-10 11-Nov-10 14-Nov-10 16-Nov-10 17-Nov-10 20-Nov-10 21-Nov-10 21-Nov-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

A S Oct N D Jan F 18-Oct-10 07-Nov-10

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 8th Cycle (4 Girders)

25-Oct-10 25-Oct-10

21-Nov-10 14-Nov-10

25-Oct-10

14-Nov-10

01-Nov-10

21-Nov-10

Page 10 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 32 C06B321000 C06B321020 C06B321040 C06B321060 C06B321080 C06B321100 C06B321120 C06B321140 C06B321160 C06B321180 Girder - 33 C06B331000 C06B331020 C06B331040 C06B331060 C06B331080 C06B331100 C06B331120 C06B331140 C06B331160 C06B331180 Girder - 34 C06B341000 C06B341020 C06B341040 C06B341060 C06B341080 C06B341100 C06B341120 C06B341140 C06B341160 C06B341180 Girder - 35 C06B351000 C06B351020 C06B351040 C06B351060 C06B351080 C06B351100 C06B351120 C06B351140 C06B351160 C06B351180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 18d 01-Nov-10 1d 01-Nov-10 1d 02-Nov-10 1d 03-Nov-10 2d 10-Nov-10 2d 13-Nov-10 1d 16-Nov-10 1d 17-Nov-10 1d 20-Nov-10 6d 15-Nov-10 1d 21-Nov-10 24d 08-Nov-10 18d 08-Nov-10 1d 08-Nov-10 1d 09-Nov-10 1d 10-Nov-10 2d 17-Nov-10 2d 20-Nov-10 1d 23-Nov-10 1d 24-Nov-10 1d 27-Nov-10 6d 22-Nov-10 1d 28-Nov-10 18d 08-Nov-10 1d 08-Nov-10 1d 09-Nov-10 1d 10-Nov-10 2d 17-Nov-10 2d 20-Nov-10 1d 23-Nov-10 1d 24-Nov-10 1d 27-Nov-10 6d 22-Nov-10 1d 28-Nov-10 18d 15-Nov-10 1d 15-Nov-10 1d 16-Nov-10 1d 17-Nov-10 2d 24-Nov-10 2d 27-Nov-10 1d 30-Nov-10 1d 01-Dec-10 1d 04-Dec-10 6d 29-Nov-10 1d 05-Dec-10 Finish Jan F 21-Nov-10 01-Nov-10 02-Nov-10 03-Nov-10 11-Nov-10 14-Nov-10 16-Nov-10 17-Nov-10 20-Nov-10 21-Nov-10 21-Nov-10 05-Dec-10 28-Nov-10 08-Nov-10 09-Nov-10 10-Nov-10 18-Nov-10 21-Nov-10 23-Nov-10 24-Nov-10 27-Nov-10 28-Nov-10 28-Nov-10 28-Nov-10 08-Nov-10 09-Nov-10 10-Nov-10 18-Nov-10 21-Nov-10 23-Nov-10 24-Nov-10 27-Nov-10 28-Nov-10 28-Nov-10 05-Dec-10 15-Nov-10 16-Nov-10 17-Nov-10 25-Nov-10 28-Nov-10 30-Nov-10 01-Dec-10 04-Dec-10 05-Dec-10 05-Dec-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

A S Oct N D Jan F 01-Nov-10 21-Nov-10

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 9th Cycle (4 Girders)

08-Nov-10 08-Nov-10

05-Dec-10 28-Nov-10

08-Nov-10

28-Nov-10

15-Nov-10

05-Dec-10

Page 11 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 36 C06B361000 C06B361020 C06B361040 C06B361060 C06B361080 C06B361100 C06B361120 C06B361140 C06B361160 C06B361180 Girder - 37 C07B371000 C07B371020 C07B371040 C07B371060 C07B371080 C07B371100 C07B371120 C07B371140 C07B371160 C07B371180 Girder - 38 C07B381000 C07B381020 C07B381040 C07B381060 C07B381080 C07B381100 C07B381120 C07B381140 C07B381160 C07B381180 Girder - 39 C07B391000 C07B391020 C07B391040 C07B391060 C07B391080 C07B391100 C07B391120 C07B391140 C07B391160 C07B391180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 18d 15-Nov-10 1d 15-Nov-10 1d 16-Nov-10 1d 17-Nov-10 2d 24-Nov-10 2d 27-Nov-10 1d 30-Nov-10 1d 01-Dec-10 1d 04-Dec-10 6d 29-Nov-10 1d 05-Dec-10 24d 22-Nov-10 18d 22-Nov-10 1d 22-Nov-10 1d 23-Nov-10 1d 24-Nov-10 2d 01-Dec-10 2d 04-Dec-10 1d 07-Dec-10 1d 08-Dec-10 1d 11-Dec-10 6d 06-Dec-10 1d 12-Dec-10 18d 22-Nov-10 1d 22-Nov-10 1d 23-Nov-10 1d 24-Nov-10 2d 01-Dec-10 2d 04-Dec-10 1d 07-Dec-10 1d 08-Dec-10 1d 11-Dec-10 6d 06-Dec-10 1d 12-Dec-10 18d 29-Nov-10 1d 29-Nov-10 1d 30-Nov-10 1d 01-Dec-10 2d 08-Dec-10 2d 11-Dec-10 1d 14-Dec-10 1d 15-Dec-10 1d 18-Dec-10 6d 13-Dec-10 1d 19-Dec-10 Finish Jan F 05-Dec-10 15-Nov-10 16-Nov-10 17-Nov-10 25-Nov-10 28-Nov-10 30-Nov-10 01-Dec-10 04-Dec-10 05-Dec-10 05-Dec-10 19-Dec-10 12-Dec-10 22-Nov-10 23-Nov-10 24-Nov-10 02-Dec-10 05-Dec-10 07-Dec-10 08-Dec-10 11-Dec-10 12-Dec-10 12-Dec-10 12-Dec-10 22-Nov-10 23-Nov-10 24-Nov-10 02-Dec-10 05-Dec-10 07-Dec-10 08-Dec-10 11-Dec-10 12-Dec-10 12-Dec-10 19-Dec-10 29-Nov-10 30-Nov-10 01-Dec-10 09-Dec-10 12-Dec-10 14-Dec-10 15-Dec-10 18-Dec-10 19-Dec-10 19-Dec-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N 15-Nov-10

D Jan F M Apr M 05-Dec-10

S Oct N

D Jan F

J Jul

Precasting - 10th Cycle (4 Girders)

22-Nov-10 22-Nov-10

19-Dec-10 12-Dec-10

22-Nov-10

12-Dec-10

29-Nov-10

19-Dec-10

Page 12 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 40 C07B401000 C07B401020 C07B401040 C07B401060 C07B401080 C07B401100 C07B401120 C07B401140 C07B401160 C07B401180 Girder - 41 C07B411000 C07B411020 C07B411040 C07B411060 C07B411080 C07B411100 C07B411120 C07B411140 C07B411160 C07B411180 Girder - 42 C07B421000 C07B421020 C07B421040 C07B421060 C07B421080 C07B421100 C07B421120 C07B421140 C07B421160 C07B421180 Girder - 43 C08B431000 C08B431020 C08B431040 C08B431060 C08B431080 C08B431100 C08B431120 C08B431140 C08B431160 C08B431180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 18d 29-Nov-10 1d 29-Nov-10 1d 30-Nov-10 1d 01-Dec-10 2d 08-Dec-10 2d 11-Dec-10 1d 14-Dec-10 1d 15-Dec-10 1d 18-Dec-10 6d 13-Dec-10 1d 19-Dec-10 24d 06-Dec-10 18d 06-Dec-10 1d 06-Dec-10 1d 07-Dec-10 1d 08-Dec-10 2d 15-Dec-10 2d 18-Dec-10 1d 21-Dec-10 1d 22-Dec-10 1d 25-Dec-10 6d 20-Dec-10 1d 26-Dec-10 18d 06-Dec-10 1d 06-Dec-10 1d 07-Dec-10 1d 08-Dec-10 2d 15-Dec-10 2d 18-Dec-10 1d 21-Dec-10 1d 22-Dec-10 1d 25-Dec-10 6d 20-Dec-10 1d 26-Dec-10 18d 13-Dec-10 1d 13-Dec-10 1d 14-Dec-10 1d 15-Dec-10 2d 22-Dec-10 2d 25-Dec-10 1d 28-Dec-10 1d 29-Dec-10 1d 01-Jan-11 6d 27-Dec-10 1d 02-Jan-11 Finish Jan F 19-Dec-10 29-Nov-10 30-Nov-10 01-Dec-10 09-Dec-10 12-Dec-10 14-Dec-10 15-Dec-10 18-Dec-10 19-Dec-10 19-Dec-10 02-Jan-11 26-Dec-10 06-Dec-10 07-Dec-10 08-Dec-10 16-Dec-10 19-Dec-10 21-Dec-10 22-Dec-10 25-Dec-10 26-Dec-10 26-Dec-10 26-Dec-10 06-Dec-10 07-Dec-10 08-Dec-10 16-Dec-10 19-Dec-10 21-Dec-10 22-Dec-10 25-Dec-10 26-Dec-10 26-Dec-10 02-Jan-11 13-Dec-10 14-Dec-10 15-Dec-10 23-Dec-10 26-Dec-10 28-Dec-10 29-Dec-10 01-Jan-11 02-Jan-11 02-Jan-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N D Jan F M Apr M 29-Nov-10 19-Dec-10

S Oct N

D Jan F

J Jul

Precasting - 11th Cycle (4 Girders)

06-Dec-10 06-Dec-10

02-Jan-11 26-Dec-10

06-Dec-10

26-Dec-10

13-Dec-10

02-Jan-11

Page 13 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 44 C08B441000 C08B441020 C08B441040 C08B441060 C08B441080 C08B441100 C08B441120 C08B441140 C08B441160 C08B441180 Girder - 45 C08B451000 C08B451020 C08B451040 C08B451060 C08B451080 C08B451100 C08B451120 C08B451140 C08B451160 C08B451180 Girder - 46 C08B461000 C08B461020 C08B461040 C08B461060 C08B461080 C08B461100 C08B461120 C08B461140 C08B461160 C08B461180 Girder - 47 C08B471000 C08B471020 C08B471040 C08B471060 C08B471080 C08B471100 C08B471120 C08B471140 C08B471160 C08B471180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 18d 13-Dec-10 1d 13-Dec-10 1d 14-Dec-10 1d 15-Dec-10 2d 22-Dec-10 2d 25-Dec-10 1d 28-Dec-10 1d 29-Dec-10 1d 01-Jan-11 6d 27-Dec-10 1d 02-Jan-11 24d 20-Dec-10 18d 20-Dec-10 1d 20-Dec-10 1d 21-Dec-10 1d 22-Dec-10 2d 29-Dec-10 2d 01-Jan-11 1d 04-Jan-11 1d 05-Jan-11 1d 08-Jan-11 6d 03-Jan-11 1d 09-Jan-11 18d 20-Dec-10 1d 20-Dec-10 1d 21-Dec-10 1d 22-Dec-10 2d 29-Dec-10 2d 01-Jan-11 1d 04-Jan-11 1d 05-Jan-11 1d 08-Jan-11 6d 03-Jan-11 1d 09-Jan-11 18d 27-Dec-10 1d 27-Dec-10 1d 28-Dec-10 1d 29-Dec-10 2d 05-Jan-11 2d 08-Jan-11 1d 11-Jan-11 1d 12-Jan-11 1d 15-Jan-11 6d 10-Jan-11 1d 16-Jan-11 Finish Jan F 02-Jan-11 13-Dec-10 14-Dec-10 15-Dec-10 23-Dec-10 26-Dec-10 28-Dec-10 29-Dec-10 01-Jan-11 02-Jan-11 02-Jan-11 16-Jan-11 09-Jan-11 20-Dec-10 21-Dec-10 22-Dec-10 30-Dec-10 02-Jan-11 04-Jan-11 05-Jan-11 08-Jan-11 09-Jan-11 09-Jan-11 09-Jan-11 20-Dec-10 21-Dec-10 22-Dec-10 30-Dec-10 02-Jan-11 04-Jan-11 05-Jan-11 08-Jan-11 09-Jan-11 09-Jan-11 16-Jan-11 27-Dec-10 28-Dec-10 29-Dec-10 06-Jan-11 09-Jan-11 11-Jan-11 12-Jan-11 15-Jan-11 16-Jan-11 16-Jan-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N D Jan F M Apr M 13-Dec-10 02-Jan-11

S Oct N

D Jan F

J Jul

Precasting - 12th Cycle (4 Girders)

20-Dec-10 20-Dec-10

16-Jan-11 09-Jan-11

20-Dec-10

09-Jan-11

27-Dec-10

16-Jan-11

Page 14 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 48 C08B481000 C08B481020 C08B481040 C08B481060 C08B481080 C08B481100 C08B481120 C08B481140 C08B481160 C08B481180 IS1-PC-FO1000 IS1-PC-FO1020 IS1-PC-FO1040 Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation of Yard for Infill Slabs Fabrication of Moulds and Rebar Delivery Casting Infill Slabs (10 No. per Day) (1.150m x 1.500m) Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 18d 27-Dec-10 1d 27-Dec-10 1d 28-Dec-10 1d 29-Dec-10 2d 05-Jan-11 2d 08-Jan-11 1d 11-Jan-11 1d 12-Jan-11 1d 15-Jan-11 6d 10-Jan-11 1d 16-Jan-11 138d 15-Sep-10 6d 15-Sep-10 12d 22-Sep-10 120d 06-Oct-10 326d 12-Aug-10 45d 12-Aug-10 Finish Jan F 16-Jan-11 27-Dec-10 28-Dec-10 29-Dec-10 06-Jan-11 09-Jan-11 11-Jan-11 12-Jan-11 15-Jan-11 16-Jan-11 16-Jan-11 22-Feb-11 21-Sep-10 05-Oct-10 22-Feb-11 27-Aug-11 03-Oct-10 26-Sep-10 26-Sep-10 03-Oct-10 23-Sep-10 11-Dec-10 30-Nov-10 16-Nov-10 17-Nov-10 18-Nov-10 21-Nov-10 23-Nov-10 25-Nov-10 27-Nov-10 29-Nov-10 30-Nov-10 30-Nov-10 01-Dec-10 17-Nov-10 18-Nov-10 20-Nov-10 22-Nov-10 24-Nov-10 27-Nov-10 28-Nov-10 30-Nov-10 01-Dec-10 01-Dec-10 02-Dec-10 12-Aug-10 12-Aug-10 15-Sep-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N D Jan F M Apr M 27-Dec-10 16-Jan-11

S Oct N

D Jan F

J Jul

Precasting - Infill Slabs (960 Nos.)

22-Feb-11

WADI BRIDGE Precast Yard Setup


PCY2-10000 PCY2-10100 PCY2-10200 PCY2-10300 Girder - 01 C01B012000 C01B012020 C01B012040 C01B012060 C01B012080 C01B012100 C01B012120 C01B012140 C01B012160 C01B012180 Girder - 02 C01B022000 C01B022020 C01B022040 C01B022060 C01B022080 C01B022100 C01B022120 C01B022140 C01B022160 C01B022180 Girder - 03 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Manufacturing and Availability of Beam Shutters Preparation of Precasting Yard Facilities Preparation & Fixing of Beds (10 Beds) Finalization and Mobilization of Prestressing Agency

27-Aug-11 03-Oct-10

39d 12-Aug-10 26d 28-Aug-10 6d 27-Sep-10 18d 04-Sep-10 22d 16-Nov-10 13d 16-Nov-10 1d 16-Nov-10 1d 17-Nov-10 1d 18-Nov-10 2d 20-Nov-10 2d 22-Nov-10 1d 25-Nov-10 1d 27-Nov-10 1d 29-Nov-10 6d 24-Nov-10 1d 30-Nov-10 13d 17-Nov-10 1d 17-Nov-10 1d 18-Nov-10 1d 20-Nov-10 2d 21-Nov-10 2d 23-Nov-10 1d 27-Nov-10 1d 28-Nov-10 1d 30-Nov-10 6d 25-Nov-10 1d 01-Dec-10 13d 18-Nov-10

Precasting - 1st Cycle (8 Girders)

16-Nov-10 16-Nov-10

11-Dec-10 30-Nov-10

17-Nov-10

01-Dec-10

18-Nov-10

02-Dec-10

Page 15 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C01B032000 C01B032020 C01B032040 C01B032060 C01B032080 C01B032100 C01B032120 C01B032140 C01B032160 C01B032180 Girder - 04 C01B042000 C01B042020 C01B042040 C01B042060 C01B042080 C01B042100 C01B042120 C01B042140 C01B042160 C01B042180 Girder - 05 C01B052000 C01B052020 C01B052040 C01B052060 C01B052080 C01B052100 C01B052120 C01B052140 C01B052160 C01B052180 Girder - 06 C01B062000 C01B062020 C01B062040 C01B062060 C01B062080 C01B062100 C01B062120 C01B062140 C01B062160 C01B062180 Girder - 07 C01B072000 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 18-Nov-10 1d 20-Nov-10 1d 21-Nov-10 2d 22-Nov-10 2d 24-Nov-10 1d 28-Nov-10 1d 29-Nov-10 1d 01-Dec-10 6d 27-Nov-10 1d 02-Dec-10 13d 20-Nov-10 1d 20-Nov-10 1d 21-Nov-10 1d 22-Nov-10 2d 23-Nov-10 2d 25-Nov-10 1d 29-Nov-10 1d 30-Nov-10 1d 02-Dec-10 6d 28-Nov-10 1d 04-Dec-10 15d 21-Nov-10 1d 21-Nov-10 1d 22-Nov-10 1d 23-Nov-10 2d 27-Nov-10 2d 29-Nov-10 1d 02-Dec-10 1d 04-Dec-10 1d 06-Dec-10 6d 01-Dec-10 1d 07-Dec-10 15d 22-Nov-10 1d 22-Nov-10 1d 23-Nov-10 1d 24-Nov-10 2d 28-Nov-10 2d 30-Nov-10 1d 04-Dec-10 1d 05-Dec-10 1d 07-Dec-10 6d 02-Dec-10 1d 08-Dec-10 15d 23-Nov-10 1d 23-Nov-10 Finish Jan F 18-Nov-10 20-Nov-10 21-Nov-10 23-Nov-10 25-Nov-10 28-Nov-10 29-Nov-10 01-Dec-10 02-Dec-10 02-Dec-10 04-Dec-10 20-Nov-10 21-Nov-10 22-Nov-10 24-Nov-10 27-Nov-10 29-Nov-10 30-Nov-10 02-Dec-10 04-Dec-10 04-Dec-10 07-Dec-10 21-Nov-10 22-Nov-10 23-Nov-10 28-Nov-10 30-Nov-10 02-Dec-10 04-Dec-10 06-Dec-10 07-Dec-10 07-Dec-10 08-Dec-10 22-Nov-10 23-Nov-10 24-Nov-10 29-Nov-10 01-Dec-10 04-Dec-10 05-Dec-10 07-Dec-10 08-Dec-10 08-Dec-10 09-Dec-10 23-Nov-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

20-Nov-10

04-Dec-10

21-Nov-10

07-Dec-10

22-Nov-10

08-Dec-10

23-Nov-10

09-Dec-10

Page 16 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C01B072020 C01B072040 C01B072060 C01B072080 C01B072100 C01B072120 C01B072140 C01B072160 C01B072180 Girder - 08 C01B082000 C01B082020 C01B082040 C01B082060 C01B082080 C01B082100 C01B082120 C01B082140 C01B082160 C01B082180 Girder - 09 C01B092000 C01B092020 C01B092040 C01B092060 C01B092080 C01B092100 C01B092120 C01B092140 C01B092160 C01B092180 Girder - 10 C01B102000 C01B102020 C01B102040 C01B102060 C01B102080 C01B102100 C01B102120 C01B102140 C01B102160 C01B102180 Girder - 11 C02B012000 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 24-Nov-10 1d 25-Nov-10 2d 29-Nov-10 2d 01-Dec-10 1d 05-Dec-10 1d 06-Dec-10 1d 08-Dec-10 6d 04-Dec-10 1d 09-Dec-10 15d 24-Nov-10 1d 24-Nov-10 1d 25-Nov-10 1d 27-Nov-10 2d 30-Nov-10 2d 02-Dec-10 1d 06-Dec-10 1d 07-Dec-10 1d 09-Dec-10 6d 05-Dec-10 1d 11-Dec-10 26d 25-Nov-10 17d 25-Nov-10 1d 25-Nov-10 1d 27-Nov-10 1d 28-Nov-10 2d 04-Dec-10 2d 06-Dec-10 1d 09-Dec-10 1d 11-Dec-10 1d 13-Dec-10 6d 08-Dec-10 1d 14-Dec-10 17d 27-Nov-10 1d 27-Nov-10 1d 28-Nov-10 1d 29-Nov-10 2d 05-Dec-10 2d 07-Dec-10 1d 11-Dec-10 1d 12-Dec-10 1d 14-Dec-10 6d 09-Dec-10 1d 15-Dec-10 14d 01-Dec-10 1d 01-Dec-10 Finish Jan F 24-Nov-10 25-Nov-10 30-Nov-10 02-Dec-10 05-Dec-10 06-Dec-10 08-Dec-10 09-Dec-10 09-Dec-10 11-Dec-10 24-Nov-10 25-Nov-10 27-Nov-10 01-Dec-10 04-Dec-10 06-Dec-10 07-Dec-10 09-Dec-10 11-Dec-10 11-Dec-10 25-Dec-10 14-Dec-10 25-Nov-10 27-Nov-10 28-Nov-10 05-Dec-10 07-Dec-10 09-Dec-10 11-Dec-10 13-Dec-10 14-Dec-10 14-Dec-10 15-Dec-10 27-Nov-10 28-Nov-10 29-Nov-10 06-Dec-10 08-Dec-10 11-Dec-10 12-Dec-10 14-Dec-10 15-Dec-10 15-Dec-10 16-Dec-10 01-Dec-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

24-Nov-10

11-Dec-10

Precasting - 2nd Cycle (8 Girders)

25-Nov-10 25-Nov-10

25-Dec-10 14-Dec-10

27-Nov-10

15-Dec-10

01-Dec-10

16-Dec-10

Page 17 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C02B012020 C02B012040 C02B012060 C02B012080 C02B012100 C02B012120 C02B012140 C02B012160 C02B012180 Girder - 12 C02B022000 C02B022020 C02B022040 C02B022060 C02B022080 C02B022100 C02B022120 C02B022140 C02B022160 C02B022180 Girder - 13 C02B032000 C02B032020 C02B032040 C02B032060 C02B032080 C02B032100 C02B032120 C02B032140 C02B032160 C02B032180 Girder - 14 C02B042000 C02B042020 C02B042040 C02B042060 C02B042080 C02B042100 C02B042120 C02B042140 C02B042160 C02B042180 Girder - 15 C02B052000 C02B052020 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 02-Dec-10 1d 04-Dec-10 2d 06-Dec-10 2d 08-Dec-10 1d 12-Dec-10 1d 13-Dec-10 1d 15-Dec-10 6d 11-Dec-10 1d 16-Dec-10 14d 02-Dec-10 1d 02-Dec-10 1d 04-Dec-10 1d 05-Dec-10 2d 07-Dec-10 2d 09-Dec-10 1d 13-Dec-10 1d 14-Dec-10 1d 16-Dec-10 6d 12-Dec-10 1d 18-Dec-10 16d 04-Dec-10 1d 04-Dec-10 1d 05-Dec-10 1d 06-Dec-10 2d 11-Dec-10 2d 13-Dec-10 1d 16-Dec-10 1d 18-Dec-10 1d 20-Dec-10 6d 15-Dec-10 1d 21-Dec-10 16d 05-Dec-10 1d 05-Dec-10 1d 06-Dec-10 1d 07-Dec-10 2d 12-Dec-10 2d 14-Dec-10 1d 18-Dec-10 1d 19-Dec-10 1d 21-Dec-10 6d 16-Dec-10 1d 22-Dec-10 14d 08-Dec-10 1d 08-Dec-10 1d 09-Dec-10 Finish Jan F 02-Dec-10 04-Dec-10 07-Dec-10 09-Dec-10 12-Dec-10 13-Dec-10 15-Dec-10 16-Dec-10 16-Dec-10 18-Dec-10 02-Dec-10 04-Dec-10 05-Dec-10 08-Dec-10 11-Dec-10 13-Dec-10 14-Dec-10 16-Dec-10 18-Dec-10 18-Dec-10 21-Dec-10 04-Dec-10 05-Dec-10 06-Dec-10 12-Dec-10 14-Dec-10 16-Dec-10 18-Dec-10 20-Dec-10 21-Dec-10 21-Dec-10 22-Dec-10 05-Dec-10 06-Dec-10 07-Dec-10 13-Dec-10 15-Dec-10 18-Dec-10 19-Dec-10 21-Dec-10 22-Dec-10 22-Dec-10 23-Dec-10 08-Dec-10 09-Dec-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

02-Dec-10

18-Dec-10

04-Dec-10

21-Dec-10

05-Dec-10

22-Dec-10

08-Dec-10

23-Dec-10

Page 18 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C02B052040 C02B052060 C02B052080 C02B052100 C02B052120 C02B052140 C02B052160 C02B052180 Girder - 16 C02B062000 C02B062020 C02B062040 C02B062060 C02B062080 C02B062100 C02B062120 C02B062140 C02B062160 C02B062180 Girder - 17 C02B072000 C02B072020 C02B072040 C02B072060 C02B072080 C02B072100 C02B072120 C02B072140 C02B072160 C02B072180 Girder - 18 C02B082000 C02B082020 C02B082040 C02B082060 C02B082080 C02B082100 C02B082120 C02B082140 C02B082160 C02B082180 Girder - 19 C02B092000 C02B092020 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 11-Dec-10 2d 13-Dec-10 2d 15-Dec-10 1d 19-Dec-10 1d 20-Dec-10 1d 22-Dec-10 6d 18-Dec-10 1d 23-Dec-10 14d 09-Dec-10 1d 09-Dec-10 1d 11-Dec-10 1d 12-Dec-10 2d 14-Dec-10 2d 16-Dec-10 1d 20-Dec-10 1d 21-Dec-10 1d 23-Dec-10 6d 19-Dec-10 1d 25-Dec-10 25d 11-Dec-10 16d 11-Dec-10 1d 11-Dec-10 1d 12-Dec-10 1d 13-Dec-10 2d 18-Dec-10 2d 20-Dec-10 1d 23-Dec-10 1d 25-Dec-10 1d 27-Dec-10 6d 22-Dec-10 1d 28-Dec-10 16d 12-Dec-10 1d 12-Dec-10 1d 13-Dec-10 1d 14-Dec-10 2d 19-Dec-10 2d 21-Dec-10 1d 25-Dec-10 1d 26-Dec-10 1d 28-Dec-10 6d 23-Dec-10 1d 29-Dec-10 14d 15-Dec-10 1d 15-Dec-10 1d 16-Dec-10 Finish Jan F 11-Dec-10 14-Dec-10 16-Dec-10 19-Dec-10 20-Dec-10 22-Dec-10 23-Dec-10 23-Dec-10 25-Dec-10 09-Dec-10 11-Dec-10 12-Dec-10 15-Dec-10 18-Dec-10 20-Dec-10 21-Dec-10 23-Dec-10 25-Dec-10 25-Dec-10 08-Jan-11 28-Dec-10 11-Dec-10 12-Dec-10 13-Dec-10 19-Dec-10 21-Dec-10 23-Dec-10 25-Dec-10 27-Dec-10 28-Dec-10 28-Dec-10 29-Dec-10 12-Dec-10 13-Dec-10 14-Dec-10 20-Dec-10 22-Dec-10 25-Dec-10 26-Dec-10 28-Dec-10 29-Dec-10 29-Dec-10 30-Dec-10 15-Dec-10 16-Dec-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

09-Dec-10

25-Dec-10

Precasting - 3rd Cycle (8 Girders)

11-Dec-10 11-Dec-10

08-Jan-11 28-Dec-10

12-Dec-10

29-Dec-10

15-Dec-10

30-Dec-10

Page 19 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C02B092040 C02B092060 C02B092080 C02B092100 C02B092120 C02B092140 C02B092160 C02B092180 Girder - 20 C02B102000 C02B102020 C02B102040 C02B102060 C02B102080 C02B102100 C02B102120 C02B102140 C02B102160 C02B102180 Girder - 21 C03B012000 C03B012020 C03B012040 C03B012060 C03B012080 C03B012100 C03B012120 C03B012140 C03B012160 C03B012180 Girder - 22 C03B022000 C03B022020 C03B022040 C03B022060 C03B022080 C03B022100 C03B022120 C03B022140 C03B022160 C03B022180 Girder - 23 C03B032000 C03B032020 C03B032040 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 18-Dec-10 2d 20-Dec-10 2d 22-Dec-10 1d 26-Dec-10 1d 27-Dec-10 1d 29-Dec-10 6d 25-Dec-10 1d 30-Dec-10 14d 16-Dec-10 1d 16-Dec-10 1d 18-Dec-10 1d 19-Dec-10 2d 21-Dec-10 2d 23-Dec-10 1d 27-Dec-10 1d 28-Dec-10 1d 30-Dec-10 6d 26-Dec-10 1d 01-Jan-11 16d 18-Dec-10 1d 18-Dec-10 1d 19-Dec-10 1d 20-Dec-10 2d 25-Dec-10 2d 27-Dec-10 1d 30-Dec-10 1d 01-Jan-11 1d 03-Jan-11 6d 29-Dec-10 1d 04-Jan-11 16d 19-Dec-10 1d 19-Dec-10 1d 20-Dec-10 1d 21-Dec-10 2d 26-Dec-10 2d 28-Dec-10 1d 01-Jan-11 1d 02-Jan-11 1d 04-Jan-11 6d 30-Dec-10 1d 05-Jan-11 14d 22-Dec-10 1d 22-Dec-10 1d 23-Dec-10 1d 25-Dec-10 Finish Jan F 18-Dec-10 21-Dec-10 23-Dec-10 26-Dec-10 27-Dec-10 29-Dec-10 30-Dec-10 30-Dec-10 01-Jan-11 16-Dec-10 18-Dec-10 19-Dec-10 22-Dec-10 25-Dec-10 27-Dec-10 28-Dec-10 30-Dec-10 01-Jan-11 01-Jan-11 04-Jan-11 18-Dec-10 19-Dec-10 20-Dec-10 26-Dec-10 28-Dec-10 30-Dec-10 01-Jan-11 03-Jan-11 04-Jan-11 04-Jan-11 05-Jan-11 19-Dec-10 20-Dec-10 21-Dec-10 27-Dec-10 29-Dec-10 01-Jan-11 02-Jan-11 04-Jan-11 05-Jan-11 05-Jan-11 06-Jan-11 22-Dec-10 23-Dec-10 25-Dec-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

16-Dec-10

01-Jan-11

18-Dec-10

04-Jan-11

19-Dec-10

05-Jan-11

22-Dec-10

06-Jan-11

Page 20 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C03B032060 C03B032080 C03B032100 C03B032120 C03B032140 C03B032160 C03B032180 Girder - 24 C03B042000 C03B042020 C03B042040 C03B042060 C03B042080 C03B042100 C03B042120 C03B042140 C03B042160 C03B042180 Girder - 25 C03B052000 C03B052020 C03B052040 C03B052060 C03B052080 C03B052100 C03B052120 C03B052140 C03B052160 C03B052180 Girder - 26 C03B062000 C03B062020 C03B062040 C03B062060 C03B062080 C03B062100 C03B062120 C03B062140 C03B062160 C03B062180 Girder - 27 C03B072000 C03B072020 C03B072040 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 27-Dec-10 2d 29-Dec-10 1d 02-Jan-11 1d 03-Jan-11 1d 05-Jan-11 6d 01-Jan-11 1d 06-Jan-11 14d 23-Dec-10 1d 23-Dec-10 1d 25-Dec-10 1d 26-Dec-10 2d 28-Dec-10 2d 30-Dec-10 1d 03-Jan-11 1d 04-Jan-11 1d 06-Jan-11 6d 02-Jan-11 1d 08-Jan-11 25d 25-Dec-10 16d 25-Dec-10 1d 25-Dec-10 1d 26-Dec-10 1d 27-Dec-10 2d 01-Jan-11 2d 03-Jan-11 1d 06-Jan-11 1d 08-Jan-11 1d 10-Jan-11 6d 05-Jan-11 1d 11-Jan-11 16d 26-Dec-10 1d 26-Dec-10 1d 27-Dec-10 1d 28-Dec-10 2d 02-Jan-11 2d 04-Jan-11 1d 08-Jan-11 1d 09-Jan-11 1d 11-Jan-11 6d 06-Jan-11 1d 12-Jan-11 14d 29-Dec-10 1d 29-Dec-10 1d 30-Dec-10 1d 01-Jan-11 Finish Jan F 28-Dec-10 30-Dec-10 02-Jan-11 03-Jan-11 05-Jan-11 06-Jan-11 06-Jan-11 08-Jan-11 23-Dec-10 25-Dec-10 26-Dec-10 29-Dec-10 01-Jan-11 03-Jan-11 04-Jan-11 06-Jan-11 08-Jan-11 08-Jan-11 22-Jan-11 11-Jan-11 25-Dec-10 26-Dec-10 27-Dec-10 02-Jan-11 04-Jan-11 06-Jan-11 08-Jan-11 10-Jan-11 11-Jan-11 11-Jan-11 12-Jan-11 26-Dec-10 27-Dec-10 28-Dec-10 03-Jan-11 05-Jan-11 08-Jan-11 09-Jan-11 11-Jan-11 12-Jan-11 12-Jan-11 13-Jan-11 29-Dec-10 30-Dec-10 01-Jan-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

23-Dec-10

08-Jan-11

Precasting - 4th Cycle (8 Girders)

25-Dec-10 25-Dec-10

22-Jan-11 11-Jan-11

26-Dec-10

12-Jan-11

29-Dec-10

13-Jan-11

Page 21 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C03B072060 C03B072080 C03B072100 C03B072120 C03B072140 C03B072160 C03B072180 Girder - 28 C03B082000 C03B082020 C03B082040 C03B082060 C03B082080 C03B082100 C03B082120 C03B082140 C03B082160 C03B082180 Girder - 29 C03B092000 C03B092020 C03B092040 C03B092060 C03B092080 C03B092100 C03B092120 C03B092140 C03B092160 C03B092180 Girder - 30 C03B102000 C03B102020 C03B102040 C03B102060 C03B102080 C03B102100 C03B102120 C03B102140 C03B102160 C03B102180 Girder - 31 C04B012000 C04B012020 C04B012040 C04B012060 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 03-Jan-11 2d 05-Jan-11 1d 09-Jan-11 1d 10-Jan-11 1d 12-Jan-11 6d 08-Jan-11 1d 13-Jan-11 14d 30-Dec-10 1d 30-Dec-10 1d 01-Jan-11 1d 02-Jan-11 2d 04-Jan-11 2d 06-Jan-11 1d 10-Jan-11 1d 11-Jan-11 1d 13-Jan-11 6d 09-Jan-11 1d 15-Jan-11 16d 01-Jan-11 1d 01-Jan-11 1d 02-Jan-11 1d 03-Jan-11 2d 08-Jan-11 2d 10-Jan-11 1d 13-Jan-11 1d 15-Jan-11 1d 17-Jan-11 6d 12-Jan-11 1d 18-Jan-11 16d 02-Jan-11 1d 02-Jan-11 1d 03-Jan-11 1d 04-Jan-11 2d 09-Jan-11 2d 11-Jan-11 1d 15-Jan-11 1d 16-Jan-11 1d 18-Jan-11 6d 13-Jan-11 1d 19-Jan-11 14d 05-Jan-11 1d 05-Jan-11 1d 06-Jan-11 1d 08-Jan-11 2d 10-Jan-11 Finish Jan F 04-Jan-11 06-Jan-11 09-Jan-11 10-Jan-11 12-Jan-11 13-Jan-11 13-Jan-11 15-Jan-11 30-Dec-10 01-Jan-11 02-Jan-11 05-Jan-11 08-Jan-11 10-Jan-11 11-Jan-11 13-Jan-11 15-Jan-11 15-Jan-11 18-Jan-11 01-Jan-11 02-Jan-11 03-Jan-11 09-Jan-11 11-Jan-11 13-Jan-11 15-Jan-11 17-Jan-11 18-Jan-11 18-Jan-11 19-Jan-11 02-Jan-11 03-Jan-11 04-Jan-11 10-Jan-11 12-Jan-11 15-Jan-11 16-Jan-11 18-Jan-11 19-Jan-11 19-Jan-11 20-Jan-11 05-Jan-11 06-Jan-11 08-Jan-11 11-Jan-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

30-Dec-10

15-Jan-11

01-Jan-11

18-Jan-11

02-Jan-11

19-Jan-11

05-Jan-11

20-Jan-11

Page 22 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C04B012080 C04B012100 C04B012120 C04B012140 C04B012160 C04B012180 Girder - 32 C04B022000 C04B022020 C04B022040 C04B022060 C04B022080 C04B022100 C04B022120 C04B022140 C04B022160 C04B022180 Girder - 33 C04B032000 C04B032020 C04B032040 C04B032060 C04B032080 C04B032100 C04B032120 C04B032140 C04B032160 C04B032180 Girder - 34 C04B042000 C04B042020 C04B042040 C04B042060 C04B042080 C04B042100 C04B042120 C04B042140 C04B042160 C04B042180 Girder - 35 C04B052000 C04B052020 C04B052040 C04B052060 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 12-Jan-11 1d 16-Jan-11 1d 17-Jan-11 1d 19-Jan-11 6d 15-Jan-11 1d 20-Jan-11 14d 06-Jan-11 1d 06-Jan-11 1d 08-Jan-11 1d 09-Jan-11 2d 11-Jan-11 2d 13-Jan-11 1d 17-Jan-11 1d 18-Jan-11 1d 20-Jan-11 6d 16-Jan-11 1d 22-Jan-11 25d 08-Jan-11 16d 08-Jan-11 1d 08-Jan-11 1d 09-Jan-11 1d 10-Jan-11 2d 15-Jan-11 2d 17-Jan-11 1d 20-Jan-11 1d 22-Jan-11 1d 24-Jan-11 6d 19-Jan-11 1d 25-Jan-11 16d 09-Jan-11 1d 09-Jan-11 1d 10-Jan-11 1d 11-Jan-11 2d 16-Jan-11 2d 18-Jan-11 1d 22-Jan-11 1d 23-Jan-11 1d 25-Jan-11 6d 20-Jan-11 1d 26-Jan-11 14d 12-Jan-11 1d 12-Jan-11 1d 13-Jan-11 1d 15-Jan-11 2d 17-Jan-11 Finish Jan F 13-Jan-11 16-Jan-11 17-Jan-11 19-Jan-11 20-Jan-11 20-Jan-11 22-Jan-11 06-Jan-11 08-Jan-11 09-Jan-11 12-Jan-11 15-Jan-11 17-Jan-11 18-Jan-11 20-Jan-11 22-Jan-11 22-Jan-11 05-Feb-11 25-Jan-11 08-Jan-11 09-Jan-11 10-Jan-11 16-Jan-11 18-Jan-11 20-Jan-11 22-Jan-11 24-Jan-11 25-Jan-11 25-Jan-11 26-Jan-11 09-Jan-11 10-Jan-11 11-Jan-11 17-Jan-11 19-Jan-11 22-Jan-11 23-Jan-11 25-Jan-11 26-Jan-11 26-Jan-11 27-Jan-11 12-Jan-11 13-Jan-11 15-Jan-11 18-Jan-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

06-Jan-11

22-Jan-11

Precasting - 5th Cycle (8 Girders)

08-Jan-11 08-Jan-11

05-Feb-11 25-Jan-11

09-Jan-11

26-Jan-11

12-Jan-11

27-Jan-11

Page 23 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C04B052080 C04B052100 C04B052120 C04B052140 C04B052160 C04B052180 Girder - 36 C04B062000 C04B062020 C04B062040 C04B062060 C04B062080 C04B062100 C04B062120 C04B062140 C04B062160 C04B062180 Girder - 37 C04B072000 C04B072020 C04B072040 C04B072060 C04B072080 C04B072100 C04B072120 C04B072140 C04B072160 C04B072180 Girder - 38 C04B082000 C04B082020 C04B082040 C04B082060 C04B082080 C04B082100 C04B082120 C04B082140 C04B082160 C04B082180 Girder - 39 C04B092000 C04B092020 C04B092040 C04B092060 C04B092080 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 19-Jan-11 1d 23-Jan-11 1d 24-Jan-11 1d 26-Jan-11 6d 22-Jan-11 1d 27-Jan-11 14d 13-Jan-11 1d 13-Jan-11 1d 15-Jan-11 1d 16-Jan-11 2d 18-Jan-11 2d 20-Jan-11 1d 24-Jan-11 1d 25-Jan-11 1d 27-Jan-11 6d 23-Jan-11 1d 29-Jan-11 16d 15-Jan-11 1d 15-Jan-11 1d 16-Jan-11 1d 17-Jan-11 2d 22-Jan-11 2d 24-Jan-11 1d 27-Jan-11 1d 29-Jan-11 1d 31-Jan-11 6d 26-Jan-11 1d 01-Feb-11 16d 16-Jan-11 1d 16-Jan-11 1d 17-Jan-11 1d 18-Jan-11 2d 23-Jan-11 2d 25-Jan-11 1d 29-Jan-11 1d 30-Jan-11 1d 01-Feb-11 6d 27-Jan-11 1d 02-Feb-11 14d 19-Jan-11 1d 19-Jan-11 1d 20-Jan-11 1d 22-Jan-11 2d 24-Jan-11 2d 26-Jan-11 Finish Jan F 20-Jan-11 23-Jan-11 24-Jan-11 26-Jan-11 27-Jan-11 27-Jan-11 29-Jan-11 13-Jan-11 15-Jan-11 16-Jan-11 19-Jan-11 22-Jan-11 24-Jan-11 25-Jan-11 27-Jan-11 29-Jan-11 29-Jan-11 01-Feb-11 15-Jan-11 16-Jan-11 17-Jan-11 23-Jan-11 25-Jan-11 27-Jan-11 29-Jan-11 31-Jan-11 01-Feb-11 01-Feb-11 02-Feb-11 16-Jan-11 17-Jan-11 18-Jan-11 24-Jan-11 26-Jan-11 29-Jan-11 30-Jan-11 01-Feb-11 02-Feb-11 02-Feb-11 03-Feb-11 19-Jan-11 20-Jan-11 22-Jan-11 25-Jan-11 27-Jan-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

13-Jan-11

29-Jan-11

15-Jan-11

01-Feb-11

16-Jan-11

02-Feb-11

19-Jan-11

03-Feb-11

Page 24 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C04B092100 C04B092120 C04B092140 C04B092160 C04B092180 Girder - 40 C04B102000 C04B102020 C04B102040 C04B102060 C04B102080 C04B102100 C04B102120 C04B102140 C04B102160 C04B102180 Girder - 41 C05B012000 C05B012020 C05B012040 C05B012060 C05B012080 C05B012100 C05B012120 C05B012140 C05B012160 C05B012180 Girder - 42 C05B022000 C05B022020 C05B022040 C05B022060 C05B022080 C05B022100 C05B022120 C05B022140 C05B022160 C05B022180 Girder - 43 C05B032000 C05B032020 C05B032040 C05B032060 C05B032080 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 30-Jan-11 1d 31-Jan-11 1d 02-Feb-11 6d 29-Jan-11 1d 03-Feb-11 14d 20-Jan-11 1d 20-Jan-11 1d 22-Jan-11 1d 23-Jan-11 2d 25-Jan-11 2d 27-Jan-11 1d 31-Jan-11 1d 01-Feb-11 1d 03-Feb-11 6d 30-Jan-11 1d 05-Feb-11 25d 22-Jan-11 16d 22-Jan-11 1d 22-Jan-11 1d 23-Jan-11 1d 24-Jan-11 2d 29-Jan-11 2d 31-Jan-11 1d 03-Feb-11 1d 05-Feb-11 1d 07-Feb-11 6d 02-Feb-11 1d 08-Feb-11 16d 23-Jan-11 1d 23-Jan-11 1d 24-Jan-11 1d 25-Jan-11 2d 30-Jan-11 2d 01-Feb-11 1d 05-Feb-11 1d 06-Feb-11 1d 08-Feb-11 6d 03-Feb-11 1d 09-Feb-11 14d 26-Jan-11 1d 26-Jan-11 1d 27-Jan-11 1d 29-Jan-11 2d 31-Jan-11 2d 02-Feb-11 Finish Jan F 30-Jan-11 31-Jan-11 02-Feb-11 03-Feb-11 03-Feb-11 05-Feb-11 20-Jan-11 22-Jan-11 23-Jan-11 26-Jan-11 29-Jan-11 31-Jan-11 01-Feb-11 03-Feb-11 05-Feb-11 05-Feb-11 19-Feb-11 08-Feb-11 22-Jan-11 23-Jan-11 24-Jan-11 30-Jan-11 01-Feb-11 03-Feb-11 05-Feb-11 07-Feb-11 08-Feb-11 08-Feb-11 09-Feb-11 23-Jan-11 24-Jan-11 25-Jan-11 31-Jan-11 02-Feb-11 05-Feb-11 06-Feb-11 08-Feb-11 09-Feb-11 09-Feb-11 10-Feb-11 26-Jan-11 27-Jan-11 29-Jan-11 01-Feb-11 03-Feb-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

20-Jan-11

05-Feb-11

Precasting - 6th Cycle (8 Girders)

22-Jan-11 22-Jan-11

19-Feb-11 08-Feb-11

23-Jan-11

09-Feb-11

26-Jan-11

10-Feb-11

Page 25 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C05B032100 C05B032120 C05B032140 C05B032160 C05B032180 Girder - 44 C05B042000 C05B042020 C05B042040 C05B042060 C05B042080 C05B042100 C05B042120 C05B042140 C05B042160 C05B042180 Girder - 45 C05B052000 C05B052020 C05B052040 C05B052060 C05B052080 C05B052100 C05B052120 C05B052140 C05B052160 C05B052180 Girder - 46 C05B062000 C05B062020 C05B062040 C05B062060 C05B062080 C05B062100 C05B062120 C05B062140 C05B062160 C05B062180 Girder - 47 C05B072000 C05B072020 C05B072040 C05B072060 C05B072080 C05B072100 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 06-Feb-11 1d 07-Feb-11 1d 09-Feb-11 6d 05-Feb-11 1d 10-Feb-11 14d 27-Jan-11 1d 27-Jan-11 1d 29-Jan-11 1d 30-Jan-11 2d 01-Feb-11 2d 03-Feb-11 1d 07-Feb-11 1d 08-Feb-11 1d 10-Feb-11 6d 06-Feb-11 1d 12-Feb-11 16d 29-Jan-11 1d 29-Jan-11 1d 30-Jan-11 1d 31-Jan-11 2d 05-Feb-11 2d 07-Feb-11 1d 10-Feb-11 1d 12-Feb-11 1d 14-Feb-11 6d 09-Feb-11 1d 15-Feb-11 16d 30-Jan-11 1d 30-Jan-11 1d 31-Jan-11 1d 01-Feb-11 2d 06-Feb-11 2d 08-Feb-11 1d 12-Feb-11 1d 13-Feb-11 1d 15-Feb-11 6d 10-Feb-11 1d 16-Feb-11 14d 02-Feb-11 1d 02-Feb-11 1d 03-Feb-11 1d 05-Feb-11 2d 07-Feb-11 2d 09-Feb-11 1d 13-Feb-11 Finish Jan F 06-Feb-11 07-Feb-11 09-Feb-11 10-Feb-11 10-Feb-11 12-Feb-11 27-Jan-11 29-Jan-11 30-Jan-11 02-Feb-11 05-Feb-11 07-Feb-11 08-Feb-11 10-Feb-11 12-Feb-11 12-Feb-11 15-Feb-11 29-Jan-11 30-Jan-11 31-Jan-11 06-Feb-11 08-Feb-11 10-Feb-11 12-Feb-11 14-Feb-11 15-Feb-11 15-Feb-11 16-Feb-11 30-Jan-11 31-Jan-11 01-Feb-11 07-Feb-11 09-Feb-11 12-Feb-11 13-Feb-11 15-Feb-11 16-Feb-11 16-Feb-11 17-Feb-11 02-Feb-11 03-Feb-11 05-Feb-11 08-Feb-11 10-Feb-11 13-Feb-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

