You are on page 1of 98

Structure Repairs &

Rehabilitation Presentation
No.3

Structure Repairs & Rehabilitation


Type Of Building Construction
A. Based On Construction Method

B. Based On Design & Supervision

Structure Repairs & Rehabilitation


A. Based On Construction Method
Load Bearing Wall With Step/Strip
Footing
R.C.C. Frame Work
Precast Structural Frame Work

Structure Repairs & Rehabilitation


B. Based On Design & Supervision
Engineered Building
(Designed & supervised By Engineer)
Non-Engineered Building
(Built by Mason, Carpenters without Input From
Engineer)
Semi Engineered Building
(Ex. In masonry Building, where Load bearing wall had
not been properly designed. Generally It is built by
Architect & Contractors without involving Engineer
effectively)
Pre- Engineered Buildings
(Those Non Engineered building which is complying IS
4326,IS 13827, IS 13828 ,IS 13935)

Structure Repairs & Rehabilitation


Categories Of Seismic Damage
Damage Categories

Extent Of Damage In
General

Suggested Post Earth


Quake Action

G
1

Slight Non
Structural
Damage

Thin Crack in Plaster,


Falling of Plaster bits in
limited parts

Building Need Not to


Vacated., only
architectural repairs
required.

G
2

Slight Structural
Damage

Small crack in walls,


Falling of Plaster in large
bits over large areas;
Damage of non structural
Parts like projecting of
cornice, kitchen chimney
etc.(The load carrying
capacity is not reduced
appreciably.)

Building Need Not to


Vacated., Cracks in
walls need grouting.
Architectural repairs
carried out to achieve
durability. Seismic
strengthening is
desirable.

G
3

Moderate
Structural
Damage

Large & deep Crack in


walls; Cracking of walls,
columns, piers, & tilting or

Building Need to be
Vacated for structural
restoration & seismic

Structure Repairs & Rehabilitation


Categories Of Seismic Damage
Damage Categories

Extent Of Damage In
General

Suggested Post Earth


Quake Action

G
4

Severe
Structural
Damage

Gaps occur in walls; Inner


or outer wall collapse;
Failure of ties.
Approximate 50% of the
main structural elements
fail. The building takes a
dangerous states.

Building has to be
vacated. For
demolishing or
extensive restoration
& strengthening work
has to be carried out.

G
5

Collapse

A large part of whole of


the building collapses.

Redesign &
construction of
Building .

This Table is useful for considering


retrofitting to be undertaken & cost for
rehabilitation of building.

Structure Repairs & Rehabilitation

Earthquake Effects on Soils & Foundations &


Solution Features For Foundations
Type I Rock Or Hard Soil-Well graded gravel
Mixtures with or without clay binder, and
clayey sands poorly graded or sand clay
mixtures(GB,CW,SB,SW & SC) N>30
Type II Medium Soils- All soils N= 10 to 30 &
Poorly Graded Sands Or Gravely Sands with
Little or No fines (SP) with N>15
Type III Soft Soils Other than SP with N < 10.

Structure Repairs & Rehabilitation


S. Type Of
No. Soil
1.
2.

3.
a.

Type I
Hard
Type II
Medium

Type III
Soft
Low
Water

Damaging
Effect Of Earth
quake
None

Earth quack Resisting


Feature

Use any foundation


type
Not much in
Use any foundation
Zones II & III
type
Relative Lateral Use tie beams in case
Movement
of Individual column
Possible in Zone Foundations
IV,V
Not Much In
Use Any Type of
Zone II
Foundation. Use plinth
bend.
Relative
Use Plinth beam to

Structure Repairs & Rehabilitation


S.No Type Of Soil
.

Damaging Effect Of
Earth quake

Earth quack Resisting Feature

3.
b.

Some relative
movement in Zone II

Use Plinth beam to connect


isolated
Foundations

Relative Lateral &


Vertical movements
in Zone III

Use piles going to stable soil


layer or minimum 10 m length.
Driven piles preferable.

Liquefaction resulting
in tilting/ overturning
of buildings &
structures likely in
zones IV & V

Improve the soil to a depth of 7


to 8m or up to stable layer if
met earlier, by dynamic
compaction or by compaction
piles. Use piles going to stable
soil layer or minimum 10 m
length. Driven piles preferable.

Soil not seen to be


affected in intensity
VII shaking in Latur,
Jabalpur earthquakes
but effect of ground

Use Plinth beams to connect


individual column footings. Use
Plinth Band in case of strip
foundations. Use of under ream
piles preferable

3c.

