Issued: Version:
22.03.2006 F/23.03.2007
ABB Oy Distribution Automation P.O. Box 699 FI-65101 Vaasa FINLAND Tel. +358 10 2211
Fax. +358 10 224 1080 www.abb.com/substationautomation Protection and Control IED Manager Configuration and Engineering
PCM 600
Copyrights
The information in this document is subject to change without notice and should not be construed as a commitment by ABB Oy. ABB Oy assumes no responsibility for any errors that may appear in this document. In no event shall ABB Oy be liable for direct, indirect, special, incidental or consequential damages of any nature or kind arising from the use of this document, nor shall ABB Oy be liable for incidental or consequential damages arising from use of any software or hardware described in this document. This document and parts thereof must not be reproduced or copied without written permission from ABB Oy, and the contents thereof must not be imparted to a third party nor used for any unauthorized purpose. The software or hardware described in this document is furnished under a license and may be
14-03-2012
Page 2 of 90
used, copied, or disclosed only in accordance with the terms of such license. Copyright 2007 ABB Oy All rights reserved. Trademarks ABB is a registered trademark of ABB Group. All other brand or product names mentioned in this document may be trademarks or registered trademarks of their respective holders. Guarantee Please inquire about the terms of guarantee from your nearest ABB representative.
Protection and Control IED Manager Configuration and Engineering PCM 600
Introduction
Use of symbols Intended audience Document conventions
Protection and Control IED Manager Configuration and Engineering PCM 600
Use of symbols
This online help includes the following icons that point out safety-related conditions or other important information:
The caution icon indicates important information or warning related to the concept discussed in the text. It might indicate the presence of a hazard which could result in corruption of software or damage to equipment or property.
The information icon alerts the reader to relevant facts and conditions.
The tip icon indicates advice on, for example, how to design your project or how to use a certain function.
It should be understood that operation of damaged equipment could, under certain operational conditions, result in degraded process performance leading to information or property loss. Therefore, comply fully with all notices.
14-03-2012
Page 3 of 90
PCM 600
Intended audience
This online help is intended for operators, supervisors and administrators to support normal use of the product.
Protection and Control IED Manager Configuration and Engineering PCM 600
Document conventions
The following conventions are used for the presentation of material: The words in names of screen elements (for example, the title in the title bar of a dialog, the label for a field of a dialog box) are initially capitalized. Capital letters are used for the name of a keyboard key if it is labeled on the keyboard. For example, press the CTRL key. Although the Enter and Shift keys are not labeled they are written in capital letters, e.g. press ENTER. Lowercase letters are used for the name of a keyboard key that is not labeled on the keyboard. For example, the space bar, comma key and so on. Press CTRL+C indicates that you must hold down the CTRL key while pressing the C key (to copy a selected object in this case). Press ALT E C indicates that you press and release each key in sequence (to copy a selected object in this case). The names of push and toggle buttons are boldfaced. For example, click OK. The names of menus and menu items are boldfaced. For example, the File menu. The following convention is used for menu operations: Menu Name > Menu Item > Cascaded Menu Item. For example: select File > Open > New Project. The Start menu name always refers to the Start menu on the Windows Task Bar. System prompts/messages and user responses/input are shown in the Courier font. For example, if you enter a value out of range, the following message is displayed: Entered value is not valid. You may be told to enter the string MIF349 in a field. The string is shown as follows in the procedure: MIF349 Variables are shown using lowercase letters: sequence name Online Help instructions The online help includes three different tabbed pages: Contents, Index and Search. You can see the structure of the online help on the Contents tab. By expanding and collapsing the subentries, you can find the certain topic. The Index tab shows index words that help you to find information easily. Double-click an index word to display the topic related to the word. If there are more than one topic related to the index word, the online help displays the Topics Found dialog where you can select the
14-03-2012
Page 4 of 90
right topic. You can also find information with the single word search on the Search tab. Type the word or words in the search box and press ENTER or click List Topics. The online help lists the topics related to the search. Double-click the right topic to see the content. The cross-references used in the text include links to other topics where you can find related information.
Protection and Control IED Manager Configuration and Engineering PCM 600
Product overview
This online help provides thorough information on the Protection and Control IED Manager PCM 600 and the central concepts related to it. In this online help, you will find information on installed tool components and a description of the basic operations. PCM 600 offers all the necessary functionality to work throughout all stages of the IED life cycle: Planning Engineering Commissioning Operation and disturbance handling Functional analysis With the individual tool components you can perform different tasks and functions and control the whole substation. PCM 600 can operate with many different topologies depending on customer needs. The following sections describe the connection types.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 5 of 90
14-03-2012
Page 6 of 90
2. Click Login to proceed or Exit to cancel. After logging off, the Login dialog is shown again. You can login again by typing the user name and password in the Login dialog. To logoff refer to Logoff PCM 600. If PCM 600 is started for the first time, the Login dialog is not shown, because the user authentication is disabled by default.
When the user authentication is disabled, no login is performed and the user is given full rights. For more information about the user authentication, refer to Selecting authentication method.
PCM 600
Opening help
PCM 600 software contains online help to support normal use of the product. Pressing F1 opens an instructive help on an active context, for example, to get information about activating the user authentication. Select Tools > Options > System Settings first and then select the User Authentication and press F1 to open the help description of the selected parameter. You can also open the online help by selecting Help > Contents to search helpful information when working with the tool. For the instruction on how to use the online help, refer to Document conventions. In some dialogs, there is a Help button. Click the Help button to see the context specific help.
14-03-2012
Page 7 of 90
PCM 600
14-03-2012
Page 8 of 90
1. Right-click the mouse in the Project Explorer window to open a shortcut menu. 2. Select Communication to open the Communication tab. 3. Redo the steps 1 and 2 to show and hide the structures. To open the different tabs, select or clear the checked commands from the shortcut menu. The setting is not stored to the permanent memory. It means that when the you start PCM 600 the next time, only the Plant Structure tab is displayed.
Protection and Control IED Manager Configuration and Engineering PCM 600
Opening documentation
You can view the available documentation for the devices shown in the object tree, if the object type supports this feature. To view the documentation: 1. Right-click the specific object in the Project Explorer window. 2. Select Documentation from the shortcut menu and select the appropriate manual to view.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 9 of 90
SCL Import/Export Signal Matrix Graphical Display Editor Disturbance Handling Parameter Setting Modem Dial-Up Signal Monitoring Event Viewer Reporting
Protection and Control IED Manager Configuration and Engineering PCM 600
Creating project
Creating a project requires a definition of new project data and configuration of the project. During the project creation, the database is created and the corresponding project is added under the selected computer in the Open Project window.
14-03-2012
Page 10 of 90
To create a new project: 1. Open the project management by selecting File > Open/Manage Project. 2. Select the computer or network where you want the project to be created from the Currently available projects box. 3. Click New Project on the left side of the dialog to open the New Project dialog. 4. Type the name for the project to Project name box. 5. Type the description of the project (optional). 6. Select the Include example configuration check box, if you want to create a new project based on the default configuration defined internally in PCM 600. Otherwise, an empty project is created. 7. Click Create to proceed or Cancel to restore the changes made.
Protection and Control IED Manager Configuration and Engineering PCM 600
Opening project
To open an existing project: 1. Open the project management by selecting File > Open/Manage Project. 2. Select the project from the Currently available projects box. 3. Click Open. The structure of the selected project is displayed in the Project Explorer's object tree. The child nodes are displayed when the parent node is expanded.
Protection and Control IED Manager Configuration and Engineering PCM 600
Closing project
To close an existing project select File > Close Project from the main menu bar and all the running tool components close. PCM 600 disconnects the project database and the project related windows.
Protection and Control IED Manager Configuration and Engineering PCM 600
Copying project
To copy an existing project:
14-03-2012
Page 11 of 90
1. Open the project management by selecting File > Open/Manage Project. 2. Select the project from Currently available projects box. 3. Copy the project by using the shortcut keystrokes CTRL+C or with the shortcut menu command. 4. Paste the project to a new location. You can use the shortcut keystroke CTRL+V or shortcut menu command. If the target computer is same as the source computer, the copied project is renamed automatically. If the target computer is some network computer that already contains a project on the same name, PCM 600 asks to confirm the overwriting. You can copy an existing project to some other location. The copying of the project includes the project data, configuration, settings and the process generated data related to the selected project, that is the data specific for the tool components.
