Professional Documents
Culture Documents
Contractor Delay:
In construction claims, a Delay is the time during which some part of the construction projects has been extended or not performed due to an unanticipated circumstance.
March 2007
Disruption is an interruption in the planned work sequence or flow of work. It is distinguished from delay in that the duration of work activities or the overall project completion may not be extended.
March 2007
March 2007
March 2007
Excusable Delay
Compensable
time+$ time
March 2007
March 2007
March 2007
effective than network schedules for measuring delays. High visibility of bar charts
Fragnet
Is
March 2007
Schedule
Schedule must be
Reliable Reflect the Intended Plan Approved Free from Mistakes Free from Manipulations.
March 2007
10
March 2007
11
Schedule Manipulations
Sometimes difficult to discover. Only an expert scheduler can discover these changes. Hard to convince a judge or jury.
Do
computers lie?
March 2007
12
Schedules Mistakes
Dangling Activity (Open end activities) Fail to tie start of activities with submission shop drawing, approval, fabrication, and material delivery. Contractors fail to recognize and schedule other trade work,
March 2007
Schedule Manipulations
Reduced or Increased Activity duration. Manipulated in activities constraints. Manipulation of the activity status or history. Change schedule sequencing. Schedule the activity based on late start.
March 2007
14
Concurrent Delay
Delays that occur in parallel path activities in the same time period are classified as concurrent delays. The concurrent delays may be:
all
on critical paths, all on noncritical paths, or distributed between critical paths and noncritical paths.
March 2007
15
Concurrent Delay
Activity A Activity B Activity C Activity D Activity E Activity F
March 2007
16
Concurrent Delay
Activity A
EC Delay
Delay Activity B
Activity C
Activity D
NE Delay
Activity E Activity F
March 2007
17
Constructive Acceleration
Activity A
EC Activity B CA Activity C Activity D Activity E Activity F Original TF
March 2007
18
Concurrent Delay
of Critical Path as result of consumption of Total Float. Defining the concurrency period time. Defining the responsibilities of Concurrent Delay.
March 2007
19
Concurrent Delay
Concurrent Delay Any delay concurrent with EN delay Concurrent EC/NE delay
March 2007
Pacing Delay*
Pacing Delay Definition: Deceleration of the project work, by one of the parties to the contract, due to a delay to the end date of the project caused by the other party, so as to maintain steady progress with the revised overall project schedule. *
* Zack, 2000
March 2007
21
activity which has owner delayed events, or The activity which has the contractor delayed events, or
The
March 2007
22
March 2007
23
Time impact technique, But-for technique, Window (Snapshot) technique, Isolated Delay Type (IDT), and Window (But-For) technique .
24
March 2007
March 2007
25
March 2007
26
March 2007
27
March 2007
28
Project Start
Project Finish
PROJECT SCHEDULE
AsPlanned Schedule Start of Analysis Time of Analysis End of Analysis Adjusted Schedule As-Built Schedule
ANALYSIS SCHEDULE
Baseline Schedule Analysis Schedule As-Built Schedule
29
March 2007
Delay (NE) Excusable Compensable Delay (EC), and Excusable Non-compensable Delay (EN)
Consider changing of critical path Solve Concurrent Delay issues. Failure to address Pacing Delay.
March 2007
Delay Type
NE
Delay
7
E
I J C B L J
NE
NE NE NE EC EC EC
2
7 2 2 6 6 3
J
M
March 2007
EN
EN
3
5
31
Total Delay Days 43 Dr. Khalid Al-Gahtani, A specialized short course, King Saud University
March 2007
32
March 2007
33
As-Built technique
March 2007
34
As-Built technique
March 2007
35
March 2007
36
March 2007
37
March 2007
38
March 2007
39
March 2007
40
March 2007
41
March 2007
42
March 2007
43
March 2007
44
March 2007
45
March 2007
46
March 2007
47
March 2007
48
March 2007
49