You are on page 1of 26

The Life Cycle of A Large System Integration Project

3. PLANNING & PROCESSES

Contract Bid, Ref

PLANNING
Design Docs Solution Method Budget Schedule Criteria Budget Schedule

Budget Payment Schedule Resource Risk

Program Plan

Schedule Resource Risk

Project Plan

Engineering Plan

Subcontract Plan

Material Plan

Requirement Plan
Criteria Procedure Doc quality Requirement verification Objectives Participants Schedule

Integration Test Plan


Objectives Method Schedule

QA Plan

Kickoff
Team/ Resource plan Schedule

Unit Test Plan

Internal

External

Requirements SRS

Objectives Method Schedule

PROGRAM PLAN
BASE DOCUMENTS:
BID PROPOSAL: solution CONTRACT: what we promised, schedule, price REFERENCES: estimation and document format

TEAM:
Program Manager, Contract Manager Chief Engineers

OUTPUT:
PROGRAM PLAN, reviewed by AQ and approved by business director

KEY CONTENTS:
Objectives and reference projects Scope and process Selection Budget: Material (LAB), manpower, Travel cost Payment schedule and Cash flow Skill set and manpower distribution Contract & subcontractor management Quality Control RISK management (program level:emergency plan) Project and review schedule and milestone Customer visit plan Contract Book structure

ENGINEERING PLAN
BASE DOCUMENTS:
BID PROPOSAL: solution CONTRACT: what we promised PROGRAM PLAN: schedule REFERENCES: experiences and document format

OUTPUT:
ENGINEERING PLAN, Reviewed by QA and approved by Program Manager and Engineer Manager

TEAM:
Chief Engineer, Network Engineer, Software Engineer

KEY CONTENTS:
High level overview System architecture Software architecture System operation Technology and Prototype Tasks and quality control in every step of the process: requirement to acceptance test Integration test methodology Devices CMMI execution plan Subcontract items list Major material selection

PROJECT PLAN
BASE DOCUMENTS:
PROGRAM PLAN: schedule, manpower, ENGINEERING PLAN: solution, REFERENCES: experiences and document

OUTPUT:
PROJECT PLAN, reviewed by QA and approved by Program Manager

TEAM:
Project Manager, Program Manager, Chief Engineers

KEY CONTENTS:
Schedule Skill set and manpower management Process execution Lab establishment Milestone (deliverable) management Risk management Requirement management Relation with other functions: QA, PM, Monthly and weekly report plan

REQUIREMENT PLAN

BASE DOCUMENTS:
PROJECT PLAN: schedule ENGINEERING PLAN: solution, REFERENCES: experiences and document

OUTPUT:
REQUIREMENT PLAN, reviewed by QA and approved by Project Manager

TEAM:
Engineers, Chief Engineer, Project Manager

KEY CONTENTS:
Schedule Questionnaires for all parts

CONTRACT MANAGEMENT
Contract manager is specialized in contract execution and has legal background and sufficient knowledge of companys charging structure.
When risks caused by customers, he/she must evaluate the impact and estimate its associated cost, and sends memorandum to customer. A personal visit may be necessary, get layer involved when issues become serious. Know the process and procedure of arbitration and suit Participate in milestone review meeting with the Program Manager.

SUBCONTRACT MANAGEMENT

With combined functions of a program manager and a contract manager, but at a smaller scale Identify potential vendors

Access vendors profile and evaluate their qualification


Contract negotiation: price, schedule Supervise the vendors activities

Risk management

WATERFALL MODEL (1)


(Winston Roy 1970)
Requirement

Design Coding & unit test

System Integration
Operation & maintenance

WATERFALL MODEL (2)


(Winston Roy 1970)

Advantages: A better model than the primitive model: code/fix Recognize the need for feedback loops between stages.

Disadvantages: When requirements are huge, a project may never get into the design phase before deadline. Does not reference prototyping activities.

