The
purpose of the state aid program is to provide resources to assist local governments with the construction and maintenance of community-interest highways and streets on the state-aid system.
The goals of the state aid program are to provide users of secondary highways and streets with: Safe highways and streets Adequate mobility and structural capacity on highways and streets An integrated transportation network State Aid administers funding that supports more than 120,000 miles of roadway and almost 14,700 bridges.
3
Division Director/State Aid Engineer Deputy State Aid Engineer District State Aid Offices Program Support Specialists Finance Bridge/Hydraulics Cultural Resources Labor Compliance Materials
Central Office
Needs Studies State Aid Programs Project Delivery Information Resources Program Support Spec. Traffic Safety Wetland Construction Practices
Minnesota
Statutes Minnesota Rules Standards for Rural & Urban designs Complete Streets Natural Preservation Routes, Forest Highway Variance Procedures Federal Aid Projects
Stewardship Plan
5
TH
= Trunk Highway CSAH = County State Aid Highway 87 Counties MSAS = Municipal State Aid Street 142 Cities Over 5000 Town Road & Bridge
6
TRUNK HIGHWAY MILES-11,878 STATETrunk ROUTES: 11,897 miles AID Highways CSAH - 30,609 MSAS - 3,597 LOCAL ROADS 91,502
95%
of highway user funds are distributed as follows: 62% to the trunk highway fund 29% to county state aid highway fund 9% to the municipal state aid fund
The
Other $3M
-Article XIV of the Minnesota Constitution -DNR transfers for unrefunded gas taxes per MS296A.18
CSAH
50% Needs 30% CSAH lane miles 10% Motor Vehicle Registration 10% Equalization
2008
Excess sum:
40%
of the regular and municipal state aid allocation is set aside for maintenance of the county state aid system 60% is set aside for construction costs
13
$483 M 87 counties
60% Construction 40% Maintenance
DEDUCTIONS
MSAS
For
15
15-35%
of the state aid allocation is set aside for maintenance, as requested by the city 65-85% is set aside for construction costs
16
50% POPULATION
50% NEEDS
DEDUCTIONS
2013
Total Available Amount is $89M Funds 3 Accounts Town Bridge Account -$14M Town Road Account -$27M Flexible Highway Account -$48M
18
State Aid is governed by three entities: Screening Boards Rules Committee Variance Committee
19
Julie Skallman State Aid Division Director and State Aid Engineer Phone: 651-366-4831 Email: julie.skallman@state.mn.us Rick Kjonaas Deputy State Aid Engineer Phone:651-366-3802 Email: rick.kjonaas@state.mn.us