27-Jan-11

12-Feb-11

29-Jan-11

15-Feb-11

30-Jan-11

16-Feb-11

02-Feb-11

17-Feb-11

Page 26 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C05B072120 C05B072140 C05B072160 C05B072180 Girder - 48 C05B082000 C05B082020 C05B082040 C05B082060 C05B082080 C05B082100 C05B082120 C05B082140 C05B082160 C05B082180 Girder - 49 C05B092000 C05B092020 C05B092040 C05B092060 C05B092080 C05B092100 C05B092120 C05B092140 C05B092160 C05B092180 Girder - 50 C05B102000 C05B102020 C05B102040 C05B102060 C05B102080 C05B102100 C05B102120 C05B102140 C05B102160 C05B102180 Girder - 51 C06B012000 C06B012020 C06B012040 C06B012060 C06B012080 C06B012100 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 14-Feb-11 1d 16-Feb-11 6d 12-Feb-11 1d 17-Feb-11 14d 03-Feb-11 1d 03-Feb-11 1d 05-Feb-11 1d 06-Feb-11 2d 08-Feb-11 2d 10-Feb-11 1d 14-Feb-11 1d 15-Feb-11 1d 17-Feb-11 6d 13-Feb-11 1d 19-Feb-11 25d 05-Feb-11 16d 05-Feb-11 1d 05-Feb-11 1d 06-Feb-11 1d 07-Feb-11 2d 12-Feb-11 2d 14-Feb-11 1d 17-Feb-11 1d 19-Feb-11 1d 21-Feb-11 6d 16-Feb-11 1d 22-Feb-11 16d 06-Feb-11 1d 06-Feb-11 1d 07-Feb-11 1d 08-Feb-11 2d 13-Feb-11 2d 15-Feb-11 1d 19-Feb-11 1d 20-Feb-11 1d 22-Feb-11 6d 17-Feb-11 1d 23-Feb-11 14d 09-Feb-11 1d 09-Feb-11 1d 10-Feb-11 1d 12-Feb-11 2d 14-Feb-11 2d 16-Feb-11 1d 20-Feb-11 Finish Jan F 14-Feb-11 16-Feb-11 17-Feb-11 17-Feb-11 19-Feb-11 03-Feb-11 05-Feb-11 06-Feb-11 09-Feb-11 12-Feb-11 14-Feb-11 15-Feb-11 17-Feb-11 19-Feb-11 19-Feb-11 05-Mar-11 22-Feb-11 05-Feb-11 06-Feb-11 07-Feb-11 13-Feb-11 15-Feb-11 17-Feb-11 19-Feb-11 21-Feb-11 22-Feb-11 22-Feb-11 23-Feb-11 06-Feb-11 07-Feb-11 08-Feb-11 14-Feb-11 16-Feb-11 19-Feb-11 20-Feb-11 22-Feb-11 23-Feb-11 23-Feb-11 24-Feb-11 09-Feb-11 10-Feb-11 12-Feb-11 15-Feb-11 17-Feb-11 20-Feb-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

03-Feb-11

19-Feb-11

Precasting - 7th Cycle (8 Girders)

05-Feb-11 05-Feb-11

05-Mar-11 22-Feb-11

06-Feb-11

23-Feb-11

09-Feb-11

24-Feb-11

Page 27 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C06B012120 C06B012140 C06B012160 C06B012180 Girder - 52 C06B022000 C06B022020 C06B022040 C06B022060 C06B022080 C06B022100 C06B022120 C06B022140 C06B022160 C06B022180 Girder - 53 C06B032000 C06B032020 C06B032040 C06B032060 C06B032080 C06B032100 C06B032120 C06B032140 C06B032160 C06B032180 Girder - 54 C06B042000 C06B042020 C06B042040 C06B042060 C06B042080 C06B042100 C06B042120 C06B042140 C06B042160 C06B042180 Girder - 55 C06B052000 C06B052020 C06B052040 C06B052060 C06B052080 C06B052100 C06B052120 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 21-Feb-11 1d 23-Feb-11 6d 19-Feb-11 1d 24-Feb-11 14d 10-Feb-11 1d 10-Feb-11 1d 12-Feb-11 1d 13-Feb-11 2d 15-Feb-11 2d 17-Feb-11 1d 21-Feb-11 1d 22-Feb-11 1d 24-Feb-11 6d 20-Feb-11 1d 26-Feb-11 16d 12-Feb-11 1d 12-Feb-11 1d 13-Feb-11 1d 14-Feb-11 2d 19-Feb-11 2d 21-Feb-11 1d 24-Feb-11 1d 26-Feb-11 1d 28-Feb-11 6d 23-Feb-11 1d 01-Mar-11 16d 13-Feb-11 1d 13-Feb-11 1d 14-Feb-11 1d 15-Feb-11 2d 20-Feb-11 2d 22-Feb-11 1d 26-Feb-11 1d 27-Feb-11 1d 01-Mar-11 6d 24-Feb-11 1d 02-Mar-11 14d 16-Feb-11 1d 16-Feb-11 1d 17-Feb-11 1d 19-Feb-11 2d 21-Feb-11 2d 23-Feb-11 1d 27-Feb-11 1d 28-Feb-11 Finish Jan F 21-Feb-11 23-Feb-11 24-Feb-11 24-Feb-11 26-Feb-11 10-Feb-11 12-Feb-11 13-Feb-11 16-Feb-11 19-Feb-11 21-Feb-11 22-Feb-11 24-Feb-11 26-Feb-11 26-Feb-11 01-Mar-11 12-Feb-11 13-Feb-11 14-Feb-11 20-Feb-11 22-Feb-11 24-Feb-11 26-Feb-11 28-Feb-11 01-Mar-11 01-Mar-11 02-Mar-11 13-Feb-11 14-Feb-11 15-Feb-11 21-Feb-11 23-Feb-11 26-Feb-11 27-Feb-11 01-Mar-11 02-Mar-11 02-Mar-11 03-Mar-11 16-Feb-11 17-Feb-11 19-Feb-11 22-Feb-11 24-Feb-11 27-Feb-11 28-Feb-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

10-Feb-11

26-Feb-11

12-Feb-11

01-Mar-11

13-Feb-11

02-Mar-11

16-Feb-11

03-Mar-11

Page 28 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C06B052140 C06B052160 C06B052180 Girder - 56 C06B062000 C06B062020 C06B062040 C06B062060 C06B062080 C06B062100 C06B062120 C06B062140 C06B062160 C06B062180 Girder - 57 C06B072000 C06B072020 C06B072040 C06B072060 C06B072080 C06B072100 C06B072120 C06B072140 C06B072160 C06B072180 Girder - 58 C06B082000 C06B082020 C06B082040 C06B082060 C06B082080 C06B082100 C06B082120 C06B082140 C06B082160 C06B082180 Girder - 59 C06B092000 C06B092020 C06B092040 C06B092060 C06B092080 C06B092100 C06B092120 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 02-Mar-11 6d 26-Feb-11 1d 03-Mar-11 14d 17-Feb-11 1d 17-Feb-11 1d 19-Feb-11 1d 20-Feb-11 2d 22-Feb-11 2d 24-Feb-11 1d 28-Feb-11 1d 01-Mar-11 1d 03-Mar-11 6d 27-Feb-11 1d 05-Mar-11 25d 19-Feb-11 16d 19-Feb-11 1d 19-Feb-11 1d 20-Feb-11 1d 21-Feb-11 2d 26-Feb-11 2d 28-Feb-11 1d 03-Mar-11 1d 05-Mar-11 1d 07-Mar-11 6d 02-Mar-11 1d 08-Mar-11 16d 20-Feb-11 1d 20-Feb-11 1d 21-Feb-11 1d 22-Feb-11 2d 27-Feb-11 2d 01-Mar-11 1d 05-Mar-11 1d 06-Mar-11 1d 08-Mar-11 6d 03-Mar-11 1d 09-Mar-11 14d 23-Feb-11 1d 23-Feb-11 1d 24-Feb-11 1d 26-Feb-11 2d 28-Feb-11 2d 02-Mar-11 1d 06-Mar-11 1d 07-Mar-11 Finish Jan F 02-Mar-11 03-Mar-11 03-Mar-11 05-Mar-11 17-Feb-11 19-Feb-11 20-Feb-11 23-Feb-11 26-Feb-11 28-Feb-11 01-Mar-11 03-Mar-11 05-Mar-11 05-Mar-11 19-Mar-11 08-Mar-11 19-Feb-11 20-Feb-11 21-Feb-11 27-Feb-11 01-Mar-11 03-Mar-11 05-Mar-11 07-Mar-11 08-Mar-11 08-Mar-11 09-Mar-11 20-Feb-11 21-Feb-11 22-Feb-11 28-Feb-11 02-Mar-11 05-Mar-11 06-Mar-11 08-Mar-11 09-Mar-11 09-Mar-11 10-Mar-11 23-Feb-11 24-Feb-11 26-Feb-11 01-Mar-11 03-Mar-11 06-Mar-11 07-Mar-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

17-Feb-11

05-Mar-11

Precasting - 8th Cycle (8 Girders)

19-Feb-11 19-Feb-11

19-Mar-11 08-Mar-11

20-Feb-11

09-Mar-11

23-Feb-11

10-Mar-11

Page 29 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C06B092140 C06B092160 C06B092180 Girder - 60 C06B102000 C06B102020 C06B102040 C06B102060 C06B102080 C06B102100 C06B102120 C06B102140 C06B102160 C06B102180 Girder - 61 C07B012000 C07B012020 C07B012040 C07B012060 C07B012080 C07B012100 C07B012120 C07B012140 C07B012160 C07B012180 Girder - 62 C07B022000 C07B022020 C07B022040 C07B022060 C07B022080 C07B022100 C07B022120 C07B022140 C07B022160 C07B022180 Girder - 63 C07B032000 C07B032020 C07B032040 C07B032060 C07B032080 C07B032100 C07B032120 C07B032140 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 09-Mar-11 6d 05-Mar-11 1d 10-Mar-11 14d 24-Feb-11 1d 24-Feb-11 1d 26-Feb-11 1d 27-Feb-11 2d 01-Mar-11 2d 03-Mar-11 1d 07-Mar-11 1d 08-Mar-11 1d 10-Mar-11 6d 06-Mar-11 1d 12-Mar-11 16d 26-Feb-11 1d 26-Feb-11 1d 27-Feb-11 1d 28-Feb-11 2d 05-Mar-11 2d 07-Mar-11 1d 10-Mar-11 1d 12-Mar-11 1d 14-Mar-11 6d 09-Mar-11 1d 15-Mar-11 16d 27-Feb-11 1d 27-Feb-11 1d 28-Feb-11 1d 01-Mar-11 2d 06-Mar-11 2d 08-Mar-11 1d 12-Mar-11 1d 13-Mar-11 1d 15-Mar-11 6d 10-Mar-11 1d 16-Mar-11 14d 02-Mar-11 1d 02-Mar-11 1d 03-Mar-11 1d 05-Mar-11 2d 07-Mar-11 2d 09-Mar-11 1d 13-Mar-11 1d 14-Mar-11 1d 16-Mar-11 Finish Jan F 09-Mar-11 10-Mar-11 10-Mar-11 12-Mar-11 24-Feb-11 26-Feb-11 27-Feb-11 02-Mar-11 05-Mar-11 07-Mar-11 08-Mar-11 10-Mar-11 12-Mar-11 12-Mar-11 15-Mar-11 26-Feb-11 27-Feb-11 28-Feb-11 06-Mar-11 08-Mar-11 10-Mar-11 12-Mar-11 14-Mar-11 15-Mar-11 15-Mar-11 16-Mar-11 27-Feb-11 28-Feb-11 01-Mar-11 07-Mar-11 09-Mar-11 12-Mar-11 13-Mar-11 15-Mar-11 16-Mar-11 16-Mar-11 17-Mar-11 02-Mar-11 03-Mar-11 05-Mar-11 08-Mar-11 10-Mar-11 13-Mar-11 14-Mar-11 16-Mar-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

24-Feb-11

12-Mar-11

26-Feb-11

15-Mar-11

27-Feb-11

16-Mar-11

02-Mar-11

17-Mar-11

Page 30 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C07B032160 C07B032180 Girder - 64 C07B042000 C07B042020 C07B042040 C07B042060 C07B042080 C07B042100 C07B042120 C07B042140 C07B042160 C07B042180 Girder - 65 C07B052000 C07B052020 C07B052040 C07B052060 C07B052080 C07B052100 C07B052120 C07B052140 C07B052160 C07B052180 Girder - 66 C07B062000 C07B062020 C07B062040 C07B062060 C07B062080 C07B062100 C07B062120 C07B062140 C07B062160 C07B062180 Girder - 67 C07B072000 C07B072020 C07B072040 C07B072060 C07B072080 C07B072100 C07B072120 C07B072140 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 6d 12-Mar-11 1d 17-Mar-11 14d 03-Mar-11 1d 03-Mar-11 1d 05-Mar-11 1d 06-Mar-11 2d 08-Mar-11 2d 10-Mar-11 1d 14-Mar-11 1d 15-Mar-11 1d 17-Mar-11 6d 13-Mar-11 1d 19-Mar-11 25d 05-Mar-11 16d 05-Mar-11 1d 05-Mar-11 1d 06-Mar-11 1d 07-Mar-11 2d 12-Mar-11 2d 14-Mar-11 1d 17-Mar-11 1d 19-Mar-11 1d 21-Mar-11 6d 16-Mar-11 1d 22-Mar-11 16d 06-Mar-11 1d 06-Mar-11 1d 07-Mar-11 1d 08-Mar-11 2d 13-Mar-11 2d 15-Mar-11 1d 19-Mar-11 1d 20-Mar-11 1d 22-Mar-11 6d 17-Mar-11 1d 23-Mar-11 14d 09-Mar-11 1d 09-Mar-11 1d 10-Mar-11 1d 12-Mar-11 2d 14-Mar-11 2d 16-Mar-11 1d 20-Mar-11 1d 21-Mar-11 1d 23-Mar-11 Finish Jan F 17-Mar-11 17-Mar-11 19-Mar-11 03-Mar-11 05-Mar-11 06-Mar-11 09-Mar-11 12-Mar-11 14-Mar-11 15-Mar-11 17-Mar-11 19-Mar-11 19-Mar-11 02-Apr-11 22-Mar-11 05-Mar-11 06-Mar-11 07-Mar-11 13-Mar-11 15-Mar-11 17-Mar-11 19-Mar-11 21-Mar-11 22-Mar-11 22-Mar-11 23-Mar-11 06-Mar-11 07-Mar-11 08-Mar-11 14-Mar-11 16-Mar-11 19-Mar-11 20-Mar-11 22-Mar-11 23-Mar-11 23-Mar-11 24-Mar-11 09-Mar-11 10-Mar-11 12-Mar-11 15-Mar-11 17-Mar-11 20-Mar-11 21-Mar-11 23-Mar-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

03-Mar-11

19-Mar-11

Precasting - 9th Cycle (8 Girders)

05-Mar-11 05-Mar-11

02-Apr-11 22-Mar-11

06-Mar-11

23-Mar-11

09-Mar-11

24-Mar-11

Page 31 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C07B072160 C07B072180 Girder - 68 C07B082000 C07B082020 C07B082040 C07B082060 C07B082080 C07B082100 C07B082120 C07B082140 C07B082160 C07B082180 Girder - 69 C07B092000 C07B092020 C07B092040 C07B092060 C07B092080 C07B092100 C07B092120 C07B092140 C07B092160 C07B092180 Girder - 70 C07B102000 C07B102020 C07B102040 C07B102060 C07B102080 C07B102100 C07B102120 C07B102140 C07B102160 C07B102180 Girder - 71 C08B012000 C08B012020 C08B012040 C08B012060 C08B012080 C08B012100 C08B012120 C08B012140 C08B012160 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 6d 19-Mar-11 1d 24-Mar-11 14d 10-Mar-11 1d 10-Mar-11 1d 12-Mar-11 1d 13-Mar-11 2d 15-Mar-11 2d 17-Mar-11 1d 21-Mar-11 1d 22-Mar-11 1d 24-Mar-11 6d 20-Mar-11 1d 26-Mar-11 16d 12-Mar-11 1d 12-Mar-11 1d 13-Mar-11 1d 14-Mar-11 2d 19-Mar-11 2d 21-Mar-11 1d 24-Mar-11 1d 26-Mar-11 1d 28-Mar-11 6d 23-Mar-11 1d 29-Mar-11 16d 13-Mar-11 1d 13-Mar-11 1d 14-Mar-11 1d 15-Mar-11 2d 20-Mar-11 2d 22-Mar-11 1d 26-Mar-11 1d 27-Mar-11 1d 29-Mar-11 6d 24-Mar-11 1d 30-Mar-11 14d 16-Mar-11 1d 16-Mar-11 1d 17-Mar-11 1d 19-Mar-11 2d 21-Mar-11 2d 23-Mar-11 1d 27-Mar-11 1d 28-Mar-11 1d 30-Mar-11 6d 26-Mar-11 Finish Jan F 24-Mar-11 24-Mar-11 26-Mar-11 10-Mar-11 12-Mar-11 13-Mar-11 16-Mar-11 19-Mar-11 21-Mar-11 22-Mar-11 24-Mar-11 26-Mar-11 26-Mar-11 29-Mar-11 12-Mar-11 13-Mar-11 14-Mar-11 20-Mar-11 22-Mar-11 24-Mar-11 26-Mar-11 28-Mar-11 29-Mar-11 29-Mar-11 30-Mar-11 13-Mar-11 14-Mar-11 15-Mar-11 21-Mar-11 23-Mar-11 26-Mar-11 27-Mar-11 29-Mar-11 30-Mar-11 30-Mar-11 31-Mar-11 16-Mar-11 17-Mar-11 19-Mar-11 22-Mar-11 24-Mar-11 27-Mar-11 28-Mar-11 30-Mar-11 31-Mar-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

10-Mar-11

26-Mar-11

12-Mar-11

29-Mar-11

13-Mar-11

30-Mar-11

16-Mar-11

31-Mar-11

Page 32 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C08B012180 Girder - 72 C08B022000 C08B022020 C08B022040 C08B022060 C08B022080 C08B022100 C08B022120 C08B022140 C08B022160 C08B022180 Girder - 73 C08B032000 C08B032020 C08B032040 C08B032060 C08B032080 C08B032100 C08B032120 C08B032140 C08B032160 C08B032180 Girder - 74 C08B042000 C08B042020 C08B042040 C08B042060 C08B042080 C08B042100 C08B042120 C08B042140 C08B042160 C08B042180 Girder - 75 C08B052000 C08B052020 C08B052040 C08B052060 C08B052080 C08B052100 C08B052120 C08B052140 C08B052160 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 31-Mar-11 14d 17-Mar-11 1d 17-Mar-11 1d 19-Mar-11 1d 20-Mar-11 2d 22-Mar-11 2d 24-Mar-11 1d 28-Mar-11 1d 29-Mar-11 1d 31-Mar-11 6d 27-Mar-11 1d 02-Apr-11 25d 19-Mar-11 16d 19-Mar-11 1d 19-Mar-11 1d 20-Mar-11 1d 21-Mar-11 2d 26-Mar-11 2d 28-Mar-11 1d 31-Mar-11 1d 02-Apr-11 1d 04-Apr-11 6d 30-Mar-11 1d 05-Apr-11 16d 20-Mar-11 1d 20-Mar-11 1d 21-Mar-11 1d 22-Mar-11 2d 27-Mar-11 2d 29-Mar-11 1d 02-Apr-11 1d 03-Apr-11 1d 05-Apr-11 6d 31-Mar-11 1d 06-Apr-11 14d 23-Mar-11 1d 23-Mar-11 1d 24-Mar-11 1d 26-Mar-11 2d 28-Mar-11 2d 30-Mar-11 1d 03-Apr-11 1d 04-Apr-11 1d 06-Apr-11 6d 02-Apr-11 Finish Jan F 31-Mar-11 02-Apr-11 17-Mar-11 19-Mar-11 20-Mar-11 23-Mar-11 26-Mar-11 28-Mar-11 29-Mar-11 31-Mar-11 02-Apr-11 02-Apr-11 16-Apr-11 05-Apr-11 19-Mar-11 20-Mar-11 21-Mar-11 27-Mar-11 29-Mar-11 31-Mar-11 02-Apr-11 04-Apr-11 05-Apr-11 05-Apr-11 06-Apr-11 20-Mar-11 21-Mar-11 22-Mar-11 28-Mar-11 30-Mar-11 02-Apr-11 03-Apr-11 05-Apr-11 06-Apr-11 06-Apr-11 07-Apr-11 23-Mar-11 24-Mar-11 26-Mar-11 29-Mar-11 31-Mar-11 03-Apr-11 04-Apr-11 06-Apr-11 07-Apr-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

17-Mar-11

02-Apr-11

Precasting - 10th Cycle (8 Girders)

19-Mar-11 19-Mar-11

16-Apr-11 05-Apr-11

20-Mar-11

06-Apr-11

23-Mar-11

07-Apr-11

Page 33 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C08B052180 Girder - 76 C08B062000 C08B062020 C08B062040 C08B062060 C08B062080 C08B062100 C08B062120 C08B062140 C08B062160 C08B062180 Girder - 77 C08B072000 C08B072020 C08B072040 C08B072060 C08B072080 C08B072100 C08B072120 C08B072140 C08B072160 C08B072180 Girder - 78 C08B082000 C08B082020 C08B082040 C08B082060 C08B082080 C08B082100 C08B082120 C08B082140 C08B082160 C08B082180 Girder - 79 C08B092000 C08B092020 C08B092040 C08B092060 C08B092080 C08B092100 C08B092120 C08B092140 C08B092160 C08B092180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 07-Apr-11 14d 24-Mar-11 1d 24-Mar-11 1d 26-Mar-11 1d 27-Mar-11 2d 29-Mar-11 2d 31-Mar-11 1d 04-Apr-11 1d 05-Apr-11 1d 07-Apr-11 6d 03-Apr-11 1d 09-Apr-11 16d 26-Mar-11 1d 26-Mar-11 1d 27-Mar-11 1d 28-Mar-11 2d 02-Apr-11 2d 04-Apr-11 1d 07-Apr-11 1d 09-Apr-11 1d 11-Apr-11 6d 06-Apr-11 1d 12-Apr-11 16d 27-Mar-11 1d 27-Mar-11 1d 28-Mar-11 1d 29-Mar-11 2d 03-Apr-11 2d 05-Apr-11 1d 09-Apr-11 1d 10-Apr-11 1d 12-Apr-11 6d 07-Apr-11 1d 13-Apr-11 14d 30-Mar-11 1d 30-Mar-11 1d 31-Mar-11 1d 02-Apr-11 2d 04-Apr-11 2d 06-Apr-11 1d 10-Apr-11 1d 11-Apr-11 1d 13-Apr-11 6d 09-Apr-11 1d 14-Apr-11 Finish Jan F 07-Apr-11 09-Apr-11 24-Mar-11 26-Mar-11 27-Mar-11 30-Mar-11 02-Apr-11 04-Apr-11 05-Apr-11 07-Apr-11 09-Apr-11 09-Apr-11 12-Apr-11 26-Mar-11 27-Mar-11 28-Mar-11 03-Apr-11 05-Apr-11 07-Apr-11 09-Apr-11 11-Apr-11 12-Apr-11 12-Apr-11 13-Apr-11 27-Mar-11 28-Mar-11 29-Mar-11 04-Apr-11 06-Apr-11 09-Apr-11 10-Apr-11 12-Apr-11 13-Apr-11 13-Apr-11 14-Apr-11 30-Mar-11 31-Mar-11 02-Apr-11 05-Apr-11 07-Apr-11 10-Apr-11 11-Apr-11 13-Apr-11 14-Apr-11 14-Apr-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

24-Mar-11

09-Apr-11

26-Mar-11

12-Apr-11

27-Mar-11

13-Apr-11

30-Mar-11

14-Apr-11

Page 34 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 80 C08B102000 C08B102020 C08B102040 C08B102060 C08B102080 C08B102100 C08B102120 C08B102140 C08B102160 C08B102180 Girder - 81 C09B012000 C09B012020 C09B012040 C09B012060 C09B012080 C09B012100 C09B012120 C09B012140 C09B012160 C09B012180 Girder - 82 C09B022000 C09B022020 C09B022040 C09B022060 C09B022080 C09B022100 C09B022120 C09B022140 C09B022160 C09B022180 Girder - 83 C09B032000 C09B032020 C09B032040 C09B032060 C09B032080 C09B032100 C09B032120 C09B032140 C09B032160 C09B032180 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 14d 31-Mar-11 1d 31-Mar-11 1d 02-Apr-11 1d 03-Apr-11 2d 05-Apr-11 2d 07-Apr-11 1d 11-Apr-11 1d 12-Apr-11 1d 14-Apr-11 6d 10-Apr-11 1d 16-Apr-11 25d 02-Apr-11 16d 02-Apr-11 1d 02-Apr-11 1d 03-Apr-11 1d 04-Apr-11 2d 09-Apr-11 2d 11-Apr-11 1d 14-Apr-11 1d 16-Apr-11 1d 18-Apr-11 6d 13-Apr-11 1d 19-Apr-11 16d 03-Apr-11 1d 03-Apr-11 1d 04-Apr-11 1d 05-Apr-11 2d 10-Apr-11 2d 12-Apr-11 1d 16-Apr-11 1d 17-Apr-11 1d 19-Apr-11 6d 14-Apr-11 1d 20-Apr-11 14d 06-Apr-11 1d 06-Apr-11 1d 07-Apr-11 1d 09-Apr-11 2d 11-Apr-11 2d 13-Apr-11 1d 17-Apr-11 1d 18-Apr-11 1d 20-Apr-11 6d 16-Apr-11 1d 21-Apr-11 Finish Jan F 16-Apr-11 31-Mar-11 02-Apr-11 03-Apr-11 06-Apr-11 09-Apr-11 11-Apr-11 12-Apr-11 14-Apr-11 16-Apr-11 16-Apr-11 30-Apr-11 19-Apr-11 02-Apr-11 03-Apr-11 04-Apr-11 10-Apr-11 12-Apr-11 14-Apr-11 16-Apr-11 18-Apr-11 19-Apr-11 19-Apr-11 20-Apr-11 03-Apr-11 04-Apr-11 05-Apr-11 11-Apr-11 13-Apr-11 16-Apr-11 17-Apr-11 19-Apr-11 20-Apr-11 20-Apr-11 21-Apr-11 06-Apr-11 07-Apr-11 09-Apr-11 12-Apr-11 14-Apr-11 17-Apr-11 18-Apr-11 20-Apr-11 21-Apr-11 21-Apr-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 D Jan F M Apr M J Jul 31-Mar-11 16-Apr-11 2012 M Apr M

S Oct N

S Oct N

D Jan F

J Jul

Precasting - 11th Cycle (8 Girders)

02-Apr-11 02-Apr-11

30-Apr-11 19-Apr-11

03-Apr-11

20-Apr-11

06-Apr-11

21-Apr-11

Page 35 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Girder - 84 C09B042000 C09B042020 C09B042040 C09B042060 C09B042080 C09B042100 C09B042120 C09B042140 C09B042160 C09B042180 Girder - 85 C09B052000 C09B052020 C09B052040 C09B052060 C09B052080 C09B052100 C09B052120 C09B052140 C09B052160 C09B052180 Girder - 86 C09B062000 C09B062020 C09B062040 C09B062060 C09B062080 C09B062100 C09B062120 C09B062140 C09B062160 C09B062180 Girder - 87 C09B072000 C09B072020 C09B072040 C09B072060 C09B072080 C09B072100 C09B072120 C09B072140 C09B072160 C09B072180 Girder - 88 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 14d 07-Apr-11 1d 07-Apr-11 1d 09-Apr-11 1d 10-Apr-11 2d 12-Apr-11 2d 14-Apr-11 1d 18-Apr-11 1d 19-Apr-11 1d 21-Apr-11 6d 17-Apr-11 1d 23-Apr-11 16d 09-Apr-11 1d 09-Apr-11 1d 10-Apr-11 1d 11-Apr-11 2d 16-Apr-11 2d 18-Apr-11 1d 21-Apr-11 1d 23-Apr-11 1d 25-Apr-11 6d 20-Apr-11 1d 26-Apr-11 16d 10-Apr-11 1d 10-Apr-11 1d 11-Apr-11 1d 12-Apr-11 2d 17-Apr-11 2d 19-Apr-11 1d 23-Apr-11 1d 24-Apr-11 1d 26-Apr-11 6d 21-Apr-11 1d 27-Apr-11 14d 13-Apr-11 1d 13-Apr-11 1d 14-Apr-11 1d 16-Apr-11 2d 18-Apr-11 2d 20-Apr-11 1d 24-Apr-11 1d 25-Apr-11 1d 27-Apr-11 6d 23-Apr-11 1d 28-Apr-11 14d 14-Apr-11 Finish Jan F 23-Apr-11 07-Apr-11 09-Apr-11 10-Apr-11 13-Apr-11 16-Apr-11 18-Apr-11 19-Apr-11 21-Apr-11 23-Apr-11 23-Apr-11 26-Apr-11 09-Apr-11 10-Apr-11 11-Apr-11 17-Apr-11 19-Apr-11 21-Apr-11 23-Apr-11 25-Apr-11 26-Apr-11 26-Apr-11 27-Apr-11 10-Apr-11 11-Apr-11 12-Apr-11 18-Apr-11 20-Apr-11 23-Apr-11 24-Apr-11 26-Apr-11 27-Apr-11 27-Apr-11 28-Apr-11 13-Apr-11 14-Apr-11 16-Apr-11 19-Apr-11 21-Apr-11 24-Apr-11 25-Apr-11 27-Apr-11 28-Apr-11 28-Apr-11 30-Apr-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 D Jan F M Apr M J Jul 07-Apr-11 23-Apr-11 2012 M Apr M

S Oct N

S Oct N

D Jan F

J Jul

09-Apr-11

26-Apr-11

10-Apr-11

27-Apr-11

13-Apr-11

28-Apr-11

14-Apr-11 TASK filter: All Activities

30-Apr-11

Page 36 of 115

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C09B082000 C09B082020 C09B082040 C09B082060 C09B082080 C09B082100 C09B082120 C09B082140 C09B082160 C09B082180 Girder - 89 C09B092000 C09B092020 C09B092040 C09B092060 C09B092080 C09B092100 C09B092120 C09B092140 C09B092160 C09B092180 Girder - 90 C09B102000 C09B102020 C09B102040 C09B102060 C09B102080 C09B102100 C09B102120 C09B102140 C09B102160 C09B102180 Girder - 91 C10B012000 C10B012020 C10B012040 C10B012060 C10B012080 C10B012100 C10B012120 C10B012140 C10B012160 C10B012180 Girder - 92 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 14-Apr-11 1d 16-Apr-11 1d 17-Apr-11 2d 19-Apr-11 2d 21-Apr-11 1d 25-Apr-11 1d 26-Apr-11 1d 28-Apr-11 6d 24-Apr-11 1d 30-Apr-11 25d 16-Apr-11 16d 16-Apr-11 1d 16-Apr-11 1d 17-Apr-11 1d 18-Apr-11 2d 23-Apr-11 2d 25-Apr-11 1d 28-Apr-11 1d 30-Apr-11 1d 02-May-11 6d 27-Apr-11 1d 03-May-11 16d 17-Apr-11 1d 17-Apr-11 1d 18-Apr-11 1d 19-Apr-11 2d 24-Apr-11 2d 26-Apr-11 1d 30-Apr-11 1d 01-May-11 1d 03-May-11 6d 28-Apr-11 1d 04-May-11 14d 20-Apr-11 1d 20-Apr-11 1d 21-Apr-11 1d 23-Apr-11 2d 25-Apr-11 2d 27-Apr-11 1d 01-May-11 1d 02-May-11 1d 04-May-11 6d 30-Apr-11 1d 05-May-11 14d 21-Apr-11 Finish Jan F 14-Apr-11 16-Apr-11 17-Apr-11 20-Apr-11 23-Apr-11 25-Apr-11 26-Apr-11 28-Apr-11 30-Apr-11 30-Apr-11 14-May-11 03-May-11 16-Apr-11 17-Apr-11 18-Apr-11 24-Apr-11 26-Apr-11 28-Apr-11 30-Apr-11 02-May-11 03-May-11 03-May-11 04-May-11 17-Apr-11 18-Apr-11 19-Apr-11 25-Apr-11 27-Apr-11 30-Apr-11 01-May-11 03-May-11 04-May-11 04-May-11 05-May-11 20-Apr-11 21-Apr-11 23-Apr-11 26-Apr-11 28-Apr-11 01-May-11 02-May-11 04-May-11 05-May-11 05-May-11 07-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 12th Cycle (8 Girders)

16-Apr-11 16-Apr-11

14-May-11 03-May-11

17-Apr-11

04-May-11

20-Apr-11

05-May-11

21-Apr-11 TASK filter: All Activities

07-May-11

Page 37 of 115

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C10B022000 C10B022020 C10B022040 C10B022060 C10B022080 C10B022100 C10B022120 C10B022140 C10B022160 C10B022180 Girder - 93 C10B032000 C10B032020 C10B032040 C10B032060 C10B032080 C10B032100 C10B032120 C10B032140 C10B032160 C10B032180 Girder - 94 C10B042000 C10B042020 C10B042040 C10B042060 C10B042080 C10B042100 C10B042120 C10B042140 C10B042160 C10B042180 Girder - 95 C10B052000 C10B052020 C10B052040 C10B052060 C10B052080 C10B052100 C10B052120 C10B052140 C10B052160 C10B052180 Girder - 96 C10B062000 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 21-Apr-11 1d 23-Apr-11 1d 24-Apr-11 2d 26-Apr-11 2d 28-Apr-11 1d 02-May-11 1d 03-May-11 1d 05-May-11 6d 01-May-11 1d 07-May-11 16d 23-Apr-11 1d 23-Apr-11 1d 24-Apr-11 1d 25-Apr-11 2d 30-Apr-11 2d 02-May-11 1d 05-May-11 1d 07-May-11 1d 09-May-11 6d 04-May-11 1d 10-May-11 16d 24-Apr-11 1d 24-Apr-11 1d 25-Apr-11 1d 26-Apr-11 2d 01-May-11 2d 03-May-11 1d 07-May-11 1d 08-May-11 1d 10-May-11 6d 05-May-11 1d 11-May-11 14d 27-Apr-11 1d 27-Apr-11 1d 28-Apr-11 1d 30-Apr-11 2d 02-May-11 2d 04-May-11 1d 08-May-11 1d 09-May-11 1d 11-May-11 6d 07-May-11 1d 12-May-11 14d 28-Apr-11 1d 28-Apr-11 Finish Jan F 21-Apr-11 23-Apr-11 24-Apr-11 27-Apr-11 30-Apr-11 02-May-11 03-May-11 05-May-11 07-May-11 07-May-11 10-May-11 23-Apr-11 24-Apr-11 25-Apr-11 01-May-11 03-May-11 05-May-11 07-May-11 09-May-11 10-May-11 10-May-11 11-May-11 24-Apr-11 25-Apr-11 26-Apr-11 02-May-11 04-May-11 07-May-11 08-May-11 10-May-11 11-May-11 11-May-11 12-May-11 27-Apr-11 28-Apr-11 30-Apr-11 03-May-11 05-May-11 08-May-11 09-May-11 11-May-11 12-May-11 12-May-11 14-May-11 28-Apr-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

23-Apr-11

10-May-11

24-Apr-11

11-May-11

27-Apr-11

12-May-11

28-Apr-11

14-May-11

Page 38 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C10B062020 C10B062040 C10B062060 C10B062080 C10B062100 C10B062120 C10B062140 C10B062160 C10B062180 Girder - 97 C10B072000 C10B072020 C10B072040 C10B072060 C10B072080 C10B072100 C10B072120 C10B072140 C10B072160 C10B072180 Girder - 98 C10B082000 C10B082020 C10B082040 C10B082060 C10B082080 C10B082100 C10B082120 C10B082140 C10B082160 C10B082180 Girder - 99 C10B092000 C10B092020 C10B092040 C10B092060 C10B092080 C10B092100 C10B092120 C10B092140 C10B092160 C10B092180 Girder - 100 C10B102000 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 30-Apr-11 1d 01-May-11 2d 03-May-11 2d 05-May-11 1d 09-May-11 1d 10-May-11 1d 12-May-11 6d 08-May-11 1d 14-May-11 25d 30-Apr-11 16d 30-Apr-11 1d 30-Apr-11 1d 01-May-11 1d 02-May-11 2d 07-May-11 2d 09-May-11 1d 12-May-11 1d 14-May-11 1d 16-May-11 6d 11-May-11 1d 17-May-11 16d 01-May-11 1d 01-May-11 1d 02-May-11 1d 03-May-11 2d 08-May-11 2d 10-May-11 1d 14-May-11 1d 15-May-11 1d 17-May-11 6d 12-May-11 1d 18-May-11 14d 04-May-11 1d 04-May-11 1d 05-May-11 1d 07-May-11 2d 09-May-11 2d 11-May-11 1d 15-May-11 1d 16-May-11 1d 18-May-11 6d 14-May-11 1d 19-May-11 14d 05-May-11 1d 05-May-11 Finish Jan F 30-Apr-11 01-May-11 04-May-11 07-May-11 09-May-11 10-May-11 12-May-11 14-May-11 14-May-11 28-May-11 17-May-11 30-Apr-11 01-May-11 02-May-11 08-May-11 10-May-11 12-May-11 14-May-11 16-May-11 17-May-11 17-May-11 18-May-11 01-May-11 02-May-11 03-May-11 09-May-11 11-May-11 14-May-11 15-May-11 17-May-11 18-May-11 18-May-11 19-May-11 04-May-11 05-May-11 07-May-11 10-May-11 12-May-11 15-May-11 16-May-11 18-May-11 19-May-11 19-May-11 21-May-11 05-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 13th Cycle (8 Girders)

30-Apr-11 30-Apr-11

28-May-11 17-May-11

01-May-11

18-May-11

04-May-11

19-May-11

05-May-11

21-May-11

Page 39 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C10B102020 C10B102040 C10B102060 C10B102080 C10B102100 C10B102120 C10B102140 C10B102160 C10B102180 Girder - 101 C11B012000 C11B012020 C11B012040 C11B012060 C11B012080 C11B012100 C11B012120 C11B012140 C11B012160 C11B012180 Girder - 102 C11B022000 C11B022020 C11B022040 C11B022060 C11B022080 C11B022100 C11B022120 C11B022140 C11B022160 C11B022180 Girder - 103 C11B032000 C11B032020 C11B032040 C11B032060 C11B032080 C11B032100 C11B032120 C11B032140 C11B032160 C11B032180 Girder - 104 C11B042000 C11B042020 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 07-May-11 1d 08-May-11 2d 10-May-11 2d 12-May-11 1d 16-May-11 1d 17-May-11 1d 19-May-11 6d 15-May-11 1d 21-May-11 16d 07-May-11 1d 07-May-11 1d 08-May-11 1d 09-May-11 2d 14-May-11 2d 16-May-11 1d 19-May-11 1d 21-May-11 1d 23-May-11 6d 18-May-11 1d 24-May-11 16d 08-May-11 1d 08-May-11 1d 09-May-11 1d 10-May-11 2d 15-May-11 2d 17-May-11 1d 21-May-11 1d 22-May-11 1d 24-May-11 6d 19-May-11 1d 25-May-11 14d 11-May-11 1d 11-May-11 1d 12-May-11 1d 14-May-11 2d 16-May-11 2d 18-May-11 1d 22-May-11 1d 23-May-11 1d 25-May-11 6d 21-May-11 1d 26-May-11 14d 12-May-11 1d 12-May-11 1d 14-May-11 Finish Jan F 07-May-11 08-May-11 11-May-11 14-May-11 16-May-11 17-May-11 19-May-11 21-May-11 21-May-11 24-May-11 07-May-11 08-May-11 09-May-11 15-May-11 17-May-11 19-May-11 21-May-11 23-May-11 24-May-11 24-May-11 25-May-11 08-May-11 09-May-11 10-May-11 16-May-11 18-May-11 21-May-11 22-May-11 24-May-11 25-May-11 25-May-11 26-May-11 11-May-11 12-May-11 14-May-11 17-May-11 19-May-11 22-May-11 23-May-11 25-May-11 26-May-11 26-May-11 28-May-11 12-May-11 14-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

07-May-11

24-May-11

08-May-11

25-May-11

11-May-11

26-May-11

12-May-11

28-May-11

Page 40 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C11B042040 C11B042060 C11B042080 C11B042100 C11B042120 C11B042140 C11B042160 C11B042180 Girder - 105 C11B052000 C11B052020 C11B052040 C11B052060 C11B052080 C11B052100 C11B052120 C11B052140 C11B052160 C11B052180 Girder - 106 C11B062000 C11B062020 C11B062040 C11B062060 C11B062080 C11B062100 C11B062120 C11B062140 C11B062160 C11B062180 Girder - 107 C11B072000 C11B072020 C11B072040 C11B072060 C11B072080 C11B072100 C11B072120 C11B072140 C11B072160 C11B072180 Girder - 108 C11B082000 C11B082020 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 15-May-11 2d 17-May-11 2d 19-May-11 1d 23-May-11 1d 24-May-11 1d 26-May-11 6d 22-May-11 1d 28-May-11 25d 14-May-11 16d 14-May-11 1d 14-May-11 1d 15-May-11 1d 16-May-11 2d 21-May-11 2d 23-May-11 1d 26-May-11 1d 28-May-11 1d 30-May-11 6d 25-May-11 1d 31-May-11 16d 15-May-11 1d 15-May-11 1d 16-May-11 1d 17-May-11 2d 22-May-11 2d 24-May-11 1d 28-May-11 1d 29-May-11 1d 31-May-11 6d 26-May-11 1d 01-Jun-11 14d 18-May-11 1d 18-May-11 1d 19-May-11 1d 21-May-11 2d 23-May-11 2d 25-May-11 1d 29-May-11 1d 30-May-11 1d 01-Jun-11 6d 28-May-11 1d 02-Jun-11 14d 19-May-11 1d 19-May-11 1d 21-May-11 Finish Jan F 15-May-11 18-May-11 21-May-11 23-May-11 24-May-11 26-May-11 28-May-11 28-May-11 11-Jun-11 31-May-11 14-May-11 15-May-11 16-May-11 22-May-11 24-May-11 26-May-11 28-May-11 30-May-11 31-May-11 31-May-11 01-Jun-11 15-May-11 16-May-11 17-May-11 23-May-11 25-May-11 28-May-11 29-May-11 31-May-11 01-Jun-11 01-Jun-11 02-Jun-11 18-May-11 19-May-11 21-May-11 24-May-11 26-May-11 29-May-11 30-May-11 01-Jun-11 02-Jun-11 02-Jun-11 04-Jun-11 19-May-11 21-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 14th Cycle (8 Girders)

14-May-11 14-May-11

11-Jun-11 31-May-11

15-May-11

01-Jun-11

18-May-11

02-Jun-11

19-May-11

04-Jun-11

Page 41 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C11B082040 C11B082060 C11B082080 C11B082100 C11B082120 C11B082140 C11B082160 C11B082180 Girder - 109 C11B092000 C11B092020 C11B092040 C11B092060 C11B092080 C11B092100 C11B092120 C11B092140 C11B092160 C11B092180 Girder - 110 C11B102000 C11B102020 C11B102040 C11B102060 C11B102080 C11B102100 C11B102120 C11B102140 C11B102160 C11B102180 Girder - 111 C12B012000 C12B012020 C12B012040 C12B012060 C12B012080 C12B012100 C12B012120 C12B012140 C12B012160 C12B012180 Girder - 112 C12B022000 C12B022020 C12B022040 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 22-May-11 2d 24-May-11 2d 26-May-11 1d 30-May-11 1d 31-May-11 1d 02-Jun-11 6d 29-May-11 1d 04-Jun-11 16d 21-May-11 1d 21-May-11 1d 22-May-11 1d 23-May-11 2d 28-May-11 2d 30-May-11 1d 02-Jun-11 1d 04-Jun-11 1d 06-Jun-11 6d 01-Jun-11 1d 07-Jun-11 16d 22-May-11 1d 22-May-11 1d 23-May-11 1d 24-May-11 2d 29-May-11 2d 31-May-11 1d 04-Jun-11 1d 05-Jun-11 1d 07-Jun-11 6d 02-Jun-11 1d 08-Jun-11 14d 25-May-11 1d 25-May-11 1d 26-May-11 1d 28-May-11 2d 30-May-11 2d 01-Jun-11 1d 05-Jun-11 1d 06-Jun-11 1d 08-Jun-11 6d 04-Jun-11 1d 09-Jun-11 14d 26-May-11 1d 26-May-11 1d 28-May-11 1d 29-May-11 Finish Jan F 22-May-11 25-May-11 28-May-11 30-May-11 31-May-11 02-Jun-11 04-Jun-11 04-Jun-11 07-Jun-11 21-May-11 22-May-11 23-May-11 29-May-11 31-May-11 02-Jun-11 04-Jun-11 06-Jun-11 07-Jun-11 07-Jun-11 08-Jun-11 22-May-11 23-May-11 24-May-11 30-May-11 01-Jun-11 04-Jun-11 05-Jun-11 07-Jun-11 08-Jun-11 08-Jun-11 09-Jun-11 25-May-11 26-May-11 28-May-11 31-May-11 02-Jun-11 05-Jun-11 06-Jun-11 08-Jun-11 09-Jun-11 09-Jun-11 11-Jun-11 26-May-11 28-May-11 29-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

21-May-11

07-Jun-11

22-May-11

08-Jun-11

25-May-11

09-Jun-11

26-May-11

11-Jun-11

Page 42 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C12B022060 C12B022080 C12B022100 C12B022120 C12B022140 C12B022160 C12B022180 Girder - 113 C12B032000 C12B032020 C12B032040 C12B032060 C12B032080 C12B032100 C12B032120 C12B032140 C12B032160 C12B032180 Girder - 114 C12B042000 C12B042020 C12B042040 C12B042060 C12B042080 C12B042100 C12B042120 C12B042140 C12B042160 C12B042180 Girder - 115 C12B052000 C12B052020 C12B052040 C12B052060 C12B052080 C12B052100 C12B052120 C12B052140 C12B052160 C12B052180 Girder - 116 C12B062000 C12B062020 C12B062040 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 31-May-11 2d 02-Jun-11 1d 06-Jun-11 1d 07-Jun-11 1d 09-Jun-11 6d 05-Jun-11 1d 11-Jun-11 25d 28-May-11 16d 28-May-11 1d 28-May-11 1d 29-May-11 1d 30-May-11 2d 04-Jun-11 2d 06-Jun-11 1d 09-Jun-11 1d 11-Jun-11 1d 13-Jun-11 6d 08-Jun-11 1d 14-Jun-11 16d 29-May-11 1d 29-May-11 1d 30-May-11 1d 31-May-11 2d 05-Jun-11 2d 07-Jun-11 1d 11-Jun-11 1d 12-Jun-11 1d 14-Jun-11 6d 09-Jun-11 1d 15-Jun-11 14d 01-Jun-11 1d 01-Jun-11 1d 02-Jun-11 1d 04-Jun-11 2d 06-Jun-11 2d 08-Jun-11 1d 12-Jun-11 1d 13-Jun-11 1d 15-Jun-11 6d 11-Jun-11 1d 16-Jun-11 14d 02-Jun-11 1d 02-Jun-11 1d 04-Jun-11 1d 05-Jun-11 Finish Jan F 01-Jun-11 04-Jun-11 06-Jun-11 07-Jun-11 09-Jun-11 11-Jun-11 11-Jun-11 25-Jun-11 14-Jun-11 28-May-11 29-May-11 30-May-11 05-Jun-11 07-Jun-11 09-Jun-11 11-Jun-11 13-Jun-11 14-Jun-11 14-Jun-11 15-Jun-11 29-May-11 30-May-11 31-May-11 06-Jun-11 08-Jun-11 11-Jun-11 12-Jun-11 14-Jun-11 15-Jun-11 15-Jun-11 16-Jun-11 01-Jun-11 02-Jun-11 04-Jun-11 07-Jun-11 09-Jun-11 12-Jun-11 13-Jun-11 15-Jun-11 16-Jun-11 16-Jun-11 18-Jun-11 02-Jun-11 04-Jun-11 05-Jun-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 15th Cycle (8 Girders)