The transfer of project data between two stand alone PCM 600 must be done by importing and exporting projects. For more information on importing and exporting projects, refer to Importing project and Exporting project.
PCM 600
Moving project
To move an existing project: 1. Open the project management by selecting File > Open/Manage Project. 2. Select the project from Currently available projects box. 3. Move the project by dragging and dropping or with the appropriate keystrokes (CTRL+X and CTRL+V) or with the shortcut menu commands to another location. You can move an existing project to an other location (to another or to the same computer). The project data, configuration, settings and the process generated data related to the selected project, that is the data specific for the tool components, are included in the moved file.
The moving of project data between two stand alone PCM 600 must be done by importing and exporting projects. For more information on importing and exporting projects, refer to Importing project and Exporting project.
PCM 600
14-03-2012
Page 12 of 90
Renaming project
To rename an existing project: 1. Open the project management by selecting File > Open/Manage Project. 2. Right-click the project in the Currently available projects box. 3. Select Rename from the shortcut menu to type a new name for the project.
Protection and Control IED Manager Configuration and Engineering PCM 600
Deleting project
To delete an existing project: 1. 2. 3. 4. Open the project management by selecting File > Open/Manage Project. Select the project from the Currently available projects box. Right-click the project and select Delete from the shortcut menu. Confirm the deleting by clicking Yes.
The deletion of an existing project deletes all project related data as well.
Protection and Control IED Manager Configuration and Engineering PCM 600
Exporting project
To export an existing project: 1. 2. 3. 4. Open the project management by selecting File > Open/Manage Project. Select the project from the Currently available projects box. Right-click the project to open the shortcut menu. Select Export Project from the shortcut menu to open the Create target file for the project export dialog. 5. Browse the target location and type the name for the exported file.
Exporting a project enables you to transfer project data between the PCM 600 based systems via different media, for instance in CD-ROM. The source and target computers do not have to be connected to the same network, thus data between two stand-alone computers can be transferred. All project related data is compressed and saved to one file, which is named and located according to the definitions.
Protection and Control IED Manager PCM 600
14-03-2012
Page 13 of 90
Importing project
To import an existing project data: 1. Open the project management by selecting File > Open/Manage Project. 2. If the project is imported to the local computer, the Projects on my computer node is selected. Otherwise select one of network computers under the Projects on network node. 3. Right-click the selected node to open the shortcut menu. 4. Select Import from the shortcut menu to open the Import project dialog. 5. Browse the location and type the name for the imported file. Importing a project enables you to transfer project data between the PCM 600 based systems via different media, for instance in CD-ROM. The source and target computers do not have to be connected to the same network, thus data between two stand alone computers can be transferred. A new project is created under the selected node and all the project related data from the imported file is copied to the defined location.
Protection and Control IED Manager Configuration and Engineering PCM 600
Converting project
If the project is created with the previous version of PCM 600, the project conversion wizard is opened. After the project is converted, it can be used with the latest version of PCM 600. When the project conversion wizard is open, follow the instructions and click Next. After reviewing the summary, click Next to proceed the conversion. During the conversion, the upper progress bar shows the total progress and the lower progress bar shows the progress of the current phase. Finish the conversion and close the dialog by clicking Finish.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 14 of 90
by using the SCD file (System Configuration Description). The SCD file follows the IEC 618506 standard. To import the project data: 1. Open the project management by selecting File > Open/Manage Project. 2. Select the project from the Currently available projects box. If the project is imported to the local computer, select the Projects on my computer node. Otherwise, select one of the network computers under the Projects on network node. 3. Right-click the project and select Import from the shortcut menu to open the Import project dialog. 4. Browse the target location and type the name for the exported file. A new project is created under the selected node and all the project related data from the imported file is copied to the defined location.
Protection and Control IED Manager Configuration and Engineering PCM 600
After making changes to the user rights, the PCM 600 must be restarted for taking the new settings in to use.
PCM 600
14-03-2012
Page 15 of 90
> Options. With the user management options you can decide the permissions a certain user has. If the user does not have permission for certain operations, these operations will either be shown and disabled, or simply removed all together.
Protection and Control IED Manager Configuration and Engineering PCM 600
Changing password
Password
14-03-2012
Page 16 of 90
Cannot be empty Starts and ends with an alphabetic character Contains at least one special character Is at least 8 characters long Contains at least one number Contains at least one uppercase character Contains at least one lowercase character To change the password: 1. 2. 3. 4. 5. 6. Start the User Management by selecting Tools > Options. Select User Manager folder. Click Set Password under User Preferences to open Set Password dialog. Enter the old password. Enter the new password. Reenter the new password for confirmation and click OK.
When you change the authentication password, the validity of password is checked and a new password is saved to the database.
Protection and Control IED Manager Configuration and Engineering PCM 600
System engineer can change the password used by the system to access SQL Server and databases. This password is not used by any PCM 600 user but by PCM 600 itself.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 17 of 90
The user management of PCM 600 is based on the users and the user categories. All users have a user account for PCM 600. Each user account is mapped to one user category, which defines the permission to access certain functions. There are three default user categories: System Engineer acts as an administrator for the PCM 600 system and has full rights to perform any function and can define the user accounts. Operator can perform certain simple tasks. Application Engineer can access most of the functions. The members of System Engineer user category can create new user categories. The name of the user category must be unique.
Protection and Control IED Manager Configuration and Engineering PCM 600
1. 2. 3. 4.
14-03-2012
Page 18 of 90
14-03-2012
Page 19 of 90
method field. Windows authentication use current user's Windows account to determine if the user is allowed to login to PCM 600 or not. If this authentication is selected, it is checked that all the PCM 600 user accounts contain the Windows account name, which is used to log the user in. The PCM 600 authentication uses user name and password specified in the user management of PCM 600. This information must then be provided in the Login dialog.
Protection and Control IED Manager Configuration and Engineering PCM 600
Creating user
You can create a new user to PCM 600 with the following information: User name (mandatory) Real name of the user User category You can login automatically using your Windows account. You can define multiple Windows account names for one PCM 600 account. The Windows account names are separated by semicolon (;). These Windows account names are only used for login if the administrator has enabled Windows authentication, see Selecting authentication method. Example DOMAIN1\USER1;DOMAIN4\USER2
14-03-2012
Page 20 of 90
To create a new user: Start the user management by selecting Tools > Options. Select User Manager folder. Click Add New User under User Profile field. An Add New User dialog is displayed. Type a user name and real name for the new user and select the right user category. The user name must be at least three characters long. The real name makes it easier to find users of PCM 600. 5. Click OK to confirm. The new user is created. Unless the new user name is no member of any user category, it has no permissions to any PCM 600 functions.
Protection and Control IED Manager Configuration and Engineering PCM 600
1. 2. 3. 4.
Deleting user
To delete a user: 1. 2. 3. 4. Start the User Management by selecting Tools > Options. Select User Manager folder. Select the right user name from the User Name drop-down list. Click Delete User under the User Profile field.
14-03-2012
Page 21 of 90
PCM 600
Adding object
You can add new objects to the Plant Structure tab by dragging, by using a shortcut menu or from the New Object dialog. To drag: 1. Select the object type from the Object Types window. 2. Drag the object to the structure with the mouse. 3. Release the mouse in the appropriate place. To use the shortcut menu: 1. Select the object from the Plant Structure tab. 2. Right-click the object to see the shortcut menu. 3. Select the right object type from the shortcut menu to fit in the structure. The shortcut menu lists only the objects that can be added under the selected object. If you add several objects, it is easy to use the New Object dialog. To use the New Object dialog: 1. Right-click the object and select New > New from the shortcut menu to open the New Object dialog. 2. Select the object you want to add. 3. Click Create or double-click the object to add the selected object to the object tree. If you select the Freeze structure focus to current location option the focus in the structure will be unchangeable while adding the new object. Otherwise, the focus is moved to the added object.
