What you will learn
The purpose of Sampling
How to draw a statistically valid Sample
How to Develop a Sampling Plan
How to construct an O-C curve for your sampling
plan
How to use (and understand) ANSI/ASQ Z1.4
How to use ANSI/ASQ Z1.9
Assessing Inspection Economics
Acceptance Sampling Webinar
20101129 4
What is Sampling
Sampling refers to the practice of evaluating
(inspecting) a portion -the sample - of a lot the
population for the purpose of inferring information
about the lot.
Statistically speaking, the properties of the sample
distribution are used to infer the properties of the
population (lot) distribution.
An accept/reject decision is normally made based on
the results of the sample
Sampling is an Audit practice
Acceptance Sampling Webinar
20101129 5
Why Sample?
Economy
Less inspection labor
Less time
Less handling damage
Provides check on process control
Fewer errors ???
i.e. inspection accuracy

Acceptance Sampling Webinar
20101129 6
What does Sampling not do?
Does not provide detailed information of lot quality
Does not provide judgment of fitness for use (of
rejected items)
Does not guarantee elimination of defectives any
AQL permits defectives

Acceptance Sampling Webinar
20101129 7
Sampling Caveats
Size of sample is more important than percentage of lot
Only random samples are statistically valid
Access to samples does not guarantee randomness
Acceptance sampling can place focus on wrong place
Supplier should provide evidence of quality
Focus should be on process control
Misuse of sampling plans can be costly and misleading.
No such thing as a single representative sample
Acceptance Sampling Webinar
20101129 8
Representative Sample?
There is no such thing as a single
representative sample
Why?
Draw repeated samples of 5 from a normally
distributed population.
Record the X-bar (mean) and s (std.dev) for each
sample
What is the result?

Acceptance Sampling Webinar
20101129 9
Distribution of Means
The Distribution of Means obeys normal distribution regardless of
distribution of parent population.
Acceptance Sampling Webinar
20101129 10
Standard Error of the Mean
Central Limit Theorem
The relationship of the standard deviation of sample
means to the standard deviation of the population
Note: For a uniform distribution, Underestimates error by 25% with
n=2, but only by 5% with n=6
Acceptance Sampling Webinar
20101129 11
The Random Sample
At any one time, each of the remaining items in the
population has an equal chance of being the next
item selected
One method is to use a table of Random Numbers
(handout from Grant & Leavenworth)
Enter the table Randomly ( like pin-the-tail-on-the-
donkey)
Proceed in a predetermined direction up, down, across
Discard numbers which cannot be applied to the sample
Acceptance Sampling Webinar
20101129 12
Random Number Table
Source: Statistical Quality Control by Grant &
Leavenworth
Acceptance Sampling Webinar
20101129 13
Stratified Sampling
Random samples are selected from a homogeneous lot.
Often, the parts may not be homogeneous because they were
produced on different machines, by different operators, in
different plants, etc.
With stratified sampling, random samples are drawn from
each group of processes that are different from other groups.
Acceptance Sampling Webinar
20101129 14
Selecting the Sample
Wrong way to select sample
Judgement: often leads to Bias
Convenience
Right ways to select sample
Randomly
Systematically: e.g. every nth unit; risk of bias occurs
when selection routine matches a process pattern
Acceptance Sampling Webinar
20101129 15
The O-C Curve
Operating Characteristic Curve
P
a
Percent Defective
Ideal O-C Curve
Acceptance Sampling Webinar
20101129 16
The Typical O-C Curve
Acceptance Sampling Webinar
20101129 17
Sampling Terms
AQL Acceptable Quality Level: The worst quality
level that can be considered acceptable.
Acceptance Number: the largest number of defective
units permitted in the sample to accept a lot usually
designated as A
c
or c
AOQ Average Outgoing Quality: The expected
quality of outgoing product, after sampling, for a
given value of percent defective in the incoming
product. AOQ = p * P
a
Acceptance Sampling Webinar
20101129 18
Sampling Terms (cont.)
AOQL Average Outgoing Quality Level: For a
given O-C curve, the maximum value of AOQ.
Rejection Number smallest number of defective
units in the sample which will cause the lot to be
rejected usually designated as R
e

