Professional Documents
Culture Documents
11
Supply of Electricity From the Rajpura Thermal Power Project (RTPP)-A Case Study
1. This petition has been filed by Punjab State Electricity Board (now Powercom) under Section 63 of the Electricity Act 2003 (hereinafter referred to as the Act) for adoption of tariff determined through an international competitive bidding process for supply of electricity from the Rajpura Thermal Power Project (RTPP).
14
24
30
31
There are voltage sensitive and frequency sensitive loads, which need quality power supply .
32
EHV
33
Frequency
Statutory limits : rule1956) 48.5 to 51.5 HZ (IE
CERC standards:
49.5 to 50.5 HZ
A commercial mechanism (viz) ABT (Availability Based Tariff) is developed as per which UI (Unscheduled interchange) is priced on the following basis: Active power based on frequency
This has resulted in Grid Discipline in Indian Power Utilities and CERC standards are being maintained. 35
Reliability
System Reliability includes three aspects
- System adequacy
- System security - Service reliability
Generation adequacy is measured in terms of LOLP (Loss of load probability) i.e. system capacity not being able to meet demand
- Preliminary (existing) 20% - Transition 8% - Final 1% (87.6 hrs in one year)
36
System Security
Ability of the power system to withstand sudden disturbances such as short circuits or sudden loss of elements (generator, transformer, line etc) System shall be designed for security level of n-1 or n-2 Loss of a critical generator (highest capacity) - ICT - Line (400 KVSC, 220 KVDC, 132 KVDC etc) - HVDC Pole
37
- Instability of system
- Overloading of lines / trfrs for more than 15 mts - Voltage drop of more than 10% - Load shedding - Rescheduling of generation Spinning Reserve 1% of system peak
IEGC specifies running of generators at 90% of MCR and all generators of 50 MW & above capacity shall be on free governor mode.
38
Service Reliability Customers perceptions of reliability are actually shaped by a combination of factors, including voltage characteristics. However, the most visible of these are the continuity of supply factors that manifest themselves in outages, be they momentary or extended.
39
Service Reliability
The type of interruption: planned or unplanned interruptions. Some customer satisfaction surveys have revealed that customers appreciate advance notice of planned interruptions. The duration of each interruption: short or long interruptions. For example, the European technical standard EN 50160 defines any interruption that lasts more than three minutes as a long interruption.
40
Service Reliability
Service Reliability is indicated by
SAIFI: System frequency index year energy is not supplied.
contd
SAIDI: System Average interruption duration index indicates how long during the year energy is not supplied.
Duration of outage in Ti (minutes) sum of interrupted loads : Pi (KVA) SAIFI = Pi / P total SAIDI = [ Pi x Ti / P total] 60
41
Service Reliability
Allowable limits
(Contd.)
Transition Stage
24 / Yr.
18 / Yr.
10 hrs/ yr
8 hrs / yr.
Scheduled outages which are communicated to consumers before hand are not included
42
Harmonic Distortion
General Description
Many types of equipment and phenomena can produce voltages and currents at frequencies that are multiples of the power frequency. These high frequency components are called harmonics and their ratio to the fundamental frequency is the harmonic order. Harmonics have many negative effects on the system and connected loads, and they have to be limited to a manageable level.
43
Utility will compile a list of all metering points and take measurements at 5 sites per month. The list has to be submitted to ERC for approval.
Measurement
The measurements should conform to IEC Std 10004-7 or IEEE Std 519. The measurements should be taken at 10 minute intervals and should last for 1 week per site.
44
Voltage Flicker
General Description If the voltage fluctuates, the luminous intensity of the lamps and TVs will fluctuate correspondingly. If the fluctuation is of a magnitude and frequency perceptible to the eye, it becomes flicker. Flicker could range from annoying to complete interference of normal activity.
45
Voltage Flicker
(Contd.)
Flicker is not usually produced by the power system but by customer loads such as arc furnaces, arc welding, compressors, starting of large motors, etc. Since voltage fluctuation of the system affects other users on the same system, the transmission company needs to control the flicker on its lines and station buses.