28-May-11 28-May-11

25-Jun-11 14-Jun-11

29-May-11

15-Jun-11

01-Jun-11

16-Jun-11

02-Jun-11

18-Jun-11

Page 43 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C12B062060 C12B062080 C12B062100 C12B062120 C12B062140 C12B062160 C12B062180 Girder - 117 C12B072000 C12B072020 C12B072040 C12B072060 C12B072080 C12B072100 C12B072120 C12B072140 C12B072160 C12B072180 Girder - 118 C12B082000 C12B082020 C12B082040 C12B082060 C12B082080 C12B082100 C12B082120 C12B082140 C12B082160 C12B082180 Girder - 119 C12B092000 C12B092020 C12B092040 C12B092060 C12B092080 C12B092100 C12B092120 C12B092140 C12B092160 C12B092180 Girder - 120 C12B102000 C12B102020 C12B102040 C12B102060 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 07-Jun-11 2d 09-Jun-11 1d 13-Jun-11 1d 14-Jun-11 1d 16-Jun-11 6d 12-Jun-11 1d 18-Jun-11 16d 04-Jun-11 1d 04-Jun-11 1d 05-Jun-11 1d 06-Jun-11 2d 11-Jun-11 2d 13-Jun-11 1d 16-Jun-11 1d 18-Jun-11 1d 20-Jun-11 6d 15-Jun-11 1d 21-Jun-11 16d 05-Jun-11 1d 05-Jun-11 1d 06-Jun-11 1d 07-Jun-11 2d 12-Jun-11 2d 14-Jun-11 1d 18-Jun-11 1d 19-Jun-11 1d 21-Jun-11 6d 16-Jun-11 1d 22-Jun-11 14d 08-Jun-11 1d 08-Jun-11 1d 09-Jun-11 1d 11-Jun-11 2d 13-Jun-11 2d 15-Jun-11 1d 19-Jun-11 1d 20-Jun-11 1d 22-Jun-11 6d 18-Jun-11 1d 23-Jun-11 14d 09-Jun-11 1d 09-Jun-11 1d 11-Jun-11 1d 12-Jun-11 2d 14-Jun-11 Finish Jan F 08-Jun-11 11-Jun-11 13-Jun-11 14-Jun-11 16-Jun-11 18-Jun-11 18-Jun-11 21-Jun-11 04-Jun-11 05-Jun-11 06-Jun-11 12-Jun-11 14-Jun-11 16-Jun-11 18-Jun-11 20-Jun-11 21-Jun-11 21-Jun-11 22-Jun-11 05-Jun-11 06-Jun-11 07-Jun-11 13-Jun-11 15-Jun-11 18-Jun-11 19-Jun-11 21-Jun-11 22-Jun-11 22-Jun-11 23-Jun-11 08-Jun-11 09-Jun-11 11-Jun-11 14-Jun-11 16-Jun-11 19-Jun-11 20-Jun-11 22-Jun-11 23-Jun-11 23-Jun-11 25-Jun-11 09-Jun-11 11-Jun-11 12-Jun-11 15-Jun-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

04-Jun-11

21-Jun-11

05-Jun-11

22-Jun-11

08-Jun-11

23-Jun-11

09-Jun-11

25-Jun-11

Page 44 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C12B102080 C12B102100 C12B102120 C12B102140 C12B102160 C12B102180 Girder - 121 C13B012000 C13B012020 C13B012040 C13B012060 C13B012080 C13B012100 C13B012120 C13B012140 C13B012160 C13B012180 Girder - 122 C13B022000 C13B022020 C13B022040 C13B022060 C13B022080 C13B022100 C13B022120 C13B022140 C13B022160 C13B022180 Girder - 123 C13B032000 C13B032020 C13B032040 C13B032060 C13B032080 C13B032100 C13B032120 C13B032140 C13B032160 C13B032180 Girder - 124 C13B042000 C13B042020 C13B042040 C13B042060 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 16-Jun-11 1d 20-Jun-11 1d 21-Jun-11 1d 23-Jun-11 6d 19-Jun-11 1d 25-Jun-11 25d 11-Jun-11 16d 11-Jun-11 1d 11-Jun-11 1d 12-Jun-11 1d 13-Jun-11 2d 18-Jun-11 2d 20-Jun-11 1d 23-Jun-11 1d 25-Jun-11 1d 27-Jun-11 6d 22-Jun-11 1d 28-Jun-11 16d 12-Jun-11 1d 12-Jun-11 1d 13-Jun-11 1d 14-Jun-11 2d 19-Jun-11 2d 21-Jun-11 1d 25-Jun-11 1d 26-Jun-11 1d 28-Jun-11 6d 23-Jun-11 1d 29-Jun-11 14d 15-Jun-11 1d 15-Jun-11 1d 16-Jun-11 1d 18-Jun-11 2d 20-Jun-11 2d 22-Jun-11 1d 26-Jun-11 1d 27-Jun-11 1d 29-Jun-11 6d 25-Jun-11 1d 30-Jun-11 14d 16-Jun-11 1d 16-Jun-11 1d 18-Jun-11 1d 19-Jun-11 2d 21-Jun-11 Finish Jan F 18-Jun-11 20-Jun-11 21-Jun-11 23-Jun-11 25-Jun-11 25-Jun-11 09-Jul-11 28-Jun-11 11-Jun-11 12-Jun-11 13-Jun-11 19-Jun-11 21-Jun-11 23-Jun-11 25-Jun-11 27-Jun-11 28-Jun-11 28-Jun-11 29-Jun-11 12-Jun-11 13-Jun-11 14-Jun-11 20-Jun-11 22-Jun-11 25-Jun-11 26-Jun-11 28-Jun-11 29-Jun-11 29-Jun-11 30-Jun-11 15-Jun-11 16-Jun-11 18-Jun-11 21-Jun-11 23-Jun-11 26-Jun-11 27-Jun-11 29-Jun-11 30-Jun-11 30-Jun-11 02-Jul-11 16-Jun-11 18-Jun-11 19-Jun-11 22-Jun-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 16th Cycle (8 Girders)

11-Jun-11 11-Jun-11

09-Jul-11 28-Jun-11

12-Jun-11

29-Jun-11

15-Jun-11

30-Jun-11

16-Jun-11

02-Jul-11

Page 45 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C13B042080 C13B042100 C13B042120 C13B042140 C13B042160 C13B042180 Girder - 125 C13B052000 C13B052020 C13B052040 C13B052060 C13B052080 C13B052100 C13B052120 C13B052140 C13B052160 C13B052180 Girder - 126 C13B062000 C13B062020 C13B062040 C13B062060 C13B062080 C13B062100 C13B062120 C13B062140 C13B062160 C13B062180 Girder - 127 C13B072000 C13B072020 C13B072040 C13B072060 C13B072080 C13B072100 C13B072120 C13B072140 C13B072160 C13B072180 Girder - 128 C13B082000 C13B082020 C13B082040 C13B082060 C13B082080 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 23-Jun-11 1d 27-Jun-11 1d 28-Jun-11 1d 30-Jun-11 6d 26-Jun-11 1d 02-Jul-11 16d 18-Jun-11 1d 18-Jun-11 1d 19-Jun-11 1d 20-Jun-11 2d 25-Jun-11 2d 27-Jun-11 1d 30-Jun-11 1d 02-Jul-11 1d 04-Jul-11 6d 29-Jun-11 1d 05-Jul-11 16d 19-Jun-11 1d 19-Jun-11 1d 20-Jun-11 1d 21-Jun-11 2d 26-Jun-11 2d 28-Jun-11 1d 02-Jul-11 1d 03-Jul-11 1d 05-Jul-11 6d 30-Jun-11 1d 06-Jul-11 14d 22-Jun-11 1d 22-Jun-11 1d 23-Jun-11 1d 25-Jun-11 2d 27-Jun-11 2d 29-Jun-11 1d 03-Jul-11 1d 04-Jul-11 1d 06-Jul-11 6d 02-Jul-11 1d 07-Jul-11 14d 23-Jun-11 1d 23-Jun-11 1d 25-Jun-11 1d 26-Jun-11 2d 28-Jun-11 2d 30-Jun-11 Finish Jan F 25-Jun-11 27-Jun-11 28-Jun-11 30-Jun-11 02-Jul-11 02-Jul-11 05-Jul-11 18-Jun-11 19-Jun-11 20-Jun-11 26-Jun-11 28-Jun-11 30-Jun-11 02-Jul-11 04-Jul-11 05-Jul-11 05-Jul-11 06-Jul-11 19-Jun-11 20-Jun-11 21-Jun-11 27-Jun-11 29-Jun-11 02-Jul-11 03-Jul-11 05-Jul-11 06-Jul-11 06-Jul-11 07-Jul-11 22-Jun-11 23-Jun-11 25-Jun-11 28-Jun-11 30-Jun-11 03-Jul-11 04-Jul-11 06-Jul-11 07-Jul-11 07-Jul-11 09-Jul-11 23-Jun-11 25-Jun-11 26-Jun-11 29-Jun-11 02-Jul-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

18-Jun-11

05-Jul-11

19-Jun-11

06-Jul-11

22-Jun-11

07-Jul-11

23-Jun-11

09-Jul-11

Page 46 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C13B082100 C13B082120 C13B082140 C13B082160 C13B082180 Girder - 129 C13B092000 C13B092020 C13B092040 C13B092060 C13B092080 C13B092100 C13B092120 C13B092140 C13B092160 C13B092180 Girder - 130 C13B102000 C13B102020 C13B102040 C13B102060 C13B102080 C13B102100 C13B102120 C13B102140 C13B102160 C13B102180 Girder - 131 C14B012000 C14B012020 C14B012040 C14B012060 C14B012080 C14B012100 C14B012120 C14B012140 C14B012160 C14B012180 Girder - 132 C14B022000 C14B022020 C14B022040 C14B022060 C14B022080 Remaining Level of Effort Actual Work Remaining Work Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Critical Remaining Work Milestone Summary Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation & Fixing of Ply over Bed Fixing of Rebars Prestress Ducts Fixing and Profiling Sheeting and Fixing of Sides (2 Sides) Checking & Concreting Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Activity Name Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 04-Jul-11 1d 05-Jul-11 1d 07-Jul-11 6d 03-Jul-11 1d 09-Jul-11 19d 25-Jun-11 16d 25-Jun-11 1d 25-Jun-11 1d 26-Jun-11 1d 27-Jun-11 2d 02-Jul-11 2d 04-Jul-11 1d 07-Jul-11 1d 09-Jul-11 1d 11-Jul-11 6d 06-Jul-11 1d 12-Jul-11 16d 26-Jun-11 1d 26-Jun-11 1d 27-Jun-11 1d 28-Jun-11 2d 03-Jul-11 2d 05-Jul-11 1d 09-Jul-11 1d 10-Jul-11 1d 12-Jul-11 6d 07-Jul-11 1d 13-Jul-11 14d 29-Jun-11 1d 29-Jun-11 1d 30-Jun-11 1d 02-Jul-11 2d 04-Jul-11 2d 06-Jul-11 1d 10-Jul-11 1d 11-Jul-11 1d 13-Jul-11 6d 09-Jul-11 1d 14-Jul-11 14d 30-Jun-11 1d 30-Jun-11 1d 02-Jul-11 1d 03-Jul-11 2d 05-Jul-11 2d 07-Jul-11 Finish Jan F 04-Jul-11 05-Jul-11 07-Jul-11 09-Jul-11 09-Jul-11 16-Jul-11 12-Jul-11 25-Jun-11 26-Jun-11 27-Jun-11 03-Jul-11 05-Jul-11 07-Jul-11 09-Jul-11 11-Jul-11 12-Jul-11 12-Jul-11 13-Jul-11 26-Jun-11 27-Jun-11 28-Jun-11 04-Jul-11 06-Jul-11 09-Jul-11 10-Jul-11 12-Jul-11 13-Jul-11 13-Jul-11 14-Jul-11 29-Jun-11 30-Jun-11 02-Jul-11 05-Jul-11 07-Jul-11 10-Jul-11 11-Jul-11 13-Jul-11 14-Jul-11 14-Jul-11 16-Jul-11 30-Jun-11 02-Jul-11 03-Jul-11 06-Jul-11 09-Jul-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Precasting - 17th Cycle (4 Girders)

25-Jun-11 25-Jun-11

16-Jul-11 12-Jul-11

26-Jun-11

13-Jul-11

29-Jun-11

14-Jul-11

30-Jun-11

16-Jul-11

Page 47 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID C14B022100 C14B022120 C14B022140 C14B022160 C14B022180 IS2-PC-WB1000 IS2-PC-WB1020 IS2-PC-WB1040 Activity Name Deshuttering of Shutter Prestressing Works (After 3 Days or 70% Strength) Strand Cutting & Grouting (After 24 Hrs Relaxation Check) Curing Lifting from Bed Preparation of Yard for Infill Slabs Fabrication of Moulds and Rebar Delivery Casting Infill Slabs (10 No. per Day) (1.150m x 1.500m)

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 11-Jul-11 1d 12-Jul-11 1d 14-Jul-11 6d 10-Jul-11 1d 16-Jul-11 281d 04-Oct-10 14d 04-Oct-10 7d 20-Oct-10 260d 28-Oct-10 389d 15-Dec-10 215d 15-Dec-10 191d 15-Dec-10 113d 15-Dec-10 1d 15-Dec-10 2d 16-Dec-10 1d 19-Dec-10 3d 20-Dec-10 2d 23-Dec-10 1d 26-Dec-10 4d 27-Dec-10 3d 01-Jan-11 1d 04-Jan-11 1d 05-Jan-11 1d 08-Jan-11 15d 06-Jan-11 1d 09-Jan-11 4d 10-Jan-11 2d 15-Jan-11 3d 17-Jan-11 1d 20-Jan-11 1d 22-Jan-11 1d 24-Jan-11 15d 23-Jan-11 5d 09-Feb-11 4d 15-Feb-11 6d 20-Feb-11 4d 27-Feb-11 1d 03-Mar-11 1d 05-Mar-11 2d 13-Mar-11 1d 15-Mar-11 1d 16-Mar-11 1d 17-Mar-11 1d 19-Mar-11 1d 24-Apr-11 Finish Jan F 11-Jul-11 12-Jul-11 14-Jul-11 16-Jul-11 16-Jul-11 27-Aug-11 19-Oct-10 27-Oct-10 27-Aug-11 12-Mar-12 22-Aug-11 25-Jul-11 25-Apr-11 15-Dec-10 18-Dec-10 19-Dec-10 22-Dec-10 25-Dec-10 26-Dec-10 30-Dec-10 03-Jan-11 04-Jan-11 05-Jan-11 08-Jan-11 23-Jan-11 09-Jan-11 13-Jan-11 16-Jan-11 19-Jan-11 20-Jan-11 22-Jan-11 24-Jan-11 08-Feb-11 14-Feb-11 19-Feb-11 26-Feb-11 02-Mar-11 03-Mar-11 05-Mar-11 14-Mar-11 15-Mar-11 16-Mar-11 17-Mar-11 19-Mar-11 24-Apr-11 04-Oct-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Precasting - Infill Slabs (2200 Nos.)

27-Aug-11

FLYOVER WIDENING
SUBSTRUCTURE PIERS
Pier - 03 (Athaibah Side Side) FO-A-P3000 FO-A-P3010 FO-A-P3020 FO-A-P3030 FO-A-P3040 FO-A-P3050 FO-A-P3060 FO-A-P3070 FO-A-P3080 FO-A-P3090 FO-A-P3100 FO-A-P3110 FO-A-P3120 FO-A-P3130 FO-A-P3140 FO-A-P3150 FO-A-P3160 FO-A-P3170 FO-A-P3180 FO-A-P3190 FO-A-P3200 FO-A-P3210 FO-A-P3220 FO-A-P3230 FO-A-P3240 FO-A-P3250 FO-A-P3260 FO-A-P3270 FO-A-P3280 FO-A-P3290 FO-A-P3300 FO-A-P3310 Remaining Level of Effort Actual Work Remaining Work Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Critical Remaining Work Milestone Summary

15-Dec-10 15-Dec-10 15-Dec-10 15-Dec-10 25-Apr-11 22-Aug-11 25-Jul-11

12-Mar-12

Page 48 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-P3320 FO-A-P4000 FO-A-P4010 FO-A-P4020 FO-A-P4030 FO-A-P4040 FO-A-P4050 FO-A-P4060 FO-A-P4070 FO-A-P4080 FO-A-P4090 FO-A-P4100 FO-A-P4110 FO-A-P4120 FO-A-P4130 FO-A-P4140 FO-A-P4150 FO-A-P4160 FO-A-P4170 FO-A-P4180 FO-A-P4190 FO-A-P4200 FO-A-P4210 FO-A-P4220 FO-A-P4230 FO-A-P4240 FO-A-P4250 FO-A-P4260 FO-A-P4270 FO-A-P4280 FO-A-P4290 FO-A-P4300 FO-A-P4310 FO-A-P4320 FO-A-P5000 FO-A-P5010 FO-A-P5020 FO-A-P5030 FO-A-P5040 FO-A-P5050 FO-A-P5060 FO-A-P5070 FO-A-P5080 Remaining Level of Effort Actual Work Remaining Work Activity Name Fixing of Bearings (Before Girder Launching) Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching) Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 25-Apr-11 113d 22-Dec-10 1d 22-Dec-10 2d 23-Dec-10 1d 26-Dec-10 3d 27-Dec-10 2d 30-Dec-10 1d 02-Jan-11 4d 03-Jan-11 3d 08-Jan-11 1d 11-Jan-11 1d 12-Jan-11 1d 15-Jan-11 15d 13-Jan-11 1d 16-Jan-11 4d 17-Jan-11 2d 22-Jan-11 3d 24-Jan-11 1d 27-Jan-11 1d 29-Jan-11 1d 31-Jan-11 15d 30-Jan-11 5d 16-Feb-11 4d 22-Feb-11 6d 27-Feb-11 4d 06-Mar-11 1d 10-Mar-11 1d 12-Mar-11 2d 20-Mar-11 1d 22-Mar-11 1d 23-Mar-11 1d 24-Mar-11 1d 26-Mar-11 1d 01-May-11 1d 02-May-11 113d 29-Dec-10 1d 29-Dec-10 2d 30-Dec-10 1d 02-Jan-11 3d 03-Jan-11 2d 06-Jan-11 1d 09-Jan-11 4d 10-Jan-11 3d 15-Jan-11 1d 18-Jan-11 Finish Jan F 25-Apr-11 02-May-11 22-Dec-10 25-Dec-10 26-Dec-10 29-Dec-10 01-Jan-11 02-Jan-11 06-Jan-11 10-Jan-11 11-Jan-11 12-Jan-11 15-Jan-11 30-Jan-11 16-Jan-11 20-Jan-11 23-Jan-11 26-Jan-11 27-Jan-11 29-Jan-11 31-Jan-11 15-Feb-11 21-Feb-11 26-Feb-11 05-Mar-11 09-Mar-11 10-Mar-11 12-Mar-11 21-Mar-11 22-Mar-11 23-Mar-11 24-Mar-11 26-Mar-11 01-May-11 02-May-11 09-May-11 29-Dec-10 01-Jan-11 02-Jan-11 05-Jan-11 08-Jan-11 09-Jan-11 13-Jan-11 17-Jan-11 18-Jan-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Pier - 04 (Athaibah Side Side)

22-Dec-10

02-May-11

Pier - 05 (Athaibah Side Side)

29-Dec-10

09-May-11

Page 49 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-P5090 FO-A-P5100 FO-A-P5110 FO-A-P5120 FO-A-P5130 FO-A-P5140 FO-A-P5150 FO-A-P5160 FO-A-P5170 FO-A-P5180 FO-A-P5190 FO-A-P5200 FO-A-P5210 FO-A-P5220 FO-A-P5230 FO-A-P5240 FO-A-P5250 FO-A-P5260 FO-A-P5270 FO-A-P5280 FO-A-P5290 FO-A-P5300 FO-A-P5310 FO-A-P5320 Pier - 03 (Ghala Side Side) FO-G-P3000 FO-G-P3010 FO-G-P3020 FO-G-P3030 FO-G-P3040 FO-G-P3050 FO-G-P3060 FO-G-P3070 FO-G-P3080 FO-G-P3090 FO-G-P3100 FO-G-P3110 FO-G-P3120 FO-G-P3130 FO-G-P3140 FO-G-P3150 FO-G-P3160 FO-G-P3170 FO-G-P3180 FO-G-P3190 Remaining Level of Effort Actual Work Remaining Work Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Critical Remaining Work Milestone Summary Activity Name Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching)

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 19-Jan-11 1d 22-Jan-11 15d 20-Jan-11 1d 23-Jan-11 4d 24-Jan-11 2d 29-Jan-11 3d 31-Jan-11 1d 03-Feb-11 1d 05-Feb-11 1d 07-Feb-11 15d 06-Feb-11 5d 23-Feb-11 4d 01-Mar-11 6d 06-Mar-11 4d 13-Mar-11 1d 17-Mar-11 1d 19-Mar-11 2d 27-Mar-11 1d 29-Mar-11 1d 30-Mar-11 1d 31-Mar-11 1d 02-Apr-11 1d 08-May-11 1d 09-May-11 113d 05-Jan-11 1d 05-Jan-11 2d 06-Jan-11 1d 09-Jan-11 3d 10-Jan-11 2d 13-Jan-11 1d 16-Jan-11 4d 17-Jan-11 3d 22-Jan-11 1d 25-Jan-11 1d 26-Jan-11 1d 29-Jan-11 15d 27-Jan-11 1d 30-Jan-11 4d 31-Jan-11 2d 05-Feb-11 3d 07-Feb-11 1d 10-Feb-11 1d 12-Feb-11 1d 14-Feb-11 15d 13-Feb-11 Finish Jan F 19-Jan-11 22-Jan-11 06-Feb-11 23-Jan-11 27-Jan-11 30-Jan-11 02-Feb-11 03-Feb-11 05-Feb-11 07-Feb-11 22-Feb-11 28-Feb-11 05-Mar-11 12-Mar-11 16-Mar-11 17-Mar-11 19-Mar-11 28-Mar-11 29-Mar-11 30-Mar-11 31-Mar-11 02-Apr-11 08-May-11 09-May-11 16-May-11 05-Jan-11 08-Jan-11 09-Jan-11 12-Jan-11 15-Jan-11 16-Jan-11 20-Jan-11 24-Jan-11 25-Jan-11 26-Jan-11 29-Jan-11 13-Feb-11 30-Jan-11 03-Feb-11 06-Feb-11 09-Feb-11 10-Feb-11 12-Feb-11 14-Feb-11 01-Mar-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

05-Jan-11

16-May-11

Page 50 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-P3200 FO-G-P3210 FO-G-P3220 FO-G-P3230 FO-G-P3240 FO-G-P3250 FO-G-P3260 FO-G-P3270 FO-G-P3280 FO-G-P3290 FO-G-P3300 FO-G-P3310 FO-G-P3320 Pier - 04 (Ghala Side Side) FO-G-P4000 FO-G-P4010 FO-G-P4020 FO-G-P4030 FO-G-P4040 FO-G-P4050 FO-G-P4060 FO-G-P4070 FO-G-P4080 FO-G-P4090 FO-G-P4100 FO-G-P4110 FO-G-P4120 FO-G-P4130 FO-G-P4140 FO-G-P4150 FO-G-P4160 FO-G-P4170 FO-G-P4180 FO-G-P4190 FO-G-P4200 FO-G-P4210 FO-G-P4220 FO-G-P4230 FO-G-P4240 FO-G-P4250 FO-G-P4260 FO-G-P4270 FO-G-P4280 FO-G-P4290 FO-G-P4300 Remaining Level of Effort Actual Work Remaining Work Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Critical Remaining Work Milestone Summary Activity Name Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching)

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 5d 02-Mar-11 4d 08-Mar-11 6d 13-Mar-11 4d 20-Mar-11 1d 24-Mar-11 1d 26-Mar-11 2d 03-Apr-11 1d 05-Apr-11 1d 06-Apr-11 1d 07-Apr-11 1d 09-Apr-11 1d 15-May-11 1d 16-May-11 113d 12-Jan-11 1d 12-Jan-11 2d 13-Jan-11 1d 16-Jan-11 3d 17-Jan-11 2d 20-Jan-11 1d 23-Jan-11 4d 24-Jan-11 3d 29-Jan-11 1d 01-Feb-11 1d 02-Feb-11 1d 05-Feb-11 15d 03-Feb-11 1d 06-Feb-11 4d 07-Feb-11 2d 12-Feb-11 3d 14-Feb-11 1d 17-Feb-11 1d 19-Feb-11 1d 21-Feb-11 15d 20-Feb-11 5d 09-Mar-11 4d 15-Mar-11 6d 20-Mar-11 4d 27-Mar-11 1d 31-Mar-11 1d 02-Apr-11 2d 10-Apr-11 1d 12-Apr-11 1d 13-Apr-11 1d 14-Apr-11 1d 16-Apr-11 Finish Jan F 07-Mar-11 12-Mar-11 19-Mar-11 23-Mar-11 24-Mar-11 26-Mar-11 04-Apr-11 05-Apr-11 06-Apr-11 07-Apr-11 09-Apr-11 15-May-11 16-May-11 23-May-11 12-Jan-11 15-Jan-11 16-Jan-11 19-Jan-11 22-Jan-11 23-Jan-11 27-Jan-11 31-Jan-11 01-Feb-11 02-Feb-11 05-Feb-11 20-Feb-11 06-Feb-11 10-Feb-11 13-Feb-11 16-Feb-11 17-Feb-11 19-Feb-11 21-Feb-11 08-Mar-11 14-Mar-11 19-Mar-11 26-Mar-11 30-Mar-11 31-Mar-11 02-Apr-11 11-Apr-11 12-Apr-11 13-Apr-11 14-Apr-11 16-Apr-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

12-Jan-11

23-May-11

Page 51 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-P4310 FO-G-P4320 Pier - 05 (Ghala Side Side) FO-G-P5000 FO-G-P5010 FO-G-P5020 FO-G-P5030 FO-G-P5040 FO-G-P5050 FO-G-P5060 FO-G-P5070 FO-G-P5080 FO-G-P5090 FO-G-P5100 FO-G-P5110 FO-G-P5120 FO-G-P5130 FO-G-P5140 FO-G-P5150 FO-G-P5160 FO-G-P5170 FO-G-P5180 FO-G-P5190 FO-G-P5200 FO-G-P5210 FO-G-P5220 FO-G-P5230 FO-G-P5240 FO-G-P5250 FO-G-P5260 FO-G-P5270 FO-G-P5280 FO-G-P5290 FO-G-P5300 FO-G-P5310 FO-G-P5320 FO-A-P1000 FO-A-P1010 FO-A-P1020 FO-A-P1030 FO-A-P1040 FO-A-P1050 FO-A-P1060 FO-A-P1070 Remaining Level of Effort Actual Work Remaining Work Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching) Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Critical Remaining Work Milestone Summary Activity Name Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching)

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 22-May-11 1d 23-May-11 113d 19-Jan-11 1d 19-Jan-11 2d 20-Jan-11 1d 23-Jan-11 3d 24-Jan-11 2d 27-Jan-11 1d 30-Jan-11 4d 31-Jan-11 3d 05-Feb-11 1d 08-Feb-11 1d 09-Feb-11 1d 12-Feb-11 15d 10-Feb-11 1d 13-Feb-11 4d 14-Feb-11 2d 19-Feb-11 3d 21-Feb-11 1d 24-Feb-11 1d 26-Feb-11 1d 28-Feb-11 15d 27-Feb-11 5d 16-Mar-11 4d 22-Mar-11 6d 27-Mar-11 4d 03-Apr-11 1d 07-Apr-11 1d 09-Apr-11 2d 17-Apr-11 1d 19-Apr-11 1d 20-Apr-11 1d 21-Apr-11 1d 23-Apr-11 1d 29-May-11 1d 30-May-11 113d 26-Jan-11 1d 26-Jan-11 2d 27-Jan-11 1d 30-Jan-11 3d 31-Jan-11 2d 03-Feb-11 1d 06-Feb-11 4d 07-Feb-11 3d 12-Feb-11 Finish Jan F 22-May-11 23-May-11 30-May-11 19-Jan-11 22-Jan-11 23-Jan-11 26-Jan-11 29-Jan-11 30-Jan-11 03-Feb-11 07-Feb-11 08-Feb-11 09-Feb-11 12-Feb-11 27-Feb-11 13-Feb-11 17-Feb-11 20-Feb-11 23-Feb-11 24-Feb-11 26-Feb-11 28-Feb-11 15-Mar-11 21-Mar-11 26-Mar-11 02-Apr-11 06-Apr-11 07-Apr-11 09-Apr-11 18-Apr-11 19-Apr-11 20-Apr-11 21-Apr-11 23-Apr-11 29-May-11 30-May-11 06-Jun-11 26-Jan-11 29-Jan-11 30-Jan-11 02-Feb-11 05-Feb-11 06-Feb-11 10-Feb-11 14-Feb-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

19-Jan-11

30-May-11

Pier - 01 (Athaibah Side Side)

26-Jan-11

06-Jun-11

Page 52 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-P1080 FO-A-P1090 FO-A-P1100 FO-A-P1110 FO-A-P1120 FO-A-P1130 FO-A-P1140 FO-A-P1150 FO-A-P1160 FO-A-P1170 FO-A-P1180 FO-A-P1190 FO-A-P1200 FO-A-P1210 FO-A-P1220 FO-A-P1230 FO-A-P1240 FO-A-P1250 FO-A-P1260 FO-A-P1270 FO-A-P1280 FO-A-P1290 FO-A-P1300 FO-A-P1310 FO-A-P1320 FO-A-P2000 FO-A-P2010 FO-A-P2020 FO-A-P2030 FO-A-P2040 FO-A-P2050 FO-A-P2060 FO-A-P2070 FO-A-P2080 FO-A-P2090 FO-A-P2100 FO-A-P2110 FO-A-P2120 FO-A-P2130 FO-A-P2140 FO-A-P2150 FO-A-P2160 FO-A-P2170 FO-A-P2180 Remaining Level of Effort Actual Work Remaining Work Activity Name Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching) Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 15-Feb-11 1d 16-Feb-11 1d 19-Feb-11 15d 17-Feb-11 1d 20-Feb-11 4d 21-Feb-11 2d 26-Feb-11 3d 28-Feb-11 1d 03-Mar-11 1d 05-Mar-11 1d 07-Mar-11 15d 06-Mar-11 5d 23-Mar-11 4d 29-Mar-11 6d 03-Apr-11 4d 10-Apr-11 1d 14-Apr-11 1d 16-Apr-11 2d 24-Apr-11 1d 26-Apr-11 1d 27-Apr-11 1d 28-Apr-11 1d 30-Apr-11 1d 05-Jun-11 1d 06-Jun-11 113d 02-Feb-11 1d 02-Feb-11 2d 03-Feb-11 1d 06-Feb-11 3d 07-Feb-11 2d 10-Feb-11 1d 13-Feb-11 4d 14-Feb-11 3d 19-Feb-11 1d 22-Feb-11 1d 23-Feb-11 1d 26-Feb-11 15d 24-Feb-11 1d 27-Feb-11 4d 28-Feb-11 2d 05-Mar-11 3d 07-Mar-11 1d 10-Mar-11 1d 12-Mar-11 1d 14-Mar-11 Finish Jan F 15-Feb-11 16-Feb-11 19-Feb-11 06-Mar-11 20-Feb-11 24-Feb-11 27-Feb-11 02-Mar-11 03-Mar-11 05-Mar-11 07-Mar-11 22-Mar-11 28-Mar-11 02-Apr-11 09-Apr-11 13-Apr-11 14-Apr-11 16-Apr-11 25-Apr-11 26-Apr-11 27-Apr-11 28-Apr-11 30-Apr-11 05-Jun-11 06-Jun-11 13-Jun-11 02-Feb-11 05-Feb-11 06-Feb-11 09-Feb-11 12-Feb-11 13-Feb-11 17-Feb-11 21-Feb-11 22-Feb-11 23-Feb-11 26-Feb-11 13-Mar-11 27-Feb-11 03-Mar-11 06-Mar-11 09-Mar-11 10-Mar-11 12-Mar-11 14-Mar-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Pier - 02 (Athaibah Side Side)

02-Feb-11

13-Jun-11

Page 53 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-P2190 FO-A-P2200 FO-A-P2210 FO-A-P2220 FO-A-P2230 FO-A-P2240 FO-A-P2250 FO-A-P2260 FO-A-P2270 FO-A-P2280 FO-A-P2290 FO-A-P2300 FO-A-P2310 FO-A-P2320 Pier - 01 (Ghala Side Side) FO-G-P1000 FO-G-P1010 FO-G-P1020 FO-G-P1030 FO-G-P1040 FO-G-P1050 FO-G-P1060 FO-G-P1070 FO-G-P1080 FO-G-P1090 FO-G-P1100 FO-G-P1110 FO-G-P1120 FO-G-P1130 FO-G-P1140 FO-G-P1150 FO-G-P1160 FO-G-P1170 FO-G-P1180 FO-G-P1190 FO-G-P1200 FO-G-P1210 FO-G-P1220 FO-G-P1230 FO-G-P1240 FO-G-P1250 FO-G-P1260 FO-G-P1270 FO-G-P1280 FO-G-P1290 Remaining Level of Effort Actual Work Remaining Work Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Critical Remaining Work Milestone Summary Activity Name Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching)

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 15d 13-Mar-11 5d 30-Mar-11 4d 05-Apr-11 6d 10-Apr-11 4d 17-Apr-11 1d 21-Apr-11 1d 23-Apr-11 2d 01-May-11 1d 03-May-11 1d 04-May-11 1d 05-May-11 1d 07-May-11 1d 12-Jun-11 1d 13-Jun-11 113d 09-Feb-11 1d 09-Feb-11 2d 10-Feb-11 1d 13-Feb-11 3d 14-Feb-11 2d 17-Feb-11 1d 20-Feb-11 4d 21-Feb-11 3d 26-Feb-11 1d 01-Mar-11 1d 02-Mar-11 1d 05-Mar-11 15d 03-Mar-11 1d 06-Mar-11 4d 07-Mar-11 2d 12-Mar-11 3d 14-Mar-11 1d 17-Mar-11 1d 19-Mar-11 1d 21-Mar-11 15d 20-Mar-11 5d 06-Apr-11 4d 12-Apr-11 6d 17-Apr-11 4d 24-Apr-11 1d 28-Apr-11 1d 30-Apr-11 2d 08-May-11 1d 10-May-11 1d 11-May-11 1d 12-May-11 Finish Jan F 29-Mar-11 04-Apr-11 09-Apr-11 16-Apr-11 20-Apr-11 21-Apr-11 23-Apr-11 02-May-11 03-May-11 04-May-11 05-May-11 07-May-11 12-Jun-11 13-Jun-11 20-Jun-11 09-Feb-11 12-Feb-11 13-Feb-11 16-Feb-11 19-Feb-11 20-Feb-11 24-Feb-11 28-Feb-11 01-Mar-11 02-Mar-11 05-Mar-11 20-Mar-11 06-Mar-11 10-Mar-11 13-Mar-11 16-Mar-11 17-Mar-11 19-Mar-11 21-Mar-11 05-Apr-11 11-Apr-11 16-Apr-11 23-Apr-11 27-Apr-11 28-Apr-11 30-Apr-11 09-May-11 10-May-11 11-May-11 12-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

09-Feb-11

20-Jun-11

Page 54 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-P1300 FO-G-P1310 FO-G-P1320 Pier - 02 (Ghala Side Side) FO-G-P2000 FO-G-P2010 FO-G-P2020 FO-G-P2030 FO-G-P2040 FO-G-P2050 FO-G-P2060 FO-G-P2070 FO-G-P2080 FO-G-P2090 FO-G-P2100 FO-G-P2110 FO-G-P2120 FO-G-P2130 FO-G-P2140 FO-G-P2150 FO-G-P2160 FO-G-P2170 FO-G-P2180 FO-G-P2190 FO-G-P2200 FO-G-P2210 FO-G-P2220 FO-G-P2230 FO-G-P2240 FO-G-P2250 FO-G-P2260 FO-G-P2270 FO-G-P2280 FO-G-P2290 FO-G-P2300 FO-G-P2310 FO-G-P2320 FO-A-P6000 FO-A-P6010 FO-A-P6020 FO-A-P6030 FO-A-P6040 FO-A-P6050 FO-A-P6060 Remaining Level of Effort Actual Work Remaining Work Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching) Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Critical Remaining Work Milestone Summary Activity Name Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching)

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 14-May-11 1d 19-Jun-11 1d 20-Jun-11 113d 16-Feb-11 1d 16-Feb-11 2d 17-Feb-11 1d 20-Feb-11 3d 21-Feb-11 2d 24-Feb-11 1d 27-Feb-11 4d 28-Feb-11 3d 05-Mar-11 1d 08-Mar-11 1d 09-Mar-11 1d 12-Mar-11 15d 10-Mar-11 1d 13-Mar-11 4d 14-Mar-11 2d 19-Mar-11 3d 21-Mar-11 1d 24-Mar-11 1d 26-Mar-11 1d 28-Mar-11 15d 27-Mar-11 5d 13-Apr-11 4d 19-Apr-11 6d 24-Apr-11 4d 01-May-11 1d 05-May-11 1d 07-May-11 2d 15-May-11 1d 17-May-11 1d 18-May-11 1d 19-May-11 1d 21-May-11 1d 26-Jun-11 1d 27-Jun-11 113d 23-Feb-11 1d 23-Feb-11 2d 24-Feb-11 1d 27-Feb-11 3d 28-Feb-11 2d 03-Mar-11 1d 06-Mar-11 4d 07-Mar-11 Finish Jan F 14-May-11 19-Jun-11 20-Jun-11 27-Jun-11 16-Feb-11 19-Feb-11 20-Feb-11 23-Feb-11 26-Feb-11 27-Feb-11 03-Mar-11 07-Mar-11 08-Mar-11 09-Mar-11 12-Mar-11 27-Mar-11 13-Mar-11 17-Mar-11 20-Mar-11 23-Mar-11 24-Mar-11 26-Mar-11 28-Mar-11 12-Apr-11 18-Apr-11 23-Apr-11 30-Apr-11 04-May-11 05-May-11 07-May-11 16-May-11 17-May-11 18-May-11 19-May-11 21-May-11 26-Jun-11 27-Jun-11 04-Jul-11 23-Feb-11 26-Feb-11 27-Feb-11 02-Mar-11 05-Mar-11 06-Mar-11 10-Mar-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

16-Feb-11

27-Jun-11

Pier - 06 (Athaibah Side Side)

23-Feb-11

04-Jul-11

Page 55 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-P6070 FO-A-P6080 FO-A-P6090 FO-A-P6100 FO-A-P6110 FO-A-P6120 FO-A-P6130 FO-A-P6140 FO-A-P6150 FO-A-P6160 FO-A-P6170 FO-A-P6180 FO-A-P6190 FO-A-P6200 FO-A-P6210 FO-A-P6220 FO-A-P6230 FO-A-P6240 FO-A-P6250 FO-A-P6260 FO-A-P6270 FO-A-P6280 FO-A-P6290 FO-A-P6300 FO-A-P6310 FO-A-P6320 FO-A-P7000 FO-A-P7010 FO-A-P7020 FO-A-P7030 FO-A-P7040 FO-A-P7050 FO-A-P7060 FO-A-P7070 FO-A-P7080 FO-A-P7090 FO-A-P7100 FO-A-P7110 FO-A-P7120 FO-A-P7130 FO-A-P7140 FO-A-P7150 FO-A-P7160 FO-A-P7170 Remaining Level of Effort Actual Work Remaining Work Activity Name Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching) Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 3d 12-Mar-11 1d 15-Mar-11 1d 16-Mar-11 1d 19-Mar-11 15d 17-Mar-11 1d 20-Mar-11 4d 21-Mar-11 2d 26-Mar-11 3d 28-Mar-11 1d 31-Mar-11 1d 02-Apr-11 1d 04-Apr-11 15d 03-Apr-11 5d 20-Apr-11 4d 26-Apr-11 6d 01-May-11 4d 08-May-11 1d 12-May-11 1d 14-May-11 2d 22-May-11 1d 24-May-11 1d 25-May-11 1d 26-May-11 1d 28-May-11 1d 03-Jul-11 1d 04-Jul-11 113d 02-Mar-11 1d 02-Mar-11 2d 03-Mar-11 1d 06-Mar-11 3d 07-Mar-11 2d 10-Mar-11 1d 13-Mar-11 4d 14-Mar-11 3d 19-Mar-11 1d 22-Mar-11 1d 23-Mar-11 1d 26-Mar-11 15d 24-Mar-11 1d 27-Mar-11 4d 28-Mar-11 2d 02-Apr-11 3d 04-Apr-11 1d 07-Apr-11 1d 09-Apr-11 Finish Jan F 14-Mar-11 15-Mar-11 16-Mar-11 19-Mar-11 03-Apr-11 20-Mar-11 24-Mar-11 27-Mar-11 30-Mar-11 31-Mar-11 02-Apr-11 04-Apr-11 19-Apr-11 25-Apr-11 30-Apr-11 07-May-11 11-May-11 12-May-11 14-May-11 23-May-11 24-May-11 25-May-11 26-May-11 28-May-11 03-Jul-11 04-Jul-11 11-Jul-11 02-Mar-11 05-Mar-11 06-Mar-11 09-Mar-11 12-Mar-11 13-Mar-11 17-Mar-11 21-Mar-11 22-Mar-11 23-Mar-11 26-Mar-11 10-Apr-11 27-Mar-11 31-Mar-11 03-Apr-11 06-Apr-11 07-Apr-11 09-Apr-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Pier - 07 (Athaibah Side Side)

02-Mar-11

11-Jul-11

Page 56 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-P7180 FO-A-P7190 FO-A-P7200 FO-A-P7210 FO-A-P7220 FO-A-P7230 FO-A-P7240 FO-A-P7250 FO-A-P7260 FO-A-P7270 FO-A-P7280 FO-A-P7290 FO-A-P7300 FO-A-P7310 FO-A-P7320 Pier - 06 (Ghala Side Side) FO-G-P6000 FO-G-P6010 FO-G-P6020 FO-G-P6030 FO-G-P6040 FO-G-P6050 FO-G-P6060 FO-G-P6070 FO-G-P6080 FO-G-P6090 FO-G-P6100 FO-G-P6110 FO-G-P6120 FO-G-P6130 FO-G-P6140 FO-G-P6150 FO-G-P6160 FO-G-P6170 FO-G-P6180 FO-G-P6190 FO-G-P6200 FO-G-P6210 FO-G-P6220 FO-G-P6230 FO-G-P6240 FO-G-P6250 FO-G-P6260 FO-G-P6270 FO-G-P6280 Remaining Level of Effort Actual Work Remaining Work Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Critical Remaining Work Milestone Summary Activity Name Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching)

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 11-Apr-11 15d 10-Apr-11 5d 27-Apr-11 4d 03-May-11 6d 08-May-11 4d 15-May-11 1d 19-May-11 1d 21-May-11 2d 29-May-11 1d 31-May-11 1d 01-Jun-11 1d 02-Jun-11 1d 04-Jun-11 1d 10-Jul-11 1d 11-Jul-11 113d 09-Mar-11 1d 09-Mar-11 2d 10-Mar-11 1d 13-Mar-11 3d 14-Mar-11 2d 17-Mar-11 1d 20-Mar-11 4d 21-Mar-11 3d 26-Mar-11 1d 29-Mar-11 1d 30-Mar-11 1d 02-Apr-11 15d 31-Mar-11 1d 03-Apr-11 4d 04-Apr-11 2d 09-Apr-11 3d 11-Apr-11 1d 14-Apr-11 1d 16-Apr-11 1d 18-Apr-11 15d 17-Apr-11 5d 04-May-11 4d 10-May-11 6d 15-May-11 4d 22-May-11 1d 26-May-11 1d 28-May-11 2d 05-Jun-11 1d 07-Jun-11 1d 08-Jun-11 Finish Jan F 11-Apr-11 26-Apr-11 02-May-11 07-May-11 14-May-11 18-May-11 19-May-11 21-May-11 30-May-11 31-May-11 01-Jun-11 02-Jun-11 04-Jun-11 10-Jul-11 11-Jul-11 18-Jul-11 09-Mar-11 12-Mar-11 13-Mar-11 16-Mar-11 19-Mar-11 20-Mar-11 24-Mar-11 28-Mar-11 29-Mar-11 30-Mar-11 02-Apr-11 17-Apr-11 03-Apr-11 07-Apr-11 10-Apr-11 13-Apr-11 14-Apr-11 16-Apr-11 18-Apr-11 03-May-11 09-May-11 14-May-11 21-May-11 25-May-11 26-May-11 28-May-11 06-Jun-11 07-Jun-11 08-Jun-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

09-Mar-11

18-Jul-11

Page 57 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-P6290 FO-G-P6300 FO-G-P6310 FO-G-P6320 Pier - 07 (Ghala Side Side) FO-G-P7000 FO-G-P7010 FO-G-P7020 FO-G-P7030 FO-G-P7040 FO-G-P7050 FO-G-P7060 FO-G-P7070 FO-G-P7080 FO-G-P7090 FO-G-P7100 FO-G-P7110 FO-G-P7120 FO-G-P7130 FO-G-P7140 FO-G-P7150 FO-G-P7160 FO-G-P7170 FO-G-P7180 FO-G-P7190 FO-G-P7200 FO-G-P7210 FO-G-P7220 FO-G-P7230 FO-G-P7240 FO-G-P7250 FO-G-P7260 FO-G-P7270 FO-G-P7280 FO-G-P7290 FO-G-P7300 FO-G-P7310 FO-G-P7320 Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Pier Footing Concreting with Starter Pier Footing Formwork - Deshuttering Pier Footing Concrete - Curing Survey Setting-out and Approval Pier Column Steel Rebar Fixing Erect the Working Platform Erect the Pier Formwork Survey Checking and Approval Pier Column Concreting Dismantle the Pier Column Formworks Pier Column Curing Water Proofing for Pier Footing and Column below GL Backfilling and Compaction in Layers Erect the Pier-Cap Formwork Pier-Cap Steel Rebar Fixing Survey Checking and Approval Pier-Cap Concreting Dismantle the Pier-Cap Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching) Activity Name Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching)

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 09-Jun-11 1d 11-Jun-11 1d 17-Jul-11 1d 18-Jul-11 113d 16-Mar-11 1d 16-Mar-11 2d 17-Mar-11 1d 20-Mar-11 3d 21-Mar-11 2d 24-Mar-11 1d 27-Mar-11 4d 28-Mar-11 3d 02-Apr-11 1d 05-Apr-11 1d 06-Apr-11 1d 09-Apr-11 15d 07-Apr-11 1d 10-Apr-11 4d 11-Apr-11 2d 16-Apr-11 3d 18-Apr-11 1d 21-Apr-11 1d 23-Apr-11 1d 25-Apr-11 15d 24-Apr-11 5d 11-May-11 4d 17-May-11 6d 22-May-11 4d 29-May-11 1d 02-Jun-11 1d 04-Jun-11 2d 12-Jun-11 1d 14-Jun-11 1d 15-Jun-11 1d 16-Jun-11 1d 18-Jun-11 1d 24-Jul-11 1d 25-Jul-11 131d 23-Mar-11 113d 23-Mar-11 1d 23-Mar-11 2d 24-Mar-11 1d 27-Mar-11 3d 28-Mar-11 2d 31-Mar-11 Finish Jan F 09-Jun-11 11-Jun-11 17-Jul-11 18-Jul-11 25-Jul-11 16-Mar-11 19-Mar-11 20-Mar-11 23-Mar-11 26-Mar-11 27-Mar-11 31-Mar-11 04-Apr-11 05-Apr-11 06-Apr-11 09-Apr-11 24-Apr-11 10-Apr-11 14-Apr-11 17-Apr-11 20-Apr-11 21-Apr-11 23-Apr-11 25-Apr-11 10-May-11 16-May-11 21-May-11 28-May-11 01-Jun-11 02-Jun-11 04-Jun-11 13-Jun-11 14-Jun-11 15-Jun-11 16-Jun-11 18-Jun-11 24-Jul-11 25-Jul-11 22-Aug-11 01-Aug-11 23-Mar-11 26-Mar-11 27-Mar-11 30-Mar-11 02-Apr-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

