General information The xSpider is a graphically oriented design software for dimensioning low-voltage networks fitted with protective devices of Eaton brands.
General information
The xSpider is intended primarily for designers, computational and checking engineers Design of networks TN/TT/IT of various voltage systems up to 1000 V Design of radial or meshed networks Design of networks supplied from one or more different power sources All calcualtions are based on IEC standards (voltage drops, load distribution, short-circuits, impedances)
3
General information
User-friendly interface allowing easy and fast design
User operation similar to standard CAD systems (eg. AutoCAD) Independent software requiring only the operating system of Windows95/98/NT/2000/XP or Vista Available free of charge after registration via internet
General information
xSpider software provides needed calculations: voltage drops (DU) load distribution (nominal load In / overload) short-circuit currents (Ik, Ikm , .) carries out check of suitability of cables (In, I, ) carries out check of suitability of protection devices calculation of impedances (Zv, ) etc.
General information
Tree structured database for all needed components
Graphical comparison of tripping characteristics Evaluation of selectivity betweem devices in the network
Evaluation of selectivity between incoming and outgoing devices according to tables from catalogue
General information
Export of graphics (drawings) - to DXF format (suitable for CAD systems, like AutoCAD)
xSpider
1
10
11
System of work
Main steps: 1: Definition of project 2: Network wiring diagram 3: Parametras of network 4: Calculations 5: Tripping characteristics 6: Results
12
System of work
Main steps: 1: Definition of project 2: Network wiring diagram 3: Parametras of network 4: Calculations 5: Tripping characteristics 6: Results
13
1. Definition of project
Start with
New project
Open DEMO
14
1. Definition of project
Network and voltage system
Change of network and voltage (if it is necessary) Default setting: TN network, 230/400 V
3
15
System of work
Main steps: 1: Definition of project 2: Network wiring diagram 3: Parametras of network 4: Calculations 5: Tripping characteristics 6: Results
16
The wiring diagram is taken as a pattern for creation of the final wiring diagram with use of xSpider
Any existing network wiring diagram, which was created by the xSpider, can be quickly modified acc to new needs
17
Sources
Lines
Breakers
Outlets Cap.
Individual components: creation of wiring diagram step by step (universal use, modifications)
Eg. Transformer
Selection of type
2
Database
18
Circle network
19
20
B) Outlet groups
21
22
23
1 3
Inserting
Outlet groups
24
B)
A)
26
27
onto the symbol of transformer Select new group from database tree Select new item from data table
2 4 5
28
System of work
Main steps: 1: Definition of project 2: Network wiring diagram 3: Parametras of network 4: Calculations 5. Tripping characteristics 6: Results
29
The tree structured database is built as open-ended. Each user can create own database User defined.
30
3
Database
Switchboard busbar
Cable Busbar trunking system Circuit breaker Fuse, Fuse disconnector Switch disconnector Motor Load Compensation unit
31
System of work
Main steps: 1: Definition of project 2: Network wiring diagram 3: Parametras of network 4: Calculations 5. Tripping characteristics 6: Results
32
4. Calculations
A. Basic calculation modes: - calculations which are needed in all projects Voltage drops and load distribution (Unode, Uwl, Inode, Iwl) 3-phase symetrical short-circuit current (Ik3p, Ikm) 1-phase asymetrical short current and tripping time (Ik1p, Ttr) B. Additional calculation modes: - advanced possibilities for more detailed information 2-phase symetrical short-circuit current (Ik2p, Ikm) calculation of impedances (Zsv, Z1, Z0) the complex expression of results (real and imaginar compoments of currents and impedances)
33
4. Calculations
Selection of a calculation mode 1 2
Network calculation modes - selection
3
34
4. Calculations
Check the network connection logic control of possible users mistakes - before start of any calculation
1 2
Check Network
connection logic
a) OK
It is possible to continue.
b) not OK
It is necessary to correct the displayed mistake(s) and repeat the check once again !!
35
4. Calculations
Voltage drops and load distribution mode: possibilities: Check, if voltage drop does not exceed the user-defined maximum value Simultaneous factor is considered in radial networks
36
4. Calculations
Voltage drops and load distribution mode: setting conditions:
37
4. Calculations
Voltage drops and load distribution: calculations
Correction of displayed problematical parametras Next calcualtion (steps 1 4) up to situation with correct result
38
4. Calculations
Voltage drops and load distribution: display of results eg. as the 3-phase outlets
Component with error: current Iwl in the line is higher than In of the cable
39
4. Calculations
Load optimalisation by use of the Operating state On/ Off 1
DOUBLE CLICK onto the device
Ics Icu
3
40
4. Calculations
Load optimalisation by use of the utilization factor Ku Can be defined for loads (motor, general load)
Example for motor application: 7.5kW motor fitted in the project, with maximum 80% load during ordinary operation utilization factor Ku=0.8
3
41
4. Calculations
Load optimalisation by use of the simultaneous factor Ks Can be defined for nodes (Switchboard trunk component)
Defines the simultaneousness of consumptions from the node (ratio between the number of devices in operation and the total number of devices) Taken into account only with radial networks.