V-SHAPE DEVELOPMENT PROCESS


Requirement

Test Plan

Design

Test Model

Coding & unit test System Integration Operation & maintenance

Test Case

Test Data

DEVELOPING PROCESS
REQUIREMENT, CONFIGURATION AND RISK MANAGEMENT Requirements specification approved by customer Integration planning UT planning

High level design

Detail design

Coding

Code review

Unit testing

Subsys testing

Integration System test planning FAT Warranty Installation Document

System testing

CODE INSPECTION AND UNIT TEST


Design

Coding

Unit Test Plan

Code Inspection

Unit Test Plan System Integration

CHANGE CONTROL
New change requests or stars
ARCHIEVE

N REDO

Change Control Board (CCB)

Initial Investigation N Y/N

Design & Modification

DONE

Estimation

Local Test & Regression Test

Fix Delivery & CLOSE

Y/N Feasibility Study

Y/N

Fix DONE

Cumulative cost

SPIRAL MODEL (1)


(Barry Boehm 1988)
Risk-Driven and Incremental Model

Progress through steps

Determine objectives, Alternative, constraints Risk analysis Risk analysis

Risk analysis

Evaluate alternatives Identify, resolve risks

Prototype Prototype Prototype Commitment Partition Requirements plan lifecycle plan Development plan

Concept of operation
Requirement validation

Software requirement Software product design Unit test Code

Integration and test plan

Design validation and verification Develop, verify Next-level product

Plan next phases

SPIRAL MODEL (2)


(Barry Boehm 1988)
Risk-Driven and Incremental Prototype Model

It works for large projects with complicated requirements that can be divided into phases

It is driven by a series of risk-driven prototype followed by a structured waterfall-like process


Multiple feedback opportunities with the users and customers to get Yes. Buts out early

ITERATIVE MODEL (1)


(Krutchten 1995)
Inception Elaboration Construction Transition

Prelim Iteration

Arch Iteration

Dev Dev Iteration Iteration


Release Release

Trans Iteration
Alpha Release Beta Release

Release

Release

Product Release

Inception: focus on understanding the business of the project, project scope and feasibility; define estimated schedule, budget, risk; the Vision document is created. Elaboration: Refine the requirements, executable architecture; early prototype(s) is developed and demonstrated for validation. Construction: focus on implementation, architecture and design are fully developed; most of code are done. Transition: alpha, beta (testing) releases are done and deployed for use internally or by customers.

ITERATIVE MODEL (2)


Inception Process Workflow
Requirement Analysis/design Implementation Test Deployment

Elaboration

Construction

Transition

Supporting Workflow
Configuration Change Management Project & process Management

ITERATIVE MODEL (3)


Inception Theory and Concept Group

THE DOOD PROJECT


Deductive Object-Oriented Database Based on Predicate Logic Support recursion Datarulesqueries are in the same format

Elaboration Design Group

Construction Development Group


P (manager, employ) select P1(manager), P2 (employee) from P1 as P , P2 as P where P1.employee = P2 (manager); P (manager m, employee e) -> P1 (m, e) ; P (manage m, employee e) and P (manager e, employee x) -> P1 (m, x);

Transition Release Group

Alpha

Beta

M-GATE PROCESS
MARKET INTELLIGENCE AND ANALYSIS PHASE

MPP
Market Product Planning

SPD
System Product Development

Business Case Development Phase

The Market and Product Planning (MPP) M-Gates, M-15 through M-11, address the Market Intelligence and Analysis, Business Case Development, and Portfolio Planning phase of the Marketing Activities associated with candidate project. The MPP M-Gates result in the development of a Business Solution. This Solution is transitioned to the System and Product Development (SPD) Project M-Gates activities of Project Definition, Implementation, Launch and Close out.