Protection and Control IED Manager Configuration and Engineering PCM 600
Naming IEDs
The IEDs in the Project Explorer's window Plant Structure must have unique naming. If there are several IEDs installed under different OPC servers, ensure that the IEDs have unique names. Using unique names applies to Substation, Voltage Level and Bay objects as well. There should not be several substations with the same name in the project, neither several voltage
14-03-2012
Page 22 of 90
levels with the same name under the same substation nor bays with the same name within the same voltage level. However, it is possible to have several voltage levels with the same name within different substations or bays, for example, you can build structures like Substation1\VoltageLevel1\Bay1 and Substation2\VoltageLevel1\Bay1 under the same project.
The identification of IEDs is based on the names of the IEDs. Using the same IED names under same directory path may cause problems in the SCL handling.
PCM 600
Deleting object
To delete an object from the object tree right-click the object to and select Delete from the shortcut menu.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 23 of 90
You can copy an object or move the object to another location in the object tree. These functions follow the typical windows principles; you can cut, copy and paste method or drag the objects. You can use the shortcut menu or the appropriate keystrokes.
Do not use the Communication tab, if you are not fully aware of how to use it.
PCM 600
14-03-2012
Page 24 of 90
PCM 600
14-03-2012
Page 25 of 90
14-03-2012
Page 26 of 90
PCM 600
General settings
In the General tab you can edit the general user management preferences of a specific IED. The user management settings that a specific IED provides are individual for every IED. You can, for example, define whether the users have to logon to an IED or not or restore the factory settings.
Protection and Control IED Manager Configuration and Engineering PCM 600
Note that a user profile must always belong to at least one user group.
To add a new user: 1. Click the icon under the Users field. A wizard opens. 2. Follow the instructions of the wizard to define a user name, password and user group. You have to select at least one user group where the defined user belongs. The user's profile can be seen under the User details field.
14-03-2012
Page 27 of 90
To add a user to a new user group: 1. Select the user from the Users list. 2. Select the new user group from the Add User to group drop-down list. 3. Click the icon. You can see in which groups the user belongs from the Member list. To delete an existing user: 1. Select the user from the Users list. 2. Click the icon under the Users field. To change the password: 1. Select the user from the Users list. 2. Click the icon under the Users field. 3. Type the old password ones and the new password twice for confirmation. The passwords can be saved to the project database or send directly to the IED.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 28 of 90
1. Select the IED function under the IED Functions field. 2. Select the new group from the Add Group drop-down list. 3. Click the icon. The new user group is shown in the Selected Groups list. To add a new permission of a specific function for a user group: 1. Select the IED function under the IED Functions field. 2. Select the user group from the Selected Groups list. 3. Define the permissions under the Permissions field by selecting the corresponding rights (Read, Write).
Protection and Control IED Manager Configuration and Engineering PCM 600
Saving password
Some of the IEDs or used protocols demand password to transmit data between an IED and PCM 600. If you want the program to remember the password, select the corresponding check box to save the password. Otherwise the Password dialog is displayed when ever the permission for data transmit is needed.
Protection and Control IED Manager Configuration and Engineering PCM 600
Communication Management
Starting Communication Management Signal selection view Copying signals between masters Configuration table view Saving communication data Writing communication data to the IED Reading communication data from the IED Printing a signal list Closing communication management Communication Management is used to configure the DNP 3.0 protocol for the IED. The configuration of DNP 3.0 is done based on the configuration made in the application configuration. Communication Management for DNP consists of two different views; the Signal Selection and the Configuration Table views, which are used to set up the DNP 3.0 protocol and the protocol-specific attributes. You can switch between these two views with the buttons on the toolbar.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 29 of 90
You can also change the signal index number in the master list. There are two ways to do this: Right-click the signal and select Set Index. To set the index for multiple signals, hold down the CTRL key and select multiple signals before right-clicking. You can move signal(s) up by clicking the button with an up arrow clicking the button with a down arrow . or down by
You can also remove signals from the master list. There are three ways to do this: Right-click the signal and select Delete. This will move the signal from the master list
14-03-2012
Page 30 of 90
to the list with available signals. To select multiple signals, hold down the CTRL key and select multiple signals before right-clicking. Select the signal and click the button with a left arrow . To select multiple signals, hold down the CTRL key and select multiple signals before clicking the arrow button. You can remove all signals from the master by clicking the button with two left arrows .
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 31 of 90
Note that the Save function is enabled only if data has been changed.
PCM 600
Note that your data automatically is saved when you start writing to the IED.
PCM 600
14-03-2012
Page 32 of 90
PCM 600
Parameter Setting
Starting Parameter Setting Setting parameters numerically Saving parameters Copying parameter values Pasting parameter values Restoring saved values Undoing Printing Reading parameters from IED Writing parameters to IED Modifying setting sheet Selecting parameter filter Selecting parameter layer Replacing values Displaying parameters Displaying parameter warnings Selecting setting group Displaying setting group parameters in matrix view Parameter Setting is used for the parameterization of IED units. The parameters can be set offline in a PC, and sent to the IED or received from the IED over a communication line. Once started, Parameter Setting will display parameter data for the selected node.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 33 of 90
Saving parameters
To save the changed parameter values select Save from the File menu. The operation writes the changed PC values (displayed as bold font) to the database.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 34 of 90
1. Select a parameter (PC Value) from the setting sheet. The selection becomes highlighted. 2. Select Edit > Copy to copy the parameter value to the clipboard. To copy multiple parameter values: 1. Select a parameter group from the setting sheet. The selection becomes highlighted. 2. Select Edit > Copy to copy the parameter values to the clipboard. To copy setting groups: 1. On the setting sheet, right-click any level header to open the shortcut menu. 2. Select source setting group. Selected level, including all setting group values, are copied to the clipboard.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 35 of 90
To restore a saved value: 1. Right-click a parameter row in the setting sheet. 2. Select Restore saved value from the shortcut menu. The saved value from the database is restored. To restore all saved values, select Edit > Restore all saved values. All changed values are replaced with saved values from the database.
Protection and Control IED Manager Configuration and Engineering PCM 600
Undoing
It is possible to undo parameter changes and parameter functions like multi paste, restore all saved values and replace all tool values with IED values. To undo the last action: 1. Right-click the object. 2. Select Undo from the shortcut menu to restore the old value from the database.
Protection and Control IED Manager Configuration and Engineering PCM 600
Printing
To print the parameters of current setting sheet: 1. Select File > Print to open the Print dialog. 2. Define the print options. 3. Click OK to print or Cancel to end the printing.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 36 of 90
1. Click Read parameters from IED toolbar button or select IED > Read parameters from IED to open the Read parameters from the IED dialog box. 2. Select one of the options under the Parameter range field to read from the IED: whole setting sheet, selected group or single parameter. 3. Select under Parameter options Copy IED values to PC values field. 4. Click OK to read the parameters or Cancel to end the operation. In case the reading of a single parameter fails, an error dialog is displayed. Continue by clicking one of the buttons in the dialog box: Click Retry to read the parameter again. Click Skip to skip the parameter. Click Skip all to continue the reading of parameters and automatically skip the possible parameters that fail. Click Cancel to end the reading procedure.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 37 of 90
Hiding or showing the parameters Hiding or showing the parameter columns Collapsing or expanding the parameter groups To hide and show parameters: 1. On the setting sheet, right-click the parameter group header to open a shortcut menu containing group parameters. 2. Select or clear the parameters from the setting sheet by clicking the corresponding parameter. To hide and show columns: 1. On the setting sheet, right-click the column header to open a shortcut menu containing columns. 2. Select or clear the columns from the setting sheet by clicking the corresponding column name. To collapse and expand parameter groups: Single group: Double-click the parameter group header in the setting sheet. Selected group + child groups: Select View > Group options > Expand/Collapse group + child groups or use the corresponding toolbar buttons.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 38 of 90
Replacing values
To replace a PC value with an IED value: 1. Right-click a parameter row in the setting sheet. 2. Select Replace PC value with IED value from the shortcut menu. The IED value is copied to the PC value field. To replace all PC values with IED values, select Edit > Replace all PC values with IED values. The PC values are replaced with IED values.