Type III Soft


Liquefiable
with high
water table

Black Cotton
Soil

Structure Repairs & Rehabilitation


Irregular Shape Building Should be
Avoided.
Diaphragm Discontinuity-(Openings
Floor
or different shape in Each floor)
Openi
ng

Out- Of Plan Offset(Discontinuity like


Stilt floor, House having open spaces
in G.F.)
Non Parallel System

Structure Repairs & Rehabilitation


Torsion Irregularities are In floor plan
like tilting or deformed or Both.

Re-entrant Corner

If A/L>0.15 to 0.2.

L
2 A
2

L
A1
1

Structure Repairs & Rehabilitation

Re- Entrant corner


12
m
24
A=18m
m

Plan A Plan B Plan C Plan D Plan F


In Plan A, As per rule In Y-dir.
A/L=18/24=0.75> 0.15 In X-dir.
A/L=6/12=0.50> 0.15

Plan F

Structure Repairs & Rehabilitation


5
Mass Irregularity
4
Example: IF
3
nd
rd
2 storey Weight> 2.0x3 Storey 2
2nd storey Weight> 2.0x 1st Storey 1
Stiffness Irregularity (If stiffness of
different floors are changed by certain
limit due to change in height or like
omitting load bearing wall at
particular floor, change in shape or
Size of floor etc.

Elevations

Structure Repairs & Rehabilitation


Vertical Geometrical Irregularity
L1

A
A

L2

IfA > 0.25 A > 0.15 L 2 > 1.5


L
1
InLPlan Discontinuity
in Lvertical
Element Resisting Lateral Force
Upper
a

Shear
Wall

Floor
Lower
Floor

Structure Repairs & Rehabilitation


Weak Storey (lateral Strength of Each
storey vary F1 < 0.8 F2 (or F3 )
F3
F2
F1

Structure Repairs & Rehabilitation


Redesigning existing structure for nature forces
It is a comprehensive task & require planning
which include following Information gathering.
Field investigations including details of sub
strata, foundation details, extent of damage
Type of Existing structure & its members stability
Design Data Collection
Identification of components required to be
strengthened
Cost Estimates (it is feasible up to 60% of new
construction)
Method or Procedure to be fallowed.

Structure Repairs & Rehabilitation


Crack Investigation
Location
Profile (vertical, Horizontal, Diagonal)
Crack Size (Depth & length)

Structure Repairs & Rehabilitation


Crack Location In Structure
Foundation:
1. Cracks Travel vertical in step footing in case of
unequal settlement.
. Flooring:
1. It is circular, Linear.
. Column:
1. Generally at 1/3rd height from bottom & top
depending on fixing conditions of column ends.
2. At laps location ,if laps are not staggered or
not sufficient length.

Structure Repairs & Rehabilitation


Brick Work:
In wall at ends of lintel in Diagonal
upward directions.
1. Horizontal, generally at slab wall joint ,
when whole wall sink.
2. Vertical, in case of unequal settlement
. Beam:
1. Near Support ,visible on both face of
beam & bottom.
2. At centre of beam in its bottom

Structure Repairs & Rehabilitation


Slab :
1. At centre of Span in ceiling (slab bottom)
2. At top & bottom face of slab near the
supporting wall or at top surface in case
of cantilever
. Plaster:
1. At joints with R.C.C & brick work
2. At localized locations in wall due to
different reasons
3. Locations as briefed in cracks in B.W.

Structure Repairs & Rehabilitation


Make structure floor, roof lighter as much as
possible.
Avoid Un- symmetry of structure as much as
possible. For this purpose structure can be
divided.
Sand Pilling ,Stabilization of weak soil, sandy soil
having high water level must be taken care off.
Proper Connections of building Elements.
Use steel to strengthen laterally for load bearing
wall as per code requirement.
Provide adequate plinth protection.
Avoid to built Rigid masonry Building freely
resting on rock in Earth Quack porn area.

Structure Repairs & Rehabilitation


Consider retaining wall, breast wall
while estimating school building in
heavy slope hills.
A building shaped like a box, such as
rectangular both in plan & elevation
is inherently stronger than one that
Open
area should
is L-shaped
or U-shaped or such a
bebuilding
not morewith
thanwings.
L<
50% of built up
B
area.

3B

Layout Plan

Structure Repairs & Rehabilitation


Suitability Of Typical School
Building Plan L < 3 B ; L <
45 mm

(A < 0 .15 L)
A

L<
3B

C
(C < 0 .15
OpenB)
area

should be
not more
than 50% of
Layout
PlanPlan
area.

