Professional Documents
Culture Documents
Sunk costs
Learning curve theory Reserves
Contingency Reserves Management Reserves
COST ESTIMATING
To complete projects within budget constraints
-25% to +75%
Budgetary
-10% to +25%
Definitive
Provides details Later in the for purchases , project less than estimates actual
-5% to +10%
Computerized tools
Spreadsheets Project management software
Typical problems with IT Cost Estimates Complex task Lagging experience Communication
144000
20%
104 100
$4600 4200
$76,000 $20000
$76000 $614000
5% 40%
Testing
Training and support
$69000
$69000
5%
2000
$1275
$156000
$202,400
13%
Actual cost
Earned value Cost variance Schedule variance Cost performance index Schedule performance index
50%
EV=10000 X 50% =5000 CV=5000-15000= -10000 SV=5000-10000= -5000 CPI=5000/15000 = 33% SPI=5000/10000 = 50%