Protection and Control IED Manager Configuration and Engineering PCM 600
Displaying parameters
You can define whether to see only the parameters of the selected node or all the parameters of the selected node and its child nodes. Especially, if the number of parameters is high, selecting View > Browse options > Display only selected node is recommended. Browse options: Display only selected node
14-03-2012
Page 39 of 90
Display selected node + child nodes When this is done, the selection setting sheet is updated according to the selected browse option.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 40 of 90
Scheduler
Opening Scheduler Closing Scheduler Starting Task Manager Stopping Task Manager Adding task Viewing task configuration Configuring task Deleting task Creating job Saving job Viewing job configuration Configuring job Deleting job Activating task Interrupting task Using task filters Viewing event log Enabling task Disabling task The Scheduler is a system tool under PCM 600. With the Scheduler you can create and configure scheduled tasks and jobs. You can use the Scheduler to define scheduled tasks performing different functions at the defined times. A task and job set up a scheduled event, you cannot have one without the other. This will be explained more clearly later in this chapter. The Scheduler provides: Graphical User Interface (GUI) for creating and configuring scheduled tasks and jobs Control over Task Manager Information on task and job status The upper pane of Scheduler contains an object tree which includes the following nodes: Task Manager: Root node of the structure Task: Each node represents a task Job: Each node represents a job under a task. The object and system jobs have slightly different symbols.
14-03-2012
Page 41 of 90
A task configuration contains information on when the task should be run, project name, owner (that is, a user who created the task), purpose of the task and the jobs the task contains. The jobs are schedulable functions provided by the Scheduler client tools. The Client tools are tools which host one or more schedulable functions. The job functions are designed for a specific purpose (like getting disturbance recording from IED). A job consists of several attributes of which the most important are name, client tool name and job function name. A task contains one or several jobs. If there are several jobs under a task, the running order is the order in which the jobs reside under the task node in Scheduler. The task and job information defined in Scheduler are stored in the PCM 600 system database. The system database is also used for exchanging task and job information between the Task Manager and Scheduler. The jobs are run by Task Manager according to the schedule defined in the task configuration. Several tasks can be active at the same time. The number of simultaneous tasks depend on system resources (CPU speed, memory, and so on).
Protection and Control IED Manager Configuration and Engineering PCM 600
Opening Scheduler
To open Scheduler and to see the task data (tasks, jobs and their status) select Tools > Scheduler.
Protection and Control IED Manager Configuration and Engineering PCM 600
Closing Scheduler
To close Scheduler: 1. Save the modified task or job data before closing. 2. Click close in the upper right corner to close Scheduler. If you have any unsaved data, the program asks whether it should be saved before closing.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 42 of 90
To start Task Manager select Task Manager > Start Task Manager or right-click the Task Manager node and select Start Task Manager. Task Manager starts and the tasks are activated according to the data read from the permanent task storage. If some unexpected errors occur while starting the service, they are displayed in the Windows Event Viewer.
Protection and Control IED Manager Configuration and Engineering PCM 600
Adding task
To create a new task select Task / Jobs > Add Task or right-click the Task Manager node in Scheduler and select Add Task. The new task is added under the Task Manager node. You can name the task by clicking the selected task and typing the name. For creating new job, see Creating job. Example To set up the Task settings: 1. Click the Task node and select the Configuration tab. 2. Set Schedule to Once under the Scheduling field. 3. Set Start Date/Time option under the Start Condition field to a specific time for the Scheduler to start the task. 4. Click on the Task Manager node and click Yes to accept the settings. For more information on configuring the tasks, refer to Configuring task.
14-03-2012
Page 43 of 90
You can also create a new task and a new Object Job by dragging a specific object from the PCM 600 Plant Structure on the Task Manager node. The task and job are created automatically.
PCM 600
Save any unsaved task and job data before viewing the task configuration.
Configuring task
To configure a task: 1. Select the task. The task configuration is shown on the Configuration tab. If the task status is not Disabled select Task / Jobs > Disable task. 2. Define the following attributes: Schedule: Defines the schedule in which the task is activated. If no schedule is required choose None. Interval Days hh:mm:ss: If the schedule is Fixed Interval, the interval in days, hours, minutes and seconds can be defined here. Start Date/Time: Defines the point of time the task is activated for the first time. End Date/Time: Defines the point of time when the task is not activated any more. Note! Overrides the possible value of Number of Activations. Number of Activations: Defines how many times the task is activated. Note! Overrides the possible value of End Date/Time. Description: Optional user description of the task. 3. Click the green button to save the task configuration into database.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 44 of 90
Deleting task
To delete a task from the system database right-click the task and select Delete Task. The task and the jobs under it are deleted from the database.
Protection and Control IED Manager Configuration and Engineering PCM 600
Creating job
To create a System Job under an existing task, right-click a task and select Add System Job. To create an Object Job under an existing task: 1. Select the task. 2. Select an object from the PCM 600 Plant Structure (the object must have schedulable functions). 3. Drag the object on the selected task node or right-click the task and select Add Object Job. Example To set up the job settings: 1. 2. 3. 4. 5. Click the Job node. Select Configuration tab. Select Disturbance Handling from the Tool drop-down menu. Select Read New Recordings from the Job drop-down menu. Click the Task Manager node and click Yes to accept the settings.
For more information on setting the job configuration, refer to Configuring job.
You can also create a new task and a new Object Job by dragging a specific object from the PCM 600 Plant Structure on the Task Manager node. The task and job are created automatically.
PCM 600
Saving job
To save a changed job configuration click the green check button on the top of the Configuration tab. The job configuration is saved into database.
14-03-2012
Page 45 of 90
PCM 600
Configuring job
To configure a job: 1. Select the job. The job configuration is shown on the Configuration tab. If status of the task containing the job is not Disabled select Task / Jobs > Disable task. 2. Select the specific tool component from the Tool drop-down menu. 3. Select a job type from the Job drop-down menu. 4. Type the purpose of the job to the Description box. 5. Click the green button on Configuration tab to save the job configuration in the database.
Some of the job types may contain job type specific properties shown in Job Properties field. Give these properties the values as required.
Example Setting up a task for single operation for reading recordings and sending a report: 1. Click the Task node and set a new time for starting the task, refer to the previous example. 2. Click the Job node. 3. Select Read Recordings and Send Report from the Job drop-down menu. 4. Right-click the Task node and select Enable Task. When the task is performed and the jobs performed successfully, the status of the task and jobs becomes Completed. You can configure the recipients by selecting Disturbance Handling > Configuration. For more information on configuring the Disturbance Handling, refer to Defining settings. Example Setting up a task for single operation for reading recordings and sending a report after shutting down PCM 600:
14-03-2012
Page 46 of 90
1. Click the Task node and set a new time for starting the task, refer to the previous example. 2. Click the Job node. 3. Select Read Recordings and Send Report from the Job drop-down menu. 4. Right-click on the Task node and select Enable Task. 5. Shut down PCM 600. Although PCM 600 is shut down, the job should be completed as scheduled. You can configure the recipients by selecting Disturbance Handling > Configuration. For more information on configuring the Disturbance Handling, refer to Defining settings. Example You can set up Scheduler to run multiple tasks for a repeatable number of jobs. Setting up a task for multiple task operation for reading recordings and sending a report: 1. Click the Task node. 2. Select one of the menu items in the Schedule drop-down menu. 3. Save the setting by clicking some other node and accepting the settings or clicking the green button in the upper left corner of the Configuration tab. 4. Right-click on the Task node and select Enable Task.
Make sure that the job is set for the Disturbance Handling on the Configuration tab.
PCM 600
Deleting job
To delete a job from the system database right-click the job and select Delete Job. The job is deleted from the database.