16-Mar-11

25-Jul-11

ABUTMENTS
Abutment - 01 (Athaibah Side Side) FO-A-A1000 FO-A-A1010 FO-A-A1020 FO-A-A1030 FO-A-A1040 Remaining Level of Effort Actual Work Remaining Work Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Critical Remaining Work Milestone Summary

23-Mar-11 23-Mar-11

22-Aug-11 01-Aug-11

Page 58 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-A1050 FO-A-A1060 FO-A-A1070 FO-A-A1080 FO-A-A1090 FO-A-A1100 FO-A-A1110 FO-A-A1120 FO-A-A1130 FO-A-A1140 FO-A-A1150 FO-A-A1160 FO-A-A1170 FO-A-A1180 FO-A-A1190 FO-A-A1200 FO-A-A1210 FO-A-A1220 FO-A-A1230 FO-A-A1240 FO-A-A1250 FO-A-A1260 FO-A-A1270 FO-A-A1280 FO-A-A1290 FO-A-A1300 FO-A-A1310 FO-A-A1320 FO-G-A1000 FO-G-A1010 FO-G-A1020 FO-G-A1030 FO-G-A1040 FO-G-A1050 FO-G-A1060 FO-G-A1070 FO-G-A1080 FO-G-A1090 FO-G-A1100 FO-G-A1110 FO-G-A1120 FO-G-A1130 FO-G-A1140 FO-G-A1150 Remaining Level of Effort Actual Work Remaining Work Activity Name Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Abutment Footing Concreting with Starter Abutment Footing Formwork - Deshuttering Abutment Footing Concrete - Curing Survey Setting-out and Approval Abutment Wall - Stage 1 - Steel Rebar Fixing Erect the Working Platform Erect the Abutment Wall - Stage 1 - Formwork Survey Checking and Approval Abutment Wall Concreteing - Stage 1 Concrete Dismantle the Abutment Stage 1 Formworks Abutment Stage 1 Curing Water Proofing for Abutment Footing and Wall below GL Backfilling and Compaction in Layers Erect the Abutment Wall - Stage 2 - Formwork Abutment Wall - Stage 2 - Steel Rebar Fixing Survey Checking and Approval Abutment Stage 2 Concreting Dismantle the Abutment Stage 2 Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching) Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Abutment Footing Concreting with Starter Abutment Footing Formwork - Deshuttering Abutment Footing Concrete - Curing Survey Setting-out and Approval Abutment Wall - Stage 1 - Steel Rebar Fixing Erect the Working Platform Erect the Abutment Wall - Stage 1 - Formwork Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 03-Apr-11 4d 04-Apr-11 3d 09-Apr-11 1d 12-Apr-11 1d 13-Apr-11 1d 16-Apr-11 15d 14-Apr-11 1d 17-Apr-11 4d 18-Apr-11 2d 23-Apr-11 3d 25-Apr-11 1d 28-Apr-11 1d 30-Apr-11 1d 02-May-11 15d 01-May-11 5d 18-May-11 4d 24-May-11 6d 29-May-11 4d 05-Jun-11 1d 09-Jun-11 1d 11-Jun-11 2d 19-Jun-11 1d 21-Jun-11 1d 22-Jun-11 1d 23-Jun-11 1d 25-Jun-11 1d 31-Jul-11 1d 01-Aug-11 113d 30-Mar-11 1d 30-Mar-11 2d 31-Mar-11 1d 03-Apr-11 3d 04-Apr-11 2d 07-Apr-11 1d 10-Apr-11 4d 11-Apr-11 3d 16-Apr-11 1d 19-Apr-11 1d 20-Apr-11 1d 23-Apr-11 15d 21-Apr-11 1d 24-Apr-11 4d 25-Apr-11 2d 30-Apr-11 3d 02-May-11 Finish Jan F 03-Apr-11 07-Apr-11 11-Apr-11 12-Apr-11 13-Apr-11 16-Apr-11 01-May-11 17-Apr-11 21-Apr-11 24-Apr-11 27-Apr-11 28-Apr-11 30-Apr-11 02-May-11 17-May-11 23-May-11 28-May-11 04-Jun-11 08-Jun-11 09-Jun-11 11-Jun-11 20-Jun-11 21-Jun-11 22-Jun-11 23-Jun-11 25-Jun-11 31-Jul-11 01-Aug-11 08-Aug-11 30-Mar-11 02-Apr-11 03-Apr-11 06-Apr-11 09-Apr-11 10-Apr-11 14-Apr-11 18-Apr-11 19-Apr-11 20-Apr-11 23-Apr-11 08-May-11 24-Apr-11 28-Apr-11 01-May-11 04-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Abutment - 01 (Ghala Side Side)

30-Mar-11

08-Aug-11

Page 59 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-A1160 FO-G-A1170 FO-G-A1180 FO-G-A1190 FO-G-A1200 FO-G-A1210 FO-G-A1220 FO-G-A1230 FO-G-A1240 FO-G-A1250 FO-G-A1260 FO-G-A1270 FO-G-A1280 FO-G-A1290 FO-G-A1300 FO-G-A1310 FO-G-A1320 FO-A-A2000 FO-A-A2010 FO-A-A2020 FO-A-A2030 FO-A-A2040 FO-A-A2050 FO-A-A2060 FO-A-A2070 FO-A-A2080 FO-A-A2090 FO-A-A2100 FO-A-A2110 FO-A-A2120 FO-A-A2130 FO-A-A2140 FO-A-A2150 FO-A-A2160 FO-A-A2170 FO-A-A2180 FO-A-A2190 FO-A-A2200 FO-A-A2210 FO-A-A2220 FO-A-A2230 FO-A-A2240 FO-A-A2250 FO-A-A2260 Remaining Level of Effort Actual Work Remaining Work Activity Name Survey Checking and Approval Abutment Wall Concreteing - Stage 1 Concrete Dismantle the Abutment Stage 1 Formworks Abutment Stage 1 Curing Water Proofing for Abutment Footing and Wall below GL Backfilling and Compaction in Layers Erect the Abutment Wall - Stage 2 - Formwork Abutment Wall - Stage 2 - Steel Rebar Fixing Survey Checking and Approval Abutment Stage 2 Concreting Dismantle the Abutment Stage 2 Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching) Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Abutment Footing Concreting with Starter Abutment Footing Formwork - Deshuttering Abutment Footing Concrete - Curing Survey Setting-out and Approval Abutment Wall - Stage 1 - Steel Rebar Fixing Erect the Working Platform Erect the Abutment Wall - Stage 1 - Formwork Survey Checking and Approval Abutment Wall Concreteing - Stage 1 Concrete Dismantle the Abutment Stage 1 Formworks Abutment Stage 1 Curing Water Proofing for Abutment Footing and Wall below GL Backfilling and Compaction in Layers Erect the Abutment Wall - Stage 2 - Formwork Abutment Wall - Stage 2 - Steel Rebar Fixing Survey Checking and Approval Abutment Stage 2 Concreting Dismantle the Abutment Stage 2 Formworks Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 05-May-11 1d 07-May-11 1d 09-May-11 15d 08-May-11 5d 25-May-11 4d 31-May-11 6d 05-Jun-11 4d 12-Jun-11 1d 16-Jun-11 1d 18-Jun-11 2d 26-Jun-11 1d 28-Jun-11 1d 29-Jun-11 1d 30-Jun-11 1d 02-Jul-11 1d 07-Aug-11 1d 08-Aug-11 113d 06-Apr-11 1d 06-Apr-11 2d 07-Apr-11 1d 10-Apr-11 3d 11-Apr-11 2d 14-Apr-11 1d 17-Apr-11 4d 18-Apr-11 3d 23-Apr-11 1d 26-Apr-11 1d 27-Apr-11 1d 30-Apr-11 15d 28-Apr-11 1d 01-May-11 4d 02-May-11 2d 07-May-11 3d 09-May-11 1d 12-May-11 1d 14-May-11 1d 16-May-11 15d 15-May-11 5d 01-Jun-11 4d 07-Jun-11 6d 12-Jun-11 4d 19-Jun-11 1d 23-Jun-11 1d 25-Jun-11 2d 03-Jul-11 Finish Jan F 05-May-11 07-May-11 09-May-11 24-May-11 30-May-11 04-Jun-11 11-Jun-11 15-Jun-11 16-Jun-11 18-Jun-11 27-Jun-11 28-Jun-11 29-Jun-11 30-Jun-11 02-Jul-11 07-Aug-11 08-Aug-11 15-Aug-11 06-Apr-11 09-Apr-11 10-Apr-11 13-Apr-11 16-Apr-11 17-Apr-11 21-Apr-11 25-Apr-11 26-Apr-11 27-Apr-11 30-Apr-11 15-May-11 01-May-11 05-May-11 08-May-11 11-May-11 12-May-11 14-May-11 16-May-11 31-May-11 06-Jun-11 11-Jun-11 18-Jun-11 22-Jun-11 23-Jun-11 25-Jun-11 04-Jul-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Abutment - 02 (Athaibah Side Side)

06-Apr-11

15-Aug-11

Page 60 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-A2270 FO-A-A2280 FO-A-A2290 FO-A-A2300 FO-A-A2310 FO-A-A2320 FO-G-A2000 FO-G-A2010 FO-G-A2020 FO-G-A2030 FO-G-A2040 FO-G-A2050 FO-G-A2060 FO-G-A2070 FO-G-A2080 FO-G-A2090 FO-G-A2100 FO-G-A2110 FO-G-A2120 FO-G-A2130 FO-G-A2140 FO-G-A2150 FO-G-A2160 FO-G-A2170 FO-G-A2180 FO-G-A2190 FO-G-A2200 FO-G-A2210 FO-G-A2220 FO-G-A2230 FO-G-A2240 FO-G-A2250 FO-G-A2260 FO-G-A2270 FO-G-A2280 FO-G-A2290 FO-G-A2300 FO-G-A2310 FO-G-A2320 Activity Name Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching) Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Footing Steel Rebar Fixing Erect the Footing Formwork Checking and Approval Abutment Footing Concreting with Starter Abutment Footing Formwork - Deshuttering Abutment Footing Concrete - Curing Survey Setting-out and Approval Abutment Wall - Stage 1 - Steel Rebar Fixing Erect the Working Platform Erect the Abutment Wall - Stage 1 - Formwork Survey Checking and Approval Abutment Wall Concreteing - Stage 1 Concrete Dismantle the Abutment Stage 1 Formworks Abutment Stage 1 Curing Water Proofing for Abutment Footing and Wall below GL Backfilling and Compaction in Layers Erect the Abutment Wall - Stage 2 - Formwork Abutment Wall - Stage 2 - Steel Rebar Fixing Survey Checking and Approval Abutment Stage 2 Concreting Dismantle the Abutment Stage 2 Formworks Checking and Approval for Pedestal Bearing Pedestals Steel Rebar Fixing Erect the Bearing Pedetsal Formwork Bearing Pedestals Concreting Cleaning, Checking and Approval Fixing of Bearings (Before Girder Launching)

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 05-Jul-11 1d 06-Jul-11 1d 07-Jul-11 1d 09-Jul-11 1d 14-Aug-11 1d 15-Aug-11 113d 13-Apr-11 1d 13-Apr-11 2d 14-Apr-11 1d 17-Apr-11 3d 18-Apr-11 2d 21-Apr-11 1d 24-Apr-11 4d 25-Apr-11 3d 30-Apr-11 1d 03-May-11 1d 04-May-11 1d 07-May-11 15d 05-May-11 1d 08-May-11 4d 09-May-11 2d 14-May-11 3d 16-May-11 1d 19-May-11 1d 21-May-11 1d 23-May-11 15d 22-May-11 5d 08-Jun-11 4d 14-Jun-11 6d 19-Jun-11 4d 26-Jun-11 1d 30-Jun-11 1d 02-Jul-11 2d 10-Jul-11 1d 12-Jul-11 1d 13-Jul-11 1d 14-Jul-11 1d 16-Jul-11 1d 21-Aug-11 1d 22-Aug-11 293d 06-Apr-11 32d 02-Aug-11 2d 02-Aug-11 2d 02-Aug-11 1d 03-Aug-11 Finish Jan F 05-Jul-11 06-Jul-11 07-Jul-11 09-Jul-11 14-Aug-11 15-Aug-11 22-Aug-11 13-Apr-11 16-Apr-11 17-Apr-11 20-Apr-11 23-Apr-11 24-Apr-11 28-Apr-11 02-May-11 03-May-11 04-May-11 07-May-11 22-May-11 08-May-11 12-May-11 15-May-11 18-May-11 19-May-11 21-May-11 23-May-11 07-Jun-11 13-Jun-11 18-Jun-11 25-Jun-11 29-Jun-11 30-Jun-11 02-Jul-11 11-Jul-11 12-Jul-11 13-Jul-11 14-Jul-11 16-Jul-11 21-Aug-11 22-Aug-11 12-Mar-12 07-Sep-11 03-Aug-11 03-Aug-11 03-Aug-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Abutment - 02 (Ghala Side Side)

13-Apr-11

22-Aug-11

SUPERSTRUCTURE PSC GIRDER AND PRECAST INFILL SLABS PLACING


Span - 04 (Athaibah Side) Side FO-A-S4000 FO-A-S4020 Remaining Level of Effort Actual Work Remaining Work Placing of I - Girders Girder Temporary Stichting Critical Remaining Work Milestone Summary

06-Apr-11 02-Aug-11 02-Aug-11 07-Sep-11 03-Aug-11

12-Mar-12

Page 61 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-S4040 FO-A-S5000 FO-A-S5020 FO-A-S5040 FO-G-S4000 FO-G-S4020 FO-G-S4040 FO-G-S5000 FO-G-S5020 FO-G-S5040 FO-A-S3000 FO-A-S3020 FO-A-S3040 FO-A-S6000 FO-A-S6020 FO-A-S6040 FO-G-S3000 FO-G-S3020 FO-G-S3040 FO-G-S6000 FO-G-S6020 FO-G-S6040 FO-A-S2000 FO-A-S2020 FO-A-S2040 FO-A-S7000 FO-A-S7020 FO-A-S7040 FO-G-S2000 FO-G-S2020 FO-G-S2040 FO-G-S7000 FO-G-S7020 FO-G-S7040 Remaining Level of Effort Actual Work Remaining Work Activity Name Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 03-Aug-11 2d 04-Aug-11 2d 04-Aug-11 1d 06-Aug-11 1d 06-Aug-11 2d 07-Aug-11 2d 07-Aug-11 1d 08-Aug-11 1d 08-Aug-11 2d 09-Aug-11 2d 09-Aug-11 1d 10-Aug-11 1d 10-Aug-11 2d 11-Aug-11 2d 11-Aug-11 1d 13-Aug-11 1d 13-Aug-11 2d 14-Aug-11 2d 14-Aug-11 1d 15-Aug-11 1d 15-Aug-11 2d 16-Aug-11 2d 16-Aug-11 1d 17-Aug-11 1d 17-Aug-11 2d 18-Aug-11 2d 18-Aug-11 1d 20-Aug-11 1d 20-Aug-11 2d 21-Aug-11 2d 21-Aug-11 1d 22-Aug-11 1d 22-Aug-11 2d 23-Aug-11 2d 23-Aug-11 1d 24-Aug-11 1d 24-Aug-11 2d 25-Aug-11 2d 25-Aug-11 1d 27-Aug-11 1d 27-Aug-11 2d 28-Aug-11 2d 28-Aug-11 1d 29-Aug-11 1d 29-Aug-11 Finish Jan F 03-Aug-11 06-Aug-11 06-Aug-11 06-Aug-11 06-Aug-11 08-Aug-11 08-Aug-11 08-Aug-11 08-Aug-11 10-Aug-11 10-Aug-11 10-Aug-11 10-Aug-11 13-Aug-11 13-Aug-11 13-Aug-11 13-Aug-11 15-Aug-11 15-Aug-11 15-Aug-11 15-Aug-11 17-Aug-11 17-Aug-11 17-Aug-11 17-Aug-11 20-Aug-11 20-Aug-11 20-Aug-11 20-Aug-11 22-Aug-11 22-Aug-11 22-Aug-11 22-Aug-11 24-Aug-11 24-Aug-11 24-Aug-11 24-Aug-11 27-Aug-11 27-Aug-11 27-Aug-11 27-Aug-11 29-Aug-11 29-Aug-11 29-Aug-11 29-Aug-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 05 (Athaibah Side) Side

04-Aug-11

06-Aug-11

Span - 04 (Ghala Side) Side

07-Aug-11

08-Aug-11

Span - 05 (Ghala Side) Side

09-Aug-11

10-Aug-11

Span - 03 (Athaibah Side) Side

11-Aug-11

13-Aug-11

Span - 06 (Athaibah Side) Side

14-Aug-11

15-Aug-11

Span - 03 (Ghala Side) Side

16-Aug-11

17-Aug-11

Span - 06 (Ghala Side) Side

18-Aug-11

20-Aug-11

Span - 02 (Athaibah Side) Side

21-Aug-11

22-Aug-11

Span - 07 (Athaibah Side) Side

23-Aug-11

24-Aug-11

Span - 02 (Ghala Side) Side

25-Aug-11

27-Aug-11

Span - 07 (Ghala Side) Side

28-Aug-11 29-Aug-11

Page 62 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name Span - 01 (Athaibah Side) Side FO-A-S1000 FO-A-S1020 FO-A-S1040 FO-A-S8000 FO-A-S8020 FO-A-S8040 FO-G-S1000 FO-G-S1020 FO-G-S1040 FO-G-S8000 FO-G-S8020 FO-G-S8040 Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs Placing of I - Girders Girder Temporary Stichting Placing Precast Infill Slabs

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 30-Aug-11 2d 30-Aug-11 1d 31-Aug-11 1d 31-Aug-11 2d 01-Sep-11 2d 01-Sep-11 1d 03-Sep-11 1d 03-Sep-11 2d 04-Sep-11 2d 04-Sep-11 1d 05-Sep-11 1d 05-Sep-11 2d 06-Sep-11 2d 06-Sep-11 1d 07-Sep-11 1d 07-Sep-11 69d 04-Aug-11 24d 04-Aug-11 3d 04-Aug-11 2d 07-Aug-11 2d 08-Aug-11 2d 10-Aug-11 1d 13-Aug-11 1d 14-Aug-11 15d 15-Aug-11 2d 22-Aug-11 1d 24-Aug-11 24d 08-Aug-11 3d 08-Aug-11 2d 10-Aug-11 2d 11-Aug-11 2d 14-Aug-11 1d 16-Aug-11 1d 17-Aug-11 15d 18-Aug-11 2d 25-Aug-11 1d 28-Aug-11 24d 11-Aug-11 3d 11-Aug-11 2d 14-Aug-11 2d 15-Aug-11 2d 17-Aug-11 1d 20-Aug-11 1d 21-Aug-11 15d 22-Aug-11 Finish Jan F 31-Aug-11 31-Aug-11 31-Aug-11 31-Aug-11 03-Sep-11 03-Sep-11 03-Sep-11 03-Sep-11 05-Sep-11 05-Sep-11 05-Sep-11 05-Sep-11 07-Sep-11 07-Sep-11 07-Sep-11 07-Sep-11 23-Oct-11 31-Aug-11 07-Aug-11 08-Aug-11 09-Aug-11 11-Aug-11 13-Aug-11 14-Aug-11 31-Aug-11 23-Aug-11 24-Aug-11 04-Sep-11 10-Aug-11 11-Aug-11 13-Aug-11 15-Aug-11 16-Aug-11 17-Aug-11 04-Sep-11 27-Aug-11 28-Aug-11 07-Sep-11 14-Aug-11 15-Aug-11 16-Aug-11 18-Aug-11 20-Aug-11 21-Aug-11 07-Sep-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul A S Oct N D Jan F 30-Aug-11 31-Aug-11 2012 M Apr M

S Oct N

D Jan F

M Apr M

J Jul

Span - 08 (Athaibah Side) Side

01-Sep-11

03-Sep-11

Span - 01 (Ghala Side) Side

04-Sep-11 05-Sep-11

Span - 08 (Ghala Side) Side

06-Sep-11 07-Sep-11

DIAPHRAGM CASTING
Span - 04 (Athaibah Side) Side FO-A-DP-4000 FO-A-DP-4020 FO-A-DP-4040 FO-A-DP-4060 FO-A-DP-4080 FO-A-DP-4100 FO-A-DP-4120 FO-A-DP-4140 FO-A-DP-4160 FO-A-DP-5000 FO-A-DP-5020 FO-A-DP-5040 FO-A-DP-5060 FO-A-DP-5080 FO-A-DP-5100 FO-A-DP-5120 FO-A-DP-5140 FO-A-DP-5160 FO-G-DP-4000 FO-G-DP-4020 FO-G-DP-4040 FO-G-DP-4060 FO-G-DP-4080 FO-G-DP-4100 FO-G-DP-4120 Remaining Level of Effort Actual Work Remaining Work Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Critical Remaining Work Milestone Summary

04-Aug-11 04-Aug-11

23-Oct-11 31-Aug-11

Span - 05 (Athaibah Side) Side

08-Aug-11

04-Sep-11

Span - 04 (Ghala Side) Side

11-Aug-11

07-Sep-11

Page 63 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-DP-4140 FO-G-DP-4160 FO-G-DP-5000 FO-G-DP-5020 FO-G-DP-5040 FO-G-DP-5060 FO-G-DP-5080 FO-G-DP-5100 FO-G-DP-5120 FO-G-DP-5140 FO-G-DP-5160 FO-A-DP-3000 FO-A-DP-3020 FO-A-DP-3040 FO-A-DP-3060 FO-A-DP-3080 FO-A-DP-3100 FO-A-DP-3120 FO-A-DP-3140 FO-A-DP-3160 FO-A-DP-6000 FO-A-DP-6020 FO-A-DP-6040 FO-A-DP-6060 FO-A-DP-6080 FO-A-DP-6100 FO-A-DP-6120 FO-A-DP-6140 FO-A-DP-6160 FO-G-DP-3000 FO-G-DP-3020 FO-G-DP-3040 FO-G-DP-3060 FO-G-DP-3080 FO-G-DP-3100 FO-G-DP-3120 FO-G-DP-3140 FO-G-DP-3160 FO-G-DP-6000 FO-G-DP-6020 Remaining Level of Effort Actual Work Remaining Work Activity Name Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 29-Aug-11 1d 31-Aug-11 24d 15-Aug-11 3d 15-Aug-11 2d 17-Aug-11 2d 18-Aug-11 2d 21-Aug-11 1d 23-Aug-11 1d 24-Aug-11 15d 25-Aug-11 2d 01-Sep-11 1d 04-Sep-11 24d 18-Aug-11 3d 18-Aug-11 2d 21-Aug-11 2d 22-Aug-11 2d 24-Aug-11 1d 27-Aug-11 1d 28-Aug-11 15d 29-Aug-11 2d 05-Sep-11 1d 07-Sep-11 24d 22-Aug-11 3d 22-Aug-11 2d 24-Aug-11 2d 25-Aug-11 2d 28-Aug-11 1d 30-Aug-11 1d 31-Aug-11 15d 01-Sep-11 2d 08-Sep-11 1d 11-Sep-11 24d 25-Aug-11 3d 25-Aug-11 2d 28-Aug-11 2d 29-Aug-11 2d 31-Aug-11 1d 03-Sep-11 1d 04-Sep-11 15d 05-Sep-11 2d 12-Sep-11 1d 14-Sep-11 24d 29-Aug-11 3d 29-Aug-11 2d 31-Aug-11 Finish Jan F 30-Aug-11 31-Aug-11 11-Sep-11 17-Aug-11 18-Aug-11 20-Aug-11 22-Aug-11 23-Aug-11 24-Aug-11 11-Sep-11 03-Sep-11 04-Sep-11 14-Sep-11 21-Aug-11 22-Aug-11 23-Aug-11 25-Aug-11 27-Aug-11 28-Aug-11 14-Sep-11 06-Sep-11 07-Sep-11 18-Sep-11 24-Aug-11 25-Aug-11 27-Aug-11 29-Aug-11 30-Aug-11 31-Aug-11 18-Sep-11 10-Sep-11 11-Sep-11 21-Sep-11 28-Aug-11 29-Aug-11 30-Aug-11 01-Sep-11 03-Sep-11 04-Sep-11 21-Sep-11 13-Sep-11 14-Sep-11 25-Sep-11 31-Aug-11 01-Sep-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 05 (Ghala Side) Side

15-Aug-11

11-Sep-11

Span - 03 (Athaibah Side) Side

18-Aug-11

14-Sep-11

Span - 06 (Athaibah Side) Side

22-Aug-11

18-Sep-11

Span - 03 (Ghala Side) Side

25-Aug-11

21-Sep-11

Span - 06 (Ghala Side) Side

29-Aug-11

25-Sep-11

Page 64 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-DP-6040 FO-G-DP-6060 FO-G-DP-6080 FO-G-DP-6100 FO-G-DP-6120 FO-G-DP-6140 FO-G-DP-6160 FO-A-DP-2000 FO-A-DP-2020 FO-A-DP-2040 FO-A-DP-2060 FO-A-DP-2080 FO-A-DP-2100 FO-A-DP-2120 FO-A-DP-2140 FO-A-DP-2160 FO-A-DP-7000 FO-A-DP-7020 FO-A-DP-7040 FO-A-DP-7060 FO-A-DP-7080 FO-A-DP-7100 FO-A-DP-7120 FO-A-DP-7140 FO-A-DP-7160 FO-G-DP-2000 FO-G-DP-2020 FO-G-DP-2040 FO-G-DP-2060 FO-G-DP-2080 FO-G-DP-2100 FO-G-DP-2120 FO-G-DP-2140 FO-G-DP-2160 FO-G-DP-7000 FO-G-DP-7020 FO-G-DP-7040 FO-G-DP-7060 FO-G-DP-7080 FO-G-DP-7100 FO-G-DP-7120 Remaining Level of Effort Actual Work Remaining Work Activity Name Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 01-Sep-11 2d 04-Sep-11 1d 06-Sep-11 1d 07-Sep-11 15d 08-Sep-11 2d 15-Sep-11 1d 18-Sep-11 24d 01-Sep-11 3d 01-Sep-11 2d 04-Sep-11 2d 05-Sep-11 2d 07-Sep-11 1d 10-Sep-11 1d 11-Sep-11 15d 12-Sep-11 2d 19-Sep-11 1d 21-Sep-11 24d 05-Sep-11 3d 05-Sep-11 2d 07-Sep-11 2d 08-Sep-11 2d 11-Sep-11 1d 13-Sep-11 1d 14-Sep-11 15d 15-Sep-11 2d 22-Sep-11 1d 25-Sep-11 24d 08-Sep-11 3d 08-Sep-11 2d 11-Sep-11 2d 12-Sep-11 2d 14-Sep-11 1d 17-Sep-11 1d 18-Sep-11 15d 19-Sep-11 2d 26-Sep-11 1d 28-Sep-11 24d 12-Sep-11 3d 12-Sep-11 2d 14-Sep-11 2d 15-Sep-11 2d 18-Sep-11 1d 20-Sep-11 1d 21-Sep-11 15d 22-Sep-11 Finish Jan F 03-Sep-11 05-Sep-11 06-Sep-11 07-Sep-11 25-Sep-11 17-Sep-11 18-Sep-11 28-Sep-11 04-Sep-11 05-Sep-11 06-Sep-11 08-Sep-11 10-Sep-11 11-Sep-11 28-Sep-11 20-Sep-11 21-Sep-11 02-Oct-11 07-Sep-11 08-Sep-11 10-Sep-11 12-Sep-11 13-Sep-11 14-Sep-11 02-Oct-11 24-Sep-11 25-Sep-11 05-Oct-11 11-Sep-11 12-Sep-11 13-Sep-11 15-Sep-11 17-Sep-11 18-Sep-11 05-Oct-11 27-Sep-11 28-Sep-11 09-Oct-11 14-Sep-11 15-Sep-11 17-Sep-11 19-Sep-11 20-Sep-11 21-Sep-11 09-Oct-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 02 (Athaibah Side) Side

01-Sep-11

28-Sep-11

Span - 07 (Athaibah Side) Side

05-Sep-11

02-Oct-11

Span - 02 (Ghala Side) Side

08-Sep-11

05-Oct-11

Span - 07 (Ghala Side) Side

12-Sep-11

09-Oct-11

Page 65 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-DP-7140 FO-G-DP-7160 FO-A-DP-1000 FO-A-DP-1020 FO-A-DP-1040 FO-A-DP-1060 FO-A-DP-1080 FO-A-DP-1100 FO-A-DP-1120 FO-A-DP-1140 FO-A-DP-1160 FO-A-DP-8000 FO-A-DP-8020 FO-A-DP-8040 FO-A-DP-8060 FO-A-DP-8080 FO-A-DP-8100 FO-A-DP-8120 FO-A-DP-8140 FO-A-DP-8160 FO-G-DP-1000 FO-G-DP-1020 FO-G-DP-1040 FO-G-DP-1060 FO-G-DP-1080 FO-G-DP-1100 FO-G-DP-1120 FO-G-DP-1140 FO-G-DP-1160 FO-G-DP-8000 FO-G-DP-8020 FO-G-DP-8040 FO-G-DP-8060 FO-G-DP-8080 FO-G-DP-8100 FO-G-DP-8120 FO-G-DP-8140 FO-G-DP-8160 Activity Name Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Formwork Fixing Reinforcement & Exposing Reinforcement Fixing Formwork Checking and Approval Diaphragm Concreting Curing Diaphragm Concrete Deshuttering of Diaphragm Formwork Dismantling Doka Staging

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 29-Sep-11 1d 02-Oct-11 24d 15-Sep-11 3d 15-Sep-11 2d 18-Sep-11 2d 19-Sep-11 2d 21-Sep-11 1d 24-Sep-11 1d 25-Sep-11 15d 26-Sep-11 2d 03-Oct-11 1d 05-Oct-11 24d 19-Sep-11 3d 19-Sep-11 2d 21-Sep-11 2d 22-Sep-11 2d 25-Sep-11 1d 27-Sep-11 1d 28-Sep-11 15d 29-Sep-11 2d 06-Oct-11 1d 09-Oct-11 24d 22-Sep-11 3d 22-Sep-11 2d 25-Sep-11 2d 26-Sep-11 2d 28-Sep-11 1d 01-Oct-11 1d 02-Oct-11 15d 03-Oct-11 2d 10-Oct-11 1d 12-Oct-11 24d 26-Sep-11 3d 26-Sep-11 2d 28-Sep-11 2d 29-Sep-11 2d 02-Oct-11 1d 04-Oct-11 1d 05-Oct-11 15d 06-Oct-11 2d 13-Oct-11 1d 16-Oct-11 69d 22-Sep-11 24d 22-Sep-11 3d 22-Sep-11 Finish Jan F 01-Oct-11 02-Oct-11 12-Oct-11 18-Sep-11 19-Sep-11 20-Sep-11 22-Sep-11 24-Sep-11 25-Sep-11 12-Oct-11 04-Oct-11 05-Oct-11 16-Oct-11 21-Sep-11 22-Sep-11 24-Sep-11 26-Sep-11 27-Sep-11 28-Sep-11 16-Oct-11 08-Oct-11 09-Oct-11 19-Oct-11 25-Sep-11 26-Sep-11 27-Sep-11 29-Sep-11 01-Oct-11 02-Oct-11 19-Oct-11 11-Oct-11 12-Oct-11 23-Oct-11 28-Sep-11 29-Sep-11 01-Oct-11 03-Oct-11 04-Oct-11 05-Oct-11 23-Oct-11 15-Oct-11 16-Oct-11 11-Dec-11 19-Oct-11 25-Sep-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 01 (Athaibah Side) Side

15-Sep-11

12-Oct-11

Span - 08 (Athaibah Side) Side

19-Sep-11

16-Oct-11

Span - 01 (Ghala Side) Side

22-Sep-11

19-Oct-11

Span - 08 (Ghala Side) Side

26-Sep-11

23-Oct-11

DECK SLAB
Span - 04 (Athaibah Side) Side FO-A-DS-4000 Remaining Level of Effort Actual Work Remaining Work Erecting Doka Staging Critical Remaining Work Milestone Summary

22-Sep-11 22-Sep-11

11-Dec-11 19-Oct-11

Page 66 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-DS-4020 FO-A-DS-4040 FO-A-DS-4060 FO-A-DS-4080 FO-A-DS-4100 FO-A-DS-4120 FO-A-DS-4140 FO-A-DS-4160 FO-A-DS-5000 FO-A-DS-5020 FO-A-DS-5040 FO-A-DS-5060 FO-A-DS-5080 FO-A-DS-5100 FO-A-DS-5120 FO-A-DS-5140 FO-A-DS-5160 FO-G-DS-4000 FO-G-DS-4020 FO-G-DS-4040 FO-G-DS-4060 FO-G-DS-4080 FO-G-DS-4100 FO-G-DS-4120 FO-G-DS-4140 FO-G-DS-4160 FO-G-DS-5000 FO-G-DS-5020 FO-G-DS-5040 FO-G-DS-5060 FO-G-DS-5080 FO-G-DS-5100 FO-G-DS-5120 FO-G-DS-5140 FO-G-DS-5160 FO-A-DS-3000 FO-A-DS-3020 FO-A-DS-3040 FO-A-DS-3060 FO-A-DS-3080 FO-A-DS-3100 Remaining Level of Effort Actual Work Remaining Work Activity Name Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 25-Sep-11 2d 26-Sep-11 2d 28-Sep-11 1d 01-Oct-11 1d 02-Oct-11 15d 03-Oct-11 2d 10-Oct-11 1d 12-Oct-11 24d 26-Sep-11 3d 26-Sep-11 2d 28-Sep-11 2d 29-Sep-11 2d 02-Oct-11 1d 04-Oct-11 1d 05-Oct-11 15d 06-Oct-11 2d 13-Oct-11 1d 16-Oct-11 24d 29-Sep-11 3d 29-Sep-11 2d 02-Oct-11 2d 03-Oct-11 2d 05-Oct-11 1d 08-Oct-11 1d 09-Oct-11 15d 10-Oct-11 2d 17-Oct-11 1d 19-Oct-11 24d 03-Oct-11 3d 03-Oct-11 2d 05-Oct-11 2d 06-Oct-11 2d 09-Oct-11 1d 11-Oct-11 1d 12-Oct-11 15d 13-Oct-11 2d 20-Oct-11 1d 23-Oct-11 24d 06-Oct-11 3d 06-Oct-11 2d 09-Oct-11 2d 10-Oct-11 2d 12-Oct-11 1d 15-Oct-11 1d 16-Oct-11 Finish Jan F 26-Sep-11 27-Sep-11 29-Sep-11 01-Oct-11 02-Oct-11 19-Oct-11 11-Oct-11 12-Oct-11 23-Oct-11 28-Sep-11 29-Sep-11 01-Oct-11 03-Oct-11 04-Oct-11 05-Oct-11 23-Oct-11 15-Oct-11 16-Oct-11 26-Oct-11 02-Oct-11 03-Oct-11 04-Oct-11 06-Oct-11 08-Oct-11 09-Oct-11 26-Oct-11 18-Oct-11 19-Oct-11 30-Oct-11 05-Oct-11 06-Oct-11 08-Oct-11 10-Oct-11 11-Oct-11 12-Oct-11 30-Oct-11 22-Oct-11 23-Oct-11 02-Nov-11 09-Oct-11 10-Oct-11 11-Oct-11 13-Oct-11 15-Oct-11 16-Oct-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 05 (Athaibah Side) Side

26-Sep-11

23-Oct-11

Span - 04 (Ghala Side) Side

29-Sep-11

26-Oct-11

Span - 05 (Ghala Side) Side

03-Oct-11

30-Oct-11

Span - 03 (Athaibah Side) Side

06-Oct-11

02-Nov-11

Page 67 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-DS-3120 FO-A-DS-3140 FO-A-DS-3160 FO-A-DS-6000 FO-A-DS-6020 FO-A-DS-6040 FO-A-DS-6060 FO-A-DS-6080 FO-A-DS-6100 FO-A-DS-6120 FO-A-DS-6140 FO-A-DS-6160 FO-G-DS-3000 FO-G-DS-3020 FO-G-DS-3040 FO-G-DS-3060 FO-G-DS-3080 FO-G-DS-3100 FO-G-DS-3120 FO-G-DS-3140 FO-G-DS-3160 FO-G-DS-6000 FO-G-DS-6020 FO-G-DS-6040 FO-G-DS-6060 FO-G-DS-6080 FO-G-DS-6100 FO-G-DS-6120 FO-G-DS-6140 FO-G-DS-6160 FO-A-DS-2000 FO-A-DS-2020 FO-A-DS-2040 FO-A-DS-2060 FO-A-DS-2080 FO-A-DS-2100 FO-A-DS-2120 FO-A-DS-2140 FO-A-DS-2160 FO-A-DS-7000 Remaining Level of Effort Actual Work Remaining Work Activity Name Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 15d 17-Oct-11 2d 24-Oct-11 1d 26-Oct-11 24d 10-Oct-11 3d 10-Oct-11 2d 12-Oct-11 2d 13-Oct-11 2d 16-Oct-11 1d 18-Oct-11 1d 19-Oct-11 15d 20-Oct-11 2d 27-Oct-11 1d 30-Oct-11 24d 13-Oct-11 3d 13-Oct-11 2d 16-Oct-11 2d 17-Oct-11 2d 19-Oct-11 1d 22-Oct-11 1d 23-Oct-11 15d 24-Oct-11 2d 31-Oct-11 1d 02-Nov-11 24d 17-Oct-11 3d 17-Oct-11 2d 19-Oct-11 2d 20-Oct-11 2d 23-Oct-11 1d 25-Oct-11 1d 26-Oct-11 15d 27-Oct-11 2d 03-Nov-11 1d 06-Nov-11 24d 20-Oct-11 3d 20-Oct-11 2d 23-Oct-11 2d 24-Oct-11 2d 26-Oct-11 1d 29-Oct-11 1d 30-Oct-11 15d 31-Oct-11 2d 07-Nov-11 1d 09-Nov-11 24d 24-Oct-11 3d 24-Oct-11 Finish Jan F 02-Nov-11 25-Oct-11 26-Oct-11 06-Nov-11 12-Oct-11 13-Oct-11 15-Oct-11 17-Oct-11 18-Oct-11 19-Oct-11 06-Nov-11 29-Oct-11 30-Oct-11 09-Nov-11 16-Oct-11 17-Oct-11 18-Oct-11 20-Oct-11 22-Oct-11 23-Oct-11 09-Nov-11 01-Nov-11 02-Nov-11 13-Nov-11 19-Oct-11 20-Oct-11 22-Oct-11 24-Oct-11 25-Oct-11 26-Oct-11 13-Nov-11 05-Nov-11 06-Nov-11 16-Nov-11 23-Oct-11 24-Oct-11 25-Oct-11 27-Oct-11 29-Oct-11 30-Oct-11 16-Nov-11 08-Nov-11 09-Nov-11 20-Nov-11 26-Oct-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 06 (Athaibah Side) Side

10-Oct-11

06-Nov-11

Span - 03 (Ghala Side) Side

13-Oct-11

09-Nov-11

Span - 06 (Ghala Side) Side

17-Oct-11

13-Nov-11

Span - 02 (Athaibah Side) Side

20-Oct-11

16-Nov-11

Span - 07 (Athaibah Side) Side

24-Oct-11

20-Nov-11

Page 68 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-DS-7020 FO-A-DS-7040 FO-A-DS-7060 FO-A-DS-7080 FO-A-DS-7100 FO-A-DS-7120 FO-A-DS-7140 FO-A-DS-7160 FO-G-DS-2000 FO-G-DS-2020 FO-G-DS-2040 FO-G-DS-2060 FO-G-DS-2080 FO-G-DS-2100 FO-G-DS-2120 FO-G-DS-2140 FO-G-DS-2160 FO-G-DS-7000 FO-G-DS-7020 FO-G-DS-7040 FO-G-DS-7060 FO-G-DS-7080 FO-G-DS-7100 FO-G-DS-7120 FO-G-DS-7140 FO-G-DS-7160 FO-A-DS-1000 FO-A-DS-1020 FO-A-DS-1040 FO-A-DS-1060 FO-A-DS-1080 FO-A-DS-1100 FO-A-DS-1120 FO-A-DS-1140 FO-A-DS-1160 FO-A-DS-8000 FO-A-DS-8020 FO-A-DS-8040 FO-A-DS-8060 FO-A-DS-8080 FO-A-DS-8100 Remaining Level of Effort Actual Work Remaining Work Activity Name Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 26-Oct-11 2d 27-Oct-11 2d 30-Oct-11 1d 01-Nov-11 1d 02-Nov-11 15d 03-Nov-11 2d 10-Nov-11 1d 13-Nov-11 24d 27-Oct-11 3d 27-Oct-11 2d 30-Oct-11 2d 31-Oct-11 2d 02-Nov-11 1d 05-Nov-11 1d 06-Nov-11 15d 07-Nov-11 2d 14-Nov-11 1d 16-Nov-11 24d 31-Oct-11 3d 31-Oct-11 2d 02-Nov-11 2d 03-Nov-11 2d 06-Nov-11 1d 08-Nov-11 1d 09-Nov-11 15d 10-Nov-11 2d 17-Nov-11 1d 20-Nov-11 24d 03-Nov-11 3d 03-Nov-11 2d 06-Nov-11 2d 07-Nov-11 2d 09-Nov-11 1d 12-Nov-11 1d 13-Nov-11 15d 14-Nov-11 2d 21-Nov-11 1d 23-Nov-11 24d 07-Nov-11 3d 07-Nov-11 2d 09-Nov-11 2d 10-Nov-11 2d 13-Nov-11 1d 15-Nov-11 1d 16-Nov-11 Finish Jan F 27-Oct-11 29-Oct-11 31-Oct-11 01-Nov-11 02-Nov-11 20-Nov-11 12-Nov-11 13-Nov-11 23-Nov-11 30-Oct-11 31-Oct-11 01-Nov-11 03-Nov-11 05-Nov-11 06-Nov-11 23-Nov-11 15-Nov-11 16-Nov-11 27-Nov-11 02-Nov-11 03-Nov-11 05-Nov-11 07-Nov-11 08-Nov-11 09-Nov-11 27-Nov-11 19-Nov-11 20-Nov-11 30-Nov-11 06-Nov-11 07-Nov-11 08-Nov-11 10-Nov-11 12-Nov-11 13-Nov-11 30-Nov-11 22-Nov-11 23-Nov-11 04-Dec-11 09-Nov-11 10-Nov-11 12-Nov-11 14-Nov-11 15-Nov-11 16-Nov-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 02 (Ghala Side) Side

27-Oct-11

23-Nov-11

Span - 07 (Ghala Side) Side

31-Oct-11

27-Nov-11

Span - 01 (Athaibah Side) Side

03-Nov-11

30-Nov-11

Span - 08 (Athaibah Side) Side

07-Nov-11

04-Dec-11

Page 69 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-A-DS-8120 FO-A-DS-8140 FO-A-DS-8160 FO-G-DS-1000 FO-G-DS-1020 FO-G-DS-1040 FO-G-DS-1060 FO-G-DS-1080 FO-G-DS-1100 FO-G-DS-1120 FO-G-DS-1140 FO-G-DS-1160 FO-G-DS-8000 FO-G-DS-8020 FO-G-DS-8040 FO-G-DS-8060 FO-G-DS-8080 FO-G-DS-8100 FO-G-DS-8120 FO-G-DS-8140 FO-G-DS-8160 Activity Name Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging Erecting Doka Staging Fixing Bottom Shutter (Cantilever) Fixing & Lapping of Reinforcement with Existing Deck Fixing Side Formwork Checking and Approval Deck Slab Concreting Curing Deck Slab Concrete Deshuttering of Deck Slab Formwork Dismantling Doka Staging

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 15d 17-Nov-11 2d 24-Nov-11 1d 27-Nov-11 24d 10-Nov-11 3d 10-Nov-11 2d 13-Nov-11 2d 14-Nov-11 2d 16-Nov-11 1d 19-Nov-11 1d 20-Nov-11 15d 21-Nov-11 2d 28-Nov-11 1d 30-Nov-11 24d 14-Nov-11 3d 14-Nov-11 2d 16-Nov-11 2d 17-Nov-11 2d 20-Nov-11 1d 22-Nov-11 1d 23-Nov-11 15d 24-Nov-11 2d 01-Dec-11 1d 04-Dec-11 69d 04-Oct-11 24d 04-Oct-11 3d 04-Oct-11 2d 06-Oct-11 2d 08-Oct-11 2d 10-Oct-11 1d 12-Oct-11 1d 13-Oct-11 15d 15-Oct-11 2d 22-Oct-11 1d 24-Oct-11 24d 08-Oct-11 3d 08-Oct-11 2d 10-Oct-11 2d 11-Oct-11 2d 13-Oct-11 1d 16-Oct-11 1d 17-Oct-11 15d 18-Oct-11 2d 25-Oct-11 1d 27-Oct-11 24d 11-Oct-11 Finish Jan F 04-Dec-11 26-Nov-11 27-Nov-11 07-Dec-11 13-Nov-11 14-Nov-11 15-Nov-11 17-Nov-11 19-Nov-11 20-Nov-11 07-Dec-11 29-Nov-11 30-Nov-11 11-Dec-11 16-Nov-11 17-Nov-11 19-Nov-11 21-Nov-11 22-Nov-11 23-Nov-11 11-Dec-11 03-Dec-11 04-Dec-11 22-Dec-11 31-Oct-11 06-Oct-11 08-Oct-11 09-Oct-11 11-Oct-11 12-Oct-11 13-Oct-11 31-Oct-11 23-Oct-11 24-Oct-11 03-Nov-11 10-Oct-11 11-Oct-11 12-Oct-11 15-Oct-11 16-Oct-11 17-Oct-11 03-Nov-11 26-Oct-11 27-Oct-11 07-Nov-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 01 (Ghala Side) Side

10-Nov-11

07-Dec-11

Span - 08 (Ghala Side) Side

14-Nov-11

11-Dec-11

CONCRETE CRASH BARRIER AND STEEL RAILING


Span - 04 (Athaibah Side) Side FO-A-CB-4000 FO-A-CB-4020 FO-A-CB-4040 FO-A-CB-4060 FO-A-CB-4080 FO-A-CB-4100 FO-A-CB-4120 FO-A-CB-4140 FO-A-CB-4160 FO-A-CB-5000 FO-A-CB-5020 FO-A-CB-5040 FO-A-CB-5060 FO-A-CB-5080 FO-A-CB-5100 FO-A-CB-5120 FO-A-CB-5140 FO-A-CB-5160 Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier

