Professional Documents
Culture Documents
Case Study of the U.S. District Courthouse Salt Lake City, Utah, USA
Presented by Boggarm S. Setty, P.E., ASHRAE Fellow President Setty & Associates, Ltd.
http://www.setty.com/
Abstract
Principles and Procedures of Total Building Commissioning (Cx) are
Presented as a Case Study of the U.S. District Courthouse in Salt Lake City,
Utah, USA The 10-story Building has an Approximate Floor Area of 357,000 Gross
Square Feet (33,166 Gross Square Meter) and has an Estimated Construction
Cost of $177 Million Focuses on Several Phases in Design Phase and Envelope Commissioning
http://www.setty.com/
http://www.setty.com/
Introduction
Most Buildings, if not Commissioned, Operate Ineffectively and Consume More Energy Commissioning Standards have been Developed for HVAC and Envelope System during the Past 10 Years GSA requires Commissioning Process for Quality Delivery; a Process for Achieving, Validating and Documenting Performance of Total Building and its Systems
The New U.S. District Courthouse in Salt Lake City, Utah, USA has been
Selected as a Case Study
http://www.setty.com/
Case Study
Design for the New Courthouse Started 10 Years Ago
FIG:
http://www.setty.com/
2 3
Curtain Walls, Opaque Walls, Doors, Roofing Chillers, Boilers, Pumps, Fan and Air Distribution System, Piping System, and Control Systems Switchgear, Transformers, Emergency Generators, Motor Control Centers, Distribution Panels, Exterior and Interior Lighting
2. Electrical Power
TAB:
All Rights Reserved |
System categories and examples of sub-systems, components and assemblies for commissioning in the new U.S. Courthouse in Salt Lake City
http://www.setty.com/
3. Sanitary 5 Indoor Environmental Quality (Pre- and Post-occupancy) 1. Air quality delivered by air handling units 2. Acoustics 3. Thermal conditions in occupied spaces 4. Lighting conditions in occupied spaces Case Study Focuses on System Categories 2 5
All Rights Reserved | http://www.setty.com/
CHART:
All Rights Reserved |
http://www.setty.com/
Findings
Findings from Design Reviews and Early Construction Field Testing
Case Study Focuses on the Envelope and MEP System Performance:
OPR Criteria for Commissioning the Systems were Incorporated into the Drawings and Specifications Enabled Coordination Sensor-controller-controlled Devices for the HVAC Control System were Identified on
Findings
Mock-up Tests for the Envelope System
Two sets of Mock-up Tests were Conducted on Envelope System
Fabrication of the Unitized Curtain Wall Panels were Observed by the CxA, with Specific Concern for Seals that would be Concealed when the Mock-up is Constructed
September 9, 2011: Mock-up of the Envelope was Observed by the CxA, with Particular Focus on the Quality of the Splice Joints and
http://www.setty.com/
Findings
On-site Test Method for Envelope System
Water Leakage Testing was Conducted in Accordance with ASTM E 1105-00 (Re-Approved 2008). The OPR and Procedures for Air Leakage Testing had not been Determined and Air Leakage Testing has not been Conducted. In Accordance with the ASTM Criteria to 0.2.5 CFM/sq ft of Fenestration.
http://www.setty.com/
Findings
On-site Test Procedure for Water Leakage
On May 23, 2012, a Static Pressure Water Penetration Test was Performed The Perimeter of the Test Chamber was Attached and Sealed to the Interior Faces of the Horizontal and Vertical Mullions Surrounding the Glazing at the Top
FIG: View of test specimen area from the exterior
FIG:
Findings
Performance Criteria for Water Leakage
Definition of Water Leakage Water Beyond a Plane Parallel to the Glaze Test Protocol no Water Leakage was to be Observed of the Test Area for 15 Minutes
Conclusions
Successful Total Building Commissioning (Cx) is Highly Dependent on the Clarity and Timeliness of the Criteria and Procedures that are Defined in the Owners Project Requirements (OPR) Cx is More than a Design Process; Commissioning of the Physical Systems to Pre-set Criteria from the Beginning is Critical to the Success
http://www.setty.com/
CO2
VOCs
CO
Filtration
Examples HVAC Controls: Design Review Controls Review OPR Issues Energy and Utility Goals Study of TAB Study of Sequences Pre-functional Tests Start-up and Verification Final Cx Plan Data Logger Program
| http://www.setty.com/
Thank you!
Contact Information: Boggarm S. Setty, P.E., ASHRAE Fellow President Setty & Associates, Ltd. www.setty.com bsetty@setty.com