Structure Repairs & Rehabilitation


Lateral Supports To Long Wall

R.C.C./B.W.
Columns
Maximum 6m
Interval
Buttress
Maximum 6m
Interval

Structure Repairs & Rehabilitation


Separation Sections to divide One
Building into more.

3
1

2
1

Structure Repairs & Rehabilitation


Avoid keeping shallow foundation on
Black Cotton Soil.
Use one type of foundation in a whole
building to avoid differential settlement.
Physical quality check on material should
me periodic.
An addition of room, which is structurally
independent from an existing building
should be designed & constructed in
accordance with the seismic requirements
of new compiled structures.

Structure Repairs & Rehabilitation


Any existing seismic resistance building if
occupied for school building then the building
has to be rechecked for seismic resistance for
building importance factor of 1.5.
Projecting parts like cornices, facia stones,
parapets etc. should be avoided as for as
possible, otherwise they should be properly
reinforced and firmly tied to the main
structure Refer IS 1893 CLAUSE -7.12.2
Ceiling plaster should be avoided as possible.

Structure Repairs & Rehabilitation


Whenever one un symmetrical building is
divided into two or more building by separation
walls the structure of the divided building up
to plinth level is generally monolithic. Refer
code IS 4326 5.1 to 5.2
Even Where calculations based on code- based
seismic coefficients may not indicate tension
steel requirements, the reinforcement
suggested in the form of seismic bands &
vertical steel bars at corners & junction of walls
& jambs of openings must be provided since
these are safe guard for probable maximum
earthquake.

Structure Repairs & Rehabilitation


Ductility Detailing
L1 should be 450 mm
or 1/6 th of clear
Column Beam Connection

height of
Ld+10 column/longer
side
of
2 for each
column section,
bend
2d
L1
whichever is greater
Spacin
In length L1 ,Spacing
d
g
Of ring < 0.25 times
h/4
L1
Shear
of minimum width of
Key
column or 75mm or
Pockets In length
2d(as shown)
100mm
,Spacing Of Stirrups
Level of Casting
(0.25X d) of beam or 8X
Of column Lift

Structure Repairs & Rehabilitation


Beam Reinforcement
Spacing
150
mm
Ld
Splice In Bottom bar: within
span

of

Splice In Top bar: within 2/ of


3
middle of span

Structure Repairs & Rehabilitation


Column Reinforcement

6mm @ 150
mm

L
d
L
d

Middle 2/3
of height
300

rd

Structure Repairs & Rehabilitation


Corrosion resistance precautions
should also be taken in ductility
detailing of cyclone prone & tsunami
prone coastal areas.
IS 456 does not allow R.C.C. below
M20 grade.

Structure Repairs & Rehabilitation


An addition of new structure which is not
structurally independent should be designed
& constructed such that the entire building
conforms to the seismic resistance
requirements for new building configuration.
The addition should not increase the
seismic force in any structural elements of
the existing building by more than 5%
unless the capacity of the element subject to
the increased force is still in compliance with
the standard.

Structure Repairs & Rehabilitation


Importance Factor(I) For Building
Depend Upon
Functional Use Of Structure
Hazardous Consequences Of Its
Failure
Post Earthquake Personal needs
Historical Value
IEconomic
Importance
value
Zone
II
III
IV
V
1.5
Building
Retrofitting
C
D
E
E
School
Building
Have
I
value=1.5
need

Structure Repairs &


Rehabilitation
Seismic wave propagation increases as

height of wall/structure increases.


Seismic wave propagation pushes bricks of
corner of wall out of building.
Movement of Seismic wave through joints of
similar or dissimilar component of building
,makes joint open resulting of falling of
component of the building.
Lateral strength of existing building is
improved by grouting, additional of vertical
reinforcement concrete coverings on the two
sides of the wall,& by pre stressing the wall.

Structure Repairs & Rehabilitation


Cyclone Obstructed by Retaining Wall

Cyclones

Structure Repairs & Rehabilitation


Although, the 2005 Kashmir earthquake destroyed many
houses and schools, But many old buildings did not suffer any
damage because they were built with timber elements
embedded in brick and stone masonry.

Structure Repairs & Rehabilitation


Himachal Pradesh also has old tradition of including many
timber elements in stone masonry walls to make the
buildings earthquake resistant. These buildings survive
earthquakes without any damage

Structure Repairs & Rehabilitation

Believe it or not this wooden school did not


crack or fall in Sikkim earth quack even it was
neglected structure.