04-Oct-11 04-Oct-11

22-Dec-11 31-Oct-11

Span - 05 (Athaibah Side) Side

08-Oct-11

03-Nov-11

Span - 04 (Ghala Side) Side Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

11-Oct-11 TASK filter: All Activities

07-Nov-11

Page 70 of 115

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-CB-4000 FO-G-CB-4020 FO-G-CB-4040 FO-G-CB-4060 FO-G-CB-4080 FO-G-CB-4100 FO-G-CB-4120 FO-G-CB-4140 FO-G-CB-4160 FO-G-CB-5000 FO-G-CB-5020 FO-G-CB-5040 FO-G-CB-5060 FO-G-CB-5080 FO-G-CB-5100 FO-G-CB-5120 FO-G-CB-5140 FO-G-CB-5160 FO-A-CB-3000 FO-A-CB-3020 FO-A-CB-3040 FO-A-CB-3060 FO-A-CB-3080 FO-A-CB-3100 FO-A-CB-3120 FO-A-CB-3140 FO-A-CB-3160 FO-A-CB-6000 FO-A-CB-6020 FO-A-CB-6040 FO-A-CB-6060 FO-A-CB-6080 FO-A-CB-6100 FO-A-CB-6120 FO-A-CB-6140 FO-A-CB-6160 FO-G-CB-3000 FO-G-CB-3020 FO-G-CB-3040 FO-G-CB-3060 FO-G-CB-3080 Remaining Level of Effort Actual Work Remaining Work Activity Name Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 3d 11-Oct-11 2d 13-Oct-11 2d 15-Oct-11 2d 17-Oct-11 1d 19-Oct-11 1d 20-Oct-11 15d 22-Oct-11 2d 29-Oct-11 1d 31-Oct-11 24d 15-Oct-11 3d 15-Oct-11 2d 17-Oct-11 2d 18-Oct-11 2d 20-Oct-11 1d 23-Oct-11 1d 24-Oct-11 15d 25-Oct-11 2d 01-Nov-11 1d 03-Nov-11 24d 18-Oct-11 3d 18-Oct-11 2d 20-Oct-11 2d 22-Oct-11 2d 24-Oct-11 1d 26-Oct-11 1d 27-Oct-11 15d 29-Oct-11 2d 05-Nov-11 1d 07-Nov-11 24d 22-Oct-11 3d 22-Oct-11 2d 24-Oct-11 2d 25-Oct-11 2d 27-Oct-11 1d 30-Oct-11 1d 31-Oct-11 15d 01-Nov-11 2d 08-Nov-11 1d 10-Nov-11 24d 25-Oct-11 3d 25-Oct-11 2d 27-Oct-11 2d 29-Oct-11 2d 31-Oct-11 1d 02-Nov-11 Finish Jan F 13-Oct-11 15-Oct-11 16-Oct-11 18-Oct-11 19-Oct-11 20-Oct-11 07-Nov-11 30-Oct-11 31-Oct-11 10-Nov-11 17-Oct-11 18-Oct-11 19-Oct-11 22-Oct-11 23-Oct-11 24-Oct-11 10-Nov-11 02-Nov-11 03-Nov-11 14-Nov-11 20-Oct-11 22-Oct-11 23-Oct-11 25-Oct-11 26-Oct-11 27-Oct-11 14-Nov-11 06-Nov-11 07-Nov-11 17-Nov-11 24-Oct-11 25-Oct-11 26-Oct-11 29-Oct-11 30-Oct-11 31-Oct-11 17-Nov-11 09-Nov-11 10-Nov-11 21-Nov-11 27-Oct-11 29-Oct-11 30-Oct-11 01-Nov-11 02-Nov-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 05 (Ghala Side) Side

15-Oct-11

10-Nov-11

Span - 03 (Athaibah Side) Side

18-Oct-11

14-Nov-11

Span - 06 (Athaibah Side) Side

22-Oct-11

17-Nov-11

Span - 03 (Ghala Side) Side

25-Oct-11

21-Nov-11

Page 71 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-CB-3100 FO-G-CB-3120 FO-G-CB-3140 FO-G-CB-3160 FO-G-CB-6000 FO-G-CB-6020 FO-G-CB-6040 FO-G-CB-6060 FO-G-CB-6080 FO-G-CB-6100 FO-G-CB-6120 FO-G-CB-6140 FO-G-CB-6160 FO-A-CB-2000 FO-A-CB-2020 FO-A-CB-2040 FO-A-CB-2060 FO-A-CB-2080 FO-A-CB-2100 FO-A-CB-2120 FO-A-CB-2140 FO-A-CB-2160 FO-A-CB-7000 FO-A-CB-7020 FO-A-CB-7040 FO-A-CB-7060 FO-A-CB-7080 FO-A-CB-7100 FO-A-CB-7120 FO-A-CB-7140 FO-A-CB-7160 FO-G-CB-2000 FO-G-CB-2020 FO-G-CB-2040 FO-G-CB-2060 FO-G-CB-2080 FO-G-CB-2100 FO-G-CB-2120 FO-G-CB-2140 FO-G-CB-2160 Activity Name Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 03-Nov-11 15d 05-Nov-11 2d 12-Nov-11 1d 14-Nov-11 24d 29-Oct-11 3d 29-Oct-11 2d 31-Oct-11 2d 01-Nov-11 2d 03-Nov-11 1d 06-Nov-11 1d 07-Nov-11 15d 08-Nov-11 2d 15-Nov-11 1d 17-Nov-11 24d 01-Nov-11 3d 01-Nov-11 2d 03-Nov-11 2d 05-Nov-11 2d 07-Nov-11 1d 09-Nov-11 1d 10-Nov-11 15d 12-Nov-11 2d 19-Nov-11 1d 21-Nov-11 24d 05-Nov-11 3d 05-Nov-11 2d 07-Nov-11 2d 08-Nov-11 2d 10-Nov-11 1d 13-Nov-11 1d 14-Nov-11 15d 15-Nov-11 2d 22-Nov-11 1d 24-Nov-11 24d 08-Nov-11 3d 08-Nov-11 2d 10-Nov-11 2d 12-Nov-11 2d 14-Nov-11 1d 16-Nov-11 1d 17-Nov-11 15d 19-Nov-11 2d 26-Nov-11 1d 28-Nov-11 24d 12-Nov-11 Finish Jan F 03-Nov-11 21-Nov-11 13-Nov-11 14-Nov-11 24-Nov-11 31-Oct-11 01-Nov-11 02-Nov-11 05-Nov-11 06-Nov-11 07-Nov-11 24-Nov-11 16-Nov-11 17-Nov-11 28-Nov-11 03-Nov-11 05-Nov-11 06-Nov-11 08-Nov-11 09-Nov-11 10-Nov-11 28-Nov-11 20-Nov-11 21-Nov-11 01-Dec-11 07-Nov-11 08-Nov-11 09-Nov-11 12-Nov-11 13-Nov-11 14-Nov-11 01-Dec-11 23-Nov-11 24-Nov-11 05-Dec-11 10-Nov-11 12-Nov-11 13-Nov-11 15-Nov-11 16-Nov-11 17-Nov-11 05-Dec-11 27-Nov-11 28-Nov-11 08-Dec-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 06 (Ghala Side) Side

29-Oct-11

24-Nov-11

Span - 02 (Athaibah Side) Side

01-Nov-11

28-Nov-11

Span - 07 (Athaibah Side) Side

05-Nov-11

01-Dec-11

Span - 02 (Ghala Side) Side

08-Nov-11

05-Dec-11

Span - 07 (Ghala Side) Side Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

12-Nov-11 TASK filter: All Activities

08-Dec-11

Page 72 of 115

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-CB-7000 FO-G-CB-7020 FO-G-CB-7040 FO-G-CB-7060 FO-G-CB-7080 FO-G-CB-7100 FO-G-CB-7120 FO-G-CB-7140 FO-G-CB-7160 FO-A-CB-1000 FO-A-CB-1020 FO-A-CB-1040 FO-A-CB-1060 FO-A-CB-1080 FO-A-CB-1100 FO-A-CB-1120 FO-A-CB-1140 FO-A-CB-1160 FO-A-CB-8000 FO-A-CB-8020 FO-A-CB-8040 FO-A-CB-8060 FO-A-CB-8080 FO-A-CB-8100 FO-A-CB-8120 FO-A-CB-8140 FO-A-CB-8160 FO-G-CB-1000 FO-G-CB-1020 FO-G-CB-1040 FO-G-CB-1060 FO-G-CB-1080 FO-G-CB-1100 FO-G-CB-1120 FO-G-CB-1140 FO-G-CB-1160 FO-G-CB-8000 FO-G-CB-8020 FO-G-CB-8040 FO-G-CB-8060 FO-G-CB-8080 Remaining Level of Effort Actual Work Remaining Work Activity Name Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier Fixing of Reinforcement Fixing of Shutter Checking and Approval Crash Barrier Concreting Dismantling of Shutter Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 3d 12-Nov-11 2d 14-Nov-11 2d 15-Nov-11 2d 17-Nov-11 1d 20-Nov-11 1d 21-Nov-11 15d 22-Nov-11 2d 29-Nov-11 1d 01-Dec-11 24d 15-Nov-11 3d 15-Nov-11 2d 17-Nov-11 2d 19-Nov-11 2d 21-Nov-11 1d 23-Nov-11 1d 24-Nov-11 15d 26-Nov-11 2d 03-Dec-11 1d 05-Dec-11 24d 19-Nov-11 3d 19-Nov-11 2d 21-Nov-11 2d 22-Nov-11 2d 24-Nov-11 1d 27-Nov-11 1d 28-Nov-11 15d 29-Nov-11 2d 06-Dec-11 1d 08-Dec-11 24d 22-Nov-11 3d 22-Nov-11 2d 24-Nov-11 2d 26-Nov-11 2d 28-Nov-11 1d 30-Nov-11 1d 01-Dec-11 15d 03-Dec-11 2d 10-Dec-11 1d 12-Dec-11 24d 26-Nov-11 3d 26-Nov-11 2d 28-Nov-11 2d 29-Nov-11 2d 01-Dec-11 1d 04-Dec-11 Finish Jan F 14-Nov-11 15-Nov-11 16-Nov-11 19-Nov-11 20-Nov-11 21-Nov-11 08-Dec-11 30-Nov-11 01-Dec-11 12-Dec-11 17-Nov-11 19-Nov-11 20-Nov-11 22-Nov-11 23-Nov-11 24-Nov-11 12-Dec-11 04-Dec-11 05-Dec-11 15-Dec-11 21-Nov-11 22-Nov-11 23-Nov-11 26-Nov-11 27-Nov-11 28-Nov-11 15-Dec-11 07-Dec-11 08-Dec-11 19-Dec-11 24-Nov-11 26-Nov-11 27-Nov-11 29-Nov-11 30-Nov-11 01-Dec-11 19-Dec-11 11-Dec-11 12-Dec-11 22-Dec-11 28-Nov-11 29-Nov-11 30-Nov-11 03-Dec-11 04-Dec-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 01 (Athaibah Side) Side

15-Nov-11

12-Dec-11

Span - 08 (Athaibah Side) Side

19-Nov-11

15-Dec-11

Span - 01 (Ghala Side) Side

22-Nov-11

19-Dec-11

Span - 08 (Ghala Side) Side

26-Nov-11

22-Dec-11

Page 73 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-G-CB-8100 FO-G-CB-8120 FO-G-CB-8140 FO-G-CB-8160 Activity Name Curing Crash Barrier Concrete Finishing & Polishing Edges Fixing Galvanized Steel Railing Painting of Crash Barrier

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 05-Dec-11 15d 06-Dec-11 2d 13-Dec-11 1d 15-Dec-11 293d 06-Apr-11 105d 06-Apr-11 70d 06-Apr-11 1d 06-Apr-11 1d 07-Apr-11 2d 09-Apr-11 1d 11-Apr-11 3d 12-Apr-11 2d 16-Apr-11 1d 18-Apr-11 8d 19-Apr-11 4d 28-Apr-11 1d 03-May-11 1d 04-May-11 1d 07-May-11 15d 05-May-11 1d 08-May-11 6d 09-May-11 2d 16-May-11 6d 18-May-11 1d 25-May-11 1d 26-May-11 1d 29-May-11 15d 30-May-11 5d 16-Jun-11 4d 22-Jun-11 70d 14-Apr-11 1d 14-Apr-11 1d 16-Apr-11 2d 17-Apr-11 1d 19-Apr-11 3d 20-Apr-11 2d 24-Apr-11 1d 26-Apr-11 8d 27-Apr-11 4d 07-May-11 1d 11-May-11 1d 12-May-11 1d 15-May-11 15d 14-May-11 1d 16-May-11 Finish Jan F 05-Dec-11 22-Dec-11 14-Dec-11 15-Dec-11 12-Mar-12 06-Aug-11 26-Jun-11 06-Apr-11 07-Apr-11 10-Apr-11 11-Apr-11 14-Apr-11 17-Apr-11 18-Apr-11 27-Apr-11 02-May-11 03-May-11 04-May-11 07-May-11 22-May-11 08-May-11 15-May-11 17-May-11 24-May-11 25-May-11 26-May-11 29-May-11 15-Jun-11 21-Jun-11 26-Jun-11 04-Jul-11 14-Apr-11 16-Apr-11 18-Apr-11 19-Apr-11 23-Apr-11 25-Apr-11 26-Apr-11 05-May-11 10-May-11 11-May-11 12-May-11 15-May-11 30-May-11 16-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

RC WALL, BACKFILL CRASH BARRIERS & APPROACH SLAB BACKFILL,


RETAINING CONCRETE WALL - SEEB - GHALA SIDE UNIT - 01 E FO-RC-SG1000 Survey Setting out FO-RC-SG1010 Excavation Works FO-RC-SG1020 Leveling and Testing FO-RC-SG1030 Blinding Concrete / PCC FO-RC-SG1040 Blinding Concrete - Curing FO-RC-SG1050 Install of Water Proofing Membrane FO-RC-SG1060 Survey Setting-out FO-RC-SG1070 Footing Steel Rebar Fixing FO-RC-SG1080 Erect the Footing Formwork FO-RC-SG1090 Checking and Approval FO-RC-SG1100 RC Footing Concreting with Starter FO-RC-SG1110 RC Footing Formwork - Deshuttering FO-RC-SG1120 RC Footing Concrete - Curing FO-RC-SG1130 Survey Setting-out and Approval FO-RC-SG1140 RC Wall Steel Rebar Fixing FO-RC-SG1150 Erect the Working Platform FO-RC-SG1160 Erect the RC Wall Formwork FO-RC-SG1170 Survey Checking and Approval FO-RC-SG1180 RC Wall Concreting FO-RC-SG1190 Dismantle the RC Wall Formwork FO-RC-SG1200 RC Wall Curing FO-RC-SG1210 Water Proofing below GL FO-RC-SG1220 Backfilling and Compaction in Layers UNIT - 02 E FO-RC-SG1230 Survey Setting out FO-RC-SG1240 Excavation Works FO-RC-SG1250 Leveling and Testing FO-RC-SG1260 Blinding Concrete / PCC FO-RC-SG1270 Blinding Concrete - Curing FO-RC-SG1280 Install of Water Proofing Membrane FO-RC-SG1290 Survey Setting-out FO-RC-SG1300 Footing Steel Rebar Fixing FO-RC-SG1310 Erect the Footing Formwork FO-RC-SG1320 Checking and Approval FO-RC-SG1330 RC Footing Concreting with Starter FO-RC-SG1340 RC Footing Formwork - Deshuttering FO-RC-SG1350 RC Footing Concrete - Curing FO-RC-SG1360 Survey Setting-out and Approval Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

06-Apr-11 06-Apr-11 06-Apr-11 06-Aug-11 26-Jun-11

12-Mar-12

14-Apr-11

04-Jul-11

Page 74 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG1370 RC Wall Steel Rebar Fixing FO-RC-SG1380 Erect the Working Platform FO-RC-SG1390 Erect the RC Wall Formwork FO-RC-SG1400 Survey Checking and Approval FO-RC-SG1410 RC Wall Concreting FO-RC-SG1420 Dismantle the RC Wall Formwork FO-RC-SG1430 RC Wall Curing FO-RC-SG1440 Water Proofing below GL FO-RC-SG1450 Backfilling and Compaction in Layers UNIT - 03 E FO-RC-SG1460 Survey Setting out FO-RC-SG1470 Excavation Works FO-RC-SG1480 Leveling and Testing FO-RC-SG1490 Blinding Concrete / PCC FO-RC-SG1500 Blinding Concrete - Curing FO-RC-SG1510 Install of Water Proofing Membrane FO-RC-SG1520 Survey Setting-out FO-RC-SG1530 Footing Steel Rebar Fixing FO-RC-SG1540 Erect the Footing Formwork FO-RC-SG1550 Checking and Approval FO-RC-SG1560 RC Footing Concreting with Starter FO-RC-SG1570 RC Footing Formwork - Deshuttering FO-RC-SG1580 RC Footing Concrete - Curing FO-RC-SG1590 Survey Setting-out and Approval FO-RC-SG1600 RC Wall Steel Rebar Fixing FO-RC-SG1610 Erect the Working Platform FO-RC-SG1620 Erect the RC Wall Formwork FO-RC-SG1630 Survey Checking and Approval FO-RC-SG1640 RC Wall Concreting FO-RC-SG1650 Dismantle the RC Wall Formwork FO-RC-SG1660 RC Wall Curing FO-RC-SG1670 Water Proofing below GL FO-RC-SG1680 Backfilling and Compaction in Layers UNIT - 04 E FO-RC-SG1690 Survey Setting out FO-RC-SG1700 Excavation Works FO-RC-SG1710 Leveling and Testing FO-RC-SG1720 Blinding Concrete / PCC FO-RC-SG1730 Blinding Concrete - Curing FO-RC-SG1740 Install of Water Proofing Membrane FO-RC-SG1750 Survey Setting-out FO-RC-SG1760 Footing Steel Rebar Fixing FO-RC-SG1770 Erect the Footing Formwork FO-RC-SG1780 Checking and Approval FO-RC-SG1790 RC Footing Concreting with Starter Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 6d 17-May-11 2d 24-May-11 6d 26-May-11 1d 02-Jun-11 1d 04-Jun-11 1d 06-Jun-11 15d 07-Jun-11 5d 25-Jun-11 4d 30-Jun-11 70d 23-Apr-11 1d 23-Apr-11 1d 24-Apr-11 2d 25-Apr-11 1d 27-Apr-11 3d 28-Apr-11 2d 02-May-11 1d 04-May-11 8d 05-May-11 4d 15-May-11 1d 19-May-11 1d 21-May-11 1d 23-May-11 15d 22-May-11 1d 24-May-11 6d 25-May-11 2d 01-Jun-11 6d 04-Jun-11 1d 11-Jun-11 1d 12-Jun-11 1d 14-Jun-11 15d 15-Jun-11 5d 03-Jul-11 4d 09-Jul-11 70d 01-May-11 1d 01-May-11 1d 02-May-11 2d 03-May-11 1d 05-May-11 3d 07-May-11 2d 10-May-11 1d 12-May-11 8d 14-May-11 4d 23-May-11 1d 28-May-11 1d 29-May-11 Finish Jan F 23-May-11 25-May-11 01-Jun-11 02-Jun-11 04-Jun-11 06-Jun-11 23-Jun-11 29-Jun-11 04-Jul-11 12-Jul-11 23-Apr-11 24-Apr-11 26-Apr-11 27-Apr-11 01-May-11 03-May-11 04-May-11 14-May-11 18-May-11 19-May-11 21-May-11 23-May-11 07-Jun-11 24-May-11 31-May-11 02-Jun-11 09-Jun-11 11-Jun-11 12-Jun-11 14-Jun-11 02-Jul-11 07-Jul-11 12-Jul-11 20-Jul-11 01-May-11 02-May-11 04-May-11 05-May-11 09-May-11 11-May-11 12-May-11 22-May-11 26-May-11 28-May-11 29-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

23-Apr-11

12-Jul-11

01-May-11

20-Jul-11

Page 75 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG1800 RC Footing Formwork - Deshuttering FO-RC-SG1810 RC Footing Concrete - Curing FO-RC-SG1820 Survey Setting-out and Approval FO-RC-SG1830 RC Wall Steel Rebar Fixing FO-RC-SG1840 Erect the Working Platform FO-RC-SG1850 Erect the RC Wall Formwork FO-RC-SG1860 Survey Checking and Approval FO-RC-SG1870 RC Wall Concreting FO-RC-SG1880 Dismantle the RC Wall Formwork FO-RC-SG1890 RC Wall Curing FO-RC-SG1900 Water Proofing below GL FO-RC-SG1910 Backfilling and Compaction in Layers UNIT - 05 E FO-RC-SG1920 Survey Setting out FO-RC-SG1930 Excavation Works FO-RC-SG1940 Leveling and Testing FO-RC-SG1950 Blinding Concrete / PCC FO-RC-SG1960 Blinding Concrete - Curing FO-RC-SG1970 Install of Water Proofing Membrane FO-RC-SG1980 Survey Setting-out FO-RC-SG1990 Footing Steel Rebar Fixing FO-RC-SG2000 Erect the Footing Formwork FO-RC-SG2010 Checking and Approval FO-RC-SG2020 RC Footing Concreting with Starter FO-RC-SG2030 RC Footing Formwork - Deshuttering FO-RC-SG2040 RC Footing Concrete - Curing FO-RC-SG2050 Survey Setting-out and Approval FO-RC-SG2060 RC Wall Steel Rebar Fixing FO-RC-SG2070 Erect the Working Platform FO-RC-SG2080 Erect the RC Wall Formwork FO-RC-SG2090 Survey Checking and Approval FO-RC-SG2100 RC Wall Concreting FO-RC-SG2110 Dismantle the RC Wall Formwork FO-RC-SG2120 RC Wall Curing FO-RC-SG2130 Water Proofing below GL FO-RC-SG2140 Backfilling and Compaction in Layers UNIT - 06 E FO-RC-SG2150 Survey Setting out FO-RC-SG2160 Excavation Works FO-RC-SG2170 Leveling and Testing FO-RC-SG2180 Blinding Concrete / PCC FO-RC-SG2190 Blinding Concrete - Curing FO-RC-SG2200 Install of Water Proofing Membrane FO-RC-SG2210 Survey Setting-out FO-RC-SG2220 Footing Steel Rebar Fixing Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 31-May-11 15d 30-May-11 1d 01-Jun-11 6d 02-Jun-11 2d 09-Jun-11 6d 12-Jun-11 1d 19-Jun-11 1d 20-Jun-11 1d 22-Jun-11 15d 23-Jun-11 5d 11-Jul-11 4d 17-Jul-11 70d 09-May-11 1d 09-May-11 1d 10-May-11 2d 11-May-11 1d 14-May-11 3d 15-May-11 2d 18-May-11 1d 21-May-11 8d 22-May-11 4d 31-May-11 1d 05-Jun-11 1d 06-Jun-11 1d 08-Jun-11 15d 07-Jun-11 1d 09-Jun-11 6d 11-Jun-11 2d 18-Jun-11 6d 20-Jun-11 1d 27-Jun-11 1d 28-Jun-11 1d 30-Jun-11 15d 02-Jul-11 5d 19-Jul-11 4d 25-Jul-11 70d 17-May-11 1d 17-May-11 1d 18-May-11 2d 19-May-11 1d 22-May-11 3d 23-May-11 2d 26-May-11 1d 29-May-11 8d 30-May-11 Finish Jan F 31-May-11 15-Jun-11 01-Jun-11 08-Jun-11 11-Jun-11 18-Jun-11 19-Jun-11 20-Jun-11 22-Jun-11 10-Jul-11 16-Jul-11 20-Jul-11 28-Jul-11 09-May-11 10-May-11 12-May-11 14-May-11 17-May-11 19-May-11 21-May-11 30-May-11 04-Jun-11 05-Jun-11 06-Jun-11 08-Jun-11 23-Jun-11 09-Jun-11 16-Jun-11 19-Jun-11 26-Jun-11 27-Jun-11 28-Jun-11 30-Jun-11 18-Jul-11 24-Jul-11 28-Jul-11 06-Aug-11 17-May-11 18-May-11 21-May-11 22-May-11 25-May-11 28-May-11 29-May-11 07-Jun-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

09-May-11

28-Jul-11

17-May-11

06-Aug-11

Page 76 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG2230 Erect the Footing Formwork FO-RC-SG2240 Checking and Approval FO-RC-SG2250 RC Footing Concreting with Starter FO-RC-SG2260 RC Footing Formwork - Deshuttering FO-RC-SG2270 RC Footing Concrete - Curing FO-RC-SG2280 Survey Setting-out and Approval FO-RC-SG2290 RC Wall Steel Rebar Fixing FO-RC-SG2300 Erect the Working Platform FO-RC-SG2310 Erect the RC Wall Formwork FO-RC-SG2320 Survey Checking and Approval FO-RC-SG2330 RC Wall Concreting FO-RC-SG2340 Dismantle the RC Wall Formwork FO-RC-SG2350 RC Wall Curing FO-RC-SG2360 Water Proofing below GL FO-RC-SG2370 Backfilling and Compaction in Layers BACKFILL - SEEB - GHALA SIDE FO-BF-SG1000 FO-BF-SG1020 FO-BF-SG1040 FO-BF-SG1060 UNIT - 01 E FO-CB-SG1000 Preparatory Work on RC Wall FO-CB-SG1010 Erect the Working Platform FO-CB-SG1020 Reinforcement Fixing FO-CB-SG1030 Checking and Approval FO-CB-SG1040 Shutter Fixing FO-CB-SG1050 Survey Checking and Approval FO-CB-SG1060 Concreting FO-CB-SG1070 Deshuttering FO-CB-SG1080 Curing Crash Barrier Concrete FO-CB-SG1090 Finishing work & Painting UNIT - 02 E FO-CB-SG1100 Preparatory Work on RC Wall FO-CB-SG1110 Erect the Working Platform FO-CB-SG1120 Reinforcement Fixing FO-CB-SG1130 Checking and Approval FO-CB-SG1140 Shutter Fixing FO-CB-SG1150 Survey Checking and Approval FO-CB-SG1160 Concreting FO-CB-SG1170 Deshuttering FO-CB-SG1180 Curing Crash Barrier Concrete FO-CB-SG1190 Finishing work & Painting UNIT - 03 E FO-CB-SG1200 Preparatory Work on RC Wall Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Bitumen Waterproofing Painting 300mm thk Single Size Pervious Backfill 150 mm dia PVC Perforated Pipe Geotextile Laying

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 4d 08-Jun-11 1d 13-Jun-11 1d 14-Jun-11 1d 16-Jun-11 15d 15-Jun-11 1d 18-Jun-11 6d 19-Jun-11 2d 26-Jun-11 6d 28-Jun-11 1d 05-Jul-11 1d 06-Jul-11 1d 09-Jul-11 15d 10-Jul-11 5d 27-Jul-11 4d 02-Aug-11 32d 07-Aug-11 6d 07-Aug-11 26d 14-Aug-11 26d 14-Aug-11 26d 14-Aug-11 43d 13-Sep-11 28d 13-Sep-11 1d 13-Sep-11 1d 14-Sep-11 2d 15-Sep-11 1d 18-Sep-11 2d 19-Sep-11 1d 21-Sep-11 1d 22-Sep-11 1d 25-Sep-11 15d 26-Sep-11 2d 13-Oct-11 28d 17-Sep-11 1d 17-Sep-11 1d 18-Sep-11 2d 19-Sep-11 1d 21-Sep-11 2d 22-Sep-11 1d 25-Sep-11 1d 26-Sep-11 1d 28-Sep-11 15d 29-Sep-11 2d 17-Oct-11 28d 20-Sep-11 1d 20-Sep-11 Finish Jan F 12-Jun-11 13-Jun-11 14-Jun-11 16-Jun-11 02-Jul-11 18-Jun-11 25-Jun-11 27-Jun-11 04-Jul-11 05-Jul-11 06-Jul-11 09-Jul-11 26-Jul-11 01-Aug-11 06-Aug-11 12-Sep-11 13-Aug-11 12-Sep-11 12-Sep-11 12-Sep-11 01-Nov-11 15-Oct-11 13-Sep-11 14-Sep-11 17-Sep-11 18-Sep-11 20-Sep-11 21-Sep-11 22-Sep-11 25-Sep-11 12-Oct-11 15-Oct-11 18-Oct-11 17-Sep-11 18-Sep-11 20-Sep-11 21-Sep-11 24-Sep-11 25-Sep-11 26-Sep-11 28-Sep-11 16-Oct-11 18-Oct-11 22-Oct-11 20-Sep-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

07-Aug-11

12-Sep-11

CRASH BARRIERS - SEEB - GHALA SIDE

13-Sep-11 13-Sep-11

01-Nov-11 15-Oct-11

17-Sep-11

18-Oct-11

20-Sep-11

22-Oct-11

Page 77 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-CB-SG1210 Erect the Working Platform FO-CB-SG1220 Reinforcement Fixing FO-CB-SG1230 Checking and Approval FO-CB-SG1240 Shutter Fixing FO-CB-SG1250 Survey Checking and Approval FO-CB-SG1260 Concreting FO-CB-SG1270 Deshuttering FO-CB-SG1280 Curing Crash Barrier Concrete FO-CB-SG1290 Finishing work & Painting UNIT - 04 E FO-CB-SG1300 Preparatory Work on RC Wall FO-CB-SG1310 Erect the Working Platform FO-CB-SG1320 Reinforcement Fixing FO-CB-SG1330 Checking and Approval FO-CB-SG1340 Shutter Fixing FO-CB-SG1350 Survey Checking and Approval FO-CB-SG1360 Concreting FO-CB-SG1370 Deshuttering FO-CB-SG1380 Curing Crash Barrier Concrete FO-CB-SG1390 Finishing work & Painting UNIT - 05 E FO-CB-SG1400 Preparatory Work on RC Wall FO-CB-SG1410 Erect the Working Platform FO-CB-SG1420 Reinforcement Fixing FO-CB-SG1430 Checking and Approval FO-CB-SG1440 Shutter Fixing FO-CB-SG1450 Survey Checking and Approval FO-CB-SG1460 Concreting FO-CB-SG1470 Deshuttering FO-CB-SG1480 Curing Crash Barrier Concrete FO-CB-SG1490 Finishing work & Painting UNIT - 06 E FO-CB-SG1500 Preparatory Work on RC Wall FO-CB-SG1510 Erect the Working Platform FO-CB-SG1520 Reinforcement Fixing FO-CB-SG1530 Checking and Approval FO-CB-SG1540 Shutter Fixing FO-CB-SG1550 Survey Checking and Approval FO-CB-SG1560 Concreting FO-CB-SG1570 Deshuttering FO-CB-SG1580 Curing Crash Barrier Concrete FO-CB-SG1590 Finishing work & Painting APPROACH SLAB - SEEB - GHALA SIDE FO-AS-SG1000 FO-AS-SG1010 Remaining Level of Effort Actual Work Remaining Work Preparatory Work on Embankment Excavation Works Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 21-Sep-11 2d 22-Sep-11 1d 25-Sep-11 2d 26-Sep-11 1d 28-Sep-11 1d 29-Sep-11 1d 02-Oct-11 15d 03-Oct-11 2d 20-Oct-11 28d 24-Sep-11 1d 24-Sep-11 1d 25-Sep-11 2d 26-Sep-11 1d 28-Sep-11 2d 29-Sep-11 1d 02-Oct-11 1d 03-Oct-11 1d 05-Oct-11 15d 06-Oct-11 2d 24-Oct-11 28d 27-Sep-11 1d 27-Sep-11 1d 28-Sep-11 2d 29-Sep-11 1d 02-Oct-11 2d 03-Oct-11 1d 05-Oct-11 1d 06-Oct-11 1d 09-Oct-11 15d 10-Oct-11 2d 27-Oct-11 28d 01-Oct-11 1d 01-Oct-11 1d 02-Oct-11 2d 03-Oct-11 1d 05-Oct-11 2d 06-Oct-11 1d 09-Oct-11 1d 10-Oct-11 1d 12-Oct-11 15d 13-Oct-11 2d 31-Oct-11 107d 02-Nov-11 1d 02-Nov-11 1d 03-Nov-11 Finish Jan F 21-Sep-11 24-Sep-11 25-Sep-11 27-Sep-11 28-Sep-11 29-Sep-11 02-Oct-11 19-Oct-11 22-Oct-11 25-Oct-11 24-Sep-11 25-Sep-11 27-Sep-11 28-Sep-11 01-Oct-11 02-Oct-11 03-Oct-11 05-Oct-11 23-Oct-11 25-Oct-11 29-Oct-11 27-Sep-11 28-Sep-11 01-Oct-11 02-Oct-11 04-Oct-11 05-Oct-11 06-Oct-11 09-Oct-11 26-Oct-11 29-Oct-11 01-Nov-11 01-Oct-11 02-Oct-11 04-Oct-11 05-Oct-11 08-Oct-11 09-Oct-11 10-Oct-11 12-Oct-11 30-Oct-11 01-Nov-11 05-Mar-12 02-Nov-11 03-Nov-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

24-Sep-11

25-Oct-11

27-Sep-11

29-Oct-11

01-Oct-11

01-Nov-11

02-Nov-11

05-Mar-12

Page 78 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-AS-SG1020 FO-AS-SG1030 FO-AS-SG1040 FO-AS-SG1050 FO-AS-SG1060 FO-AS-SG1070 FO-AS-SG1080 FO-AS-SG1090 FO-AS-SG1100 FO-AS-SG1110 FO-AS-SG1120 UNIT - 01 W FO-RC-SG2380 Survey Setting out FO-RC-SG2390 Excavation Works FO-RC-SG2400 Leveling and Testing FO-RC-SG2410 Blinding Concrete / PCC FO-RC-SG2420 Blinding Concrete - Curing FO-RC-SG2430 Install of Water Proofing Membrane FO-RC-SG2440 Survey Setting-out FO-RC-SG2450 Footing Steel Rebar Fixing FO-RC-SG2460 Erect the Footing Formwork FO-RC-SG2470 Checking and Approval FO-RC-SG2480 RC Footing Concreting with Starter FO-RC-SG2490 RC Footing Formwork - Deshuttering FO-RC-SG2500 RC Footing Concrete - Curing FO-RC-SG2510 Survey Setting-out and Approval FO-RC-SG2520 RC Wall Steel Rebar Fixing FO-RC-SG2530 Erect the Working Platform FO-RC-SG2540 Erect the RC Wall Formwork FO-RC-SG2550 Survey Checking and Approval FO-RC-SG2560 RC Wall Concreting FO-RC-SG2570 Dismantle the RC Wall Formwork FO-RC-SG2580 RC Wall Curing FO-RC-SG2590 Water Proofing below GL FO-RC-SG2600 Backfilling and Compaction in Layers UNIT - 02 W FO-RC-SG2610 Survey Setting out FO-RC-SG2620 Excavation Works FO-RC-SG2630 Leveling and Testing FO-RC-SG2640 Blinding Concrete / PCC FO-RC-SG2650 Blinding Concrete - Curing FO-RC-SG2660 Install of Water Proofing Membrane FO-RC-SG2670 Survey Setting-out FO-RC-SG2680 Footing Steel Rebar Fixing Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Activity Name Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Survey Setting-out Approach Slab Steel Rebar Fixing Approach Slab Formwork Fixing Checking and Approval Approach Slab Concreting Approach Slab Formwork - Deshuttering Approach Slab Concrete - Curing Expansion Joint

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 05-Nov-11 1d 06-Nov-11 3d 07-Nov-11 1d 08-Nov-11 2d 10-Nov-11 2d 13-Nov-11 1d 15-Nov-11 1d 16-Nov-11 1d 17-Nov-11 15d 19-Nov-11 2d 04-Mar-12 105d 18-Apr-11 70d 18-Apr-11 1d 18-Apr-11 1d 19-Apr-11 2d 20-Apr-11 1d 23-Apr-11 3d 24-Apr-11 2d 27-Apr-11 1d 30-Apr-11 8d 01-May-11 4d 10-May-11 1d 15-May-11 1d 16-May-11 1d 18-May-11 15d 17-May-11 1d 19-May-11 6d 21-May-11 2d 28-May-11 6d 30-May-11 1d 06-Jun-11 1d 07-Jun-11 1d 09-Jun-11 15d 11-Jun-11 5d 28-Jun-11 4d 04-Jul-11 70d 26-Apr-11 1d 26-Apr-11 1d 27-Apr-11 2d 28-Apr-11 1d 01-May-11 3d 02-May-11 2d 05-May-11 1d 08-May-11 8d 09-May-11 Finish Jan F 05-Nov-11 06-Nov-11 09-Nov-11 08-Nov-11 12-Nov-11 14-Nov-11 15-Nov-11 16-Nov-11 17-Nov-11 05-Dec-11 05-Mar-12 17-Aug-11 07-Jul-11 18-Apr-11 19-Apr-11 21-Apr-11 23-Apr-11 26-Apr-11 28-Apr-11 30-Apr-11 09-May-11 14-May-11 15-May-11 16-May-11 18-May-11 02-Jun-11 19-May-11 26-May-11 29-May-11 05-Jun-11 06-Jun-11 07-Jun-11 09-Jun-11 27-Jun-11 03-Jul-11 07-Jul-11 16-Jul-11 26-Apr-11 27-Apr-11 30-Apr-11 01-May-11 04-May-11 07-May-11 08-May-11 17-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

RETAINING CONCRETE WALL - SEEB - ATHAIBAH SIDE

18-Apr-11 18-Apr-11

17-Aug-11 07-Jul-11

26-Apr-11

16-Jul-11

Page 79 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG2690 Erect the Footing Formwork FO-RC-SG2700 Checking and Approval FO-RC-SG2710 RC Footing Concreting with Starter FO-RC-SG2720 RC Footing Formwork - Deshuttering FO-RC-SG2730 RC Footing Concrete - Curing FO-RC-SG2740 Survey Setting-out and Approval FO-RC-SG2750 RC Wall Steel Rebar Fixing FO-RC-SG2760 Erect the Working Platform FO-RC-SG2770 Erect the RC Wall Formwork FO-RC-SG2780 Survey Checking and Approval FO-RC-SG2790 RC Wall Concreting FO-RC-SG2800 Dismantle the RC Wall Formwork FO-RC-SG2810 RC Wall Curing FO-RC-SG2820 Water Proofing below GL FO-RC-SG2830 Backfilling and Compaction in Layers UNIT - 03 W FO-RC-SG2840 Survey Setting out FO-RC-SG2850 Excavation Works FO-RC-SG2860 Leveling and Testing FO-RC-SG2870 Blinding Concrete / PCC FO-RC-SG2880 Blinding Concrete - Curing FO-RC-SG2890 Install of Water Proofing Membrane FO-RC-SG2900 Survey Setting-out FO-RC-SG2910 Footing Steel Rebar Fixing FO-RC-SG2920 Erect the Footing Formwork FO-RC-SG2930 Checking and Approval FO-RC-SG2940 RC Footing Concreting with Starter FO-RC-SG2950 RC Footing Formwork - Deshuttering FO-RC-SG2960 RC Footing Concrete - Curing FO-RC-SG2970 Survey Setting-out and Approval FO-RC-SG2980 RC Wall Steel Rebar Fixing FO-RC-SG2990 Erect the Working Platform FO-RC-SG3000 Erect the RC Wall Formwork FO-RC-SG3010 Survey Checking and Approval FO-RC-SG3020 RC Wall Concreting FO-RC-SG3030 Dismantle the RC Wall Formwork FO-RC-SG3040 RC Wall Curing FO-RC-SG3050 Water Proofing below GL FO-RC-SG3060 Backfilling and Compaction in Layers UNIT - 04 W FO-RC-SG3070 Survey Setting out FO-RC-SG3080 Excavation Works FO-RC-SG3090 Leveling and Testing FO-RC-SG3100 Blinding Concrete / PCC FO-RC-SG3110 Blinding Concrete - Curing Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 4d 18-May-11 1d 23-May-11 1d 24-May-11 1d 26-May-11 15d 25-May-11 1d 28-May-11 6d 29-May-11 2d 05-Jun-11 6d 07-Jun-11 1d 14-Jun-11 1d 15-Jun-11 1d 18-Jun-11 15d 19-Jun-11 5d 06-Jul-11 4d 12-Jul-11 70d 04-May-11 1d 04-May-11 1d 05-May-11 2d 07-May-11 1d 09-May-11 3d 10-May-11 2d 14-May-11 1d 16-May-11 8d 17-May-11 4d 26-May-11 1d 31-May-11 1d 01-Jun-11 1d 04-Jun-11 15d 02-Jun-11 1d 05-Jun-11 6d 06-Jun-11 2d 13-Jun-11 6d 15-Jun-11 1d 22-Jun-11 1d 23-Jun-11 1d 26-Jun-11 15d 27-Jun-11 5d 14-Jul-11 4d 20-Jul-11 70d 12-May-11 1d 12-May-11 1d 14-May-11 2d 15-May-11 1d 17-May-11 3d 18-May-11 Finish Jan F 22-May-11 23-May-11 24-May-11 26-May-11 11-Jun-11 28-May-11 04-Jun-11 06-Jun-11 13-Jun-11 14-Jun-11 15-Jun-11 18-Jun-11 05-Jul-11 11-Jul-11 16-Jul-11 24-Jul-11 04-May-11 05-May-11 08-May-11 09-May-11 12-May-11 15-May-11 16-May-11 25-May-11 30-May-11 31-May-11 01-Jun-11 04-Jun-11 19-Jun-11 05-Jun-11 12-Jun-11 14-Jun-11 21-Jun-11 22-Jun-11 23-Jun-11 26-Jun-11 13-Jul-11 19-Jul-11 24-Jul-11 01-Aug-11 12-May-11 14-May-11 16-May-11 17-May-11 21-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

04-May-11

24-Jul-11

12-May-11

01-Aug-11

Page 80 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG3120 Install of Water Proofing Membrane FO-RC-SG3130 Survey Setting-out FO-RC-SG3140 Footing Steel Rebar Fixing FO-RC-SG3150 Erect the Footing Formwork FO-RC-SG3160 Checking and Approval FO-RC-SG3170 RC Footing Concreting with Starter FO-RC-SG3180 RC Footing Formwork - Deshuttering FO-RC-SG3190 RC Footing Concrete - Curing FO-RC-SG3200 Survey Setting-out and Approval FO-RC-SG3210 RC Wall Steel Rebar Fixing FO-RC-SG3220 Erect the Working Platform FO-RC-SG3230 Erect the RC Wall Formwork FO-RC-SG3240 Survey Checking and Approval FO-RC-SG3250 RC Wall Concreting FO-RC-SG3260 Dismantle the RC Wall Formwork FO-RC-SG3270 RC Wall Curing FO-RC-SG3280 Water Proofing below GL FO-RC-SG3290 Backfilling and Compaction in Layers UNIT - 05 W FO-RC-SG3300 Survey Setting out FO-RC-SG3310 Excavation Works FO-RC-SG3320 Leveling and Testing FO-RC-SG3330 Blinding Concrete / PCC FO-RC-SG3340 Blinding Concrete - Curing FO-RC-SG3350 Install of Water Proofing Membrane FO-RC-SG3360 Survey Setting-out FO-RC-SG3370 Footing Steel Rebar Fixing FO-RC-SG3380 Erect the Footing Formwork FO-RC-SG3390 Checking and Approval FO-RC-SG3400 RC Footing Concreting with Starter FO-RC-SG3410 RC Footing Formwork - Deshuttering FO-RC-SG3420 RC Footing Concrete - Curing FO-RC-SG3430 Survey Setting-out and Approval FO-RC-SG3440 RC Wall Steel Rebar Fixing FO-RC-SG3450 Erect the Working Platform FO-RC-SG3460 Erect the RC Wall Formwork FO-RC-SG3470 Survey Checking and Approval FO-RC-SG3480 RC Wall Concreting FO-RC-SG3490 Dismantle the RC Wall Formwork FO-RC-SG3500 RC Wall Curing FO-RC-SG3510 Water Proofing below GL FO-RC-SG3520 Backfilling and Compaction in Layers UNIT - 06 W FO-RC-SG3530 Survey Setting out FO-RC-SG3540 Excavation Works Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 22-May-11 1d 24-May-11 8d 25-May-11 4d 04-Jun-11 1d 08-Jun-11 1d 09-Jun-11 1d 12-Jun-11 15d 11-Jun-11 1d 13-Jun-11 6d 14-Jun-11 2d 21-Jun-11 6d 23-Jun-11 1d 30-Jun-11 1d 02-Jul-11 1d 04-Jul-11 15d 05-Jul-11 5d 23-Jul-11 4d 28-Jul-11 70d 21-May-11 1d 21-May-11 1d 22-May-11 2d 23-May-11 1d 25-May-11 3d 26-May-11 2d 30-May-11 1d 01-Jun-11 8d 02-Jun-11 4d 12-Jun-11 1d 16-Jun-11 1d 18-Jun-11 1d 20-Jun-11 15d 19-Jun-11 1d 21-Jun-11 6d 22-Jun-11 2d 29-Jun-11 6d 02-Jul-11 1d 09-Jul-11 1d 10-Jul-11 1d 12-Jul-11 15d 13-Jul-11 5d 31-Jul-11 4d 06-Aug-11 70d 29-May-11 1d 29-May-11 1d 30-May-11 Finish Jan F 23-May-11 24-May-11 02-Jun-11 07-Jun-11 08-Jun-11 09-Jun-11 12-Jun-11 27-Jun-11 13-Jun-11 20-Jun-11 22-Jun-11 29-Jun-11 30-Jun-11 02-Jul-11 04-Jul-11 21-Jul-11 27-Jul-11 01-Aug-11 09-Aug-11 21-May-11 22-May-11 24-May-11 25-May-11 29-May-11 31-May-11 01-Jun-11 11-Jun-11 15-Jun-11 16-Jun-11 18-Jun-11 20-Jun-11 05-Jul-11 21-Jun-11 28-Jun-11 30-Jun-11 07-Jul-11 09-Jul-11 10-Jul-11 12-Jul-11 30-Jul-11 04-Aug-11 09-Aug-11 17-Aug-11 29-May-11 30-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

21-May-11

09-Aug-11

29-May-11

17-Aug-11

Page 81 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG3550 Leveling and Testing FO-RC-SG3560 Blinding Concrete / PCC FO-RC-SG3570 Blinding Concrete - Curing FO-RC-SG3580 Install of Water Proofing Membrane FO-RC-SG3590 Survey Setting-out FO-RC-SG3600 Footing Steel Rebar Fixing FO-RC-SG3610 Erect the Footing Formwork FO-RC-SG3620 Checking and Approval FO-RC-SG3630 RC Footing Concreting with Starter FO-RC-SG3640 RC Footing Formwork - Deshuttering FO-RC-SG3650 RC Footing Concrete - Curing FO-RC-SG3660 Survey Setting-out and Approval FO-RC-SG3670 RC Wall Steel Rebar Fixing FO-RC-SG3680 Erect the Working Platform FO-RC-SG3690 Erect the RC Wall Formwork FO-RC-SG3700 Survey Checking and Approval FO-RC-SG3710 RC Wall Concreting FO-RC-SG3720 Dismantle the RC Wall Formwork FO-RC-SG3730 RC Wall Curing FO-RC-SG3740 Water Proofing below GL FO-RC-SG3750 Backfilling and Compaction in Layers BACKFILL - SEEB - ATHAIBAH SIDE FO-BF-SG1010 FO-BF-SG1030 FO-BF-SG1050 FO-BF-SG1070 UNIT - 01 W FO-CB-SG1600 Preparatory Work on RC Wall FO-CB-SG1610 Erect the Working Platform FO-CB-SG1620 Reinforcement Fixing FO-CB-SG1630 Checking and Approval FO-CB-SG1640 Shutter Fixing FO-CB-SG1650 Survey Checking and Approval FO-CB-SG1660 Concreting FO-CB-SG1670 Deshuttering FO-CB-SG1680 Curing Crash Barrier Concrete FO-CB-SG1690 Finishing work & Painting UNIT - 02 W FO-CB-SG1700 Preparatory Work on RC Wall FO-CB-SG1710 Erect the Working Platform FO-CB-SG1720 Reinforcement Fixing FO-CB-SG1730 Checking and Approval FO-CB-SG1740 Shutter Fixing FO-CB-SG1750 Survey Checking and Approval Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Bitumen Waterproofing Painting 300mm thk Single Size Pervious Backfill 150 mm dia PVC Perforated Pipe Geotextile Laying

