You are on page 1of 3

Team Members Task no.

TASK DESCRIPTION

Ajay

Roshan

Jorge

Sam

David

Mustafa

Tom

Milad

1.0 1.1 1.2 1.3 1.4 2.0 2.1 2.2 2.3 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 4.0 4.1 4.2

Teamwork Forming Team Creating Team Charter Establishing team roles Establishing communication medium Project Abstract Tracking PM Gathering information on the PM and their company Compiling project abstract Project Plan Preparing Project Scope Statement Preparing Work breakdown structure Creating Work schedule Gantt chart Creating AON Project network diagram Preparing Budget Plan Preparing Responsibility matrix Preparing Risk and Quality Management Plan Preparing Monitoring and Control Plan Writing Cover Letter Compiling project plan, TurnitIn SPARK Research Researching project management processes Gathering information on upcoming trends for efficient project management Interview and Report Interview Plan Conducting and recording interview Transcribing audio recording Researching and writing

R R S

R R S R

R R S

R R R

R R S

R R S

R R S

R R S

R R R R R S R R S R R R R R R R R S R R R S R R R S R R R S R R R S R R R S R R R S R R R R

5.0 5.1 5.2 5.3 5.4

R R R R

R R

R R R

R R

R R S

R R

R R

R R S

report 5.5 5.6 5.7 5.8 6.0 6.1 6.2 Printing report Binding report Submitting onto TurnItIn Completing SPARK Project Presentation Preparing presentation slides Rehearsing presentation and making appropriate amendments Making presentation Submission of Report Submitting report Audit Report Analysing and assessing specific segments Conducting Audit Review meeting Printing report Binding report Submitting onto TurnItIn Progress and Status Report 1 Conducting meeting Completing assigned tasks Compiling report Printing report Binding report Submitting onto TurnItIn Progress and Status Report 2 Conducting meeting Completing assigned tasks Compiling report Printing report Binding report Submitting report onto TurnItIn Progress and Status Report 3 Conducting meeting Completing assigned tasks Compiling report Printing report Binding report

R R R R R S R R S R S R R R R S R S R R R S R S R S R R R S R R R S R R R S R R R S R R R S R R R S R R R R R

6.3 7.0 7.1 8.0 8.1 8.2 8.3 8.4 8.5 9.0 9.1 9.2 9.3 9.4 9.5 9.6 10.0 10.1 10.2 10.3 10.4 10.5 10.6 11.0 11.1 11.2 11.3 11.4 11.5

R R R

R R R R R

R R R

R R R

R R R

R R R

R R R

R R R

R R R

R R R R R

R R R

R R R

R R R

R R R

R R R

R R R

R R R

R R R R R

R R R

R R R

R R R

R R R

R R R

R R R

11.6

Submitting onto TurnItIn

R 30 4 34 33 4 37 22 5 27 23 3 26 24 4 28 23 4 27 23 4 27 25 4 29

Total number of Responsible tasks (R): Total number of Support tasks (S): Total number of tasks (R+S):