46
Voltage Flicker
(Contd.)
At the same time, flicker-generating loads connected to the system have to be controlled. Indicator of Quality for System Flicker Flicker is expressed as: V = 100 x (Vmax Vmin) Vnom. 50% people perceived light flicker as annoyance under the following conditions: Voltage Change 1 Volt 2 Volts 4 Volts 2 1
47
an
Changes / Sec. 4
Voltage Flicker
Control and Measurement
(Contd.)
Substations which supply heavy industrial loads such as furnaces, steel mills, etc. are targets for flicker monitoring. Other substations and connection points will be selected for monitoring on a random basis. At least one site is monitored each month.
The list of monitoring points is submitted to APERC for approval at least 2 months before the monitoring.
48
Voltage Flicker
(Contd.)
The flicker measurement will be conducted at 10 minute intervals according to procedures outlined in IEC Std 61000-4-15. Each site is measured for 1 week. Enforcement of Limits (As per AP Grid Code)
Flicker limits and control and measurement procedure will be in effect only in the Final Stage
49
Power Factor
General Description It is desirable that loads on the system have power factors at or close to unity as that represents the most efficient use of the system capability and the least loss of energy. It also eliminates many transient stability problems.
Any load with a power factor lower than 90% is imposing burden on the transmission system and other Users. Power Companies restrictions on the customer loads. therefore impose power factors of 50
Imposition of limits of power factor shall be with immediate effect (A.P. Grid Code)
52
. Reliability
- Breakdown Maintenance
Efficient and pleasant relations of the discoms with the consumers. Communication with the customer through IVC (interactive voice calls) by dial-up connections. Introducing customer PIN (Personal Identification Number) for registration of no current complaints and following up till supply is restored.
53
54
Creating asset database of all sub-station equipment and on-the-ground equipment, which would include key information relating to the history beginning from its installation, defining the time of periodic maintenance requirements (viz.., checking of tightness of bolted connection, visual inspection, oil filtration of transformers etc.) of all equipment in the network.
55
56
. Reliability Contd--
Responding to failure of suppliers fuse: within 4 hours in urban areas and 8 hours in rural areas. Restoring electricity supply after faults (ex. force majeure events): 80% within 8 hours.
There is not yet a well-developed history with these standards, so adaptation may be required after an initial period of experimentation with measurement and reporting.
Maximum no. of interruptions per LV customer per year: - Urban = 12 - Suburban = 15 - Rural Concentrated = 18 - Rural Sparse = 24 Maximum no. of interruptions per MV customer per year: - Urban = 8 - Suburban = 12 - Rural Concentrated = 16 - Rural Sparse = 20
These standards are very new to the regulation of electric companies and should be used cautiously until sufficient experience has been gained to instill confidence in companies and regulator alike.
63
These standards are very new to the regulation of electric companies and should be used cautiously until sufficie experience has been gained to instill confidence in companies and regulator alike.
Improvement Standard
Provisional target a minimum rate of improvement in total customer minutes lost and customer interruptions of 3%. This must be refined on the basis of an analysis of demographic and other data.
Refinement of an appropriate rate of improvement will require analysis of the demographics of the territory served (customer density, etc.)
64
An alternative KPI might require responding to, say, 80% of outages within 4 hrs
An alternative could require connecting 90% within 4 days and 100% within 30
Estimating Charges
Appointment scheduling
Within 15 days
65
Time to complete will depend on the complexity of work Standard relates to the start of service not resolution.
Voltage complaints
Standards range from 95% to 100% and one calls for at least 6 actual reads per year
66
Conclusion
Quality Power Supply is to be maintained as consumers, especially of process industries have voltage sensitive and frequency sensitive loads. Automation, Modern maintenance techniques and Expert Systems for corrections have to be
implemented although , the gap between demand and availability is the impediment for moving towards quality power supply. Maintaining Quality Power Supply for total customer satisfaction & hence improving Financial status of the supply utility is to be taken as a Challenge.
67