You are on page 1of 35

25

th
Feb 2013
Reputed for its ability to execute large and complex industrial
infrastructure projects
Tata Projects is one of the fastest growing and highly admired
Infrastructure companies in India

TATA Projects Limited

Safety First
Safety
Mission-
Creating
Zero Harm
Work place
Safety
Awareness
Safety
Implementation
System
Implementation
Safety Audit
,Review &
Learning
Safety KPMs in:
BSCs of all SBUs
KRAs of SBU Heads, PCs, PDs &
RCMs
OHSAS 18001 &ISO14001
implemented across all locations &
project sites
Lead Lag Measures all sites
OCP / Method statement for
critical activities
Induction training for
Employees & subcontractors
Daily Safety Tool Box Talks
at all Sites
Visual displays at sites and
offices
Height work training and
Height work pass
Safety inspections
Safety alerts
Executive safety checklist
Corporate Safety Council review
ORM-Safety review
Reviews in BRMs, Board level
EHS Policy
Safety record
Project site
Safe Million Man-
hours worked
Krishnapatnam power
Plant
32
SAIL, Rourkela 7.5
IPP- Jharsuguda 15.6
BPCL,Kochi-(Part A & B) 3.3
RINL,VSP, Vizag 4.0
ONGC , Rajahmundry 2.1
NSC
Krishnapatnam SAIL - RSP
HPCL RAK Gas
EHS Statistics for Projects executed by TPL in Oil, Gas & Hydrocarbons
YEAR 2007-08 2008-09 2009-10 2010-11 2011-2012
2012-13
(till date)
TOTAL
Number of employee Project man
hours worked
398650 2764280 5015903 5602213 1134271 2499066 17414383
Number of Project fatalities
0 0 0 0 0 0 0
Number of Reportable Lost Time
Cases (Lost Time Cases)
0 0 1* 0 0 0 1
Number of other recordable
cases
0 0 0 0 0 0 0
Incidence Rate (total recordable
cases x 200,000/total work hours)
0 0 0.39 0 0 0 0.013
Number of EHS Issues / Legal
Notices
0 0 0 0 0 0 0
* Minor head injury suffered by worker being hit by bolt falling from height. He was equipped with safety helmet.
Quality @Tata Projects
Approvals
Empanelment
Central Boiler Board (CBB)
Petroleum and Explosive Safety Organisation
(PESO) (Formerly known as CCOE)
Warehousing Development and Regulatory
Authority (WDRA)

Petroleum & Natural Gas Regulatory Board
(PNGRB)
Rural Electrification Corporation (REC)
Research Designs and Standards Organisation
(RDSO)


ISO 17020
TQ Services is accredited by NABCB of Quality
Council of India.
ISO 17021
TQ Services is accredited by NABCB to issue ISO
9001 Certification.
Accreditations
ISO and OHSAS Certifications
ISO 9001 : Quality
Assurance
ISO 14001 :
Environment
Management
OHSAS 18001 :
Occupational Health
& Safety
Management
Organizational Flow
CORPORATE OFFICE
HYDERABAD
REGIONAL OFFICE
KOLKATA
REGIONAL OFFICE
DELHI
REGIONAL OFFICE
MUMBAI
76 Projects
at 51 locations
Domestic Project Sites
Global reach SBU QS
Experience of working in these countries, surveyors present there.

