Professional Documents
Culture Documents
concepts
with
Microsoft Project 2010
By:
Abdul Ghaffar PMP
ghaffarsarwar@gmail.com
+923434017209
Objective
Projects Management Basics
What is a Project
Project Constraints
Project Planning, Monitoring & control
WBS
Objective
Lead & Lag
MileStone
Network Diagram
Critical Path
Adding Resource and its cost
Creating Baseline
Custom Fields
Tracking Project
Other Views and Reports
7/7/15
What is a Project?
A project is a temporary endeavor that helps to
accomplish some specific objective by utilizing
definite interconnected tasks and the effective
utilization of resources.
7/7/15
To achieve an objective
One Time (Start and finish dates)
Constraints of time, cost and resources
Performed by People Single or Group
Coordinated and controlled activities
Specific Deliverables
Progressive Elaboration
By : Abdul Ghaffar, PMP
7/7/15
7/7/15
PMBOK 5
7/7/15
1.1
Scope
1.2
Analysis/S
oftware
Requireme
nts
1.3
Design
1.4
Develop
ment
1.5
Testing
1.6
Training
1.7
Docume
ntation
1.8
Pilot
1.9
Deploy
ment
1.10
Post
Implem
entation
Review
1.5.1
Unit Testing
1.5.2
Integration
Testing
7/7/15
File
->options
-> Display
7/7/15
10
File
->options
-> Schedule
7/7/15
11
MS Project 2010
7/7/15
12
Task List
7/7/15
13
Task Duration
7/7/15
14
WBS Code
7/7/15
15
Sub Task
7/7/15
16
Link Task..
Finish to Start
(FS),
Start to Start
(SS),
same time.
Finish to Finish
(FF),
Start to Finish
(SF) ,
7/7/15
17
Link Task
7/7/15
18
Predecessors
7/7/15
19
20
7/7/15
21
Calendar
7/7/15
22
MileStone
Resource
7/7/15
24
7/7/15
25
26
Critical Path
7/7/15
27
Critical Path..
7/7/15
28
Slack
7/7/15
29
Custom Field
7/7/15
30
Tracking Project
To control the variations from actual plan
(baseline) we need to track project and
continuously check the health of the project.
EVM is a financial measurement tool that
combines the conflicting aspects of scope,
schedule and cost into a unified set of metrics.
These metrics can be used for measuring,
monitoring, reporting and forecasting project
performance. It can be used through all the
phases of a project, from initiation to closure.
7/7/15
31
Earned Value
7/7/15
32
Example
You have a project to build a new fence. the
fence is four sided as shown.
Each side is to take one day to build and is
budgeted for $1000 per side.
The sides are planed to be completed one after
the other.
Today is the end of day three.
33
Plan Tasks
7/7/15
34
Set Baseline
7/7/15
35
Actual Status
7/7/15
36
Check Status
7/7/15
37
Status Summary
7/7/15
38
Calendar View
7/7/15
39
Network Diagram
7/7/15
40
Other Reports
7/7/15
41
THANKS
7/7/15
42