Structure Repairs & Rehabilitation


Believe it or not this Ekra school did
survive in Sikkim earth quack even it
has been poorly built in as Plinth &
ground is on same level.

Structure Repairs & Rehabilitation


This slide shows joint of plinth beams at corner
of column.

Due to no hook in
many of bars in
plinth beam
,whole of wall
above plinth
beam came out
with the plinth
beam at corner
column in sikkim
earth Bar
quack
without
hook

Structure Repairs & Rehabilitation


Plaster came out in few panel of one
old Accra school building in Sikkim
earth quack.

Structure Repairs & Rehabilitation

Higher plinth level with plinth


protection

Structure Repairs & Rehabilitation


Elevation : Distance b1 to b8 changes as
per Building l
Retrofitting
l2
1
Need
b8
3
t
b
b7
h3
6
b
b
b
1

h
2
b
b5
4
1
2
h1
b

2 b

b4

h2
b5

Structure Repairs & Rehabilitation

Table :Size, Position Of Opening In


Building
Action For
Above Figure
Descripti
on

Mortar

Retrofitting
Need/Category
C
D&E

Retrofitting, if code
requirement not
found satisfied

Cement Cement
Chemical test of
: lime:
: lime:
mortar is carried
sand
sand
out ,if it is less than
1:2:9 or 1:1:6 or recommendation than
CS-1: 6 CS-1: 4 wall grouting or wire
mesh fixing or fiber
reinforce mortar is

Structure Repairs & Rehabilitation

Table :Size, Position Of Opening In Above


Building
Action For
Figure
Description
Retrofitting
Need/Category
C
D&E

(b1+b2+b3)/l1
; (b6+b7)/l2 =
shall not
exceed
( For one
Storey

Retrofitting, if
code
requirement not
found satisfied

This limit is
fallowed by
changing
opening size,
closing opening
or reinforcing
opening by

Structure Repairs & Rehabilitation


Table :Size, Position Of Opening In Above Figure

Description

Building
Action For
Retrofitting
Retrofitting, if
Need/Category
code
C
D & E requirement not
found satisfied

Seismic belt at plinth is provided if plinth is 900mm above ground.


Belt around door, window provided with details as per zone on both face
of opening.
600
600 mm
`h3 (minimum)
Ceiling or eve level belt onmm
both side wall for prefab & slopping roof.
Gable & ridge level belt on both side of wall in case of pitched roof.
`b8 (Max.)
900
900 mm
Window sill level belt on both face in three story building for achieving
mm
category D , E
Vertical bar or belt in all story at corner & junction of wall & in jambs for
achieving category D,E & in three story in category C.

Structure Repairs & Rehabilitation

Elevation : Masonry Building With Limitations for retrofitting limit

t 190
mm
t
Maximu
m 4.0 M
15
t

35 t or 8.0
m
20
t
V

Buttress Wall
35
35
t

t
W

Buttress Can Be Avoided by increasing wall thickness between


the cross wall.

Structure Repairs & Rehabilitation

Cracks are Cleaned by Air.


Nozzles 1 & 4 are fixed by 1:3 mortar.

1 2 3

Bea
m

Crac
k
Then Compressed air is passed through nozzles 1 & 4.
Nozzles 2 & 3 are fixed using mortar 1:3.
Filled cracks with mortar1:3.
Grout Nozzles in this face of beam in sequence of 1,4,2,3.Use sand in
grout for nozzle 2 & 3 .
Same is fallowed in opposite face of beam for nozzles 1 & 4.
Use Non shrinking grout ,which is 225 gram packet for 1 bag of
cement.
Pressure of grout is normally 3 kg/c.m.2 It vary with size of crack.

Structure Repairs & Rehabilitation


S. Item Of
N Roof/Floor
o.

1
2
1. Roof/Floor
with

Requirement as
per IS 4326 For
School Building
category
C
D
E

3
Tie
Beam

4
5
Tie Beam
All round

Retrofittin
g Action, if
code
provision
not
satisfied

6
Provide R.C.
screed &

Structure Repairs & Rehabilitation


S. Item Of
N Roof/Floor
o.

Requirement as
per IS 4326 For
School Building
category
C
D
E

Retrofittin
g Action, if
code
provision
not
satisfied

1
2
3. Sloping
roofs with

3
4
5
i) Horizontal cross
bracing at level of

6
Install the
cross

Structure Repairs & Rehabilitation


S.
N
o.

Item Of
Roof/Floor

Requirement as
per IS 4326 For
School Building
category
C
D
E

Retrofitting
Action, if
code
provision
not satisfied

1
4.