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 31-May-11 1d 02-Jun-11 3d 04-Jun-11 2d 07-Jun-11 1d 09-Jun-11 8d 11-Jun-11 4d 20-Jun-11 1d 25-Jun-11 1d 26-Jun-11 1d 28-Jun-11 15d 27-Jun-11 1d 29-Jun-11 6d 30-Jun-11 2d 07-Jul-11 6d 10-Jul-11 1d 17-Jul-11 1d 18-Jul-11 1d 20-Jul-11 15d 21-Jul-11 5d 08-Aug-11 4d 14-Aug-11 32d 18-Aug-11 6d 18-Aug-11 26d 25-Aug-11 26d 25-Aug-11 26d 25-Aug-11 43d 25-Sep-11 28d 25-Sep-11 1d 25-Sep-11 1d 26-Sep-11 2d 27-Sep-11 1d 29-Sep-11 2d 01-Oct-11 1d 03-Oct-11 1d 04-Oct-11 1d 06-Oct-11 15d 08-Oct-11 2d 25-Oct-11 28d 28-Sep-11 1d 28-Sep-11 1d 29-Sep-11 2d 01-Oct-11 1d 03-Oct-11 2d 04-Oct-11 1d 06-Oct-11 Finish Jan F 01-Jun-11 02-Jun-11 06-Jun-11 08-Jun-11 09-Jun-11 19-Jun-11 23-Jun-11 25-Jun-11 26-Jun-11 28-Jun-11 13-Jul-11 29-Jun-11 06-Jul-11 09-Jul-11 16-Jul-11 17-Jul-11 18-Jul-11 20-Jul-11 07-Aug-11 13-Aug-11 17-Aug-11 24-Sep-11 24-Aug-11 24-Sep-11 24-Sep-11 24-Sep-11 13-Nov-11 26-Oct-11 25-Sep-11 26-Sep-11 28-Sep-11 29-Sep-11 02-Oct-11 03-Oct-11 04-Oct-11 06-Oct-11 24-Oct-11 26-Oct-11 30-Oct-11 28-Sep-11 29-Sep-11 02-Oct-11 03-Oct-11 05-Oct-11 06-Oct-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

18-Aug-11

24-Sep-11

CRASH BARRIERS - SEEB - ATHAIBAH SIDE

25-Sep-11 25-Sep-11

13-Nov-11 26-Oct-11

28-Sep-11

30-Oct-11

Page 82 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-CB-SG1760 Concreting FO-CB-SG1770 Deshuttering FO-CB-SG1780 Curing Crash Barrier Concrete FO-CB-SG1790 Finishing work & Painting UNIT - 03 W FO-CB-SG1800 Preparatory Work on RC Wall FO-CB-SG1810 Erect the Working Platform FO-CB-SG1820 Reinforcement Fixing FO-CB-SG1830 Checking and Approval FO-CB-SG1840 Shutter Fixing FO-CB-SG1850 Survey Checking and Approval FO-CB-SG1860 Concreting FO-CB-SG1870 Deshuttering FO-CB-SG1880 Curing Crash Barrier Concrete FO-CB-SG1890 Finishing work & Painting UNIT - 04 W FO-CB-SG1900 Preparatory Work on RC Wall FO-CB-SG1910 Erect the Working Platform FO-CB-SG1920 Reinforcement Fixing FO-CB-SG1930 Checking and Approval FO-CB-SG1940 Shutter Fixing FO-CB-SG1950 Survey Checking and Approval FO-CB-SG1960 Concreting FO-CB-SG1970 Deshuttering FO-CB-SG1980 Curing Crash Barrier Concrete FO-CB-SG1990 Finishing work & Painting UNIT - 05 W FO-CB-SG2000 Preparatory Work on RC Wall FO-CB-SG2010 Erect the Working Platform FO-CB-SG2020 Reinforcement Fixing FO-CB-SG2030 Checking and Approval FO-CB-SG2040 Shutter Fixing FO-CB-SG2050 Survey Checking and Approval FO-CB-SG2060 Concreting FO-CB-SG2070 Deshuttering FO-CB-SG2080 Curing Crash Barrier Concrete FO-CB-SG2090 Finishing work & Painting UNIT - 06 W FO-CB-SG2100 Preparatory Work on RC Wall FO-CB-SG2110 Erect the Working Platform FO-CB-SG2120 Reinforcement Fixing FO-CB-SG2130 Checking and Approval FO-CB-SG2140 Shutter Fixing FO-CB-SG2150 Survey Checking and Approval FO-CB-SG2160 Concreting Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 08-Oct-11 1d 10-Oct-11 15d 11-Oct-11 2d 29-Oct-11 28d 02-Oct-11 1d 02-Oct-11 1d 03-Oct-11 2d 04-Oct-11 1d 06-Oct-11 2d 08-Oct-11 1d 10-Oct-11 1d 11-Oct-11 1d 13-Oct-11 15d 15-Oct-11 2d 01-Nov-11 28d 05-Oct-11 1d 05-Oct-11 1d 06-Oct-11 2d 08-Oct-11 1d 10-Oct-11 2d 11-Oct-11 1d 13-Oct-11 1d 15-Oct-11 1d 17-Oct-11 15d 18-Oct-11 2d 05-Nov-11 28d 09-Oct-11 1d 09-Oct-11 1d 10-Oct-11 2d 11-Oct-11 1d 13-Oct-11 2d 15-Oct-11 1d 17-Oct-11 1d 18-Oct-11 1d 20-Oct-11 15d 22-Oct-11 2d 08-Nov-11 28d 12-Oct-11 1d 12-Oct-11 1d 13-Oct-11 2d 15-Oct-11 1d 17-Oct-11 2d 18-Oct-11 1d 20-Oct-11 1d 22-Oct-11 Finish Jan F 08-Oct-11 10-Oct-11 27-Oct-11 30-Oct-11 02-Nov-11 02-Oct-11 03-Oct-11 05-Oct-11 06-Oct-11 09-Oct-11 10-Oct-11 11-Oct-11 13-Oct-11 31-Oct-11 02-Nov-11 06-Nov-11 05-Oct-11 06-Oct-11 09-Oct-11 10-Oct-11 12-Oct-11 13-Oct-11 15-Oct-11 17-Oct-11 03-Nov-11 06-Nov-11 09-Nov-11 09-Oct-11 10-Oct-11 12-Oct-11 13-Oct-11 16-Oct-11 17-Oct-11 18-Oct-11 20-Oct-11 07-Nov-11 09-Nov-11 13-Nov-11 12-Oct-11 13-Oct-11 16-Oct-11 17-Oct-11 19-Oct-11 20-Oct-11 22-Oct-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

02-Oct-11

02-Nov-11

05-Oct-11

06-Nov-11

09-Oct-11

09-Nov-11

12-Oct-11

13-Nov-11

Page 83 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-CB-SG2170 Deshuttering FO-CB-SG2180 Curing Crash Barrier Concrete FO-CB-SG2190 Finishing work & Painting APPROACH SLAB - SEEB - ATHAIBAH SIDE FO-AS-SG1130 FO-AS-SG1140 FO-AS-SG1150 FO-AS-SG1160 FO-AS-SG1170 FO-AS-SG1180 FO-AS-SG1190 FO-AS-SG1200 FO-AS-SG1210 FO-AS-SG1220 FO-AS-SG1230 FO-AS-SG1240 FO-AS-SG1250 UNIT - 07 E FO-RC-SG3760 Survey Setting out FO-RC-SG3770 Excavation Works FO-RC-SG3780 Leveling and Testing FO-RC-SG3790 Blinding Concrete / PCC FO-RC-SG3800 Blinding Concrete - Curing FO-RC-SG3810 Install of Water Proofing Membrane FO-RC-SG3820 Survey Setting-out FO-RC-SG3830 Footing Steel Rebar Fixing FO-RC-SG3840 Erect the Footing Formwork FO-RC-SG3850 Checking and Approval FO-RC-SG3860 RC Footing Concreting with Starter FO-RC-SG3870 RC Footing Formwork - Deshuttering FO-RC-SG3880 RC Footing Concrete - Curing FO-RC-SG3890 Survey Setting-out and Approval FO-RC-SG3900 RC Wall Steel Rebar Fixing FO-RC-SG3910 Erect the Working Platform FO-RC-SG3920 Erect the RC Wall Formwork FO-RC-SG3930 Survey Checking and Approval FO-RC-SG3940 RC Wall Concreting FO-RC-SG3950 Dismantle the RC Wall Formwork FO-RC-SG3960 RC Wall Curing FO-RC-SG3970 Water Proofing below GL FO-RC-SG3980 Backfilling and Compaction in Layers UNIT - 08 E FO-RC-SG3990 Survey Setting out FO-RC-SG4000 Excavation Works Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Preparatory Work on Embankment Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Survey Setting-out Approach Slab Steel Rebar Fixing Approach Slab Formwork Fixing Checking and Approval Approach Slab Concreting Approach Slab Formwork - Deshuttering Approach Slab Concrete - Curing Expansion Joint

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 24-Oct-11 15d 25-Oct-11 2d 12-Nov-11 99d 14-Nov-11 1d 14-Nov-11 1d 15-Nov-11 1d 16-Nov-11 1d 17-Nov-11 3d 19-Nov-11 1d 20-Nov-11 2d 22-Nov-11 2d 24-Nov-11 1d 27-Nov-11 1d 28-Nov-11 1d 29-Nov-11 15d 30-Nov-11 2d 06-Mar-12 119d 10-May-11 70d 10-May-11 1d 10-May-11 1d 11-May-11 2d 12-May-11 1d 15-May-11 3d 16-May-11 2d 19-May-11 1d 22-May-11 8d 23-May-11 4d 01-Jun-11 1d 06-Jun-11 1d 07-Jun-11 1d 09-Jun-11 15d 08-Jun-11 1d 11-Jun-11 6d 12-Jun-11 2d 19-Jun-11 6d 21-Jun-11 1d 28-Jun-11 1d 29-Jun-11 1d 02-Jul-11 15d 03-Jul-11 5d 20-Jul-11 4d 26-Jul-11 70d 18-May-11 1d 18-May-11 1d 19-May-11 Finish Jan F 24-Oct-11 10-Nov-11 13-Nov-11 07-Mar-12 14-Nov-11 15-Nov-11 16-Nov-11 17-Nov-11 21-Nov-11 20-Nov-11 23-Nov-11 26-Nov-11 27-Nov-11 28-Nov-11 29-Nov-11 17-Dec-11 07-Mar-12 25-Sep-11 30-Jul-11 10-May-11 11-May-11 14-May-11 15-May-11 18-May-11 21-May-11 22-May-11 31-May-11 05-Jun-11 06-Jun-11 07-Jun-11 09-Jun-11 25-Jun-11 11-Jun-11 18-Jun-11 20-Jun-11 27-Jun-11 28-Jun-11 29-Jun-11 02-Jul-11 19-Jul-11 25-Jul-11 30-Jul-11 07-Aug-11 18-May-11 19-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

14-Nov-11

07-Mar-12

RETAINING CONCRETE WALL - MUSCAT - GHALA SIDE

10-May-11 10-May-11

25-Sep-11 30-Jul-11

18-May-11

07-Aug-11

Page 84 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG4010 Leveling and Testing FO-RC-SG4020 Blinding Concrete / PCC FO-RC-SG4030 Blinding Concrete - Curing FO-RC-SG4040 Install of Water Proofing Membrane FO-RC-SG4050 Survey Setting-out FO-RC-SG4060 Footing Steel Rebar Fixing FO-RC-SG4070 Erect the Footing Formwork FO-RC-SG4080 Checking and Approval FO-RC-SG4090 RC Footing Concreting with Starter FO-RC-SG4100 RC Footing Formwork - Deshuttering FO-RC-SG4110 RC Footing Concrete - Curing FO-RC-SG4120 Survey Setting-out and Approval FO-RC-SG4130 RC Wall Steel Rebar Fixing FO-RC-SG4140 Erect the Working Platform FO-RC-SG4150 Erect the RC Wall Formwork FO-RC-SG4160 Survey Checking and Approval FO-RC-SG4170 RC Wall Concreting FO-RC-SG4180 Dismantle the RC Wall Formwork FO-RC-SG4190 RC Wall Curing FO-RC-SG4200 Water Proofing below GL FO-RC-SG4210 Backfilling and Compaction in Layers UNIT - 09 E FO-RC-SG4220 Survey Setting out FO-RC-SG4230 Excavation Works FO-RC-SG4240 Leveling and Testing FO-RC-SG4250 Blinding Concrete / PCC FO-RC-SG4260 Blinding Concrete - Curing FO-RC-SG4270 Install of Water Proofing Membrane FO-RC-SG4280 Survey Setting-out FO-RC-SG4290 Footing Steel Rebar Fixing FO-RC-SG4300 Erect the Footing Formwork FO-RC-SG4310 Checking and Approval FO-RC-SG4320 RC Footing Concreting with Starter FO-RC-SG4330 RC Footing Formwork - Deshuttering FO-RC-SG4340 RC Footing Concrete - Curing FO-RC-SG4350 Survey Setting-out and Approval FO-RC-SG4360 RC Wall Steel Rebar Fixing FO-RC-SG4370 Erect the Working Platform FO-RC-SG4380 Erect the RC Wall Formwork FO-RC-SG4390 Survey Checking and Approval FO-RC-SG4400 RC Wall Concreting FO-RC-SG4410 Dismantle the RC Wall Formwork FO-RC-SG4420 RC Wall Curing FO-RC-SG4430 Water Proofing below GL FO-RC-SG4440 Backfilling and Compaction in Layers Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 21-May-11 1d 23-May-11 3d 24-May-11 2d 28-May-11 1d 30-May-11 8d 31-May-11 4d 09-Jun-11 1d 14-Jun-11 1d 15-Jun-11 1d 18-Jun-11 15d 16-Jun-11 1d 19-Jun-11 6d 20-Jun-11 2d 27-Jun-11 6d 29-Jun-11 1d 06-Jul-11 1d 07-Jul-11 1d 10-Jul-11 15d 11-Jul-11 5d 28-Jul-11 4d 03-Aug-11 70d 26-May-11 1d 26-May-11 1d 28-May-11 2d 29-May-11 1d 31-May-11 3d 01-Jun-11 2d 05-Jun-11 1d 07-Jun-11 8d 08-Jun-11 4d 18-Jun-11 1d 22-Jun-11 1d 23-Jun-11 1d 26-Jun-11 15d 25-Jun-11 1d 27-Jun-11 6d 28-Jun-11 2d 05-Jul-11 6d 07-Jul-11 1d 14-Jul-11 1d 16-Jul-11 1d 18-Jul-11 15d 19-Jul-11 5d 06-Aug-11 4d 11-Aug-11 Finish Jan F 22-May-11 23-May-11 26-May-11 29-May-11 30-May-11 08-Jun-11 13-Jun-11 14-Jun-11 15-Jun-11 18-Jun-11 03-Jul-11 19-Jun-11 26-Jun-11 28-Jun-11 05-Jul-11 06-Jul-11 07-Jul-11 10-Jul-11 27-Jul-11 02-Aug-11 07-Aug-11 15-Aug-11 26-May-11 28-May-11 30-May-11 31-May-11 04-Jun-11 06-Jun-11 07-Jun-11 16-Jun-11 21-Jun-11 22-Jun-11 23-Jun-11 26-Jun-11 11-Jul-11 27-Jun-11 04-Jul-11 06-Jul-11 13-Jul-11 14-Jul-11 16-Jul-11 18-Jul-11 04-Aug-11 10-Aug-11 15-Aug-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

26-May-11

15-Aug-11

Page 85 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID UNIT - 10 E FO-RC-SG4450 Survey Setting out FO-RC-SG4460 Excavation Works FO-RC-SG4470 Leveling and Testing FO-RC-SG4480 Blinding Concrete / PCC FO-RC-SG4490 Blinding Concrete - Curing FO-RC-SG4500 Install of Water Proofing Membrane FO-RC-SG4510 Survey Setting-out FO-RC-SG4520 Footing Steel Rebar Fixing FO-RC-SG4530 Erect the Footing Formwork FO-RC-SG4540 Checking and Approval FO-RC-SG4550 RC Footing Concreting with Starter FO-RC-SG4560 RC Footing Formwork - Deshuttering FO-RC-SG4570 RC Footing Concrete - Curing FO-RC-SG4580 Survey Setting-out and Approval FO-RC-SG4590 RC Wall Steel Rebar Fixing FO-RC-SG4600 Erect the Working Platform FO-RC-SG4610 Erect the RC Wall Formwork FO-RC-SG4620 Survey Checking and Approval FO-RC-SG4630 RC Wall Concreting FO-RC-SG4640 Dismantle the RC Wall Formwork FO-RC-SG4650 RC Wall Curing FO-RC-SG4660 Water Proofing below GL FO-RC-SG4670 Backfilling and Compaction in Layers UNIT - 11 E FO-RC-SG4680 Survey Setting out FO-RC-SG4690 Excavation Works FO-RC-SG4700 Leveling and Testing FO-RC-SG4710 Blinding Concrete / PCC FO-RC-SG4720 Blinding Concrete - Curing FO-RC-SG4730 Install of Water Proofing Membrane FO-RC-SG4740 Survey Setting-out FO-RC-SG4750 Footing Steel Rebar Fixing FO-RC-SG4760 Erect the Footing Formwork FO-RC-SG4770 Checking and Approval FO-RC-SG4780 RC Footing Concreting with Starter FO-RC-SG4790 RC Footing Formwork - Deshuttering FO-RC-SG4800 RC Footing Concrete - Curing FO-RC-SG4810 Survey Setting-out and Approval FO-RC-SG4820 RC Wall Steel Rebar Fixing FO-RC-SG4830 Erect the Working Platform FO-RC-SG4840 Erect the RC Wall Formwork FO-RC-SG4850 Survey Checking and Approval FO-RC-SG4860 RC Wall Concreting FO-RC-SG4870 Dismantle the RC Wall Formwork Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 70d 04-Jun-11 1d 04-Jun-11 1d 05-Jun-11 2d 06-Jun-11 1d 08-Jun-11 3d 09-Jun-11 2d 13-Jun-11 1d 15-Jun-11 8d 16-Jun-11 4d 26-Jun-11 1d 30-Jun-11 1d 02-Jul-11 1d 04-Jul-11 15d 03-Jul-11 1d 05-Jul-11 6d 06-Jul-11 2d 13-Jul-11 6d 16-Jul-11 1d 23-Jul-11 1d 24-Jul-11 1d 26-Jul-11 15d 27-Jul-11 5d 14-Aug-11 4d 20-Aug-11 70d 12-Jun-11 1d 12-Jun-11 1d 13-Jun-11 2d 14-Jun-11 1d 16-Jun-11 3d 18-Jun-11 2d 21-Jun-11 1d 23-Jun-11 8d 25-Jun-11 4d 04-Jul-11 1d 09-Jul-11 1d 10-Jul-11 1d 12-Jul-11 15d 11-Jul-11 1d 13-Jul-11 6d 14-Jul-11 2d 21-Jul-11 6d 24-Jul-11 1d 31-Jul-11 1d 01-Aug-11 1d 03-Aug-11 Finish Jan F 23-Aug-11 04-Jun-11 05-Jun-11 07-Jun-11 08-Jun-11 12-Jun-11 14-Jun-11 15-Jun-11 25-Jun-11 29-Jun-11 30-Jun-11 02-Jul-11 04-Jul-11 19-Jul-11 05-Jul-11 12-Jul-11 14-Jul-11 21-Jul-11 23-Jul-11 24-Jul-11 26-Jul-11 13-Aug-11 18-Aug-11 23-Aug-11 31-Aug-11 12-Jun-11 13-Jun-11 15-Jun-11 16-Jun-11 20-Jun-11 22-Jun-11 23-Jun-11 03-Jul-11 07-Jul-11 09-Jul-11 10-Jul-11 12-Jul-11 27-Jul-11 13-Jul-11 20-Jul-11 23-Jul-11 30-Jul-11 31-Jul-11 01-Aug-11 03-Aug-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 M Apr M J Jul 04-Jun-11 2012 M Apr M

S Oct N

D Jan F

S Oct N 23-Aug-11

D Jan F

J Jul

12-Jun-11

31-Aug-11

Page 86 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG4880 RC Wall Curing FO-RC-SG4890 Water Proofing below GL FO-RC-SG4900 Backfilling and Compaction in Layers UNIT - 12 E FO-RC-SG4910 Survey Setting out FO-RC-SG4920 Excavation Works FO-RC-SG4930 Leveling and Testing FO-RC-SG4940 Blinding Concrete / PCC FO-RC-SG4950 Blinding Concrete - Curing FO-RC-SG4960 Install of Water Proofing Membrane FO-RC-SG4970 Survey Setting-out FO-RC-SG4980 Footing Steel Rebar Fixing FO-RC-SG4990 Erect the Footing Formwork FO-RC-SG5000 Checking and Approval FO-RC-SG5010 RC Footing Concreting with Starter FO-RC-SG5020 RC Footing Formwork - Deshuttering FO-RC-SG5030 RC Footing Concrete - Curing FO-RC-SG5040 Survey Setting-out and Approval FO-RC-SG5050 RC Wall Steel Rebar Fixing FO-RC-SG5060 Erect the Working Platform FO-RC-SG5070 Erect the RC Wall Formwork FO-RC-SG5080 Survey Checking and Approval FO-RC-SG5090 RC Wall Concreting FO-RC-SG5100 Dismantle the RC Wall Formwork FO-RC-SG5110 RC Wall Curing FO-RC-SG5120 Water Proofing below GL FO-RC-SG5130 Backfilling and Compaction in Layers UNIT - 13 E FO-RC-SG6520 Survey Setting out FO-RC-SG6530 Excavation Works FO-RC-SG6540 Leveling and Testing FO-RC-SG6550 Blinding Concrete / PCC FO-RC-SG6560 Blinding Concrete - Curing FO-RC-SG6570 Install of Water Proofing Membrane FO-RC-SG6580 Survey Setting-out FO-RC-SG6590 Footing Steel Rebar Fixing FO-RC-SG6600 Erect the Footing Formwork FO-RC-SG6610 Checking and Approval FO-RC-SG6620 RC Footing Concreting with Starter FO-RC-SG6630 RC Footing Formwork - Deshuttering FO-RC-SG6640 RC Footing Concrete - Curing FO-RC-SG6650 Survey Setting-out and Approval FO-RC-SG6660 RC Wall Steel Rebar Fixing FO-RC-SG6670 Erect the Working Platform FO-RC-SG6680 Erect the RC Wall Formwork Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 15d 04-Aug-11 5d 22-Aug-11 4d 28-Aug-11 70d 20-Jun-11 1d 20-Jun-11 1d 21-Jun-11 2d 22-Jun-11 1d 25-Jun-11 3d 26-Jun-11 2d 29-Jun-11 1d 02-Jul-11 8d 03-Jul-11 4d 12-Jul-11 1d 17-Jul-11 1d 18-Jul-11 1d 20-Jul-11 15d 19-Jul-11 1d 21-Jul-11 6d 23-Jul-11 2d 30-Jul-11 6d 01-Aug-11 1d 08-Aug-11 1d 09-Aug-11 1d 11-Aug-11 15d 13-Aug-11 5d 30-Aug-11 4d 05-Sep-11 70d 28-Jun-11 1d 28-Jun-11 1d 29-Jun-11 2d 30-Jun-11 1d 03-Jul-11 3d 04-Jul-11 2d 07-Jul-11 1d 10-Jul-11 8d 11-Jul-11 4d 20-Jul-11 1d 25-Jul-11 1d 26-Jul-11 1d 28-Jul-11 15d 27-Jul-11 1d 30-Jul-11 6d 31-Jul-11 2d 07-Aug-11 6d 09-Aug-11 Finish Jan F 21-Aug-11 27-Aug-11 31-Aug-11 08-Sep-11 20-Jun-11 21-Jun-11 23-Jun-11 25-Jun-11 28-Jun-11 30-Jun-11 02-Jul-11 11-Jul-11 16-Jul-11 17-Jul-11 18-Jul-11 20-Jul-11 04-Aug-11 21-Jul-11 28-Jul-11 31-Jul-11 07-Aug-11 08-Aug-11 09-Aug-11 11-Aug-11 29-Aug-11 04-Sep-11 08-Sep-11 17-Sep-11 28-Jun-11 29-Jun-11 02-Jul-11 03-Jul-11 06-Jul-11 09-Jul-11 10-Jul-11 19-Jul-11 24-Jul-11 25-Jul-11 26-Jul-11 28-Jul-11 13-Aug-11 30-Jul-11 06-Aug-11 08-Aug-11 15-Aug-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

20-Jun-11

08-Sep-11

28-Jun-11

17-Sep-11

Page 87 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG6690 Survey Checking and Approval FO-RC-SG6700 RC Wall Concreting FO-RC-SG6710 Dismantle the RC Wall Formwork FO-RC-SG6720 RC Wall Curing FO-RC-SG6730 Water Proofing below GL FO-RC-SG6740 Backfilling and Compaction in Layers UNIT - 14 E FO-RC-SG6750 Survey Setting out FO-RC-SG6760 Excavation Works FO-RC-SG6770 Leveling and Testing FO-RC-SG6780 Blinding Concrete / PCC FO-RC-SG6790 Blinding Concrete - Curing FO-RC-SG6800 Install of Water Proofing Membrane FO-RC-SG6810 Survey Setting-out FO-RC-SG6820 Footing Steel Rebar Fixing FO-RC-SG6830 Erect the Footing Formwork FO-RC-SG6840 Checking and Approval FO-RC-SG6850 RC Footing Concreting with Starter FO-RC-SG6860 RC Footing Formwork - Deshuttering FO-RC-SG6870 RC Footing Concrete - Curing FO-RC-SG6880 Survey Setting-out and Approval FO-RC-SG6890 RC Wall Steel Rebar Fixing FO-RC-SG6900 Erect the Working Platform FO-RC-SG6910 Erect the RC Wall Formwork FO-RC-SG6920 Survey Checking and Approval FO-RC-SG6930 RC Wall Concreting FO-RC-SG6940 Dismantle the RC Wall Formwork FO-RC-SG6950 RC Wall Curing FO-RC-SG6960 Water Proofing below GL FO-RC-SG6970 Backfilling and Compaction in Layers BACKFILL - MUSCAT - GHALA SIDE FO-BF-SG1080 FO-BF-SG1090 FO-BF-SG1100 FO-BF-SG1110 UNIT - 07 E FO-CB-SG2200 Preparatory Work on RC Wall FO-CB-SG2210 Erect the Working Platform FO-CB-SG2220 Reinforcement Fixing FO-CB-SG2230 Checking and Approval FO-CB-SG2240 Shutter Fixing FO-CB-SG2250 Survey Checking and Approval FO-CB-SG2260 Concreting FO-CB-SG2270 Deshuttering Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Bitumen Waterproofing Painting 150 mm dia PVC Perforated Pipe 300mm thk Single Size Pervious Backfill Geotextile Laying

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 16-Aug-11 1d 17-Aug-11 1d 20-Aug-11 15d 21-Aug-11 5d 07-Sep-11 4d 13-Sep-11 70d 06-Jul-11 1d 06-Jul-11 1d 07-Jul-11 2d 09-Jul-11 1d 11-Jul-11 3d 12-Jul-11 2d 16-Jul-11 1d 18-Jul-11 8d 19-Jul-11 4d 28-Jul-11 1d 02-Aug-11 1d 03-Aug-11 1d 06-Aug-11 15d 04-Aug-11 1d 07-Aug-11 6d 08-Aug-11 2d 15-Aug-11 6d 17-Aug-11 1d 24-Aug-11 1d 25-Aug-11 1d 28-Aug-11 15d 29-Aug-11 5d 15-Sep-11 4d 21-Sep-11 32d 26-Sep-11 6d 26-Sep-11 26d 03-Oct-11 26d 03-Oct-11 26d 03-Oct-11 49d 02-Nov-11 28d 02-Nov-11 1d 02-Nov-11 1d 03-Nov-11 2d 05-Nov-11 1d 07-Nov-11 2d 08-Nov-11 1d 10-Nov-11 1d 12-Nov-11 1d 14-Nov-11 Finish Jan F 16-Aug-11 17-Aug-11 20-Aug-11 06-Sep-11 12-Sep-11 17-Sep-11 25-Sep-11 06-Jul-11 07-Jul-11 10-Jul-11 11-Jul-11 14-Jul-11 17-Jul-11 18-Jul-11 27-Jul-11 01-Aug-11 02-Aug-11 03-Aug-11 06-Aug-11 21-Aug-11 07-Aug-11 14-Aug-11 16-Aug-11 23-Aug-11 24-Aug-11 25-Aug-11 28-Aug-11 14-Sep-11 20-Sep-11 25-Sep-11 01-Nov-11 02-Oct-11 01-Nov-11 01-Nov-11 01-Nov-11 28-Dec-11 04-Dec-11 02-Nov-11 03-Nov-11 06-Nov-11 07-Nov-11 09-Nov-11 10-Nov-11 12-Nov-11 14-Nov-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

06-Jul-11

25-Sep-11

26-Sep-11

01-Nov-11

CRASH BARRIERS - MUSCAT - GHALA SIDE

02-Nov-11 02-Nov-11

28-Dec-11 04-Dec-11

Page 88 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-CB-SG2280 Curing Crash Barrier Concrete FO-CB-SG2290 Finishing work & Painting UNIT - 08 E FO-CB-SG2300 Preparatory Work on RC Wall FO-CB-SG2310 Erect the Working Platform FO-CB-SG2320 Reinforcement Fixing FO-CB-SG2330 Checking and Approval FO-CB-SG2340 Shutter Fixing FO-CB-SG2350 Survey Checking and Approval FO-CB-SG2360 Concreting FO-CB-SG2370 Deshuttering FO-CB-SG2380 Curing Crash Barrier Concrete FO-CB-SG2390 Finishing work & Painting UNIT - 09 E FO-CB-SG2400 Preparatory Work on RC Wall FO-CB-SG2410 Erect the Working Platform FO-CB-SG2420 Reinforcement Fixing FO-CB-SG2430 Checking and Approval FO-CB-SG2440 Shutter Fixing FO-CB-SG2450 Survey Checking and Approval FO-CB-SG2460 Concreting FO-CB-SG2470 Deshuttering FO-CB-SG2480 Curing Crash Barrier Concrete FO-CB-SG2490 Finishing work & Painting UNIT - 10 E FO-CB-SG2500 Preparatory Work on RC Wall FO-CB-SG2510 Erect the Working Platform FO-CB-SG2520 Reinforcement Fixing FO-CB-SG2530 Checking and Approval FO-CB-SG2540 Shutter Fixing FO-CB-SG2550 Survey Checking and Approval FO-CB-SG2560 Concreting FO-CB-SG2570 Deshuttering FO-CB-SG2580 Curing Crash Barrier Concrete FO-CB-SG2590 Finishing work & Painting UNIT - 11 E FO-CB-SG2600 Preparatory Work on RC Wall FO-CB-SG2610 Erect the Working Platform FO-CB-SG2620 Reinforcement Fixing FO-CB-SG2630 Checking and Approval FO-CB-SG2640 Shutter Fixing FO-CB-SG2650 Survey Checking and Approval FO-CB-SG2660 Concreting FO-CB-SG2670 Deshuttering FO-CB-SG2680 Curing Crash Barrier Concrete Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 15d 15-Nov-11 2d 03-Dec-11 28d 06-Nov-11 1d 06-Nov-11 1d 07-Nov-11 2d 08-Nov-11 1d 10-Nov-11 2d 12-Nov-11 1d 14-Nov-11 1d 15-Nov-11 1d 17-Nov-11 15d 19-Nov-11 2d 06-Dec-11 28d 09-Nov-11 1d 09-Nov-11 1d 10-Nov-11 2d 12-Nov-11 1d 14-Nov-11 2d 15-Nov-11 1d 17-Nov-11 1d 19-Nov-11 1d 21-Nov-11 15d 22-Nov-11 2d 10-Dec-11 28d 13-Nov-11 1d 13-Nov-11 1d 14-Nov-11 2d 15-Nov-11 1d 17-Nov-11 2d 19-Nov-11 1d 21-Nov-11 1d 22-Nov-11 1d 24-Nov-11 15d 26-Nov-11 2d 13-Dec-11 28d 16-Nov-11 1d 16-Nov-11 1d 17-Nov-11 2d 19-Nov-11 1d 21-Nov-11 2d 22-Nov-11 1d 24-Nov-11 1d 26-Nov-11 1d 28-Nov-11 15d 29-Nov-11 Finish Jan F 01-Dec-11 04-Dec-11 07-Dec-11 06-Nov-11 07-Nov-11 09-Nov-11 10-Nov-11 13-Nov-11 14-Nov-11 15-Nov-11 17-Nov-11 05-Dec-11 07-Dec-11 11-Dec-11 09-Nov-11 10-Nov-11 13-Nov-11 14-Nov-11 16-Nov-11 17-Nov-11 19-Nov-11 21-Nov-11 08-Dec-11 11-Dec-11 14-Dec-11 13-Nov-11 14-Nov-11 16-Nov-11 17-Nov-11 20-Nov-11 21-Nov-11 22-Nov-11 24-Nov-11 12-Dec-11 14-Dec-11 18-Dec-11 16-Nov-11 17-Nov-11 20-Nov-11 21-Nov-11 23-Nov-11 24-Nov-11 26-Nov-11 28-Nov-11 15-Dec-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

06-Nov-11

07-Dec-11

09-Nov-11

11-Dec-11

13-Nov-11

14-Dec-11

16-Nov-11

18-Dec-11

Page 89 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-CB-SG2690 Finishing work & Painting UNIT - 12 E FO-CB-SG2700 Preparatory Work on RC Wall FO-CB-SG2710 Erect the Working Platform FO-CB-SG2720 Reinforcement Fixing FO-CB-SG2730 Checking and Approval FO-CB-SG2740 Shutter Fixing FO-CB-SG2750 Survey Checking and Approval FO-CB-SG2760 Concreting FO-CB-SG2770 Deshuttering FO-CB-SG2780 Curing Crash Barrier Concrete FO-CB-SG2790 Finishing work & Painting UNIT - 13 E FO-CB-SG3400 Preparatory Work on RC Wall FO-CB-SG3410 Erect the Working Platform FO-CB-SG3420 Reinforcement Fixing FO-CB-SG3430 Checking and Approval FO-CB-SG3440 Shutter Fixing FO-CB-SG3450 Survey Checking and Approval FO-CB-SG3460 Concreting FO-CB-SG3470 Deshuttering FO-CB-SG3480 Curing Crash Barrier Concrete FO-CB-SG3490 Finishing work & Painting UNIT - 14 E FO-CB-SG3500 Preparatory Work on RC Wall FO-CB-SG3510 Erect the Working Platform FO-CB-SG3520 Reinforcement Fixing FO-CB-SG3530 Checking and Approval FO-CB-SG3540 Shutter Fixing FO-CB-SG3550 Survey Checking and Approval FO-CB-SG3560 Concreting FO-CB-SG3570 Deshuttering FO-CB-SG3580 Curing Crash Barrier Concrete FO-CB-SG3590 Finishing work & Painting APPROACH SLAB - MUSCAT - GHALA SIDE FO-AS-SG1260 FO-AS-SG1270 FO-AS-SG1280 FO-AS-SG1290 FO-AS-SG1300 FO-AS-SG1310 FO-AS-SG1320 FO-AS-SG1330 FO-AS-SG1340 FO-AS-SG1350 Remaining Level of Effort Actual Work Remaining Work Preparatory Work on Embankment Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Survey Setting-out Approach Slab Steel Rebar Fixing Approach Slab Formwork Fixing Checking and Approval Approach Slab Concreting Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 17-Dec-11 28d 20-Nov-11 1d 20-Nov-11 1d 21-Nov-11 2d 22-Nov-11 1d 24-Nov-11 2d 26-Nov-11 1d 28-Nov-11 1d 29-Nov-11 1d 01-Dec-11 15d 03-Dec-11 2d 20-Dec-11 28d 23-Nov-11 1d 23-Nov-11 1d 24-Nov-11 2d 26-Nov-11 1d 28-Nov-11 2d 29-Nov-11 1d 01-Dec-11 1d 03-Dec-11 1d 05-Dec-11 15d 06-Dec-11 2d 24-Dec-11 28d 27-Nov-11 1d 27-Nov-11 1d 28-Nov-11 2d 29-Nov-11 1d 01-Dec-11 2d 03-Dec-11 1d 05-Dec-11 1d 06-Dec-11 1d 08-Dec-11 15d 10-Dec-11 2d 27-Dec-11 62d 29-Dec-11 1d 29-Dec-11 1d 31-Dec-11 1d 01-Jan-12 1d 02-Jan-12 3d 03-Jan-12 1d 04-Jan-12 2d 07-Jan-12 2d 09-Jan-12 1d 11-Jan-12 1d 12-Jan-12 Finish Jan F 18-Dec-11 21-Dec-11 20-Nov-11 21-Nov-11 23-Nov-11 24-Nov-11 27-Nov-11 28-Nov-11 29-Nov-11 01-Dec-11 19-Dec-11 21-Dec-11 25-Dec-11 23-Nov-11 24-Nov-11 27-Nov-11 28-Nov-11 30-Nov-11 01-Dec-11 03-Dec-11 05-Dec-11 22-Dec-11 25-Dec-11 28-Dec-11 27-Nov-11 28-Nov-11 30-Nov-11 01-Dec-11 04-Dec-11 05-Dec-11 06-Dec-11 08-Dec-11 26-Dec-11 28-Dec-11 10-Mar-12 29-Dec-11 31-Dec-11 01-Jan-12 02-Jan-12 05-Jan-12 04-Jan-12 08-Jan-12 10-Jan-12 11-Jan-12 12-Jan-12 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N 20-Nov-11

D Jan F

J Jul

21-Dec-11

23-Nov-11

25-Dec-11

27-Nov-11

28-Dec-11

29-Dec-11

10-Mar-12

Page 90 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID FO-AS-SG1360 FO-AS-SG1370 FO-AS-SG1380 UNIT - 07 W FO-RC-SG5140 Survey Setting out FO-RC-SG5150 Excavation Works FO-RC-SG5160 Leveling and Testing FO-RC-SG5170 Blinding Concrete / PCC FO-RC-SG5180 Blinding Concrete - Curing FO-RC-SG5190 Install of Water Proofing Membrane FO-RC-SG5200 Survey Setting-out FO-RC-SG5210 Footing Steel Rebar Fixing FO-RC-SG5220 Erect the Footing Formwork FO-RC-SG5230 Checking and Approval FO-RC-SG5240 RC Footing Concreting with Starter FO-RC-SG5250 RC Footing Formwork - Deshuttering FO-RC-SG5260 RC Footing Concrete - Curing FO-RC-SG5270 Survey Setting-out and Approval FO-RC-SG5280 RC Wall Steel Rebar Fixing FO-RC-SG5290 Erect the Working Platform FO-RC-SG5300 Erect the RC Wall Formwork FO-RC-SG5310 Survey Checking and Approval FO-RC-SG5320 RC Wall Concreting FO-RC-SG5330 Dismantle the RC Wall Formwork FO-RC-SG5340 RC Wall Curing FO-RC-SG5350 Water Proofing below GL FO-RC-SG5360 Backfilling and Compaction in Layers UNIT - 08 W FO-RC-SG5370 Survey Setting out FO-RC-SG5380 Excavation Works FO-RC-SG5390 Leveling and Testing FO-RC-SG5400 Blinding Concrete / PCC FO-RC-SG5410 Blinding Concrete - Curing FO-RC-SG5420 Install of Water Proofing Membrane FO-RC-SG5430 Survey Setting-out FO-RC-SG5440 Footing Steel Rebar Fixing FO-RC-SG5450 Erect the Footing Formwork FO-RC-SG5460 Checking and Approval FO-RC-SG5470 RC Footing Concreting with Starter FO-RC-SG5480 RC Footing Formwork - Deshuttering FO-RC-SG5490 RC Footing Concrete - Curing FO-RC-SG5500 Survey Setting-out and Approval FO-RC-SG5510 RC Wall Steel Rebar Fixing FO-RC-SG5520 Erect the Working Platform Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Activity Name Approach Slab Formwork - Deshuttering Approach Slab Concrete - Curing Expansion Joint

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 14-Jan-12 15d 15-Jan-12 2d 08-Mar-12 119d 22-May-11 70d 22-May-11 1d 22-May-11 1d 23-May-11 2d 24-May-11 1d 26-May-11 3d 28-May-11 2d 31-May-11 1d 02-Jun-11 8d 04-Jun-11 4d 13-Jun-11 1d 18-Jun-11 1d 19-Jun-11 1d 21-Jun-11 15d 20-Jun-11 1d 22-Jun-11 6d 23-Jun-11 2d 30-Jun-11 6d 03-Jul-11 1d 10-Jul-11 1d 11-Jul-11 1d 13-Jul-11 15d 14-Jul-11 5d 01-Aug-11 4d 07-Aug-11 70d 30-May-11 1d 30-May-11 1d 31-May-11 2d 01-Jun-11 1d 04-Jun-11 3d 05-Jun-11 2d 08-Jun-11 1d 11-Jun-11 8d 12-Jun-11 4d 21-Jun-11 1d 26-Jun-11 1d 27-Jun-11 1d 29-Jun-11 15d 28-Jun-11 1d 30-Jun-11 6d 02-Jul-11 2d 09-Jul-11 Finish Jan F 14-Jan-12 31-Jan-12 10-Mar-12 06-Oct-11 10-Aug-11 22-May-11 23-May-11 25-May-11 26-May-11 30-May-11 01-Jun-11 02-Jun-11 12-Jun-11 16-Jun-11 18-Jun-11 19-Jun-11 21-Jun-11 06-Jul-11 22-Jun-11 29-Jun-11 02-Jul-11 09-Jul-11 10-Jul-11 11-Jul-11 13-Jul-11 31-Jul-11 06-Aug-11 10-Aug-11 18-Aug-11 30-May-11 31-May-11 02-Jun-11 04-Jun-11 07-Jun-11 09-Jun-11 11-Jun-11 20-Jun-11 25-Jun-11 26-Jun-11 27-Jun-11 29-Jun-11 14-Jul-11 30-Jun-11 07-Jul-11 10-Jul-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

RETAINING CONCRETE WALL - MUSCAT - ATHAIBAH SIDE

22-May-11 22-May-11

06-Oct-11 10-Aug-11

30-May-11

18-Aug-11

Page 91 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG5530 Erect the RC Wall Formwork FO-RC-SG5540 Survey Checking and Approval FO-RC-SG5550 RC Wall Concreting FO-RC-SG5560 Dismantle the RC Wall Formwork FO-RC-SG5570 RC Wall Curing FO-RC-SG5580 Water Proofing below GL FO-RC-SG5590 Backfilling and Compaction in Layers UNIT - 09 W FO-RC-SG5600 Survey Setting out FO-RC-SG5610 Excavation Works FO-RC-SG5620 Leveling and Testing FO-RC-SG5630 Blinding Concrete / PCC FO-RC-SG5640 Blinding Concrete - Curing FO-RC-SG5650 Install of Water Proofing Membrane FO-RC-SG5660 Survey Setting-out FO-RC-SG5670 Footing Steel Rebar Fixing FO-RC-SG5680 Erect the Footing Formwork FO-RC-SG5690 Checking and Approval FO-RC-SG5700 RC Footing Concreting with Starter FO-RC-SG5710 RC Footing Formwork - Deshuttering FO-RC-SG5720 RC Footing Concrete - Curing FO-RC-SG5730 Survey Setting-out and Approval FO-RC-SG5740 RC Wall Steel Rebar Fixing FO-RC-SG5750 Erect the Working Platform FO-RC-SG5760 Erect the RC Wall Formwork FO-RC-SG5770 Survey Checking and Approval FO-RC-SG5780 RC Wall Concreting FO-RC-SG5790 Dismantle the RC Wall Formwork FO-RC-SG5800 RC Wall Curing FO-RC-SG5810 Water Proofing below GL FO-RC-SG5820 Backfilling and Compaction in Layers UNIT - 10 W FO-RC-SG5830 Survey Setting out FO-RC-SG5840 Excavation Works FO-RC-SG5850 Leveling and Testing FO-RC-SG5860 Blinding Concrete / PCC FO-RC-SG5870 Blinding Concrete - Curing FO-RC-SG5880 Install of Water Proofing Membrane FO-RC-SG5890 Survey Setting-out FO-RC-SG5900 Footing Steel Rebar Fixing FO-RC-SG5910 Erect the Footing Formwork FO-RC-SG5920 Checking and Approval FO-RC-SG5930 RC Footing Concreting with Starter FO-RC-SG5940 RC Footing Formwork - Deshuttering FO-RC-SG5950 RC Footing Concrete - Curing Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 6d 11-Jul-11 1d 18-Jul-11 1d 19-Jul-11 1d 21-Jul-11 15d 23-Jul-11 5d 09-Aug-11 4d 15-Aug-11 70d 07-Jun-11 1d 07-Jun-11 1d 08-Jun-11 2d 09-Jun-11 1d 12-Jun-11 3d 13-Jun-11 2d 16-Jun-11 1d 19-Jun-11 8d 20-Jun-11 4d 29-Jun-11 1d 04-Jul-11 1d 05-Jul-11 1d 07-Jul-11 15d 06-Jul-11 1d 09-Jul-11 6d 10-Jul-11 2d 17-Jul-11 6d 19-Jul-11 1d 26-Jul-11 1d 27-Jul-11 1d 30-Jul-11 15d 31-Jul-11 5d 17-Aug-11 4d 23-Aug-11 70d 15-Jun-11 1d 15-Jun-11 1d 16-Jun-11 2d 18-Jun-11 1d 20-Jun-11 3d 21-Jun-11 2d 25-Jun-11 1d 27-Jun-11 8d 28-Jun-11 4d 07-Jul-11 1d 12-Jul-11 1d 13-Jul-11 1d 16-Jul-11 15d 14-Jul-11 Finish Jan F 17-Jul-11 18-Jul-11 19-Jul-11 21-Jul-11 08-Aug-11 14-Aug-11 18-Aug-11 27-Aug-11 07-Jun-11 08-Jun-11 11-Jun-11 12-Jun-11 15-Jun-11 18-Jun-11 19-Jun-11 28-Jun-11 03-Jul-11 04-Jul-11 05-Jul-11 07-Jul-11 23-Jul-11 09-Jul-11 16-Jul-11 18-Jul-11 25-Jul-11 26-Jul-11 27-Jul-11 30-Jul-11 16-Aug-11 22-Aug-11 27-Aug-11 04-Sep-11 15-Jun-11 16-Jun-11 19-Jun-11 20-Jun-11 23-Jun-11 26-Jun-11 27-Jun-11 06-Jul-11 11-Jul-11 12-Jul-11 13-Jul-11 16-Jul-11 31-Jul-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

