Customer
Problem Description
Quantity Reported
ERA/ICA(Containment Action)
1)On receipt of the complaint, Screening has been started at Mahindra and defect free tyres are feed to the Line .-1500 tyres 2)Screening at JK Tyres ,Chennai Plant started- 809 tyres 3)All the concerned operatives and others were well informed about the issue and high level of awareness was created.
Problem Description: Tyres are identified with Trim knife cut mark on the tread portion at Mahindra Customer assembly line. Defect is shown below in the image
Mixing
Static Balancing
Stock preparation
Dynamic Balancing
Tyre Building
Tyre Curing
Warehousing
Vents to be trimmed
As cured
As cured
Trimming
Trimming Knifes
Radial Blade
Lateral Blade
6
Man
Machine
Missed to identify damage in First Line and Second Line Fire wall
Material Lightness
Method
Material
Man
Missed to identify damage in First Line and Second Line Fire wall Flash Trimming Knife cut damage Tire Holder Damage in Trimming Lateral Blade position incorrect Material Lightness
Checked in the Finished Good and tyres are identified Not possible by Flash removing knife .Flash is in the mid of the sidewall circumference Holder surface is smooth and no such issue Simulated and found the cut mark
Man
Insignificant
Machine
Insignificant
Machine
Significant
Material
No such defect in this tyre size from the start of the production itself and the defect records of Oct 13&Sep 13 also reveals the same
Insignificant
Why-Why Analysis
Lateral Trimming Blade Position incorrect (excess forwarding which caused tire damage)
Why
End effect was not known and the setting was common for all tires
Root Cause
Counter Measure
Tire specific Height and Time setting Carried in M/C to tire specific
Blade Required Po
Root Cause Analysis Cause Missed to identify damage in First Line and Second Line Fire wall
Why
Why-Why Analysis
Root Cause
Counter Measure
All the persons involved were counselled and high level of alert was created in CTP
10
Man
Missed to identify damage in First Line and Second Line Fire wall
Awareness created and the tyres are ensured with no such cut marks
Completed on 21.10.2013
Machine
Height and Time setting carried to tire specific. The same will be ensured in weekly check by maintenance
Completed on 21.10.2013
11
3 Levels Of Inspection
Dock Inspection-QA
12
Conclusion :
JK will ensure the defect free dispatch to M&M by maintaining the tyre specific heights/time setting in PLC and strengthening the Inspection at three levels(First Line Inspection by Production/Second Line Inspection by Quality and Final Dock Inspection by Quality)
JKTIL (CTP) will continue to ensure the above points to ensure there is no customer line hindrances henceforth.
13