Sample Size number of items in sample usually
designated by n
Lot Size number of items in the lot (population)
usually designated by N
Acceptance Sampling Webinar
20101129 19
Sampling Risks
Producers Risk : calling the population bad
when it is good; also called Type I error

Consumers Risk : calling the population good
when it is bad; also called Type II error
Acceptance Sampling Webinar
20101129 20
Sampling Risks (cont)
Acceptance Sampling Webinar
20101129 21
Acceptance Sampling
II
Acceptance Sampling Webinar
20101129 22
Constructing the O-C curve
We will do the following O-C curves
Use Hyper-geometric and Poisson for each of the
following
N=60, n=6, A
c
= 2
N=200, n=20, A
c
= 2
N=1000, n=100, A
c
= 2
N=1000, n=6, A
c
= 2

Lets do k (A
c
, c - # of successes) = 0 first

Acceptance Sampling Webinar
20101129 23
Hyper-geometric
The number of distinct combination of n items
taken r at a time is
Acceptance Sampling Webinar
20101129 24
Hyper-geometric (cont)
Construct the following Table
p D=Np P(k=0) P(k=1) P(k=2) P(k 2)
0 %
1%
2%
3%
etc.
A Hyper-geometric calculator can be found at www.stattrek.com
Note: The Hyper-geometric distribution applies when the population, N, is
small compared to the sample size, however, it can always be used.
Sampling is done without replacement.

= (
D
C
k

Nq
C
n-k
) /
N
C
n
Acceptance Sampling Webinar
20101129 25
Hypergeometric Calculator
N = 100 D=Defects in Pop.
n = 10
p D=Np Nq=N-Np P(k=0) P(k=1) P(k=2) P(k 2)
K 0 1 2
0% 0 100 1 1
1% 1 99 0.9 0.1 1
2% 2 98 0.809091 0.181818 0.009091 1
3% 3 97 0.726531 0.247681 0.025046 0.999258
4% 4 96 0.651631 0.2996 0.045961 0.997192
5% 5 95 0.583752 0.339391 0.070219 0.993362
6% 6 94 0.522305 0.368686 0.096458 0.987449
7% 7 93 0.46674 0.38895 0.123549 0.97924
t ot al
successes
in Popl.
Acceptance Sampling Webinar
20101129 26
Hypergeometric Calculator
Example: p=0.02, k=0, N=100,
n=10
Acceptance Sampling Webinar
20101129 27
Hypergeometric Calculator
Example: p=0.02, k=0, N=100, n=10
Acceptance Sampling Webinar
20101129 28
Hypergeometric Calculator
Example: p=0.02, k=0, N=100, n=10

P (k=0) = 0.809091
P (k=1) = 0.181818
P (k=2) = 0.009091
-----------------------
P(k2) = 1.0
Acceptance Sampling Webinar
20101129 29
Acceptance Sampling Webinar
20101129 30
From QCI-CQE Primer 2005, pVI-9
Acceptance Sampling Webinar
20101129 31
Poisson
Construct the following Table, using the Poisson Cumulative Table
p np P (k 2)
0%
1%
2%
3%
4%
etc.
Compare. When is Poisson a good approximation
Use the Poisson when n/N0.1 and np 5.
Acceptance Sampling Webinar
20101129 32
Poisson Calculator
Example: p=0.02, n=10, c=0
X=k, the number of successes in the sample, i.e. c
Acceptance Sampling Webinar
20101129 33
Poisson Calculator
Example: p=0.02, n=10, c=0
Mean = np
Acceptance Sampling Webinar
20101129 34
Poisson Calculator
Example: p=0.02, n=10, c=0
TRUE for cumulative, i.e. k; FALSE for probability mass function, i.e.p(x=k)
Acceptance Sampling Webinar
20101129 35
From QCI-CQE Primer 2005, pVI-8
Acceptance Sampling Webinar
20101129 36
From QCI-CQE Primer 2005, pVI-8
Acceptance Sampling Webinar
20101129 37
From QCI-CQE Primer 2005, pVI-9
Acceptance Sampling Webinar
20101129 38
O-C Curve & AOQ
Determine the O-C curve.
Prepare the following Table using the Poisson distribution
p P
a
AOQ = p * P
a

0%
1%
2%
3%
etc
Graph the results: P
a
and AOQ vs p.
Acceptance Sampling Webinar
20101129 39
OC Curve & AOQ (2)
Acceptance Sampling Webinar
20101129 40
OC Curve & AOQ (3)
Acceptance Sampling Webinar
20101129 41
Acceptance Sampling
III
Acceptance Sampling Webinar
20101129 42
Questions
1. What if this AOQ is not adequate?
2. What if you would like to add a 2
nd
sample when
the first sample fails?