07-Jun-11

27-Aug-11

15-Jun-11

04-Sep-11

Page 92 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG5960 Survey Setting-out and Approval FO-RC-SG5970 RC Wall Steel Rebar Fixing FO-RC-SG5980 Erect the Working Platform FO-RC-SG5990 Erect the RC Wall Formwork FO-RC-SG6000 Survey Checking and Approval FO-RC-SG6010 RC Wall Concreting FO-RC-SG6020 Dismantle the RC Wall Formwork FO-RC-SG6030 RC Wall Curing FO-RC-SG6040 Water Proofing below GL FO-RC-SG6050 Backfilling and Compaction in Layers UNIT - 11 W FO-RC-SG6060 Survey Setting out FO-RC-SG6070 Excavation Works FO-RC-SG6080 Leveling and Testing FO-RC-SG6090 Blinding Concrete / PCC FO-RC-SG6100 Blinding Concrete - Curing FO-RC-SG6110 Install of Water Proofing Membrane FO-RC-SG6120 Survey Setting-out FO-RC-SG6130 Footing Steel Rebar Fixing FO-RC-SG6140 Erect the Footing Formwork FO-RC-SG6150 Checking and Approval FO-RC-SG6160 RC Footing Concreting with Starter FO-RC-SG6170 RC Footing Formwork - Deshuttering FO-RC-SG6180 RC Footing Concrete - Curing FO-RC-SG6190 Survey Setting-out and Approval FO-RC-SG6200 RC Wall Steel Rebar Fixing FO-RC-SG6210 Erect the Working Platform FO-RC-SG6220 Erect the RC Wall Formwork FO-RC-SG6230 Survey Checking and Approval FO-RC-SG6240 RC Wall Concreting FO-RC-SG6250 Dismantle the RC Wall Formwork FO-RC-SG6260 RC Wall Curing FO-RC-SG6270 Water Proofing below GL FO-RC-SG6280 Backfilling and Compaction in Layers UNIT - 12 W FO-RC-SG6290 Survey Setting out FO-RC-SG6300 Excavation Works FO-RC-SG6310 Leveling and Testing FO-RC-SG6320 Blinding Concrete / PCC FO-RC-SG6330 Blinding Concrete - Curing FO-RC-SG6340 Install of Water Proofing Membrane FO-RC-SG6350 Survey Setting-out FO-RC-SG6360 Footing Steel Rebar Fixing FO-RC-SG6370 Erect the Footing Formwork FO-RC-SG6380 Checking and Approval Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 17-Jul-11 6d 18-Jul-11 2d 25-Jul-11 6d 27-Jul-11 1d 03-Aug-11 1d 04-Aug-11 1d 07-Aug-11 15d 08-Aug-11 5d 25-Aug-11 4d 31-Aug-11 70d 23-Jun-11 1d 23-Jun-11 1d 25-Jun-11 2d 26-Jun-11 1d 28-Jun-11 3d 29-Jun-11 2d 03-Jul-11 1d 05-Jul-11 8d 06-Jul-11 4d 16-Jul-11 1d 20-Jul-11 1d 21-Jul-11 1d 24-Jul-11 15d 23-Jul-11 1d 25-Jul-11 6d 26-Jul-11 2d 02-Aug-11 6d 04-Aug-11 1d 11-Aug-11 1d 13-Aug-11 1d 15-Aug-11 15d 16-Aug-11 5d 03-Sep-11 4d 08-Sep-11 70d 02-Jul-11 1d 02-Jul-11 1d 03-Jul-11 2d 04-Jul-11 1d 06-Jul-11 3d 07-Jul-11 2d 11-Jul-11 1d 13-Jul-11 8d 14-Jul-11 4d 24-Jul-11 1d 28-Jul-11 Finish Jan F 17-Jul-11 24-Jul-11 26-Jul-11 02-Aug-11 03-Aug-11 04-Aug-11 07-Aug-11 24-Aug-11 30-Aug-11 04-Sep-11 12-Sep-11 23-Jun-11 25-Jun-11 27-Jun-11 28-Jun-11 02-Jul-11 04-Jul-11 05-Jul-11 14-Jul-11 19-Jul-11 20-Jul-11 21-Jul-11 24-Jul-11 08-Aug-11 25-Jul-11 01-Aug-11 03-Aug-11 10-Aug-11 11-Aug-11 13-Aug-11 15-Aug-11 01-Sep-11 07-Sep-11 12-Sep-11 20-Sep-11 02-Jul-11 03-Jul-11 05-Jul-11 06-Jul-11 10-Jul-11 12-Jul-11 13-Jul-11 23-Jul-11 27-Jul-11 28-Jul-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

23-Jun-11

12-Sep-11

02-Jul-11

20-Sep-11

Page 93 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG6390 RC Footing Concreting with Starter FO-RC-SG6400 RC Footing Formwork - Deshuttering FO-RC-SG6410 RC Footing Concrete - Curing FO-RC-SG6420 Survey Setting-out and Approval FO-RC-SG6430 RC Wall Steel Rebar Fixing FO-RC-SG6440 Erect the Working Platform FO-RC-SG6450 Erect the RC Wall Formwork FO-RC-SG6460 Survey Checking and Approval FO-RC-SG6470 RC Wall Concreting FO-RC-SG6480 Dismantle the RC Wall Formwork FO-RC-SG6490 RC Wall Curing FO-RC-SG6500 Water Proofing below GL FO-RC-SG6510 Backfilling and Compaction in Layers UNIT - 13 W FO-RC-SG7210 Survey Setting out FO-RC-SG7220 Excavation Works FO-RC-SG7230 Leveling and Testing FO-RC-SG7240 Blinding Concrete / PCC FO-RC-SG7250 Blinding Concrete - Curing FO-RC-SG7260 Install of Water Proofing Membrane FO-RC-SG7270 Survey Setting-out FO-RC-SG7280 Footing Steel Rebar Fixing FO-RC-SG7290 Erect the Footing Formwork FO-RC-SG7300 Checking and Approval FO-RC-SG7310 RC Footing Concreting with Starter FO-RC-SG7320 RC Footing Formwork - Deshuttering FO-RC-SG7330 RC Footing Concrete - Curing FO-RC-SG7340 Survey Setting-out and Approval FO-RC-SG7350 RC Wall Steel Rebar Fixing FO-RC-SG7360 Erect the Working Platform FO-RC-SG7370 Erect the RC Wall Formwork FO-RC-SG7380 Survey Checking and Approval FO-RC-SG7390 RC Wall Concreting FO-RC-SG7400 Dismantle the RC Wall Formwork FO-RC-SG7410 RC Wall Curing FO-RC-SG7420 Water Proofing below GL FO-RC-SG7430 Backfilling and Compaction in Layers UNIT - 14 W FO-RC-SG6980 Survey Setting out FO-RC-SG6990 Excavation Works FO-RC-SG7000 Leveling and Testing FO-RC-SG7010 Blinding Concrete / PCC FO-RC-SG7020 Blinding Concrete - Curing FO-RC-SG7030 Install of Water Proofing Membrane FO-RC-SG7040 Survey Setting-out Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 30-Jul-11 1d 01-Aug-11 15d 31-Jul-11 1d 02-Aug-11 6d 03-Aug-11 2d 10-Aug-11 6d 13-Aug-11 1d 20-Aug-11 1d 21-Aug-11 1d 23-Aug-11 15d 24-Aug-11 5d 11-Sep-11 4d 17-Sep-11 70d 10-Jul-11 1d 10-Jul-11 1d 11-Jul-11 2d 12-Jul-11 1d 14-Jul-11 3d 16-Jul-11 2d 19-Jul-11 1d 21-Jul-11 8d 23-Jul-11 4d 01-Aug-11 1d 06-Aug-11 1d 07-Aug-11 1d 09-Aug-11 15d 08-Aug-11 1d 10-Aug-11 6d 11-Aug-11 2d 18-Aug-11 6d 21-Aug-11 1d 28-Aug-11 1d 29-Aug-11 1d 31-Aug-11 15d 01-Sep-11 5d 19-Sep-11 4d 25-Sep-11 70d 18-Jul-11 1d 18-Jul-11 1d 19-Jul-11 2d 20-Jul-11 1d 23-Jul-11 3d 24-Jul-11 2d 27-Jul-11 1d 30-Jul-11 Finish Jan F 30-Jul-11 01-Aug-11 16-Aug-11 02-Aug-11 09-Aug-11 11-Aug-11 18-Aug-11 20-Aug-11 21-Aug-11 23-Aug-11 10-Sep-11 15-Sep-11 20-Sep-11 28-Sep-11 10-Jul-11 11-Jul-11 13-Jul-11 14-Jul-11 18-Jul-11 20-Jul-11 21-Jul-11 31-Jul-11 04-Aug-11 06-Aug-11 07-Aug-11 09-Aug-11 24-Aug-11 10-Aug-11 17-Aug-11 20-Aug-11 27-Aug-11 28-Aug-11 29-Aug-11 31-Aug-11 18-Sep-11 24-Sep-11 28-Sep-11 06-Oct-11 18-Jul-11 19-Jul-11 21-Jul-11 23-Jul-11 26-Jul-11 28-Jul-11 30-Jul-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

10-Jul-11

28-Sep-11

18-Jul-11

06-Oct-11

Page 94 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-RC-SG7050 Footing Steel Rebar Fixing FO-RC-SG7060 Erect the Footing Formwork FO-RC-SG7070 Checking and Approval FO-RC-SG7080 RC Footing Concreting with Starter FO-RC-SG7090 RC Footing Formwork - Deshuttering FO-RC-SG7100 RC Footing Concrete - Curing FO-RC-SG7110 Survey Setting-out and Approval FO-RC-SG7120 RC Wall Steel Rebar Fixing FO-RC-SG7130 Erect the Working Platform FO-RC-SG7140 Erect the RC Wall Formwork FO-RC-SG7150 Survey Checking and Approval FO-RC-SG7160 RC Wall Concreting FO-RC-SG7170 Dismantle the RC Wall Formwork FO-RC-SG7180 RC Wall Curing FO-RC-SG7190 Water Proofing below GL FO-RC-SG7200 Backfilling and Compaction in Layers BACKFILL - MUSCAT - ATHAIBAH SIDE FO-BF-SG1120 FO-BF-SG1130 FO-BF-SG1140 FO-BF-SG1150 UNIT - 07 W FO-CB-SG2800 Preparatory Work on RC Wall FO-CB-SG2810 Erect the Working Platform FO-CB-SG2820 Reinforcement Fixing FO-CB-SG2830 Checking and Approval FO-CB-SG2840 Shutter Fixing FO-CB-SG2850 Survey Checking and Approval FO-CB-SG2860 Concreting FO-CB-SG2870 Deshuttering FO-CB-SG2880 Curing Crash Barrier Concrete FO-CB-SG2890 Finishing work & Painting UNIT - 08 W FO-CB-SG2900 Preparatory Work on RC Wall FO-CB-SG2910 Erect the Working Platform FO-CB-SG2920 Reinforcement Fixing FO-CB-SG2930 Checking and Approval FO-CB-SG2940 Shutter Fixing FO-CB-SG2950 Survey Checking and Approval FO-CB-SG2960 Concreting FO-CB-SG2970 Deshuttering FO-CB-SG2980 Curing Crash Barrier Concrete FO-CB-SG2990 Finishing work & Painting UNIT - 09 W Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Bitumen Waterproofing Painting 150 mm dia PVC Perforated Pipe 300mm thk Single Size Pervious Backfill Geotextile Laying

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 8d 31-Jul-11 4d 09-Aug-11 1d 14-Aug-11 1d 15-Aug-11 1d 17-Aug-11 15d 16-Aug-11 1d 18-Aug-11 6d 20-Aug-11 2d 27-Aug-11 6d 29-Aug-11 1d 05-Sep-11 1d 06-Sep-11 1d 08-Sep-11 15d 10-Sep-11 5d 27-Sep-11 4d 03-Oct-11 32d 08-Oct-11 6d 08-Oct-11 26d 15-Oct-11 26d 15-Oct-11 26d 15-Oct-11 50d 14-Nov-11 28d 14-Nov-11 1d 14-Nov-11 1d 15-Nov-11 2d 16-Nov-11 1d 19-Nov-11 2d 20-Nov-11 1d 22-Nov-11 1d 23-Nov-11 1d 26-Nov-11 15d 27-Nov-11 2d 14-Dec-11 28d 17-Nov-11 1d 17-Nov-11 1d 19-Nov-11 2d 20-Nov-11 1d 22-Nov-11 2d 23-Nov-11 1d 26-Nov-11 1d 27-Nov-11 1d 29-Nov-11 15d 30-Nov-11 2d 18-Dec-11 28d 21-Nov-11 Finish Jan F 08-Aug-11 13-Aug-11 14-Aug-11 15-Aug-11 17-Aug-11 01-Sep-11 18-Aug-11 25-Aug-11 28-Aug-11 04-Sep-11 05-Sep-11 06-Sep-11 08-Sep-11 26-Sep-11 02-Oct-11 06-Oct-11 13-Nov-11 13-Oct-11 13-Nov-11 13-Nov-11 13-Nov-11 10-Jan-12 15-Dec-11 14-Nov-11 15-Nov-11 17-Nov-11 19-Nov-11 21-Nov-11 22-Nov-11 23-Nov-11 26-Nov-11 13-Dec-11 15-Dec-11 19-Dec-11 17-Nov-11 19-Nov-11 21-Nov-11 22-Nov-11 24-Nov-11 26-Nov-11 27-Nov-11 29-Nov-11 17-Dec-11 19-Dec-11 22-Dec-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

08-Oct-11

13-Nov-11

CRASH BARRIERS - MUSCAT - ATHAIBAH SIDE

14-Nov-11 14-Nov-11

10-Jan-12 15-Dec-11

17-Nov-11

19-Dec-11

21-Nov-11 TASK filter: All Activities

22-Dec-11

Page 95 of 115

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-CB-SG3000 Preparatory Work on RC Wall FO-CB-SG3010 Erect the Working Platform FO-CB-SG3020 Reinforcement Fixing FO-CB-SG3030 Checking and Approval FO-CB-SG3040 Shutter Fixing FO-CB-SG3050 Survey Checking and Approval FO-CB-SG3060 Concreting FO-CB-SG3070 Deshuttering FO-CB-SG3080 Curing Crash Barrier Concrete FO-CB-SG3090 Finishing work & Painting UNIT - 10 W FO-CB-SG3100 Preparatory Work on RC Wall FO-CB-SG3110 Erect the Working Platform FO-CB-SG3120 Reinforcement Fixing FO-CB-SG3130 Checking and Approval FO-CB-SG3140 Shutter Fixing FO-CB-SG3150 Survey Checking and Approval FO-CB-SG3160 Concreting FO-CB-SG3170 Deshuttering FO-CB-SG3180 Curing Crash Barrier Concrete FO-CB-SG3190 Finishing work & Painting UNIT - 11 W FO-CB-SG3200 Preparatory Work on RC Wall FO-CB-SG3210 Erect the Working Platform FO-CB-SG3220 Reinforcement Fixing FO-CB-SG3230 Checking and Approval FO-CB-SG3240 Shutter Fixing FO-CB-SG3250 Survey Checking and Approval FO-CB-SG3260 Concreting FO-CB-SG3270 Deshuttering FO-CB-SG3280 Curing Crash Barrier Concrete FO-CB-SG3290 Finishing work & Painting UNIT - 12 W FO-CB-SG3300 Preparatory Work on RC Wall FO-CB-SG3310 Erect the Working Platform FO-CB-SG3320 Reinforcement Fixing FO-CB-SG3330 Checking and Approval FO-CB-SG3340 Shutter Fixing FO-CB-SG3350 Survey Checking and Approval FO-CB-SG3360 Concreting FO-CB-SG3370 Deshuttering FO-CB-SG3380 Curing Crash Barrier Concrete FO-CB-SG3390 Finishing work & Painting UNIT - 13 W FO-CB-SG3600 Preparatory Work on RC Wall Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 21-Nov-11 1d 22-Nov-11 2d 23-Nov-11 1d 26-Nov-11 2d 27-Nov-11 1d 29-Nov-11 1d 30-Nov-11 1d 03-Dec-11 15d 04-Dec-11 2d 21-Dec-11 28d 24-Nov-11 1d 24-Nov-11 1d 26-Nov-11 2d 27-Nov-11 1d 29-Nov-11 2d 30-Nov-11 1d 03-Dec-11 1d 04-Dec-11 1d 06-Dec-11 15d 07-Dec-11 2d 25-Dec-11 28d 28-Nov-11 1d 28-Nov-11 1d 29-Nov-11 2d 30-Nov-11 1d 03-Dec-11 2d 04-Dec-11 1d 06-Dec-11 1d 07-Dec-11 1d 10-Dec-11 15d 11-Dec-11 2d 28-Dec-11 28d 01-Dec-11 1d 01-Dec-11 1d 03-Dec-11 2d 04-Dec-11 1d 06-Dec-11 2d 07-Dec-11 1d 10-Dec-11 1d 11-Dec-11 1d 13-Dec-11 15d 14-Dec-11 2d 01-Jan-12 28d 05-Dec-11 1d 05-Dec-11 Finish Jan F 21-Nov-11 22-Nov-11 24-Nov-11 26-Nov-11 28-Nov-11 29-Nov-11 30-Nov-11 03-Dec-11 20-Dec-11 22-Dec-11 26-Dec-11 24-Nov-11 26-Nov-11 28-Nov-11 29-Nov-11 01-Dec-11 03-Dec-11 04-Dec-11 06-Dec-11 24-Dec-11 26-Dec-11 29-Dec-11 28-Nov-11 29-Nov-11 01-Dec-11 03-Dec-11 05-Dec-11 06-Dec-11 07-Dec-11 10-Dec-11 27-Dec-11 29-Dec-11 02-Jan-12 01-Dec-11 03-Dec-11 05-Dec-11 06-Dec-11 08-Dec-11 10-Dec-11 11-Dec-11 13-Dec-11 31-Dec-11 02-Jan-12 05-Jan-12 05-Dec-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

24-Nov-11

26-Dec-11

28-Nov-11

29-Dec-11

01-Dec-11

02-Jan-12

05-Dec-11

05-Jan-12

Page 96 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name FO-CB-SG3610 Erect the Working Platform FO-CB-SG3620 Reinforcement Fixing FO-CB-SG3630 Checking and Approval FO-CB-SG3640 Shutter Fixing FO-CB-SG3650 Survey Checking and Approval FO-CB-SG3660 Concreting FO-CB-SG3670 Deshuttering FO-CB-SG3680 Curing Crash Barrier Concrete FO-CB-SG3690 Finishing work & Painting UNIT - 14 W FO-CB-SG3700 Preparatory Work on RC Wall FO-CB-SG3710 Erect the Working Platform FO-CB-SG3720 Reinforcement Fixing FO-CB-SG3730 Checking and Approval FO-CB-SG3740 Shutter Fixing FO-CB-SG3750 Survey Checking and Approval FO-CB-SG3760 Concreting FO-CB-SG3770 Deshuttering FO-CB-SG3780 Curing Crash Barrier Concrete FO-CB-SG3790 Finishing work & Painting APPROACH SLAB - MUSCAT - ATHAIBAH SIDE FO-AS-SG1390 FO-AS-SG1400 FO-AS-SG1410 FO-AS-SG1420 FO-AS-SG1430 FO-AS-SG1440 FO-AS-SG1450 FO-AS-SG1460 FO-AS-SG1470 FO-AS-SG1480 FO-AS-SG1490 FO-AS-SG1500 FO-AS-SG1510 Preparatory Work on Embankment Excavation Works Leveling and Testing Blinding Concrete / PCC Blinding Concrete - Curing Survey Setting-out Approach Slab Steel Rebar Fixing Approach Slab Formwork Fixing Checking and Approval Approach Slab Concreting Approach Slab Formwork - Deshuttering Approach Slab Concrete - Curing Expansion Joint

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 06-Dec-11 2d 07-Dec-11 1d 10-Dec-11 2d 11-Dec-11 1d 13-Dec-11 1d 14-Dec-11 1d 17-Dec-11 15d 18-Dec-11 2d 04-Jan-12 28d 10-Dec-11 1d 10-Dec-11 1d 11-Dec-11 2d 12-Dec-11 1d 14-Dec-11 2d 15-Dec-11 1d 18-Dec-11 1d 19-Dec-11 1d 21-Dec-11 15d 22-Dec-11 2d 09-Jan-12 53d 11-Jan-12 1d 11-Jan-12 1d 12-Jan-12 1d 14-Jan-12 1d 15-Jan-12 3d 16-Jan-12 1d 17-Jan-12 2d 19-Jan-12 2d 22-Jan-12 1d 24-Jan-12 1d 25-Jan-12 1d 26-Jan-12 15d 28-Jan-12 2d 11-Mar-12 334d 01-Dec-10 45d 01-Dec-10 10d 01-Dec-10 4d 13-Dec-10 20d 18-Dec-10 7d 10-Jan-11 4d 18-Jan-11 16d 23-Jan-11 2d 23-Jan-11 2d 25-Jan-11 4d 27-Jan-11 Finish Jan F 06-Dec-11 08-Dec-11 10-Dec-11 12-Dec-11 13-Dec-11 14-Dec-11 17-Dec-11 03-Jan-12 05-Jan-12 10-Jan-12 10-Dec-11 11-Dec-11 13-Dec-11 14-Dec-11 17-Dec-11 18-Dec-11 19-Dec-11 21-Dec-11 08-Jan-12 10-Jan-12 12-Mar-12 11-Jan-12 12-Jan-12 14-Jan-12 15-Jan-12 18-Jan-12 17-Jan-12 21-Jan-12 23-Jan-12 24-Jan-12 25-Jan-12 26-Jan-12 13-Feb-12 12-Mar-12 25-Dec-11 22-Jan-11 12-Dec-10 16-Dec-10 09-Jan-11 17-Jan-11 22-Jan-11 09-Feb-11 24-Jan-11 26-Jan-11 31-Jan-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

10-Dec-11

10-Jan-12

11-Jan-12

12-Mar-12

WADI BRIDGE
TRAFFIC ROAD DIVERSION (TRD)
WB-R-TD-1000 WB-R-TD-1020 WB-R-TD-1040 WB-R-TD-1060 WB-R-TD-1080 WB-B-DM-1000 WB-B-DM-1020 WB-B-DM-1040 Remaining Level of Effort Actual Work Remaining Work Utilities Relocation Grubbing and Grading for Temporary Diversion Roadworks Traffic Barrication by Placing Concrete/ Plastic Barriers Road Marking and Road Furniture Fixing Removal of Crash Barrier Dismantling & Removal of Deck Slab Dismantling & Removal of PSC Girders Critical Remaining Work Milestone Summary

01-Dec-10 01-Dec-10 22-Jan-11

25-Dec-11

DISMANTLING OF EXISTING WADI BRIDGE (DWB)

23-Jan-11

09-Feb-11

Page 97 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-B-DM-1060 WB-B-DM-1080 Activity Name Dismantling & Removal of Pier Cap, Pier and Footing Excavation and Preparation of Platform for Piling

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 4d 01-Feb-11 4d 06-Feb-11 67d 10-Feb-11 17d 10-Feb-11 2d 10-Feb-11 1d 13-Feb-11 3d 14-Feb-11 5d 24-Feb-11 2d 13-Feb-11 1d 17-Feb-11 3d 19-Feb-11 17d 22-Feb-11 2d 22-Feb-11 1d 24-Feb-11 3d 26-Feb-11 5d 08-Mar-11 2d 24-Feb-11 1d 01-Mar-11 3d 02-Mar-11 17d 06-Mar-11 2d 06-Mar-11 1d 08-Mar-11 3d 09-Mar-11 5d 20-Mar-11 2d 08-Mar-11 1d 13-Mar-11 3d 14-Mar-11 17d 17-Mar-11 2d 17-Mar-11 1d 20-Mar-11 3d 21-Mar-11 5d 31-Mar-11 2d 20-Mar-11 1d 24-Mar-11 3d 26-Mar-11 17d 29-Mar-11 2d 29-Mar-11 1d 31-Mar-11 3d 02-Apr-11 5d 12-Apr-11 2d 31-Mar-11 1d 05-Apr-11 3d 06-Apr-11 17d 10-Apr-11 2d 10-Apr-11 Finish Jan F 05-Feb-11 09-Feb-11 28-Apr-11 01-Mar-11 12-Feb-11 13-Feb-11 16-Feb-11 01-Mar-11 14-Feb-11 17-Feb-11 21-Feb-11 13-Mar-11 23-Feb-11 24-Feb-11 28-Feb-11 13-Mar-11 26-Feb-11 01-Mar-11 05-Mar-11 24-Mar-11 07-Mar-11 08-Mar-11 12-Mar-11 24-Mar-11 09-Mar-11 13-Mar-11 16-Mar-11 05-Apr-11 19-Mar-11 20-Mar-11 23-Mar-11 05-Apr-11 21-Mar-11 24-Mar-11 28-Mar-11 17-Apr-11 30-Mar-11 31-Mar-11 04-Apr-11 17-Apr-11 02-Apr-11 05-Apr-11 09-Apr-11 28-Apr-11 11-Apr-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

PILING (P) ABUTMENT - 01 - PILING


WB-P-A1-1000 WB-P-A1-1010 WB-P-A1-1020 WB-P-A1-1030 WB-P-A1-1040 WB-P-A1-1050 WB-P-A1-1060 Preparation of Platform and Coordinates Marking Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (17 No.) PILE LOAD TEST (1) Preparation of Platform and Co-ordinates Marking Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (15 No.) Preparation of Platform and Coordinates Marking Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (24 No.) PILE LOAD TEST (2) Preparation of Platform and Co-ordinates Marking Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (24 No.) Preparation of Platform and Coordinates Marking Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (18 No.) PILE LOAD TEST (3) Preparation of Platform and Co-ordinates Marking Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (15 No.) Preparation of Platform and Coordinates Marking Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (24 No.) PILE LOAD TEST (4) Preparation of Platform and Co-ordinates Marking Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (24 No.) Preparation of Platform and Coordinates Marking Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (24 No.) PILE LOAD TEST (5) Preparation of Platform and Co-ordinates Marking Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (24 No.) Preparation of Platform and Coordinates Marking Critical Remaining Work Milestone Summary

10-Feb-11 10-Feb-11

28-Apr-11 01-Mar-11

PIER - 01 - PILING
WB-P-P1-1000 WB-P-P1-1010 WB-P-P1-1020 WB-P-P1-1030 WB-P-P1-1040 WB-P-P1-1050 WB-P-P1-1060 WB-P-A2-1000 WB-P-A2-1010 WB-P-A2-1020 WB-P-A2-1030 WB-P-A2-1040 WB-P-A2-1050 WB-P-A2-1060

22-Feb-11

13-Mar-11

ABUTMENT - 02 - PILING

06-Mar-11

24-Mar-11

PIER - 04 - PILING
WB-P-P4-1000 WB-P-P4-1010 WB-P-P4-1020 WB-P-P4-1030 WB-P-P4-1040 WB-P-P4-1050 WB-P-P4-1060

17-Mar-11

05-Apr-11

PIER - 02 - PILING
WB-P-P2-1000 WB-P-P2-1010 WB-P-P2-1020 WB-P-P2-1030 WB-P-P2-1040 WB-P-P2-1050 WB-P-P2-1060

29-Mar-11

17-Apr-11

PIER - 03 - PILING
WB-P-P3-1000 Remaining Level of Effort Actual Work Remaining Work

10-Apr-11

28-Apr-11

Page 98 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-P-P3-1010 WB-P-P3-1020 WB-P-P3-1030 WB-P-P3-1040 WB-P-P3-1050 WB-P-P3-1060 Activity Name Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (24 No.) PILE LOAD TEST (6) Preparation of Platform and Co-ordinates Marking Piling Rig Setting in Position Boring, Placing Reinforcement and Concreting (24 No.)

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 12-Apr-11 3d 13-Apr-11 5d 24-Apr-11 2d 12-Apr-11 1d 17-Apr-11 3d 18-Apr-11 138d 02-Mar-11 59d 02-Mar-11 37d 02-Mar-11 1d 02-Mar-11 2d 03-Mar-11 2d 06-Mar-11 1d 08-Mar-11 3d 09-Mar-11 2d 13-Mar-11 1d 15-Mar-11 4d 16-Mar-11 4d 21-Mar-11 1d 26-Mar-11 1d 27-Mar-11 2d 29-Mar-11 15d 28-Mar-11 37d 02-Mar-11 1d 02-Mar-11 2d 03-Mar-11 2d 06-Mar-11 1d 08-Mar-11 3d 09-Mar-11 2d 13-Mar-11 1d 15-Mar-11 4d 16-Mar-11 4d 21-Mar-11 1d 26-Mar-11 1d 27-Mar-11 2d 29-Mar-11 15d 28-Mar-11 37d 28-Mar-11 1d 28-Mar-11 2d 29-Mar-11 2d 31-Mar-11 1d 03-Apr-11 3d 04-Apr-11 2d 07-Apr-11 1d 10-Apr-11 4d 11-Apr-11 Finish Jan F 12-Apr-11 16-Apr-11 28-Apr-11 13-Apr-11 17-Apr-11 20-Apr-11 09-Aug-11 09-May-11 13-Apr-11 02-Mar-11 05-Mar-11 07-Mar-11 08-Mar-11 12-Mar-11 14-Mar-11 15-Mar-11 20-Mar-11 24-Mar-11 26-Mar-11 27-Mar-11 30-Mar-11 13-Apr-11 13-Apr-11 02-Mar-11 05-Mar-11 07-Mar-11 08-Mar-11 12-Mar-11 14-Mar-11 15-Mar-11 20-Mar-11 24-Mar-11 26-Mar-11 27-Mar-11 30-Mar-11 13-Apr-11 09-May-11 28-Mar-11 30-Mar-11 02-Apr-11 03-Apr-11 06-Apr-11 09-Apr-11 10-Apr-11 14-Apr-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

SUBSTRUCTURE ABUTMENTS
Abutment - 01 (Ghala Side Side) WB-G-A1-1000 WB-G-A1-1010 WB-G-A1-1020 WB-G-A1-1030 WB-G-A1-1040 WB-G-A1-1050 WB-G-A1-1060 WB-G-A1-1070 WB-G-A1-1080 WB-G-A1-1090 WB-G-A1-1100 WB-G-A1-1110 WB-G-A1-1120 WB-A-A1-1000 WB-A-A1-1010 WB-A-A1-1020 WB-A-A1-1030 WB-A-A1-1040 WB-A-A1-1050 WB-A-A1-1060 WB-A-A1-1070 WB-A-A1-1080 WB-A-A1-1090 WB-A-A1-1100 WB-A-A1-1110 WB-A-A1-1120 WB-G-A2-1000 WB-G-A2-1010 WB-G-A2-1020 WB-G-A2-1030 WB-G-A2-1040 WB-G-A2-1050 WB-G-A2-1060 WB-G-A2-1070 Remaining Level of Effort Actual Work Remaining Work Co-ordinates Marking Excavation Works Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Abutment - Footing Steel Rebar Fixing Abutment - Erect the Footing Formwork Checking and Approval Abutment Footing Concreting with Wingwall Abutment Footing Formwork - Deshuttering Abutment Footing Concrete - Curing Co-ordinates Marking Excavation Works Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Abutment - Footing Steel Rebar Fixing Abutment - Erect the Footing Formwork Checking and Approval Abutment Footing Concreting with Wingwall Abutment Footing Formwork - Deshuttering Abutment Footing Concrete - Curing Co-ordinates Marking Excavation Works Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Abutment - Footing Steel Rebar Fixing Critical Remaining Work Milestone Summary

02-Mar-11 02-Mar-11 02-Mar-11 09-May-11 13-Apr-11

09-Aug-11

Abutment - 01 (Athaibah Side Side)

02-Mar-11

13-Apr-11

Abutment - 02 (Ghala Side Side)

28-Mar-11

09-May-11

Page 99 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-G-A2-1080 WB-G-A2-1090 WB-G-A2-1100 WB-G-A2-1110 WB-G-A2-1120 WB-A-A2-1000 WB-A-A2-1010 WB-A-A2-1020 WB-A-A2-1030 WB-A-A2-1040 WB-A-A2-1050 WB-A-A2-1060 WB-A-A2-1070 WB-A-A2-1080 WB-A-A2-1090 WB-A-A2-1100 WB-A-A2-1110 WB-A-A2-1120 Activity Name Abutment - Erect the Footing Formwork Checking and Approval Abutment Footing Concreting with Wingwall Abutment Footing Formwork - Deshuttering Abutment Footing Concrete - Curing Co-ordinates Marking Excavation Works Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Abutment - Footing Steel Rebar Fixing Abutment - Erect the Footing Formwork Checking and Approval Abutment Footing Concreting with Wingwall Abutment Footing Formwork - Deshuttering Abutment Footing Concrete - Curing

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 4d 16-Apr-11 1d 20-Apr-11 1d 21-Apr-11 2d 24-Apr-11 15d 23-Apr-11 37d 28-Mar-11 1d 28-Mar-11 2d 29-Mar-11 2d 31-Mar-11 1d 03-Apr-11 3d 04-Apr-11 2d 07-Apr-11 1d 10-Apr-11 4d 11-Apr-11 4d 16-Apr-11 1d 20-Apr-11 1d 21-Apr-11 2d 24-Apr-11 15d 23-Apr-11 128d 14-Mar-11 77d 14-Mar-11 Finish Jan F 19-Apr-11 20-Apr-11 21-Apr-11 25-Apr-11 09-May-11 09-May-11 28-Mar-11 30-Mar-11 02-Apr-11 03-Apr-11 06-Apr-11 09-Apr-11 10-Apr-11 14-Apr-11 19-Apr-11 20-Apr-11 21-Apr-11 25-Apr-11 09-May-11 09-Aug-11 11-Jun-11 14-Mar-11 16-Mar-11 20-Mar-11 21-Mar-11 24-Mar-11 28-Mar-11 29-Mar-11 03-Apr-11 07-Apr-11 09-Apr-11 10-Apr-11 12-Apr-11 30-Apr-11 24-Apr-11 28-Apr-11 30-Apr-11 04-May-11 05-May-11 09-May-11 12-May-11 17-May-11 21-May-11 22-May-11 23-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Abutment - 02 (Athaibah Side Side)

28-Mar-11

09-May-11

PIERS
Pier - 01 (Ghala Side Side) WB-G-P1-1000 WB-G-P1-1010 WB-G-P1-1020 WB-G-P1-1030 WB-G-P1-1040 WB-G-P1-1050 WB-G-P1-1060 WB-G-P1-1070 WB-G-P1-1080 WB-G-P1-1090 WB-G-P1-1100 WB-G-P1-1110 WB-G-P1-1120 WB-G-P1-1130 WB-G-P1-1140 WB-G-P1-1150 WB-G-P1-1160 WB-G-P1-1170 WB-G-P1-1180 WB-G-P1-1190 WB-G-P1-1200 WB-G-P1-1210 WB-G-P1-1220 WB-G-P1-1230 Remaining Level of Effort Actual Work Remaining Work Co-ordinates Marking Excavation Works Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Pile Cap - Rebar Fixing Pile Cap - Erect the Footing Formwork Checking and Approval Pile Cap - Concreting with Starters Pile Cap - Formwork - Deshuttering Pile Cap - Concrete - Curing Pier Column - Rebar Fixing Pier Column - Shuttering Fixing (3 Columns) Pier Column - Concreting (3 Columns) Pier Column - Shuttering Fixing (2 Columns) Pier Column - Concreting (2 Columns) Pier Cap - Staging Pier Cap - Bottom Formwork Pier Cap - Rebar Fixing Pier Cap - Side Formwork Pier Cap - Checking Pier Cap - Concreting Critical Remaining Work Milestone Summary

14-Mar-11 14-Mar-11

09-Aug-11 11-Jun-11

1d 14-Mar-11 2d 15-Mar-11 3d 17-Mar-11 1d 21-Mar-11 3d 22-Mar-11 3d 26-Mar-11 1d 29-Mar-11 4d 30-Mar-11 4d 04-Apr-11 1d 09-Apr-11 1d 10-Apr-11 2d 11-Apr-11 15d 13-Apr-11 10d 13-Apr-11 4d 25-Apr-11 1d 30-Apr-11 2d 03-May-11 1d 05-May-11 2d 08-May-11 3d 10-May-11 4d 14-May-11 3d 18-May-11 1d 22-May-11 1d 23-May-11

Page 100 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-G-P1-1240 WB-G-P1-1250 WB-G-P1-1260 WB-A-P1-1000 WB-A-P1-1010 WB-A-P1-1020 WB-A-P1-1030 WB-A-P1-1040 WB-A-P1-1050 WB-A-P1-1060 WB-A-P1-1070 WB-A-P1-1080 WB-A-P1-1090 WB-A-P1-1100 WB-A-P1-1110 WB-A-P1-1120 WB-A-P1-1130 WB-A-P1-1140 WB-A-P1-1150 WB-A-P1-1160 WB-A-P1-1170 WB-A-P1-1180 WB-A-P1-1190 WB-A-P1-1200 WB-A-P1-1210 WB-A-P1-1220 WB-A-P1-1230 WB-A-P1-1240 WB-A-P1-1250 WB-A-P1-1260 Pier - 04 (Ghala Side Side) WB-G-P4-1000 WB-G-P4-1010 WB-G-P4-1020 WB-G-P4-1030 WB-G-P4-1040 WB-G-P4-1050 WB-G-P4-1060 WB-G-P4-1070 WB-G-P4-1080 WB-G-P4-1090 WB-G-P4-1100 WB-G-P4-1110 WB-G-P4-1120 Remaining Level of Effort Actual Work Remaining Work Co-ordinates Marking Excavation Works Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Pile Cap - Rebar Fixing Pile Cap - Erect the Footing Formwork Checking and Approval Pile Cap - Concreting with Starters Pile Cap - Formwork - Deshuttering Pile Cap - Concrete - Curing Critical Remaining Work Milestone Summary Activity Name Pier Cap - Pedestal Concreting Pier Cap - Concrete - Curing Pier Cap - Formwork - Deshuttering Co-ordinates Marking Excavation Works Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Pile Cap - Rebar Fixing Pile Cap - Erect the Footing Formwork Checking and Approval Pile Cap - Concreting with Starters Pile Cap - Formwork - Deshuttering Pile Cap - Concrete - Curing Pier Column - Rebar Fixing Pier Column - Shuttering Fixing (3 Columns) Pier Column - Concreting (3 Columns) Pier Column - Shuttering Fixing (2 Columns) Pier Column - Concreting (2 Columns) Pier Cap - Staging Pier Cap - Bottom Formwork Pier Cap - Rebar Fixing Pier Cap - Side Formwork Pier Cap - Checking Pier Cap - Concreting Pier Cap - Pedestal Concreting Pier Cap - Concrete - Curing Pier Cap - Formwork - Deshuttering

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 24-May-11 15d 25-May-11 3d 31-May-11 77d 14-Mar-11 1d 14-Mar-11 2d 15-Mar-11 3d 17-Mar-11 1d 21-Mar-11 3d 22-Mar-11 3d 26-Mar-11 1d 29-Mar-11 4d 30-Mar-11 4d 04-Apr-11 1d 09-Apr-11 1d 10-Apr-11 2d 11-Apr-11 15d 13-Apr-11 10d 13-Apr-11 4d 25-Apr-11 1d 30-Apr-11 2d 03-May-11 1d 05-May-11 2d 08-May-11 3d 10-May-11 4d 14-May-11 3d 18-May-11 1d 22-May-11 1d 23-May-11 1d 24-May-11 15d 25-May-11 3d 31-May-11 78d 06-Apr-11 1d 06-Apr-11 2d 07-Apr-11 3d 10-Apr-11 1d 13-Apr-11 3d 14-Apr-11 3d 18-Apr-11 1d 21-Apr-11 4d 23-Apr-11 4d 27-Apr-11 1d 02-May-11 1d 03-May-11 2d 04-May-11 15d 07-May-11 Finish Jan F 24-May-11 11-Jun-11 02-Jun-11 11-Jun-11 14-Mar-11 16-Mar-11 20-Mar-11 21-Mar-11 24-Mar-11 28-Mar-11 29-Mar-11 03-Apr-11 07-Apr-11 09-Apr-11 10-Apr-11 12-Apr-11 30-Apr-11 24-Apr-11 28-Apr-11 30-Apr-11 04-May-11 05-May-11 09-May-11 12-May-11 17-May-11 21-May-11 22-May-11 23-May-11 24-May-11 11-Jun-11 02-Jun-11 05-Jul-11 06-Apr-11 09-Apr-11 12-Apr-11 13-Apr-11 17-Apr-11 20-Apr-11 21-Apr-11 26-Apr-11 01-May-11 02-May-11 03-May-11 05-May-11 23-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Pier - 01 (Athaibah Side Side)

14-Mar-11

11-Jun-11

06-Apr-11

05-Jul-11

Page 101 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-G-P4-1130 WB-G-P4-1140 WB-G-P4-1150 WB-G-P4-1160 WB-G-P4-1170 WB-G-P4-1180 WB-G-P4-1190 WB-G-P4-1200 WB-G-P4-1210 WB-G-P4-1220 WB-G-P4-1230 WB-G-P4-1240 WB-G-P4-1250 WB-G-P4-1260 WB-A-P4-1000 WB-A-P4-1010 WB-A-P4-1020 WB-A-P4-1030 WB-A-P4-1040 WB-A-P4-1050 WB-A-P4-1060 WB-A-P4-1070 WB-A-P4-1080 WB-A-P4-1090 WB-A-P4-1100 WB-A-P4-1110 WB-A-P4-1120 WB-A-P4-1130 WB-A-P4-1140 WB-A-P4-1150 WB-A-P4-1160 WB-A-P4-1170 WB-A-P4-1180 WB-A-P4-1190 WB-A-P4-1200 WB-A-P4-1210 WB-A-P4-1220 WB-A-P4-1230 WB-A-P4-1240 WB-A-P4-1250 WB-A-P4-1260 Pier - 02 (Ghala Side Side) WB-G-P2-1000 WB-G-P2-1010 Remaining Level of Effort Actual Work Remaining Work Co-ordinates Marking Excavation Works Critical Remaining Work Milestone Summary Activity Name Pier Column - Rebar Fixing Pier Column - Shuttering Fixing (3 Columns) Pier Column - Concreting (3 Columns) Pier Column - Shuttering Fixing (2 Columns) Pier Column - Concreting (2 Columns) Pier Cap - Staging Pier Cap - Bottom Formwork Pier Cap - Rebar Fixing Pier Cap - Side Formwork Pier Cap - Checking Pier Cap - Concreting Pier Cap - Pedestal Concreting Pier Cap - Concrete - Curing Pier Cap - Formwork - Deshuttering Co-ordinates Marking Excavation Works Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Pile Cap - Rebar Fixing Pile Cap - Erect the Footing Formwork Checking and Approval Pile Cap - Concreting with Starters Pile Cap - Formwork - Deshuttering Pile Cap - Concrete - Curing Pier Column - Rebar Fixing Pier Column - Shuttering Fixing (3 Columns) Pier Column - Concreting (3 Columns) Pier Column - Shuttering Fixing (2 Columns) Pier Column - Concreting (2 Columns) Pier Cap - Staging Pier Cap - Bottom Formwork Pier Cap - Rebar Fixing Pier Cap - Side Formwork Pier Cap - Checking Pier Cap - Concreting Pier Cap - Pedestal Concreting Pier Cap - Concrete - Curing Pier Cap - Formwork - Deshuttering

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 10d 07-May-11 4d 18-May-11 1d 23-May-11 2d 26-May-11 1d 29-May-11 2d 31-May-11 3d 04-Jun-11 4d 07-Jun-11 3d 12-Jun-11 1d 15-Jun-11 1d 16-Jun-11 1d 18-Jun-11 15d 19-Jun-11 3d 25-Jun-11 78d 06-Apr-11 1d 06-Apr-11 2d 07-Apr-11 3d 10-Apr-11 1d 13-Apr-11 3d 14-Apr-11 3d 18-Apr-11 1d 21-Apr-11 4d 23-Apr-11 4d 27-Apr-11 1d 02-May-11 1d 03-May-11 2d 04-May-11 15d 07-May-11 10d 07-May-11 4d 18-May-11 1d 23-May-11 2d 26-May-11 1d 29-May-11 2d 31-May-11 3d 04-Jun-11 4d 07-Jun-11 3d 12-Jun-11 1d 15-Jun-11 1d 16-Jun-11 1d 18-Jun-11 15d 19-Jun-11 3d 25-Jun-11 77d 18-Apr-11 1d 18-Apr-11 2d 19-Apr-11 Finish Jan F 17-May-11 22-May-11 23-May-11 28-May-11 29-May-11 01-Jun-11 06-Jun-11 11-Jun-11 14-Jun-11 15-Jun-11 16-Jun-11 18-Jun-11 05-Jul-11 27-Jun-11 05-Jul-11 06-Apr-11 09-Apr-11 12-Apr-11 13-Apr-11 17-Apr-11 20-Apr-11 21-Apr-11 26-Apr-11 01-May-11 02-May-11 03-May-11 05-May-11 23-May-11 17-May-11 22-May-11 23-May-11 28-May-11 29-May-11 01-Jun-11 06-Jun-11 11-Jun-11 14-Jun-11 15-Jun-11 16-Jun-11 18-Jun-11 05-Jul-11 27-Jun-11 16-Jul-11 18-Apr-11 20-Apr-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Pier - 04 (Athaibah Side Side)

06-Apr-11

05-Jul-11

18-Apr-11

16-Jul-11

Page 102 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-G-P2-1020 WB-G-P2-1030 WB-G-P2-1040 WB-G-P2-1050 WB-G-P2-1060 WB-G-P2-1070 WB-G-P2-1080 WB-G-P2-1090 WB-G-P2-1100 WB-G-P2-1110 WB-G-P2-1120 WB-G-P2-1130 WB-G-P2-1140 WB-G-P2-1150 WB-G-P2-1160 WB-G-P2-1170 WB-G-P2-1180 WB-G-P2-1190 WB-G-P2-1200 WB-G-P2-1210 WB-G-P2-1220 WB-G-P2-1230 WB-G-P2-1240 WB-G-P2-1250 WB-G-P2-1260 WB-A-P2-1000 WB-A-P2-1010 WB-A-P2-1020 WB-A-P2-1030 WB-A-P2-1040 WB-A-P2-1050 WB-A-P2-1060 WB-A-P2-1070 WB-A-P2-1080 WB-A-P2-1090 WB-A-P2-1100 WB-A-P2-1110 WB-A-P2-1120 WB-A-P2-1130 WB-A-P2-1140 WB-A-P2-1150 WB-A-P2-1160 WB-A-P2-1170 WB-A-P2-1180 Remaining Level of Effort Actual Work Remaining Work Activity Name Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Pile Cap - Rebar Fixing Pile Cap - Erect the Footing Formwork Checking and Approval Pile Cap - Concreting with Starters Pile Cap - Formwork - Deshuttering Pile Cap - Concrete - Curing Pier Column - Rebar Fixing Pier Column - Shuttering Fixing (3 Columns) Pier Column - Concreting (3 Columns) Pier Column - Shuttering Fixing (2 Columns) Pier Column - Concreting (2 Columns) Pier Cap - Staging Pier Cap - Bottom Formwork Pier Cap - Rebar Fixing Pier Cap - Side Formwork Pier Cap - Checking Pier Cap - Concreting Pier Cap - Pedestal Concreting Pier Cap - Concrete - Curing Pier Cap - Formwork - Deshuttering Co-ordinates Marking Excavation Works Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Pile Cap - Rebar Fixing Pile Cap - Erect the Footing Formwork Checking and Approval Pile Cap - Concreting with Starters Pile Cap - Formwork - Deshuttering Pile Cap - Concrete - Curing Pier Column - Rebar Fixing Pier Column - Shuttering Fixing (3 Columns) Pier Column - Concreting (3 Columns) Pier Column - Shuttering Fixing (2 Columns) Pier Column - Concreting (2 Columns) Pier Cap - Staging Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 3d 21-Apr-11 1d 25-Apr-11 3d 26-Apr-11 3d 30-Apr-11 1d 03-May-11 4d 04-May-11 4d 09-May-11 1d 14-May-11 1d 15-May-11 2d 16-May-11 15d 18-May-11 10d 18-May-11 4d 30-May-11 1d 04-Jun-11 2d 07-Jun-11 1d 09-Jun-11 2d 12-Jun-11 3d 14-Jun-11 4d 18-Jun-11 3d 22-Jun-11 1d 26-Jun-11 1d 27-Jun-11 1d 28-Jun-11 15d 29-Jun-11 3d 05-Jul-11 77d 18-Apr-11 1d 18-Apr-11 2d 19-Apr-11 3d 21-Apr-11 1d 25-Apr-11 3d 26-Apr-11 3d 30-Apr-11 1d 03-May-11 4d 04-May-11 4d 09-May-11 1d 14-May-11 1d 15-May-11 2d 16-May-11 15d 18-May-11 10d 18-May-11 4d 30-May-11 1d 04-Jun-11 2d 07-Jun-11 1d 09-Jun-11 2d 12-Jun-11 Finish Jan F 24-Apr-11 25-Apr-11 28-Apr-11 02-May-11 03-May-11 08-May-11 12-May-11 14-May-11 15-May-11 17-May-11 04-Jun-11 29-May-11 02-Jun-11 04-Jun-11 08-Jun-11 09-Jun-11 13-Jun-11 16-Jun-11 21-Jun-11 25-Jun-11 26-Jun-11 27-Jun-11 28-Jun-11 16-Jul-11 07-Jul-11 16-Jul-11 18-Apr-11 20-Apr-11 24-Apr-11 25-Apr-11 28-Apr-11 02-May-11 03-May-11 08-May-11 12-May-11 14-May-11 15-May-11 17-May-11 04-Jun-11 29-May-11 02-Jun-11 04-Jun-11 08-Jun-11 09-Jun-11 13-Jun-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Pier - 02 (Athaibah Side Side)

