Professional Documents
Culture Documents
B1.2
Reservoirs
Seminars Monday A206a
Group 1 (16:00)
Group 2 (16:30)
Gunjan Dhingra
Dafydd Caffery
Rob Morford
Roger Palmer
Mike Farrow
Samuel Carter
Chris Swinburn
Anthony Pearson
Hannah Jones
Nedim Dzananovic
Kate Taylor
Gareth Pilmoor
Matt Knight
Philip Hallgarth
Celia Way
Ann Ruthven
Paul Knowles
Neil Harding
Marie Wells
Matthew Scott
Peter Adams
Martin Hill
Matt Whitley
Ben Sheterline
Elizabeth Aldridge
Karen Hockey
Eral Kahveci
Melanie Sim
Jonathan Bailey
Ching Hong
Imra Karimn
Nicholas Thompson
Khesraw Bashir
Adam Ithier
Martin Kendrick
Daniel Tkotsch
Christopher Baxter
Peter Jordan
Shua Lii
Christopher Tompkins
Richard Buckland
Jan Jozefowski
Beth Mcdowall
Ian Yeung
Adil Munir
B2.1
Hydro power
Topics: Fundamentals
Power available
Hydro systems
power needs
z2
z1 hq hs h f
2
g
g
2
g
Heat energyFriction
losses
p
= Pressure (Pa)
g
= Gravity (m s2)
= fluid density (kg m-3)
v
= velocity (m s-1)
zt
= Elevation (m)
h = energy (meters)
z1
Energy line
p gh
v2
z2
p2
z1
Energy line
p g h h f
v2
z2
p2
Hf
2
L v
Hf f
D 2 g
f
= Friction factor
L = Pipe length (m)
D
= Pipe diameter (m)
v
= velocity (m s-1)
g
= Gravity (m s2)
0.3164
f
Re0.25
f
= Friction factor
k = Surface roughness
D
= Pipe diameter (m)
Re
= Reynolds number
g
= Gravity (m s2)
Swamee-Jain equation
10-6 < k/D < 0.01
(Re 5,000 3x108)
0.25
5.74
k
log10 3.7 D Re0.9
v1 v2 v3
Energy line
p1 p3
z1
v2
so
p2
v3
z2
p3
hs h h f
hs h h f H
p1
Energy line
p g h h f gH
z1
v2
So
p2
v3
z2
p3
P Fv APv vA gH
Q gH
Cheaper per kW
Quick import delivered Little (or no)
on a turnkey basis
dependence on overseas
technologies
Capacity building
Can use local
labour/materials
Fisheries/leisure
Forebay
Must be able to cope with largest flow required
by turbine
Penstock
Keep as short as possible?
Powerhouse
Should be close to settlement (reduces
transmission costs) or easily accessible (for
maintenance)
Tailrace
Should empty into natural water course
Control
generator
Coupling
Turbine
Paverage demand
Ppeak demand
Plant factor
f plant
Etotal demand
Einstalled
community
100 households
bulbs/house
wattage/bulb
13 W
2.6 kW
3 kW
2,500
2,000
1,500
1,000
500
0
00:00
06:00
12:00
Series1
18:00
00:00
industry
Fraction
0
0
0
0
0
0
0
0.25
0.5
0.75
1
1
1
1
1
1
1
1
0.5
0.25
0.1
0.1
0
0
Total
0
0
0
0
0
0
0
500
1,000
1,500
2,000
2,000
2,000
2,000
2,000
2,000
2,000
2,000
1,000
500
200
200
0
0
lighting
Fraction
0.05
0.05
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0.2
0.5
1
1
0.7
0.2
Total
Total
130
130
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
520
1,300
2,600
2,600
1,820
520
130
130
0
0
0
0
0
500
1,000
1,500
2,000
2,000
2,000
2,000
2,000
2,000
2,000
2,000
1,520
1,800
2,800
2,800
1,820
520
2,500
2,000
1,500
1,000
500
0
00:00
06:00
12:00
Lights only
18:00
00:00
Battery charging
Fraction
Total
0.013
625
0.013
625
0.013
625
0.013
625
0.013
625
0.013
625
0.013
625
0.013
625
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
industry
Fraction
Total
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0.25
500
0.5
1,000
0.75
1,500
1
2,000
1
2,000
1
2,000
1
2,000
1
2,000
1
2,000
1
2,000
1
2,000
0.5
1,000
0.25
500
0.1
200
0.1
200
0
0
0
0
lighting
Fraction
Total
0.025
65
0.025
65
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0.1
260
0.25
650
0.5
1,300
0.5
1,300
0.35
910
0.1
260
Total
690
690
625
625
625
625
625
1,125
1,000
1,500
2,000
2,000
2,000
2,000
2,000
2,000
2,000
2,000
1,260
1,150
1,500
1,500
910
260
2,500
2,000
1,500
1,000
500
0
00:00
06:00
Lights only
12:00
18:00
00:00
Discharge (m /s)
10
99.8
99.9
99.95
99.98
99.99
98
99
95
90
70
50
30
10
0.5
1
2
0.01
0.02
0.05
0.1
0.2
0.1
http://www.geocities.com/jonpeltier/Excel/Charts/ProbabilityChart.html
Discharge (m /s)
10
99.8
99.9
99.95
99.98
99.99
98
99
95
90
70
50
30
10
0.5
1
2
0.01
0.02
0.05
0.1
0.2
0.1
P Q gH 0.5e 24 365
13,731kWh/m head
14,000 kWh/m head
99.8
99.9
99.95
99.98
99.99
98
99
95
90
70
50
30
10
0.5
1
2
0.1
0.01
0.02
0.05
0.1
0.2
Discharge (m 3 /s)
10
Discharge (m /s)
10
18,000 kWh/mhead
14,000 kWh/mhead
12,000 kWh/mhead
99.8
99.9
99.95
99.98
99.99
98
99
95
90
70
50
30
10
0.5
1
2
0.01
0.02
0.05
0.1
0.2
0.1
Discharge (m /s)
10
1
17,000 kWh/mhead
8,500 kWh/mhead
4,000 kWh/mhead
99.8
99.9
99.95
99.98
99.99
98
99
95
90
70
50
30
10
0.5
1
2
0.01
0.02
0.05
0.1
0.2
0.1
f plant
Etotal demand
Einstalled
fplant
= Plant factor
Etotal demand
= Surface
roughness
= Pipe diameter
(m)
= Reynolds number
Einstalled
= fraction of time
that demand is
exceeded
Cunit energy
Cunit energy
Cannual
= Annualised cost
Pinstalled
= Operation and
maintenance cost
= Installed power
fplant
= Plant factor
Cannual CO&M
CO&M
(24 365) Pinstalled f plant
Cannual Ccapital
i1 i
1 i 1
n
Cannual
= Annualised cost
Ccapital
= Capital cost
i
n
= Interest rate
= number of years
Electromechanical
27%
Civil works
19%
Civil works
13%
Penstock
21%
Penstock
12%
Engineering
12%
Distribution
14%
Nepal
Engineering
12%
Distribution
6%
Sri Lanka
Electromechanical
48%
Cost
Planning
4,000
Management/finance
2,000
Penstock
27
37,000
25
35,000
Electro-mechanical
26
36,000
12,000
10
13,000
Distribution
Contingency
Total capital
Annualised cost (based on 10% interest over 10 years)
139,000
22,600
4,000
Annual cost
26,000
Plant factor
0.6
0.085/kWh
Water storage
Mosquito breeding
Drinking animals
Who benefits?
Who loses?