2
Jack arch
roof/floor

3
4
5
Connect the steel
joists by horizontal
ties at intervals to
prevent spreading &
cracking of the

6
Install steel
flats as ties by
welding them
to the steel
joists and

Structure Repairs & Rehabilitation


S.
N
o.

Item

a.

b.

Sloping
raftered roofs

Requirement Retrofitting Action,


as per IS
if code provision
4326 For
not satisfied
School
Building
category
C
D
E

Preferably use Convert rafters into A


full trusses
frames or full
trusses to reduce
thrust on walls

Structure Repairs & Rehabilitation


Beam Jacketing
Beam
Chipped
Surface
painted with
Flooring
epoxy
Along Beam
New Bar
are removed

Shortcrete
Column

Structure Repairs & Rehabilitation


New Bars are fixed In
Beam strengthening
Columns for beam in top
Remove
& bottom face
Plaster of

beam and
flooring is
removed
along beam
Jacketing is
done using
Micro
concrete with
self flowing
admixture.

U shape stirrups
are fixed from bottom
of beam into slab
COLUM
N
Pull test is carried out grouted
bars in drilled holes randomly.

Structure Repairs & Rehabilitation


Strengthening of Cracked Wall

20x40 mm
thick
Mortar or
Micro
concrete

Clamps or Tie Rod


connected to Wire
Mesh along cracks
Crack wider than 5
mm Port
Grout
Wire Mesh (50mmx
50 mm Opening)

Sectional Elevation Of

Structure Repairs & Rehabilitation

School Buildings has to be construct as per


Building Category C,D,E ( as per its EQ
Zone). These Category define specific mortar
for brick work & corresponding strength can
be achieved by injecting grout in existing
building walls. Same procedure is fallowed in
cracked wall having crack width 0.5 to 5 mm
ports
are
with grouting port fixed Grouting
along crack,
spacing
@ of wall thickness
fixed 2 to 4 No. /

Front

sqm, Grout 1:1: 225


gram of Non
Shrinking compound
Per 1Bag Of Cement
Side

Structure Repairs & Rehabilitation


Strengthening of Multiple Cracked Wall

Tie Rods 300 to


400mm C/C
connected to Wire
Mesh
cracks
Crack
Oralong
Cracks
>5
mm
widePort
Grout
Mortar(1:1) + Non
Shrink
Grout(50mmx
Wire Mesh
50 mm Opening)

20x40
mm thick
Mortar or
Micro
concrete
Grout 1:1
+ non
shrink
compoun
d
Sectional Elevation Of Cracked Or

Structure Repairs & Rehabilitation


Cross Wall Connection
Strengthening
Drilled
Hole

Tor Rod
Grouted

t 2t
Elevation Of Stone Masonry

PLAN

Structure Repairs & Rehabilitation


Fill the
concrete
from both
side &
then use
non
shrink
grout

Temporary Support

75 mm Hole is
made carefully
through R.R.
masonry & S-shape
bar is casted using
small size
aggregate concrete
1:2:4 with NSC or
self (free) flowing
readymade grout.

Curing for 10 days is must for such


element

Structure Repairs & Rehabilitation

Vertical Face Of Stone Masonry Wall


Through Stone are 1.0m apart
vertically & horizontally with 0.5 m
staggering horizontal

1.0
m
1.0
m

0.5
m

Structure Repairs & Rehabilitation

0 Orientation of mesh
45 Orientation of mes
Orientation of mesh increases tensile
strength of structure by way of increased
energy absorption. It is maximum for 45

Structure Repairs & Rehabilitation

As per above photograph ,it is possible that the


reinforcement would have buckled or elongated or
excessive yielding may have occurred. This element can
be repaired by replacing the old portion of steel with new
steel using butt welding or lap welding instead of just
Splicing or overlapping . Additional stirrup ties are to be
added in the damaged portion. Additional steel if

Structure Repairs & Rehabilitation


S.N
o
1.

Classification Of Damageability Of
Masonry Buildings
Grade 1 : Negligible to slight damage ( no structural
damage , slight non-structural damage)

Structure Repairs & Rehabilitation


S.N
o.
3.

4.