Protection and Control IED Manager Configuration and Engineering PCM 600
Activating task
A task is activated in order to run the jobs under it. Task Manager activates tasks according to the schedule defined in the task configuration. Alternatively, you can activate a task outside the defined schedule. A task may contain one or several jobs. If there are several jobs under a task, the running order is the order the jobs reside under the task node. To activate a task manually outside the schedule:
14-03-2012
Page 47 of 90
1. Select None from the Schedule drop-down menu under the Scheduling field. 2. Make sure the Task Manager is running, refer to Starting Task Manager. 3. Right-click the task and select Enable Task. The task is now activated and the jobs under it are running. Example Setting up a task for single operation: Click the Task node Select the Configuration tab. Select Once from the Schedule drop-down menu under the Scheduling field. Select the Start Date/Time check box under the Start Condition field. Define the starting date and time by setting the correct values to the Start Date/Time boxes. 6. Save the setting by clicking some other node and accepting the settings, or by clicking the green button in the Configuration tab. To set up the Job settings: 1. 2. 3. 4. Click the Job node. Select Configuration tab. Select Read New Recordings from the Tool drop-down menu. Save the setting by clicking some other node and accepting the settings, or by clicking the green button in the Configuration tab.
PCM 600
1. 2. 3. 4. 5.
Interrupting task
An active task can be interrupted manually. This means that the currently running job is stopped and task is set to wait for the next scheduled activation (if any). To interrupt a task manually: 1. Select the active task you want to interrupt. 2. Right-click the Task node and select Interrupt Task. The jobs running under the task are stopped and the task is set into Waiting state, if it has scheduled activations in the future. The task is deactivated and dynamic task data is updated.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 48 of 90
or select Task Manager > Filter The available filters are: All Tasks: Shows all tasks within the PCM 600 system. Project Tasks: Shows tasks created under currently open project. User Tasks: Shows all tasks created by the current user. After selecting the filter the tasks are shown in the Scheduler's object tree.
Protection and Control IED Manager Configuration and Engineering PCM 600
Enabling task
14-03-2012
Page 49 of 90
Enabling a task includes it in the scheduling. This means that the task is activated according to the schedule defined in the task configuration. To enable a task: 1. Start Task Manager, see Starting Task Manager. 2. Select a task from the Scheduler's object tree. 3. Select Tasks / Jobs > Enable Task or right-click the task and select Enable Task. The task status changes and the Task Manager starts to activate the tasks according to the schedule.
Protection and Control IED Manager Configuration and Engineering PCM 600
Disabling task
Disabling a task takes it out of the scheduling. This means that the task is not activated according to the schedule defined in the task configuration. To disable a task: 1. Select a task from the Scheduler's object tree. 2. Select Tasks / Jobs > Disable Task or right-click the task and select Disable Task. The task status is changed in the Scheduler's object tree.
Protection and Control IED Manager Configuration and Engineering PCM 600
Disturbance Handling
Starting Disturbance Handling Reading available recordings from IED Processing uploaded recordings Importing and exporting recordings Arranging columns Creating report Saving PDF document Analyzing recordings with alternative tool Defining settings Structuring report manually The Disturbance Handling tool is used for uploading and processing disturbance files located in the specific IEDs. With the disturbance handling, you can process the disturbance data and create reports from this data. The reports can be distributed among the chosen clients. After creating a PDF report manually, save it on your computer and send it, for example by e-
14-03-2012
Page 50 of 90
mail, to the recipients. You can also distribute the reports automatically with the Scheduler. The Scheduler creates the reports and sends them out to the recipients, defined in the Disturbance Handling tool. For more information on Scheduler, see Scheduler.
Protection and Control IED Manager Configuration and Engineering PCM 600
It is not necessary to connect PCM 600 to an IED, you can work offline by using the uploaded recordings or by importing the recordings.
14-03-2012
Page 51 of 90
Defining settings. When there are recordings available, you can refresh the IED pane to collect the saved recordings and view them in the IED pane. Right-click on the Available Recordings in IED pane. If the recordings are listed, then by right-clicking again, you can perform the following operations: Get the recordings Refresh the recordings Select the recordings Clear the recordings Read the recordings Delete the recordings Manual trig Clear the LEDs Template editor Settings Copy
Protection and Control IED Manager Configuration and Engineering PCM 600
Getting recordings
Get Recordings Information retrieves information about the recordings that are available to be uploaded from the specific IED. The data displayed in the view after the Get Recordings Information command is pre-information about the data presented in the COMTRADE file. To get information about the available recordings: Select IED > Available Recordings in IED > Get Recordings Information. Click the Get IED Recordings Information toolbar button. Right-click the view and select Get Recordings Information from the shortcut menu.
Protection and Control IED Manager Configuration and Engineering PCM 600
Refreshing recordings
Refresh Recordings List collects the disturbances saved on the local disc. These disturbances are then displayed in the view for you to process. To force a refresh list: Click the Refresh Recordings List toolbar button.
14-03-2012
Page 52 of 90
Select IED > Recordings > Refresh List. Right-click the view and select Refresh List.
Protection and Control IED Manager Configuration and Engineering PCM 600
Selecting recordings
To select recordings: Select a row by right-clicking the recording and select Select Row. Select all the rows by right-clicking somewhere on the recordings and select Select All Rows. Select multiple rows manually by clicking the left border of the row and drag the mouse up or down to select the rows.
Protection and Control IED Manager Configuration and Engineering PCM 600
Clearing recordings
Clear List removes all the recording information from the view. To clear recordings: Select IED > Available Recordings in IED > Clear List. Right-click the view and select Clear List from the shortcut menu.
Clearing list removes only the recordings from the view. It does not remove anything from IED.
PCM 600
Deleting recordings
Delete Recording deletes all or a subset of recordings in a specified IED, physically and also from the recording view. A notification is received once the deletion of recording is complete.
14-03-2012
Page 53 of 90
To delete recordings: Select IED > Recordings > Delete Selected Recordings or IED > Available Recordings in IED > Delete All Recordings in IED. Right-click the view and select Delete Recording from the shortcut menu.
Protection and Control IED Manager Configuration and Engineering PCM 600
Reading recordings
Read All uploads all recordings from the specific IED to the Recordings view of the Disturbance Handling for processing. Read Selected Recordings in IED uploads the selected recordings to the Recordings view of the Disturbance Handling for processing, if there are new or selected recordings. You need at least medium user rights to perform the operation. To read selected recordings: 1. Select appropriate recordings in the view. 2. Select IED > Available Recordings in IED > Read Selected Recordings in IED To read all recordings, select IED > Available Recordings in IED > Read All.
Protection and Control IED Manager Configuration and Engineering PCM 600
Manual trig
Manual Trig is used to activate a specified IED to trigger true recordings. A notification is displayed, once the manual trig of recording is complete. The generated recordings are then available for upload. This feature can be useful during system verification. To trig manually: Select IED > Execute Manual Trig. Click the Execute Manual Trig toolbar button. Right-click the view and select Execute Manual Trig from the shortcut menu.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 54 of 90
Clearing LEDs
Clear LEDs switches off the LEDs for a specified IED. This is used to reset the status LEDs. To clear LEDs, select IED > Clear LEDs.
Protection and Control IED Manager Configuration and Engineering PCM 600
Template editor
The Template Editor is a tool for editing templates used by the Disturbance Handling tool. Its purpose is to encapsulate the complexity in a template. It is also possible to get a block preview of the disturbance document. The Template Editor has two main functions: Creating a new Template. Editing an existing Template. To start the Template Editor Select Customize > Template Editor. Right-click the Recordings view and select Template Editor from the shortcut menu. For more information about the Template editor, refer to Structuring report manually.
Protection and Control IED Manager Configuration and Engineering PCM 600
Settings
Settings opens the Disturbance Handling - Settings dialog. You need at least medium user rights to perform to operation. For more information on configuring recordings, refer to Defining settings.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 55 of 90
Copying
Copy copies the selected text objects.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 56 of 90
Arranging columns
You can arrange the columns in a certain order for you to have the most often used information first. To arrange the columns: Rearrange the column by dragging the column header to a new place over the other column headers. Undo the rearranging by selecting somewhere in the view and Undo Layout Change. Save the new column order settings by selecting somewhere in the view and select Save Layout Changes.
Protection and Control IED Manager Configuration and Engineering PCM 600
Creating report
The Disturbance Handling manages and benefits the disturbance recordings. The report templates can be created manually with Template Editor and the reports automatically with Report Viewer. To be able to create a report, you need a template that specifies the report structure, included modules and their settings.