Existing Offices

India
Italy
Spain
Turkey
Oman
South Africa (JV)
Bahrain
China
Saudi Arabia
Abu - Dhabi
South
Korea
Egypt
Mauritius (JV)
Vietnam
Kuwait
Syria
Tunisia
Poland
France
Switzerland
Netherlands
Denmark
Germany
Sweden
Belgium
Kazakhastan
Taiwan
Thailand
Malaysia
Indonesia
USA
More than 100 surveyors are deployed outside India and we have experience of working in 32 countries
1205
502
630
Managerial Supervisors
Staff
84
146
215
923
308
384
68
13
Managerial
Supervisors
Staff
Non-Technical Technical Professional
Our Team
Over 2000 + strong, carefully chosen for their knowledge,
capabilities, attitude and value system
Distribution 70% Technical Manpower
Growth Trajectory
All Figures are in Rs Crs
2007-08 2008-09 2009-10 2010-11 2011-12
3,404
7,276
6,460
7,345 7,370
Closing Order book (As on 31
st
March)
2007-08 2008-09 2009-10 2010-11 2011-12
1,371
1,952
2,780
3,097 3,123
Turnover
CAGR : 23 %
2007-08 2008-09 2009-10 2010-11 2011-12
90
128
240
303
276
EBITDA
CAGR : 32 % CAGR : 21 %
TATA Projects - Engineering Capabilities
3 Pole Engineering Centre (at Hyderabad, Kolkata & Mumbai)
Competent engineers with relevant experience
Incorporation of Modern Software Tools
Work Flow based Engineering Document Management System
In house and Review Engineering capabilities
Embedment of Safety & Constructability in Engineering
Access to the latest National & International standards (i.e. IS, ASME, API, AWWA, BS, PTC,
IEEE, IEC etc.)
Head Corporate Engineering
Hyderabad Pole Kolkata Pole Mumbai Pole
Engineering Softwares
Mechanical Discipline
Auto CAD Full version 2013.
Pipenet standard version 1.40 for analysis of fluid
flow networks
CAESAR-II version 5.30 for Pipe stress analysis
Pvelite version 2012 for Vessel and Exchanger
analysis
CADWORX Plant version 2013 for 3D Modeling
Autodesk Navisworks manage version 2013-3D
Smart plant 3D review software version 2012
Engineers Draughtsmen
Mechanical 47 14
Civil 29 10
Electrical 17 5
Instrumentation 11 2
Total 106 31
Civil Discipline
STADD Pro V8i with IS codes for Structural
analysis & design
STADD Foundation V8i for foundation analysis &
design
STADD Pro Steel V8i
ANSYS version 13.1 for Finite Element analysis
I-Towers 2.0 for Analysis & Design of Towers
PLS Towers for Analysis & Design of Towers
PLS CAD for Profile preparation
2D Plus Plate cutting plan software
Highbar Technologies Rebar software
Electrical Discipline
ETAP for Electrical System Studies
EPlan for Panel design/wiring drawing


About our SBUs


16
Background
184
259
451
475
938
1371
1952
2780
3097
3122
Establised
1979
2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12
ISO 9001, 14001 and OHSAS18001
Fastest Growing Construction Company
Top Ten Most Admired Construction Companies
Certifications
A
w
a
r
d
s

2 x 800MW
BOP
Krishnapatnam
Largest Blast
furnace - RSP
Largest Blast
furnace - NMDC
2 x 500MW
BOP Bhusawal Figures in Rs. Cr.
Well Pad Field
Development
Cairn Energy
EPC for Oil
Terminal
EMARAT
Power
Key Projects
2x500 MW BoP Thermal Power Plant for MahaGenco
2x800 MW BoP Thermal Power Plant for APGenco
3x67.5 MW Total EPC Gas based Power Plant for IEL
Customized turnkey solutions for thermal power plants
Expertise in coal and gas based, super and subcritical
technologies
Transmission
Key Projects
194 Kms 400 kV D/C Kishenpur Transmission Line
152 Kms 765 kV S/C Seoni Transmission Line
313 Kms 800 kV HVDC Barabisa Transmission Line
A leader in building transmission infrastructure
Construction experience in tough ,hilly and snowy terrains
Commissioned more than 10,000 Kms of transmission lines
State-of-the-art Tower Manufacturing Unit
Metals
Key Projects
4506 m3 Blast Furnace of 3 MTPA Steel Plant,
Nagarnar for NMDC
4060 m3 Blast Furnace of 4.2 MTPA Steel Plant,
Rourkela for SAIL
1.2 MTPA pellet plant at Donimalai for NMDC
End to end customized solutions for Ferrous and
Non-Ferrous industries
Expertise in executing Blast furnaces, Ore
beneficiation plants, Pelletization plants
Railways
Key Projects
240 TKm OHE of Chhapra section for CORE
355 TKm OHE, S&T of Gooty section for RVNL
350 TKm OHE of Kondapuram section for RVNL
Proficient in executing railway electrification, signaling &
telecommunications works, bridges and earthworks.
Executed over 1800 track km of projects
Poised to take on large and complex Freight Corridor projects
Water
Key Projects
Water System for Steel Melting Shop for RINL
Water System for 3 MTPA Steel Plant at Jamshedpur for
Tata Steel
Water System of Hot Strip Mill at Kalinganagar for Tata
Steel
Expertise in Industrial water systems for steel and power
Desalination and effluent treatment
Collaboration with world renown technology providers
Manufacture RO based Water Purification plants
Quality
Inspection Services
6x800 MW Medupi Power Station for Eskom Holdings South Africa
400 kV Transmission Line for Jaypee
Gas Field Development Project at Turkmenistan for Petrofac
International
Provides comprehensive inspection, certification and training services
across all infrastructure sectors
Large base of over a 1000 clients spread across 80 countries
Known for our responsiveness and ontime completion of assignments
Oil & Gas
Key Projects
Gas Processing & Compression at Rajahmundry for ONGC
Oil Blending Terminal at Radhanpur for Cairn Energy
EPC for Expansion of Petroleum Product Storage at Fujairah for
EMARAT
Solutions in Oil & Gas to the Indian and Middle East markets
Expertise in executing mid and downstream projects including refinery
expansion, tank farms, terminals, on-shore oil field development and
process plants
Key Projects Oil, Gas & Hydrocarbons
Cairn Energy, Mangala Processing Terminal
Brief Scope of Work
Construction of 2 Nos. of crude oil storage tanks, 2 Nos. of settling tanks, new pipe rack, strengthening of
existing pipe rack, equipment foundations with all Civil, Piping and Equipment erection with electrical
/Instrumentation works..
Extension of existing fire fighting and protection system to provide complete coverage for new facility.
Design supply and installation of Electrical heat tracing.
Hook up to the electrical feeders in the substation .
Fabrication of off skid piping, inspection, NDT, testing, painting, erection, insulation and hook up with existing
system.
Hook up new instruments to local control system in and integrate with existing ICS. Modification of ICS and
integration with existing YOKOGAWA systems.
E&I Cable tray interfaces with other contractors.
Completion Management System implementation.
Conduct Geotechnical investigation survey in new tank area to verify data.
Existing Plant Model updating in PDS, procurement of piping components. Extension of sleepers or addition of
pipe racks/sleeper, if required.
Critical Packages:
Crude Oil Export Pumps (2 Mw Motor)
Fiscal Oil Metering Skids.
ICS/DCS.
Scope Contd .
U/G System design for open, closed drains, storm water systems, fire water systems etc.
Statutory approvals including DGMS, PESO etc. with the help from CEIL.
Pre-Commissioning and performance guarantee test runs. Design, specify, tender, evaluate, procure and review
vendor drawings, etc. of packages/long lead items .