Classification Of Damageability Of Masonry


Buildings

Grade 3: Substantial to heavy damage ( moderate


structural damage, heavy non structural damage)
a) Structural: Large in extensive cracks in most walls.
Wide spread cracking of column & piers.
b) Non Structural : Roof tiles detach. Chimney
fracture at the roof line : failure of non structural
elements( partitions , gable walls).
Grade 4: Very heavy damage ( heavy structural
damage , very heavy non structural damage) .New
construction may explore.
For low strength masonry building use IS 13828.
Structural : Serious failure of walls (gaps in walls),
inner wall collapse ,Partial structural failure of roofs

S.
N
o.

Buildi
ng
Type

Structure Repairs & Rehabilitation

a)

Rubble stone in mud mortar or without mortar usually


with sloping wooden roof

b)

Mud walls , Adobe walls of two storey

c)

Un coursed rubble masonry without adequate through


stones

d)

Masonry with rounded ( undresses) stones

2
3

A a)

Adobe ( un burnt block or brick) walls of single storey

Rammed earth Pile construction

b)

B a)

b)
4

Description

B a)
+

Semi-dressed, rubble , brought to courses, with through


stones & long corner stone. unreinforced brick walls with
country type wooden roofs, unreinforced CC block wall
constructed in mud mortar or weak lime mortar.
Earthen walls (Adobe , rammed earth ) with horizontal
wooden elements
Un reinforced brick masonry in mud mortar with vertical
wood posts or horizontal wood element or seismic band

S.N Buildi
o.
ng
Type

Contd.

a
)

Description

Structure Repairs & Rehabilitation

b
)
6

C+

a
)

a
)

Unreinforced masonry walls built from fully


dressed( Ashlar ) stone masonry or CC
block or burn brick using good lime or
cement mortar, either having RC floor/roof
or sloping roof having eave level
horizontal bracing system or seismic band.
As at description B (a) with horizontal
seismic bands (IS 13828)
Like C (a) type but also having horizontal
seismic bands at lintel level of doors and
windows( IS 4326)
Masonry construction as at type C (a) but
reinforced with bands & vertical
reinforcement ,etc ( IS 4326) or confined
masonry using horizontal & vertical

Structure Repairs & Rehabilitation


Medvedev-Sponheuer-Karnik (MSK) intensity
scale is used to evaluate the severity of ground
shaking on the basis of observed efforts in an
area of the earthquake occurrence.
In the Scale few means 5-15 % buildings
damage, Many means 50%, Most means 75%.
For damageability of important building
(school) in any zone , should be checked for the
just higher zone.
Table below provide help in evaluating need for
improvement in building in consideration by
using simple retrofitting methods for which
more detailed evaluation is not feasible.

Structure Repairs & Rehabilitation

Damageability Grades Of Masonry Buildings


S.N
o.

Type
Of
Buildi
ng

Zone II
(MSK VI or
less)

Zone III
(MSK VII)

Zone IV
(MSK VIII)

Zone V
(MSK IX or
More)

A&
A+

Many( 50%)
of grade 1
damage

Most( 75%) of
grade 3
damage

Most of grade
4
damage

Many( 50%) of
grade 5

Few of grade
2

Few (5 to
15%) of grade
4

Few of grade 5

Rest no
damage

Rest of grade
2,1

Rest of grade
3,2

B&
B+

C&

Many of grade Most of grade


2
3

Rest of grade 4
,3
Many of grade
4

Few of grade
1

Few of grade
3

Few of grade 4 Few of grade 5

Rest no
damage

Rest of grade
1

Rest of grade
2

Rest of grade 3

Many of grade Most of grade

Many of grade3

Structure Repairs & Rehabilitation

Drilling And Grouting Of Tie Rod At Spring


Level

Weld 12

Load of roof from Arch are


transferred through prop. Before

Grouting
using
NSC/ Hilti
compoun
d

Structure Repairs & Rehabilitation

GROUTING in
between wall
& lintel

Props are Placed on both


side of wall To Support
wall above R.C.C. Lintel
Or Steel Joist.

Structure Repairs & Rehabilitation

Last slide continue


Fixing Of
Lintel (Or
Steel Joist
encased in
concrete )
over Weak
Arch

Wall
Above
Arch
ARC
H

ROO
F

PROP
S

Sectional Elevation showing fixing of Lintel

Structure Repairs & Rehabilitation

Preventing Arch Cracking By providing


Ties
A Flat Iron Or Rod
Connecting Bottom Flanges
Of I Section by Bolt Or
Welding

Bearing
Plate

Jack Arch

Flat Iron Or
Rod

Structure Repairs & Rehabilitation

Arch Supporting Pillar.