14-03-2012
Page 57 of 90
To create a report automatically, right-click the recording on the Recordings pane and select Create Report on the left pane. Choose a template for the report and click OK. If you do not want to use the default template, select another template and click OK to generate the report. Refer to Defining settings for selecting template. Each report is based on a template file that describes the report output. With the Template Editor it is possible to create and manipulate template files on a higher level, refer to Structuring report manually. The template is build from one or several report modules. A report module can be for example a time diagram, a vector diagram or some other dynamically created visual module. The new modules can be created and added to the system without re-compilation of the report framework. Report viewer With the report viewer it is possible to display the reports generated from the COMTRADE data and a template file. The report can be printed or saved as a PDF document. To examine the report more in detail it is possible to zoom in and out. With the Report Viewer it is easy and efficient to handle the templates. You can also get a block preview of the document. To create report: 1. Select appropriate recordings in the view. 2. Click the Create Report toolbar button.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 58 of 90
It is possible to open and view the recordings with an alternative tool, for example, an analysis tool. To open a recording: 1. Right-click a recording in the Recordings pane and select Open With to open the Browse dialog. 2. Select a tool to view the recording, for example REVAL, WinEve or WordPad. 3. Click OK to open the specified tool and view the recording.
Protection and Control IED Manager Configuration and Engineering PCM 600
Defining settings
You can edit the settings of the Disturbance Handling by clicking a certain IED and selecting Customize > DH Settings or by right-clicking the IED and selecting DH Settings from the shortcut menu. The Disturbance Handling - Settings dialog is shown. To edit the layout of the displayed information, select one of the items from the list on the left side of the Disturbance Handling - Settings dialog: By selecting Create Report, you for example, which SMTP server is By selecting Recording List, you Recordings pane. By selecting IED Recording List, Available Recordings in the pane. can change template or set the e-mail information, used and define the recipients. can define the information visible for the user in the you can define the information visible for the user in
You can save the changes by clicking Apply or OK. Clicking Reset sets the last saved values.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 59 of 90
The object tree on the left displays all the nodes in the template structure. It also makes it possible to edit the nodes. The property editor is mainly meant for editing property values as well as adding and deleting nodes. The layout window is meant for previewing the template. It is possible to move and align the components by dragging. For more information on using Template Editor, refer to the Template Editor User Manual. The templates created with Template Editor are used in Report Viewer. For more information on handling the reports, refer to Creating report. Time diagram The time diagram is a graphical module that displays either the analogue or binary channels. The diagrams can display one graph per channel or a whole channel group in the same graph. The module can be configured to show the total recording overview or a diagram for a specific disturbance, for example the first detected disturbance, A channel group can for example include currents with all the ampere unit channels or voltages with all the voltage unit channels. When displaying the overview graph, both the RMS and the pure sample values are shown in the analogue channels. When displaying a diagram from the disturbance, only the sample values are shown. The beginning of the RMS graph is not shown, because the RMS value calculations need a sample to calculate the current RMS value. Therefore, displaying the graph starts from the first calculated RMS value. Vector diagram The vector diagram is a graphical module that displays RMS and angle values in a vector diagram. Each vector in the diagram does have a corresponding row in the description table where the exact data for the vector is displayed (RMS value, angle, channel name and so on). The magnitude circle is always indicating the largest RMS value, even if the largest value is equal to zero. The module supports multiple channels, and therefore the diagram might be quite unreadable. The vector description table is added below the diagram to display each of the vector's RMS value and angle. The calculation of the RMS value requires at least one period to be able to calculate the RMS value and its angle. The time window below the diagram is used to display the starting time and the ending time in milliseconds. Template The template is build from one or more report modules. A report module could be a time diagram, vector diagram or other visual modules created dynamically. New modules can therefore be created and added to the system without re-compilation of the report framework. Some modules need calculation modules to function, those must be added to the templates as well. The report includes the following elements: Document Header Pages
14-03-2012
Page 60 of 90
Calcmodules Reportobject Header The header report module is a graphical module that presents data from the COMTRADE header file (COMTRADE files with extension hdr) in an appropriate way. Four different graphical modules are available in this version. See the Template [link] Reference Manual for details about template settings. Calculation modules A calculation module is a nonvisible part of the report. It gathers all the important information to the report in the background.
Protection and Control IED Manager Configuration and Engineering PCM 600
Signal Matrix
Starting Signal Matrix Mapping analog inputs Mapping binary inputs Mapping binary outputs Mapping GOOSE receive Printing Exporting to Microsoft Excel Writing configuration to IED Reading configuration from IED Signal Matrix is used to map the input and output signals of the existing functions to the physical input/output (IO) channels and/or LEDs of the target IED. Signal Matrix contains one row per signal for the software functions that are presently configured in the IED, and one column per possible input/output channel according to the target hardware configuration. Signal Matrix contains the following matrices for the different signals: Binary Inputs display the configured binary input modules and LEDs. Binary Outputs display the configured binary output modules and LEDs Analog Inputs display the analog input modules. Goose Receiver The Object Properties window shows the parameters for the functions, signals, hardware modules and channels according to the currently selected objects. Most of the properties are read only, however, some properties can be configured.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 61 of 90
14-03-2012
Page 62 of 90
Several different VAIn signals can be mapped to the same physical analog input channel, but one VAIn signal can be mapped only to one physical analog input channel.
Example If a connectivity package provides only 1-phase VAIn signal, subject to the above rules, any VAIn signal can be mapped to any analog channel on any available hardware module. Each analog input channel refers to a certain transformer type: Current transformer for protection (CT) Voltage transformer type (VT) Voltage transformer for measuring (MT) Signal Matrix helps you to produce a valid signal mapping. Non-configurable cells are colored light red.
Mapping a VAIn current signal to a voltage transformer analog channel, or mapping a VAIn voltage signal to a current transformer analog channel is not allowed.
PCM 600
Several different VBIn signals can be mapped to the same physical binary input channel, but one VBIn signal can be mapped only to one physical binary input channel.
14-03-2012
Page 63 of 90
Signal Matrix displays the LED channels both in the Binary Inputs sheet and in the Binary Outputs sheet. This means that both VBIn and VBOut signals can be mapped to the LED channels. If you map some already mapped signal, the previous mapping is automatically deleted. A cell colored light blue informs that the cell is already mapped. If the previous mapping is in another signal matrix, a message for this effect is displayed. A cell colored light red informs that the cell is already in use in another signal matrix.
One VBIn/VBOut signal can be mapped to several different LED channels, but one LED channel can be mapped only to one signal (either VBIn or VBOut).
If you attempt to map one LED channel to more than one signal, the most recent mapping is used and the previous mapping is deleted. Error channels In the Binary Inputs matrix there are several modules displayed containing just one channel. These channels are binary input error channels, but they are physically in other hardware modules, for example, in the Binary Output and Analog Input modules. These binary input error channels contain information on the state of the associated physical hardware module.
Protection and Control IED Manager Configuration and Engineering PCM 600
One physical binary output channel can be mapped to only one VBOut signal, but several different physical binary output channels can be mapped to one VBOut signal.
Output signal to channel mapping Refer to Mapping binary inputs. Output signal to led mapping
14-03-2012
Page 64 of 90
Refer to Mapping binary inputs. Block channel The Binary output module has two zero channels defined. One is the binary input error channel, which is displayed in the Binary Inputs sheet and the other is the binary output block channel. The remaining channels of the binary output module are the normal binary output channels.
Protection and Control IED Manager Configuration and Engineering PCM 600
Several different VCOM signals can map to the same GOOSE Receive data object attribute, but one VCOM signal can be mapped only to one GOOSE Receive data object attribute.
PCM 600
Printing
To print the configuration that is currently displayed in Signal Matrix:
14-03-2012
Page 65 of 90
Select File > Print or Click the Print toolbar button. In the Print dialog box, select the wanted options and click OK. To examine the generated print document before printing it: Select Select File > Print Preview or Click the Print Preview toolbar button.
Protection and Control IED Manager Configuration and Engineering PCM 600
Before writing a new configuration, write the current PCM 600 configuration to IED by using Application Configuration Tool.
PCM 600
14-03-2012
Page 66 of 90
To read the configuration from IED to Signal Matrix: Select IED > Read Configuration From IED or Click the Read From IED toolbar button.
Before writing a new configuration, read the current IED configuration to PCM 600 by using Application Configuration Tool.