2.1 Lakh
Man Hrs
Zero LTI
ONGC, Revamping of Fire Water Network at Uran
Brief Scope of Work
Dismantling & Removal of existing fire water network.
Construction of Fire station building, sub-station, fire water pump house, raw water reservoir & control room.
- Substation ( 35m x 24 m x 8.7 m G + 1 )
- Fire Station Building ( 44.2m x 15m & 12.5m x 35m , Ht- 13.2m G + 2)
- Fire Water Pump House ( 68m x 15m & 20m x 5m - 12m Height )
- Raw Water Reservoir ( 105m x 30.4m to 17.4m x 5 m) 8000 Cu.m
RCC foundations, roads & drains, pipe pedestals & sleepers.
Site grading & all associated civil & structural work.
Construction of Raw Water Tank & Fire Water Steel Tanks.
- Fire Water Tank 2 nos. ( 38 mm Dia x 20 mm Ht. - 18000 Cu.m each)
Supply & erection of Diesel Engine Driven (5 no.s 1000m3/hr each) & Motor driven Jockey Pumps
(4 no.s 1000 m3/hr).
Entire fire water piping (A/G & U/G)
- Piping 24.3 KM. ( Sizes- 1 to 42 - 31428 Inch Dia / 373092 IM )
ONGC, Revamping of Fire Water Network at Uran
Scope Contd
Supply & Installation of hydrant landing valves & hydrant monitors.
- HVLR Manual Monitor ( 4000 GPM) 7 Nos.
- HVLR Remote Control Monitor ( 4000 GPM ) 8 nos.
- Water Monitors ( 1000 GPM ) 4 Nos.
- Hydrants - 386 Nos & Water Monitor- 114 Nos.
All associated Electrical and Instrumentation works.
- Transformers 6 Nos. ( 7.5 MVA 2nos, 1 MVA -2 nos. 50 KVA 2 nos.)
- MV Switch Board & Auxiliary Switch Board 415 V
- HV Switch Board - 22 KV & 6.6 KV (1 each)
- PLC & DCS Modifications
- Field Instruments Pressure / Level Transmitters , Pressure Gauge, Annubar
- Fire Alarm System
- Cables - 47 Km.
- Plant Communication System
- HVAC / Ventilation System
Commissioning, Trail run Test of New System.