Example
OC curve after 1
st
Sample:
p=0.02, n=30, N=500, c (A
c
)=0, R
e
=2
OC curve after 2
nd
Sample (of 30 more):
p=0.02, n=60, N=500, c (A
c
)= 1, R
e
=2

Acceptance Sampling Webinar
20101129 43
Hypergeometric Multiple Sampling
N = 500 500 500 500
n = 30 60 60 60

p D=Np Nq=N-Np P(k=0) P(k=0) P(k=1) P(k 1)
K 0 0 1
0.00 0 500 1 1 1
0.01 5 495 0.73 0.53 0.36 0.89
0.02 10 490 0.54 0.28 0.38 0.66
0.03 15 485 0.39 0.14 0.30 0.44
0.04 20 480 0.28 0.07 0.21 0.28
0.05 25 475 0.20 0.04 0.14 0.17
0.06 30 470 0.15 0.02 0.08 0.10
0.07 35 465 0.11 0.01 0.05 0.06
Acceptance Sampling Webinar
20101129 44
Hypergeometric Multiple Sampling
Hypergeometric Multiple Sample
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07
Lot defective
P
r
o
b

o
f

A
c
c
e
p
t
a
n
c
e
N=500, n=30, c=0 N=500, n=60, c=1
Acceptance Sampling Webinar
20101129 45
ANSI/ASQC Z1.4-1993
Mil-Std 105
Sampling for Attributes; 95 page Document
P
a
s from 83% to 99%
Information necessary: N, AQL, Inspection Level


How to Use
Code Letters
Single, Double, Multiple Plans
Switching Rules
Obtain: n, A
c
, R
e
,
O-C Curves

Acceptance Sampling Webinar
20101129 46
ANSI/ASQC Z1.4-1993
Exercises
N=475, AQL = 0.1%, Single Plan, Normal
What is Code Letter
What is Sample Size,
What is A
c,
R
e
Repeat for Tightened Inspection
Repeat for Reduced Inspection

Note: 0.1% is 1000 ppm
Acceptance Sampling Webinar
20101129 47
Z1.4 Code Letters
I-Reduced, II-Normal, III-tightened |||| For N=475, Normal, code letter is H
Acceptance Sampling Webinar
20101129 48
Z1.4 Single Plan Normal Insp.
Table II-A
n=125, New code Letter K
Acceptance Sampling Webinar
20101129 49
Z1.4 O-C Curve for Code Letter K
Table X-K
Acceptance Sampling Webinar
20101129 50
Z1.4 Switching Rules
Acceptance Sampling Webinar
20101129 51
ANSI/ASQC Z1.4-1993

What happens when AQL = . 1% isnt
good enough
AQL = 0.1% => 1000 ppm

Is Z1.4 Adequate?
How would you decide?
If not, what would you do?
Construct O-C curve for n=1000, c=0 (Poisson). Use
100ppm < p < 5000 ppm (see slides 38 & 39)
Acceptance Sampling Webinar
20101129 52
ANSI/ASQC Z1.9-1993
Mil-Std 414
Sampling for Variables; 110 page Document

Four Sections in the document
Section A: General description of Plans
Section B: Plans used when variability is unknown
(Std. deviation method is used)
Section C: Plans used when variability is unknown
(range method is used)
Section D: Plans used when the variability is known.