PCM 600
14-03-2012
Page 67 of 90
Every symbol type has a corresponding representation in both the ANSI and the IEC symbol palettes. Indication only symbols An isolator or a breaker may be displayed with an indication only symbol. An indication only object is not controllable. The position of an indication only object is dynamically updated on the display. However, an indication only object cannot be selected for control on the IED display. Indication only symbols can be configured the same way as the other symbols. The SortIdx property, which controls the order in which an object is selected on the display, is not available on an indication only object. Refer also Creating single-line diagram.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 68 of 90
Read display configuration from the IED, refer to Reading display information from IED. Write the display configuration from the Graphical Display Editor to the IED, refer to Writing display information to IED. Add display pages, refer to Adding display pages. Remove display pages, refer to Removing display pages. The Select function selects and moves symbols, refer to Selecting symbols and links and Moving symbols. The Pan function moves the display page. For more information about the Pan tool, refer to Panning and zooming. The Show Grid function displays or hides the grid in the display page. With Snap to Grid function enabled, a symbol is positioned with its top left corner at the intersection of the nearest grid lines. For more information about the Snap to Grid function, refer to Creating single-line diagram. The Zoom function zooms in and out of the current diagram. For more information about the Zoom tool, refer to Panning and zooming. The Directed Link function inserts a link, that is connection between two links. The Directed Link tool activates symbol ports, that is the possible connection points on a symbol. Clicking first on the source port and then on the destination port draws the link. For more information about the Directed Link tool, refer to Creating single-line diagram. The Rotate Left function rotates a symbol 90 degrees to the left. The Rotate Right function rotates a symbol 90 degrees to the right. Undo the latest action, refer to Adding display pages. Redo the latest undo, refer to Adding display pages. Print the current display page, refer to Printing display page. Displays the preview of the current display page before printing, refer to Printing display page. Protection and Control IED Manager PCM 600
14-03-2012
Page 69 of 90
14-03-2012
Page 70 of 90
PCM 600
14-03-2012
Page 71 of 90
5. Consider the necessary connections. As a general rule, wherever a connection needs to be made at a right angle, a junction symbol should be placed on the diagram. For example, a junction symbol should be placed at the T intersection between the two busbar isolators and the circuit breaker in a typical double busbar feeder. 6. Connect the symbols where necessary using the Directed Link tool.
It is not necessary to electrically connect all the symbols by using the Directed Link tool. If a symbol already appears to be connected, it is not necessary to explicitly create a directed link.
7.
8.
9. 10.
1. Activate the Directed Link tool by clicking the Directed Link button or selecting Graphical Display Editor > Directed Link. The connection ports of all the symbols are activated. 2. Select the wanted source port by clicking it. 3. Select the wanted target port by clicking it. 4. A line is automatically drawn between the two ports. Once a directed link has been used to connect symbols, the link follows the symbol if it is moved to a new position. Refer to Moving symbols. When the connections are complete, the Directed Link tool can be deactivated by: Clicking the Directed Link button again Selecting Graphical Display Editor > Directed Link Right-clicking Activating the Select or Pan tools by clicking the Select toolbar button or clicking the Pan toolbar button or selecting corresponding menu items from the Graphical Display Editor menu Press ESC. Select the IED from the PCM 600 Plant Structure and then select View > Object Properties or click the Object Properties toolbar button. Refer to Modifying symbol properties. Connect dynamic symbols to their source data as described in Connecting dynamic symbols. Configure the sort order of controllable objects. The sort order defines the order in which the controllable objects are selected when the Select button is pressed on the IED. The sort order is set via the SortIdx property. The first symbol to be selected should be set with a SortIdx of the Object Properties window.
It is recommended that a single-line diagram should be designed to fit within the available eleven grid rows and eight grid columns. The remaining space to the right and bottom of the grid can only be used if the Snap to Grid function is disabled, which is not recommended.
In general, all lines pass through the middle of a grid square, and symbols fill an entire grid square.
PCM 600
14-03-2012
Page 72 of 90
containing a list of appropriate signals for this symbol is displayed. The AttrGroup Id property in the property grid is updated to reflect the new configuration.
Protection and Control IED Manager Configuration and Engineering PCM 600
Moving symbols
To move a symbol: 1. Select a symbol to be moved. Refer to Selecting symbols and links. 2. Drag the symbol to the wanted position. Symbols must remain completely within the boundaries of the display page. If a symbol is dragged to a position beyond the boundaries of the display page, it is automatically returned to its last position when the mouse button is released. Existing links are also moved with their connected symbols.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 73 of 90
14-03-2012
Page 74 of 90
14-03-2012
Page 75 of 90
To deactivate the Pan tool: Click the Pan button again or Click the Select button or Press ESC.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 76 of 90
To write the display configuration to IED: Select IED > Write Display Configuration to IED or Click the Write Display Configuration to IED toolbar button or Press CTRL+D It is required to confirm an action before it is carried out, because the action overwrites the existing display configuration of IED. The writing operation can take a few minutes. Depending on the version of the installed connectivity package, the write operation progress displayed in a progress dialog.
Protection and Control IED Manager Configuration and Engineering PCM 600
Modem Dial-up
IEC 61850-based dial-up SPA-based dial-up PCM 600 provides two kinds of dial-up services for the remote communication with an IED: IEC 61850-based dial-up services SPA-based dial-up services
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 77 of 90
Connecting dial-up To make a dial-up connection: 1. Right-click the voltage level in the Plant Structure. 2. Select Connect from the shortcut menu. A Connectingdialog box is displayed. The name of the connection is displayed in the title bar of the dialog box. After the connection is established, the connection status can be seen in the PCM 600 tool message. Disconnecting dial-up To disconnect the dial-up connection: 1. Right-click the voltage level in the Plant Structure. 2. Select Disconnect from the shortcut menu. The connection status can be seen in the PCM 600 tool message.
Protection and Control IED Manager Configuration and Engineering PCM 600
SPA-based dial-up
Before connecting to the remote mode, configure the Connection Type and Modem Configuration parameters. To open the Object Properties window, right-click the voltage level in the plant structure and select Properties from the shortcut menu. In the Object Properties window: Set the Connection Type to Dialup. Click Modem Configuration to start the SPA communication wizard which guides you through the configuration of parameters required for establishing a SPA-based dial-up connection. Connecting dial-up To make a dial-up connection: 1. Right-click the voltage level in the Plant Structure. 2. Select Connect from the shortcut menu. A Connectingdialog box is displayed. The name of the connection is displayed in the title bar of the dialog box. After the connection is established, the connection status can be seen in the PCM 600 tool message. Disconnecting dial-up To disconnect the dial-up connection: 1. Right-click the voltage level in the Plant Structure. 2. Select Disconnect from the shortcut menu.
14-03-2012
Page 78 of 90
The connection status can be seen in the PCM 600 tool message.
Protection and Control IED Manager Configuration and Engineering PCM 600
Signal Monitoring
Starting Signal Monitoring Closing Signal Monitoring Online monitoring Manual refresh Switching views Filtering signals Printing Exporting to Microsoft Excel Forcing Signal Monitoring is a tool for visualizing all configured signals of an IED. The Signal Monitoring tool consists of: List View which is an overview of all the signals One or more tabbed pages where each tabbed page contains a set of signals displayed with a seven segment graphical LED and/or binary LED display.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 79 of 90
1. Right-click the Signal Monitoring tab at the top of the Signal Monitoring window. 2. Select Close from the shortcut menu. Alternatively, close the Signal Monitoring by clicking the close button at the upper right side of the window.
Protection and Control IED Manager Configuration and Engineering PCM 600
Online monitoring
To start continuous online monitoring: Click the Continuous Reading toolbar button or Select IED > Toggle Continuous Reading.
The menus are available only if the corresponding IED is connected to PCM 600 with the proper IED communication properties configured.
The values displayed are refreshed automatically when new values are received. Meanwhile, it is possible to freely switch to other tools without having to stop the monitoring process. To stop continuous online monitoring: Click again the Continuous Reading toolbar button again or Select againIED > Toggle Continuous Reading. The last received values remain when online monitoring stops.