18-Apr-11

16-Jul-11

Page 103 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-A-P2-1190 WB-A-P2-1200 WB-A-P2-1210 WB-A-P2-1220 WB-A-P2-1230 WB-A-P2-1240 WB-A-P2-1250 WB-A-P2-1260 Pier - 03 (Ghala Side Side) WB-G-P3-1000 WB-G-P3-1010 WB-G-P3-1020 WB-G-P3-1030 WB-G-P3-1040 WB-G-P3-1050 WB-G-P3-1060 WB-G-P3-1070 WB-G-P3-1080 WB-G-P3-1090 WB-G-P3-1100 WB-G-P3-1110 WB-G-P3-1120 WB-G-P3-1130 WB-G-P3-1140 WB-G-P3-1150 WB-G-P3-1160 WB-G-P3-1170 WB-G-P3-1180 WB-G-P3-1190 WB-G-P3-1200 WB-G-P3-1210 WB-G-P3-1220 WB-G-P3-1230 WB-G-P3-1240 WB-G-P3-1250 WB-G-P3-1260 WB-A-P3-1000 WB-A-P3-1010 WB-A-P3-1020 WB-A-P3-1030 WB-A-P3-1040 WB-A-P3-1050 WB-A-P3-1060 WB-A-P3-1070 Remaining Level of Effort Actual Work Remaining Work Co-ordinates Marking Excavation Works Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Pile Cap - Rebar Fixing Pile Cap - Erect the Footing Formwork Checking and Approval Pile Cap - Concreting with Starters Pile Cap - Formwork - Deshuttering Pile Cap - Concrete - Curing Pier Column - Rebar Fixing Pier Column - Shuttering Fixing (3 Columns) Pier Column - Concreting (3 Columns) Pier Column - Shuttering Fixing (2 Columns) Pier Column - Concreting (2 Columns) Pier Cap - Staging Pier Cap - Bottom Formwork Pier Cap - Rebar Fixing Pier Cap - Side Formwork Pier Cap - Checking Pier Cap - Concreting Pier Cap - Pedestal Concreting Pier Cap - Concrete - Curing Pier Cap - Formwork - Deshuttering Co-ordinates Marking Excavation Works Pile Hacking and Removal of Pile Debris Blinding Concrete / PCC Blinding Concrete - Curing Install of Water Proofing Membrane Survey Setting-out Pile Cap - Rebar Fixing Critical Remaining Work Milestone Summary Activity Name Pier Cap - Bottom Formwork Pier Cap - Rebar Fixing Pier Cap - Side Formwork Pier Cap - Checking Pier Cap - Concreting Pier Cap - Pedestal Concreting Pier Cap - Concrete - Curing Pier Cap - Formwork - Deshuttering

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 3d 14-Jun-11 4d 18-Jun-11 3d 22-Jun-11 1d 26-Jun-11 1d 27-Jun-11 1d 28-Jun-11 15d 29-Jun-11 3d 05-Jul-11 88d 30-Apr-11 1d 30-Apr-11 2d 01-May-11 3d 03-May-11 1d 07-May-11 3d 08-May-11 3d 11-May-11 1d 15-May-11 4d 16-May-11 4d 21-May-11 1d 25-May-11 1d 26-May-11 2d 28-May-11 15d 30-May-11 10d 30-May-11 4d 11-Jun-11 1d 15-Jun-11 2d 19-Jun-11 1d 21-Jun-11 2d 23-Jun-11 3d 09-Jul-11 4d 12-Jul-11 3d 17-Jul-11 1d 20-Jul-11 1d 21-Jul-11 1d 23-Jul-11 15d 24-Jul-11 3d 30-Jul-11 88d 30-Apr-11 1d 30-Apr-11 2d 01-May-11 3d 03-May-11 1d 07-May-11 3d 08-May-11 3d 11-May-11 1d 15-May-11 4d 16-May-11 Finish Jan F 16-Jun-11 21-Jun-11 25-Jun-11 26-Jun-11 27-Jun-11 28-Jun-11 16-Jul-11 07-Jul-11 09-Aug-11 30-Apr-11 02-May-11 05-May-11 07-May-11 10-May-11 14-May-11 15-May-11 19-May-11 24-May-11 25-May-11 26-May-11 29-May-11 15-Jun-11 09-Jun-11 14-Jun-11 15-Jun-11 20-Jun-11 21-Jun-11 25-Jun-11 11-Jul-11 16-Jul-11 19-Jul-11 20-Jul-11 21-Jul-11 23-Jul-11 09-Aug-11 01-Aug-11 09-Aug-11 30-Apr-11 02-May-11 05-May-11 07-May-11 10-May-11 14-May-11 15-May-11 19-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

30-Apr-11

09-Aug-11

Pier - 03 (Athaibah Side Side)

30-Apr-11

09-Aug-11

Page 104 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-A-P3-1080 WB-A-P3-1090 WB-A-P3-1100 WB-A-P3-1110 WB-A-P3-1120 WB-A-P3-1130 WB-A-P3-1140 WB-A-P3-1150 WB-A-P3-1160 WB-A-P3-1170 WB-A-P3-1180 WB-A-P3-1190 WB-A-P3-1200 WB-A-P3-1210 WB-A-P3-1220 WB-A-P3-1230 WB-A-P3-1240 WB-A-P3-1250 WB-A-P3-1260 Activity Name Pile Cap - Erect the Footing Formwork Checking and Approval Pile Cap - Concreting with Starters Pile Cap - Formwork - Deshuttering Pile Cap - Concrete - Curing Pier Column - Rebar Fixing Pier Column - Shuttering Fixing (3 Columns) Pier Column - Concreting (3 Columns) Pier Column - Shuttering Fixing (2 Columns) Pier Column - Concreting (2 Columns) Pier Cap - Staging Pier Cap - Bottom Formwork Pier Cap - Rebar Fixing Pier Cap - Side Formwork Pier Cap - Checking Pier Cap - Concreting Pier Cap - Pedestal Concreting Pier Cap - Concrete - Curing Pier Cap - Formwork - Deshuttering

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 4d 21-May-11 1d 25-May-11 1d 26-May-11 2d 28-May-11 15d 30-May-11 10d 30-May-11 4d 11-Jun-11 1d 15-Jun-11 2d 19-Jun-11 1d 21-Jun-11 2d 23-Jun-11 3d 28-Jun-11 4d 02-Jul-11 3d 06-Jul-11 1d 10-Jul-11 1d 11-Jul-11 1d 12-Jul-11 15d 24-Jul-11 3d 30-Jul-11 125d 02-Aug-11 65d 02-Aug-11 48d 02-Aug-11 2d 02-Aug-11 2d 04-Aug-11 1d 07-Aug-11 5d 08-Aug-11 2d 14-Aug-11 3d 16-Aug-11 2d 20-Aug-11 1d 22-Aug-11 1d 23-Aug-11 5d 28-Aug-11 4d 03-Sep-11 1d 07-Sep-11 1d 08-Sep-11 15d 10-Sep-11 4d 17-Sep-11 3d 21-Sep-11 46d 04-Aug-11 2d 04-Aug-11 2d 07-Aug-11 1d 09-Aug-11 5d 10-Aug-11 2d 16-Aug-11 3d 18-Aug-11 Finish Jan F 24-May-11 25-May-11 26-May-11 29-May-11 15-Jun-11 09-Jun-11 14-Jun-11 15-Jun-11 20-Jun-11 21-Jun-11 25-Jun-11 30-Jun-11 05-Jul-11 09-Jul-11 10-Jul-11 11-Jul-11 12-Jul-11 09-Aug-11 01-Aug-11 25-Dec-11 16-Oct-11 26-Sep-11 03-Aug-11 06-Aug-11 07-Aug-11 13-Aug-11 15-Aug-11 18-Aug-11 21-Aug-11 22-Aug-11 23-Aug-11 01-Sep-11 06-Sep-11 07-Sep-11 08-Sep-11 26-Sep-11 20-Sep-11 24-Sep-11 26-Sep-11 06-Aug-11 08-Aug-11 09-Aug-11 15-Aug-11 17-Aug-11 21-Aug-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

SUPERSTRUCTURE PSC GIRDER, DIAPHRAGM DECK SLAB & CRASH BARRIERS DIAPHRAGM,
Span - 01 (Ghala Side) Side WB-G-S1-1000 WB-G-S1-1010 WB-G-S1-1020 WB-G-S1-1030 WB-G-S1-1040 WB-G-S1-1050 WB-G-S1-1060 WB-G-S1-1070 WB-G-S1-1080 WB-G-S1-1090 WB-G-S1-1100 WB-G-S1-1110 WB-G-S1-1120 WB-G-S1-1130 WB-G-S1-1140 WB-G-S1-1150 WB-A-S1-1000 WB-A-S1-1010 WB-A-S1-1020 WB-A-S1-1030 WB-A-S1-1040 WB-A-S1-1050 Remaining Level of Effort Actual Work Remaining Work Preparation of Platform for Erection of Girders Temporary Staging and Stools Fixing POT Bearing Fixing and Boxing Precast Girder Erection (14 Nos.) Diaphragm Bottom Shuttering Diaphragm Reinforcement Fixing Diaphragm Side Shutter Fixing Diaphragm Checking Diaphragm Concreting Infill Slab Placing Deck - Rebar Fixing Deck - Checking Deck - Concreting Deck - Concrete Curing Crash Barrier Fixing Facia Fixing Preparation of Platform for Erection of Girders Temporary Staging and Stools Fixing POT Bearing Fixing and Boxing Precast Girder Erection (14 Nos.) Diaphragm Bottom Shuttering Diaphragm Reinforcement Fixing Critical Remaining Work Milestone Summary

02-Aug-11 02-Aug-11 02-Aug-11 26-Sep-11

25-Dec-11 16-Oct-11

Span - 01 (Athaibah Side) Side

04-Aug-11

26-Sep-11

Page 105 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-A-S1-1060 WB-A-S1-1070 WB-A-S1-1080 WB-A-S1-1090 WB-A-S1-1100 WB-A-S1-1110 WB-A-S1-1120 WB-A-S1-1130 WB-A-S1-1140 WB-A-S1-1150 WB-G-S2-1000 WB-G-S2-1010 WB-G-S2-1020 WB-G-S2-1030 WB-G-S2-1040 WB-G-S2-1050 WB-G-S2-1060 WB-G-S2-1070 WB-G-S2-1080 WB-G-S2-1090 WB-G-S2-1100 WB-G-S2-1110 WB-G-S2-1120 WB-G-S2-1130 WB-G-S2-1140 WB-G-S2-1150 WB-A-S2-1000 WB-A-S2-1010 WB-A-S2-1020 WB-A-S2-1030 WB-A-S2-1040 WB-A-S2-1050 WB-A-S2-1060 WB-A-S2-1070 WB-A-S2-1080 WB-A-S2-1090 WB-A-S2-1100 WB-A-S2-1110 WB-A-S2-1120 WB-A-S2-1130 WB-A-S2-1140 WB-A-S2-1150 Activity Name Diaphragm Side Shutter Fixing Diaphragm Checking Diaphragm Concreting Infill Slab Placing Deck - Rebar Fixing Deck - Checking Deck - Concreting Deck - Concrete Curing Crash Barrier Fixing Facia Fixing Preparation of Platform for Erection of Girders Temporary Staging and Stools Fixing POT Bearing Fixing and Boxing Precast Girder Erection (14 Nos.) Diaphragm Bottom Shuttering Diaphragm Reinforcement Fixing Diaphragm Side Shutter Fixing Diaphragm Checking Diaphragm Concreting Infill Slab Placing Deck - Rebar Fixing Deck - Checking Deck - Concreting Deck - Concrete Curing Crash Barrier Fixing Facia Fixing Preparation of Platform for Erection of Girders Temporary Staging and Stools Fixing POT Bearing Fixing and Boxing Precast Girder Erection (14 Nos.) Diaphragm Bottom Shuttering Diaphragm Reinforcement Fixing Diaphragm Side Shutter Fixing Diaphragm Checking Diaphragm Concreting Infill Slab Placing Deck - Rebar Fixing Deck - Checking Deck - Concreting Deck - Concrete Curing Crash Barrier Fixing Facia Fixing

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 22-Aug-11 1d 24-Aug-11 1d 25-Aug-11 5d 28-Aug-11 4d 03-Sep-11 1d 07-Sep-11 1d 08-Sep-11 15d 10-Sep-11 4d 17-Sep-11 3d 21-Sep-11 45d 07-Aug-11 2d 07-Aug-11 2d 09-Aug-11 1d 11-Aug-11 5d 13-Aug-11 2d 18-Aug-11 3d 21-Aug-11 2d 24-Aug-11 1d 27-Aug-11 1d 28-Aug-11 5d 29-Aug-11 4d 04-Sep-11 1d 08-Sep-11 1d 10-Sep-11 15d 11-Sep-11 4d 18-Sep-11 3d 22-Sep-11 45d 09-Aug-11 2d 09-Aug-11 2d 11-Aug-11 1d 14-Aug-11 5d 15-Aug-11 2d 21-Aug-11 3d 23-Aug-11 2d 27-Aug-11 1d 29-Aug-11 1d 30-Aug-11 5d 31-Aug-11 4d 06-Sep-11 1d 11-Sep-11 1d 12-Sep-11 15d 13-Sep-11 4d 20-Sep-11 3d 25-Sep-11 45d 14-Aug-11 Finish Jan F 23-Aug-11 24-Aug-11 25-Aug-11 01-Sep-11 06-Sep-11 07-Sep-11 08-Sep-11 26-Sep-11 20-Sep-11 24-Sep-11 27-Sep-11 08-Aug-11 10-Aug-11 11-Aug-11 17-Aug-11 20-Aug-11 23-Aug-11 25-Aug-11 27-Aug-11 28-Aug-11 03-Sep-11 07-Sep-11 08-Sep-11 10-Sep-11 27-Sep-11 21-Sep-11 25-Sep-11 29-Sep-11 10-Aug-11 13-Aug-11 14-Aug-11 20-Aug-11 22-Aug-11 25-Aug-11 28-Aug-11 29-Aug-11 30-Aug-11 05-Sep-11 10-Sep-11 11-Sep-11 12-Sep-11 29-Sep-11 24-Sep-11 27-Sep-11 04-Oct-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 02 (Ghala Side) Side

07-Aug-11

27-Sep-11

Span - 02 (Athaibah Side) Side

09-Aug-11

29-Sep-11

Span - 03 (Ghala Side) Side Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

14-Aug-11 TASK filter: All Activities

04-Oct-11

Page 106 of 115

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-G-S3-1000 WB-G-S3-1010 WB-G-S3-1020 WB-G-S3-1030 WB-G-S3-1040 WB-G-S3-1050 WB-G-S3-1060 WB-G-S3-1070 WB-G-S3-1080 WB-G-S3-1090 WB-G-S3-1100 WB-G-S3-1110 WB-G-S3-1120 WB-G-S3-1130 WB-G-S3-1140 WB-G-S3-1150 WB-A-S3-1000 WB-A-S3-1010 WB-A-S3-1020 WB-A-S3-1030 WB-A-S3-1040 WB-A-S3-1050 WB-A-S3-1060 WB-A-S3-1070 WB-A-S3-1080 WB-A-S3-1090 WB-A-S3-1100 WB-A-S3-1110 WB-A-S3-1120 WB-A-S3-1130 WB-A-S3-1140 WB-A-S3-1150 WB-G-S4-1000 WB-G-S4-1010 WB-G-S4-1020 WB-G-S4-1030 WB-G-S4-1040 WB-G-S4-1050 WB-G-S4-1060 WB-G-S4-1070 WB-G-S4-1080 WB-G-S4-1090 WB-G-S4-1100 Remaining Level of Effort Actual Work Remaining Work Activity Name Preparation of Platform for Erection of Girders Temporary Staging and Stools Fixing POT Bearing Fixing and Boxing Precast Girder Erection (13 Nos.) Diaphragm Bottom Shuttering Diaphragm Reinforcement Fixing Diaphragm Side Shutter Fixing Diaphragm Checking Diaphragm Concreting Infill Slab Placing Deck - Rebar Fixing Deck - Checking Deck - Concreting Deck - Concrete Curing Crash Barrier Fixing Facia Fixing Preparation of Platform for Erection of Girders Temporary Staging and Stools Fixing POT Bearing Fixing and Boxing Precast Girder Erection (13 Nos.) Diaphragm Bottom Shuttering Diaphragm Reinforcement Fixing Diaphragm Side Shutter Fixing Diaphragm Checking Diaphragm Concreting Infill Slab Placing Deck - Rebar Fixing Deck - Checking Deck - Concreting Deck - Concrete Curing Crash Barrier Fixing Facia Fixing Preparation of Platform for Erection of Girders Temporary Staging and Stools Fixing POT Bearing Fixing and Boxing Precast Girder Erection (13 Nos.) Diaphragm Bottom Shuttering Diaphragm Reinforcement Fixing Diaphragm Side Shutter Fixing Diaphragm Checking Diaphragm Concreting Infill Slab Placing Deck - Rebar Fixing Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 2d 14-Aug-11 2d 16-Aug-11 1d 18-Aug-11 5d 20-Aug-11 2d 25-Aug-11 3d 28-Aug-11 2d 31-Aug-11 1d 03-Sep-11 1d 04-Sep-11 5d 05-Sep-11 4d 11-Sep-11 1d 15-Sep-11 1d 17-Sep-11 15d 18-Sep-11 4d 25-Sep-11 3d 29-Sep-11 45d 16-Aug-11 2d 16-Aug-11 2d 18-Aug-11 1d 21-Aug-11 5d 22-Aug-11 2d 28-Aug-11 3d 30-Aug-11 2d 03-Sep-11 1d 05-Sep-11 1d 06-Sep-11 5d 07-Sep-11 4d 13-Sep-11 1d 18-Sep-11 1d 19-Sep-11 15d 20-Sep-11 4d 27-Sep-11 3d 02-Oct-11 45d 18-Aug-11 2d 18-Aug-11 2d 21-Aug-11 1d 23-Aug-11 5d 24-Aug-11 2d 30-Aug-11 3d 01-Sep-11 2d 05-Sep-11 1d 07-Sep-11 1d 08-Sep-11 5d 10-Sep-11 4d 15-Sep-11 Finish Jan F 15-Aug-11 17-Aug-11 18-Aug-11 24-Aug-11 27-Aug-11 30-Aug-11 01-Sep-11 03-Sep-11 04-Sep-11 10-Sep-11 14-Sep-11 15-Sep-11 17-Sep-11 04-Oct-11 28-Sep-11 02-Oct-11 06-Oct-11 17-Aug-11 20-Aug-11 21-Aug-11 27-Aug-11 29-Aug-11 01-Sep-11 04-Sep-11 05-Sep-11 06-Sep-11 12-Sep-11 17-Sep-11 18-Sep-11 19-Sep-11 06-Oct-11 01-Oct-11 04-Oct-11 09-Oct-11 20-Aug-11 22-Aug-11 23-Aug-11 29-Aug-11 31-Aug-11 04-Sep-11 06-Sep-11 07-Sep-11 08-Sep-11 14-Sep-11 19-Sep-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 03 (Athaibah Side) Side

16-Aug-11

06-Oct-11

Span - 04 (Ghala Side) Side

18-Aug-11

09-Oct-11

Page 107 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-G-S4-1110 WB-G-S4-1120 WB-G-S4-1130 WB-G-S4-1140 WB-G-S4-1150 WB-A-S4-1000 WB-A-S4-1010 WB-A-S4-1020 WB-A-S4-1030 WB-A-S4-1040 WB-A-S4-1050 WB-A-S4-1060 WB-A-S4-1070 WB-A-S4-1080 WB-A-S4-1090 WB-A-S4-1100 WB-A-S4-1110 WB-A-S4-1120 WB-A-S4-1130 WB-A-S4-1140 WB-A-S4-1150 WB-G-S5-1000 WB-G-S5-1010 WB-G-S5-1020 WB-G-S5-1030 WB-G-S5-1040 WB-G-S5-1050 WB-G-S5-1060 WB-G-S5-1070 WB-G-S5-1080 WB-G-S5-1090 WB-G-S5-1100 WB-G-S5-1110 WB-G-S5-1120 WB-G-S5-1130 WB-G-S5-1140 WB-G-S5-1150 WB-A-S5-1000 WB-A-S5-1010 WB-A-S5-1020 WB-A-S5-1030 WB-A-S5-1040 Remaining Level of Effort Actual Work Remaining Work Activity Name Deck - Checking Deck - Concreting Deck - Concrete Curing Crash Barrier Fixing Facia Fixing Preparation of Platform for Erection of Girders Temporary Staging and Stools Fixing POT Bearing Fixing and Boxing Precast Girder Erection (13 Nos.) Diaphragm Bottom Shuttering Diaphragm Reinforcement Fixing Diaphragm Side Shutter Fixing Diaphragm Checking Diaphragm Concreting Infill Slab Placing Deck - Rebar Fixing Deck - Checking Deck - Concreting Deck - Concrete Curing Crash Barrier Fixing Facia Fixing Preparation of Platform for Erection of Girders Temporary Staging and Stools Fixing POT Bearing Fixing and Boxing Precast Girder Erection (12 Nos.) Diaphragm Bottom Shuttering Diaphragm Reinforcement Fixing Diaphragm Side Shutter Fixing Diaphragm Checking Diaphragm Concreting Infill Slab Placing Deck - Rebar Fixing Deck - Checking Deck - Concreting Deck - Concrete Curing Crash Barrier Fixing Facia Fixing Preparation of Platform for Erection of Girders Temporary Staging and Stools Fixing POT Bearing Fixing and Boxing Precast Girder Erection (12 Nos.) Diaphragm Bottom Shuttering Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 1d 20-Sep-11 1d 21-Sep-11 15d 22-Sep-11 4d 29-Sep-11 3d 04-Oct-11 45d 21-Aug-11 2d 21-Aug-11 2d 23-Aug-11 1d 25-Aug-11 5d 27-Aug-11 2d 01-Sep-11 3d 04-Sep-11 2d 07-Sep-11 1d 10-Sep-11 1d 11-Sep-11 5d 12-Sep-11 4d 18-Sep-11 1d 22-Sep-11 1d 24-Sep-11 15d 25-Sep-11 4d 02-Oct-11 3d 06-Oct-11 45d 23-Aug-11 2d 23-Aug-11 2d 25-Aug-11 1d 28-Aug-11 5d 29-Aug-11 2d 04-Sep-11 3d 06-Sep-11 2d 10-Sep-11 1d 12-Sep-11 1d 13-Sep-11 5d 14-Sep-11 4d 20-Sep-11 1d 25-Sep-11 1d 26-Sep-11 15d 27-Sep-11 4d 04-Oct-11 3d 09-Oct-11 45d 25-Aug-11 2d 25-Aug-11 2d 28-Aug-11 1d 30-Aug-11 5d 31-Aug-11 2d 06-Sep-11 Finish Jan F 20-Sep-11 21-Sep-11 09-Oct-11 03-Oct-11 06-Oct-11 11-Oct-11 22-Aug-11 24-Aug-11 25-Aug-11 31-Aug-11 03-Sep-11 06-Sep-11 08-Sep-11 10-Sep-11 11-Sep-11 17-Sep-11 21-Sep-11 22-Sep-11 24-Sep-11 11-Oct-11 05-Oct-11 09-Oct-11 13-Oct-11 24-Aug-11 27-Aug-11 28-Aug-11 03-Sep-11 05-Sep-11 08-Sep-11 11-Sep-11 12-Sep-11 13-Sep-11 19-Sep-11 24-Sep-11 25-Sep-11 26-Sep-11 13-Oct-11 08-Oct-11 11-Oct-11 16-Oct-11 27-Aug-11 29-Aug-11 30-Aug-11 05-Sep-11 07-Sep-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Span - 04 (Athaibah Side) Side

21-Aug-11

11-Oct-11

Span - 05 (Ghala Side) Side

23-Aug-11

13-Oct-11

Span - 05 (Athaibah Side) Side

25-Aug-11

16-Oct-11

Page 108 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-A-S5-1050 WB-A-S5-1060 WB-A-S5-1070 WB-A-S5-1080 WB-A-S5-1090 WB-A-S5-1100 WB-A-S5-1110 WB-A-S5-1120 WB-A-S5-1130 WB-A-S5-1140 WB-A-S5-1150 Activity Name Diaphragm Reinforcement Fixing Diaphragm Side Shutter Fixing Diaphragm Checking Diaphragm Concreting Infill Slab Placing Deck - Rebar Fixing Deck - Checking Deck - Concreting Deck - Concrete Curing Crash Barrier Fixing Facia Fixing

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 3d 08-Sep-11 2d 12-Sep-11 1d 14-Sep-11 1d 15-Sep-11 5d 17-Sep-11 4d 22-Sep-11 1d 27-Sep-11 1d 28-Sep-11 15d 29-Sep-11 4d 06-Oct-11 3d 11-Oct-11 64d 17-Sep-11 55d 17-Sep-11 1d 17-Sep-11 2d 18-Sep-11 2d 20-Sep-11 2d 22-Sep-11 1d 25-Sep-11 15d 26-Sep-11 3d 16-Nov-11 58d 17-Sep-11 1d 17-Sep-11 2d 18-Sep-11 2d 20-Sep-11 2d 22-Sep-11 1d 25-Sep-11 15d 26-Sep-11 3d 20-Nov-11 46d 04-Oct-11 1d 04-Oct-11 2d 05-Oct-11 2d 08-Oct-11 2d 10-Oct-11 1d 12-Oct-11 15d 13-Oct-11 3d 23-Nov-11 47d 06-Oct-11 1d 06-Oct-11 2d 08-Oct-11 2d 10-Oct-11 2d 12-Oct-11 1d 15-Oct-11 15d 17-Oct-11 3d 27-Nov-11 75d 29-Sep-11 Finish Jan F 11-Sep-11 13-Sep-11 14-Sep-11 15-Sep-11 21-Sep-11 26-Sep-11 27-Sep-11 28-Sep-11 16-Oct-11 10-Oct-11 13-Oct-11 29-Nov-11 19-Nov-11 17-Sep-11 19-Sep-11 21-Sep-11 24-Sep-11 25-Sep-11 12-Oct-11 19-Nov-11 22-Nov-11 17-Sep-11 19-Sep-11 21-Sep-11 24-Sep-11 25-Sep-11 12-Oct-11 22-Nov-11 26-Nov-11 04-Oct-11 06-Oct-11 09-Oct-11 11-Oct-11 12-Oct-11 30-Oct-11 26-Nov-11 29-Nov-11 06-Oct-11 09-Oct-11 11-Oct-11 13-Oct-11 15-Oct-11 02-Nov-11 29-Nov-11 25-Dec-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

APPROACH SLAB
Approach Slab (SEEB - GHALA) WB-A-ASG-1000 WB-A-ASG-1010 WB-A-ASG-1020 WB-A-ASG-1030 WB-A-ASG-1040 WB-A-ASG-1050 WB-A-ASG-1060 WB-A-ASA-1000 WB-A-ASA-1010 WB-A-ASA-1020 WB-A-ASA-1030 WB-A-ASA-1040 WB-A-ASA-1050 WB-A-ASA-1060 WB-A-AMG-1000 WB-A-AMG-1010 WB-A-AMG-1020 WB-A-AMG-1030 WB-A-AMG-1040 WB-A-AMG-1050 WB-A-AMG-1060 WB-A-AMA-1000 WB-A-AMA-1010 WB-A-AMA-1020 WB-A-AMA-1030 WB-A-AMA-1040 WB-A-AMA-1050 WB-A-AMA-1060 Excavation and Leveling Blinding / PCC Approach Slab - Rebar Fixing Approach Slab - Shuttering Fixing Approach Slab - Concreting Approach Slab Concrete - Curing Expansion Joint Excavation and Leveling Blinding / PCC Approach Slab - Rebar Fixing Approach Slab - Shuttering Fixing Approach Slab - Concreting Approach Slab Concrete - Curing Expansion Joint Excavation and Leveling Blinding / PCC Approach Slab - Rebar Fixing Approach Slab - Shuttering Fixing Approach Slab - Concreting Approach Slab Concrete - Curing Expansion Joint Excavation and Leveling Blinding / PCC Approach Slab - Rebar Fixing Approach Slab - Shuttering Fixing Approach Slab - Concreting Approach Slab Concrete - Curing Expansion Joint

17-Sep-11 17-Sep-11

29-Nov-11 19-Nov-11

Approach Slab (SEEB - ATHAIBAH)

17-Sep-11

22-Nov-11

Approach Slab (MUSCAT - GHALA)

04-Oct-11

26-Nov-11

Approach Slab (MUSCAT - ATHAIBAH)

06-Oct-11

29-Nov-11

MISCELLANEOUS WORKS
Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary

29-Sep-11 TASK filter: All Activities

25-Dec-11

Page 109 of 115

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID WB-D-WPW-1000 WB-M-SHR-1000 WB-M-SPC-1000 Activity Name Water Proofing for Bridge Deck Slab Steel Hand Rail Fixing Special Coating - Painting

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 15d 29-Sep-11 7d 30-Nov-11 15d 08-Dec-11 585d 01-Jun-10 149d 01-Jun-10 Finish Jan F 16-Oct-11 07-Dec-11 25-Dec-11 12-Apr-12 21-Nov-10 22-Jul-10 29-Jul-10 15-Aug-10 08-Aug-10 21-Sep-10 23-Aug-10 07-Sep-10 08-Sep-10 28-Sep-10 29-Sep-10 04-Oct-10 12-Oct-10 17-Oct-10 27-Oct-10 21-Nov-10 19-Jan-11 20-Sep-10 27-Sep-10 13-Oct-10 06-Oct-10 20-Nov-10 21-Oct-10 06-Nov-10 07-Nov-10 27-Nov-10 28-Nov-10 02-Dec-10 11-Dec-10 15-Dec-10 26-Dec-10 19-Jan-11 20-Mar-11 18-Nov-10 25-Nov-10 12-Dec-10 05-Dec-10 18-Jan-11 20-Dec-10 04-Jan-11 05-Jan-11 28-Sep-10 31-Jul-10 01-Jun-10 01-Jun-10 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

ROAD WORKS
Road Section - 09
RW-S09-R000 RW-S09-R020 RW-S09-R040 RW-S09-R060 RW-S09-R080 RW-S09-R100 RW-S09-R120 RW-S09-R140 RW-S09-R160 RW-S09-R180 RW-S09-R200 RW-S09-R220 RW-S09-R240 RW-S09-R260 RW-S09-R280 Utilities Identification and Relocation & Laying Trees and Land Scape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Critical Remaining Work Milestone Summary

12-Apr-12 21-Nov-10

45d 01-Jun-10 6d 24-Jul-10 14d 31-Jul-10 7d 01-Aug-10 45d 01-Aug-10 7d 16-Aug-10 18d 18-Aug-10 14d 24-Aug-10 7d 21-Sep-10 1d 29-Sep-10 4d 30-Sep-10 1d 12-Oct-10 4d 13-Oct-10 9d 18-Oct-10 30d 18-Oct-10 149d 31-Jul-10 45d 31-Jul-10 6d 21-Sep-10 14d 28-Sep-10 7d 29-Sep-10 45d 29-Sep-10 7d 14-Oct-10 18d 17-Oct-10 14d 23-Oct-10 7d 20-Nov-10 1d 28-Nov-10 4d 29-Nov-10 1d 11-Dec-10 4d 12-Dec-10 9d 16-Dec-10 30d 16-Dec-10 149d 28-Sep-10 45d 28-Sep-10 6d 20-Nov-10 14d 27-Nov-10 7d 28-Nov-10 45d 28-Nov-10 7d 13-Dec-10 18d 15-Dec-10 14d 21-Dec-10

Road Section - 10
RW-S10-R000 RW-S10-R020 RW-S10-R040 RW-S10-R060 RW-S10-R080 RW-S10-R100 RW-S10-R120 RW-S10-R140 RW-S10-R160 RW-S10-R180 RW-S10-R200 RW-S10-R220 RW-S10-R240 RW-S10-R260 RW-S10-R280

19-Jan-11

Road Section - 11
RW-S11-R000 RW-S11-R020 RW-S11-R040 RW-S11-R060 RW-S11-R080 RW-S11-R100 RW-S11-R120 RW-S11-R140 Remaining Level of Effort Actual Work Remaining Work

20-Mar-11

Page 110 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID RW-S11-R160 RW-S11-R180 RW-S11-R200 RW-S11-R220 RW-S11-R240 RW-S11-R260 RW-S11-R280 RW-S12-R000 RW-S12-R020 RW-S12-R040 RW-S12-R060 RW-S12-R080 RW-S12-R100 RW-S12-R120 RW-S12-R140 RW-S12-R160 RW-S12-R180 RW-S12-R200 RW-S12-R220 RW-S12-R240 RW-S12-R260 RW-S12-R280 Activity Name Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 7d 18-Jan-11 1d 26-Jan-11 4d 27-Jan-11 1d 08-Feb-11 4d 09-Feb-11 9d 14-Feb-11 30d 14-Feb-11 149d 27-Nov-10 45d 27-Nov-10 6d 18-Jan-11 14d 25-Jan-11 7d 26-Jan-11 45d 26-Jan-11 7d 10-Feb-11 18d 13-Feb-11 14d 19-Feb-11 7d 19-Mar-11 1d 27-Mar-11 4d 28-Mar-11 1d 09-Apr-11 4d 10-Apr-11 9d 14-Apr-11 30d 14-Apr-11 149d 25-Jan-11 45d 25-Jan-11 6d 19-Mar-11 14d 26-Mar-11 7d 27-Mar-11 45d 27-Mar-11 7d 11-Apr-11 18d 13-Apr-11 14d 19-Apr-11 7d 17-May-11 1d 25-May-11 4d 26-May-11 1d 07-Jun-11 4d 08-Jun-11 9d 13-Jun-11 30d 13-Jun-11 149d 26-Mar-11 45d 26-Mar-11 6d 17-May-11 14d 24-May-11 7d 25-May-11 45d 25-May-11 Finish Jan F 25-Jan-11 26-Jan-11 31-Jan-11 08-Feb-11 13-Feb-11 23-Feb-11 20-Mar-11 18-May-11 17-Jan-11 24-Jan-11 09-Feb-11 02-Feb-11 19-Mar-11 17-Feb-11 05-Mar-11 06-Mar-11 26-Mar-11 27-Mar-11 31-Mar-11 09-Apr-11 13-Apr-11 24-Apr-11 18-May-11 17-Jul-11 17-Mar-11 24-Mar-11 10-Apr-11 03-Apr-11 17-May-11 18-Apr-11 03-May-11 04-May-11 24-May-11 25-May-11 30-May-11 07-Jun-11 12-Jun-11 22-Jun-11 17-Jul-11 14-Sep-11 16-May-11 23-May-11 08-Jun-11 01-Jun-11 16-Jul-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Road Section - 12, 12 A, 12 B & 12 C A

27-Nov-10

18-May-11

Road Section - 13
RW-S13-R000 RW-S13-R020 RW-S13-R040 RW-S13-R060 RW-S13-R080 RW-S13-R100 RW-S13-R120 RW-S13-R140 RW-S13-R160 RW-S13-R180 RW-S13-R200 RW-S13-R220 RW-S13-R240 RW-S13-R260 RW-S13-R280

25-Jan-11

17-Jul-11

Road Section - 14
RW-S14-R000 RW-S14-R020 RW-S14-R040 RW-S14-R060 RW-S14-R080 Remaining Level of Effort Actual Work Remaining Work

26-Mar-11

14-Sep-11

Page 111 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID RW-S14-R100 RW-S14-R120 RW-S14-R140 RW-S14-R160 RW-S14-R180 RW-S14-R200 RW-S14-R220 RW-S14-R240 RW-S14-R260 RW-S14-R280 Activity Name Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 7d 09-Jun-11 18d 12-Jun-11 14d 18-Jun-11 7d 16-Jul-11 1d 24-Jul-11 4d 25-Jul-11 1d 06-Aug-11 4d 07-Aug-11 9d 11-Aug-11 30d 11-Aug-11 149d 24-May-11 45d 24-May-11 6d 16-Jul-11 14d 23-Jul-11 7d 24-Jul-11 45d 24-Jul-11 7d 08-Aug-11 18d 10-Aug-11 14d 16-Aug-11 7d 13-Sep-11 1d 21-Sep-11 4d 22-Sep-11 1d 04-Oct-11 4d 05-Oct-11 9d 10-Oct-11 30d 10-Oct-11 371d 25-Jan-11 45d 25-Jan-11 6d 19-Mar-11 14d 26-Mar-11 7d 27-Mar-11 45d 27-Mar-11 7d 11-Apr-11 18d 13-Apr-11 14d 19-Apr-11 7d 17-May-11 1d 25-May-11 4d 26-May-11 1d 21-Feb-12 4d 22-Feb-12 9d 27-Feb-12 30d 27-Feb-12 321d 26-Mar-11 45d 26-Mar-11 6d 17-May-11 Finish Jan F 16-Jun-11 02-Jul-11 03-Jul-11 23-Jul-11 24-Jul-11 28-Jul-11 06-Aug-11 10-Aug-11 21-Aug-11 14-Sep-11 13-Nov-11 14-Jul-11 21-Jul-11 07-Aug-11 31-Jul-11 13-Sep-11 15-Aug-11 30-Aug-11 31-Aug-11 20-Sep-11 21-Sep-11 26-Sep-11 04-Oct-11 09-Oct-11 19-Oct-11 13-Nov-11 01-Apr-12 17-Mar-11 24-Mar-11 10-Apr-11 03-Apr-11 17-May-11 18-Apr-11 03-May-11 04-May-11 24-May-11 25-May-11 30-May-11 21-Feb-12 26-Feb-12 07-Mar-12 01-Apr-12 02-Apr-12 16-May-11 23-May-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Road Section - 15
RW-S15-R000 RW-S15-R020 RW-S15-R040 RW-S15-R060 RW-S15-R080 RW-S15-R100 RW-S15-R120 RW-S15-R140 RW-S15-R160 RW-S15-R180 RW-S15-R200 RW-S15-R220 RW-S15-R240 RW-S15-R260 RW-S15-R280 RW-S04-R000 RW-S04-R020 RW-S04-R040 RW-S04-R060 RW-S04-R080 RW-S04-R100 RW-S04-R120 RW-S04-R140 RW-S04-R160 RW-S04-R180 RW-S04-R200 RW-S04-R220 RW-S04-R240 RW-S04-R260 RW-S04-R280 RW-S03-R000 RW-S03-R020 Remaining Level of Effort Actual Work Remaining Work

24-May-11

13-Nov-11

Road Section - 04 (Flyover (Flyover)

25-Jan-11

01-Apr-12

Road Section - 03 (Seeb Side Ramp) Ramp

26-Mar-11

02-Apr-12

Page 112 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID RW-S03-R040 RW-S03-R060 RW-S03-R080 RW-S03-R100 RW-S03-R120 RW-S03-R140 RW-S03-R160 RW-S03-R180 RW-S03-R200 RW-S03-R220 RW-S03-R240 RW-S03-R260 RW-S03-R280 RW-S05-R000 RW-S05-R020 RW-S05-R040 RW-S05-R060 RW-S05-R080 RW-S05-R100 RW-S05-R120 RW-S05-R140 RW-S05-R160 RW-S05-R180 RW-S05-R200 RW-S05-R220 RW-S05-R240 RW-S05-R260 RW-S05-R280 Activity Name Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Critical Remaining Work Milestone Summary

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 14d 24-May-11 7d 25-May-11 45d 25-May-11 7d 09-Jun-11 18d 12-Jun-11 14d 18-Jun-11 7d 16-Jul-11 1d 24-Jul-11 4d 25-Jul-11 1d 22-Feb-12 4d 23-Feb-12 9d 28-Feb-12 30d 28-Feb-12 325d 26-Mar-11 45d 26-Mar-11 6d 17-May-11 14d 24-May-11 7d 25-May-11 45d 25-May-11 7d 09-Jun-11 18d 12-Jun-11 14d 18-Jun-11 7d 16-Jul-11 1d 24-Jul-11 4d 25-Jul-11 1d 23-Feb-12 4d 28-Feb-12 9d 04-Mar-12 30d 04-Mar-12 149d 26-Mar-11 45d 26-Mar-11 6d 17-May-11 14d 24-May-11 7d 25-May-11 45d 25-May-11 7d 09-Jun-11 18d 12-Jun-11 14d 18-Jun-11 7d 16-Jul-11 1d 24-Jul-11 4d 25-Jul-11 1d 06-Aug-11 4d 07-Aug-11 9d 11-Aug-11 30d 11-Aug-11 Finish Jan F 08-Jun-11 01-Jun-11 16-Jul-11 16-Jun-11 02-Jul-11 03-Jul-11 23-Jul-11 24-Jul-11 28-Jul-11 22-Feb-12 27-Feb-12 08-Mar-12 02-Apr-12 07-Apr-12 16-May-11 23-May-11 08-Jun-11 01-Jun-11 16-Jul-11 16-Jun-11 02-Jul-11 03-Jul-11 23-Jul-11 24-Jul-11 28-Jul-11 23-Feb-12 03-Mar-12 13-Mar-12 07-Apr-12 14-Sep-11 16-May-11 23-May-11 08-Jun-11 01-Jun-11 16-Jul-11 16-Jun-11 02-Jul-11 03-Jul-11 23-Jul-11 24-Jul-11 28-Jul-11 06-Aug-11 10-Aug-11 21-Aug-11 14-Sep-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Road Section - 05 (Muscat Side Ramp) Ramp

26-Mar-11

07-Apr-12

Road Section - 02
RW-S02-R000 RW-S02-R020 RW-S02-R040 RW-S02-R060 RW-S02-R080 RW-S02-R100 RW-S02-R120 RW-S02-R140 RW-S02-R160 RW-S02-R180 RW-S02-R200 RW-S02-R220 RW-S02-R240 RW-S02-R260 RW-S02-R280 Remaining Level of Effort Actual Work Remaining Work

26-Mar-11

14-Sep-11

Page 113 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID Activity Name

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 149d 24-May-11 Finish Jan F 13-Nov-11 14-Jul-11 21-Jul-11 07-Aug-11 31-Jul-11 13-Sep-11 15-Aug-11 30-Aug-11 31-Aug-11 20-Sep-11 21-Sep-11 26-Sep-11 04-Oct-11 09-Oct-11 19-Oct-11 13-Nov-11 20-Dec-11 14-Jul-11 21-Jul-11 07-Aug-11 31-Jul-11 13-Sep-11 15-Aug-11 30-Aug-11 31-Aug-11 20-Sep-11 21-Sep-11 26-Sep-11 10-Nov-11 15-Nov-11 26-Nov-11 20-Dec-11 13-Nov-11 14-Jul-11 21-Jul-11 07-Aug-11 31-Jul-11 13-Sep-11 15-Aug-11 30-Aug-11 31-Aug-11 20-Sep-11 21-Sep-11 26-Sep-11 04-Oct-11 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

Road Section - 01
RW-S01-R000 RW-S01-R020 RW-S01-R040 RW-S01-R060 RW-S01-R080 RW-S01-R100 RW-S01-R120 RW-S01-R140 RW-S01-R160 RW-S01-R180 RW-S01-R200 RW-S01-R220 RW-S01-R240 RW-S01-R260 RW-S01-R280 RW-S06-R000 RW-S06-R020 RW-S06-R040 RW-S06-R060 RW-S06-R080 RW-S06-R100 RW-S06-R120 RW-S06-R140 RW-S06-R160 RW-S06-R180 RW-S06-R200 RW-S06-R220 RW-S06-R240 RW-S06-R260 RW-S06-R280 Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Critical Remaining Work Milestone Summary

M Apr M 24-May-11

S Oct N

D Jan F 13-Nov-11

J Jul

45d 24-May-11 6d 16-Jul-11 14d 23-Jul-11 7d 24-Jul-11 45d 24-Jul-11 7d 08-Aug-11 18d 10-Aug-11 14d 16-Aug-11 7d 13-Sep-11 1d 21-Sep-11 4d 22-Sep-11 1d 04-Oct-11 4d 05-Oct-11 9d 10-Oct-11 30d 10-Oct-11 181d 24-May-11 45d 24-May-11 6d 16-Jul-11 14d 23-Jul-11 7d 24-Jul-11 45d 24-Jul-11 7d 08-Aug-11 18d 10-Aug-11 14d 16-Aug-11 7d 13-Sep-11 1d 21-Sep-11 4d 22-Sep-11 1d 10-Nov-11 4d 12-Nov-11 9d 16-Nov-11 30d 16-Nov-11 149d 24-May-11 45d 24-May-11 6d 16-Jul-11 14d 23-Jul-11 7d 24-Jul-11 45d 24-Jul-11 7d 08-Aug-11 18d 10-Aug-11 14d 16-Aug-11 7d 13-Sep-11 1d 21-Sep-11 4d 22-Sep-11 1d 04-Oct-11

Road Section - 06 (Wadi Bridge Area) Area

24-May-11

20-Dec-11

Road Section - 07
RW-S07-R000 RW-S07-R020 RW-S07-R040 RW-S07-R060 RW-S07-R080 RW-S07-R100 RW-S07-R120 RW-S07-R140 RW-S07-R160 RW-S07-R180 RW-S07-R200 RW-S07-R220 Remaining Level of Effort Actual Work Remaining Work

24-May-11

13-Nov-11

Page 114 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.

Client: MUSCAT MUNICIPALITY


Activity ID RW-S07-R240 RW-S07-R260 RW-S07-R280 Activity Name Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Utilities Identification and Relocation & Laying Trees and LandScape Turfing Removal Excavation Kerb and Interlocking Pavers Removal Drainworks, Slope Protection & Rip Rap Subgrade Preparation Kerb Laying Sub Base Works Base Course Laying Prime Coat Spraying Bit. Base Course Laying Tack Coat Spraying Bit. Wearing Course Laying Interlocking Pavers Laying Soft Landscaping and Irrigation Works Highway Signs Road Marking Traffic Sign Illumination Traffic Signal Street Lighting Impact Attenuators Site Clearing and Handing Over

Contractor: LARSEN & TOUBRO (OMAN) LLC


Original Start Duration 4d 05-Oct-11 9d 10-Oct-11 30d 10-Oct-11 149d 23-Jul-11 45d 23-Jul-11 6d 13-Sep-11 14d 20-Sep-11 7d 21-Sep-11 45d 21-Sep-11 7d 06-Oct-11 18d 09-Oct-11 14d 15-Oct-11 7d 12-Nov-11 1d 20-Nov-11 4d 21-Nov-11 1d 03-Dec-11 4d 04-Dec-11 9d 08-Dec-11 30d 08-Dec-11 109d 08-Dec-11 45d 29-Jan-12 30d 04-Mar-12 20d 21-Mar-12 30d 04-Mar-12 60d 08-Dec-11 6d 21-Mar-12 30d 14-Apr-12 30d 14-Apr-12 Finish Jan F 09-Oct-11 19-Oct-11 13-Nov-11 11-Jan-12 12-Sep-11 19-Sep-11 05-Oct-11 28-Sep-11 12-Nov-11 13-Oct-11 29-Oct-11 30-Oct-11 19-Nov-11 20-Nov-11 24-Nov-11 03-Dec-11 07-Dec-11 18-Dec-11 11-Jan-12 12-Apr-12 20-Mar-12 07-Apr-12 12-Apr-12 07-Apr-12 15-Feb-12 27-Mar-12 17-May-12 17-May-12 M Apr M 2010 J Jul

Consultant: PARSONS INTERNATIONAL & COMPANY LLC


2011 J Jul 2012 M Apr M

S Oct N

D Jan F

M Apr M

S Oct N

D Jan F

J Jul

Road Section - 08
RW-S08-R000 RW-S08-R020 RW-S08-R040 RW-S08-R060 RW-S08-R080 RW-S08-R100 RW-S08-R120 RW-S08-R140 RW-S08-R160 RW-S08-R180 RW-S08-R200 RW-S08-R220 RW-S08-R240 RW-S08-R260 RW-S08-R280 RW-MI-R1000 RW-MI-R1100 RW-MI-R1200 RW-MI-R1300 RW-MI-R1400 RW-MI-R1500

23-Jul-11

11-Jan-12

Miscellaneous Works - All Sections

08-Dec-11

12-Apr-12

HANDING OVER
AT-HO-1000

14-Apr-12

17-May-12

Remaining Level of Effort Actual Work Remaining Work

Critical Remaining Work Milestone Summary

Page 115 of 115

TASK filter: All Activities

AL ATHAIBAH INTERCHANGE PROJECT - CONSTRUCTION PROGRAMME

07th JULY 2010


(c) Primavera Systems, Inc.