6 Lakh Man
Hrs
Zero LTI
Emirates General Petroleum Corporation (EMARAT)
Expansion of Petroleum Products Storage and Distribution Terminal at Fujairah
Brief Scope of Work:
Dismantling of existing truck loading gantries & pump house.
Integrity up gradation of Bulk piping between 13 tanks , pumps and equipments.
Supply, Fabrication & erection of Pig launcher & receivers at port and tank farm respectively.
Supply, Fabrication & erection of Tank Truck Loading Rack.
Supply & Installation of 3000 valves (manual & actuated)
Improvement in Jetty area, head & manifolds.
Supply, Fabrication & Erection of Drinking Water Distribution ,Service water line.
Relocation of Weigh Bridges.
Supply & Installation of 23 pumps for Gas Oil/Jet A1/MS Export/Blending etc.
Fire Fighting and Fire Protection System.
Supply & installation of hydrant landing valves, hydrant monitors.
New hydrant network for the entire terminal.
Sprinkler System, Foam tanks & foam line for entire terminal.
Installation of manually operated hydrants & water -foam monitors.
Substation including transformer, switchgears, DG etc.
Communication system with replacement of entire terminal cables.
Complete Instrumentation for control/monitoring, ESD, Data Server, MOVs, Tank gauging system
Terminal Automation Control System including PLCs, Control Panel, Rack Computer, Ethernet Switch etc. .
Radar Level Transmitters with multipoint temp element.
Oily water treatment package unit.
One Hot Oil heater package Unit.
2.8 Mn
Man Hrs
Zero LTI

Emirates National Oil Company, Dubai, UAE
Engineering, Procurement & Construction of Oil Terminal Facilities inside Fujairah Port, UAE.

Brief Scope of Work:
Design, Engineering, Supply & Construction of Administrative Building (G+1), Switchgear & transformer Building,
Ship loading Pump House/ shed & fire water pump, Pigging station, Security cabin, Car Parking.
All associated structural pipe racks, columns, supports, bridges, walk away platforms, construction of OWS,
Terminal Roads & Drainage System, Foundations for various equipments, pumps, tanks & vessels, valve etc.
Flush tanks, Fresh Water Tanks, Diesel Storage Tanks, Slop Tanks, Pig Launchers & Receivers
Installation, Testing & commissioning of 6 Nos 1450m3/hr centrifugal pumps with electric motor & 3 Nos
900m3/hr diesel driven.
Piping from jetty to terminal & terminal product piping.
Valves, Radar gauges, Temperature elements, Actuators for all tanks .
Fire Protection system with all mainlines & Interconnection pipes, main fire water pumps,
fire monitors, fire alarm system.



1.2 Mn
Man Hrs
Zero LTI
Cairn Energy, Aishwarya Field Development
Brief Scope of Work:
Nine (9) Well Pad facilities for Aishwarya cluster of Well Pads and In-field road corridors with manifold, flow
meters, utilities and other infrastructural development.
Production fluid, fuel gas and water pipeline for other purposes from MPT to Well Pads.
33 KVA Overhead power transmission lines from MPT to Well Pads.
Instrumentation, Fire Alarm system, IT (Data & Voice), PAGA, CCTV, Access Control and other E&I packages.
Other Mechanical, Piping, Electrical, Instrumentation, Civil & Structural Works for all 9 well pads including
infield & trunk pipelines for oil/gas/water and integration.
Tie-in and seamless integration of the new facilities with existing facilities at MPT and other locations.
Concurrent Commitments Cairn India
2.5 Mn
Man Hrs
Zero LTI
Other Significant Projects
Oil & Natural Gas Corporation (ONGC)
Low Pressure Gas Processing and Compression Facilities
Gas Collection Station Expansion Project at ONGC Olpad, Gujarat.
Steam Heater In CSU Train 15 At CPF, Ankleshwar, Gujarat.
Additional Condensate Recovery Unit for LPG Augmentation at CPF, Gandhar, Gujarat.
Revamp & Expansion of Gas Gathering Station-VI (GGS-VI) at Ankleshwar, Gujarat.
Gas Lift Compressors at CPF, Gandhar, Gujarat.
Cairn Energy
EPC for Radhanpur Blending Terminal.

Rak Gas LLC, Ras Al Khaimah
Bukha Control Reconstruction (BCR), Revamping of all the Pneumatic Instruments.



ADNOC - Abu Dhabi
Ruwais Oil Refinery Project - Electrical and Instrumentation Works.

Special Projects
Defence Research & Development Organisation (DRDO), Compressed Air Facility at Research Centre, Hyderabad.
Indian Space Research Organisation (ISRO), Shriharikota, Design, Manufacturing, Supply, Installation, Testing &
Commissioning of Casting Facility Equipment.
Long
Reliable
Warranty

Total Solution
High Quality
Control
System
World
Wide
Network
Financial
Strength
Long
Reliability

Good bankability.
Zero Debt company.
Internal funding capability through
cash reserves.
Capital funding availability through
TATA Capital.
Wide Global Presence.
Presence in 32 countries
through SBU QS.
Group companies presence in
85 countries.
Highest safety standards.
Prime importance to safety.
Continuous safety training.
Intense safety practices monitoring
through support safety dept.
Dedicated SBU QS for Quality
Control.
Rarest construction companies to
have all three certifications of
ISO 9001, ISO14001 & OHSAS 18001
Our Strengths
Why TATA Projects ?
Client Appreciation

You might also like