Nozzle
Use props to release load from wall
for
grouting
Concret
cement
e Bond
slurry
Stone at
using
1.0 m
non
spacing
shrinkin
g
Localize
compou
d bulge
nd 14
Non shrinking compound are injected after

Structure Repairs & Rehabilitation

Strengthening of footing & Column


Column
Top Surface
Jacketing
Should Be
roughened &
Bar grouted
suitable
in
drilled
hole
epoxy is
coated
Bottom Bar
Bottom
welded 12
Bar is
Additio
Exposed
n Of
at
edges
Pull test should be done on Some DrilledP.C.C.
&

Structure Repairs & Rehabilitation

Strengthening of wall around Door &


window

200 mm
250 mm
wide Wire
of 13
Mesh of 10
gauge
Gauge
having
having 8
10
wire with 25
vertical
mm pitch or
wire
250 mm of
with 25
13 gauge
mm
having 10
pitch
for
Wire
mesh
is
provided
on
both
wire with 25
C

face for room except those

Structure Repairs & Rehabilitation

G.I. Mesh Reinforcement in seismic belts


in various building categories with
overlapping of 300 mm

S.N Leng Category


o
th of
C
wall
In M G No Wid
.
e
1.
5.0 1 9 250
3
2.
6.0
1 9 250
2
GAUGE
3.
7.0
1 10 280

Category
D

Category
E

No Wid G
.
e
12 9 250 1
0
10 10 280 1
0
10 14 380 1

No Wid
.
e
10 280
14 380
18 460

(G)10=3.25,G12=2.64,G13=2.34,G14=2.0
Transverse wire in G.I.mesh up to 150

Structure Repairs & Rehabilitation


Unless otherwise required for category
C,D,E building. Seismic belt is not required
for following situation
1. Under roof & floor if they are R.C.C.
2. If plinth level is less than 900 mm.
3. Eve level bend is provided instead of lintel
level bend if eve level is not more than
900mm above the door opening.
4. For wall of shorter then 5.0 m, one face G.I.
mesh & tied to the wall by hook of full
width equal to wall @ 2.5 M. C/C & at
turning of belt.

Structure Repairs & Rehabilitation


Procedure of Seismic belt Construction
1. Mark the belt on wall & remove the plaster in
area.
2. Rack joint 20mm deep & wash with enough water.
3. Apply 15 mm thick 1:3 mortar immediately after
washing . Make plaster sufficiently rough.
4. Fix mesh using binding wire & nail of 150 mm @
450 mm c/c. If mesh is on both face of wall then
use anchor to connect both mesh & grout the
anchor.
5. Wet the first layer & brush with slurry before
doing second layer of 15 mm thick plaster.
6. Do curing for 10 days.

Structure Repairs & Rehabilitation

Vertical Belt At Corners & Junction


S. No.
Store
Category C
Category D
Category E
of
Rooms
N Of
y
Single
Mesh
Sing Mesh
Singl
Mesh
o

Store
y

Bar in
mm

G 10
W
NO.
of
wir
e

1.

One

2.

Two

3.

le
Bar
in
mm

G 10
NO. W
of
wire

e
Bar
in
mm

G 10
W
NO.
of
wir
e

10

10

30
0

12

14

400

First

10

10

30
0

12

14

400

Groun
d

12

14

40
0

16

4. 10=
Three 3.25
Seconmm10dia@
10 25
30mm;
10 Transverse
10 30
12 wire
14 in
400
G
d
0
0
mesh
@ First
150 mm.
5.
10 c/c
10
30
12
14 40
16
25
650

Structure Repairs & Rehabilitation

Vertical Belt
200 mm overlap in
Steel Mesh on each
face

200 mm
wide
Mortar belt

150 mm wide Steel


Mesh held by wide
head 150mm long
nail

150 mm

Vertical
Bar at
corner
of room

300 mm

t+60

Structure Repairs & Rehabilitation

Vertical Bar At Corner of L


room
Shape

Roo
f
75
mm
Hole
Grout
by
NSC
P.L
.

G.L

Dowel of 8
mm of vertical
leg 400 mm &
150 mm
First Dowel
just
horizontal
legat
above
P.L. & next
every
1.0bar
m at
Vertical
corner & 15 mm
covered with 1:3
cement mortar or
Steel
barMicro
1:1.5:3
minimum750 mm

Structure Repairs & Rehabilitation

Compressing The Walls for Box Action


The Vertical
Spacing of prestressing steel
rods shall be
1/3 rd & 2/3rd of
the height of
the wall from
bottom. In case
of slopping roof
or pre
fabricated
element
structure
provide tie at

In R.C. slab
provide such
tie only at
mid height of
wall

ROOM
PLAN

1
kg(f)/c.m.2
pre stress
is sufficient
to
compress
the wall

Structure Repairs & Rehabilitation

Before applying compression in


the wall it has to ensure that
1. Wall should not be low
strengthening mortar.
2. It will be better to strengthen week
wall by injection grouting first.