M-Gate 15

M-Gate 14

M-Gate 13

Portfolio Planning Phase

M-Gate 12

M-Gate 11

Project Definition Phase

M-Gate 10

M-Gate 9

M-Gate 8

M-Gate 7

Implementation Phase

M-Gate 6

M-Gate
5

M-Gate 4

M-Gate 3

Launch & Closeout Phase

M-Gate 2

M-Gate
1

M-Gate 0

M-GATE BUSINESS OBJECTIVES


M-Gates defines a set of requirements that must be satisfied by all proposed solutions from different sectors/business units enabling the selection of cross-sector solutions that are the best fit for the company and its customers. Clearly define roles and responsibilities that are cross-sector and cross-functional to enable efficient and sound decisionmaking.
Clearly identified and documented M-Gate decisions that allow all sectors and business units to understand why certain solutions are selected and why others are not, which helps sectors understand the overall strategy of the company.

SPD M-GATE PROCESS (1)


Project Definition Phase
Project Initiation
M-Gate 10

System Requirement Baselined


M-Gate 9

System Requirement Allocated


M-Gate 8

Contract Book Baselined & Approved


M-Gate 7

Implementation Phase
Design Readiness
M-Gate 6

System Test Readiness


M-Gate 5

Ready For Field Test


M-Gate 4

Ready For Controlled Introduction


M-Gate 3

Launch & Closeout Phase


Volume Development
M-Gate 5

Retirement Plan
M-Gate 4

End of Life
M-Gate 3

SPD M-GATE PROCESS (2)


Project Definition Phase (M-Gate 10 M-Gate 7)
Deliverables: Project Plan, Engineering Plan, Quality Assurance Plan, Requirement Plan, Requirement Specification, System Architecture Key Note: These deliverables are base lined in a formal contract book that defined the projects commitment to deliver the specified system, product or platform within the identified schedule and cost targets.

Implementation Phase (M-Gate 7 M-Gate3)


Deliverables: Integration Test Plan, High Level Design, Low Level Design, Code, Unit Test Plan, Test Reports Key Notes: These deliverables are the design, implementation, the implementation, and validations of the product according to the allocated requirements. Each performing team organization may have its own unique development lifecycle for this phase.

Launch & Closeout Phase (M-Gate3 M-Gate 0)


Deliverables: Final Acceptance Report, User Manual, Operation Manuals Key Notes: All required sources, manufacturing, sales, customer services, and marketing process are in-place for volume production until a trigger is activated for the retirement or the the product. If the product is a system, the deliverable signals the end of the project and maintenances/services process begin.

SPD M-GATE PROCESS (3)


Complete -- all applicable requirements and associated criteria have been evaluated and are completed

In Progress -- not all of the applicable requirements and criteria have been completed, the project has not deviated from the inter
A risk assessment has been performed and an action plan developed, with owners, complete with triggers and final due dates that are tracked at a solution level. The review board at the specific M-Gate will approve these action plans, complete execution or which is required for final completion of the gate or Activities are in progress, and on target; but not enough to satisfy gate completion

Significant Issues -- this status arises when the project is deviating from the intent (e.g., critical success factors, schedule etc) and this condition can occur due to one or a combination of reasons:
Majority of the requirements and criteria have not been completed Associated action plans are incomplete Factors or influences external to the project are impacting the project to an unacceptable extent To proceed with the current status would incur unacceptable risk Not started or late

No Issues not started yet

M-GATE IN SPIRIL LIFECYCLE MODEL


Gate 3 Gate 4
Contract Book Baselined & Approved Ready for Field Test

Gate 2

Gate 1

Gate 0
End of Life

Volume Retirement Ready Ror Plan Controlled Development Approved Information

Launch & Closeout Phase

Gate 10

Gate 9

Gate 8

Gate 7
System Validation &verification

Project System Req System Req Definition Baselined Allocated

Definition Phase Gate 5


System Test Readiness

Start

Design Implementation Subsystem Integration & Evaluation

Next Level Requirement

Gate 6
System Design Readiness

LINEAR CHAN FOR MULTIPLE PRODUCT GENERATIONS


Initial Product Development
Definition Phase Implement Phase Launch & Closeout Phase

Gate 10

Gate 7

Gate 3

Gate 2

Gate 1

Gate 0

Product Enhancement
Definition Phase Implement Phase Launch & Closeout Phase

Gate 10

Gate 7

Gate 3

Gate 2

Gate 1

Gate 0

You might also like