3
42
4. Calculations
Short currents in the low voltage network
Conditions in the TN system during of 1-phase short current to the earth (asymmetric short current, Ik1p)
43
4. Calculations
3-phase short-circuit current mode: possibilities Prospective maximal short-circuit current during 3-phase symmetrical fault Ik3p Calculation according to IEC 60909 Check of faults: a) in all nodes - global overview about situation in the network b) in the selected node - optimalisation of network, focuse to the selected problematical details Check of correct dimensioning: - breaking capacity of circuit breakers (Icu, Ics) - withstand current of conductors (Icw)
44
4. Calculations
3-phase short-current circuit mode: parametras
Ik - Initial impulse short-circuit current: the r.m.s. value of symmetrical short-circuit current without the direct-current component at the time of the short-circuit formation. Ikm (ip) - Peak short-circuit current: the first amplitude (peak value) of the asymmetric short-circuit current with the DC component (iss). Ike - Thermal equivalent short-circuit current: the r.m.s. value equivalent or imaginary symmetric (balanced) short-circuit current value Ik - Steady-state short-circuit current: the effective (symmetric) short-circuit current value after all the transient components disappear. In a case of electrically remote short-circuits (the majority of cases in practice), it equals to the initial impulse short-circuit current Ik
45
4. Calculations
3-phase short-circuit current: a) check the entire network in all nodes 1 2
Selection of the calculation mode
1
6 4 5
3
8 9
7
46
4. Calculations
3-phase short-circuit current: a) display of results in all nodes
Zoom
47
4. Calculations
3-phase short-circuit current: b) check in the selected node 1 2
Selection of the calculation mode
9 5 6 1 2 3 7
48
4. Calculations
Cascading a solution where the first c.b. (1) is able to reduce a short current value to level which can be switched-off by the second c.b. (2)
Checking the breaking capacities of the outgoing protective devices with respect to the breaking capacity of incomming protective components
Example:
i
Prospective short current (effective value) Limited current (max. value)
Icu1 = 50 kA
Icu2 = 15 kA
Ik = 25 kA
49
Itr = 30 kA
4. Calculations
Check of cascading: optional check during short-circuit current calculation mode 1 2
4
Selection of cascading in the node
50
4. Calculations
Selectivity function to evaluate the selectivity of circuit-breakers based on selectivity tables specified in the catalogue A) comparison of both circuit-breakers selected from the database 1 2
3 4
5
51
4. Calculations
Selectivity function to evaluate the selectivity of circuit-breakers based on selectivity tables specified in the catalogue B) comparison of circuit-breakers in the project
(cascade must be defined for every network node)
3 2
52
4. Calculations
1-phase short-circuit current: display of results
Check of faults: a) in all nodes RM-1.1, Z1, ...
global overview about network
Ttr
Ik1p
53
System of work
Main steps: 1: Definition of project 2: Network wiring diagram 3: Parametras of network 4: Calculations and optimalisations 5: Tripping characteristics 6: Results
54
5. Tripping characteristics
Comparison of tripping characteristics
Eg. optimalisation of selectivity between fuse and circuit breaker by change of release settings.
A
55
5. Tripping characteristics
Release setting
56
5. Tripping characteristics
Tripping units of MCCBs (NZM type)
- A type - AE type - M type - ME type - VE type Ir Ir Ir Ir Ir Ii Ii tr Isd tr Isd tsd Ii (I2t - on/off)
- ME
-VE
I2t - off
I2t - on
Load characteristic of engine
57
System of work
Main steps: 1: Definition of project 2: Network wiring diagram 3: Parametras of network 4: Calculations and optimalisations 5: Tripping characteristics 6: Results
58
6. Results
The list of unsuitable components is displayed immediately after performing the calculation and it can be printed out. The calculated values for the individual components are displayed in the network wiring diagram. It can be printed on any output device for which a driver is available in the Windows (printer, plotter). The list of components with the calculation results - possibility to print tables. The list of components with their parameters - possibility to print tables including the list of cables.
59
6. Results
Print of the last calculation: eg. 3-phase short-circuit current 1
Print Preview
4
60
6. Results
Save of project: a) after definition of project (see Step 1) b) anytime during work c) after finishing project 1