Structure Repairs & Rehabilitation

Strengthening of wall for making fit for


compression for
pre-stressing
Nozzle
spacing 2 to 4 No.
per sqm c/c; Grout 1
cement: 1 Water under
pressure 1 to 3 kg/c.m2
Nozzle
for
Injectio
n Grout
Elevation OF Weak Masonry

Cross

Structure Repairs & Rehabilitation

For roofing in zone 3 to 5 ,avoid tiles


& use corrugated iron or asbestos
sheeting. Asbestos sheet due to
radioactivity & snow loading (due to
rough surface) is avoided.
Avoid false ceiling, otherwise it
should be light & flexible like Hessian
cloth, bamboo matting, non
flammable foam.

Structure Repairs & Rehabilitation

Strengthening Of Rafter roof having attic.


Steel anchor
Intermediate
Flat 50x3 or
wall may not
50x4 mm @ 3
exist
to
4
mtr
Apart
Rafte
r

Attic Floor Beam


Pair of Planks
200x40 mm
nailed at ends

100 mm

Structure Repairs & Rehabilitation

Three Nails
5 filled in
member
made by
splitting
bamboo in
two part

Cross
bracings at
Xends of
room
Y

Detail Y
Refer Next
Half Split Bamboo Ties To Rafter
Slide
Brace the Rafter to 50 mm Dia Bamboo (B)
Seismic Bend & Rafter should be tied Properly

Structure Repairs & Rehabilitation


Detail Y
Rafte
r

Groutin
g of bolt

New Plank
for bracing,
at end
bay ,nailed
through wall

Flat on both M.S. Flat


face,
clamp
clamped to

Structure Repairs & Rehabilitation


Where the roof or floor consists of prefabricated
units like RC rectangular, T or channel units or
wooden poles & joists carrying brick tiles,
integration of such unit is necessary. Timber
elements could be connected to diagonal planks
nailed to them & spiked to an all round wooden
frame at the ends.
Reinforcement concrete elements may either
have 40 mm cast-in situ concrete topping with 6
mm bars @150 c/c both ways or bounded by
a horizontal cast-in situ reinforcement concrete
ring beam all round into which the ends of R.C.
elements are embedded.

Structure Repairs & Rehabilitation

6 bw@150c/c Bar In
16 , 2 Topping
No. shear
6 , 2
No.Rin
X
Cage For g
Key
Key In Wall for
RC bend @
3mtr
c/c slab
Pre-fab
Out of400 mm wide RCunit
bend ,150
mm rested
in wallof an existing
Stiffening

Structure Repairs & Rehabilitation

Stiffening flat wooden floor/roof


Resting On stone or brick masonry

Tie Plank 100x 25


thick connecting joist
Woo
Diagonal Ties & diagonal bracing
d
Wooden Joist
Plan
1.5
to
3.0
m
thick
G.I.
flat
k

PLAN

Structure Repairs & Rehabilitation


Connection of old brick work with new
Old wall
Steel bar
embedd
Concrete
ed in
grout
6 mm - 1
mortar
150 No.
mm

20

120
50
150
mm

New wall
Plan Showing
connection of

12 mm - 1
No.
500 mm 220 mm
200

100

mm

Structure Repairs & Rehabilitation

Connection of New brick wall with


Stone Masonry
Brick masonry

xisting old Stone masonry

Structure Repairs & Rehabilitation

Corner Connection

16 ,1.15 m
210

8
@200c/c

100
0

150

Plan

250 mm

Steel
Grouting

500 mm
500 mm

Section

Structure Repairs & Rehabilitation


Strengthening Of Foundations

a. Introducing new load bearing


members
b. Improving the drainage of the area
to prevent saturation of foundation
soil
c. Providing apron around the building
to prevent soaking of foundation
d. Adding strong elements in the form
of reinforced concrete strips

Structure Repairs & Rehabilitation

To avoid disturbance to the integrity of


the existing wall, during the foundation
strengthening process, proper
investigation & design is a must.
25
0
300

35
0

8,350
x 350
mm

2-16
Top &
Bottom
Each

400
4-16

35

30

4-16

Structure Repairs & Rehabilitation

Conclusion :

School building comes under


important building of importance
factor 1.5 & therefore while using
any of above method should be
under taken only with consent of
structural designer as he is the
person who can well judge which
method is most suited for getting
non collapse criteria for the EQ
zone.

You might also like