Protection and Control IED Manager Configuration and Engineering PCM 600
Manual refresh
To force a synchronous value refresh of signal monitoring: Click the Read Latest Values from IED toolbar button or Select IED > Read Latest Values from IED
The menus are available only if the corresponding IED is connected to PCM 600 with the proper IED communication properties configured.
PCM 600 freezes until the values or time-out events are received. Meanwhile, it is not
14-03-2012
Page 80 of 90
Switching views
Switch to another view in the Signal Monitoring tool by clicking the tab at the top of the Signal Monitoring view.
PCM 600
Filtering signals
To filter the monitored signals: Switch to a specific graphical tab view or Apply a filter to the List View tabbed page. To apply a filter to the List View: 1. Select the List View tab. 2. Click the Filter On/Off toolbar button or select Signal Monitoring > Filter On/Off to enable filtering. 3. Select the wanted combination of filter criteria on the filter bar displayed under the header row.
Protection and Control IED Manager Configuration and Engineering PCM 600
Printing
To print the last retrieved values: Select File > Print or Click the Print toolbar button or Press CTRL+P
14-03-2012
Page 81 of 90
In the Print dialog box, select the wanted options and click OK. To examine the generated print document before printing it: Select File > Print Preview or Click the Print Preview toolbar button or Press CTRL+SHIFT+P
PCM 600
Forcing
Depending on your access rights and IED capabilities, Forcing Mode is accessible in Frame Menu. Select IED > Forcing Session on the List View tab. If IED successfully enters in forcing mode, the Forcing Value Edit button is displayed on the toolbar. Click the Forcing Value Edit toolbar button. Signals that can be forced are displayed with the different background color in the List View tab. You can perform the following operations: Edit an analog signal by double-clicking the signal cell, typing a new value and then pressing ENTER. Edit a digital signal by selecting a different signal state from the available drop-down menu. If both analog and digital signal is already in the state that should be forced, right-click and select Force Signal Value from the shortcut menu. Remove a forcing flag by right-clicking an edited value select UnForce Signal Value from the shortcut menu.
14-03-2012
Page 82 of 90
Assign the same command for several signals by holding down the left mouse button while moving the mouse in the grid. Depending on the selected signals, it is possible to: Force all selected signals into their current state Force all selected digital signals into true or false state Force all analog signals to 0 Unforce all selected forced signals Every re-edited value is highlighted. After completing the edition phase: Force or Unforce the selected and edited values by clicking the Acknowledge and Send toolbar button. Ignore the changes made since the Forcing Value Edit toolbar button was last selected by clicking the Cancel toolbar button. Monitoring Tool refresh automatically all its values and forced signals in the IED remains highlighted. To stop the forcing or unforcing signals, select IED > Forcing Session.
If the signals are still forced in the IED after a Forcing Session, they are highlighted. Release the signals by using the UnForce Signal Value command.
PCM 600
Event Viewer
Starting Event Viewer Closing Event Viewer Event Viewer data columns Sorting event data Filtering event data Reading newest events from IED Selecting period type Moving to another period Clearing event buffers in IED Deleting events in datastore Printing events Exporting events to other programs Event viewer options Event Viewer displays the actual events stored in the IED. These events can be sorted and filtered for easier examination or they can be printed or exported to a file. All uploaded events from the IED are stored in a dedicated database called Events datastore.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 83 of 90
14-03-2012
Page 84 of 90
[empty] ? T M
Valid event (default) Event status is unknown Event is not time-synchronized Event value has been manually altered (for example by manual data entry)
Type
One (optional) character showing the status of the event as follows: [empty] P S T Event type is unknown Process event (default) System event Test event
Date&Time
The date and time (including milliseconds) of the event. The format can be selected in Regional Options of the Windows Control Panel.
The actual value of the signal at the time the event was generated. The value displayed in this column is usually empty for binary signals. Their current value is displayed only in the Status column. For analog signals a numeric value (integer or floating point) is usually displayed together with the unit text. It can also be an empty value.
Status
The text representation of the signal's status at the time the event was generated.
Additional info
An optional IED-specific (signal) information text (for example function block name). It can be empty for some IED types.
Note that some of these columns can be hidden because all their values are either empty or equal to a default value (for example all values of the Type column are process events).
PCM 600
14-03-2012
Page 85 of 90
changes back to ascending. The Date & Time column can also be sorted by selecting Event Viewer > Show newest events on top/on bottom or by clicking the Show newest events on top/on bottom toolbar button. If the event list is already sorted by date and time, the order is reversed by the command. The actual sort order is stored when closing Event Viewer and the same sort order is held when Event Viewer is opened the next time.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 86 of 90
PCM 600
Note that depending on the capabilities of the IED and the corresponding Connectivity Package new events are either automatically added to the tabular display or collected and displayed by Event Viewer on a regular basis. The command Read newest events from IED is therefore only useful if the waiting time until the next automatic update seems to be too long. New events (if any) are only added to the display if the actual time period is displayed, that is, the user has not moved to a different time period (Refer to Moving to another period ).
PCM 600
Note that when selecting period types with a long period length, for example Unlimited, Month or Week, loading events takes a considerable amount of time depending on the number of events generated by the IED. In case an IED generates a lot of events, it can be true also for period type Day or even shorter period types.
14-03-2012
Page 87 of 90
The actual period type is stored when closing Event Viewer and the same period type is held when Event Viewer is opened the next time.
Protection and Control IED Manager Configuration and Engineering PCM 600
Note that when selecting period types with a long period length, for example Unlimited, Month or Week, loading events takes a considerable amount of time depending on the number of events generated by the IED. In case an IED generates a lot of events, it can be true also for period type Day or even shorter period types.
PCM 600
14-03-2012
Page 88 of 90
this feature, and the current PCM 600 user has access rights to clear the IED event buffers. Refer to the PCM 600 user management settings Modifying existing user category.
Note that this command only deletes all events in the IED but not the already uploaded events that are stored in the Events datastore in PCM 600. Use Deleting events in datastore for this purpose.
PCM 600
Note that this command does not delete the events that are currently stored in the internal event buffer (s) of the IED. Use Clearing event buffers in IED for this purpose.
PCM 600
Printing events
To print the events that are currently displayed in Event Viewer: Select File > Print or Click the Print toolbar button or Press CTRL+P In the Print dialog box, select the wanted options and click OK. To examine the generated print document before printing it: Select File > Print Preview or
14-03-2012
Page 89 of 90
Click the Print Preview toolbar button or Press CTRL+SHIFT+P Use the Zoom functionality to check how many pages there are and how exactly the pages will be printed. Click OK to print. The Print and Print Preview functions are disabled, if no events are currently shown in the Event Viewer display or if the default printer is not defined.
Protection and Control IED Manager Configuration and Engineering PCM 600
14-03-2012
Page 90 of 90
Click the Options toolbar button The following options can be modified: Select the default value Show actual IED events only or Show historic and actual IED events. Historic events are read earlier from IED and they are no more stored in the IED event buffers. Modify Interval used for reading new events from IED. The number of seconds is only relevant for IEDs, who's corresponding IED Connectivity Package does not support spontaneous notification about new events in IED. Modify the scope for which the current settings of sort options, column filter settings, period type, and read interval are stored, e.g. identically for all IEDs (default), differently per substation, differently per bay, differently per IED type, or differently for each IED.
Protection and Control IED Manager Configuration and Engineering PCM 600
Reporting
Modifying header Reporting is used by tools for viewing, saving, and printing of the reports. Reports are opened in the report viewer, which normally provides zooming and navigating functions.
Protection and Control IED Manager Configuration and Engineering PCM 600
Modifying header
The reporting and printing system makes it possible to change the company logo in the header of the page and the company name in the footer of the page of the printed report. The height and width of the image should be relatively small not to interfere with the layout of the report. The height of the image should be less than 2.5 cm or one inch. To change the logo: 1. Copy the company logo image file, which must be a .jpg file, to [PCM 600 installation path]\bin\Tools directory and rename it COMPANY.jpg. 2. Create a new text file, called COMPANY.txt, with Notepad text editor and store it in the same directory. 3. Open the COMPANY.txt file and add the company name to the first line of the document. 4. Save the file with Unicode encoding. 5. Restart PCM 600.