Professional Documents
Culture Documents
BUILDING
SERVICES
CHAPTER 4
DEMOLITION
WORKS
DEMOLITION WORKS
4.1 Understand on demolition works
4.1.1 Describe the objectives of demolition
works.
4.1.2 State the reasons of the demolition works.
DEMOLITION WORKS
4.2 Know the method of demolition work
4.2.1 Describe the demolition works by manually.
4.2.2 Explain the mechanical equipment's used for
demolition work
a. crane and the demolition ball
b. pneumatic impact tools
c. mechanical arm
d. explosive
DEMOLITION WORKS
4.3 Learn safety procedures and best
practices of demolition works
4.3.1 State the safety procedures in demolition
works
4.3.2 Identify the best practices in demolition
work for specified building
4.3.3 Relate the best practices and environmental
effects in demolition works
DEMOLITION
WORKS
"The dismantling,
Definition
: wrecking, pulling down or
DEMOLITION WORKS
4.1 Understand on demolition works
4.1.1 Describe the objectives of demolition
works
Objective
s
:
The objectives
of demolition works is to
understand demolition works ina safe and
economical manner.
DEMOLITION WORKS
Aiming of the demolition works
:
DEMOLITION WORKS
4.1 Understand on demolition works
4.1.2 State the reasons of the demolition
works
Main reason of demolition works is because of:
1.Commercial
2.Aesthetic
3.Human health
4.Human safety
5.Build new building
6.Renovation
7.Structure problem
8.Environment (near slope)
9.Population density
10.Adjacent building
11.
Traffic
DEMOLITION WORKS
4.2 Know the method of demolition work
DEMOLITION WORKS
4.2 Know the method of demolition work
Demolition Processes :
DEMOLITION WORKS
Demolition Processes :
DEMOLITION WORKS
9. Prepare demolition schedule
10. Test and remove hazardous materials
11. Identify the safetymeasures for protection of
the public
12. Arrange for debris handling
13. Prepare demolition plan
14. Prepare stability report with calculations
15. Apply consent(alsosubmit supervision plan,
named and detail of Technically Competent
Persons)
DEMOLITION WORKS
Demolition Processes :
1. Install site precautionarymeasures
2. Remove hazardous materials
3. Inform site personnel the specifics and
precautionary measures
4. Establish emergency access
5. Establish line of communication to supervisor
6. Progressworkinaccordance withmethod
7. statements approved.
8. Remove debris to avoid accumulation
DEMOLITION WORKS
9.
10.
11.
12.
13.
Controldustemission
Adequatesupervision
Protectpartywalls
Ensure workers follow safety procedures
Ensure machines and equipment are well
maintained.
14. Providesecurity
15. Schedule regular inspection and maintenance
ofscaffolding
DEMOLITION WORKS
Demolition Processes :
1.
2.
3.
4.
a.
b.
c.
DEMOLITION WORKS
4.2 Know the method of demolition work
4.2.1 Describe the demolition works by
manually
Demolitionofbuildingsorstructurebyhan
dheldtoolssuchaselectricorpneumaticbr
eakers,
sometimesasapreliminarytousingother
methods,shouldbe carried out, where
practicable, in the reverse order to the
original construction sequence.
DEMOLITION WORKS
Lifting appliances may be necessary to hold
larger structural members during cutting and
forloweringseveredstructuralmembersand
otherdebris.
Chutes maybeusedto discharge debris into
a vehicle or hopper. Foundations would
normally be grubbed up by excavation
machines.
DEMOLITION WORKS
DEMOLITION WORKS
4.2 Know the method of demolition work
4.2.2 Explain the mechanical equipment's
used for
demolition
Simple
roof work
structures supported on wall
plates should normally be demolished to the
level of wall plates by hand, but if this may
involve unsafe working, then demolition
totally by machine may be appropriate.
Where a building that is to be demolished by
machine is attached to anotherstructure, the
two properties should be separated by the
use of hand methods before the main
demolition process begins.
DEMOLITION WORKS
When any part of a building is being
demolished by a balling machine, pusherarm
or similar equipment, only the machine
operator and banks man should be allowed
close to the working area.
The cabs of all machines should be strong
enough to protect the operator against the
fall of debris. In particular, the windscreen
and roof light shouldbe of shatterproof
material and guardedby a grille of steel bars
or a substantial mesh.
DEMOLITION WORKS
Demolition by machineryscomponents
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
The manufacturer should be consulted before a
machine is used for balling to establish any
restrictions on the type or length of jib or the
weight of the ball.
Balling operations subject cranes to dynamic
stresses and wear, and the ball chosen should
have the minimum weight necessary for
effective use. In many cases, demolition balls of
quite light weight will be adequate.
DEMOLITION WORKS
Floors should be demolished by dropping the
ball
on
the
highest
remaining
floorandallowingthe
debris
tofallinside
thebuilding.The
debrisshouldberemoved
regularly
to
prevent
excessive
weight
accumulating on the lower floors.
Walls or columns can be demolished either by
swinging the ball in line with the stationary jib,
using the drag rope, or by slewing the jib. The
ball should not swing by derricking the jib.
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
Pusher Arm
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
Clam Shell
Demolition by Clam Shell typically involves
the use of a crane equipped with a Clam
Shell attachment which progressively bites
away the structure.
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
Wire Rope
Demolition by Wire Rope pulling generally
involves the use of an earth mover machine or
mechanical winch device equipped with heavy
steel wire for pulling down structural members.