Acceptance Sampling Webinar
20101129 53
ANSI/ASQC Z1.9-1993
Mil-Std 414
Information necessary: N, AQL, Inspection Level
How to Use
Code Letters
Single or Double Limit, Std. Dev or Range Method Plans
Switching Rules
Obtain: Code Letter, n, Accept/Reject criteria,
critical statistic (k)
O-C Curves

Acceptance Sampling Webinar
20101129 54
ANSI/ASQC Z1.9-1993
Exercise (From QCI, CQE Primer, pVI-37)
The specified max. temp for operation of a device is
209F. A lot of 40 is submitted for inspection. Use
Normal (Level II) with AQL = 0.75%. The Std.
Dev. is unknown.
Use Std. Dev. Method, variation unknown
Find Code Letter, Sample Size, k
Should lot be accepted or rejected
Acceptance Sampling Webinar
20101129 55
Z1.9 Code Letters
For N=40, AQL=0.75 |||||| Use AQL=1.0 & Code Letter D
Acceptance Sampling Webinar
20101129 56
Z1.9 Finding Decision Criteria
Std. Dev method Table B-1
For Code Letter D, n=5 & AQL=1, k=1.52
Acceptance Sampling Webinar
20101129 57
ANSI/ASQC Z1.9-1993
What is k

k is a critical statistic (term used in hypothesis testing).
It defines the maximum area of the distribution which can be
above the USL.
When Q
calc
> k, there is less of distribution above Q
calc
than above
k and lot is accepted. (Compare to Z table)
Increasing (USL - X-bar) increases P
a
Acceptance Sampling Webinar
20101129 58
ANSI/ASQC Z1.9-1993
Exercise Solution
The five reading are 197F, 188F, 184F, 205F, 201F.
X-bar (mean) = 195F
S (Std. Dev) = 8.8F
Q
calc
= (USL X-bar)/s = 1.59
Because Q
calc
= 1.59 is greater than k=1.52, lot is
accepted
Acceptance Sampling Webinar
20101129 59
Z1.9 OC Curve for D
Table A-3 (p9)
Acceptance Sampling Webinar
20101129 60
ANSI/ASQC Z1.9-1993

Another Exercise

Same information as before
AQL = 0.1
Find Code Letter, n, k
Accept or Reject Lot?
Acceptance Sampling Webinar
20101129 61
Solution 2
nd
Exercise
New code letter is E, n=7, & k=2.22

The seven reading are 197F, 188F, 184F, 205F, 201F,
193F & 197F.
X-bar (mean) = 195F
S (std. Dev) = 7.3F
Q
calc
= (USL X-bar)/s = 1.91
Because Q
calc
= 1.91 is less than k=2.22, lot is
rejected

Acceptance Sampling Webinar
20101129 62
Inspection Economics
Average Total Inspection: The average number
of devices inspected per lot by the defined sampling
plan
ATI = n P
a
+ N(1- P
a
)
which assumes each rejected lot is 100% inspected.
Average Fraction Inspected:
AFI = ATI/N
Average Outgoing Quality:
AOQ = AQL (1 AFI)
Acceptance Sampling Webinar
20101129 63
Inspection Economics
Exercise (from Grant & Leavenworth, p395)
AQL = 0.5%, N=1000
Which sampling plan would have least ATI.
n = 100, c = 0
n = 170, c = 1
n = 240, c = 2
Acceptance Sampling Webinar
20101129 64
Inspection Economics
Exercise Solution
N 1000 1000 1000
n 100 170 240
c 0 1 2
P
a
0.59 0.8 0.92
n P
a
59 136 220.8
N(1- P
a
) 410 200 80
ATI 460 336 300.8
AFI 0.460 0.336 0.301
AOQ 0.0027 0.00332 .00349
Acceptance Sampling Webinar
20101129 65
Inspection Economics
Comparison of Cost Alternatives
No Inspection
NpD
100% Inspection
NC
Sampling
nC + (N-n)pDP
a
+ (N-n)(1-P
a
)C

D = Cost if defective passes; C = Inspection cost/item
Acceptance Sampling Webinar
20101129 66
Inspection Economics
Sample Size Break-Even Point

n
BE
= D/C

D = Cost if defective passes; C = Inspection cost/item

Acceptance Sampling Webinar
20101129 67
Resources
American Society for Quality
Quality Press
www.asq.org
ASQ/NC A&T partnership quality courses
CQIA, CMI, CQT, CQA, CQMgr, CQE, CSSBB