Professional Documents
Culture Documents
Lessons Learned
Arieh Stark Keter Plastic Ltd
ECC6 Upgrade
Project Aim:
Why:
ECC6 Upgrade
BIDI Migration
ECC6 Upgrade
Business Background:
ECC6 Upgrade
Technical:
Before:
Operating System is Windows 2003 Enterprise.
Our 46C DataBase was SQL 2000 Advanced- 900 GB.
After:
Operating System is Windows 2003 Enterprise 32 Bit.
Upgrade Project:
Management:
Defines the scope of the Project Planning.
Kick Off - Project beginning and end.
Support, Redefinition if required. Keeping to Deadlines.
Technical Aspects:
Infrastructure sizing Servers, Communication, Desk Top.
Functionality:
Modifications and Custom Development.
Mapping of Delta Functionality.
Testing of functionality and Modifications .
Training
ECC6 Upgrade
Project Team:
Keter Project Leaders:
Shuky Sigura
Arieh Stark
HP Basis Team:
Moshe Yerushalmi
Yagil Hadri
Boaz Paz
NESS Advisory:
Zohar Sarig
Keter IT:
Ilan Yacoby
Igal Verbel
ECC6 Upgrade
Special Issues/Decisions:
SPAU Clean the SPAU in the original 4.6C system or only in the Final
System.
ECC6 Upgrade
Pre-Upgrade Analysis:
Hardware Sizing:
SAP Service that checks Hardware and performance capabilities before and after Upgrade.
Includes application specific documents that outline problems with corresponding solutions
including relevant SAP Notes.
For each application area CO , PP , MM, FI and SD.
Tools to correct known problems Variants etc These tools were mostly built in to the ECC6
Upgrade Package already.
Solution Manager:
Upgrade Roadmap
Solution Browser:
Release Notes:
ECC6 Upgrade
Pre-Upgrade Analysis:
Internal Interface analysis:
10
ECC6 Upgrade
Project Scope.
11
ECC6 Upgrade
AUE Highlights:
ECC6 Upgrade
Testing and Final System Verification and acceptance was done on this System.
13
ECC6 Upgrade
2nd Level testing was done by the Top Users in the SBU's.
14
ECC6 Upgrade
Top Users.
15
ECC6 Upgrade
Project Gantt:
16
ECC6 Upgrade
ECC6
DEV
DEV
Trial
Test/QA
PRD
17
ECC6 Upgrade
DEV
Test/QA
PRD
Testing
ECC6
SPAU
Corrections
Save Transports
SandBox
18
ECC6 Upgrade
DEV
Test/QA
R3 Code Freeze.
SPAU again.
Transports from Sandbox
ECC6
DEV
Final
Transports
PRD
Testing and
Training in SBUs
Test/QA
19
ECC6 Upgrade
:PRD Rehearsal
Copy of Production System
R3
DEV
Test/QA
PRD
ECC6
DEV
Final
Transports
PRD
Rehearsal
20
ECC6 Upgrade
DEV
Test/QA
PRD
ECC6
DEV
Final
Transports
PRD
Final
21
ECC6 Upgrade
ECC6
DEV
DEV
Final
Test/QA
Test/QA
PRD
DB Copy
PRD
Final
22
ECC6 Upgrade
HR SPAU entries.
23
ECC6 Upgrade
Post Upgrade:
Go-Live Problems/Issues and Lessons:
Application Problems
Basis Problems.
24
ECC6 Upgrade
Application Problems:
1st Week Problems:
25
ECC6 Upgrade
26
ECC6 Upgrade
Basis :
Performance tuning.
Database tuning.
Memory Tuning.
ECC6 Upgrade
Summary:
28
ECC6 Upgrade
Lessons Learned:
It was problematic to Deploy Citrix and the new SAP GUI at the same time.
Do not strive for too much Perfection Know the Business Risks and
Limits.
29