Wire Rope pulling should not be used on brick
or masonry structures. The method should only
be used on structures where it is possible to
safely attach the ropes.
Restraining ropes shall be provided to prevent
premature
collapse
before
the
pull
commences, from before pre-weakening until it
has been completed.
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
The explosives are just the trigger for the
demolition. It's gravity that brings the building
down. Explosives are loaded and progressively
detonated on several different levels of the
building so that the building structure falls
down on itself at multiple points.
When everything is planned and executed
correctly, the total damage of the explosives
and falling building material is sufficient to
collapse the structure entirely, so cleanup
crews are left with only a pile of rubble.
DEMOLITION WORKS
In order to demolish a building safely, each
element of the implosion must be studied
ahead of time. This is done by a blasting
expert. The first step is to examine
architectural blueprints of the building to
determine how the building is put together.
Next, the building is surveyed to study about
the support structure on each floor. Based on
this data and drawing from past experiences
with similar buildings, the expert decides what
explosives to use, where to position them in
the building and how to time their
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
CASE STUDY :
On December 30, the demolition of a 22-story building in
Liuzhou city, Guangxi province failed.
The building was split into two, with one half falling down
and the other half standing at an angle.
The demolition was effected by explosives which divided
the building into two halves which were supposed to fall
down. Instead, one half fell but the half didn't.
The demolition company sent equipment to take down the
standing building in order to prevent accidents.
DEMOLITION WORKS
DEMOLITION WORKS
DEMOLITION WORKS
4.3 Learn safety procedures and best
practices of demolition works
4.3.1 State the safety procedures in
demolition
Before works
the start of every demolition job, the
demolition contractor should take a number
of steps to safeguard the health and safety
of workers at the job site.
These preparatory operations involve the
overall planning of the demolition job,
including the methods to be used to bring
the
structure
down,
the
equipment
necessary to do the job, and the measures
to be taken to perform the work safely.
DEMOLITION WORKS
Planning for a demolition job is as important
as actually doing the work. Therefore all
planning work should be performed by a
competent person experienced in all phases
of the demolition work to be performed.
DEMOLITION WORKS
Demolition Safety Plan (Safety procedures )
Demolition safety plan is one of the phase involve
in demolition process which covers all the steps
acquire to identify, asses an control hazard which
might occur at the workplace during the
demolition work.
It should be developed in consultation with
employees and health and safety representative.
According to ACT Safe Demolition Works Third
Revised Edition November 2000, any demolition
activity is forbidden until a demolition safety plan
is completed and it must include the following :
DEMOLITION WORKS
1. Description of the demolition Workplace
DEMOLITION WORKS
Demolition Code of Practice
This Code of Practice outlines good practices for the
planning and implementation of demolition works for
different types of buildings in aiming at minimizing the
risks of :
a. causing damage to persons and properties of the
public;
b. endangering the health and safety of site personnel;
and
c. damaging the neighborhood environment different
types of buildings in aiming at minimizing the risks
of :
causing damage to persons and properties of the
public;
endangering the health and safety of site personnel;
DEMOLITION WORKS
Had
i.
ii.
iii.
DEMOLITION WORKS
EXERCISE 4. 1
The choice of technique depends on the nature of
the building or structure and its environment,
risks to public, operatives involved in the
demolition process, adjacent structure and
buildings.
Proposed a type of demolition work suitable to be
used for structure located in the middle of the city
and design a safety sign to put on the demolition
site.
DEMOLITION WORKS
DEMOLITION WORKS
4.3 Learn safety procedures and best
practices of demolition works
4.3.2
Identify
the
best
practices
in
demolition work for specified building
Although the definition varies depends on the
sources, it still reflect the same meaning and
objective. There are three main categories of
structural demolition and they are:
DEMOLITION WORKS
Deconstruction (DCON)
Deconstruction or Top-down Technique is a
technique that proceeds from the roof to ground in a
general trend. It is the common technique use in
Malaysia to demolished multi-storey structure.
The process can be done manually using
jackhammer, or breaking away the structure by
machine mounted with percussive breaker or other
hydraulic attachments.
DEMOLITION WORKS
DEMOLITION WORKS
Deliberate Collapse Mechanisms (DCM)
Considered to be the removal of key structural
members to cause complete collapse of the whole or part
of the structure.
It is usually employed for detached, isolated and
reasonably leveled sites where the whole structure is
intended to be demolished.
Sufficient space should be available to enable
equipment and personnel to be relocated to a safe
distance.
The process can be carried out by using wire rope
DEMOLITION WORKS
DEMOLITION WORKS
Progressive Demolition (PD)
The progressive demolition is the controlled removal of
sections of the structure, at the same time retaining the
stability of the remainder and avoiding collapse of the
whole or part of the structure to be demolished.
The process can be done using balling machine or any
long reach machine with hydraulic attachment.
DEMOLITION WORKS
DEMOLITION WORKS
4.3 Learn safety procedures and best
practices of demolition works
4.3.3 Relate the best practices and
environmental effects in demolition works
EXERCISE 4. 2
Identify the related of best practices and
environmental effects in demolition works.
DEMOLITION WORKS
The general requirements to minimise environmental impacts from
construction sites can also be applied to demolition processes. The
following sections contain some of the procedures to be adopted:
No
Section
Best Practices
Air
Pollution
Water
DEMOLITION WORKS
THANK
YOU